New PURPA Section 210(m) Regulations Applicable to Small Power Production and Cogeneration Facilities, 64342-64375 [06-8928]
Download as PDF
64342
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
18 CFR Part 292
[Docket No. RM06–10–000; Order No. 688]
New PURPA Section 210(m)
Regulations Applicable to Small Power
Production and Cogeneration Facilities
Issued October 20, 2006.
Federal Energy Regulatory
Commission, DOE.
ACTION: Final rule.
AGENCY:
SUMMARY: The Federal Energy
Regulatory Commission (Commission) is
amending its regulations governing
small power production and
cogeneration in response to section 1253
of the Energy Policy Act of 2005 (EPAct
2005), which added section 210(m) to
the Public Utility Regulatory Policies
Act of 1978 (PURPA).
DATES: Effective Date: The rule will
become effective January 2, 2007.
FOR FURTHER INFORMATION CONTACT:
Deborah Wyrick (Technical
Information), Office of Energy Markets
and Reliability, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426,
(202) 502–6113. Marka Shaw (Technical
Information), Office of Energy Markets
and Reliability, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426,
(202) 502–8641. Samuel Higginbottom
(Legal Information), Office of the
General Counsel, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426,
(202) 502–8561. Eric Winterbauer (Legal
Information), Office of the General
Counsel, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426, (202) 502–8329.
SUPLEMENTARY INFORMATION:
Before Commissioners: Joseph T.
Kelliher, Chairman; Suedeen G. Kelly,
Marc Spitzer, Philip D. Moeller, and Jon
Wellinghoff.
sroberts on PROD1PC70 with RULES
I. Introduction
1. On August 8, 2005, the Energy
Policy Act of 2005 (EPAct 2005)1 was
signed into law. Section 1253(a) of
EPAct 2005 adds section 210(m) to the
Public Utility Regulatory Policies Act of
1978 (PURPA)2 which provides, among
other things, for termination of the
requirement that an electric utility enter
into a new contract or obligation to
1 Pub.
L. 109–58, 1253, 119 Stat. 594 (2005).
2 16 U.S.C. 824a–3 (2000).
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
purchase electric energy from qualifying
cogeneration facilities and qualifying
small power production facilities (QFs)
if the Federal Energy Regulatory
Commission (Commission) finds that
the QF has nondiscriminatory access to
one of three categories of markets
defined in section 210(m)(1)(A), (B) or
(C). Thus, to relieve an electric utility of
its mandatory purchase obligation under
PURPA, the Commission must identify
which, if any, markets meet the criteria
contained in 210(m)(1)(A), (B) or (C),
and, if such markets are identified, it
must determine whether QFs have
nondiscriminatory access to those
markets.
2. On January 19, 2006, the
Commission issued a notice of proposed
rulemaking (NOPR) proposing
regulations to implement the provisions
of the new PURPA section 210(m) and
proposing to terminate the requirement
that an electric utility enter into a new
contract or obligation to purchase
electric energy from QFs if the electric
utility is a member of Midwest
Independent Transmission System
Operator, Inc. (Midwest ISO), PJM
Interconnection, L.L.C. (PJM), ISO New
England, Inc. (ISO–NE), or New York
Independent System Operator (NYISO).
After considering industry comments on
the NOPR, the Commission issues this
Final Rule amending the Commission’s
regulations to implement the
requirements in section 210(m). We
believe the regulations adopted in the
Final Rule reflect Congress’s intent to
differentiate between three types of
market structures, each of which
presents differing factors relevant to our
determination of whether QFs have
access to a sufficiently competitive
market to support elimination of the
purchase requirement. Our Final Rule
also recognizes the special
circumstances faced by small QFs and,
accordingly, applies a different test for
this class of QFs. In addition to a
presumption in favor of small QFs, the
rule also recognizes that some QFs,
irrespective of size, may not have the
ability to sell in certain markets because
of operational characteristics or other
constraints.
3. The Commission received extensive
comments on its NOPR.3 At one extreme
are commenters who argue that the
Commission may not address the
mandatory purchase requirement issues
by rulemaking and that competitive
capacity and energy markets do not yet
exist to support a generic finding that
QFs in the four regional transmission
3 Attached as Appendix A is a list of all
commenters and the abbreviations that are used
throughout the order to refer to the commenters.
PO 00000
Frm 00002
Fmt 4701
Sfmt 4700
organization/independent system
operator (RTO/ISO) regions should lose
the right to require electric utilities to
purchase their electric output. At the
other extreme are those who argue that
the Commission, with limited
exceptions, should eliminate the
mandatory purchase requirement
altogether.
4. We do not believe that either
extreme reflects the letter or the spirit of
section 210(m). The QFs who advocate
that we may not or should not act at all
by rulemaking fail to recognize that the
Commission has broad latitude to act by
either rulemaking or adjudication.
Nowhere does section 210(m) preclude
the Commission from acting by
rulemaking. Moreover, where, as here,
recurring and common issues of fact
arise, acting by rulemaking is not only
permissible, but provides more effective
notice to and opportunity for
participation by all affected parties. To
some extent, generic findings about
markets are inevitable, either by
rulemaking or in the first utility specific
filing concerning a specific market.
Making generic findings by rulemaking
provides affected entities, including
QFs, a better opportunity to participate
in the generic proceeding as well as the
individual proceedings that will follow.
Finally, the substantive arguments of
these entities that underlie their
procedural objections fail to recognize
that Congress, in enacting section
210(m), explicitly recognized three
different market structures and required
the Commission to respect the
differences in those markets when
making determinations as to whether to
rescind the purchase obligation. In
essence, they are rearguing the very
debates that Congress settled in
adopting section 210(m).
5. We also do not agree with the
position of utilities that advocate we
should terminate the purchase
obligation in summary fashion in this
rulemaking. Although our action today
respects the choice of Congress in
establishing different tests for different
market structures, we do not, in this
rulemaking, terminate the purchase
obligation of any utility. In this respect,
we modify our approach in the NOPR.
In contrast to the NOPR, in this Final
Rule we establish only rebuttable
presumptions that the purchase
obligation should be eliminated with
respect to certain QFs, not final
determinations.
6. In sum, this Final Rule
appropriately reflects Congressional
intent in enacting section 210(m). It
does not, as some commenters suggest,
ignore the fact that Congress did not
repeal PURPA section 210(a)’s directive
E:\FR\FM\01NOR2.SGM
01NOR2
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
sroberts on PROD1PC70 with RULES
that the Commission prescribe, and
from time to time revise, such rules as
it determines necessary to encourage
cogeneration and small power
production. Rather, it recognizes the
fundamental change which Congress
made to the statutory construct when it
determined that ‘‘no electric utility shall
be required * * * to purchase electric
energy from’’ a QF if certain findings are
made with respect to various markets.
Our action properly implements
Congressional intent in the new section
210(m) that the three different market
structures present different
considerations in determining whether
to relieve utilities of the purchase
obligation. Our action also properly
recognizes that smaller QFs can face
more significant challenges than larger
QFs in accessing competitive wholesale
markets. Our action continues to
support QF development by ensuring
that, where the requirements of section
210(m) are met, QF development will,
as determined by Congress, be
stimulated by market forces, and that
where those requirements have not been
met, QF development will continue to
be stimulated as it is today through the
mandatory purchase obligation. Finally,
nothing in this Final Rule affects any
electric utility’s resource adequacy
obligations, compliance with the
Electric Reliability Organization’s
reliability standards, prudent utility
practice to build or purchase reliable
power at the most economical price, or
resource portfolio obligations under
state law including obligations to
purchase renewable energy.
II. Executive Summary
7. This Final Rule amends the
Commission’s regulations in part 292 4
(pertaining to electric utilities’
requirement to purchase electric energy
from or sell electric energy to a QF) to
implement section 1253 of the EPAct
2005. As relevant here, section 1253
added a new section 210(m) to PURPA,
which:
A. Provides for the termination of the
requirement that an electric utility enter
into new contracts or obligations to
purchase electric energy from a QF, after
appropriate findings by the
Commission;
B. Preserves existing contracts and
obligations to purchase electric energy
or capacity from or to sell electric
energy or capacity to a QF;
C. Provides for the reinstatement of
the requirement to purchase electric
4 18 CFR part 292, subpart C, Arrangements
Between Electric Utilities and Qualifying
Cogeneration and Small Power Production
Facilities Under section 210 of the Public Utility
Regulatory Policies Act of 1978.
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
energy from a QF, upon a showing that
the conditions for terminating the
requirement are no longer met; and
D. Provides for the termination of the
requirement that an electric utility enter
into new contracts to sell electric energy
to QFs, after appropriate findings by the
Commission.
The Commission is amending its Part
292 regulations to address the above
section 210(m) provisions and also to
provide a process for applying for the
reinstatement of the requirement to sell
electric energy to QFs upon a showing
that the conditions for the removal of
that requirement are no longer met.
A. Termination of the Mandatory
Purchase Requirement That an Electric
Utility Enter Into a New Contract or
Obligation To Purchase Electric Energy
From QFs
8. This Final Rule promulgates
regulations that set forth the process by
which electric utilities may apply to be
relieved of the requirement that they
enter into new contracts or obligations
for the purchase of electric energy from
QFs after August 8, 2005. New § 292.309
of the Commission’s regulations
describes the findings that the
Commission must make to justify
relieving an electric utility’s obligation
to enter into new QF purchase contracts.
If the Commission finds that the QF has
nondiscriminatory access to one of three
wholesale markets described in the
statute, the requirement that the electric
utility enter into new contracts or
obligations is terminated. These three
wholesale markets, set forth in the
statute in section 210(m)(1), and
incorporated in the new Commission
regulations at § 292.309, are:
(A)(i) Independently administered,
auction-based day ahead and real time
wholesale markets for the sale of electric
energy; and (ii) wholesale markets for longterm sales of capacity and electric energy; or
(B)(i) Transmission and interconnection
services that are provided by a Commissionapproved regional transmission entity and
administered pursuant to an open access
transmission tariff that affords
nondiscriminatory treatment to all
customers; and (ii) competitive wholesale
markets that provide a meaningful
opportunity to sell capacity, including longterm and short-term sales, and electric
energy, including long-term, short-term and
real-time sales, to buyers other than the
utility to which the qualifying facility is
interconnected. In determining whether a
meaningful opportunity to sell exists, the
Commission shall consider, among other
factors, evidence of transactions within the
relevant market; or
(C) Wholesale markets for the sale of
capacity and electric energy that are, at a
minimum, of comparable competitive quality
PO 00000
Frm 00003
Fmt 4701
Sfmt 4700
64343
as markets described in subparagraphs (A)
and (B).
We interpret section 210(m)(1) to
require the Commission to eliminate the
purchase obligation in markets which
meet the criteria of section 210(m)(1)(A),
(B) or (C) if QFs have nondiscriminatory
access to such markets. These three
wholesale markets are characterized in
this rule in short-hand terms as ‘‘Day 2’’
markets (auction based day-ahead and
real-time markets), ‘‘Day 1’’ markets
(auction based real-time markets but not
auction based day-ahead markets), and
comparable markets, respectively.5 The
Final Rule finds that the Midwest ISO,
PJM, ISO–NE, and NYISO all meet the
criteria of section 210(m)(1)(A). These
RTOs are independently administered
and offer auction-based day ahead and
real time wholesale markets for the sale
of electric energy; and within the
regions represented by these RTOs there
is nondiscriminatory access to
wholesale markets for long-term sales of
capacity and electric energy. Therefore,
except for the rebuttable presumptions
set forth below, the member electric
utilities of these four RTO/ISOs will be
eligible for relief from the requirement
to enter into new contracts for the
purchase of QF electric energy.
9. The Final Rule creates three
rebuttable presumptions:
(A) For all three of the above markets,
with the exception of the 20 megawatt
(MW) presumption discussed next, the
Final Rule finds that the existence of an
open access transmission tariff (OATT),
or a reciprocity tariff filed by a nonjurisdictional utility, pursuant to the
Commission’s open access regulations,6
creates a rebuttable presumption, under
section 210(m)(1), that QFs have
‘‘nondiscriminatory access to’’ the
relevant wholesale markets.7
(B) For all three of the above markets,
the Final Rule establishes a rebuttable
presumption that QFs with a net
capacity no greater than 20 MW, do not
have nondiscriminatory access to
5 Reference to ‘‘Day 2’’ and ‘‘Day 1’’ and the
corresponding parenthetical are meant to be
descriptive and thus are not a recitation of the
elements of section 210(m)(1)(A) or (B).
6 18 CFR 35.28(e). An OATT provides
interconnection as well as transmission services on
a nondiscriminatory basis.
7 To the extent that a QF raises issues about the
adequacy of an electric utility’s implementation of
an OATT, such issues are more properly addressed
in a complaint proceeding and will not be
considered in the context of petitions for the
termination of mandatory purchase requirements.
However, a QF may raise other issues, such as
operational characteristics and transmission
limitations, to attempt to rebut the presumption of
market access when it files a response to an
application submitted pursuant to section 210(m)(3)
of PURPA and section 292.310 of our regulations.
E:\FR\FM\01NOR2.SGM
01NOR2
64344
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
sroberts on PROD1PC70 with RULES
wholesale markets.8 Unless an electric
utility seeking the right to terminate its
requirement to purchase small QF
power specifically rebuts this small QF
presumption, and that electric utility’s
request is granted by the Commission, a
small QF would be eligible to require
the electric utility to purchase its
electric energy.
(C) The Final Rule finds that the four
RTO/ISOs with ‘‘Day 2’’ markets, i.e.,
the Midwest ISO, PJM, ISO–NE, and
NYISO, qualify as markets under section
210(m)(1)(A) and establishes a
rebuttable presumption that these
organizations provide large QFs (above
20 MWs net capacity) interconnected
with member electric utilities with
nondiscriminatory access to the ‘‘Day 2’’
wholesale markets set forth in section
210(m)(1)(A). An electric utility member
of one of these four RTO filing for relief
from the requirement to purchase will
need to refer to this rebuttable
presumption in the Final Rule as part of
its application. When it files an
application for relief from the purchase
requirement it must also submit certain
information, including information
about transmission constraints within
its service territory, in order to give
potentially affected QFs information
that may be useful in rebutting the
presumption that they have access to all
aspects of the applicable ‘‘Day 2’’
markets.9 A QF above 20 MWs net
capacity may rebut the presumption of
nondiscriminatory access by showing
that it in fact lacks access.
10. The rule does not find that any
markets meet the statutory criteria at
this time other than the four listed RTO/
ISOs (Midwest ISO, PJM, ISO–NE, and
NYISO) and the Electric Reliability
Council of Texas (ERCOT) (discussed
below). There will be a rebuttable
presumption that QFs above 20 MWs
net capacity have nondiscriminatory
access to these markets if they are
eligible for service under a Commissionapproved OATT or Commission-filed
reciprocity tariff.
11. With respect to the California
Independent System Operator (CAISO),
and the Southwest Power Pool (SPP),
which have only ‘‘Day 1’’ markets, it
would be premature to find now that the
CAISO and SPP would meet the criteria
of section 210(m)(1)(A) once their
ongoing market redesigns become
effective. However, we find that: the
CAISO and SPP meet the section
210(m)(1)(B)(i) criterion because they
8 Herein
referred to as small QFs.
electric utility would have to make
additional showings if it wished to rebut the
presumption that small QFs do not have
nondiscriminatory access to its region’s ‘‘Day 2’’
wholesale markets.
9 The
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
are Commission-approved regional
transmission entities that provide
transmission and interconnection
services pursuant to open access
transmission tariffs that provide
nondiscriminatory treatment to all
customers. A member electric utility of
the CAISO or SPP may rely on this
finding in its application to be relieved
of the obligation to enter into new
contracts to purchase QF electric
energy, but must make all the other
showings required under section
210(m)(1)(B) before its request may be
granted.
12. The Final Rule finds that ERCOT
meets the criteria of section
210(m)(1)(C). ERCOT offers wholesale
markets for the sale of capacity and
electric energy that are of comparable
competitive quality as the markets
described in sections 210(m)(1)(A) and
(C). Therefore, except for the rebuttable
presumptions set forth herein, the
member electric utilities of ERCOT will
be eligible for relief from the
requirement to enter into new contracts
for the purchase of QF electric energy.
13. New § 292.310 of the
Commission’s regulations sets forth the
filing requirements for an application by
an electric utility seeking to terminate
its requirement to enter into new
purchase contracts with QFs. Among
other things, the regulations require the
electric utility to list the names and
addresses of all potentially affected QFs,
existing or under development. After
notice and comment, the Commission
will issue an order making a final
determination within 90 days of the
application, as required by section
210(m)(3).
B. Preservation of Existing Contracts
14. The Final Rule preserves the
rights or remedies of any party under
existing contracts or obligations, in
effect or pending approval before the
appropriate state regulatory authority or
non-regulated electric utility on or
before August 8, 2005, to purchase
electric energy from or to sell electric
energy to a QF. This provision is stated
in the new § 292.314 of the
Commission’s regulations. The Final
Rule defines the term ‘‘obligations’’
broadly to encompass any legally
enforceable obligation established
through a state’s implementation of
PURPA.
C. Reinstatement of the Mandatory
Purchase Requirement
15. The Final Rule also sets forth a
process by which a QF may seek the
reinstatement of the requirement to
purchase electric energy, by showing
that the conditions necessary for the
PO 00000
Frm 00004
Fmt 4701
Sfmt 4700
removal of the requirement to purchase
are no longer met. After notice,
including notice to the affected utilities,
and comment, the Commission will
issue an order within 90 days of the
application. This process is set forth in
the new § 292.311 of the Commission’s
regulations. A QF’s request may be
specific (and limited) to itself alone,
generic for the entire service territory of
an electric utility, or regional in scope.
The Commission will address the merits
of each request as warranted by the
circumstances presented in each case.
D. Termination of the Requirement To
Sell Electric Energy to QFs
16. The Final Rule provides for
applications to remove the requirement
to enter into new contracts to sell
electric energy to QFs. The statute
provides that if the Commission finds
that competing retail electric suppliers
are willing and able to sell and deliver
electric energy to a QF, and the electric
utility is not required by state law to sell
electric energy in its service territory,
the requirement to sell should be
terminated. The new § 292.312 of the
Commission’s regulations describes this
process. The Final Rule makes no
findings or presumptions with respect
to an electric utility’s obligation to sell
electric energy to QFs.
E. Reinstatement of the Requirement To
Sell Electric Energy to QFs
17. Finally, the Final Rule provides
for applications to reinstate the
requirement of an electric utility to sell
electric energy to QFs, by showing that
the conditions necessary for the removal
of the requirement to sell are no longer
met. After notice and comment, the
Commission will issue an order within
90 days if the required showing is made.
Applications for reinstatement are
addressed in the new § 292.313 of the
Commission’s regulations.
F. Recovery of Prudently Incurred Costs
Relating to QF Power Purchases
18. The Final Rule does not adopt
new regulations implementing section
210(m)(7), regarding an electric utility’s
recovery of prudently incurred costs
relating to purchases of electricity from
QFs.
III. Background
A. History of Section 210 of PURPA
19. When Congress enacted section
210 of PURPA, it required the
Commission to prescribe such rules as
the Commission determined necessary
to encourage cogeneration and small
power production, including rules
requiring electric utilities to offer to
purchase electric energy from and sell
E:\FR\FM\01NOR2.SGM
01NOR2
sroberts on PROD1PC70 with RULES
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
electric energy to QFs. Additionally,
section 210 of PURPA authorized the
Commission to exempt QFs from certain
federal and state laws and regulations if
necessary to encourage cogeneration
and small power production.
20. A cogeneration facility is defined
in the Federal Power Act (FPA) 10 as a
facility which produces electric energy
and steam or forms of useful energy
(such as heat) which are used for
industrial, commercial, heating, or
cooling purposes.11 Thus, cogeneration
facilities simultaneously produce two
forms of useful energy, namely electric
energy and heat. Cogeneration facilities
can use significantly less fuel to
produce electric energy and steam (or
other forms of energy) than would be
needed to produce the two separately.
21. Small power production facilities,
as defined in the FPA, use biomass,
waste, or renewable resources,
including wind, solar energy and water,
to produce electric energy and have a
power production capacity which,
together with any other facilities located
at the same site, is not greater than 80
megawatts.12 Reliance on these sources
of energy can reduce the need to
consume fossil fuels to generate electric
power.
22. Prior to the enactment of PURPA,
a cogenerator or small power producer
seeking to establish interconnected
operation with a utility faced three
major obstacles. First, utilities were not
generally willing to purchase this
electric output or were not willing to
pay an appropriate rate for that output.
Second, utilities generally charged
discriminatorily high rates for back-up
service to cogenerators and small power
producers. Third, a cogenerator or small
power producer which provided electric
energy to a utility’s grid ran the risk of
being considered a public utility and
thus being subjected to extensive state
and federal regulation.
23. Section 210 of PURPA was
designed to remove these obstacles.
Each electric utility is required under
section 210 to offer to purchase
available electric energy from
cogeneration and small power
production facilities which obtain
qualifying status. The rates for such
purchases from QFs must be just and
reasonable to the ratepayers of the
utility, in the public interest, and must
not discriminate against cogenerators or
small power producers. Rates also must
not exceed the incremental cost to the
electric utility of alternative electric
energy (also known as the electric
10 16
U.S.C. 824 et seq.
796(18).
12 Id. 796(17)(A)(i)–(ii).
11 Id.
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
utility’s ‘‘avoided costs’’). Section 210
also requires electric utilities to provide
electric energy to QFs at rates which are
just and reasonable, in the public
interest, and which do not discriminate
against cogenerators and small power
producers. Rates for the purchase of
energy from and the sale of energy to a
QF are set by the appropriate state
regulatory authority or non-regulated
utility pursuant to the Commission’s
regulations, 18 CFR 292.301–308 (2006).
24. Since Congress enacted PURPA,
electric utilities have complained that
their requirement to purchase from and
sell to QFs, as implemented by the
Commission in 18 CFR 292.303(a)–(b),
was not economically beneficial and
that they were purchasing energy they
did not need and selling energy they did
not want to sell. In 1995, the
Commission clarified that
determinations of the avoided-cost rate
must take into account all alternative
sources including third-party suppliers
and an electric utility does not pay for
electric energy it does not need.13 In the
past decade, with the development of
exempt wholesale generators (EWGs)
introduced by the Energy Policy Act of
1992,14 the implementation of open
access transmission via Order No. 888,
the advent of ISOs and RTOs and
organized markets, the Commission’s
new interconnection requirements, and
increasing competition in wholesale
electric markets as well as some retail
electric markets, Congress has debated
whether to repeal PURPA altogether, or
to revise it. The result is new section
210(m), which is the subject of this
rulemaking, and new section 210(n),
which was addressed in Docket No.
RM05–36–000.15
B. New Section 210(m)
25. Section 210(m) of PURPA is titled
‘‘Termination of Mandatory Purchase
and Sale Requirements.’’ The section
revises the rights and obligations
between electric utilities and QFs.
Section 210(m)(1) requires the
Commission to terminate the
13 Southern California Edison Company and San
Diego Gas & Electric Company, 70 FERC ¶ 61,215
at 61,677–78, reconsideration denied, 71 FERC
¶ 61,269 at 62,078 (1995) (finding that the
determination of avoided cost must take into
account ‘‘all sources’’).
14 Energy Policy Act of 1992, Pub. L. No. 102–486,
106 Stat. 2776, (1993) (EPAct 1992). EPAct 1992
added a new section 32 to the Public Utility
Holding Company Act of 1935 (PUHCA) to permit
a category of sellers called EWGs to be exempt from
PUHCA.
15 Revised Regulations Governing Small Power
Production and Cogeneration Facilities, Order No.
671, 71 FR 7852 (Feb. 15, 2006), FERC Stats. & Regs.
¶ 31,203 (2006), order on reh’g, Order No. 671–A,
71 FR 30585 (May 30, 2006), FERC Stats. & Regs.
¶ 31,219 (2006).
PO 00000
Frm 00005
Fmt 4701
Sfmt 4700
64345
requirement of an electric utility to
enter into a new contract or obligation
with the QF if it finds that a QF has
nondiscriminatory access to a market
described in section 210(m)(1)(A), (B) or
(C). Section 210(m)(2) states that after
the date of enactment, no utility will be
required to enter into a contract to
purchase from or sell to a new
cogeneration facility, unless the facility
meets the criteria for new cogeneration
facilities established by the Commission
in implementing section 210(n) of
PURPA. Section 210(m)(3) provides that
an electric utility may file ‘‘an
application for relief from the
mandatory purchase obligation’’ on a
service territory-wide basis and
provides that the Commission must
make a final determination on such an
application within 90 days of the
application. Section 210(m)(4) provides
that a QF, a state agency, or other
affected person may apply for an order
reinstating the electric utility’s
‘‘obligation to purchase electric energy
under this section’’ upon a change in
the market. Section 210(m)(5) provides
for the termination of the requirement
that an electric utility enter into a new
contract or obligation to sell electric
energy to a QF upon a finding that
specified competitive conditions exist.
Section 210(m)(6) provides that nothing
in section 210(m) affects the rights or
remedies of any party under any
contract or obligation in effect or
pending approval before the appropriate
state regulatory authority or
nonregulated utility on the date of
enactment of section 210(m). And
finally, section 210(m)(7) provides that
the Commission shall issue and enforce
such regulations as are necessary to
ensure that an electric utility that
purchases electric energy or capacity
from a QF in accordance with a legally
enforceable obligation entered into or
imposed under section 210 of PURPA
recovers all prudently incurred costs
associated with the purchase.
C. NOPR
26. On January 19, 2006, the
Commission issued a NOPR containing
its proposal to implement section
210(m) of PURPA. Generally, the
Commission proposed to incorporate
the language of section 210(m) in its
regulations. While section 210(m)
permits electric utilities to file
applications for relief from the
mandatory purchase requirement, and
requires the Commission to act on such
applications within 90 days, the
Commission determined in the NOPR
that it is appropriate to act generically
as much as possible. Specifically,
section 210(m)(1)(A) is most suitable for
E:\FR\FM\01NOR2.SGM
01NOR2
64346
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
such a generic implementation and the
Commission proposed to make generic
findings that certain markets meet the
section 210(m)(1)(A) criteria. The NOPR
concluded that the most reasonable
interpretation of section 210(m)(1)(A) is
that it was crafted to apply to regions in
which ISOs and RTOs administer
auction-based day ahead and real time
wholesale markets for the sale of electric
energy; and wholesale markets for longterm sales of capacity and electric
energy are that these are available to
participants/QFs in these markets.16
The Commission proposed in the NOPR
that it would make a generic finding
that the Midwest ISO, PJM, ISO–NE,
and NYISO provide markets that meet
the requirements of section 210(m)(1)(A)
and therefore utilities that are members
of those ISOs or RTOs meet the criteria
for relieving those electric utilities of
the requirement to enter into new
contracts or obligations with QFs.17
Because the Commission proposed to
make a generic finding with respect to
210(m)(1)(A), the Commission proposed
that the electric utilities that are
members of these four RTO/ISOs submit
a compliance filing instead of filing
applications for relief of the purchase
requirement pursuant to 210(m)(3). In
the compliance filing, the electric utility
would demonstrate: (1) Membership in
the RTO/ISO; (2) that the Commission
has made a final finding that the RTO/
ISO it is a member of provides
nondiscriminatory access to a section
210(m)(1)(A) market; (3) a list of all
potentially affected QFs; and (4) the QFs
have the rights to request service under
the OATT.18
27. The Commission concluded that
QFs have nondiscriminatory access to
transmission and interconnection if they
have access to utilities providing service
under an Order No. 888 OATT (or to
utilities providing service under a
Commission-accepted reciprocity tariff)
and interconnection services pursuant
to the Commission’s interconnection
rules.19 The Commission also proposed,
however, that there be a rebuttable
presumption that a utility provides
nondiscriminatory access if it has an
open access transmission tariff in
compliance with our pro forma OATT
(or a Commission-approved reciprocity
tariff) and that QFs or any other affected
16 NOPR
at P 14.
at P 22–28.
18 Id. at P 40. We note that, since the time
comments were filed in this proceeding, the
Commission has issued a NOPR proposing
amendments to the OATT. Preventing Undue
Discrimination and Preference in Transmission
Service, 71 FR 32636 (2006), FERC Stats. & Regs.
¶ 32,603 (2006).
19 Id. at P 20.
sroberts on PROD1PC70 with RULES
17 Id.
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
party should be allowed to rebut that
presumption, for example, by providing
specific and credible evidence that the
QF does not have nondiscriminatory
access to wholesale markets.20 The
Commission noted that improper
implementation of an OATT is more
properly the subject of a complaint.
28. Further, the Commission proposed
in the NOPR that other markets, i.e.,
both non-auction-based markets and
non-RTO/ISO markets described in
section 210(m)(1)(B) and (C), would not
be addressed generically in this
rulemaking but would be addressed on
a case-by-case basis in response to
applications filed pursuant to the
Commission’s implementation of
section 210(m)(3) of PURPA, i.e.,
pursuant to the proposed § 292.310 of
the Commission’s regulations.21 The
Commission proposed that subsequent
changes to market conditions in all
markets, i.e., markets described
subparagraphs (A), (B) and (C) also
would be handled on a case-by-case
basis as well. Applications for
termination of the requirement to enter
into new contracts or obligations to
purchase from QFs in markets described
in subparagraphs (B) and (C) would be
addressed pursuant to the proposed
§ 292.310 of the Commission’s
regulations. An application to reinstate
the requirement that a utility enter in
the new contracts or obligations to
purchase from QFs, alleging subsequent
changes to market conditions, would be
addressed pursuant to the proposed
§ 292.311 of the Commission’s
regulations. The Commission noted that
it must make a finding regarding an
application for relief of the purchase
requirement and that the finding must
be made within 90 days of the date of
such application. The Commission
stated that it expected an application for
relief to be fully supported by
documentation upon which the required
finding can be made.22
29. Of the approximately 2,000 pages
of comments the Commission has
received to its NOPR, a large portion of
the comments focused on the standards
applicable to utilities within the ‘‘Day
2’’ RTO/ISOs and the procedures for
utilities within ‘‘Day 2’’ markets to
claim relief from the purchase
requirement. Based on careful
consideration of the comments
submitted in response to the NOPR, the
Commission adopts a Final Rule that
makes certain modifications and
20 Id.
at P 31.
at P 29–30.
