Portland & Western Railroad, Inc.-Trackage Rights Exemption-BNSF Railway Company, 67705-67706 [E6-19775]
Download as PDF
Federal Register / Vol. 71, No. 225 / Wednesday, November 22, 2006 / Notices
pwalker on PROD1PC61 with NOTICES
northeasterly from within the LNG
terminal in Cameron Parish, LA, to an
interconnection with a Columbia Gulf
Transmission Company pipeline in
Evangeline Parish, LA. Along this route,
the pipeline connects to ten or more
interstate and intrastate transmission
pipelines and has a peak day capacity
of approximately 2,130,000 Dth/d. This
is the only leg of the pipeline to which
the waiver will apply.
• Leg 2, is a 1-mile, 36-inch diameter
pipeline, running northerly from the
LNG terminal to an interconnection
with a Natural Gas Pipeline Company of
America (NGPL) pipeline, located
approximately 0.41 miles north of the
terminal. This leg is entirely within
Cameron Parish, LA.
• The Florida Gas Transmission
(FGT) lateral is 2.2-mile, 24-inch
diameter, lateral pipeline extending
from Leg 1 to an existing compressor
station owned by FGT in Acadia Parish,
LA.
• The Bi-Directional Tie-in line is an
interconnection between Leg 1 and Leg
2. The tie-in allows Leg 1 to receive gas
from NGPL when not receiving gas from
the LNG terminal.
Pipeline Design, Specifications and
Quality Control
KMLP’s waiver petition describes
various qualitative characteristics of its
proposed pipeline system and it
believes the proposed pipeline system
meets and/or exceeds current PHMSA
pipeline safety regulations. KMLP plans
to design and construct the pipeline
using steel pipe that conforms to Kinder
Morgan’s Material Standard M8270.
KMLP also states that the Class 1
location line pipe for its proposed
pipeline conforms to American
Petroleum Institute’s (API) 5L Grade
X80 and X70 longitudinal or helical
seam submerged are welded pipe. This
specific pipe is externally coated with
plan fusion bonded epoxy (FBE) as
specified in Kinder Morgan’s
Engineering Standard (M8370).
In its waiver request, KMLP states all
pipeline welds will undergo
nondestructive testing during
construction. Crews will repair or
remove and replace any weld
imperfections discovered during testing
that do not meet the pipeline safety
regulations. To help and inspect the
pipeline, KMLP will install pig
launchers and receivers designed to
allow the use of inline inspection (ILI)
tools. KMLP will survey the pipeline
with a multi-channel geometry ILI
‘‘smart’’ tool capable of detecting
anomalies (including dents and buckles)
before commissioning the pipeline for
nature gas service. KMLP will also
VerDate Aug<31>2005
23:20 Nov 21, 2006
Jkt 211001
conduct a hydrostatic test of the
pipeline to no less than 100 percent of
SMYS before the pipeline is placed into
service.
Risk Analysis
KMLP stated it conducted a risk
analysis for the pipeline project using a
proprietary risk assessment program to
compare the risks associated with using
a 0.80 design criteria for a Class 1
location pipeline with the risks
associated with the 0.72 design criteria
required by § 192.111. The analysis
determined there was no significant
increase in the risk associated with
using the 0.80 design criteria for this
pipeline design and location. The risk
analysis considered the following nine
risk areas: (1) Stress corrosion cracking,
(2) manufacturing defects, (3) weather/
outside factors, (4) welding and
fabrication defects, (5) equipment
failure, (6) equipment impact (third
party damage), (7) external corrosion, (8)
external corrosion and (9) incorrect
operation. For the first five of these risk
areas, the analysis showed zero or a
negligible increase in the risk of failure
between 0.70 and 0.80 design factor
pipelines.
Though KMLP’s risk analysis did not
show a significant risk increase, it did
find a slightly higher degree of risk in
the areas of external and internal
corrosion when using a 0.80 design
factor as compared to a 0.72 design
factor. KMLP attributes this to the
thinner pipe wall designed using a 0.80
design factor as compared to a pipe wall
using a 0.72 design factor. Additionally,
the risk analysis shows a slightly higher
risk for incorrect operation because a
pipe designed with a 0.80 design factor
operates a higher stress levels and with
a smaller margin between MAOP and
SMYS. KMLP plans to employ several
control and prevention programs to
mitigate these slightly higher risks,
PHMSA will consider a KMLP’s
waiver request and whether its proposal
will yield an equivalent or greater
degree of safety than currently provided
by the regulations. After considering
any comments received, PHMSA may
grant a waiver to KMLP as proposed,
with modifications and conditions, or
deny the request. If PHMSA grants a
waiver and subsequently determines the
effects of the waiver are inconsistent
with pipeline safety, PHMSA reserves
the right to revoke the waiver at any
time.
