Public Meeting on Consideration of Rulemaking To Reduce the Likelihood of Funding Shortfalls for Decommissioning Under the License Termination Rule, 74847-74848 [E6-21154]
Download as PDF
jlentini on PROD1PC65 with PROPOSAL
Federal Register / Vol. 71, No. 239 / Wednesday, December 13, 2006 / Proposed Rules
that the importer is notified by the
overseeing APHIS representative that
the horse has been refused entry into the
United States. Subsequent disposition of
the horse must occur under the direct
oversight of APHIS representatives. The
operator must have a preapproved
contingency plan for the disposal of all
horses housed in the facility prior to
issuance of the import permit.
(I) Vaccination of horses in quarantine
is prohibited.
(vi) Records.
(A) The facility operator must
maintain a current daily record to
record the entry and exit of all persons
entering and leaving the quarantine
facility.
(B) The operator must maintain the
daily record, along with any records
kept by APHIS and deposited with the
operator, for at least 2 years following
the date of release of the horses from
quarantine and must make such records
available to APHIS representatives upon
request.
(5) Environmental quality. If APHIS
determines that a privately operated
quarantine facility does not meet
applicable local, State, or Federal
environmental regulations, APHIS may
deny or suspend approval of the facility
until appropriate remedial measures
have been applied.
(6) Variances. The Administrator may
grant variances to existing requirements
relating to location, construction, and
other design features of the physical
facility, as well as to sanitation,
security, operating procedures,
recordkeeping, and other provisions of
paragraph (c) of this section, but only if
the Administrator determines that the
variance causes no detrimental impact
to the overall biological security of the
quarantine operations. The operator
must submit a request for a variance
from the requirements for the
construction of the facility in paragraph
(c)(3) of this section to the
Administrator in writing prior to the
construction of the facility. The operator
must submit a request for a variance
from the operational requirements in
paragraph (c)(4) of this section to the
Administrator in writing at least 30 days
in advance of the arrival of horses to the
facility. Any variance must also be
expressly provided for in the
compliance agreement.
8. In § 93.309, the section heading
would be revised to read as follows:
§ 93.309 Horse quarantine facilities;
payment information.
*
*
*
*
*
9. Section 93.310 would be revised to
read as follows:
VerDate Aug<31>2005
16:44 Dec 12, 2006
Jkt 211001
§ 93.310 Quarantine stations, visiting
restricted; sales prohibited.
Visitors are not permitted in the
quarantine enclosure during any time
that horses are in quarantine unless an
APHIS representative specifically grants
access under such conditions and
restrictions as may be imposed by
APHIS. An importer (or his or her agent
or accredited veterinarian) may be
admitted to the lot-holding area(s)
containing his or her quarantined horses
at such intervals as may be deemed
necessary, and under such conditions
and restrictions as may be imposed, by
an APHIS representative. On the last
day of the quarantine period, owners,
officers or registry societies, and others
having official business or whose
services may be necessary in the
removal of the horses may be admitted
upon written permission from an APHIS
representative. No exhibition or sale
shall be allowed within the quarantine
grounds.
Done in Washington, DC, this 1st day of
December 2006.
Bruce Knight,
Under Secretary for Marketing and Regulatory
Programs.
[FR Doc. E6–21032 Filed 12–12–06; 8:45 am]
BILLING CODE 3410–34–P
NUCLEAR REGULATORY
COMMISSION
10 CFR Part 20
Public Meeting on Consideration of
Rulemaking To Reduce the Likelihood
of Funding Shortfalls for
Decommissioning Under the License
Termination Rule
Nuclear Regulatory
Commission.
ACTION: Notice of meeting.
AGENCY:
SUMMARY: The Nuclear Regulatory
Commission (NRC) is working on a
proposed rule to reduce the likelihood
that a licensee will have insufficient
funds to decommission its facility in
accordance with 10 CFR part 20,
Subpart E, Radiological Criteria for
License Termination. In the past, these
funding shortfalls resulted in ‘‘legacy
sites,’’ which are sites that are in
decommissioning but whose operators
do not have enough funds to complete
the work and terminate the license in
accordance with NRC regulations. All of
the legacy sites have been materials
facilities, primarily those that processed
uranium and thorium, with undetected
subsurface contamination from
operations arising as a significant
problem during decommissioning. A
PO 00000
Frm 00022
Fmt 4702
Sfmt 4702
74847
risk-informed approach addressing
subsurface contamination at operating
facilities would affect materials
licensees and operators of nuclear
power reactors. The purpose of the
meeting is to give stakeholders an
opportunity to discuss their views and
interact with other interested parties on
the regulatory issues summarized in the
Supplementary Information section of
this document.