22 The Commission interprets the 90-day period
to begin upon receipt of a completed application.
21 Id.
PO 00000
Frm 00006
Fmt 4701
Sfmt 4700
clarifications to the approach in the
NOPR.
IV. Discussion
A. Section 210(m)(1)
30. The new PURPA section 210(m)(1)
amends the statutory requirement that
electric utilities purchase electric energy
from QFs and states that:
* * * No electric utility shall be required to
enter into a new contract or obligation to
purchase electric energy from a qualifying
cogeneration facility or a qualifying small
power production facility under this section
if the Commission finds that the qualifying
cogeneration facility or qualifying small
power production facility has
nondiscriminatory access to—
(A)(i) Independently administered, auctionbased day ahead and real time wholesale
markets for the sale of electric energy; and (ii)
wholesale markets for long-term sales of
capacity and electric energy; or
(B)(i) Transmission and interconnection
services that are provided by a Commissionapproved regional transmission entity and
administered pursuant to an open access
transmission tariff that affords
nondiscriminatory treatment to all
customers; and (ii) competitive wholesale
markets that provide a meaningful
opportunity to sell capacity, including longterm and short-term sales, and electric
energy, including long-term, short-term and
real-time sales, to buyers other than the
utility to which the qualifying facility is
interconnected. In determining whether a
meaningful opportunity to sell exists, the
Commission shall consider, among other
factors, evidence of transactions within the
relevant market; or
(C) Wholesale markets for the sale of capacity
and electric energy that are, at a minimum,
of comparable competitive quality as markets
described in subparagraphs (A) and (B).
1. Three Standards for Relief
a. NOPR
31. Section 210(m)(1) defines under
what conditions the Commission must
relieve an electric utility of the
obligation to enter into a new contract
or obligation to purchase electric energy
from a QF. Essentially, section
210(m)(1) establishes three different
standards for relief from the purchase
requirement depending on whether: (1)
Electric utilities are members of ‘‘Day 2’’
RTO/ISOs; (2) electric utilities are
members of ‘‘Day 1’’ RTO/ISOs; and (3)
electric utilities are in neither ‘‘Day 2’’
nor ‘‘Day 1’’ RTO/ISOs. The NOPR
interpreted the language of section
210(m)(1) as to what conditions must
exist for the three types of markets and
sought comments.
32. The NOPR explained that the first
standard for relief is established in
section 210(m)(1)(A) of section
210(m)(1), which applies to ‘‘Day 2’’
markets with wholesale bilateral long-
E:\FR\FM\01NOR2.SGM
01NOR2
sroberts on PROD1PC70 with RULES
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
term contracts for the sale of capacity
and electric energy available to
participants. The Commission indicated
that, under section 210(m)(1)(A)(ii),
there was no requirement, given the
statutory language, to consider
‘‘evidence of transactions within the
relevant market’’ when determining
whether QFs have nondiscriminatory
access to ‘‘wholesale markets for longterm sales of capacity and electric
energy.’’ The Commission suggested
that Congress presumed QFs, which
have ‘‘nondiscriminatory access to’’ ISO
and RTO regions with auction-based
day ahead and real time markets, have
nondiscriminatory access to long-term
sales of electric energy and capacity
wholesale markets outside the
interconnected utility. The Commission
proposed to find that Midwest ISO, PJM,
ISO–NE, and NYISO meet the
requirements of section 210(m)(1)(A).
33. The second standard for relief is
established in section 210(m)(1)(B),
which the Commission found to be
intended to apply in ‘‘Day 1’’ RTO/ISOs,
i.e., those that do not have both auctionbased day ahead and real time markets.
Section 210(m)(1)(B) provides for
termination of the requirement that an
electric utility enter into a new contract
or obligation to purchase electric energy
from a QF so long as there is (i) a
Commission-approved regional
transmission entity providing
nondiscriminatory transmission and
interconnection services; and (ii)
‘‘competitive wholesale markets that
provide a meaningful opportunity’’ to
sell capacity and energy on both a shortand long-term basis and energy on a
real-time basis (emphasis added) to
buyers other than the utility to which
the QF is interconnected. In the NOPR,
the Commission stated that ‘‘meaningful
opportunity’’ is to be determined by the
Commission after considering, among
other factors, ‘‘evidence of transactions
within the relevant market.’’ The
Commission indicated that taken
together, the terms ‘‘competitive,’’
‘‘meaningful opportunity’’ and
‘‘evidence of transactions’’ suggest that
Congress intended that termination of
the purchase requirement in a ‘‘Day 1’’
market only if it could be established
that QFs had opportunities to make
long-term and short-term sales of
capacity and long-term, short-term and
real-time sales of energy into
competitive wholesale markets.
34. The third standard for relief is
established in section 210(m)(1)(C) of
section 210(m)(1). Under this standard,
the purchase requirement is removed in
wholesale markets for the sale of
capacity and electric energy that are, ‘‘at
a minimum,’’ of comparable competitive
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
quality as markets described in
subparagraphs (A) and (B). The
Commission explained that although
this provision is not clear on its face, its
reference to subparagraphs (A) and (B)
requires the Commission to be mindful,
in interpreting the provision, of the two
types of requirements that are embodied
in those sections, i.e., (1)
nondiscriminatory access to
transmission and interconnection
services, and (2) competitive short-term
and long-term markets that provide a
meaningful opportunity to sell to buyers
other than the utility to which the QF
is interconnected.
b. Comments
35. ELCON, AWEA, Caithness and
Public Interest Organizations (PIOs),23
for example, state that Congress did not
repeal the mandatory purchase
requirement and that the Commission
has a continuing obligation to promote
QF development. This, they contend,
can only be accomplished by assuring
that markets meet criteria that guarantee
that QFs will enter into contracts with
electric utilities of similar quality to
those that they received prior to the
enactment of section 210(m) of PURPA
before the mandatory purchase
obligation can be terminated. ELCON
appears to suggest that there is only one
standard for relief from the purchase
requirement: ‘‘assurance of a
competitive market.’’ 24 In essence,
ELCON argues that sections
210(m)(1)(A), (B) and (C) establish a
single standard for terminating the
mandatory purchase obligation. ELCON
states that section 210(m) authorizes the
Commission to grant relief from the
purchase requirement ‘‘if and only if a
viable market exists.’’ 25 ELCON
expresses its concern that because
discrimination continues and the
markets are flawed, competition and onsite generation will be discouraged.
AWEA and Caithness state that the
Commission should grant relief from the
purchase requirement only in markets
which are ‘‘sufficiently competitive.’’ 26
EPSA argues that the mandatory
purchase requirement can be terminated
only where the Commission finds that
the ‘‘economic and technical equivalent
23 The PIOs filing these comments are the Center
for Energy Efficiency & Renewable Technologies,
Delaware Division of the Public Advocate,
Environmental Law & Policy Center, Interwest
Energy Alliance, Izaak Walton League of America,
Natural Resources Defense Council, Northwest
Energy Coalition, Office of the Ohio Consumers’
Counsel, Pace Energy Project, Project for
Sustainable FERC Energy Policy, West Wind Wires,
and Western Resource Advocates.
24 ELCON Comments at 8.
25 Id.
26 AWEA Comments at 2.
PO 00000
Frm 00007
Fmt 4701
Sfmt 4700
64347
to mandatory purchase is available
through a competitive market.’’27 PIOs
argue that electric utilities have to
demonstrate that QFs do, in fact, have
physical and economic access to all of
the required markets on a
nondiscriminatory basis. The American
Chemistry Council contends that the
mandatory purchase requirement can be
terminated only in those situations
where wholesale markets have evolved
to ensure the long-term commercial
viability of QFs which enables QFs to
attract investment capital and facilitates
QF development; the American
Chemistry Council urges the
Commission to interpret section
210(m)(1) in such a manner.
36. NPRA reminds the Commission
that the main purpose of cogeneration is
not to serve the needs of an electric
power grid or ‘‘market,’’ but, rather, it is
to serve the interconnecting industrial
thermal and electrical load.
Consequently, NPRA argues that the
operation of these facilities may require
different market features than are
required by utility electric generation or
merchant generation. NPRA argues that
Congress intended to terminate the
‘‘must take’’ requirement only when it
can be demonstrated that an electric
market supports not only the role of
merchant power, but the retention and
encouragement of cogeneration. In other
words, while a market may prove an
efficient and viable alternative for a
merchant plant, it does not necessarily
ensure that it is an efficient and viable
alternative for sales of power by a
cogeneration facility.
c. Commission Determination
37. We disagree with commenters’
interpretation of the statutory standard
for relief from the requirement that an
electric utility enter into a new contract
or obligation to purchase electric energy
from a QF. There is nothing in section
210(m) to suggest that Congress
intended to ensure a QF’s commercial
viability. Nor does the statute require
the Commission to find that the
‘‘economic and technical equivalent to
mandatory purchase is available
through a competitive market’’ before it
terminates the requirement that an
electric utility enter into a new contract
or obligation to purchase electric energy
from QFs. Although we certainly agree
with the QF commenters that Congress
did not repeal the mandatory purchase
requirement in its entirety, Congress
clearly left the Commission with no
choice but to eliminate the mandatory
purchase requirement for utilities
operating in certain markets upon
27 EPSA
E:\FR\FM\01NOR2.SGM
Comments at 9.
01NOR2
sroberts on PROD1PC70 with RULES
64348
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
certain findings being made. The fact is
that the language of section 210(m)(1)
provides that an electric utility shall be
relieved of the requirement to purchase
from a QF if the Commission makes
certain findings, which findings do not
include a determination that the
‘‘economic and technical equivalent to
mandatory purchase is available
through a competitive market.’’ This is
not what section 210(m) says, nor would
it make any sense to infer such an
interpretation. Competitive markets do
not, by definition, impose ‘‘mandatory’’
purchase obligations on buyers. Buyers
choose among differing sellers based on
their relative cost, reliability, etc. The
QFs making this argument therefore
ignore the relevant statutory language
and, in doing so, reargue the debate
before Congress when it enacted section
210(m).
38. The most reasonable
interpretation of section 210(m)(1) is
that Congress, in setting forth discrete
tests for three different types of markets,
was requiring the Commission to
differentiate among these markets, and
the differing circumstances they
present, in determining whether a
utility must be relieved of the
mandatory purchase obligation.
Although the statute is ambiguous in
certain respects, it clearly reflects
Congressional intent that the
Commission differentiate among these
three markets in making its
determination regarding whether to
terminate the purchase obligation. This
approach not only reflects a natural
reading of the words of the statute, it
also is reasonable given the nature of the
determination being made. There is
little debate in this proceeding that Day
2 organized markets, as a general matter,
provide greater opportunities for QFs
(and other independent generators) to
compete than unorganized markets
because of the existence of day-ahead
and real-time energy markets that allow
all competing generators to submit bids
to participate in the market on a
nondiscriminatory basis. Although other
markets—including ‘‘Day 1’’ markets
and non-organized markets—also
provide opportunities for independent
generators to compete, it is not
surprising that Congress would find
that, as a general matter, they have less
formalized structures for doing so and,
hence, utilities seeking relief from the
purchase obligation in those markets
would bear a heavier evidentiary burden
to obtain relief. The Commission
cannot, as some commenters in effect
ask us to do, simply collapse the three
discrete tests into one test that requires
an electric utility to demonstrate that a
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
QF will remain economically viable if
the purchase requirement is eliminated.
This would make the three different
statutory standards meaningless.
2. The Nondiscriminatory Access
Requirement of Section 210(m)(1) and
the OATT
a. NOPR
39. Section 210(m)(1) provides for
termination of the requirement for an
electric utility to enter into a new
contract or obligation to purchase from
a QF if the QF has ‘‘nondiscriminatory
access’’ to a wholesale market described
in section 210(m)(1)(A), (B), or (C). In
the NOPR, the Commission proposed
that there be a rebuttable presumption
that a utility provides
nondiscriminatory access if it has an
Order No. 888 OATT (or a utility
providing service under a Commissionapproved reciprocity tariff). The
Commission stated that QFs or any
other party should be allowed to rebut
that presumption, but that improper
implementation of an OATT is more
properly the subject of a complaint to
ensure that the OATT is properly
implemented.
b. Comments
40. ELCON and virtually every other
commenter from the QF industry argue
that the Commission erred in the NOPR
by proposing a rebuttable presumption
that a utility provides
‘‘nondiscriminatory access’’ to the
market conditions identified in section
210(m)(1)(A), (B), or (C) if it has an
OATT in compliance with the
Commission’s pro forma OATT, or a
Commission-approved reciprocity tariff.
They argue that the proposal reflects an
overly simplified interpretation of the
statute’s ‘‘nondiscriminatory access’’
requirement and that the mere existence
of transmission rights under an OATT
does not necessarily ensure that QFs
have nondiscriminatory access to
markets. ELCON and the QF industry
argue that barriers that discriminate
against QFs could exist notwithstanding
the adoption of an OATT. The
California Cogeneration Council (CCC),
for instance, states that these barriers
could be present in ISO policies that
make it more difficult or burdensome
for QFs to participate in a market as
compared with other types of generators
or market participants. ELCON and the
QF industry argue that section 210(m)(1)
requires the Commission to consider
such potential barriers, and to evaluate
whether QFs truly have
nondiscriminatory access to alternative
markets, before concluding that the
PO 00000
Frm 00008
Fmt 4701
Sfmt 4700
requirements of section 210(m)(1) have
been met.
41. In addition, ELCON and the QF
industry state that the Commission has
recognized that the intent of Order No.
888 concerning nondiscriminatory
access to transmission has not been
fully realized; first in Order No. 2000 28
and more recently in the NOPR on
Preventing Undue Discrimination and
Preference in Transmission Service.29
42. EPSA, Reliant and PIOs add that
any tariff for transmission and
interconnection services must
incorporate changes consistent with the
Commission’s pro-competitive policies
of Order No. 2000 and any further
improvements determined as part of the
notice of inquiry (NOI). EPSA argues
that only then will the transmission and
interconnection services be provided on
a nondiscriminatory, pro-competitive
basis.
43. Dow Chemical Company (Dow)
states that there are numerous instances
in which QFs effectively have no access
to organized markets or to transmission
services regardless of whether the
utilities to which they are
interconnected technically participate
in organized markets or provide
transmission and interconnection
services on an open access basis. Dow
states that instead, in such instances,
the only entity physically capable of
acquiring QF output is the utility with
which the QF is interconnected.
American Forest & Paper states that
market rules designed for merchant
generation are often highly
discriminatory to QFs which, because of
the thermal needs of a cogeneration
QF’s thermal host, have limited
dispatchability and must often be
operated in base load configurations.
American Forest & Paper states that
market rules designed around the
dispatchability of resources which do
not have attendant manufacturing
facility obligations may discriminate
unnecessarily and unreasonably against
QFs. Council of Industrial Boiler
Owners (CIBO) state that by finding that
an OATT is sufficient to ensure
nondiscriminatory access to markets,
the Commission fails to consider the
operational differences faced by QFs.
44. In addition, Commenters argue
that the NOPR’s proposal that there be
a rebuttable presumption that a utility
provides nondiscriminatory access if it
28 Regional Transmission Organizations, Order
No. 2000, 65 FR 809 (Jan. 6, 2000), FERC Stats. &
Regs. P 31,089 (1999), order on reh’g, Order No.
2000–A, 65 FR. 12,088 (Mar. 8, 2000), FERC Stats.
& Regs. P 31,092 (2000), aff’d sub nom. Pub. Util.
Dist. No. 1 of Snohomish County, Washington v.
FERC, 272_F.3d_607 (D.C. Cir. 2001).
29 See supra note 15.
E:\FR\FM\01NOR2.SGM
01NOR2
sroberts on PROD1PC70 with RULES
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
has an OATT is in essence an
irrebuttable presumption. ELCON and
the American Chemistry Council state
that although the Commission
characterizes the presumption as
‘‘rebuttable,’’ it also states that the
presumption ‘‘cannot be rebutted by an
argument that the utility has not
properly implemented or administered
its OATT.’’
45. ELCON argues that it will be
difficult for the Commission to sustain
on judicial review an irrebuttable
presumption that the OATT provides
nondiscriminatory transmission access
for all QFs when its own NOI recognizes
the continuation of patterns of abuse—
if anything exacerbated as transmission
owners feel the pressure of competition
from independent generation. ELCON
states that the concern over potential
discrimination will only be exacerbated
in a scenario like the Entergy
Independent Coordinator of
Transmission (ICT) where the utility
and not the RTO provide service.
ELCON states that while the problem of
discrimination in transmission is
pervasive, a fortiori, QFs of whatever
size connected at distribution voltage do
not have access to markets. ELCON
states that the scenario of QFs
connected at distribution voltage and
the circumstances of small QFs
illustrate why generic conclusions are
inappropriate.
46. Further, Occidental Chemical
Corporation (Occidental) argues that the
Commission’s conclusion that a
complaint, rather than the application
proceeding, is the only vehicle available
to address a QF’s concern that the
OATT is being administered or
implemented in a discriminatory
manner is inconsistent with the plain
language of the statute. Occidental states
that a QF cannot provide meaningful
comments on whether an electric
utility’s application meets the
nondiscriminatory showing required by
statute, if the QF is barred from raising
issues regarding discriminatory
administration or implementation of the
OATT and can only raise such issues in
a separate complaint proceeding. In
addition, Occidental argues that it is
unclear how the Commission could
make a determination that QFs have
nondiscriminatory access under an
electric utility’s OATT if the
Commission bars, from the outset, all
evidence that the OATT is being
administered or implemented in a
discriminatory manner.
47. PJM is concerned with the
Commission’s presumption for both
section 210(m)(1)(B) and (C) that having
an Order No. 888 OATT on file is
enough to establish a presumption of
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
nondiscriminatory access to the grid.
PJM states that rather, the Commission
should analyze particular facts and
circumstances relative to concerns
raised with potential access to the
marketplace for QFs.
48. EEI, Allegheny Power, Alliant,
Entergy, National Grid and PSNM/TNP
agree with the NOPR’s proposal. EEI
states that QF commenters raise no
compelling evidence that access
provided pursuant to Commissionapproved OATTs is deficient. EEI states
that nondiscriminatory access is the
standard set by Congress in EPAct 2005,
and Congress was fully aware when it
used this standard that the OATT is the
mechanism for achieving
nondiscriminatory access. Allegheny
joins EEI in stating that the Commission
should make a generic finding that QF
access pursuant to a Commissionapproved OATT meets the
‘‘nondiscriminatory access’’ test of
section 210(m) for all markets, whether
centrally organized and administered or
not.
49. EEI states that the fact that the
Commission is considering updating
Order No. 888 through its ongoing NOI
does not mean that reliance on the
OATT as the current benchmark for
nondiscriminatory access is
inappropriate. EEI states that at this
preliminary stage of the Commission’s
inquiry into whether changes to the
OATT should be required, it is
premature to predict what the
Commission may or may not finally
conclude with respect to the OATT. EEI
states that by basing so much of their
argument on the Commission’s
consideration of reforms to Order No.
888, QF commenters are in essence
converting a Commission NOI into a
Commission final rule. EEI states that
even if the Commission fine tunes the
OATT, it would not mean that existing
open access practices pursuant to
Commission-approved OATT are
discriminatory. EEI states that if the
Commission does ultimately require
changes, QFs—like any other
generator—will reap the benefit of those
enhancements.
50. EEI further argues that where
issues regarding implementation or
administration of a particular OATT
arise, a complaint pursuant to section
206 of the FPA is the established
mechanism available to QFs (or any
other generator or transmission
customer) to raise such concerns. It
states that in a complaint proceeding,
the Commission has the ability to
remedy any denial of open access that
results from improper administration of
an OATT, but that ability is not present
under PURPA section 210(m), where the
PO 00000
Frm 00009
Fmt 4701
Sfmt 4700
64349
Commission’s only authority is to reject
an application for termination of the
mandatory purchase requirement.
51. EEI argues against the QFs’ claim
that the Commission has made the
presumption of nondiscriminatory
access under an OATT essentially
irrebuttable. It states that as the NOPR
provides, QFs or any other party will be
afforded the opportunity to provide
‘‘specific and credible evidence that the
QF does not have nondiscriminatory
access to wholesale markets.’’
c. Commission Determination
52. Under section 210(m)(1), the
Commission must find that the QF has
‘‘nondiscriminatory access’’ to the
wholesale markets described in section
210(m)(1)(A), (B), or (C) in order to
terminate the requirement that an
electric utility enter into a new contract
or obligation to purchase electric energy
from a QF. The Commission proposed
in the NOPR that there be a rebuttable
presumption that a utility provides the
nondiscriminatory access required in
section 210(m)(1) if it has an open
access transmission tariff in compliance
with our pro forma OATT (or a
Commission-approved reciprocity
tariff). However, the Commission also
proposed that QFs or any other affected
party should be allowed to rebut that
presumption, for example, by providing
specific and credible evidence that the
QF does not have nondiscriminatory
access to wholesale markets.
53. The Commission reaffirms the
determination in the NOPR that only
issues not related to the provision of
open access transmission under the
OATT may be raised to rebut the
nondiscriminatory access presumption.
We disagree with arguments of ELCON
and Occidental that a QF should be able
to litigate open access implementation
issues in the context of 90-day QF
applications or that, as Occidental
claims, use of complaint proceedings to
address OATT implementation is
inconsistent with the language of the
statute. We also reject arguments that,
because the Commission issued a NOPR
to reform the OATT, that we can no
longer adopt a presumption that a
Commission-approved OATT meets the
requirements of section 210(m)
regarding nondiscriminatory
transmission access.30 As we have
30 In this regard we note that the rulemaking to
reform the OATT is intended to remedy the
‘‘opportunity’’ for undue discrimination; the
Commission did not base its institution of the
rulemaking in Docket No. RM05–25–000 on any
finding that the OATT allows actual discrimination.
To the extent that ELCON argues that, through the
NOPR process, the Commission has recognized ‘‘the
E:\FR\FM\01NOR2.SGM
Continued
01NOR2
64350
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
found in market-based rate proceedings
and other contexts, a transmission
owner that has an OATT on file has met
the obligation set forth in Order No. 888
to provide nondiscriminatory
transmission access. Until we issue a
Final Rule in RM05–25–000 that
modifies Order No. 888, no more is
required. Further, the FPA provides
specific mechanisms, complaints under
FPA section 206 or 306, to address
allegations that a particular utility is not
properly administering the OATT. We
take very seriously allegations that a
transmission owner is violating its
OATT, but there are established
statutory procedures for addressing such
allegations. PURPA section 210(m) does
not change this statutory framework.31
54. As to PJM’s argument that a filed
Order No. 888 OATT is not enough to
establish a presumption of
nondiscriminatory access to the grid
with respect to markets in
subparagraphs (B) and (C) of section
210(m)(1), we find PJM to have
misinterpreted the NOPR. Affected
parties under subparagraphs (B) and (C)
have the same opportunity to rebut the
presumption of nondiscriminatory
access as parties affected under
subsection (A). We note that, in general,
the evidentiary showings for relief from
the requirement that an electric utility
enter into a new obligation to purchase
electric energy from a QF in section
210(m)(1)(B) are higher than the
evidentiary showings in section
210(m)(1)(A), and the evidentiary
showings in section 210(m)(1)(C) are
higher than the evidentiary showings
required in section 210(m)(1)(B).
55. Comments discussed above that
are raised in the context of open access
service but also touch upon concerns
with market rules and or operational
issues, for example, are addressed
further below.
3. Other Market Access Issues Under
Section 210(m)(1)
sroberts on PROD1PC70 with RULES
56. The Commission explained in the
NOPR, and has confirmed in this rule,
that the OATT adopted in Order No.
continuation of patterns of abuse,’’ ELCON
mischaracterizes the basis of the OATT rulemaking.
31 In fact, PURPA section 210(m) provides a
compressed 90-day time frame in which the
Commission, after notice and opportunity for
comment, must act on applications. This provides
a clear indication that Congress did not intend
hearing or lengthy proceedings in order to make a
determination of whether the electric utility must
be relieved of the mandatory purchase requirement.
A QF may, of course, file a complaint with the
Commission at any time, including a separate
complaint in conjunction with its comments on an
electric utility’s application for relief from the
mandatory purchase requirement.
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
888,32 and interconnection rules,
adopted in Order Nos. 2003 33 and
2006,34 are designed to eliminate undue
discrimination in the provision of
transmission and interconnection
services. However, in the NOPR the
Commission recognized that small QFs
may be in a unique situation with
respect to nondiscriminatory access
because they interconnect with the
interconnected utility at a distribution
level.35 In the NOPR, the Commission
sought comment on whether the
utilities’ purchase obligation should be
retained for small renewable projects.
The Commission also sought comment
on whether there may be other
categories of QFs that lack
nondiscriminatory access to RTO/ISO
short-term or long-term wholesale
markets for which the Commission
should retain the utilities’ purchase
obligation. With respect to whether the
purchase obligation should be retained
for small renewable projects, the
Commission sought comments on how
to define ‘‘small,’’ e.g., 5 MWs or below,
20 MWs or below.36
57. Commenters from the QF industry
essentially argue that certain categories
of QFs should be ‘‘exempt’’ from section
210(m)(1) because these QFs lack
nondiscriminatory access to the markets
described in section 210(m)(1)(A), (B),
or (C). In general, they argue that QFs
lack nondiscriminatory access if: (1)
They are of a small size, (2) they have
certain operational characteristics such
that the QF cannot access a particular
market, (3) they are interconnected at
the distribution level, or (4) a
combination of the above. As discussed
32 Promoting Wholesale Competition Through
Open Access Non-discriminatory Transmission
Services by Public Utilities and Recovery of
Stranded Costs by Public Utilities and Transmitting
Utilities, Order No. 888, 61 FR 21540 (1996), FERC
Stats. & Regs. ¶ 31,036 (1996), Order No. 888–A,
FERC Stats. & Regs. ¶ 31,048 (1997), order on reh’g,
Order No. 888–B, 81 FERC ¶ 61,248 (1997), order
on reh’g, Order No. 888–C, 82 FERC ¶ 61,046
(1998), aff’d in relevant part sub nom. Transmission
Access Policy Study Group v. FERC, 225 F.3d 667
(D.C. Cir. 2000), aff’d sub nom. New York v. FERC,
535 U.S. 1 (2002).
33 Standardization of Generator Interconnection
Agreements and Procedures, Order No. 2003, 68 FR
49845 (Aug. 19, 2003), FERC Stats. & Regs. ¶ 31,146
(2003), order on reh’g, Order No. 2003–A, 69 FR
15932 (Mar. 26, 2004), FERC Stats. & Regs. ¶ 31,160
(2004), order on reh’g, Order No. 2003–B, 70 FR265
(Jan. 4, 2005), FERC Stats. & Regs. ¶ 31,171 (2004),
order on reh’g, Order No. 2003–C, 70 FR 37661
(June 30, 2005), FERC Stats. & Regs. ¶ 31,190 (2005).
34 Standardization of Small Generator
Interconnection Agreements and Procedures, Order
No. 2006, 70 Fed. Reg. 34,100 (Jun. 13, 2005), FERC
Stats. & Regs. ¶ 31,180 at 31,406–31,551 (2005),
order on reh’g, Order No. 2006–A, 70 Fed. Reg.
71,760 (Nov. 30, 2005), FERC Stats. & Regs. ¶ 31,196
(2005).
35 NOPR at P 20.
36 Id.
PO 00000
Frm 00010
Fmt 4701
Sfmt 4700
further below, the comments we have
received do not provide a justification
for categorically exempting any category
of QFs from any future orders which
may terminate a utility’s requirement to
enter into new contracts or obligations
to purchase from QFs. No class of QFs
has been shown to uniformly lack
nondiscriminatory access based on a
single factor. We also agree with
commenters, such as AEP, Entergy,
Missouri River, Montana-Dakota, PJM
Transmission Owners, PPL, Progress
Energy and Xcel, that section 210(m)
does not give the Commission authority
to categorically exempt certain QFs from
statutory provisions. However, we
believe the record does support creating
a rebuttable presumption that certain
QFs may not have nondiscriminatory
access to markets because of their small
size.
a. Small Size
i. Comments
58. CIBO argue that smaller QFs
typically are less able to predict their
generation and power export/import
levels due to unpredictable demand
fluctuations. They state that while larger
facilities may face similar unpredictable
situations, they may have more latitude
in selecting and operating alternative
equipment and that latitude could allow
for a higher level of power flow control.
CIBO also argue that because of a QF’s
small size, the transmission charges
involved in accessing the three markets
described in section 210(m)(1),
including locational marginal pricing
and transition charges, can place a small
QF in a position where it cannot reach
those markets. Also, CIBO, AWEA, and
Granite State argue that certain markets
may require membership fees in order to
participate in the market. CIBO state
that a sufficiently large QF may face
similar problems, but it presumably has
greater resources to address those
problems, and sufficient economic
interest in the success of the generator
to bring those resources to bear on the
problem. On the other hand, they argue
that a small QF is more likely to lack the
resources and to have less economic
incentive to apply those resources to the
problem, especially in light of the
staying power of its competition.