Authority: 49 U.S.C. 60118(c) and 49 CFR
1.53.
PO 00000
Frm 00165
Fmt 4703
Sfmt 4703
67705
Issued in Washington, DC on November 16,
2006.
Theodore L. Willke,
Acting Associate Administrator for Pipeline
Safety.
[FR Doc. 06–9355 Filed 11–17–06; 3:36 pm]
BILLING CODE 4910–60–M
DEPARTMENT OF TRANSPORTATION
Surface Transportation Board
[STB Finance Docket No. 34951]
Portland & Western Railroad, Inc.—
Trackage Rights Exemption—BNSF
Railway Company
Pursuant to a trackage rights
agreement dated October 30, 2006,
between Portland & Western Railroad,
Inc. (PNWR), and BNSF Railway
Company (BNSF), BNSF has agreed to
grant PNWR overhead trackage rights:
(a) Between milepost 10.0 in Vancouver,
WA, on the BNSF Fallbridge
Subdivision, and milepost 0.69 (Main
Track 1) and milepost 0.91 (Main Track
2) in Portland, OR; and (b) between
milepost 132.5 and milepost 136.5 in
Vancouver, WA, on the BNSF Seattle
Subdivision, a total distance of
approximately 13.31 miles.1
The transaction was scheduled to be
consummated on or after November 13,
2006. On November 13, 2006, PNWR
filed a petition for partial revocation to
permit the expiration of the trackage
rights on May 30, 2016, the termination
date agreed to by the parties.2 The
purpose of the trackage rights is to allow
PNWR and BNSF to shift their
interchange from Salem or Albany, OR,
to Vancouver, WA.3
As a condition to this exemption, any
employee affected by the trackage rights
will be protected by the conditions
imposed in Norfolk and Western Ry.
Co.—Trackage Rights—BN, 354 I.C.C.
605 (1978), as modified in Mendocino
Coast Ry., Inc.—Lease and Operate, 360
I.C.C. 653 (1980).
This notice is filed under 49 CFR
1180.2(d)(7). If it contains false or
1 A redacted version of the trackage rights
agreement between PNWR and BNSF was filed with
the notice of exemption. The full version of the
agreement, as required by 49 CFR 1180.6(a)(7)(ii),
was concurrently filed under seal along with a
motion for protective order. The request for a
protective order is being addressed in a separate
decision.
2 The petition for partial revocation will be
handled in a separate Sub-No. 1 docket in this
proceeding.
3 To accomplish this shift, PNWR will also use
trackage rights between Labish, OR, and Portland,
OR. See Portland & Western Railroad, Inc.—
Trackage Rights Exemption—Union Pacific
Railroad Company, STB Finance Docket No. 34883
(STB served July 19, 2006).
E:\FR\FM\22NON1.SGM
22NON1
67706
Federal Register / Vol. 71, No. 225 / Wednesday, November 22, 2006 / Notices
misleading information, the exemption
is void ab initio. Petitions to revoke the
exemption under 49 U.S.C. 10502(d)
may be filed at any time. The filing of
a petition to revoke will not
automatically stay the transaction.
An original and 10 copies of all
pleadings, referring to STB Finance
Docket No. 34951, must be filed with
the Surface Transportation Board, 1925
K Street, NW., Washington, DC 20423–
0001. In addition, one copy of each
pleading must be served on Eric M.
Hocky, Gollatz, Griffin & Ewing, P.C.,
Four Penn Center Plaza, Suite 200, 1600
John F. Kennedy Blvd., Philadelphia,
PA 19103–2808.
Board decisions and notices are
available on our Web site at https://
www.stb.dot.gov.
Dated: November 17, 2006.
By the Board, David M. Konschnik,
Director, Office of Proceedings.
Vernon A. Williams,
Secretary.
[FR Doc. E6–19775 Filed 11–21–06; 8:45 am]
BILLING CODE 4915–01–P
DEPARTMENT OF TRANSPORTATION
Surface Transportation Board
[STB Finance Docket No. 34177]
Iowa, Chicago & Eastern Railroad
Corporation—Acquisition and
Operation Exemption—Lines of I&M
Rail Link, LLC
AGENCY:
Surface Transportation Board,
DOT.