To aid in the rulemaking process,
NRC is holding a public meeting with a
‘‘roundtable’’ format (defined further in
the body of this notice) to solicit input.
The meeting is open to the public. The
NRC is asking those planning to attend
the meeting to pre-register by contacting
Jayne McCausland as noted under the
For Further Information section of this
document. Individuals unable to attend
the meeting will be able to listen by
teleconference.
The meeting will be held on
January 10, 2007, from 9 a.m. to 4 p.m.
Registration is from 8:30 a.m. to 9 a.m.;
however, all persons planning to attend
the meeting are encouraged to preregister in order to facilitate check-in on
the day of the meeting.
ADDRESSES: Residence Inn Bethesda
Downtown, 7335 Wisconsin Avenue,
Bethesda, Maryland, 20814. Telephone
(301) 718–0200.
FOR FURTHER INFORMATION CONTACT:
Kevin O’Sullivan, telephone (301) 415–
8112, e-mail kro2@nrc.gov, of the Office
of Federal and State Materials and
Environmental Management Programs,
U.S. Nuclear Regulatory Commission,
Washington, DC 20555–0001. Questions
on the meeting format, including
participation in the roundtable, should
be directed to the meeting facilitator,
Lance Rakovan. Mr. Rakovan can be
reached at (301) 415–2589 or
ljr2@nrc.gov. To pre-register to attend
the meeting in person or to participate
via teleconference, or if a participant
has special needs, please contact Jayne
McCausland, telephone (301) 415–6219,
fax (301) 415–5369, or e-mail
jmm2@nrc.gov.
DATES:
Current
NRC regulations in 10 CFR part 20,
Subpart F, Surveys and Monitoring,
require licensees to conduct surveys, as
reasonable under the circumstances, to
evaluate (1) the magnitude and extent of
radiation levels; (2) concentrations or
quantities of radioactive material; and
(3) the potential radiological hazards.
NRC regulations in 10 CFR 20, Subpart
L, Records, contain related recordkeeping requirements. There have been
past occurrences among materials
licensees, and recent occurrences at
SUPPLEMENTARY INFORMATION:
E:\FR\FM\13DEP1.SGM
13DEP1
jlentini on PROD1PC65 with PROPOSAL
74848
Federal Register / Vol. 71, No. 239 / Wednesday, December 13, 2006 / Proposed Rules
nuclear power reactors, of inadvertent
and undetected release of radioactive
material into the underlying soils and
groundwater. Such undetected
subsurface contamination from
operations may significantly expand the
scope of decommissioning when the
facility is shut down, to the extent that
the licensee has insufficient funds to
terminate the license in accordance with
NRC regulations.
Amendments to NRC regulations are
under consideration that will affect both
facility operations and financial
assurance for decommissioning
requirements. One proposed change
would require each NRC licensee to
conduct operations, to the extent
practicable, so as to minimize the
presence of contamination in the
subsurface environment. A second
would require certain licensees, based
on their capability for causing longlasting subsurface contamination, to
check for the presence of such
contamination. NRC experience with
legacy sites demonstrates that soil or
groundwater contamination, if not
addressed during the operating life of
the facility, can increase
decommissioning costs to levels much
higher than initially funded and may
contribute to off-site radionuclide
migration, causing additional expense
and delay in returning the site to other
productive uses.
Another regulatory amendment under
consideration is to eliminate the escrow
account as an approved financial
assurance mechanism due to its
ineffectiveness in bankruptcy actions.
Two other financial assurance
mechanisms that pose similar financial
risk during bankruptcy are the
unsecured Parent Company Guarantee
and unsecured Self-Guarantee. Reliance
on these financial assurance
mechanisms may increase the
likelihood of future legacy sites.
The January 10, 2007, public meeting
is being held to discuss these and
related issues using a ‘‘roundtable’’
format. Participants at the roundtable
will be the invited stakeholders
representing the broad spectrum of
interests who may be affected by this
rulemaking. The roundtable format is
being used for this meeting to promote
a dialogue among the representatives at
the table on the issues of concern.
Opportunities will be provided for
comments and questions from the
audience. The meeting notice and a
meeting agenda will be posted on the
NRC Web site at: https://www.nrc.gov/
public-involve/public-meetings/
index.cfm.
VerDate Aug<31>2005
16:44 Dec 12, 2006
Jkt 211001
Dated at Rockville, Maryland, this 6th day
of December 2006.
For the Nuclear Regulatory Commission.
Dennis Rathbun,
Director, Division of Intergovernmental
Liaison and Rulemaking, Office of Federal
and State Materials and Environmental
Management Programs.
[FR Doc. E6–21154 Filed 12–12–06; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
10 CFR Part 54
[Docket Nos. PRM–54–02 and PRM–54–03]
Andrew J. Spano and Joseph C.