59. Granite State adds that most small
QF hydroelectric plants, for example,
are located in areas which do not
provide direct access to RTO/ISOs. It
states that small QF hydroelectric
projects are generally located in areas
remote from high voltage power lines,
their locations being determined by the
site of existing dams. Granite State
states that the amount of generation
E:\FR\FM\01NOR2.SGM
01NOR2
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
sroberts on PROD1PC70 with RULES
from a small QF hydroelectric plant is
dependent on the amount of water
flowing through the turbines on a
particular hour. It states that they have
limited resources and the staff
employed by these projects are generally
engaged in the day to day operation of
the projects. Granite State states that
developers of small hydroelectric plants
do not have the software, computer and
monitoring equipment to integrate to
RTO/ISO operations and, in many
regions, would not even be eligible to
bid their energy into these markets
because they are too small for the
applicable minimum block.
60. CIBO also argue that a small QF
exemption, such as a MW limit, would
provide an administrative advantage
because it would be less likely to
involve the QF and the Commission in
additional proceedings and thus, avoid
potential additional burden on parties
and the Commission.
61. Although not arguing for a size
exemption, EEI states that it would be
appropriate to allow affected small QFs
in all markets, including ‘‘Day 2’’
organized markets, to have an
opportunity to demonstrate that they
effectively lack nondiscriminatory
access to those markets, despite their
legal right to such access under an
OATT.
62. EEI suggests that that the
Commission could consider evidence of
the following limited circumstances as a
basis for finding that a small QF
effectively may not have
nondiscriminatory access to markets.
One, where a small industrial
cogenerator 37 (with a nameplate
capacity of 5 MW or less) has: (a) highly
variable thermal and electrical demand
on a daily basis; (b) highly variable and
unpredictable wholesale sales on a daily
basis; and (c) no access to a mechanism
to schedule transmission service or
make sales in advance on a consistent
basis, either because of the variability of
its electricity production or because of
market rules that prevent the QF from
scheduling transmission service or
participating in organized markets. Two,
where a QF is very small,38 and cannot
aggregate its electricity production with
other nearby facilities, and can
demonstrate that it is not directly or
indirectly modeled in the energy
management or market information
system, cannot directly sell any product
or service into the RTO or ISO market
and appears to the RTO or ISO only as
a reduction to load.
63. AEP, Entergy, FirstEnergy,
Missouri River and Montana-Dakota,
PJM Transmission Owners, PPL,
Progress Energy and Xcel argue that no
exemption should be allowed because:
(1) All QFs are eligible to receive
transmission service under the pro
forma OATT, regardless of the level at
which they are interconnected; (2)
Congress has not given the Commission
the authority to exempt QFs from the
provisions of section 210(m); and (3) an
exemption could lead to uneconomic
QF ‘‘gaming’’ strategies through
dividing generating facilities so that
they are under the size limit for the
mandatory purchase obligation to kickin.
64. Other Commenters argue that no
exemption should be granted in certain
RTO/ISOs. PJM Transmission Owners
and PPL Electric argue that PJM has
developed special procedures to ensure
that small generators, even those under
20 MW, have comparable access to
energy and capacity markets.
Specifically, the PJM Transmission
Owners state that Subpart G of PJM’s
tariff is dedicated to small generators to
provide clear and concise rules for these
power producers to ensure that they
have comparable access to participate in
energy and capacity markets allowing
load to rely upon such resources. PJM
notes that since 1999, PJM has
successfully interconnected numerous
small projects. These include 44
projects rated between 5–20 MW and 28
rated at 5MW or less. It further states
that the majority of these projects are
sponsored by developers unaffiliated
with transmission or distribution system
owners. Montana-Dakota adds that QFs
have nondiscriminatory access to the
Midwest ISO markets regardless of size.
65. With regard to the Midwest ISO,
several commenters such as Missouri
37 EEI does not expect that the Commission would
extend the opportunity to demonstrate lack of
access under this proposal to wind generators. EEI
states that while electricity production from wind
power is variable, wind generation is predictable in
its variability, and the Commission has
accommodated this variability through
interconnection rules and other policies. EEI asserts
that wind generators differ as well from small
industrial cogenerators, whose primary purpose, in
accordance with PURPA, is not intended to be the
production of electricity, while wind generators are
exclusively electricity producers.
38 EEI states that the size of a ‘‘very small’’ QF for
purposes of its proposed exception to the
termination of the mandatory purchase obligation is
likely to vary among RTO/ISOs, based on factors
such as operational requirements of the particular
RTO, any threshold level for transactions that may
be required in an RTO, any minimum size
requirements for participation in the RTO market,
or other factors specific to the RTO/ISO market
involved. For example, EEI notes a ‘‘very small’’ QF
for the NYISO market could be a QF less than 1 MW
that has not been able to aggregate supply in order
to participate at the 1 MW minimum transaction
level established in the NYISO tariff. See NYISO
FERC Electric Tariff, Original Volume No. 2
(‘‘Services Tariff’’), Sections 4.1.4, 4.2.2(c)(1) and
5.12.
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
PO 00000
Frm 00011
Fmt 4701
Sfmt 4700
64351
River Energy and Montana-Dakota argue
that no exemption is necessary for small
QFs because small renewable projects
have become very marketable given the
current regulatory and political
environment of increasing renewable
portfolio standards.
66. As to NYISO and ISO–NE,
National Grid states that they have
generation interconnection policies in
place for small as well as large
generators. National Grid states that
there are no minimum size requirements
for a generator to join NEPOOL, and
while the NYISO currently will not
accept bids in the markets it administers
from generators with 1 MW or less of
capacity, that limitation is not
immutable. It states that subject to that
limitation, the market rules in ISO–NE
and the NYISO allow settlement for all
sizes of generators. NSTAR adds that
there are sufficient privileges afforded to
small renewable resources in NEPOOL,
and regulatory requirements and
monetary incentives in the New
England states to sustain small
renewable projects. The New York
Transmission Owners argue that in
NYISO, all facilities, including those
with a capacity under 20 MW, have the
same equal and nondiscriminatory
access to all NYISO markets and all
services offered by the NYISO under its
tariffs. NYISO does not take a position
on whether there should be an
exemption. It states, however, that any
unit, regardless of ownership or QF
status, that has a generating capacity of
two MWs or higher can bid directly into
the NYISO markets.
67. As to what QF size should be
considered ‘‘small,’’ the proposals
varied significantly from 1 MW to 80
MWs.39 However, in general, most of the
QF industry supports a 20 MW
exemption, utilities generally support
no exemption, and some entities are
willing to support an exemption for very
small QFs (i.e., smaller than 1 MW) in
specific service territories. Granite State
and American Energy argue that a 20
MW demarcation strikes a reasonable
balance between small and large
projects. The nameplate capacity of
many renewable technologies like wind
and hydro do not accurately reflect the
annual generating capacity of such units
due to the lower capacity factor dictated
by the variability in available river flow
and wind. Granite State states that the
20 MW limitation would provide the
39 Industrial Boilers proposed 80 MW, UAE
proposed 30 MW, AWEA and ELCON proposed 20,
and EEI proposed 1 MW for cogeneration and 5 MW
for small production.
E:\FR\FM\01NOR2.SGM
01NOR2
sroberts on PROD1PC70 with RULES
64352
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
needed flexibility to ensure that small
projects are protected.
68. In addition, ELCON, Granite State,
AWEA, and Landfill Gas state that the
20 MW demarcation is consistent with:
(1) Order No. 671; and (2) the
Standardization for Small Generation
Interconnection Agreements and
Procedures, Order Nos. 2006 and 2006–
A, which recognizes that small
generators, i.e., 20 MW or below, should
have different standards than large
generators. AWEA also states that
utilizing a 20 MW threshold for ‘‘small’’
generators will also avoid
inconsistencies with state
interconnection procedures which are
designed around the current 20 MW
threshold for ‘‘small’’ generators.
Further, AWEA states that a 20 MW
threshold will help prevent RTO/ISO
market-participation costs from
discouraging market participation and
development of small generators.
69. CIBO argue that ‘‘small’’ should be
defined as 80 MW or less. They state
that Congress already adopted 80 MW to
reflect what is small in PURPA, which
used 80 MW to treat as QFs small power
production facilities with a net capacity
of 80 MW or less that produce
electricity from biomass, waste,
renewable resources, geothermal
resources, or any combination of these
sources. In addition, CIBO argue that an
80 MW bright line would also resolve a
number of the operational concerns
faced by QFs. They argue that a QF of
greater than 80 MW is more likely to
interconnect to the grid at higher
voltages, and less likely to interconnect
at distribution voltages, thereby
addressing a number of the transmission
access issues, including in particular the
distribution facilities charges that lower
voltage QFs will face. Regardless of the
interconnection voltage, CIBO argue that
a QF of greater than 80 MW will more
likely have an economic interest
sufficient to seek to participate in the
market and the resources to participate.
Further, CIBO argue that a QF of greater
than 80 MW will probably have more
latitude in selecting and operating
alternative equipment and that latitude
can allow for a higher level of power
flow control. Finally, they argue that an
80 MW bright line will not undercut
what they claim is the Commission’s
goal of limiting PURPA abuse and
would ensure that units benefiting from
the mandatory purchase and sale
obligations will in fact be the QFs that
Congress has wanted to protect.
70. Granite State and USCHPA are
open to a hybrid definition of ‘‘small’’
QF whereby small QFs with a
nameplate capacity of 5 MW or less
would automatically retain the right to
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
make sales to their utilities at avoided
cost rates. Those QFs with capacities of
more than 5 MW and less than 20 MW
would have the benefit of a rebuttable
presumption in favor of retaining the
utility’s mandatory purchase obligation.
UAE simply states that it believes that
a small QF should be defined as less
than 30 MW without elaboration.
71. PJM agrees that EEI’s size limit
exception (1 or 5 MWs) may be
appropriate as applied to very small
entities that do not aggregate their
generation. PJM states, however, that in
the PJM market resources rated below
very small levels are permitted to
aggregate for the purpose of submitting
offers. Therefore, PJM concludes that a
facility less than 100 kW may meet a
‘‘unique circumstances’’ standard. PJM
states that it does not impose a size limit
on modeling. PJM states that it requires
that new resources rated higher than 10
MW, whether in the PJM market or
behind the meter, as well as any new
capacity resource intending to set realtime locational marginal pricing (LMP),
must be explicitly modeled in the PJM
Energy Management System network
model. As to access, PJM states that the
PJM market has a 100 kW minimum for
offers to buy and sell in the Capacity
and Day-Ahead Markets and 1 kW for
offers in the Real-Time Market.
ii. Commission Determination
72. We believe that the record
supports creating a rebuttable
presumption 40 that certain QFs may not
have nondiscriminatory access to
markets because of their small size. In
addition, we find that a reasonable and
administratively workable definition of
‘‘small’’ is 20 MW. As a result, the Final
Rule creates a rebuttable presumption
that the requirement that an electric
utility enter into new contracts or
obligations to purchase from a QF
remains in effect, in all markets, for QFs
sized 20 MW net capacity 41 or
smaller.42 This rebuttable presumption
will apply to applications in markets
40 As we noted above in P 57, no class of QFs has
been shown to uniformly lack nondiscriminatory
access based on a single factor. Thus, we are not
making a finding here but are establishing a
rebuttable presumption.
41 A QF, when it seeks certification, states what
size it is. The size it is required to state is its ‘‘net
capacity’’ which is its gross capacity, less station
power. In the case of Commission-certified
facilities, the Commission certifies the QF at its net
capacity; self-certified facilities self-certify at net
capacity. The Commission has been consistent over
the years in requiring QFs to state their net capacity
in the Form 556 which is the basis of both
applications for Commission certification, and
notices of self-certification. A QF’s Commission
certified (or self-certified) net capacity would
determine whether the QF qualifies for the ‘‘small
size’’ rebuttable presumption in this Final Rule.
42 Herein referred to as ‘‘small QF.’’
PO 00000
Frm 00012
Fmt 4701
Sfmt 4700
described in section 210(m)(A), (B), or
(C). To rebut this presumption, the filing
electric utility will be required in its
application to demonstrate, with regard
to each small QF that it, in fact, has
nondiscriminatory access to the market.
73. The Commission finds persuasive
commenters’ arguments that some QFs
may not have nondiscriminatory access
to one of the three markets described in
section 210(m)(1)(A), (B), or (C) because
of their small size. There was agreement
among commenters representing both
QFs and utilities that small size could
affect a QF’s ability to access markets.
To varying degrees, the QF industry,
EEI, and also PJM, recognized that small
QFs may not have nondiscriminatory
access to the three markets described in
section 210(m)(1)(A), (B), or (C). There
was not, however, consensus as to what
constitutes ‘‘small’’ for purposes of
identifying QFs that may not have
nondiscriminatory access to markets.
74. In determining what constitutes
‘‘small’’ for purposes of the rebuttable
presumption, we are not making a
finding that all QFs smaller than a
certain size lack nondiscriminatory
access to markets. Rather, utilities
seeking to terminate the requirement
that they enter into new contracts or
obligations to purchase from small QFs
will be required to rebut the
presumption that QFs sized 20 MW net
capacity or smaller do not have access.
A utility’s demonstration must be filed
as part of its application filed pursuant
to section 292.310 of our regulations.
75. Commenters suggested various
sizes as the demarcation between QFs
that can access markets. CIBO suggested
80 MW as the logical demarcation point,
pointing to the definition of ‘‘small
power production facilities’’ in PURPA.
Granite State, AWEA and Landfill Gas
suggest that the Commission use 20 MW
as the demarcation pointing to the
Commission’s use of 20 MW as being
the demarcation between large and
small generators for interconnection
purposes and for purposes of QF
exemption from sections 205 and 206 of
the FPA.
76. Keeping in mind that we are
creating a rebuttable presumption, and
to include most small QFs that may lack
nondiscriminatory access to markets
within the presumption, we find that
the 20 MW demarcation is reasonable.
As pointed out by commenters, the
Commission used 20 MW in Order No.
671 to exempt QFs that are 20 MW or
smaller from sections 205 and 206 of the
FPA. The Commission also used the 20
MW demarcation for eligibility for the
interconnection rules contained in
Order Nos. 2006 and 2006–A, which
recognize that small generators, i.e., 20
E:\FR\FM\01NOR2.SGM
01NOR2
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
sroberts on PROD1PC70 with RULES
MW or below, should be subject to
different standards than large
generators.43 In adopting this 20 MW
demarcation in this proceeding, we
recognize that no single per-MW
demarcation is perfect. However, we
believe that, in creating a rebuttable
presumption, it is necessary to establish
a clear demarcation and, as indicated,
that 20 MW is appropriate for that
purpose. We are influenced by the fact
that the statute provides a very
compressed 90-day time frame in which
parties may provide the record support
for a determination of whether a utility
must be relieved of the purchase
obligation. The statute does not provide
time for lengthy litigation. Unlike other
provisions of the FPA, which require
notice and an opportunity for ‘‘hearing,’’
section 210(m)(a)(3) provides for notice
and opportunity for ‘‘comment’’ and a
final decision within 90 days of filing.
Thus, it is consistent with the statutory
framework to provide clear
demarcations that will permit the
Commission to make reasoned
determinations within the 90-day
period. After balancing all relevant
considerations, we therefore adopt a
clear demarcation of ‘‘small QF’’ in this
Final Rule.
77. The Commission will not allow
for gaming of this 20 MW rebuttable
presumption. If parties are concerned
that a QF has engaged in such gaming
with regard to the certification or siting
of a particular facility, we encourage
those parties to bring their concerns to
our attention. In any such proceeding,
we will consider all relevant factors,
including, but not limited to,
ownership, proximity of facilities, and
whether facilities share a point of
interconnection. For purposes of
evaluating proximity of facilities with
regard to alleged gaming of this
rebuttable presumption, we will not be
bound by the one-mile standard set
forth in 18 CFR 292.204(a)(2).
78. In order to rebut the 20 MW
presumption, an electric utility will
have the full burden to show that small
QFs have nondiscriminatory access to
the market of which the electric utility
is a member. We will not specify, in this
Final Rule, what evidence would be
sufficient, but note that relevant
evidence may include the extent to
43 Order No. 2006 defined a ‘‘Small Generating
Facility’’ as a device used for the production of
electricity having a capacity of no more than 20
MW. The Commission concluded in Order No. 2006
that general consistency between the Commission’s
interconnection procedures document and
interconnection agreement adopted in that final
rule and those of the states will be helpful to
removing roadblocks to the interconnection of
Small Generating Facilities. See Order No. 2006 at
P 4.
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
which the QF has been participating in
the market or is is owned by, or is an
affiliate of, a entity that has been
participating in the relevant market.
b. Operational Characteristics and
Transmission Constraints
i. Comments
79. Many commenters argue that
dispatchability and intermittent
resource characteristics do not allow
QFs to have nondiscriminatory access to
the markets described in section
210(m)(1)(A), (B), or (C). Several
commenters argue that before the
purchase requirement is lifted the
Commission must consider the unique
generation operational differences of
certain QFs that affect their
nondiscriminatory access to competitive
markets. For example, American Forest
& Paper states that real-time and dayahead, bid-based markets are, in
themselves, inadequate to support
baseload operations of QFs with limited
dispatchability. American Forest &
Paper states that bidding into an hourly
energy market subjects QFs to
unworkable dispatch risks which may
require either: (1) Bidding a price too
low to support fixed cost recovery in
order to ensure dispatch; or (2)
jeopardizing industrial or other
processes required to be primary under
newly enacted section 210(n). Similarly,
CIBO argues that the Commission
should require an analysis of the
operational issues, including, for
example, the voltage level of the
interconnection between the QF and the
grid, and the fact that cogeneration
thermal host limits the ability to
dispatch a QF. It states that the
mandatory purchase obligation should
only be removed if it is demonstrated
that markets are truly accessible to QFs,
taking into consideration QF operational
issues, including size, in some cases
interconnecting at distribution voltage
(with the attendant costs of paying for
distribution adders), the different
efficiency and operational constraints of
industrial boilers, the different
efficiency and operational constraints
caused by industrial cogeneration hosts,
and the impact of transmission charges,
including locational marginal pricing
and transition charges, on economically
marginal QF generation.
80. Florida Industrial argues that the
Commission should specifically retain
the utility obligations to purchase for
that category of ‘‘process-following’’
QFs that rely on a reject waste heat from
an associated industrial manufacturing
process for the production of electricity
and thermal energy—and where the
amount of reject waste heat varies with
PO 00000
Frm 00013
Fmt 4701
Sfmt 4700
64353
manufacturing production rates—such
as in phosphate fertilizer manufacturing
operations. It states that such processfollowing QFs generate at high
efficiencies and consume little or no
fossil fuels. However, because the rate of
electric energy production varies
(‘‘follows’’) in direct proportion to the
underlying manufacturing processes,
such QFs would find themselves at a
significant and untenable
disadvantage—especially with regard to
deviation from schedule and energy
imbalances, as well as other associated
factors—if PURPA’s mandatory
purchase obligation were lifted in
Florida.
81. In addition to EEI’s comments
regarding a QF’s size as a contributor to
a lack of nondiscriminatory access, EEI
states that it would also be appropriate
to allow affected QFs in all markets,
including ‘‘Day 2’’ organized markets, to
have an opportunity to demonstrate that
they effectively lack nondiscriminatory
access to those markets, despite their
legal right to such access under an
OATT where an existing QF 44 is located
in an area in which persistent
transmission capacity constraints
effectively cause the QF to have neither
physical 45 nor financial access 46 to
markets outside the persistently
congested area and there is not a
sufficient opportunity to relieve the
transmission constraint or to sell its
output or capacity within the area on a
short-term and long-term basis because
of the transmission constraint.
44 An existing QF is one that is in existence as
of the date the mandatory purchase obligation is
terminated.
45 EEI suggests that for purposes of this exception,
a QF is prevented from having ‘‘physical access’’
outside its congested area when the QF is located
in a ‘‘generation pocket.’’ EEI believes this means
that during annual system peak conditions, the QF
is unable (because of transmission congestion) to
deliver the power it generates that is not consumed
by local loads to the remainder of the relevant ISO’s
or RTO’s control area, or to other areas if the QF
is not located in an ISO or RTO control area. EEI
concludes the geographic area that should be
evaluated as a potential ‘‘generation pocket’’ is the
area containing the QF and other generators that
sufficiently contribute to the congestion on the
transmission line, as defined by the ISO or RTO in
its applicable resource adequacy deliverability
analysis, if the QF is located in an ISO or RTO
control area. See, e.g., CAISO Preliminary
Deliverability Baseline Analysis Study Report, May
3, 2005, Appendix I. In addition, a given QF’s lack
of physical access should be subject to annual
review in order to determine whether the
mandatory purchase obligation should continue.
46 EEI states that existing ‘‘Day 2’’ organized
markets rely on LMP and financial transmission
rights rather than physical transmission rights.
Where a financial right exists, a generator enjoys
access to markets, regardless of whether a physical
right exists.
E:\FR\FM\01NOR2.SGM
01NOR2
sroberts on PROD1PC70 with RULES
64354
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
ii. Commission Determination
82. While we agree with commenters
that there may be factors unique to a QF
that prevent its nondiscriminatory
access to one of the three markets
described in section 210(m)(1), we do
not believe that any factor, other than
small size, has been shown in this
rulemaking to be an appropriate basis
on which the Commission can establish
a rebuttable presumption of lack of
nondiscriminatory access. Unlike the
size limitation discussed above,
operational characteristics and
transmission limitations are not
susceptible to a clear demarcation for
purposes of establishing a rebuttable
presumption. We do believe, however,
that by establishing a rebuttable
presumption based on size, we in effect
capture some of the operational issues
expressed by commenters. Accordingly,
the final rule does not establish a
rebuttable presumption specific to
operational characteristics.
83. However, with respect to the
rebuttable presumption that QFs larger
than 20 MW net capacity in the four
listed RTO/ISOs do have access to
markets, QFs larger than 20 MW may
seek to rebut this presumption in their
response to applications pursuant to
section 210(m)(3) of PURPA and
§ 292.310 of our regulations. The
comments suggest that a QF may rebut
the presumption by showing, for
example, one or more of the following
factors. Although we do not make any
final determinations herein as to
whether any such factor, standing alone,
is sufficient to rebut the presumption of
market access, we do agree with the
commenters that these factors are
relevant to the question of whether the
purchase obligation should be
terminated and, upon an appropriate
evidentiary showing, may be sufficient
to rebut that presumption:
(A) The QF has certain operational
characteristics that effectively prevent
the QF’s participation in a market. Such
operational characteristics might
include, but are not limited to: (a)
Highly variable thermal and electrical
demand (from the QF host) on a daily
basis, such that the QF cannot
participate in a market; or (b) highly
variable and unpredictable wholesale
sales on a daily basis.
(B) The QF has no access to a
mechanism to schedule transmission
service or make sales in advance on a
consistent basis, either because of the
variability of the QF’s electric energy
production or because of market rules
that prevent the QF from scheduling
transmission service or participating in
organized markets. Such operational
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
characteristics might include, but are
not limited to, dispatchability or some
other characteristic.
(C) A QF lacks access to markets due
to transmission constraints. A QF may
show that it is located in an area where
persistent transmission constraints in
effect cause the QF not to have access
to markets outside a persistently
congested area to sell the QF output or
capacity.
84. In evaluating transmission
constraints, the Commission will
consider, on a case-by-case basis, among
other things, the opportunity for QFs, on
a nondiscriminatory basis, to obtain
transmission upgrades to relieve
constraints and whether the structure of
the relevant market provides for the
opportunity for the QF to sell
notwithstanding the constraint.
c. Distribution Level
i. Comments
85. AWEA and others point out that
the problems for QFs connecting at the
distribution level include: (1) Wheeling
charges over distribution to reach RTO/
ISO markets; (2) costs associated with
access to the RTO/ISO market; and (3)
other costs and procedural barriers that
can be unilaterally imposed by the
distribution utility to deny or hinder
access to the market.
86. Many commenters including
AWEA, argue that QFs are typically
located in areas which do not provide
direct access to competitive wholesale
markets, such as RTO/ISO markets.
AWEA states that, instead such facilities
are forced to connect to the distribution
market operated by competing utilities.
AWEA states that utilities and state
commissions—not FERC or RTOs—
control who can interconnect at the
distribution level and charge costs that
are prohibitive for many QFs. AWEA
states that because QFs cannot reach the
RTO/ISO without incurring significant
costs to interconnect at the distribution
level, access is typically uneconomic for
QFs. AWEA states that accordingly,
these QFs have no opportunity to sell
power in a competitive market. AWEA
states that there is no way to ensure fair
and nondiscriminatory treatment to QFs
forced to interconnect with a competing
utility. NPRA states that a competitive
market in which the utility baseloads its
own generation and seeks ‘‘competitive’’
solutions for peaking power may not
fairly accommodate the sale of capacity
and energy from non-dispatchable QF
generating facilities.
87. Other commenters disagree with
the argument that the Commission
should retain the mandatory purchase
obligation for QFs interconnected at the
PO 00000
Frm 00014
Fmt 4701
Sfmt 4700
distribution level. They argue that
whether a QF interconnects at the
distribution or transmission level is
irrelevant because it has
nondiscriminatory access to competitive
markets through open access
transmission and interconnection
services. Central Vermont and Southern
California Edison Company (SCE) state
that under Order Nos. 2003–C and
2006–A all of the utility’s facilities,
including its distribution facilities, that
are used to implement a sale for resale
or to transmit electricity in interstate
commerce are subject to the
nondiscriminatory requirements of the
utility’s OATT. In addition, EEI and SCE
state that QFs may take advantage of the
interconnection provisions of section
210 of the FPA, under which they can
obtain services at Commissiondetermined rates, terms and conditions.
Also, EEI points out that section 1.11 of
the pro forma OATT makes clear that a
generator interconnected at the
distribution level is entitled to request
transmission service under the OATT.
88. PJM states that regardless of
whether a resource interconnects at the
transmission or distribution level, it is
entitled in PJM to obtain
interconnection service and open-access
delivery service. SCE argues that if the
Commission does not adopt a generic
finding that generators have open access
on a nondiscriminatory basis to the
local distribution facilities of all
Commission-regulated utilities, there is
support for such a finding as to the State
of California, given the existence of
Wholesale Distribution Access Tariffs
ii. Commission Determination
89. The connection of a QF to
distribution-level facilities can present
two different issues: (i) Whether the
utility owning the distribution facilities
will permit the QF to have access to
markets and (ii) if that access is granted,
whether any associated distribution
charges are sufficient to negate that
access for purposes of applying section
210(m). As to the first question, we
agree that a denial of actual access to
distribution facilities for purposes of
selling power into the wholesale market
would constitute sufficient evidence to
find that section 210(m) has not been
satisfied (and hence to retain the
mandatory purchase obligation). We
recognize that open access transmission
service, adopted in Order No. 888,47 and
interconnection rules, adopted in Order
Nos. 2003 48 and 2006,49 are designed to
eliminate undue discrimination in the
47 Supra
note 32.
note 33.
49 Supra note 34.
48 Supra
E:\FR\FM\01NOR2.SGM
01NOR2
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
sroberts on PROD1PC70 with RULES
provision of transmission and
interconnection services but do not
address certain distribution level issues.
Indeed, the Commission does not have
jurisdiction over all distribution level
facilities,50 and thus QFs interconnected
to those facilities face access issues that
are different from the access issues that
are faced by QFs interconnected directly
to RTO/ISO facilities.51 Although we do
not believe the record supports any
generic findings that QFs
interconnected at a distribution level do
not have non-discriminatory access to
markets, a QF may be able to show,
based on its specific circumstances, that
it does not have such access to markets
as a result of not being able to obtain
non-discriminatory access to
distribution facilities. Thus, for
purposes of the rebuttable presumption
that QFs above 20 MWs in the four
ISOs/RTOs (ISO–NE, NYISO, PJM and
Midwest ISO) have non-discriminatory
access to markets, QFs may be able to
rebut the presumption by, e.g.,
demonstrating a denial of actual access
to distribution facilities for the purposes
of selling power to the wholesale
market. Moreover, we note that, for
small QFs (many of whom may be
connected at distribution level), the
utility must also overcome the
rebuttable presumption that such small
QFs do not have sufficient access to
markets to satisfy section 210(m).
90. With respect to the second issue,
we find that the imposition of a charge
for access to the distribution system
does not mean that the QF does not
have ‘‘access’’ to competitive markets. A
QF wishing to access competitive
markets is expected to pay the
reasonable charges, whether for
transmission or distribution facilities,
that are associated with such action.
There is nothing in section 210(m) that
50 See, e.g., PJM Interconnection, LLC, 114 FERC
¶ 61,191, order on reh’g, 116 FERC ¶ 61,102 (2006).
51 The Small Generator Interconnection
Procedures (SGIP) and the Small Generator
Interconnection Agreement (SGIA) outlined in
Orders Nos. 2006 and 2006–A, include separate
definitions for ‘‘Transmission System’’ and
‘‘Distribution System’’ to account for the distinct
engineering and cost allocation implications of an
interconnection with a Distribution System. Order
No. 2006 states that use of the term ‘‘Distribution
System’’ has nothing to do with whether the facility
is under this Commission’s jurisdiction; some
‘‘distribution’’ facilities are under our jurisdiction
and others are ‘‘local distribution facilities’’ subject
to state jurisdiction. Further Order No. 2006 applies
only to interconnections to facilities that are already
subject to a jurisdictional OATT at the time the
interconnection request is made and that will be
used for purposes of jurisdictional wholesale sales.