Notice of Availability of
Environmental Appendix and Request
for Public Review and Comment.
pwalker on PROD1PC61 with NOTICES
ACTION:
SUMMARY: The purpose of this notice is
to announce the availability of, and
invite public review and comment on,
the Environmental Appendix prepared
by the Dakota, Minnesota and Eastern
Railroad Corporation (DM&E) and the
Iowa, Chicago & Eastern Railroad
Corporation (IC&E), which the railroads
submitted to the Board on November 9,
2006. The Environmental Appendix sets
forth the contention of DM&E and IC&E
that their acquisition of rail lines
formerly owned by I&M Rail Link
(IMRL) will not materially alter the
traffic projections or routings for
DM&E’s Powder River Basin coal traffic
that have already been considered in a
separate but related rail construction
case, and that therefore no formal
analysis of the cumulative impacts of
these transactions is required under the
National Environmental Policy Act of
1969 (NEPA), 42 U.S.C. 4321 et seq., or
VerDate Aug<31>2005
22:25 Nov 21, 2006
Jkt 211001
the National Historic Preservation Act of
1966 (NHPA), 16 U.S.C. 470.
Briefly summarized, in a separate
proceeding initiated in 1998, four years
before the filing of the instant
acquisition proceeding, DM&E sought
approval to construct and operate some
280 miles of new rail line so that it
could reach coal mines in Wyoming’s
Powder River Basin (PRB) and thereby
generate adequate revenue to
rehabilitate DM&E’s existing rail system
in South Dakota and Minnesota (DM&E
Construction). During that proceeding it
was contemplated that DM&E’s PRB
coal traffic would move from DM&E’s
new line to various interchange points
with other carriers on DM&E’s existing
line. One of the interchange points
considered in detail was Owatonna,
Minnesota, where DM&E’s PRB coal
traffic was expected to be transferred to
the lines that were then owned by IMRL
to reach some of the utilities in DM&E’s
core markets.
Following extensive environmental
review, the Board authorized the DM&E
Construction in 2002. Following
litigation, a remand by the Eighth
Circuit Court of Appeals, and
subsequent supplemental
environmental analysis, the Board once
again authorized the DM&E construction
project in 2006. Judicial review of that
decision is currently pending.
On June 7, 2002, about 5 months after
the Board had authorized the DM&E
Construction, IC&E filed a notice of
exemption in this proceeding to acquire
and operate the lines of IMRL. In a
related transaction, on August 29, 2002,
DM&E and its subsidiary Cedar
American Rail Holdings, Inc., filed an
application with the Board seeking
approval for control of IC&E. In
decisions issued on July 22, 2002 and
February 3, 2003, the Board allowed
both IC&E’s acquisition of IMRL and
DM&E’s control of IC&E to go forward
subject to a traffic restriction prohibiting
DM&E and IC&E from moving DM&E
coal trains to or from the PRB over the
newly acquired IMRL lines until the
Board could consider what, if any,
environmental review of cumulative
environmental impacts (that is, impacts
from more DM&E coal trains operating
over the former IMRL lines as a result
of the change in ownership of IMRL
than would otherwise have moved over
the IMRL lines) was warranted. The
Board also directed that it be notified if
and when DM&E starts construction of
its new rail line and be provided with
information regarding any anticipated
additional DM&E PRB coal trains that
would move on the IMRL lines as a
result of the acquisition.
PO 00000
Frm 00166
Fmt 4703
Sfmt 4703
In response to a petition filed by
DM&E and IC&E asking that the above
conditions should be lifted, the Board
issued a decision on October 18, 2006,
in the acquisition proceeding. In that
decision, the Board agreed with DM&E
and IC&E that it is not necessary to wait
until DM&E actually begins construction
of its new line to determine the level of
further environmental review, if any,
that is appropriate to consider in the
acquisition case any cumulative effects
of the construction and acquisition
proceedings. The Board further directed
DM&E and IC&E to prepare an
Environmental Appendix setting out the
basis for their contention that the
change in ownership of IMRL does not
materially alter the traffic projections or
routings for DM&E’s PRB coal traffic
previously considered in the DM&E
Construction case and that therefore
there is no need for any further
environmental review under NEPA or
historic review under the NHPA.
The railroads submitted their
Environmental Appendix to the Board
on November 9, 2006. To afford the
public an opportunity to review and
comment on DM&E’s and IC&E’s
position, the entire text of the
Environmental Appendix has been
posted on the Board’s Web site. The
railroads also have distributed the
Environmental Appendix to certain
agencies and communities, as well as all
of the parties on the Board’s service list
in the acquisition case and have
published newspaper notices.