Scarpelli; Denials of Petition for
Rulemaking
Nuclear Regulatory
Commission.
ACTION: Petitions for rulemaking; denial.
AGENCY:
SUMMARY: The Nuclear Regulatory
Commission (NRC) is denying two
nearly identical petitions for rulemaking
submitted by Andrew J. Spano, County
Executive, Westchester County, New
York (PRM–54–02), and Mayor Joseph
Scarpelli of Brick Township, New Jersey
(PRM–54–03). The petitioners requested
that the NRC amend its regulations to
provide that the agency renew a license
only if the plant operator demonstrates
that the plant meets all criteria and
requirements that would apply if it were
proposing the plant de novo for initial
construction. The petitioners assert that
amendments are necessary because they
believe the process and criteria
established in the Commission’s license
renewal regulations are seriously flawed
and should consider critical plantspecific factors as demographics, siting,
emergency evacuation, and site security.
The NRC is denying the petitions
because the petitioners raise issues that
the Commission has already considered
at length in developing the license
renewal rule. These issues are managed
by the on-going regulatory process or
under other regulations; or are issues
beyond the Commission’s regulatory
authority. The petitioners did not
present new information that would
contradict positions taken by the
Commission when the license renewal
rule was established or demonstrate that
sufficient reason exists to modify the
current regulations.
ADDRESSES: Publicly available
documents related to these petitions,
including the petitions, public
comments received, and the NRC’s
letters of denial to the petitioners, may
be viewed electronically on public
PO 00000
Frm 00023
Fmt 4702
Sfmt 4702
computers in the NRC’s Public
Document Room (PDR), O–1 F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland. The PDR
reproduction contractor will copy
documents for a fee. Selected
documents, including comments, may
be viewed and downloaded
electronically via the NRC rulemaking
Web site at https://ruleforum.llnl.gov.
Publicly available documents created
or received at the NRC after November
1, 1999, are also available electronically
at the NRC’s Electronic Reading Room at
https://www.nrc.gov/reading-rm/
adams.html. From this site, the public
can gain entry into the NRC’s
Agencywide Document Access and
Management System (ADAMS), which
provides text and image files of NRC’s
public documents. If you do not have
access to ADAMS or if there are
problems in accessing the documents
located in ADAMS, contact the PDR
reference staff at (800) 387–4209, (301)
415–4737 or by e-mail to pdr@nrc.gov.
FOR FURTHER INFORMATION CONTACT: Lee
Banic, Office of Nuclear Reactor
Regulation, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001, telephone (301) 415–2771, e-mail
mjb@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Background
The NRC received two separate, but
nearly identical, petitions for
rulemaking in 2005 requesting that part
54, Requirements for renewal of
operating licenses for nuclear power
plants be amended. Mr. Andrew J.
Spano, the County Executive of
Westchester County, New York, filed
the first petition on May 10, 2005,
which was assigned Docket No. PRM–
54–02. The NRC published a notice of
receipt of the petition and request for
public comment in the Federal Register
on June 15, 2005 (70 FR 34700). Mayor
Joseph C. Scarpelli of Brick Township,
New Jersey, filed the second petition on
July 20, 2005, which was assigned
Docket Number PRM–54–03.1 The NRC
published a notice of receipt of the
petition and request for public comment
in the Federal Register on September
14, 2005 (70 FR 54310). Because of the
similarities to PRM–54–02, Mayor
1 Attorney Michelle R. Donato actually filed
PRM–54–03 on behalf of Mayor Scarpelli, the New
Jersey Environmental Federation (NJEF), and the
New Jersey Sierra Club (NJSC). Although Ms.
Donato’s letter indicates that she is presenting three
‘‘formal’’ petitions to the NRC, the submissions
from NJEF and NJSC state that they are submitted
‘‘in support of’’ or joining Mayor Scarpelli’s
petition. They do not appear to request petitioner
status. Thus, any reference in this document to the
PRM–54–03 petitioner is limited to Mayor
Scarpelli.
E:\FR\FM\13DEP1.SGM
13DEP1
Agencies
[Federal Register Volume 71, Number 239 (Wednesday, December 13, 2006)]
[Proposed Rules]
[Pages 74847-74848]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-21154]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
10 CFR Part 20
Public Meeting on Consideration of Rulemaking To Reduce the
Likelihood of Funding Shortfalls for Decommissioning Under the License
Termination Rule
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice of meeting.
-----------------------------------------------------------------------
SUMMARY: The Nuclear Regulatory Commission (NRC) is working on a
proposed rule to reduce the likelihood that a licensee will have
insufficient funds to decommission its facility in accordance with 10
CFR part 20, Subpart E, Radiological Criteria for License Termination.