Order No. 2006 explains that because of this limited
applicability, and because the majority of small
generators interconnect with facilities that are not
subject to an OATT, Order No. 2006 will not apply
to most small generator interconnections. See Order
No. 2006 at P 6, 7 and 8.
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
suggests otherwise. Thus, the
requirement to pay an interconnection
charge, transmission charge, or
distribution charge, in and of itself, is
not an indication that a QF does not
have nondiscriminatory access to a
market.
4. Burden of Proof
a. NOPR
91. In the NOPR, the Commission
proposed to make generic findings that
certain markets satisfy the conditions of
section 210(m)(1)(A). In addition, the
Commission proposed to create a
rebuttable presumption that the Order
No. 888 OATT provides
nondiscriminatory access to markets.
b. Comments
92. American Chemistry Council,
Caithness, American Forest & Paper,
CCC, CIBO, Occidental, PIOs, Dow, and
ELCON argue that the burden of
establishing that the section 210(m)
criteria are met is placed squarely on the
electric utility seeking relief from the
must purchase requirement. Several of
these commenters argue that the
Commission erred in making generic
determinations for section 210(m)(1)(A).
All of these commenters argue that
section 210(m)(3) shows Congressional
intent that electric utilities can be
relieved only after careful consideration
on a utility-specific service territory
basis—not on a broader region-wide
basis. ELCON and many others claim
that the Commission has a statutory
obligation to make facility-specific
determinations that nondiscriminatory
access to long-term markets truly exists.
Industrial Energy Consumers add that
the statute requires that the utility make
a specific showing, supported by
evidence, about the existence of and
nondiscriminatory access to long-term
markets. ELCON and others contend
that the statute does not provide the
Commission with the discretion or legal
authority to abandon this QF-level
analysis in favor of a generic analysis.
Granite State is concerned that a generic
finding will adversely affect small
developers because they would not
receive actual notice of the elimination
of the mandatory purchase requirement.
93. The CCC argues that section
210(m) requires utilities to make
principal showings demonstrating that
market conditions justifying removal of
the mandatory purchase requirement
exist. It states that QFs then have the
ability to rebut the utilities’
presentations. The CCC states that the
NOPR turns this scheme on its head by
making initial, unsupported conclusions
regarding the existence of market
PO 00000
Frm 00015
Fmt 4701
Sfmt 4700
64355
opportunities for QFs without any
utility submission or evidence, and then
shifting the burden to QFs to rebut the
NOPR’s conclusions.
94. CIBO argue that placing the
burden on industrial QFs is arbitrary,
because industrial QFs generally lack
the resources and Commission
regulatory expertise to participate in
litigation before the Commission. In
addition, it argues that such a shifting
of the burden of proof is contrary to 5
U.S.C. 556(d) and contrary to the
structure of section 1253, which
envisions that the Commission will act
on applications submitted by the utility
and supported by a demonstration made
by the utility. Finally, the Council
argues that it creates a disincentive for
its members and other industrial QFs,
who generally lack the resources and
regulatory expertise to bear that burden.
95. Occidental adds that section
210(m)(3) provides the single
mechanism by which an electric utility
can eliminate its mandatory purchase
requirement. It argues that the statute
does not permit the Commission to
relieve the applicants’ burden to
demonstrate the ‘‘factual basis’’ of their
requested relief by rulemaking.
96. EEI states in its reply comments
that it strongly believes the four RTO/
ISOs provide nondiscriminatory access
to all generators, operate competitive
wholesale markets meeting the criteria
in section 210(m)(1)(A)(i), and afford
opportunities for long-term sales of
capacity and energy within the meaning
of section 210(m)(1)(A)(ii). EEI states
that the Commission is correct to make
generic findings regarding these
markets. EEI states that to do otherwise
would compel the Commission to relitigate the same issues time and time
again to reach the identical
determination.
97. EEI states that only QFs will have
the evidence necessary to demonstrate
that they, in fact, lack access and
thereby to rebut the presumption and
that the Commission is not reversing the
burden of proof, but placing it where it
belongs. EEI states that the opportunity
to rebut this presumption generally will
be available to QFs in their comments
to applications for relief filed pursuant
to section 210(m)(3).
c. Commission Determination
98. Commenters, in response to the
NOPR’s proposal to find that the
markets of the four RTO/ISOs satisfy
section 210(m)(1)(A), raise essentially
the same issue from two different
perspectives: (1) The Commission’s
authority to make generic findings; and
(2) section 210(m)(3) places the burden
E:\FR\FM\01NOR2.SGM
01NOR2
sroberts on PROD1PC70 with RULES
64356
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
of proof on the electric utility, not the
QF.
99. We have previously discussed the
rebuttable presumptions being adopted
herein—in favor of electric utilities with
respect to ‘‘large’’ QFs in the four
organized markets and in favor of
‘‘small’’ QFs in all markets. Several
parties challenge our ability to make any
such determinations on a generic basis
in this rulemaking. We disagree. First,
we have broad discretion to adopt
generic policy or make generic findings
through either rulemaking or
adjudication.52 We believe doing so
through this rulemaking provides all
affected entities—including both
utilities and QFs—a reasonable
opportunity to be heard on common
issues that arise in various market
structures and for classes of QFs. It
makes little sense to adopt such generic
determinations in the first case to
present them, thereby effectively
denying the vast majority of utilities and
QFs the ability to comment on those
policies or findings before they are
adopted for the first time. To some
extent, generic findings about certain
aspects of ‘‘Day 2’’ markets are
inevitable, either by rulemaking or in
the first utility specific filing in each
‘‘Day 2’’ market. Making generic
findings by rulemaking provides
affected QFs better notice.
100. Second, we are not persuaded
that the issues relevant to the findings
and rebuttable presumptions we adopt
here vary so significantly in each case
that they must be resolved only on a
case-by-case basis. For example, the
issue of whether the four ‘‘Day 2’’
markets satisfy section 210(m)(1)(A) is
one that can be resolved generically. We
find no merit in the contention that we
should relitigate that issue hundreds of
times for every QF located in ‘‘Day 2’’
organized markets. Our approach here is
consistent with the language of the
statute. Section 210(m)(1)(B) provides
for the submission of ‘‘evidence of
transactions within the relevant
market.’’ Because this language is not
included in section 210(m)(1)(A), our
approach providing for findings and
rebuttable presumptions is consistent
with the statute. Finally, we note that,
unlike the NOPR, we are only
establishing rebuttable presumptions of
access to markets, not final
determinations. These rebuttable
presumptions are not only reasonable
because they address common,
recurring issues, but also will permit
better processing of applications under
52 See SEC v. Chenery, 332 U.S. 194, 202–03,
reh’g denied, 332 U.S. 747 (1947).
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
the compressed 90-day timeframe
required by statute.53
101. We also note that certain QFs
recognize our authority to make generic
findings. PIOs implicitly acknowledge
the Commission’s authority to make
generic findings in supplemental
comments filed on August 25, 2006. In
those comments, PIOs urged the
Commission to find that certain classes
of QFs should retain the right to require
electric utility purchases regardless of
the state of the markets on the ground
that certain classes of QFs lack access to
markets.
102. As noted, while the Commission
is making a finding in this rulemaking
that four markets satisfy the market
criteria of section 210(m)(1)(A) of
PURPA, and is establishing a rebuttable
presumption that QFs above 20 MWs
have nondiscriminatory access to those
markets, electric utilities within those
markets will nevertheless have to file an
application pursuant to our regulations
implementing section 210(m)(3) of
PURPA, that is pursuant to section
292.310 of the Commission’s
regulations, for relief from the
requirement to enter into new contracts
or obligations with QFs. An electric
utility member of one of these four
RTO/ISOs filing for relief from the
obligation to purchase will need to refer
to this finding in the Final Rule as part
of its application. When it files for relief
from the purchase obligation it must
also submit information about
transmission constraints within its
service territory in order to give
potentially affected QFs information
that may be relevant to rebutting the
presumption that they have access to all
aspects of the applicable ‘‘Day 2’’
market. A QF 20 MW or smaller located
within the Midwest ISO, PJM, ISO–NE,
and NYISO will be presumed not to
have nondiscriminatory access to these
wholesale markets.54 A QF larger than
20 MW located within the Midwest ISO,
PJM, ISO–NE, and NYISO will be
presumed to have nondiscriminatory
access to these wholesale markets. A QF
larger than 20 MW may rebut that
53 We note in this regard that section 210(m) of
PURPA requires the Commission to act on an
application, within 90 days of such application,
‘‘after notice * * * and an opportunity for
comment.’’ This contrasts with the requirement of
sections 205 and 206 of the FPA that the
Commission act after a ‘‘hearing,’’ not just after an
opportunity to comment. See 16 U.S.C. 824d, e.
54 The electric utility would have to make
additional showings if it wished to rebut the
presumption that small QFs do not have
nondiscriminatory access to its region’s Day 2
wholesale markets, and to long term capacity and
energy markets.
PO 00000
Frm 00016
Fmt 4701
Sfmt 4700
presumption by showing that it in fact
lacks access.
103. A similar process will be used in
cases for utilities located in ‘‘Day 1’’ or
other markets. However, in those
markets, other than ERCOT, there will
be no presumption that a market that
satisfies section 210(m)(1)(B) or (C)
criteria for termination of the purchase
obligation exists. The utility seeking
relief will have to make that showing. In
addition to providing evidence that
such markets satisfy the criteria of
subsections (B) and (C) generally, a
utility will have to submit evidence
sufficient to overcome the presumption
that a QF of 20 MWs net capacity or
below does not have nondiscriminatory
access to those markets. Further, as
indicated, there will be no presumption
regarding QFs above 20 MWs for
markets covered by sections
210(m)(1)(B) and (C).
104. The result of this procedural
process is that, before the Commission
relieves an electric utility of its
requirement to enter into a new contract
or obligation to purchase electric energy
from any QF, the Commission will have
made a facility-specific determination
that the QF has nondiscriminatory
access to a section 210(m)(1)(A), (B) or
(C) market. It is true that the process
utilizes certain rebuttable presumptions.
But as discussed above, we believe that
there is a reasonable basis for the
presumptions we are establishing, and
we stress that all of the presumptions
being established are rebuttable. We also
believe that the use of the presumptions
will assist the parties—QFs as well as
electric utilities—and the Commission
to more readily process applications for
termination of the purchase requirement
consistent with the statute and within
the 90-day timeframe required by
section 210(m)(1)(3) of PURPA. Finally,
we recognize concerns that QFs may not
have access to the level of information
that electric utilities have and that some
QFs lack the resources and expertise to
participate in Commission litigation.
The creation of the rebuttable
presumption in favor of small QFs, as
well as the information requirements we
are imposing on electric utilities as part
of their applications, should help QFs in
this regard. Thus, we believe that the
procedures we are creating for
processing applications to terminate the
requirement that an electric utility
purchase electric energy from a QF are
consistent with the requirement in
section 210(m)(3) of PURPA that: (1)
QFs be given sufficient notice; (2) a
utility set forth the factual basis on
which relief is requested; and (3) a
utility describe why the conditions set
E:\FR\FM\01NOR2.SGM
01NOR2
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
for in sections 210(m)(1)(A), (B) or (C)
have been met.
105. As to the arguments that QFs do
not have sufficient notice of the
Commission’s generic conclusions, we
disagree. As indicated above, these
parties have it backwards. We are
providing greater, not lesser, notice of
our conclusions regarding these issues
by addressing them in a proposed
rulemaking, rather than in individual
adjudications. Moreover, every
potentially affected QF will be given
notice of the proceedings filed under
§ 292.310 of our regulations and will, in
those proceedings, have the opportunity
to rebut the generic findings made in
this Final Rule.
B. Section 210(m)(1)(A) of PURPA
1. Midwest ISO, PJM, ISO–NE, and
NYISO
sroberts on PROD1PC70 with RULES
a. NOPR
106. Section 210(m)(1)(A) of PURPA
requires the Commission to terminate an
electric utility’s obligation to purchase
from QFs if QFs have nondiscriminatory
access to (i) independently
administered, auction-based, day-ahead
and real-time wholesale markets for the
sale of electric energy; and (ii)
wholesale markets for long-term sales of
capacity and electric energy.
107. In the NOPR, the Commission
interpreted section 210(m)(1)(A) to
apply in regions in which ISOs and
RTOs administer day-ahead and realtime markets, and bilateral long-term
contracts for the sale of capacity and
electric energy are available to
participants/QFs in these markets.
These are commonly known as ‘‘Day 2’’
RTO/ISOs. The Commission proposed
to find that the Midwest ISO, PJM, ISO–
NE, and NYISO satisfy the requirements
of section 210(m)(1)(A).55 The
Commission stated in the NOPR that
these entities are Commission approved
ISOs or RTOs that provide
nondiscriminatory open access
transmission services and
independently administer auction-based
wholesale markets for day-ahead and
real-time energy sales. The Commission
stated in the NOPR that additionally,
with respect to subparagraph (A)(ii), the
existence of bilateral long-term contracts
for long-term sales of capacity and
energy indicates that there is a market.
55 In the NOPR the Commission noted that while
SPP and the CAISO, respectively are a Commissionapproved RTO and ISO, they do not satisfy the
requirements of section 210(m)(1)(A) because
neither has day-ahead markets. The Commission
stated, however, that any utility within SPP and
CAISO may file an application with the
Commission to seek relief from the mandatory
purchase requirement under section 210(m)(1)(B) or
(C), on a case-by-case basis.
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
The Commission stated that it is
reasonable to conclude that the second
prong of section 210(m)(1)(A) is met
because bilateral long-term contracts are
available to participants in the
footprints of the Midwest ISO, PJM,
ISO–NE, and NYISO. Therefore, the
Commission proposed to find that
electric utilities that are members of the
Midwest ISO, PJM, ISO–NE, and NYISO
would meet the requirements for relief
from the mandatory purchase
requirement.56
b. Comments
108. The American Chemistry
Council, American Energy, American
Forest & Paper, CCC, and Midwest
Transmission Customers disagree with
the Commission’s finding and argue that
Midwest ISO, PJM, ISO–NE, and NYISO
do not meet section 210(m)(1)(A).
Several commenters argue that the
Commission’s proposed findings with
respect to the Midwest ISO, PJM, ISO–
NE, and NYISO markets are
insufficiently supported by record
evidence. In addition, the American
Chemistry Council and CCC argue that
these markets are premature.
109. Wisconsin Industrial Energy
Group, Inc. argues that the
Commission’s proposed findings with
respect to Midwest ISO are premature
because a viable competive market does
not exist in the Midwest ISO footprint
and because QF owners and operators
do not have nondiscriminatory access to
the Midwest ISO market. Midwest
Transmission Customers argue that
Midwest ISO markets are still not
sufficiently mature to justify the
Commission terminating the PURPA
purchase obligation in Midwest ISO.
The American Chemistry Council and
CCC argue that there is no evidentiary
basis that shows bilateral contracts for
long-term sales of capacity are available
to QFs on a nondiscriminatory basis or
that there is a ‘‘market’’ for such
contracts. These commenters argue that
the NOPR offers no qualitative analysis
of the bilateral markets that are
presumed to exist. ELCON argues that a
QF-specific review would establish that,
in many cases, QFs do not have
nondiscriminatory access to long-term
bilateral markets whether in RTOs or
otherwise. ELCON states that
considerable evidence establishes that
markets either are in their infancy (e.g.,
Midwest ISO), or are not functioning
`
vis-a-vis long-term sales of capacity or
energy. ELCON states that it will be
difficult for the Commission to sustain
on judicial review a generic finding that
ISOs and RTOs offer long-term markets
56 NOPR
PO 00000
Fmt 4701
for power when the Commission’s own
recent rulemaking announcing financial
transmission rights (FTRs) is predicated
on the need for FTRs to jump start longterm power markets specifically in
regions with ISOs and RTOs. ELCON
takes issue with the assertion that PJM
operates an open, competitive market,
citing the State of Delaware as an
example. ELCON states that according
to a recent report by the Delaware
Cabinet Committee on Energy,
competitive markets are not working in
Delaware.57
110. Deere & Company (Deere) states
that open access transmission service
presumes the existence of bilateral sale
and purchase parties separate from the
transmitting utility, with the
transmitting utility providing the
transmission service to either the seller
or the buyer. Deere states that that does
not mean that there is
nondiscriminatory access to the longterm sale and purchase market. Deere
states that one buyer for all long-term
sellers in a market would mean that
there is a monopsony, and through the
exercise by the single buyer of its
monopsony ‘‘market power,’’
manifested in the form of a refusal to
deal, a new seller would not have any
access to the long-term sale and
purchase market.
111. Caithness argues that sections
210(m)(1)(A) and (B) both require that
there be markets for long-term
wholesale sales of energy and capacity
before the must-purchase requirement
can be terminated. The American
Chemistry Council argues that in trying
to make sense of the fact that section
210(m)(1)(B) contains a directive to
‘‘consider evidence of transactions in
the relevant market,’’ while section
210(m)(1)(A) contains no such directive,
the Commission’s proposed
interpretation effectively reads an
essential element of section
210(m)(1)(A)—namely, the existence of
‘‘wholesale markets for long-term sales
of capacity and electric energy’’—out of
the statute. The American Chemistry
Council states that for this reason, the
Commission’s proposed interpretation
contravenes the clear language of
section 210(m)(1)(A).
112. American Forest & Paper states
that bilateral contracts have always
existed, but the Commission has never
determined that the mere existence of
bilateral contracts constituted a market,
particularly, where those contracts are
mostly between utilities and their
affiliates.
57 ELCON’s August 25, 2006 Supplemental
Comments at 8–9.
at P 22.
Frm 00017
64357
Sfmt 4700
E:\FR\FM\01NOR2.SGM
01NOR2
sroberts on PROD1PC70 with RULES
64358
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
113. The CCC states that the
Commission must require an affirmative
showing that buyers other than the
utility are willing to purchase QF energy
and capacity on a short-term and longterm basis, including through long-term
purchases of capacity before the
purchase obligation is lifted.
114. EEI, PJM, Constellation, Exelon,
FirstEnergy, Montana-Dakota, National
Grid, PJM Transmission Owners, and
PPL support the Commission’s
preliminary finding that QFs
interconnected with utilities that are
members of the Midwest ISO, PJM, ISO–
NE and NYISO have nondiscriminatory
access to those markets and that those
markets readily satisfy the section
210(m)(1)(A) criteria for removing the
PURPA section 210 purchase obligation.
EEI states that additional evidence of
the scope of market opportunities for
QFs is seen in the increasing number of
QFs filing for authority to sell at marketbased rates in response to the
Commission’s recent Order No. 671.58
EEI states that the QF’s argument against
the Commission’s proposal in essence is
that markets must assure QFs will
receive the same amount of revenues
that they would receive from mandatory
utility sales at avoided cost rates before
the mandatory purchase requirement
may be lifted. Exelon believes that the
PJM markets are effective and offer
nondiscriminatory opportunities for
QFs and small power producers to sell
their output to entities other than the
interconnecting utility. To facilitate
these small generators participating in
the RTO markets in the absence of a
mandatory purchase requirement,
Exelon suggests that the Commission
encourage utilities to work with the QFs
and small power producers that qualify
under state renewable resource
programs to develop and implement a
voluntary standard offer contract.
115. EEI, PJM, Constellation, Exelon,
FirstEnergy, Montana-Dakota, National
Grid, PJM Transmission Owners, and
PPL also support the NOPR’s finding
regarding bilateral contracts for longterm sales of energy and capacity. PJM
states that the Commission reasonably
concludes that the existence of
organized and transparent competitive
markets for capacity and energy provide
a platform for the development of
competitive bilateral contracts in
satisfaction of section 210(m)(1)A(ii) of
EPAct 2005. EEI states that the test of
section 210(m)(1)(A)(ii) can be and is
met by markets that provide
opportunities for long term sales
pursuant to bilateral transactions—
58 Supra
note 15.
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
markets which flourish in all the ‘‘Day
2’’ RTOs.
c. Commission Determination
116. Under section 210(m)(1)(A), the
Commission must terminate the
requirement that an electric utility enter
a new contract or obligation to purchase
electric energy from a QF if the QF has
nondiscriminatory access to (i)
independently administered, auctionbased day-ahead and real-time
wholesale markets for the sale of electric
energy; and (ii) wholesale markets for
long-term sales of capacity and electric
energy.
117. We find that the Midwest ISO,
PJM, ISO–NE, and NYISO satisfy section
210(m)(1)(A)(i) because the markets
administered by these RTO/ISOs are, as
required by subparagraph (A)(i),
independently administered, auctionbased day-ahead and real-time
wholesale markets for the sale of electric
energy. With respect to section
210(m)(1)(A)(ii) and the requirement for
wholesale markets for long-term sales of
capacity and electric energy, we find
that, as proposed in the NOPR, the
existence of bilateral long-term contracts
for long-term sales of capacity and
energy is a sufficient indication of a
market. As the Commission explained
in the NOPR, it is reasonable to
conclude that subparagraph (A)(ii) is
met because bilateral long-term
contracts are available to participants in
the footprints of the Midwest ISO, PJM,
ISO–NE, and NYISO. Although there is
no formalized market for such long-term
contracts, nothing in the statute requires
such an organized market. Rather, the
only requirement for organized markets
relates to subparagraph A(i), and the
requirement that there be auction-based
day-ahead and real-time markets.
118. We disagree with those who
argue that because these markets are
premature or in their infancy, the
Commission cannot relieve utilities of
the purchase obligations. The relevant
issue under the statute is whether these
markets satisfy the requirements
enumerated above, not whether they are
‘‘perfect’’ today or are undergoing
reforms as they develop. Again, nothing
in the statutory language suggests such
a test, nor have its proponents provided
us with any clear demarcation to
determine when such a market is too
‘‘premature’’ to qualify under section
210(m)(A). Further, we note that the
Midwest ISO has been an RTO since
2001 and began ‘‘Day 2’’ operations (i.e.,
auction-based, day-ahead markets) in
2005. PJM has been an RTO since 2001
and began ‘‘Day 2’’ operations in 2000.
ISO–NE has been an RTO since 2004
and began ‘‘Day 2’’ operations in 2003.
PO 00000
Frm 00018
Fmt 4701
Sfmt 4700
NYISO has been an ISO since 1998 and
began ‘‘Day 2’’ operations in 1999.
These RTOs and ISOs are established
and operate ‘‘Day 2’’ wholesale markets,
as required by subparagraph (A)(i), in
their respective regions.
119. CCC and the American
Chemistry Council argue that the
Commission’s proposed findings with
respect to the Midwest ISO, PJM, ISO–
NE, and NYISO markets are
insufficiently supported by record
evidence. We find this argument
without merit. The day ahead and real
time markets are precisely those
contemplated by the words of section
210(m)(A)(i) and, indeed, there is no
real dispute that they are Commission
approved independently administered
entities,59 and that they operate auctionbased day-ahead and real-time
wholesale markets for the sale of electric
energy as represented pursuant to their
respective, Commission approved,
tariffs.60
120. With respect to bilateral markets
in these ISOs/RTOs, i.e., section
210(m)(A)(ii), no party argues that longterm contracts do not exist in these
markets or that QFs are precluded from
entering into them with willing
buyers.61 The transmission access
offered by RTOs allows suppliers
(including QFs) the opportunity to enter
into long-term bilateral contracts in a
competitive wholesale market. RTOs
have no incentive to favor one set of
suppliers over others in providing
transmission access. RTO footprints
encompass many different wholesale
buyers, thus proving significant
opportunity for sellers to reach many
different wholesale buyers. In addition,
the organized markets operated by RTOs
facilitate long-term bilateral contracts
between sellers (including qualifying
59 See Midwest Independent Transmission System
Operator, Inc., 97 FERC ¶ 61,326 (2001) order on
reh’g, 103 FERC ¶ 61,169 (2003); PJM
Interconnection, L.L.C., 96 FERC ¶ 61,061 (2001).
On December 20, 2002, in PJM Interconnection,
L.L.C., 101 FERC ¶ 61,345 (2002), PJM was granted
full, rather than provisional, RTO status.
Independence was one of the matters considered in
the 2002 Order; ISO New England, Inc., 106 FERC
¶ 61,280 (2004); Central Hudson Gas & Electric Co.,
83 FERC ¶ 61,352 (1998), order on reh’g, 87 FERC
¶ 61,135 (1999).
60 See Midwest Independent Transmission System
Operator, Inc., 108 FERC ¶ 61,163 (Midwest ISO,
FERC Electric Tariff, Third Revised Volume No. 1,
Module C), order on reh’g, 109 FERC ¶ 61,157
(2004), order on reh’g, 111 FERC ¶ 61,043 (2005),
PJM Interconnection, L.L.C., FERC Electric Tariff,
Sixth Revised Volume No. 1; New York
Independent System Operator, Inc., FERC Electric
Tariff Original Volume No. 2.
61 We also know from electric quarterly report
(EQR) filings by public utilities that there are longterm contracts for long-term sales of capacity and
energy in each of the markets; those data are
available on the Commissions Web site. https://
www.ferc.gov/docs-filing/eqr/data.asp.
E:\FR\FM\01NOR2.SGM
01NOR2
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
facilities) and wholesale buyers. First,
organized markets provide transparent
spot energy prices that can serve as a
reference in negotiating longer term
contract prices. Second, organized
markets reduce the costs to suppliers of
making long-term bilateral supply
commitments. That is because whenever
a supplier is unable to produce the
energy required under the bilateral
contract (for example, because of an
outage), the supplier can easily acquire
replacement energy from the organized
market at a transparent and competitive
price. Moreover, even when the supplier
is physically capable of producing its
contractually-required energy, the
supplier can acquire the energy from the
RTO’s market whenever it is cheaper to
do so. Both of these factors reduce the
cost to a supplier of entering into a longterm bilateral contract. Furthermore, our
approach is consistent with the
language of section 210(m)(1)(A)(ii). As
discussed above, section 210(m)(1)(B)
provides for the submission of
‘‘evidence of transactions within the
relevant market.’’ Because this language
is not included in section 210(m)(1)(A),
our finding with respect to section
210(m)(1)(A)(ii) is consistent with the
statute. We, therefore, find it reasonable
to conclude that Day 2 markets provide
an opportunity to make long-term sales
of capacity and electric energy and meet
the criteria of section 210(m)(1)(A)(ii) as
well as section 210(m)(1)(A)(i).
121. As to ELCON’s citation to a study
by the State of Delaware finding that
competitive electric energy markets are
not working well in Delaware, we find
it inapposite. The issue under the
statute is not whether these organized
markets are perfect or, alternatively,
could be improved. As we stated above,
all that is required by section
210(m)(A)(ii) is the presence of
‘‘wholesale markets for long-term sales
of capacity and electric energy.’’ The
Delaware report does not demonstrate
that such a market does not exist.
2. Whether Membership in an RTO/ISO
Is Necessary To Invoke the Rebuttable
Presumption of Access to ‘‘Day 2’’
Markets
sroberts on PROD1PC70 with RULES
a. NOPR
122. In the NOPR, the Commission
concluded that QFs interconnected with
electric utilities that are members of
Midwest ISO, PJM, ISO–NE, and NYISO
have nondiscriminatory access to
markets described in section
210(m)(1)(A).
b. Comments
123. Missouri River Energy Services
(MRES), a municipal, and the NRECA
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
seek clarification as to which entities
are eligible for the exemption from the
mandatory purchase requirement. For
example, MRES states that not all
entities within the Midwest ISO
footprint are transmission-owning
electric utility members of Midwest ISO.
MRES states that it is currently a market
participant in the Midwest ISO, but not
a member. MRES states that in addition,
MRES has assumed the section 210
mandatory purchase requirement on
behalf of its members, many of which
are located within the Midwest ISO
footprint.
124. Progress states that while a caseby-case analysis may be appropriate, it
believes that utilities such as CP&L, that
have Commission-approved OATTs and
are adjacent to and directly connected
with a ‘‘Day 2’’ RTO (such as PJM),
should obtain a rebuttable presumption
that the second prong of the test is met.
Progress states that there is no
difference between a QF located within
PJM and a QF located within CP&L’s
service territory with respect to access
to short-term and long-term capacity
and energy wholesale markets.
c. Commission Determination
125. The statute is clear that the
obligation to purchase and thus relief of
the obligation resides with the electric
utility. For purposes of establishing a
rebuttable presumption that QFs
interconnected with certain utilities
have access to ‘‘Day 2’’ markets, we
think that a reasonable line to draw is
with the member utilities of the ‘‘Day 2’’
RTO/ISOs. These utilities have turned
over the operation of their transmission
facilities to an independent entity that
has no stake in the marketplace and will
ensure that all users of the transmission
system are treated on a
nondiscriminatory basis and are
provided access to markets. We
recognize that other electric utilities
may provide nondiscriminatory access
to the ‘‘Day 2’’ markets. But for purposes
of applying a rebuttable presumption
that QFs have nondiscriminatory access
to the ‘‘Day 2’’ markets, we believe that
it is reasonable to draw the line with
members of the Midwest ISO, PJM, ISONE, or NYISO. Nevertheless, entities
that are not members of the Midwest
ISO, PJM, ISO-NE, or NYISO may seek
relief from the purchase obligation
pursuant to either section 210(m)(1)(B)
or (C) pursuant to the procedures
contained in § 292.310 of the
Commission’s regulations. Such
applications will be reviewed on an
electric utility-by-electric utility basis
pursuant to the procedures contained in
§ 292.310 of the Commission’s
regulations. A utility making such an
PO 00000
Frm 00019
Fmt 4701
Sfmt 4700
64359
application will have the burden of
showing that all elements necessary for
granting relief exist.