Interested members of the public are
invited to submit comments on any
potentially significant impacts related to
the cumulative effects, if any, of the
acquisition and DM&E Construction to
the Board’s Section of Environmental
Analysis (SEA) by December 11, 2006.
Directions on how to submit comments
are set forth below.
Based on SEA’s consideration of all
timely comments and its own
independent review of all available
environmental information, SEA will
make a recommendation to the Board
regarding what level of further
environmental review, if any, is
warranted here. The Board will then
determine whether to issue a finding of
no significant environmental impact
(FONSI), or, alternatively, to prepare
either an Environmental Impact
Statement or an Environmental
Assessment to examine cumulative
effects of the two proceedings.
The Environmental Appendix may be
viewed on the Board’s Web site by going
to https://www.stb.dot.gov and clicking
on ‘‘E-Library,’’ then clicking on
‘‘Filings.’’ The Environmental Appendix
is listed under November 9, 2006, and
E:\FR\FM\22NON1.SGM
22NON1
Agencies
[Federal Register Volume 71, Number 225 (Wednesday, November 22, 2006)]
[Notices]
[Pages 67705-67706]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-19775]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Surface Transportation Board
[STB Finance Docket No. 34951]
Portland & Western Railroad, Inc.--Trackage Rights Exemption--
BNSF Railway Company
Pursuant to a trackage rights agreement dated October 30, 2006,
between Portland & Western Railroad, Inc. (PNWR), and BNSF Railway
Company (BNSF), BNSF has agreed to grant PNWR overhead trackage rights:
(a) Between milepost 10.0 in Vancouver, WA, on the BNSF Fallbridge
Subdivision, and milepost 0.69 (Main Track 1) and milepost 0.91 (Main
Track 2) in Portland, OR; and (b) between milepost 132.5 and milepost
136.5 in Vancouver, WA, on the BNSF Seattle Subdivision, a total
distance of approximately 13.31 miles.\1\
---------------------------------------------------------------------------
\1\ A redacted version of the trackage rights agreement between
PNWR and BNSF was filed with the notice of exemption. The full
version of the agreement, as required by 49 CFR 1180.6(a)(7)(ii),
was concurrently filed under seal along with a motion for protective
order. The request for a protective order is being addressed in a
separate decision.
---------------------------------------------------------------------------
The transaction was scheduled to be consummated on or after
November 13, 2006. On November 13, 2006, PNWR filed a petition for
partial revocation to permit the expiration of the trackage rights on
May 30, 2016, the termination date agreed to by the parties.\2\ The
purpose of the trackage rights is to allow PNWR and BNSF to shift their
interchange from Salem or Albany, OR, to Vancouver, WA.\3\
---------------------------------------------------------------------------
\2\ The petition for partial revocation will be handled in a
separate Sub-No. 1 docket in this proceeding.
\3\ To accomplish this shift, PNWR will also use trackage rights
between Labish, OR, and Portland, OR. See Portland & Western
Railroad, Inc.--Trackage Rights Exemption--Union Pacific Railroad
Company, STB Finance Docket No. 34883 (STB served July 19, 2006).
---------------------------------------------------------------------------
As a condition to this exemption, any employee affected by the
trackage rights will be protected by the conditions imposed in Norfolk
and Western Ry. Co.--Trackage Rights--BN, 354 I.C.C. 605 (1978), as
modified in Mendocino Coast Ry., Inc.--Lease and Operate, 360 I.C.C.
653 (1980).
This notice is filed under 49 CFR 1180.2(d)(7). If it contains
false or
[[Page 67706]]
misleading information, the exemption is void ab initio. Petitions to
revoke the exemption under 49 U.S.C. 10502(d) may be filed at any time.
The filing of a petition to revoke will not automatically stay the
transaction.
An original and 10 copies of all pleadings, referring to STB
Finance Docket No. 34951, must be filed with the Surface Transportation
Board, 1925 K Street, NW., Washington, DC 20423-0001. In addition, one
copy of each pleading must be served on Eric M. Hocky, Gollatz, Griffin
& Ewing, P.C., Four Penn Center Plaza, Suite 200, 1600 John F. Kennedy
Blvd., Philadelphia, PA 19103-2808.
Board decisions and notices are available on our Web site at http:/
/www.stb.dot.gov.
Dated: November 17, 2006.
By the Board, David M. Konschnik, Director, Office of
Proceedings.
Vernon A. Williams,
Secretary.
[FR Doc. E6-19775 Filed 11-21-06; 8:45 am]
BILLING CODE 4915-01-P