In the past, these funding shortfalls resulted in ``legacy sites,''
which are sites that are in decommissioning but whose operators do not
have enough funds to complete the work and terminate the license in
accordance with NRC regulations. All of the legacy sites have been
materials facilities, primarily those that processed uranium and
thorium, with undetected subsurface contamination from operations
arising as a significant problem during decommissioning. A risk-
informed approach addressing subsurface contamination at operating
facilities would affect materials licensees and operators of nuclear
power reactors. The purpose of the meeting is to give stakeholders an
opportunity to discuss their views and interact with other interested
parties on the regulatory issues summarized in the Supplementary
Information section of this document.
To aid in the rulemaking process, NRC is holding a public meeting
with a ``roundtable'' format (defined further in the body of this
notice) to solicit input. The meeting is open to the public. The NRC is
asking those planning to attend the meeting to pre-register by
contacting Jayne McCausland as noted under the For Further Information
section of this document. Individuals unable to attend the meeting will
be able to listen by teleconference.
DATES: The meeting will be held on January 10, 2007, from 9 a.m. to 4
p.m. Registration is from 8:30 a.m. to 9 a.m.; however, all persons
planning to attend the meeting are encouraged to pre-register in order
to facilitate check-in on the day of the meeting.
ADDRESSES: Residence Inn Bethesda Downtown, 7335 Wisconsin Avenue,
Bethesda, Maryland, 20814. Telephone (301) 718-0200.
FOR FURTHER INFORMATION CONTACT: Kevin O'Sullivan, telephone (301) 415-
8112, e-mail kro2@nrc.gov, of the Office of Federal and State Materials
and Environmental Management Programs, U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001. Questions on the meeting format,
including participation in the roundtable, should be directed to the
meeting facilitator, Lance Rakovan. Mr. Rakovan can be reached at (301)
415-2589 or ljr2@nrc.gov. To pre-register to attend the meeting in
person or to participate via teleconference, or if a participant has
special needs, please contact Jayne McCausland, telephone (301) 415-
6219, fax (301) 415-5369, or e-mail jmm2@nrc.gov.
SUPPLEMENTARY INFORMATION: Current NRC regulations in 10 CFR part 20,
Subpart F, Surveys and Monitoring, require licensees to conduct
surveys, as reasonable under the circumstances, to evaluate (1) the
magnitude and extent of radiation levels; (2) concentrations or
quantities of radioactive material; and (3) the potential radiological
hazards. NRC regulations in 10 CFR 20, Subpart L, Records, contain
related record-keeping requirements. There have been past occurrences
among materials licensees, and recent occurrences at
[[Page 74848]]
nuclear power reactors, of inadvertent and undetected release of
radioactive material into the underlying soils and groundwater. Such
undetected subsurface contamination from operations may significantly
expand the scope of decommissioning when the facility is shut down, to
the extent that the licensee has insufficient funds to terminate the
license in accordance with NRC regulations.
Amendments to NRC regulations are under consideration that will
affect both facility operations and financial assurance for
decommissioning requirements. One proposed change would require each
NRC licensee to conduct operations, to the extent practicable, so as to
minimize the presence of contamination in the subsurface environment. A
second would require certain licensees, based on their capability for
causing long-lasting subsurface contamination, to check for the
presence of such contamination. NRC experience with legacy sites
demonstrates that soil or groundwater contamination, if not addressed
during the operating life of the facility, can increase decommissioning
costs to levels much higher than initially funded and may contribute to
off-site radionuclide migration, causing additional expense and delay
in returning the site to other productive uses.
Another regulatory amendment under consideration is to eliminate
the escrow account as an approved financial assurance mechanism due to
its ineffectiveness in bankruptcy actions. Two other financial
assurance mechanisms that pose similar financial risk during bankruptcy
are the unsecured Parent Company Guarantee and unsecured Self-
Guarantee. Reliance on these financial assurance mechanisms may
increase the likelihood of future legacy sites.
The January 10, 2007, public meeting is being held to discuss these
and related issues using a ``roundtable'' format. Participants at the
roundtable will be the invited stakeholders representing the broad
spectrum of interests who may be affected by this rulemaking. The
roundtable format is being used for this meeting to promote a dialogue
among the representatives at the table on the issues of concern.
Opportunities will be provided for comments and questions from the
audience. The meeting notice and a meeting agenda will be posted on the
NRC Web site at: https://www.nrc.gov/public-involve/public-meetings/
index.cfm.
Dated at Rockville, Maryland, this 6th day of December 2006.
For the Nuclear Regulatory Commission.
Dennis Rathbun,
Director, Division of Intergovernmental Liaison and Rulemaking, Office
of Federal and State Materials and Environmental Management Programs.
[FR Doc. E6-21154 Filed 12-12-06; 8:45 am]
BILLING CODE 7590-01-P