3. Compliance Filing
a. NOPR
126. The Commission proposed that
to claim relief from the purchase
obligation, electric utilities that are
members of Midwest ISO, PJM, ISO-NE,
and NYISO will need to make
compliance filings pursuant to section
210(m)(3).
b. Comments
127. AEP and PJM Transmission
Owners argue that the Commission
should remove the obligation to require
a compliance filing for utilities located
in one of the exempted RTO/ISOs. PJM
Transmission Owners argue that it is not
apparent that Congress intended the
Commission only to grant relief from
such mandatory purchase requirements
upon receipt of an application. AEP and
PJM Transmission Owners contend
there is nothing prohibiting the
Commission from granting blanket relief
for all electric utilities in a particular
RTO/ISO that meets the requirements of
section 210(m). PJM Transmission
Owners request, if compliance filings
are ultimately required, to be allowed to
make one filing on behalf of all the
electric utilities in PJM.
128. EEI states that, instead of
compliance filings by utilities located
within the four ‘‘Day 2’’ markets, the
Commission may wish to require
utilities to apply for relief from the
mandatory purchase requirement, in
accordance with section 210(m)(3) of
PURPA. EEI states that utilities applying
for relief would be entitled to rely on
generic Commission findings (as the
Commission has proposed in the NOPR)
that the four ‘‘Day 2’’ markets meet the
tests established in section 210(m)(1)(A)
and that a Commission-approved OATT
is evidence of nondiscriminatory access
to these markets under section
210(m)(1).
c. Commission Determination
129. In light of the comments filed,
we conclude that utilities in ‘‘Day 2’’
RTO/ISO markets should file
applications pursuant to section
210(m)(3), instead of the ‘‘compliance
filings’’ proposed in the NOPR. We
believe that this will be more consistent
with the statute than the compliance
filings proposed in the NOPR. In the
section 210(m)(3) application, a utility
within a ‘‘Day 2’’ RTO/ISO will be
required to: (a) Show that it is a member
of a ‘‘Day 2’’ RTO; (b) provide
information to enable QFs larger than 20
MW to seek to rebut the presumption
E:\FR\FM\01NOR2.SGM
01NOR2
64360
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
that they have nondiscriminatory access
to the market; such information will be
a description of transmission constraints
not otherwise publicly available, and if
publicly available, provide a specific
link to such information; and (c)
provide a list of affected interconnected
QFs. With respect to the section
210(m)(A) ‘‘Day 2’’ RTO/ISO markets,
these applications, in conjunction with
the generic findings and rebuttable
presumptions adopted in this Final Rule
and discussed elsewhere, will allow us
to timely and fairly process applications
within the 90-day time period intended
by Congress.
C. Section 210(m)(1)(B)
1. Definition of ‘‘Regional’’ for Purposes
of Section 210(m)(1)(B)(i)
sroberts on PROD1PC70 with RULES
a. NOPR
130. Section 210(m)(1)(B) requires the
Commission to make a finding, among
other things, that a QF has
nondiscriminatory access to
transmission and interconnection
services provided by a Commissionapproved ‘‘regional transmission
entity.’’ In the NOPR, the Commission
noted that amended section 210 does
not contain any express definition of
‘‘regional transmission entity.’’ The
Commission therefore explained in the
NOPR that we have discretion in
interpreting section 210(m)(1)(B)(i) to
deem an entity to be ‘‘regional.’’ The
Commission listed factors, such as
sufficient regional scope or
configuration of the multiple discrete
transmission systems the regional
transmission entity controls, to be
considered when determining a
‘‘regional transmission entity.’’ 62
b. Comments
131. American Forest & Paper, LEUG,
and NISCO offer suggestions as to how
the Commission should define
‘‘regional’’ as it is used in section
210(m)(1)(B). LEUG suggests that the
Commission should use a similar
standard in defining the term ‘‘regional’’
as it’s used in Order No. 2000. American
Forest & Paper believes that the
Commission should exercise the
discretion it has under section 210 in
conformance with its observations,
concerns and findings regarding the
scope and independence of RTOs and
ISOs necessary to assure
nondiscriminatory access and
independence. American Forest & Paper
states that the Commission has
extensive jurisprudence regarding its
concerns surrounding the scope and the
level of independence necessary to
62 NOPR
at P 16.
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
assure nondiscriminatory and
independent administration, and should
rely on this existing body of precedent
when making determinations pursuant
to newly enacted section 210(m).
Occidental argued that the NOPR
incorrectly suggests that the
Commission has discretion to deem an
entity to be a ‘‘Commission-approved
regional transmission entity’’ solely in
the context of a determination that the
QF is provided nondiscriminatory
access in accordance with section
210(m)(1)(B)(i). It requests the
Commission to clarify, at a minimum,
that ‘‘Commission-approved regional
transmission entity’’ does not include
stand-alone electric utilities or Entergy’s
ICT.
c. Commission Determination
132. In determining whether a
transmission entity is ‘‘regional,’’ we
will not rely solely on the ‘‘scope and
regional configuration’’ standard as
discussed in Order No. 2000 as one
commenter suggests. Section
210(m)(1)(B) does not tie ‘‘regional’’ to
Order No. 2000 but rather leaves to the
Commission’s discretion whether to
deem an entity ‘‘regional’’ and we will
make that determination on a case-bycase basis in response to applications
filed by electric utilities pursuant to
§ 292.310 of the Commission’s
regulations. Accordingly, we will not
make a finding that Entergy’s ICT or a
stand-alone electric utility would not be
deemed a ‘‘regional transmission entity’’
at this time. The NOPR laid out some of
the factors the Commission may
consider in its determination, such as
sufficient regional scope or
configuration or the multiple discrete
transmission systems and electric utility
controls. In this Final Rule, an electric
utility claiming relief pursuant to
section 210(m)(1)(B) must set forth the
reasons that it meets the requirements of
section 210(m)(1)(B)(i) in an application
made pursuant to § 292.310 of the
Commission’s regulations.
2. Section 210(m)(1)(B)(ii)
a. NOPR
133. Section 210(m)(1)(B)(ii) requires
QFs to have access to competitive
wholesale markets that provide a
meaningful opportunity to sell capacity
and energy on both a short- and longterm basis and energy on a real-time
basis to a buyer other than the utility to
which the QF is interconnected. The
Commission is to consider, among other
factors, evidence of transactions within
the relevant market in determining
‘‘meaningful opportunity.’’ The
Commission stated that, taken together,
PO 00000
Frm 00020
Fmt 4701
Sfmt 4700
the terms ‘‘competitive,’’ ‘‘meaningful
opportunity,’’ and ‘‘evidence of
transactions’’ suggest that Congress
intended waiver to occur in a nonauction based market only if it could be
established that QFs had the
opportunity to sell their output into
competitive wholesale markets to
buyers other than the utility to which
the QF is interconnected. In the NOPR,
the Commission sought comment on
ways that section 210(m)(1)(B)(ii) could
be satisfied. The Commission asked if a
demonstration that an organized power
procurement process exists in which
QFs can participate would satisfy.
b. Comments
134. AES Shady Point, Deere, Energy
Producers of California, Utah
Association of Energy Users (UAE), and
Solid Waste of Palm Beach believe that
the existence of an organized power
procurement process does not indicate
the presence of a competitive wholesale
market. Occidental argues that the
Commission’s reference to a generic
‘‘organized procurement process’’ lacks
the specificity required in order to
analyze whether it would satisfy any
element of section 210(m)(1)(B)(ii) and
omits the statutory requirement that QFs
have a meaningful opportunity to sell to
‘‘buyers other than the utility to which
the qualifying facility is
interconnected.’’ ELCON states that the
critical question is whether potential
suppliers have access to other potential
buyers apart from the monopsony buyer
holding the request for proposals (RFP).
ELCON states that the Commission
should seek a demonstration of
contractual sales of capacity or energy to
utilities other than the interconnected
utility in response to RFPs. The UAE
argues that an organized procurement
process does not ensure fairness since
utilities often control their own
procurement processes and can affect
the outcome. The lack of an
independently administered market
makes it easy for a utility to select its
own resource or a resource that it
prefers. UAE also states that QF
resources are likely to be eliminated in
early rounds of the procurement process
by unreasonably stringent credit
requirements.
135. Entergy and EEI contend that a
procurement process should constitute
ample evidence that QFs have access to
competitive wholesale energy markets.
EEI states that the Commission would
be correct in finding that QFs with
opportunities to participate in organized
power procurement processes have
access to short-term and long-term
markets for the sale of energy and
capacity. EEI states that roughly
E:\FR\FM\01NOR2.SGM
01NOR2
sroberts on PROD1PC70 with RULES
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
nineteen states already require some
form of competitive power procurement
process.63 EEI states that QF
commenters have submitted no
evidence to disprove their ability to
participate in these state-overseen
processes. EEI states that competitive
procurements also are a feature of retail
access programs and state renewable or
resource portfolio programs.
136. Pacific Gas and Electric
Company (PG&E) suggests the
Commission should adopt a rebuttable
presumption of a ‘‘competitive
wholesale market’’ in which an
organized power procurement process
exists in which QFs can participate.
PG&E notes that the California
legislature established a comprehensive
procurement process to be administered
and overseen by the California Public
Utilities Commission (CPUC). PG&E
states that load serving entities must
prepare a procurement plan which
contains a process for utility
procurement and CPUC approval of
procurement strategies. PG&E claims
that California’s procurement process
ensures QFs have fair access to this
process. SCE argues that QFs have
robust opportunities to compete in
competitive solicitations issued by
IOUs. SCE notes that its power
procurement solicitations that are
conducted pursuant to California’s
Renewable Portfolio Standard are open
to generators as small as one megawatt.
137. SCE suggests the Commission
should make a generic finding that if the
Commission has authorized marketbased rate authority for any seller in a
market then that market should be
competitive enough to satisfy
subparagraph (B)(ii). Several
commenters oppose SCE’s market-based
rate proposal and request that the
Commission reject it. The CCC argues
that SCE’s arguments focus solely on the
issue of whether sellers in a given
market are able to exercise market
power and fails to address the extent to
which utilities are able to exercise
monopsony buying power given their
role as the only load serving entities
(LSEs) with the ability and potential
willingness to buy power on a long-term
basis or in significant quantities. Deere
contends that market-based rate
authority is focused on the seller and its
attributes, whereas section 210(m) is
focused on the QF and its ability to
access a market. Occidental adds that
such a finding would render the
distinction between ‘‘competitive
wholesale markets,’’ as used in
subparagraph (B)(ii), and ‘‘wholesale
markets,’’ as used in subparagraphs (B)
63 EEI
Initial Comments at 44.
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
and (C), meaningless because the
Commission has authorized marketbased sales in every region of the
continental United States.
c. Commission Determination
138. The Commission in the NOPR set
forth its interpretation of the statute and
sought comments on ways section
210(m)(1)(B)(ii) could be satisfied.
Specifically, the Commission asked if an
organized procurement process would
meet the requirements of section
210(m)(1)(B)(ii). After reviewing the
comments received, we have decided
not to make any generic findings
concerning whether procurement
processes might satisfy section
210(m)(1(B)(ii). Reflecting on parties’
comments and the Commission’s own
experience with utilities’ procurement
processes leads us to conclude that the
processes are complex and not uniform.
Thus, we cannot find that simply
requiring an organized procurement
process without elaboration would meet
the requirements of the statute.
Accordingly, we will not make a generic
finding nor establish a rebuttable
presumption, as PG&E and SCE suggest.
As discussed in a later section, the
Commission will entertain applications
for relief of the mandatory purchase
requirement pursuant to section
210(m)(1)(B) on a case-by-case basis
pursuant to the procedures specified in
section 292.310 of the Commission’s
regulations. The only rebuttable
presumption that will apply in the
context of applications under section
210(m)(1)(B) (as well as (C)) is the
presumption that QFs 20 MWs or below
do not have nondiscriminatory access to
the relevant markets.
139. The Commission, however, will
not rule out the possibility of an
organized procurement process
satisfying some or all of the
requirements of section 210(m)(1)(B)(ii).
Should an electric utility seek such a
finding in its application, it is
incumbent upon the utility to fully
demonstrate that the procurement
process satisfies one or all of the
elements of section 210(m)(1)(B)(ii).64
The utility must support its application
with a detailed description of how the
procurement process is designed, how
winning bids are selected, evidence of
past solicitations and winning bids,65
64 All the elements of section 210(m)(1)(B)(ii)
must be satisfied whether it is through an organized
procurement process or by some other means or a
combination.
65 The Commission would be particularly
interested in whether QFs have participated in the
solicitations and whether QFs have been selected as
a winning bidder.
PO 00000
Frm 00021
Fmt 4701
Sfmt 4700
64361
solicitation characteristics,66 and any
other information about the
procurement process. This list is not
meant to be exhaustive, but rather
provides examples of the type of
information the Commission needs in
order to make a finding.
140. SCE argues that the
‘‘competitive’’ element of section
210(m)(1)(B)(ii) could be met if the
Commission has authorized marketbased rate authority to the utility
seeking relief from the mandatory
purchase requirement. We will not
make a generic finding as suggested by
SCE. When the Commission grants an
applicant market-based rate authority, it
examines an applicant’s generation
market power potential. The
competitive element of section
210(m)(1)(B)(ii) is not concerned with
how much generation a utility owns or
its ability to exercise generation seller
market power, but rather, whether the
wholesale market provides a meaningful
opportunity for a QF to sell its capacity
and energy to a buyer other than the
utility to which the QF is
interconnected.
3. Case-by-Case Determinations for
Subparagraphs (B) and (C)
a. NOPR
141. In the NOPR, the Commission
proposed to determine on a case-by-case
basis, rather than generically, whether a
utility has met the requirements of
sections 210(m)(1)(B) and 210(m)(1)(C)
for relief from its mandatory purchase
requirement. The Commission also
proposed to allow joint applications to
be filed by several utilities in a region
if the applications for relief present
common issue of law and fact. The
NOPR concluded that utilities would be
required to file such applications for
relief with the Commission pursuant to
section 210(m)(3), which the
Commission proposed to implement in
section 292.310 of its regulations.
b. Comments
142. No comments were filed
opposing the NOPR’s proposal.
Constellation seeks clarification as to
how the Commission will treat current
Day 1 or non-RTO markets which may,
in the future, become ‘‘Day 2’’ markets.
Constellation wants any future ‘‘Day 2’’
market to be analyzed on a case-by-case
basis pursuant to section 210(m)(3).
143. EPSA supports a case-by-case
approach for subparagraphs (B) and (C)
provided that an individual QF can
66 Solicitation characteristics refers to the contract
term, type of service requested, dispatchability, the
power terms and conditions, the non-power terms
and conditions, etc.
E:\FR\FM\01NOR2.SGM
01NOR2
64362
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
rebut utility’s application. EPSA also
argues that utilities should be required
to file specific contract information that
would support the premise that there
are ‘‘competitive wholesale markets that
provide a meaningful opportunity to sell
capacity, including long-term, shortterm and real-time sales to buyers other
than the utility to which the qualifying
facility is interconnected.’’
144. LEUG, NISCO, and Occidental
seek clarification in the Final Rule that
Entergy’s ICT does not satisfy the
requirements of section 210(m)(1)(B).
These commenters state that access to
section 210(m)(1)(B) markets does not
exist in Louisiana today, and will not
result from Entergy’s ICT and weekly
procurement process proposals. The
commenters state that an ICT can not
satisfy section 210(m)(1)(B)(i) because
Entergy’s ICT proposal calls for Entergy
to remain the owner and operator of the
transmission system and continue to
have ultimate responsibility for
providing transmission service.
sroberts on PROD1PC70 with RULES
c. Commission Determination
145. The Commission adopts the
NOPR’s proposal to determine on a
case-by-case basis in response to
applications filed pursuant to section
292.310 of the Commission’s regulations
whether an electric utility has met the
requirements of sections 210(m)(1)(B)
and 210(m)(1)(C) for relief from its
mandatory purchase requirement. We
clarify for EPSA that individual QFs
may file comments opposing a utility’s
section 210(m)(3) application for relief
pursuant to subparagraphs (B) and (C).67
We will also clarify for Constellation
that any current ‘‘Day 1’’ market or nonRTO market that becomes a ‘‘Day 2’’
market after issuance of this Final Rule
will not be addressed generically in a
rulemaking but will be addressed on a
case-by-case basis. This is consistent
with what the Commission proposed in
the NOPR. The Commission proposed,
and we adopt here, that all issues
relating to non-RTO/ISOs and RTO/ISOs
that do not have both auction-based
real-time and day-ahead markets will be
addressed on a case-by-case basis,
pursuant to section 210(m)(3) as
implemented by the Commission in
§ 292.310 of the Commission’s
regulations. The only generic finding in
this Final Rule that will apply to caseby-case determinations are the
rebuttable presumptions that the OATT
and interconnection rules provide
nondiscriminatory access to markets,
67 This also applies to section 210(m)(3)
applications for relief pursuant to section
210(m)(1)(A), which is discussed in another part of
the Final Rule.
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
and that QFs 20 MWs or below do not
have nondiscriminatory access to
markets.
146. While we will not institute
another rulemaking to address whether
a new ‘‘Day 2’’ RTO/ISO satisfies the
statutory criteria for a utility to claim
relief from the requirement that it enter
into new contracts or obligations with
QFs within the markets, we note that
the 90-day proceedings provided for in
section 210(m)(3) of PURPA and
§ 292.310 of our regulations, provide a
very compressed period for making the
complex determinations that a regional
market satisfies the statutory criteria.
Accordingly, for utilities that wish to
obtain a regional generic determination
that a market satisfies the criteria of
section 210(m)(1)(A), we will entertain
declaratory orders to make such
determinations. If a generic
determination is made in a declaratory
order context, the utility members of the
market would then be obligated to file
for relief from the requirement that they
purchase from QFs on a utility specific
basis pursuant to section 292.310 of our
regulations before the Commission
would terminate the requirement that
the electric utility purchase electric
energy from QFs.
147. For purposes of obtaining
regulatory certainty earlier rather than
later, it is also possible that a QF may
want to seek a declaratory order that,
based on its specific circumstances, it
does not have nondiscriminatory access
to markets. We will entertain such
declaratory order requests. If a QF
obtains such an advance declaratory
order, it may file the order in response
to a utility’s application to be relieved
of the mandatory purchase obligation
under section 292.310 of the
Commission’s regulations.
148. We will not grant the three
commenters’ request that we clarify in
the Final Rule that Entergy’s ICT does
not satisfy the requirements of section
210(m)(1)(B). Rather, consistent with the
approach adopted herein, we will
consider Entergy’s ICT on a case-by-case
basis should Entergy decide to file an
application for relief pursuant to section
210(m)(3) and § 292.310 of the
Commission’s regulations.
D. Section 210(m)(1)(C)—Nonpublic
Utilities
1. NOPR
149. The NOPR proposed that there be
a rebuttable presumption that a utility
provides nondiscriminatory access if it
has an Order No. 888 OATT on file with
the Commission or a Commissionapproved reciprocity tariff.
PO 00000
Frm 00022
Fmt 4701
Sfmt 4700
2. Comments
150. NRECA states that some nonpublic utility cooperatives do not have
reciprocity tariffs however, a number of
these non-public electric utilities have
adopted OATTs based on the
Commission’s pro forma OATT, and
have provided nondiscriminatory access
to third parties for years. NRECA states
that they too should be deemed to
provide nondiscriminatory access on a
case-by-case basis, or they should at
least be accorded a rebuttable
presumption that they provide such
service.
3. Commission Determination
151. We decline to establish a
rebuttable presumption of
nondiscriminatory access here for nonpublic utilities which may have adopted
transmission tariffs that are based on the
Commission’s pro forma OATT but are
not on file with the Commission. The
statute clearly states that the
Commission must find that the QF has
nondiscriminatory access to specific
markets before the purchase obligation
may be lifted. While the Commission
appreciates that some non-public
cooperatives have adopted OATTs
based on the Commission’s pro forma
OATT, the Commission has not had
opportunity to review these nor has the
public, including any affected QF. We
therefore believe that it is more
appropriate for the Commission to
evaluate whether QFs interconnected
with such utilities have
nondiscriminatory access to a market
defined by section 210(m)(1)(A), (B), or
(C) on a case-by-case basis. Non-public
utilities seeking relief from the
mandatory purchase requirement may
file an application pursuant to § 292.310
of the Commission’s regulation and may
include their tariffs in support of their
applications.
E. California Independent System
Operator Corporation
1. NOPR
152. In the NOPR, the Commission
did not make a preliminary finding that
the California region operated by the
CAISO met the requirements of PURPA
section 210(m)(1). The Commission did
recognize that the CAISO is a
Commission-approved ISO, but that the
requirements of section 210(m)(1)(A)
have not been satisfied because the
CAISO does not have a day-ahead
market. The Commission noted that any
utility within the CAISO footprint may
file an application with the Commission
to seek relief from the mandatory
purchase requirement pursuant to
sections 210(m)(1)(B) or (C).
E:\FR\FM\01NOR2.SGM
01NOR2
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
sroberts on PROD1PC70 with RULES
2. Comments
153. SCE and PG&E submitted
comments requesting that the
Commission find that the CAISO will
meet the requirements of section
210(m)(1)(A) once the CAISO’s Market
Redesign and Technology Upgrade
Tariff (MRTU Tariff) is effective.68 SCE
and PG&E note that the MRTU Tariff
filing demonstrates that the CAISO
region will have the requisite features to
satisfy section 210(m)(1)(A)(i),
specifically a day-ahead market. SCE
argues that the features described in the
MRTU Tariff compare with those of
other regions for which the Commission
is prepared to make generic findings.
SCE also states there are bilateral longterm contracts in the CAISO region
today. Therefore, the CAISO region
meets section 210(m)(1)(A)(ii). The
California Public Utilities Commission
(CPUC) and PG&E also request a finding
that once the Commission has
determined that CAISO has met the
requirements of section 210(m)(1)(A),
utilities participating in CAISO need
only make a ministerial filing to be
granted a waiver by the Commission.
154. PG&E, SCE and the EEI request
a generic finding that the CAISO
satisfies section 210(m)(1)(B)(i), and
thus, a utility interconnected to the
CAISO meets section 210(m)(1)(B)(i).
EEI notes that the Commission has ruled
that the CAISO Tariff provides
nondiscriminatory access to the ISO
controlled grid.
155. The CCC objects to the NOPR’s
suggestion that California could qualify
for termination of the PURPA purchase
obligation once a day-ahead market
starts operating. It argues that such a
suggestion ignores the realities of the
California market. CCC contends that
QFs continue to have difficulty finding
meaningful opportunities to sell their
output in California due to utilities’
general reluctance to execute contracts
with QFs and a lack of viable
alternatives to the utility purchaser. It
states that merely adding an organized
day-ahead market will not resolve these
problems. The CCC points to a
California Energy Commission’s 2005
Integration Energy Policy Report (Energy
Report) as support for the position that
QFs do not have meaningful
opportunities to sell their power in
California. According to CCC, the
Energy Report finds that cogenerators
have few opportunities to sell their
68 The CAISO filed its proposed MRTU Tariff on
February 9, 2006, in Docket No. ER06–615–000, and
requested an effective date of November 1, 2007.
The Commission conditionally accepted MRTU on
September 21, 2006. California Independent System
Operator Corporation, 116 FERC ¶ 61,274 (2006).
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
power in the existing wholesale markets
and a lack of a robust, functioning
wholesale market in California
discourages cogenerators from installing
new generation. SCE disputes CCC’s
representation of the Energy Report.
156. Independent Energy Producers
Association of California (Independent
Energy Producers) states that the MRTU
has yet to be implemented let alone
analyzed to ensure it is operating as
designed and in a manner that the
CAISO itself has determined sufficient
to remedy the market deficiencies it has
identified. Independent Energy
Producers also notes that the California
market cannot provide the
nondiscriminatory access required
because projects smaller than 1 MW are
excluded by rule from participation.
Independent Energy Producers further
notes CAISO’s intent to subject existing
QFs with existing interconnections to
renewed interconnection studies.
3. Commission Determination
157. Certain commenters request that
the Commission make a generic finding
that the CAISO will meet the
requirements of section 210(m)(1)(A)
once the CAISO’s MRTU Tariff filing
becomes effective. According to the
CAISO, the MRTU Tariff provides for
operation of a day-ahead market, which
is the missing element in meeting the
requirements of section 210(m)(1)(A). It
would be premature for the Commission
to make such a generic finding in this
rulemaking proceeding. The CAISO
filed its proposed MRTU Tariff on
February 9, 2006, in Docket No. ER06–
615–000, and requested an effective date
of November 1, 2007. While the
Commission conditionally approved
CAISO’s MRTU Tariff on September 21,
2006,69 the tariff will not become
effective until November 1, 2007, as
requested. Until there is a functioning
‘‘Day 2’’ RTO/ISO in California, the
Commission is unable to make the
findings required by section
210(m)(1)(A) for termination of the
mandatory purchase requirement.
However, for utilities that wish to obtain
a regional generic determination that a
market satisfies the criteria of section
210(m)(1)(A), we will entertain requests
for declaratory orders to make such
determinations.
158. Certain commenters request that
the Commission make a finding that the
CAISO satisfies section 210(m)(1)(B)(i).
Section 210(m)(1)(B)(i) requires a QF to
have nondiscriminatory access to
transmission and interconnection
services that are provided by a
Commission-approved regional
69 Supra
PO 00000
note 67.
Frm 00023
Fmt 4701
transmission entity and administered
pursuant to an open access transmission
tariff that affords nondiscriminatory
treatment to all customers. In the NOPR,
the Commission interpreted section
210(m)(1)(B)(i) to mean that QFs must
have access to transmission and
interconnection service pursuant to a
Commission-approved OATT and
interconnection rules and provided by
an entity that is regional in scope.70 The
CAISO has a Commission-approved
OATT that has been amended to
incorporate the interconnection
requirements of Order No. 2003. Thus,
in order to make a finding that the
CAISO satisfies section 210(m)(1)(B)(i),
the Commission would have to find that
the CAISO is a ‘‘regional transmission
entity.’’ We noted in the NOPR that
amended PURPA section 210 does not
define ‘‘regional transmission entity,’’
and therefore, the Commission has
discretion to deem an entity to be
‘‘regional’’ based on factors such as
sufficient regional scope or
configuration of the multiple discrete
transmission systems it controls. The
CAISO offers transmission and
interconnection services throughout the
state of California over the transmission
systems of several electric utilities. We
find that California is large enough in
size and configures several discrete
transmission systems for the CAISO to
be considered a ‘‘regional transmission
entity.’’ Accordingly, the Commission
finds that the CAISO satisfies section
210(m)(1)(B)(i). A member electric
utility of the CAISO may rely on this
finding in its application to be relieved
of the obligation to enter into new
contracts to purchase QF electric
energy. We will not, however, make any
findings with regard to section
210(m)(1)(B)(ii). Thus, electric utilities
that are members of the CAISO seeking
relief from the mandatory purchase
requirement will need to file an
application pursuant to section
210(m)(3) and § 292.310 of the
Commission’s regulations with the
Commission and make the showings
required by section 210(m)(1)(B)(ii) in
order to be relieved of the PURPA
purchase obligation. The presumption
that QFs 20 MWs or below do not have
nondiscriminatory access to markets
will apply.
F. Southwest Power Pool
1. NOPR
159. In the NOPR, the Commission
did not make a preliminary finding that
the region operated by the SPP meets
the requirements of PURPA section
70 NOPR
Sfmt 4700
64363
E:\FR\FM\01NOR2.SGM
at P 16.
01NOR2
64364
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
210(m)(1). The Commission did
recognize that the SPP is a Commissionapproved RTO, but that the
requirements of section 210(m)(1)(A)
have not been satisfied because the SPP
does not operate a day-ahead market.
The Commission noted that any utility
within the SPP footprint may file an
application with the Commission to
seek relief from the mandatory purchase
requirement pursuant to sections
210(m)(1)(B) or (C).
sroberts on PROD1PC70 with RULES
2. Comments
160. OG&E requests the Commission
find that utilities located in the SPP
satisfy section 210(m)(1)(A). OG&E
notes that the SPP filed revisions to its
OATT to implement a real-time
imbalance market (EIS Market). The EIS
Market will enable market participants
to undertake both day-ahead and realtime transactions.
161. OG&E and AEP also request the
Commission find that SPP utilities
satisfy section 210(m)(1)(B). The SPP is
a Commission-approved RTO and the
SPP OATT affords all customers with
nondiscriminatory treatment and
complies with all currently-effective
Commission policies and regulations as
they apply to the development of an
OATT. Therefore, OG&E and AEP ask
the Commission to find that the SPP
OATT satisfies the criteria of section
210(m)(1)(B)(i). OG&E states that section
210(m)(1)(B)(ii) is satisfied because load
serving entities in SPP actively solicit
power supplies using competitive
bidding procedures. OG&E notes that
the Oklahoma Corporation Commission
requires electric public utilities
providing retail service in Oklahoma to
procure long-term electric generation
through competitive bidding. AEP notes
that Louisiana established competitive
bidding rules that require a utility to
follow a formal RFP process for the
acquisition of generation resources and
for purchases of capacity and/or energy
of more than one year in duration.
Based on these aspects, OG&E and AEP
argue that the SPP region satisfies
section 210(m)(1)(B).
162. Deere disagrees with OG&E and
AEP and argues that the SPP market has
not yet satisfied the criteria for relief
from the PURPA mandatory purchase
requirement. Deere notes that SPP’s EIS
Market implementation has been
delayed until at least October 2006, and
therefore, it has not been ‘‘road tested.’’
3. Commission Determination
163. Similar to the determination we
made for the CAISO, the Commission
will not make the findings required by
section 210(m)(1)(A) for termination
until there is a functioning ‘‘Day 2’’
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
market. The Commission, on September
26, 2006, acted on rehearing requests
concerning SPP’s proposed tariff
revisions to implement an imbalance
market,71 which will not be functional
until December 1, 2006, at the earliest.
Thus, it would be premature for the
Commission to make such a finding in
this rulemaking proceeding. Once SPP’s
market is operational, electric utilities
who are members of SPP may file,
individually or jointly, an application
for relief of the PURPA purchase
obligation pursuant to section 210(m)(3)
and section 292.310 of the
Commission’s regulations.
164. OG&E and AEP also request the
Commission to make a determination
that electric utilities operating in the
SPP satisfy section 210(m)(1)(B). These
commenters also request a finding that
the SPP OATT satisfies the
requirements of section 210(m)(1)(B)(i).
With regard to the latter request, section
210(m)(1)(B)(i) requires a QF to have
nondiscriminatory access to
transmission and interconnection
services that are provided by a
Commission-approved regional
transmission entity and administered
pursuant to an OATT that affords
nondiscriminatory treatment to all
customers. In the NOPR, the
Commission interpreted section
210(m)(1)(B)(i) to mean that QFs must
have access to transmission and
interconnection service pursuant to a
Commission-approved OATT and
interconnection rules provided by an
entity that is regional in scope.72 SPP
provides transmission and
interconnection service pursuant to a
Commission-approved OATT that has
been amended to incorporate the
interconnection requirements of Order
No. 2003. As noted above, SPP is a
Commission-approved RTO, and,
therefore, SPP satisfies the ‘‘regional
transmission entity’’ requirement of
section 210(m)(1)(B)(i). Accordingly, the
Commission finds that SPP meets the
criteria of section 210(m)(1)(B)(i). A
member electric utility of the SPP may
rely on this finding in its application to
be relieved of the obligation to enter
into new contracts to purchase QF
electric energy.
165. Turning our attention to whether
electric utilities operating in the SPP
market satisfy section 210(m)(1)(B), we
decline to make such a finding in this
rulemaking proceeding. As an initial
matter, the Commission does not have
the evidence of transactions, as required
by the statute, to make the requisite
71 Southwest Power Pool, Inc., 116 FERC ¶ 61,289
(September 26, 2006).
72 NOPR at P 16.
PO 00000
Frm 00024
Fmt 4701
Sfmt 4700
finding that QFs in the SPP market have
nondiscriminatory access to
‘‘competitive’’ wholesale markets that
provide a ‘‘meaningful opportunity’’ to
make sales to buyers other than the
electric utility to which the QFs are
interconnected.
166. Moreover, as discussed above,
the Commission will make
determinations on a case-by-case basis,
rather than generically, for utilities
seeking relief from the mandatory
purchase requirement pursuant to
sections 210(m)(1)(B) and (C).
Accordingly, OG&E, AEP, or any other
electric utility may file with the
Commission an application for relief
pursuant to section 210(m)(3) of PURPA
and § 292.310 of the Commission’s
regulations and make the showings
required by section 210(m)(1)(B)(ii) in
order to be relieved of the PURPA
purchase obligation. The rebuttable
presumption that QFs 20MW or below
do not have nondiscriminatory access to
markets will apply.
G. ERCOT
1. Comments
167. Reliant, TXU Energy, Power and
Wholesale Companies (TXU) and the
Public Utility Commission of Texas
(PUCT) request that the Commission
extend its preliminary finding regarding
approved RTO/ISOs to include ERCOT
through a generic finding under section
210(m)(1)(C) of section 210(m) rather
than requiring case-by-case review.
Direct Energy filed reply comments in
support of this request.
168. Reliant explains that, while the
ERCOT ISO does not meet all the
criteria under section 210(m)(1)(A), the
region is competitive in compliance
with Texas law under the Public Utility
Regulatory Act (PURA) and was
certified as an ISO by the Public
Utilities Commission of Texas. PURA
provided for the creation of a regional
independent organization to perform
key functions to facilitate wholesale and
retail competition similar to those the
Commission prescribed for RTOs in
Order No. 2000.
169. Reliant describes the features of
the ERCOT market without explicitly
suggesting that it meets the criteria of
section 210(m)(1)(A). Reliant notes that
ERCOT is independently administered.
While it does not administer a
centralized day-ahead market or forward
market, ERCOT has a real-time market
sufficient to support a robust marketbased day-ahead market for sales of
electricity. The ERCOT ISO supports the
scheduling of bilateral capacity and
energy contracts (both short- and longterm) by qualified scheduling entities
E:\FR\FM\01NOR2.SGM
01NOR2
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
sroberts on PROD1PC70 with RULES
and conducts day-ahead auctions for
ancillary services.
170. Reliant asserts that the ERCOT
region meets the criteria for electric
utility relief from the purchase
obligation under 210(m)(1)(C) because
access to a sufficiently competitive
market for QFs to sell their power
currently exists in ERCOT and has been
affirmed by the PUCT. Reliant contends
that this access parallels the
nondiscriminatory access to competitive
markets in Commission-approved RTOs
and ISOs. It believes that the PUCT’s
certification of ERCOT as a competitive
market and the ‘‘operational reality’’ of
a robust wholesale and retail market in
ERCOT further support this conclusion.
171. Reliant argues that the most
administratively efficient application of
section 210(m)(1) would be to extend
the Commission’s preliminary finding
regarding its approved RTOs or ISOs to
the ERCOT region through a generic
finding under section 210(m)(1)(C). This
would allow ERCOT entities to submit
ministerial applications under this
section and to have the application
treated as a compliance filing under
§ 292.310(a) of the proposed rule. It
would allow the Commission to avoid
the filing of separate applications from
electric utilities located in a region that
has robust wholesale and retail
competition. Reliant states that
extension of the Commission’s finding
is appropriately based on the
demonstrated competitive market
conditions existing in the ERCOT
region, in which QFs have the
opportunity to sell energy and capacity
to buyers other than the utilities to
which they are interconnected. TXU
supports Reliant’s positions for the same
reasons.
172. The PUCT adds that wholesale
competition has been in effect in
ERCOT under open-access rules
prescribed by the PUCT since 1996. It
states that, on January 1, 2002, retail
competition in the electric market began
for all customers of investor-owned
utilities in the ERCOT region. The PUCT
also states that, as of October 2004, there
were 85 retail electric providers
certified by the PUCT, with 55 of those
actively serving customers.
2. Commission Determination
173. The information Reliant provides
with regard to ERCOT supports a
finding that QFs have access to the
transmission and distribution systems
so that they have access to markets in
ERCOT; the information also supports a
finding that the markets in ERCOT
satisfy the criteria of section
210(m)(1)(C) in that they are of
comparable competitive quality as the
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
markets described in section
210(m)(1)(A).
174. The PUCT states that wholesale
competition has been in effect in
ERCOT under open-access rules
prescribed by the PUCT since 1996.
According to the PUCT, these open
access rules ensure access to the
transmission and distribution systems
for all buyers and sellers of electricity
on nondiscriminatory terms. PUCT
states that the ERCOT system is
administered independently of any
individual market participant. Utility
and non-utility sellers have
nondiscriminatory access to wholesale
transmission service. Scheduling
protocols afford non-discriminatory
access to all customers. In ERCOT, there
is no ‘‘native load preference,’’ and thus
QFs receive the same quality of access
to ERCOT markets as all other market
participants. In addition, ERCOT uses a
market-based congestion management
system. ERCOT’s zonal model uplifts
local congestion costs system-wide,
while directly assigning the cost of
relieving inter-zonal congestion. ERCOT
conducts auctions that allow market
participants to hedge their risk by
buying financial transmission rights on
commercially significant flowgates.
175. On January 1, 2002, retail
competition in the electric market began
for all customers of investor-owned
utilities (IOU) in the ERCOT region. As
of October 2004, there were 85 retail
electric providers (REPs) certified by the
PUCT. The PUCT states that with the
numerous REPs in the ERCOT marketplace QFs have ample opportunity,
equal to that of all other generators in
the marketplace, to competitively
procure contracts for the output of their
facilities.
176. According to the PUCT, QFs in
ERCOT have ample opportunity to sell
both firm and non-firm power. Power is
sold to REPs in the ERCOT market
primarily through bilateral contracts of
varying lengths of time. While ERCOT
operates a real-time balancing energy
market, bilateral transactions permit a
buyer and seller to come to mutually
agreed to terms with a greater degree of
price certainty than in the balancing
market and the majority of transactions
in ERCOT take place pursuant to
bilateral transactions.
177. In ERCOT, QFs have the
opportunity to sell in an organized
energy market. ERCOT’s balancing
energy market is an independently
administered, aution-based, real time
market and provides cogeneration QFs
an opportunity to sell in the electric
market while fulfilling contractual
obligations to provide steam to their
thermal hosts. QFs, as well as others,
PO 00000
Frm 00025
Fmt 4701
Sfmt 4700
64365
may use the balancing energy market to
sell energy in the real-time at the market
clearing price of energy. In addition,
ERCOT operates a day-ahead and realtime market for ancillary services.
ERCOT does not administer a
centralized day-ahead market for
energy, but Reliant submitted testimony
that ERCOT’s real-time market has been
sufficient to support a robust marketbased (as opposed to administrativelycreated) day-ahead market for sale of
electricity.
178. As part of its filing, Reliant
submitted the ERCOT protocols to
support its claim that QFs have
nondiscminatory access to markets that
are of equal competitive quality to
section 210(m)(1)(A) markets. These
protocols are not a FERC tariff. They are,
however, approved by the PUCT.73 In its
comments, the PUCT states that the
market that has developed in ERCOT is
sufficiently robust that QFs operating
within ERCOT now rely on the market
to make sales and no longer rely on the
PURPA purchase obligation to make
sales.
179. As noted above, Reliant, TXU
and the PUCT have asked that the
Commission make a generic finding that
QFs in ERCOT have nondiscriminatory
access to markets that satisfy section
210(m)(1)(C). No commenters have
opposed this request. Based on our
review of the ERCOT protocols, the
support of the PUCT for termination of
the purchase obligation in ERCOT, and
the lack of opposition to our making a
generic finding, the Commission finds
that: (1) there is a rebuttable
presumption that QFs larger than 20
MW operating in ERCOT have
nondiscriminatory access to markets,74
and (2) the markets in ERCOT satisfy the
criteria of section 210(m)(1)(C) in that
they are markets of comparative
73 Texas State law requires states: ‘‘The
commission shall ensure that an electric utility or
transmission and distribution utility provides
nondiscriminatory access to wholesale transmission
service for qualifying facilities, exempt wholesale
generators, power marketers, power generation
companies, retail electric providers, and other
utilities or transmission and distribution utilities.’’
Public Utility Regulatory Act, TEX. UTIL. CODE
ANN. 35.0004 (PURA).
74 QFs may rebut this presumption by making a
demonstration by making a demonstration that: (i)
The QF has certain operational characteristics that
effectively prevent the QF’s participation in a
market; or (ii) a QF lacks access to markets due to
transmission constraints. An existing QF can show
that it is located in an area where persistent
transmission constraints in effect cause the QF to
have neither physical nor financial access to
markets outside a persistently congested area and
there is not a sufficient opportunity to redispatch
around the constraint or to sell the QF output or
capacity within the area on a short-term and/or
long-term basis because of the constraint.
E:\FR\FM\01NOR2.SGM
01NOR2
64366
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
competitive quality to markets
described in section 210(m)(1)(A).
180. Electric utilities operating within
ERCOT may make a filing to be relieved
of the purchase obligation pursuant to
section 292.310 of the regulations. The
rebuttable presumption that QFs 20 MW
or smaller lack nondiscriminatory
access shall be applicable to QFs in
ERCOT. Electric utilities may rebut that
presumption on the same grounds as
electric utilities in other markets rebut
the presumption.
H. Section 210(m)(2)—Revised Purchase
and Sale Obligation for New
Cogeneration Facilities
181. Section 210(m)(2)(A) reads:
REVISED PURCHASE AND SALE
OBLIGATIONS FOR NEW FACILITIES—(A)
After the date of enactment of this
subsection, no electric utility shall be
required pursuant to this section to enter into
a new contract or obligation to purchase from
or sell electric energy to a facility that is not
an existing qualifying cogeneration facility
unless the facility meets the criteria for
qualifying cogeneration facilities established
by the Commission pursuant to the
rulemaking required by subsection (n).
182. In the NOPR the Commission
stated that this provision reinforces the
requirement that new qualifying
cogeneration facilities must satisfy the
section 210(n) criteria for new
qualifying cogeneration facilities. The
Commission proposed to include this
language in § 292.309(d) of the proposed
regulations. There were no comments
objecting to this proposal, and the
Commission will adopt the NOPR’s
proposal. The language proposed by the
Commission is adopted in this Final
Rule as § 292.309(h) of the
Commission’s regulations.
183. Section 210(m)(1)(B) defines the
term ‘‘existing qualifying cogeneration
facility.’’ The Commission proposed a
definition of ‘‘existing qualifying
cogeneration’’ in § 292.309(b)(1) of the
proposed regulations. There were no
comments objecting to the proposal. The
proposed language is adopted in this
Final Rule as § 292.309(i).
I. Section 210(m)(3)—Commission
Review
1. Sufficient Notice
sroberts on PROD1PC70 with RULES
a. NOPR
184. Section 210(m)(3) states, in
relevant part, that ‘‘after notice,
including sufficient notice to potentially
affected [QFs], and an opportunity for
comment, the Commission shall make a
final determination within 90 days of
such application regarding whether the
conditions set forth in subparagraph (A),
(B), or (C) of paragraph (1) have been
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
met.’’ 75 Prior to the issuance of the
NOPR, the Commission dealt with two
section 210(m)(3) applications.76 In
Alliant, the Commission explained its
interpretation and application of
‘‘notice, including sufficient notice to
potentially affected [QFs].’’ The
Commission clarified that an applicant
would be required to identify all
potentially affected QFs in any section
210(m)(3) application. The Commission
also listed five categories of facilities
that would constitute ‘‘all potentially
affected QFs.’’ In the NOPR, the
Commission proposed to incorporate
this interpretation of ‘‘sufficient notice’’
and ‘‘all potentially affected QFs’’ in
new § 292.310(b) and (c) of the
Commission’s regulation.
b. Comments
185. PSNM is concerned with
requiring notice by applicants seeking
relief from the purchase obligation to
developers of facilities that have
pending state avoided cost proceedings
and any other QFs that the applicant
reasonably believes to be affected by its
petition. Specifically, it states that the
applicant seeking relief may not
necessarily be aware of all of the entities
falling within these classifications.
PSNM recommends that the
Commission revise the proposed
§ 292.310(c)(4) to state: ‘‘developers of
facilities that have pending state
avoided cost proceedings involving the
applicant.’’
186. SCE is concerned with proposed
§ 292.310(b), (c)(2) and (c)(5). It states
that these categories may capture too
broad a category of entities and thus
lead to needless debates over the scope
of notice provided. It states that in any
case uncertified QFs and certified QFs
not in the service territory of the
applicant, as well as all other interested
parties, will receive sufficient notice
through the Federal Register notice
process. SCE argues that the relevant
statute requires sufficient notice, not
actual notice.
c. Commission Determination
187. The Commission will adopt the
NOPR’s proposal to incorporate its
interpretation of ‘‘sufficient notice’’ and
‘‘all potentially affected QFs’’ as
described in Alliant with one
modification. PSNM points out that an
applicant may not be aware of state
avoided cost proceedings that do not
involve the applicant and recommends
adding ‘‘involving the applicant’’ to
75 16
U.S.C. 824a–3(m)(3) (emphasis added).
Alliant Energy Corporate Services, Inc., 113
FERC ¶ 61,024 (2005) (Alliant); Montana-Dakota
Utilities Co., 113 FERC ¶ 61,045 (2005) (MontanaDakota).
76 See
PO 00000
Frm 00026
Fmt 4701
Sfmt 4700
proposed § 292.310(c)(4). We agree that
an applicant would not necessarily
know about QF developers that have
initiated state avoided cost proceedings
that do not involve the applicant. Nor
did we intend for applicants in this
situation to identify such QF
developers. We find PSNM’s proposed
revision adds clarity to § 292.310(c)(4)
and it is consistent with the
Commission’s interpretation of ‘‘all
potentially affected QFs.’’ Accordingly,
we will modify § 292.310(c)(4) to state:
‘‘(4) The developers of facilities that
have pending state avoided cost
proceedings involving the applicant;
and’’.
188. We disagree with SCE’s notion
that ‘‘all potentially affected QFs’’ will
receive sufficient notice through the
Federal Register notice process. While
the statutory language does not
explicitly state that the ‘‘notice,
including sufficient notice’’ shall be
actual notice, the Commission
nonetheless believes its statutory
requirement is best met by providing all
potentially affected QFs, many of which
are small entities that do not regularly
read the Federal Register, with actual
notice.
2. Filing Fee
a. NOPR
189. Section 210(m)(3) states, in
relevant part, that any electric utility
may file an application for relief from
the mandatory purchase requirement. In
the NOPR, the Commission proposed
that utilities seeking relief from the
mandatory purchase requirement would
need to file an application pursuant to
section 210(m)(3).
b. Comments
190. SCE seeks confirmation that an
application filed pursuant to section
210(m)(3) is not subject to Rule 207.77
SCE argues that the statute indicates
that the filing is an ‘‘application’’ and
thus should be subject to Rule 204,78
which does not require the payment of
a fee.
c. Commission Determination
191. SCE is the only commenter to
seek clarification on whether or not a
filing fee is associated with a section
210(m)(3) application. We find that no
filing fee shall apply to section
210(m)(3) applications.
J. Section 210(m)(4)—Reinstatement of
Obligation to Purchase
192. In the NOPR, the Commission
proposed § 292.311 to the Commission’s
77 18
78 18
E:\FR\FM\01NOR2.SGM
CFR 385.207.
CFR 385.204.
01NOR2
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
regulations which is identical to
statutory language of section 210(m)(4).
The Commission viewed section
210(m)(4) as an opportunity for a QF, a
state agency, or any affected person to
seek to reinstate the purchase obligation
should there be a material change in the
circumstances under which the
Commission granted relief. The
Commission noted that the applicant
bears the burden to ‘‘set forth the factual
basis’’ upon which the application is
based. The Commission further stated
that the requirement for a ‘‘factual
basis’’ indicates that allegations of a
change in the conditions upon which
relief was granted must be supported
with evidence. The Commission
proposed to consider these applications
on a case-by-case basis.79
193. No adverse comments were filed
in response to the Commission’s
proposal. Therefore, the Commission
will adopt § 292.311 to the
Commission’s regulations, as proposed.
K. Section 210(m)(5)—Obligation to Sell
1. NOPR
194. Section 210(m)(5) of PURPA
removes the requirement that an electric
utility sell electric energy to any QF if
the Commission finds that: ‘‘competing
retail electric suppliers are willing and
able to sell and deliver electric energy
to the qualifying cogeneration facility or
qualifying small power production
facility; and the electric utility is not
required by State law to sell electric
energy in its service territory.’’ In the
NOPR, the Commission proposed to
incorporate the statutory language into
its regulations.
sroberts on PROD1PC70 with RULES
2. Comments
195. ACC, American Iron and Steel
Institute, ELCON and Midwest ISO
Transmission Customers argue that by
simply importing into its regulations the
statutory standard in section 210(m)(5),
the Commission provides no assurance
that it will continue to protect the rights
of QFs to receive standby and backup
power at just, reasonable, and
nondiscriminatory rates. They argue
that no such finding can be made unless
the Commission conducts an
investigation to assure itself that there is
sufficient competition among suppliers
that market power will not be exercised
in the sale of power. For instance,
ELCON and American Forest & Paper
suggest that the Commission require
79 In the NOPR, the Commission also stated that,
consistent with our interpretation of ‘‘notice’’ under
section 210(m)(3), the Commission will require an
applicant to identify all potentially affected utilities
in the application so that the Commission will be
able to meet its statutory requirement to provide
sufficient notice and an opportunity for comment.
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
QFs have available at least two
competing suppliers who are not
affiliated with the utility before
relieving the utility of its sales
obligations under section 210(m)(5).
They assert that this is required by the
statutory language referring to
‘‘competing retail electric providers’’ in
the plural. Moreover, the Coalition of
CIBO argue that the utility be required
to demonstrate that all of the services
are competitively available.
196. In addition, CCC, EPSA, Florida
Industrial, Energy Consumers, Solid
Waste Authority request that the
Commission clarify that lifting of the
PURPA obligation to purchase QF
electricity for a particular utility does
not relieve such utility of its obligation
to sell supplemental, backup, standby
and maintenance power to the QF at
fair, reasonable and nondiscriminatory
rates.
197. Also, the CCC argues that the
statute requires that the competing
supplier must be able to ‘‘deliver’’ as
well as ‘‘sell’’ the backup and standby
power and that the Commission must
make certain that the utility cannot use
its monopoly over retail delivery (i.e.,
distribution) service to impede the
development of QF projects.
198. Further, the CCC states that the
Commission should recognize that in
addition to a showing of an alternative
retail supplier of electricity, the statute
requires a second showing that the
utility no longer has any state law
obligation to serve retail customers in its
service territory. ELCON and American
Forest & Paper add that the Commission
should interpret this second prong to
require any utility that has an obligation
to provide Standard Offer or Default
service is ‘‘required by state law to sell
electric energy in its service territory.’’
They state that typically the state has
imposed such obligations where
necessary to achieve just and reasonable
rates or adequate, reliable service.
ELCON and American Forest & Paper
state that QFs should not be deprived of
any benefit that the state has determined
to be appropriate for retail customers.
199. In response to the arguments for
the Commission to retain a utility
obligation to supply backup power at
just and reasonable rates, EEI argues that
as backup power is a retail electric
service, it is beyond the Commission’s
jurisdiction to determine the justness
and reasonableness of such retail rates.
It argues that the most the Commission
can find, as the statute makes clear, is
that competing retail suppliers are
willing and able to sell to the QF, and
that there is no applicable state
obligation to serve.
PO 00000
Frm 00027
Fmt 4701
Sfmt 4700
64367
3. Commission Determination
200. We clarify that lifting of the
PURPA obligation to purchase QF
electricity for a particular utility does
not relieve such utility of its obligation
to sell supplemental, backup, standby
and maintenance power to the QF. Any
finding under section 210(m)(5) which
would relieve the utility from selling to
a QF would be made under a separate
standard and in a separate proceeding
pursuant to § 292.312 of the
Commission’s regulations. We agree,
with EEI, however, that it is beyond the
Commission’s jurisdiction to determine
the justness and reasonableness of retail
rates.
201. Also, we agree with ELCON and
American Forest & Paper that the
language in section 210(m)(5),
‘‘competing retail electric providers,’’
requires that QFs have available at least
two competing suppliers who are not
affiliated with the utility before
relieving the utility of its sales
obligations under section 210(m)(5). We
emphasize that during a section
210(m)(5) proceeding, the Commission
will strictly interpret the statutory
language. We note that the
Commission’s regulations provide that a
utility must interconnect with a QF, and
nothing in section 210(m) of PURPA
terminates that obligation.
202. As to the CCC’s argument that
section 210(m)(5) has an additional state
law prong that has to be met, we agree.
Whether a utility that has an obligation
to provide Standard Offer or Default
service is ‘‘required by state law to sell
electric energy in its service territory’’ is
an issue that invokes consideration of
particular state laws or state regulatory
authority actions. Accordingly, the
Commission believes that the issue is
more appropriately addressed on a caseby-case basis in proceedings under
§ 292.312 of the Commission’s
regulations rather than generically in
this rulemaking.
L. Section 210(m)(6)—No Effect on
Existing Rights and Remedies
1. NOPR
203. Section 210(m)(6) protects the
right and remedies under a contract or
obligation in effect or pending approval
before the state regulatory authority. In
the NOPR, the Commission clarified
that the protections provided for in
section 210(m)(6) are triggered
regardless of the stage of construction of
a facility that may be the subject of the
contract or obligation. The Commission
proposed to adopt the language of the
statute and solicited comments on
whether further or different language
and/or clarifications other than those
E:\FR\FM\01NOR2.SGM
01NOR2
64368
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
sroberts on PROD1PC70 with RULES
proposed should be incorporated into
our regulations.
2. Comments
204. Most of the comments received
regarding the Commission’s
interpretation of section 210(m)(6) were
focused on the terms ‘‘contract’’ and
‘‘obligation.’’ EEI and PG&E argue that
the terms ‘‘contract’’ and ‘‘obligation’’
are synonymous and that an
‘‘obligation’’ within the meaning of
PURPA section 210(m)(6) thus refers to
a specific legal arrangement between
specific parties that establishes all the
relevant and material rates, terms and
conditions under which power will be
bought and sold. They contend that
‘‘obligation’’ must provide the same
level of certainty as a contract, even
though a contract per se may not
actually be formed until regulatory
approval is obtained. They further argue
that the only obligations that were
preserved under the savings clause were
those obligations that (1) contain the
mutual commitments of specific buyers
and sellers of QF-generated electricity;
(2) define all the relevant and material
rates, terms and conditions of the sales;
and (3) were in effect or pending
regulatory approval on August 8, 2005.
205. SCE supports EEI and argues that
‘‘obligation’’ should refer only to mutual
arrangements that were sufficiently
developed to include all relevant terms
and mutual commitments of the parties
and were in effect, or awaiting state
commission approval, as of August 8,
2005.
206. Midwest Renewable Energy
Products argues that the Commission
should clarify that any QF that was
certified under 18 CFR 292.206 and
made a filing with the relevant state
regulatory authority before August 8,
2005 (to implement the mandatory
purchase requirement) falls under the
protection of the savings clause in
section 210(m)(6), as having an
‘‘obligation’’ in effect as of August 8,
2005.
207. Deere argues that EEI and SCE
ignore that there can be non-contractual
legally enforceable obligations, created
pursuant to a state’s PURPA
implementing scheme, which do not
necessarily involve a single writing
completely containing all material
terms. Deere also argues that they ignore
the new act’s express mention of
‘‘contracts’’ separate from ‘‘obligations,’’
using the disjunctive ‘‘or.’’ It states that
equating ‘‘obligations’’ to contracts
would make it superfluous, contrary to
the rules of statutory construction.
Deere also states that Congress
recognized that PURPA’s purchase
obligation is effectuated not only
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
through contracts, but through
obligations created by non-contractual
mechanisms, such as a state regulatory
process.
208. ELCON and American Forest &
Paper state that the Commission should
emphasize that even where mandatory
purchase requirements are terminated as
to new contracts, existing contracts and
obligations may not be reopened.
3. Commission Determination
209. The Commission will adopt the
statutory language of section 210(m)(6)
into its regulations. Based on the
comments received, it is evident that the
term ‘‘obligation’’ as it is used in section
210(m)(6) and section 210(m)(1) needs
to be clarified. Section 210(m)(6) reads,
in relevant part, that ‘‘Nothing in this
subsection affects the rights and
remedies of any party under any
contract or obligation, in effect or
pending approval before the appropriate
State regulatory authority * * *.’’ 80
Section 210(m)(1) states, in relevant
part, that ‘‘no electric utility shall be
required to enter into a new contract or
obligation to purchase electric energy
* * *.’’ 81 Because the term
‘‘obligation’’ appears in two distinct
subsections of amended section 210(m),
we believe it necessary to clarify how
the Commission will interpret the term
‘‘obligation.’’
210. The Commission has previously
addressed the meaning of section
210(m)(6) in Midwest Renewable Energy
Projects, LLC.82 In Midwest Renewable,
we rejected the notion offered here by
EEI and PG&E that ‘‘contract’’ and
‘‘obligation’’ are synonymous terms. We
stated that such an interpretation would
render the term ‘‘obligation’’
superfluous because then section
210(m)(6) would only apply to existing
contracts. Had Congress intended
section 210(m)(6) to apply to only
existing contracts, it would not have
included the term ‘‘obligation.’’ Thus,
we found Congress intended there to be
a distinction between ‘‘contract’’ and
‘‘obligation.’’
211. In Midwest Renewable, we also
disagreed with the theory offered by EEI
and PG&E in this proceeding that an
‘‘obligation’’ within the meaning of
PURPA section 210(m)(6) refers to a
specific legal arrangement between
specific parties that establishes all the
relevant and material rates, terms and
conditions under which power will be
bought and sold. As we stated in
Midwest Renewable:
80 16
U.S.C. 824a–3(m)(3) (emphasis added).
U.S.C. 824a–3(m)(6) (emphasis added).
82 Midwest Renewable Energy Projects, LLC, 116
FERC ¶ 61,017 (2006) (Midwest Renewable).
81 16
PO 00000
Frm 00028
Fmt 4701
Sfmt 4700
While there appears to be some ambiguity
surrounding the term ‘‘obligation’’ in
210(m)(6), we find that the reading favored
by protestors would eliminate the term ‘‘or
pending approval’’ from the statutory
language, and would be contrary to the wellestablished rule of statutory construction that
every clause and word of a statute be given
effect and that no clause or word be
interpreted so as to render it superfluous,
redundant, void or insignificant. To the
contrary, we find the phrase ‘‘or pending
approval’’ to be quite significant, as it
ensures that contracts or obligations that had
not yet been entered into but were being
pursued in the context of the state
commission proceedings that were pending
on the date of enactment of EPAct 2005 will
fall within savings clause.83
212. When a utility refuses to enter
into a contract with a QF and the QF
seeks state regulatory authority help to
enforce its PURPA regulations, a noncontractual legally enforceable
obligation may be created pursuant to
the state’s implementation of PURPA.
Such obligations do not necessarily
involve a single writing completely
containing all material terms. How QFs
initiate the PURPA process varies from
state to state. Thus, to narrowly define
‘‘obligation’’ to encompasses only a
specific legal arrangement with all the
relevant and material rates, terms and
conditions established may be at odds
with a state’s implementation of
PURPA. Accordingly, the Commission
views the term ‘‘obligation’’ as a ‘‘legally
enforceable obligation’’ which is
established through a state’s
implementation of PURPA. A QF that
had initiated, prior to August 8, 2005, a
state PURPA proceeding that may result
in a contract or legally enforceable
obligation would be considered to have
triggered an ‘‘obligation’’ with the
electric utility regarding section
210(m)(6).
213. With regard to section 210(m)(1),
‘‘obligation’’ will be viewed as a ‘‘legally
enforceable obligation’’ and a QF that
has initiated a state’s PURPA
proceeding that may result in a legally
enforceable contract or obligation prior
to the applicable electric utility filing its
petition for relief pursuant to § 292.310
of the Commission’s regulations will be
considered to have triggered an
‘‘obligation’’ with the electric utility.
Whether or not the utility’s date of filing
a petition for relief pursuant to
§ 292.310 of the Commission’s
regulations becomes the end date for the
mandatory purchase requirement
depends on whether the Commission
makes a final determination that the
criteria for granting relief have been
satisfied, and the Commission
83 Midwest
E:\FR\FM\01NOR2.SGM
Renewable at P 14.
01NOR2
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
terminates the mandatory purchase
requirement.
M. Section 210(m)(7)—Recovery of Costs
1. NOPR
214. In the NOPR the Commission
stated that it did not believe that
regulations are necessary at this time to
ensure that an electric utility that
purchases electric energy or capacity
from a QF recovers all prudently
incurred costs associated with the
purchase as described in section
210(m)(7). Nonetheless, the Commission
requested comments on whether there is
a need for the Commission to consider
such a regulation.
2. Comments
215. EEI, Allegheny, Alliant,
Montana-Dakota, PSNM and TNMP
state that the Commission should adopt
the statutory language in section
210(m)(7) into its regulations and
provide for case-by-case relief where
required. Central Vermont and Progress
Energy argue that the Commission
should establish wholesale and retail
riders to permit consistent, complete
and timely recovery of the utility’s
prudently-incurred QF purchase costs.
They state that the states and the
Commission often use different
methodologies for allocating costs
between the jurisdictions and the fact
that utilities do not traditionally have
general rate cases before the
Commission and the state commissions
every year. Therefore, when a QF
purchase is made in a year without a
general rate case at wholesale and retail,
those costs are not recovered via the
utility’s retail or wholesale rates.
3. Commission Determination
216. We adopt our proposal in the
NOPR. We do not find Central Vermont
and Progress Energy’s argument
persuasive. No evidence has been
presented that utilities will not be able
to recover costs associated with
purchases of electric energy or capacity
from a QF. Until such time, we are
reluctant to review an issue that should
be handled by the states in the first
instance. Therefore, we see no reason to
act now.
N. Other Issues
sroberts on PROD1PC70 with RULES
1. Contract Termination
a. NOPR
217. In the NOPR, the Commission
proposed to find that when a contract
terminates by its own accord, an electric
utility is not compelled to enter into a
new, successor contract with the QF if
the Commission has made a finding that
section 210(m)(1) has been satisfied.
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
The Commission further clarified that
QF status does not mean that an electric
utility has an ‘‘obligation’’ to purchase
from the QF in perpetuity, or that a QF
has the right to demand that the utility
purchase at avoided-cost rates in
perpetuity.
b. Comments
218. AEP, Deere, EEI, Entergy,
Occidental, PPL, and PSNM agree with
the NOPR’s position. AEP and
Occidental seek clarification or
expansion of the NOPR’s position. AEP
believes that ‘‘terminates by its own
accord’’ should also include the fact that
a contract may terminate mutually
between the parties and the electric
utility would not be compelled to enter
into another contract with that QF.
Occidental seeks clarification that the
proposed rules do not abrogate existing
contracts. As such, Occidental wants the
terms ‘‘terminates by its own accord’’
clarified to mean ‘‘expires by its own
terms.’’
c. Commission Determination
219. The Commission will adopt the
NOPR’s proposal regarding contract
termination in the context of finding
made pursuant to section 210(m)(1).
Two commenters, AEP and Occidental,
seek clarification of the phrase
‘‘terminates by its own accord.’’ AEP
points out that some contracts may be
terminated by mutual agreement
between the parties to the contract and
believes this type of contract
termination should also be included in
the Commission’s interpretation of
‘‘terminates by its own accord.’’ As long
as there is mutual agreement between a
QF and the electric utility to terminate
a contract, then the Commission finds
that the electric utility is not compelled
to enter into a new, successor contract
with the QF. Occidental requests
clarification that the NOPR does not
abrogate existing contracts and thus
wants the phrase ‘‘terminates by its own
accord’’ to be clarified to mean ‘‘expires
by its own terms.’’ We will also clarify
that the proposed rules adopted in this
Final Rule do not abrogate existing
contracts. Thus, under the Final Rule, a
QF contract is to remain in effect until
it terminates by mutual agreement or by
its own terms. We note, however, that
there may be contracts that contain
provisions that legislation, such as
EPAct 2005, or a Final Rule, such as this
one, trigger a termination clause in the
contract. To the extent that the parties
to a contract cannot agree whether a
termination clause has been triggered,
the issue will be best determined in an
individual case-specific proceeding in
PO 00000
Frm 00029
Fmt 4701
Sfmt 4700
64369
which the particulars of the contract can
be examined.
2. Effective Date of Contracts
a. NOPR
220. In the NOPR, the Commission
proposed to find that if a contract is
entered into after August 8, 2005, the
date of EPAct 2005 enactment, but
before the Commission has determined
that an electric utility is entitled to relief
from the mandatory purchase
requirement, the contract already
entered into will be treated as though it
was in effect on August 8, 2005 for
purposes of section 210(m)(1).
b. Comments
221. EEI, SCE, and PG&E disagree
with the Commission’s proposed
statutory construction. They argue that
once a utility is granted relief from the
PURPA purchase obligation, it should
not be required to honor any QF
contracts entered into after August 8,
2005. EEI, SCE, and PG&E argue that
this is the only determination that is
consistent with the clear intent and
express language of EPAct 2005, setting
August 8, 2005 as the end date of the
PURPA purchase obligation for utilities
in appropriate markets. They state that
this finding is also critical to preventing
a QF ‘‘gold rush,’’ i.e., QFs with expiring
contracts and/or new QFs may seek to
obtain a contract prior to the
Commission making the requisite
finding under section 210(m)(1) that
would relieve electric utilities like SCE
and PG&E from the mandatory purchase
requirement.
222. In the alternative, SCE and PG&E
state that if the Commission believes
that some contracts entered into after
August 8, 2005 must be honored, it
should adopt a rule that ensures that
electric utilities either: (1) are not
compelled by their state commissions to
enter into new contracts or extend
existing contracts after a petition for
relief is filed pursuant to section 210(m)
(PURPA Petition) until and unless the
PURPA Petition is denied; or (2) are not
required to honor contracts (or contract
extensions) entered into after a PURPA
Petition is filed, if the PURPA Petition
is subsequently granted. Under this
approach, contracts entered into
between August 8, 2005, and the filing
of a PURPA Petition would be honored,
but there would be no ‘‘gold rush’’
incentive created by the filing of the
utility’s PURPA Petition.
223. OG&E proposes that when a QF
attempts to establish a contract or
obligation after August 8, 2005, a utility
should have a reasonable opportunity to
demonstrate in a filing at the
E:\FR\FM\01NOR2.SGM
01NOR2
64370
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
Commission that the utility satisfies one
of the tests set forth in section
210(m)(1). A QF attempting to establish
a new obligation would be required to
provide the utility with formal notice.
Within 60 days of such notice, the
utility could file a PURPA Petition if it
believed the requisite market conditions
existed.
224. The CCC, and the APPA and
LPPC argue that the language is clear
that the ability of a utility to have its
mandatory purchase requirement
terminated is dependent on a
Commission determination that a
nondiscriminatory market satisfying the
statutory conditions exists. Until this
determination is made, the mandatory
purchase requirement remains in effect.
Deere adds that generation project
financing is long-term in nature, and
contractual and non-contractual legally
enforceable obligations are typically for
up to 20 years or longer so as to support
the long-term financing. The possibility
of a new QF contract or obligation being
negated, either ab initio or at the time
of a section 210(m) order, would leave
the remaining term of the financing
arrangements unsupported.
225. The CPUC states that should the
Commission adopt a rule as suggested
by SCE and PG&E, the rule should
affirm that state commissions retain
oversight of such terminable contracts to
ensure utilities afford equal treatment of
all QF contracts.
c. Commission Determination
226. Section 210(m)(1) states, in
relevant part, that, after August 8, 2005,
no electric utility shall be required to
enter into a new contract or obligation
to purchase electric energy from QFs if
the Commission finds that the QF has
nondiscriminatory access to either
section 210(m)(1)(A), (B), or (C). The
Commission’s interpretation of this
statutory language, as expressed in the
NOPR, was to treat new contracts or
obligations entered into after August 8,
2006, but before the Commission makes
a finding, as contracts or obligations in
effect prior to August 8, 2005. This
interpretation is consistent with the
Commission’s policy of not abrogating
contracts. Moreover, this is consistent
with the statute. Under the statue, the
purchase obligation is not terminated on
August 8, 2005, but only when the
Commission terminates the obligation,
after an electric utility filing. Until an
electric utility makes a filing pursuant
to the regulations, and the Commission
makes the required findings, the
purchase obligations remains in effect.
A different statutory interpretation, such
as the one advocated by EEI, would lead
to QF contracts being abrogated
potentially several years after execution.
We believe Congress did not intend for
this after-the-fact abrogation of contracts
to occur. Thus, we believe the NOPR’s
interpretation of this statutory language
is reasonable.
227. Nonetheless, some of EEI, SCE,
and PG&E’s arguments are compelling.
The Commission’s interpretation could
potentially lead to what these
commenters describe as a ‘‘gold rush’’ of
QFs seeking contracts once an electric
utility files for relief. Since the
Commission has 90 days in which to
render a finding, QFs would be able to
seek new contracts or obligations from
the electric utility upon learning of the
electric utility’s relief application until
the Commission makes a finding, and
the electric utility would be subject to
the mandatory purchase requirement
even if the Commission eventually
made a finding removing the mandatory
purchase requirement. We believe this
possibility would undermine and
circumvent the intent of section
210(m)(1).
228. In order to prevent the possibility
of a ‘‘gold rush,’’ the Commission will
modify its proposed interpretation.
Rather than treat new contracts and
obligations entered into after a PURPA
petition is filed but before the
Commission renders a finding as in
effect prior to August 8, 2005, the
Commission will temporarily suspend
an electric utility’s obligation to enter
into new contracts and obligations upon
the filing of its PURPA petition. When
an electric utility files its PURPA
petition, that electric utility will not be
obligated to enter into new contracts or
obligations with QFs as of the date its
PURPA petition is filed. If the
Commission finds that section 210(m)(1)
has been met, then the mandatory
purchase requirement for that electric
utility ends as of the date of the PURPA
petition. However, if the Commission
finds that the requirements of section
210(m)(1) have not been met, then the
Number of
respondents
sroberts on PROD1PC70 with RULES
Data collection FERC–556
§ 292.310 .........................................................................................................
§ 292.312 .........................................................................................................
84 See
44 U.S.C. 3507(d).
VerDate Aug<31>2005
17:43 Oct 31, 2006
85 5
Jkt 211001
PO 00000
electric utility’s obligation to enter into
new contracts or obligations is
reinstated as of the date of a
Commission order and a QF seeking a
new contract or obligation shall not be
denied. As such, a new contract or
obligation in this situation will be
treated as in effect prior to August 8,
2005. We believe this modification will
remove any ‘‘gold rush’’ incentive QFs
may have and preserves the integrity of
the mandatory purchase requirement
and contracts entered into between QFs
and electric utilities. We note, however,
that to the extent that a QF had a
contract or obligation pending approval
before an appropriate state regulatory
authority, or non-regulated utility on
August 8, 2005, a finding by that state
regulatory authority or non-regulated
utility that an electric utility has an
obligation to purchase or must enter
into a contract is binding.
229. The Commission recognizes that
there is a possibility of electric utilities
filing PURPA Petitions one right after
another in order to invoke the
temporary suspension period of the
mandatory purchase requirement.
Repeated section 210(m)(3) applications
by utilities intended will not be
tolerated and the Commission will take
appropriate action if utilities abuse the
process.
V. Information Collection Statement
The following collections of
information referenced in this Final
Rule have been submitted to the Office
of Management and Budget (OMB) for
review under section 3507(d) of the
Paperwork Reduction Act of 1995.84
OMB’s regulations require OMB to
approve certain information collection
requirements imposed by agency rule.85
Upon approval of a collection of
information, OMB will assign an OMB
control number and expiration date.
Respondents subject to the filing
requirements of this Final Rule will not
be penalized for failing to respond to
these collections of information unless
the collections of information display a
valid OMB control number or the
Commission had provided a
justification as why the control number
should be displayed.
In the NOPR the Commission
provided the following burden estimates
for complying with the rule as follows:
Number of
responses
230
230
Hours per
response
1
1
CFR 1320.11.
Frm 00030
Fmt 4701
Sfmt 4700
E:\FR\FM\01NOR2.SGM
01NOR2
Total annual
hours
2
2
460
460
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
Number of
respondents
Data collection FERC–556
Number of
responses
Hours per
response
64371
Total annual
hours
630
1
3
1,890
Totals ........................................................................................................
sroberts on PROD1PC70 with RULES
§ 292.313 .........................................................................................................
860
1
........................
2,810
Information Collection Costs: Because of
the regional differences and the various
staffing levels that have been involved
in preparing the documentation (legal,
technical and support) the Commission
is using the hourly rate of $150 to
estimate the costs for filing and other
administrative processes (reviewing
instructions, searching data sources,
completing and transmitting the
collection of information). The
estimated cost is anticipated to be
$421,500.
In response to the NOPR, the
Commission received no comments
concerning its estimates for burden and
costs and will use those estimates here
in the final rule. Where commenters
believed that a disproportionate amount
of burden had been placed on certain
entities in order to meet statutory
criteria, the Commission has addressed
this issue elsewhere in the rule and will
not repeat its responses here. The
actions taken in the Final Rule should
ameliorate their concerns of a
significant shift in the burden.
Title: FERC–556 ‘‘Small Power
Production and Cogeneration
Facilities’’.
Action: Proposed collections.
OMB Control Nos.: 1902–0075.
Respondents: Businesses or other for
profit.
Frequency of responses: Annually and
on occasion.
Necessity of the Information: The
Commission amends its regulations to
implement Section 210(m) of PURPA
which was enacted in Section 1253 of
the EPACT 2005 to implement a process
by which electric utilities may apply for
removal of the requirement that they
enter into new contracts or obligations
for the purchase of electric energy from
qualifying facilities (QFs) after August 8,
2005. The Final Rule is in response to
a Congressional mandate that addresses
complaints of electric utilities of having
to pay contractually high prices for
power they did not need. In adding
Section 210, Congress described a
standard of relief for the requirement
that electric utilities enter into new
obligations to purchase electric power
from QFs.
Interested persons may obtain
information on the reporting
requirements by contacting the
following: Federal Energy Regulatory
Commission, 888 First Street, NE.,
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
Washington, DC 20426 [Attention:
Michael Miller, Office of the Executive
Director, Phone (202)502–8415, fax:
(202)273–0873, e-mail:
michael.miller@ferc.gov] For submitting
comments concerning the collection of
information(s) and the associated
burden estimates, please send your
comments to the contact listed above
and to the Office of Management and
Budget, Office of Information and
Regulatory Affairs, Washington, DC
20503, Attention: Desk Officer for the
Federal Energy Regulatory Commission;
Phone: (202) 395–4650, fax: (202) 395–
7285.
VI. Environmental Analysis
230. The Commission is required to
prepare an Environmental Assessment
or an Environmental Impact Statement
for any action that may have a
significant adverse effect on the human
environment. The Commission has
categorically excluded certain actions
from this requirement as not having a
significant effect on the human
environment. As explained above, this
rule is clarifying in nature. It interprets
several amendments made to PURPA by
EPAct 2005, and clarifies the
applicability of these amendments to
electric utilities and QFs; it does not
substantially change the effect of the
legislation. Accordingly, no
environmental consideration is
necessary.
VII. Regulatory Flexibility Act
Certification
231. The Regulatory Flexibility Act of
1980 (RFA) 86 generally requires a
description and analysis of rules that
will have significant economic impact
on a substantial number of small entities
and where notice and comment
rulemaking is required. Certain rules are
exempt from notice and comment from
the RFA requirements; exempt rules
include interpretative rules, general
statements of policy, or rules of agency
organization procedure or practice.87
Interpretative rules ‘‘generally interpret
the intent expressed by Congress, where
an agency does not insert its own
judgments or interpretations in
implementing a rule and simply
86 5
87 5
PO 00000
U.S.C. 601–12.
U.S.C. 553(b)(A).
Frm 00031
Fmt 4701
Sfmt 4700
regurgitates statutory language.’’ 88 The
rule we are proposing in this docket is
mostly an interpretative rule and thus,
does not require a regulatory flexibility
analysis. The exception, however, is the
Commission’s establishment of a
rebuttable presumption that small QFs,
with a net capacity no greater than 20
MW, do not have nondiscriminatory
access to wholesale markets described
in section 210(m)(1)(A), (B), or (C).
Unless an electric utility seeking the
right to terminate its requirement to
purchase small QF power specifically
rebuts this small QF presumption, and
that electric utility’s request is granted
by the Commission, a small QF would
continue to be eligible to require the
electric utility to purchase its electric
energy. With this 20 MW rebuttable
presumption the Commission reduces
the burden, i.e., the cost of participating
in termination proceedings, of small
QFs to participate in the section
210(m)(3) proceedings. In fact, the
Commission is being generous in
allowing small QFs up to 20 MWs to
have a rebuttable presumption given
that the Small Business Administration
considers ‘‘small’’ to mean 4 MW or
less.
VIII. Document Availability
232. In addition to publishing the full
text of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the Internet through
FERC’s Home Page (https://www.ferc.gov)
and in FERC’s Public Reference Room
during normal business hours (8:30 a.m.
to 5 p.m. Eastern time) at 888 First
Street, NE., Room 2A, Washington DC
20426.
233. From FERC’s Home Page on the
Internet, this information is available on
eLibrary. The full text of this document
is available on eLibrary in PDF and
Microsoft Word format for viewing,
printing, and/or downloading. To access
this document in eLibrary, type the
docket number excluding the last three
digits of this document in the docket
number field.
234. User assistance is available for
eLibrary and the FERC’s Web site during
88 ‘‘How to Comply with the Regulatory
Flexibility Act: A Guide for Government Agencies’’,
Small Business Administration, Office of Advocacy,
P.5, May 2003.
E:\FR\FM\01NOR2.SGM
01NOR2
64372
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
normal business hours from our Help
line at (202) 502–8222 or the Public
Reference Room at (202) 502–8371 Press
0, TTY (202) 502–8659. E-mail the
Public Reference Room at
public.referenceroom@ferc.gov.
IX. Effective Date
235. These regulations are effective
January 2, 2007. The Commission has
determined, with the concurrence of the
Administrator of the Office of
Information and Regulatory Affairs of
OMB, that this rule is not a ‘‘major rule’’
as defined in section 251 of the Small
Business Regulatory Enforcement
Fairness Act of 1996. The Commission
will submit the Final Rule to both
houses of Congress and the General
Accounting Office.
List of Subjects in 18 CFR Part 292
Electric power, Electric power plants,
Electric utilities.
By the Commission.
Magalie R. Salas,
Secretary.
In consideration of the foregoing, the
Commission amends part 292, chapter I,
title 18, Code of Federal Regulations, as
follows.
I
PART 292—REGULATIONS UNDER
SECTIONS 201 AND 210 OF THE
PUBLIC UTILITY REGULATORY
POLICIES ACT OF 1978 WITH REGARD
TO SMALL POWER PRODUCTION AND
COGENERATION
1. The authority citation for part 292
continues to read as follows:
I
Authority: 16 U.S.C. 791a–825r, 2601–
2645; 31 U.S.C. 9701; 42 U.S.C. 7101–7352.
2. Section 292.303 is revised to read
as follows:
I
sroberts on PROD1PC70 with RULES
§ 292.303 Electric utility obligations under
this subpart.
(a) Obligation to purchase from
qualifying facilities. Each electric utility
shall purchase, in accordance with
§ 292.304, unless exempted by § 292.309
and § 292.310, any energy and capacity
which is made available from a
qualifying facility:
(1) Directly to the electric utility; or
(2) Indirectly to the electric utility in
accordance with paragraph (d) of this
section.
(b) Obligation to sell to qualifying
facilities. Each electric utility shall sell
to any qualifying facility, in accordance
with § 292.305, unless exempted by
§ 292.312, energy and capacity
requested by the qualifying facility.
(c) Obligation to interconnect. (1)
Subject to paragraph (c)(2) of this
section, any electric utility shall make
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
such interconnections with any
qualifying facility as may be necessary
to accomplish purchases or sales under
this subpart. The obligation to pay for
any interconnection shall be determined
in accordance with § 292.306.
(2) No electric utility is required to
interconnect with any qualifying facility
if, solely by reason of purchases or sales
over the interconnection, the electric
utility would become subject to
regulation as a public utility under part
II of the Federal Power Act.
(d) Transmission to other electric
utilities. If a qualifying facility agrees, an
electric utility which would otherwise
be obligated to purchase energy and
capacity from such qualifying facility
may transmit the energy or capacity to
any other electric utility. Any electric
utility to which such energy or capacity
is transmitted shall purchase such
energy or capacity under this subpart as
if the qualifying facility were supplying
energy or capacity directly to such
electric utility. The rate for purchase by
the electric utility to which such energy
is transmitted shall be adjusted up or
down to reflect line losses pursuant to
§ 292.304(e)(4) and shall not include
any charges for transmission.
(e) Parallel operation. Each electric
utility shall offer to operate in parallel
with a qualifying facility, provided that
the qualifying facility complies with any
applicable standards established in
accordance with § 292.308.
3. Sections 292.309 through 292.314
are added to read as follows:
I
Sec.
292.309 Termination of obligation to
purchase from qualifying facilities.
292.310 Procedures for utilities requesting
termination of obligation to purchase
from qualifying facilities.
292.311 Reinstatement of obligation to
purchase.
292.312 Termination of obligation to sell to
qualifying facilities.
292.313 Reinstatement of obligation to sell.
292.314 Existing rights and remedies.
§ 292.309 Termination of obligation to
purchase from qualifying facilities.
(a) After August 8, 2005, an electric
utility shall not be required, under this
part, to enter into a new contract or
obligation to purchase electric energy
from a qualifying cogeneration facility
or a qualifying small power production
facility if the Commission finds that the
qualifying cogeneration facility or
qualifying small power facility
production has nondiscriminatory
access to:
(1)(i) Independently administered,
auction-based day ahead and real time
wholesale markets for the sale of electric
energy; and
PO 00000
Frm 00032
Fmt 4701
Sfmt 4700
(ii) Wholesale markets for long-term
sales of capacity and electric energy; or
(2)(i) Transmission and
interconnection services that are
provided by a Commission-approved
regional transmission entity and
administered pursuant to an open
access transmission tariff that affords
nondiscriminatory treatment to all
customers; and
(ii) Competitive wholesale markets
that provide a meaningful opportunity
to sell capacity, including long-term and
short-term sales, and electric energy,
including long-term, short-term and
real-time sales, to buyers other than the
utility to which the qualifying facility is
interconnected. In determining whether
a meaningful opportunity to sell exists,
the Commission shall consider, among
other factors, evidence of transactions
within the relevant market; or
(3) Wholesale markets for the sale of
capacity and electric energy that are, at
a minimum, of comparable competitive
quality as markets described in
paragraphs (a)(1) and (a)(2) of this
section.
(b) For purposes of § 292.309(a), a
renewal of a contract that expires by its
own terms is a ‘‘new contract or
obligation’’ without a continuing
obligation to purchase under an expired
contract.
(c) For purposes of § 292.309(a)(1), (2)
and (3), with the exception of paragraph
(d) of this section, there is a rebuttable
presumption that a qualifying facility
has nondiscriminatory access to the
market if it is eligible for service under
a Commission-approved open access
transmission tariff or Commission-filed
reciprocity tariff, and Commissionapproved interconnection rules. If the
Commission determines that a market
meets the criteria of § 292.309(a)(1), (2)
or (3), and if a qualifying facility in the
relevant market is eligible for service
under a Commission-approved open
access transmission tariff or
Commission-filed reciprocity tariff, a
qualifying facility may seek to rebut the
presumption of access to the market by
demonstrating, inter alia, that it does
not have access to the market because of
operational characteristics or
transmission constraints.
(d)(1) For purposes of § 292.309(a)(1),
(2), and (3), there is a rebuttable
presumption that a qualifying facility
with a capacity at or below 20
megawatts does not have
nondiscriminatory access to the market.
(2) For purposes of implementing
paragraph (d)(1) of this section, the
Commission will not be bound by the
one-mile standard set forth in
§ 292.204(a)(2).
E:\FR\FM\01NOR2.SGM
01NOR2
sroberts on PROD1PC70 with RULES
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
(e) Midwest Independent
Transmission System Operator
(Midwest ISO), PJM Interconnection,
L.L.C. (PJM), ISO New England, Inc.
(ISO–NE), and New York Independent
System Operator (NYISO) qualify as
markets described in § 292.309(a)(1)(i)
and (ii), and there is a rebuttable
presumption that qualifying facilities
with a capacity greater than 20
megawatts have nondiscriminatory
access to those markets through
Commission-approved open access
transmission tariffs and interconnection
rules, and that electric utilities that are
members of such regional transmission
organizations or independent system
operators (RTO/ISOs) should be relieved
of the obligation to purchase electric
energy from the qualifying facilities. A
qualifying facility may seek to rebut this
presumption by demonstrating, inter
alia, that:
(1) The qualifying facility has certain
operational characteristics that
effectively prevent the qualifying
facility’s participation in a market; or
(2) The qualifying facility lacks access
to markets due to transmission
constraints. The qualifying facility may
show that it is located in an area where
persistent transmission constraints in
effect cause the qualifying facility not to
have access to markets outside a
persistently congested area to sell the
qualifying facility output or capacity.
(f) The Electric Reliability Council of
Texas (ERCOT) qualifies as a market
described in § 292.309(a)(3), and there is
a rebuttable presumption that qualifying
facilities with a capacity greater than 20
megawatts have nondiscriminatory
access to that market through Public
Utility Commission of Texas (PUCT)
approved open access protocols, and
that electric utilities that operate within
ERCOT should be relieved of the
obligation to purchase electric energy
from the qualifying facilities. A
qualifying facility may seek to rebut this
presumption by demonstrating, inter
alia, that:
(1) The qualifying facility has certain
operational characteristics that
effectively prevent the qualifying
facility’s participation in a market; or
(2) The qualifying facility lacks access
to markets due to transmission
constraints. The qualifying facility may
show that it is located in an area where
persistent transmission constraints in
effect cause the qualifying facility not to
have access to markets outside a
persistently congested area to sell the
qualifying facility output or
(g) The California Independent
System Operator and Southwest Power
Pool, Inc. satisfy the criteria of
§ 292.309(a)(2)(i).
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
(h) No electric utility shall be
required, under this part, to enter into
a new contract or obligation to purchase
from or sell electric energy to a facility
that is not an existing qualifying
cogeneration facility unless the facility
meets the criteria for new qualifying
cogeneration facilities established by the
Commission in § 292.205.
(i) For purposes of § 292.309(h), an
‘‘existing qualifying cogeneration
facility’’ is a facility that:
(1) Was a qualifying cogeneration
facility on or before August 8, 2005; or
(2) Had filed with the Commission a
notice of self-certification or selfrecertification, or an application for
Commission certification, under
§ 292.207 prior to February 2, 2006.
(j) For purposes of § 292.309(h), a
‘‘new qualifying cogeneration facility’’
is a facility that satisfies the criteria for
qualifying cogeneration facilities
pursuant to § 292.205.
§ 292.310 Procedures for utilities
requesting termination of obligation to
purchase from qualifying facilities.
(a) An electric utility may file an
application with the Commission for
relief from the mandatory purchase
requirement under § 292.303(a)
pursuant to this section on a service
territory-wide basis. Such application
shall set forth the factual basis upon
which relief is requested and describe
why the conditions set forth in
§ 292.309(a)(1), (2) or (3) have been met.
After notice, including sufficient notice
to potentially affected qualifying
cogeneration facilities and qualifying
small power production facilities, and
an opportunity for comment, the
Commission shall make a final
determination within 90 days of such
application regarding whether the
conditions set forth in § 292.309(a)(1),
(2) or (3) have been met.
(b) Sufficient notice shall mean that
an electric utility must identify with
names and addresses all potentially
affected qualifying facilities in an
application filed pursuant to paragraph
(a).
(c) All potentially affected qualifying
facilities shall include:
(1) Those qualifying facilities that
have existing power purchase contracts
with the applicant;
(2) Other qualifying facilities that sell
their output to the applicant or that
have pending self-certification or
Commission certification with the
Commission for qualifying facility status
whereby the applicant will be the
purchaser of the qualifying facility’s
output;
(3) Any developer of generating
facilities with whom the applicant has
PO 00000
Frm 00033
Fmt 4701
Sfmt 4700
64373
agreed to enter into power purchase
contracts, as of the date of the
application filed pursuant to this
section, or are in discussion, as of the
date of the application filed pursuant to
this section, with regard to power
purchase contacts;
(4) The developers of facilities that
have pending state avoided cost
proceedings, as of the date of the
application filed pursuant to this
section; and
(5) Any other qualifying facilities that
the applicant reasonably believes to be
affected by its application filed pursuant
to paragraph (a) of this section.
(d) The following information must be
filed with an application:
(1) Identify whether applicant seeks a
finding under the provisions of
§ 292.309(a)(1), (2), or (3).
(2) A narrative setting forth the factual
basis upon which relief is requested and
describing why the conditions set forth
in § 292.309(a)(1), (2), or (3) have been
met. Applicant should also state in its
application whether it is relying on the
findings or rebuttable presumptions
contained in § 292.309(e), (f) or (g). To
the extent applicant seeks relief from
the purchase obligation with respect to
a qualifying facility 20 megawatts or
smaller, and thus seeks to rebut the
presumption in § 292.309(d), applicant
must also set forth, and submit evidence
of, the factual basis supporting its
contention that the qualifying facility
has nondiscriminatory access to the
wholesale markets which are the basis
for the applicant’s filing.
(3) Studies, including the applicant’s
long-term transmission plan, conducted
by applicant, or the RTO, ISO or other
relevant entity, that show:
(i) Transmission constraints by path,
element or other level of comparable
detail that have occurred and/or are
known and expected to occur, and any
proposed mitigation including
transmission construction plans;
(ii) Levels of congestion, if available;
(iii) Relevant system impact studies
for the generation interconnections,
already completed;
(iv) Other information pertinent to
showing whether transfer capability is
available; and
(v) The appropriate link to applicant’s
OASIS, if any, from which a qualifying
facility may obtain applicant’s available
transmission capacity (ATC)
information.
(4) Describe the process, procedures
and practices that qualifying facilities
interconnected to the applicant’s system
must follow to arrange for the
transmission service to transfer power to
purchasers other than the applicant.
This description must include the
E:\FR\FM\01NOR2.SGM
01NOR2
64374
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
process, procedures and practices of all
distribution, transmission and regional
transmission facilities necessary for
qualifying facility access to the market.
(5) If qualifying facilities will be
required to execute new interconnection
agreements, or renegotiate existing
agreements so that they can effectuate
wholesale sales to third-party
purchasers, explain the requirements,
charges and the process to be followed.
Also, explain any differences in these
requirements as they apply to qualifying
facilities compared to other generators,
or to applicant-owned generation.
(6) Applicants seeking a Commission
finding pursuant to § 292.309(a)(2) or
(3), except those applicants located in
ERCOT, also must provide evidence of
competitive wholesale markets that
provide a meaningful opportunity to sell
capacity, including long-term and shortterm sales, and electric energy,
including long-term, short-term and
real-time sales, to buyers other than the
utility to which the qualifying facility is
interconnected. In demonstrating that a
meaningful opportunity to sell exists,
provide evidence of transactions within
the relevant market. Applicants must
include a list of known or potential
purchasers, e.g., jurisdictional and nonjurisdictional utilities as well as retail
energy service providers.
(7) Signature of authorized individual
evidencing the accuracy and
authenticity of information provided by
applicant.
(8) Person(s) to whom
communications regarding the filed
information may be addressed,
including name, title, telephone
number, and mailing address.
Commission finds that the conditions
set forth in § 292.309(a), (b), or (c) which
relieved the obligation to purchase, are
no longer met.
§ 292.312 Termination of obligation to sell
to qualifying facilities.
(a) Any electric utility may file an
application with the Commission for
relief from the mandatory obligation to
sell under this section on a service
territory-wide basis or a single
qualifying facility basis. Such
application shall set forth the factual
basis upon which relief is requested and
describe why the conditions set forth in
paragraphs (b)(1) and (b)(2) of this
section have been met. After notice,
including sufficient notice to potentially
affected qualifying facilities, and an
opportunity for comment, the
Commission shall make a final
determination within 90 days of such
application regarding whether the
conditions set forth in paragraphs (b)(1)
and (b)(2) of this section have been met.
(b) After August 8, 2005, an electric
utility shall not be required to enter into
a new contract or obligation to sell
electric energy to a qualifying small
power production facility, an existing
qualifying cogeneration qualifying
facility, or a new qualifying
cogeneration facility if the Commission
has found that;
(1) Competing retail electric suppliers
are willing and able to sell and deliver
electric energy to the qualifying
cogeneration facility or qualifying small
power production facility; and
(2) The electric utility is not required
by State law to sell electric energy in its
service territory.
sroberts on PROD1PC70 with RULES
§ 292.311 Reinstatement of obligation to
purchase.
§ 292.313
sell.
At any time after the Commission
makes a finding under §§ 292.309 and
292.310 relieving an electric utility of its
obligation to purchase electric energy, a
qualifying cogeneration facility, a
qualifying small power production
facility, a State agency, or any other
affected person may apply to the
Commission for an order reinstating the
electric utility’s obligation to purchase
electric energy under this section. Such
application shall set forth the factual
basis upon which the application is
based and describe why the conditions
set forth in § 292.309(a), (b) or (c) are no
longer met. After notice, including
sufficient notice to potentially affected
electric utilities, and opportunity for
comment, the Commission shall issue
an order within 90 days of such
application reinstating the electric
utility’s obligation to purchase electric
energy under this section if the
At any time after the Commission
makes a finding under § 292.312
relieving an electric utility of its
obligation to sell electric energy, a
qualifying cogeneration facility, a
qualifying small power production
facility, a State agency, or any other
affected person may apply to the
Commission for an order reinstating the
electric utility’s obligation to purchase
electric energy under this section. Such
application shall set forth the factual
basis upon which the application is
based and describe why the conditions
set forth in Paragraph (b)(1) and (b)(2) of
this section are no longer met. After
notice, including sufficient notice to
potentially affected utilities, and
opportunity for comment, the
Commission shall issue an order within
90 days of such application reinstating
the electric utility’s obligation to sell
electric energy under this section if the
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
PO 00000
Reinstatement of obligation to
Frm 00034
Fmt 4701
Sfmt 4700
Commission finds that the conditions
set forth in paragraphs (b)(1) and (b)(2)
of this section are no longer met.
§ 292.314
Existing rights and remedies.
Nothing in this section affects the
rights or remedies of any party under
any contract or obligation, in effect or
pending approval before the appropriate
State regulatory authority or nonregulated electric utility on or before
August 8, 2005, to purchase electric
energy or capacity from or to sell
electric energy or capacity to a
qualifying cogeneration facility or
qualifying small power production
facility under this Act (including the
right to recover costs of purchasing
electric energy or capacity).
Note: The following appendix will not be
published in the Code of Federal
Regulations.
Appendix A: List of Petitioners
Requesting Clarification or Submitting
Comments
AES Shady Point, LLC (AES Shady Point)
Albers, John D. (Mr. Albers)
Allegheny Power (Allegheny)
Alliant Energy Corporate Services, Inc.
(Alliant)
American Chemistry Council
American Electric Power Service Corporation
(AEP)
American Energy Company
American Forest and Paper Association
(American Forest & Paper)
American Iron and Steel Institute
American Petroleum Institute
American Public Power Association and
Large Public Power Council (APPA)
American Wind Energy Association (AWEA)
Caithness Energy, LLC (Caithness)
California Cogeneration Council (CCC)
California Independent System Operator
Corporation (CAISO)
Central Hudson Gas & Electric Corporation,
Consolidated Edison Company of New
York, Inc., LIPA, New York Power
Authority, New York State Electric & Gas
Corporation, Orange and Rockland
Utilities, Inc., and Rochester Gas and
Electric Corporation (New York
Transmission Owners)
Central Vermont Public Service Corporation
and Green Mountain Power Corporation
(Central Vermont)
Coalition of Midwest Transmission
Customers (Midwest Transmission
Customers)
Cogeneration Association of California and
Energy Producers and Users Coalition
(Cogeneration Association of California)
Cogeneration Coalition of Washington
Congressmen Boucher, Brown and Pickering
Consolidated Edison Company of New York,
Inc. (ConEd)
Constellation Energy Group, Inc.
(Constellation)
Council of Industrial Boiler Owners (CIBO)
Deere & Company (Deere)
Direct Energy Services, LLC (Direct Energy)
Dow Chemical Company (Dow)
E:\FR\FM\01NOR2.SGM
01NOR2
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 / Rules and Regulations
sroberts on PROD1PC70 with RULES
Edison Electric Institute (EEI)
Electricity Consumers Resource Council
(ELCON)
Electric Power Supply Association (EPSA)
Entergy Services, Inc. (Entergy)
Environmental Law and Policy Center
Exelon Corporation (Exelon)
The Fertilizer Institute
FirstEnergy Corp. (FirstEnergy)
Florida Industrial Cogeneration Association
(Florida Industrial Cogeneration)
Granite State Hydropower Association, Inc.
and Vermont Independent Power
Producers Association (Granite State)
Independent Energy Producers Association of
California (Independent Energy Producers)
Industrial Energy Consumers of America
(Industrial Energy Consumers)
Landfill Gas Coalition
Louisiana Energy Users Group (LEUG)
Midwest Renewable Energy Projects, LLC
(Midwest Renewable Energy Projects)
Missouri River Energy Services (Missouri
River)
Midwest Transmission Customers
Modesto Irrigation District (Modesto
Irrigation)
Montana-Dakota Utilities Co. (MontanaDakota)
National Grid USA (National Grid)
VerDate Aug<31>2005
17:43 Oct 31, 2006
Jkt 211001
National Petrochemical & Refiners
Association (NPRA)
National Rural Electric Cooperative
Association (NRECA)
Nelson Industrial Steam Company’s
Industrial Participants (NISCO)
New York Independent System Operator, Inc.
(NYISO)
NSTAR Electric & Gas Corporation (NSTAR)
Occidental Chemical Corporation
(Occidental)
Oklahoma Corporation Commission
Oklahoma Gas and Electric Company (OG&E)
Ottinger, Richard L. (Mr. Ottinger)
Pacific Gas and Electric Company (PG&E)
PacifiCorp
PJM Interconnection, LLC (PJM)
PJM Transmission Owners
PPL Electric Utilities Corporation (PPL)
Progress Energy, Inc. (Progress Energy)
Public Interest Organizations (PIOs) (Center
for Energy Efficiency & Renewable
Technologies, Delaware Division of the
Public Advocate, Environmental Law &
Policy Center, Interwest Energy Alliance,
Izaak Walton League of America, Natural
Resources Defense Council, Northwest
Energy Coalition, Office of the Ohio
Consumers’ Counsel, Pace Energy Project,
Project for Sustainable FERC Energy
PO 00000
Frm 00035
Fmt 4701
Sfmt 4700
64375
Policy, West Wind Wires, and Western
Resource Advocates)
Public Interest and Renewable Energy
Organizations
Public Power Council
Public Service Company of New Mexico
(PSNM) jointly with Texas-New Mexico
Power Company (TNP)
Public Utilities Commission of the State of
California (CPUC)
Public Utility Commission of Texas (PUCT)
Reliant Energy, Inc. (Reliant)
Senators Alexander, Carper and Collins
Solid Waste Authority of Palm Beach, Florida
(Solid Waste Authority)
Southeast Electricity Consumers Association
(SeECA)
Southern California Edison Company (SCE)
Swecker, Gregory (Mr. Swecker)
Transmission Agency of Northern California
(TANC)
TXU Energy, Power and Wholesale
Companies (TXU)
U.S. Combined Heat & Power Association
(USCHPA)
Utah Association of Energy Users (UAE)
Wisconsin Industrial Energy Group, Inc.
Xcel Energy Services Inc. (Xcel)
[FR Doc. 06–8928 Filed 10–31–06; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\01NOR2.SGM
01NOR2
Agencies
[Federal Register Volume 71, Number 211 (Wednesday, November 1, 2006)]
[Rules and Regulations]
[Pages 64342-64375]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 06-8928]
[[Page 64341]]
-----------------------------------------------------------------------
Part II
Department of Energy
-----------------------------------------------------------------------
Federal Energy Regulatory Commission
-----------------------------------------------------------------------
18 CFR Part 292
New PURPA Section 210(m) Regulations Applicable to Small Power
Production and Cogeneration Facilities; Final Rule
Federal Register / Vol. 71, No. 211 / Wednesday, November 1, 2006 /
Rules and Regulations
[[Page 64342]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
18 CFR Part 292
[Docket No. RM06-10-000; Order No. 688]
New PURPA Section 210(m) Regulations Applicable to Small Power
Production and Cogeneration Facilities
Issued October 20, 2006.
AGENCY: Federal Energy Regulatory Commission, DOE.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: The Federal Energy Regulatory Commission (Commission) is
amending its regulations governing small power production and
cogeneration in response to section 1253 of the Energy Policy Act of
2005 (EPAct 2005), which added section 210(m) to the Public Utility
Regulatory Policies Act of 1978 (PURPA).
DATES: Effective Date: The rule will become effective January 2, 2007.
FOR FURTHER INFORMATION CONTACT: Deborah Wyrick (Technical
Information), Office of Energy Markets and Reliability, Federal Energy
Regulatory Commission, 888 First Street, NE., Washington, DC 20426,
(202) 502-6113. Marka Shaw (Technical Information), Office of Energy
Markets and Reliability, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426, (202) 502-8641. Samuel
Higginbottom (Legal Information), Office of the General Counsel,
Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426, (202) 502-8561. Eric Winterbauer (Legal
Information), Office of the General Counsel, Federal Energy Regulatory
Commission, 888 First Street, NE., Washington, DC 20426, (202) 502-
8329.
SUPLEMENTARY INFORMATION:
Before Commissioners: Joseph T. Kelliher, Chairman; Suedeen G.
Kelly, Marc Spitzer, Philip D. Moeller, and Jon Wellinghoff.
I. Introduction
1. On August 8, 2005, the Energy Policy Act of 2005 (EPAct 2005)\1\
was signed into law. Section 1253(a) of EPAct 2005 adds section 210(m)
to the Public Utility Regulatory Policies Act of 1978 (PURPA)\2\ which
provides, among other things, for termination of the requirement that
an electric utility enter into a new contract or obligation to purchase
electric energy from qualifying cogeneration facilities and qualifying
small power production facilities (QFs) if the Federal Energy
Regulatory Commission (Commission) finds that the QF has
nondiscriminatory access to one of three categories of markets defined
in section 210(m)(1)(A), (B) or (C). Thus, to relieve an electric
utility of its mandatory purchase obligation under PURPA, the
Commission must identify which, if any, markets meet the criteria
contained in 210(m)(1)(A), (B) or (C), and, if such markets are
identified, it must determine whether QFs have nondiscriminatory access
to those markets.
---------------------------------------------------------------------------
\1\ Pub. L. 109-58, 1253, 119 Stat. 594 (2005).
\2\ 16 U.S.C. 824a-3 (2000).
---------------------------------------------------------------------------
2. On January 19, 2006, the Commission issued a notice of proposed
rulemaking (NOPR) proposing regulations to implement the provisions of
the new PURPA section 210(m) and proposing to terminate the requirement
that an electric utility enter into a new contract or obligation to
purchase electric energy from QFs if the electric utility is a member
of Midwest Independent Transmission System Operator, Inc. (Midwest
ISO), PJM Interconnection, L.L.C. (PJM), ISO New England, Inc. (ISO-
NE), or New York Independent System Operator (NYISO). After considering
industry comments on the NOPR, the Commission issues this Final Rule
amending the Commission's regulations to implement the requirements in
section 210(m). We believe the regulations adopted in the Final Rule
reflect Congress's intent to differentiate between three types of
market structures, each of which presents differing factors relevant to
our determination of whether QFs have access to a sufficiently
competitive market to support elimination of the purchase requirement.
Our Final Rule also recognizes the special circumstances faced by small
QFs and, accordingly, applies a different test for this class of QFs.
In addition to a presumption in favor of small QFs, the rule also
recognizes that some QFs, irrespective of size, may not have the
ability to sell in certain markets because of operational
characteristics or other constraints.
3. The Commission received extensive comments on its NOPR.\3\ At
one extreme are commenters who argue that the Commission may not
address the mandatory purchase requirement issues by rulemaking and
that competitive capacity and energy markets do not yet exist to
support a generic finding that QFs in the four regional transmission
organization/independent system operator (RTO/ISO) regions should lose
the right to require electric utilities to purchase their electric
output. At the other extreme are those who argue that the Commission,
with limited exceptions, should eliminate the mandatory purchase
requirement altogether.
---------------------------------------------------------------------------
\3\ Attached as Appendix A is a list of all commenters and the
abbreviations that are used throughout the order to refer to the
commenters.
---------------------------------------------------------------------------
4. We do not believe that either extreme reflects the letter or the
spirit of section 210(m). The QFs who advocate that we may not or
should not act at all by rulemaking fail to recognize that the
Commission has broad latitude to act by either rulemaking or
adjudication. Nowhere does section 210(m) preclude the Commission from
acting by rulemaking. Moreover, where, as here, recurring and common
issues of fact arise, acting by rulemaking is not only permissible, but
provides more effective notice to and opportunity for participation by
all affected parties. To some extent, generic findings about markets
are inevitable, either by rulemaking or in the first utility specific
filing concerning a specific market. Making generic findings by
rulemaking provides affected entities, including QFs, a better
opportunity to participate in the generic proceeding as well as the
individual proceedings that will follow. Finally, the substantive
arguments of these entities that underlie their procedural objections
fail to recognize that Congress, in enacting section 210(m), explicitly
recognized three different market structures and required the
Commission to respect the differences in those markets when making
determinations as to whether to rescind the purchase obligation. In
essence, they are rearguing the very debates that Congress settled in
adopting section 210(m).
5. We also do not agree with the position of utilities that
advocate we should terminate the purchase obligation in summary fashion
in this rulemaking. Although our action today respects the choice of
Congress in establishing different tests for different market
structures, we do not, in this rulemaking, terminate the purchase
obligation of any utility. In this respect, we modify our approach in
the NOPR. In contrast to the NOPR, in this Final Rule we establish only
rebuttable presumptions that the purchase obligation should be
eliminated with respect to certain QFs, not final determinations.
6. In sum, this Final Rule appropriately reflects Congressional
intent in enacting section 210(m). It does not, as some commenters
suggest, ignore the fact that Congress did not repeal PURPA section
210(a)'s directive
[[Page 64343]]
that the Commission prescribe, and from time to time revise, such rules
as it determines necessary to encourage cogeneration and small power
production. Rather, it recognizes the fundamental change which Congress
made to the statutory construct when it determined that ``no electric
utility shall be required * * * to purchase electric energy from'' a QF
if certain findings are made with respect to various markets. Our
action properly implements Congressional intent in the new section
210(m) that the three different market structures present different
considerations in determining whether to relieve utilities of the
purchase obligation. Our action also properly recognizes that smaller
QFs can face more significant challenges than larger QFs in accessing
competitive wholesale markets. Our action continues to support QF
development by ensuring that, where the requirements of section 210(m)
are met, QF development will, as determined by Congress, be stimulated
by market forces, and that where those requirements have not been met,
QF development will continue to be stimulated as it is today through
the mandatory purchase obligation. Finally, nothing in this Final Rule
affects any electric utility's resource adequacy obligations,
compliance with the Electric Reliability Organization's reliability
standards, prudent utility practice to build or purchase reliable power
at the most economical price, or resource portfolio obligations under
state law including obligations to purchase renewable energy.
II. Executive Summary
7. This Final Rule amends the Commission's regulations in part 292
\4\ (pertaining to electric utilities' requirement to purchase electric
energy from or sell electric energy to a QF) to implement section 1253
of the EPAct 2005. As relevant here, section 1253 added a new section
210(m) to PURPA, which:
---------------------------------------------------------------------------
\4\ 18 CFR part 292, subpart C, Arrangements Between Electric
Utilities and Qualifying Cogeneration and Small Power Production
Facilities Under section 210 of the Public Utility Regulatory
Policies Act of 1978.
---------------------------------------------------------------------------
A. Provides for the termination of the requirement that an electric
utility enter into new contracts or obligations to purchase electric
energy from a QF, after appropriate findings by the Commission;
B. Preserves existing contracts and obligations to purchase
electric energy or capacity from or to sell electric energy or capacity
to a QF;
C. Provides for the reinstatement of the requirement to purchase
electric energy from a QF, upon a showing that the conditions for
terminating the requirement are no longer met; and
D. Provides for the termination of the requirement that an electric
utility enter into new contracts to sell electric energy to QFs, after
appropriate findings by the Commission.
The Commission is amending its Part 292 regulations to address the
above section 210(m) provisions and also to provide a process for
applying for the reinstatement of the requirement to sell electric
energy to QFs upon a showing that the conditions for the removal of
that requirement are no longer met.
A. Termination of the Mandatory Purchase Requirement That an Electric
Utility Enter Into a New Contract or Obligation To Purchase Electric
Energy From QFs
8. This Final Rule promulgates regulations that set forth the
process by which electric utilities may apply to be relieved of the
requirement that they enter into new contracts or obligations for the
purchase of electric energy from QFs after August 8, 2005. New Sec.
292.309 of the Commission's regulations describes the findings that the
Commission must make to justify relieving an electric utility's
obligation to enter into new QF purchase contracts. If the Commission
finds that the QF has nondiscriminatory access to one of three
wholesale markets described in the statute, the requirement that the
electric utility enter into new contracts or obligations is terminated.
These three wholesale markets, set forth in the statute in section
210(m)(1), and incorporated in the new Commission regulations at Sec.
292.309, are:
(A)(i) Independently administered, auction-based day ahead and
real time wholesale markets for the sale of electric energy; and
(ii) wholesale markets for long-term sales of capacity and electric
energy; or
(B)(i) Transmission and interconnection services that are
provided by a Commission-approved regional transmission entity and
administered pursuant to an open access transmission tariff that
affords nondiscriminatory treatment to all customers; and (ii)
competitive wholesale markets that provide a meaningful opportunity
to sell capacity, including long-term and short-term sales, and
electric energy, including long-term, short-term and real-time
sales, to buyers other than the utility to which the qualifying
facility is interconnected. In determining whether a meaningful
opportunity to sell exists, the Commission shall consider, among
other factors, evidence of transactions within the relevant market;
or
(C) Wholesale markets for the sale of capacity and electric
energy that are, at a minimum, of comparable competitive quality as
markets described in subparagraphs (A) and (B).
We interpret section 210(m)(1) to require the Commission to
eliminate the purchase obligation in markets which meet the criteria of
section 210(m)(1)(A), (B) or (C) if QFs have nondiscriminatory access
to such markets. These three wholesale markets are characterized in
this rule in short-hand terms as ``Day 2'' markets (auction based day-
ahead and real-time markets), ``Day 1'' markets (auction based real-
time markets but not auction based day-ahead markets), and comparable
markets, respectively.\5\ The Final Rule finds that the Midwest ISO,
PJM, ISO-NE, and NYISO all meet the criteria of section 210(m)(1)(A).
These RTOs are independently administered and offer auction-based day
ahead and real time wholesale markets for the sale of electric energy;
and within the regions represented by these RTOs there is
nondiscriminatory access to wholesale markets for long-term sales of
capacity and electric energy. Therefore, except for the rebuttable
presumptions set forth below, the member electric utilities of these
four RTO/ISOs will be eligible for relief from the requirement to enter
into new contracts for the purchase of QF electric energy.
---------------------------------------------------------------------------
\5\ Reference to ``Day 2'' and ``Day 1'' and the corresponding
parenthetical are meant to be descriptive and thus are not a
recitation of the elements of section 210(m)(1)(A) or (B).
---------------------------------------------------------------------------
9. The Final Rule creates three rebuttable presumptions:
(A) For all three of the above markets, with the exception of the
20 megawatt (MW) presumption discussed next, the Final Rule finds that
the existence of an open access transmission tariff (OATT), or a
reciprocity tariff filed by a non-jurisdictional utility, pursuant to
the Commission's open access regulations,\6\ creates a rebuttable
presumption, under section 210(m)(1), that QFs have ``nondiscriminatory
access to'' the relevant wholesale markets.\7\
---------------------------------------------------------------------------
\6\ 18 CFR 35.28(e). An OATT provides interconnection as well as
transmission services on a nondiscriminatory basis.
\7\ To the extent that a QF raises issues about the adequacy of
an electric utility's implementation of an OATT, such issues are
more properly addressed in a complaint proceeding and will not be
considered in the context of petitions for the termination of
mandatory purchase requirements. However, a QF may raise other
issues, such as operational characteristics and transmission
limitations, to attempt to rebut the presumption of market access
when it files a response to an application submitted pursuant to
section 210(m)(3) of PURPA and section 292.310 of our regulations.
---------------------------------------------------------------------------
(B) For all three of the above markets, the Final Rule establishes
a rebuttable presumption that QFs with a net capacity no greater than
20 MW, do not have nondiscriminatory access to
[[Page 64344]]
wholesale markets.\8\ Unless an electric utility seeking the right to
terminate its requirement to purchase small QF power specifically
rebuts this small QF presumption, and that electric utility's request
is granted by the Commission, a small QF would be eligible to require
the electric utility to purchase its electric energy.
---------------------------------------------------------------------------
\8\ Herein referred to as small QFs.
---------------------------------------------------------------------------
(C) The Final Rule finds that the four RTO/ISOs with ``Day 2''
markets, i.e., the Midwest ISO, PJM, ISO-NE, and NYISO, qualify as
markets under section 210(m)(1)(A) and establishes a rebuttable
presumption that these organizations provide large QFs (above 20 MWs
net capacity) interconnected with member electric utilities with
nondiscriminatory access to the ``Day 2'' wholesale markets set forth
in section 210(m)(1)(A). An electric utility member of one of these
four RTO filing for relief from the requirement to purchase will need
to refer to this rebuttable presumption in the Final Rule as part of
its application. When it files an application for relief from the
purchase requirement it must also submit certain information, including
information about transmission constraints within its service
territory, in order to give potentially affected QFs information that
may be useful in rebutting the presumption that they have access to all
aspects of the applicable ``Day 2'' markets.\9\ A QF above 20 MWs net
capacity may rebut the presumption of nondiscriminatory access by
showing that it in fact lacks access.
---------------------------------------------------------------------------
\9\ The electric utility would have to make additional showings
if it wished to rebut the presumption that small QFs do not have
nondiscriminatory access to its region's ``Day 2'' wholesale
markets.
---------------------------------------------------------------------------
10. The rule does not find that any markets meet the statutory
criteria at this time other than the four listed RTO/ISOs (Midwest ISO,
PJM, ISO-NE, and NYISO) and the Electric Reliability Council of Texas
(ERCOT) (discussed below). There will be a rebuttable presumption that
QFs above 20 MWs net capacity have nondiscriminatory access to these
markets if they are eligible for service under a Commission-approved
OATT or Commission-filed reciprocity tariff.
11. With respect to the California Independent System Operator
(CAISO), and the Southwest Power Pool (SPP), which have only ``Day 1''
markets, it would be premature to find now that the CAISO and SPP would
meet the criteria of section 210(m)(1)(A) once their ongoing market
redesigns become effective. However, we find that: the CAISO and SPP
meet the section 210(m)(1)(B)(i) criterion because they are Commission-
approved regional transmission entities that provide transmission and
interconnection services pursuant to open access transmission tariffs
that provide nondiscriminatory treatment to all customers. A member
electric utility of the CAISO or SPP may rely on this finding in its
application to be relieved of the obligation to enter into new
contracts to purchase QF electric energy, but must make all the other
showings required under section 210(m)(1)(B) before its request may be
granted.
12. The Final Rule finds that ERCOT meets the criteria of section
210(m)(1)(C). ERCOT offers wholesale markets for the sale of capacity
and electric energy that are of comparable competitive quality as the
markets described in sections 210(m)(1)(A) and (C). Therefore, except
for the rebuttable presumptions set forth herein, the member electric
utilities of ERCOT will be eligible for relief from the requirement to
enter into new contracts for the purchase of QF electric energy.
13. New Sec. 292.310 of the Commission's regulations sets forth
the filing requirements for an application by an electric utility
seeking to terminate its requirement to enter into new purchase
contracts with QFs. Among other things, the regulations require the
electric utility to list the names and addresses of all potentially
affected QFs, existing or under development. After notice and comment,
the Commission will issue an order making a final determination within
90 days of the application, as required by section 210(m)(3).
B. Preservation of Existing Contracts
14. The Final Rule preserves the rights or remedies of any party
under existing contracts or obligations, in effect or pending approval
before the appropriate state regulatory authority or non-regulated
electric utility on or before August 8, 2005, to purchase electric
energy from or to sell electric energy to a QF. This provision is
stated in the new Sec. 292.314 of the Commission's regulations. The
Final Rule defines the term ``obligations'' broadly to encompass any
legally enforceable obligation established through a state's
implementation of PURPA.
C. Reinstatement of the Mandatory Purchase Requirement
15. The Final Rule also sets forth a process by which a QF may seek
the reinstatement of the requirement to purchase electric energy, by
showing that the conditions necessary for the removal of the
requirement to purchase are no longer met. After notice, including
notice to the affected utilities, and comment, the Commission will
issue an order within 90 days of the application. This process is set
forth in the new Sec. 292.311 of the Commission's regulations. A QF's
request may be specific (and limited) to itself alone, generic for the
entire service territory of an electric utility, or regional in scope.
The Commission will address the merits of each request as warranted by
the circumstances presented in each case.
D. Termination of the Requirement To Sell Electric Energy to QFs
16. The Final Rule provides for applications to remove the
requirement to enter into new contracts to sell electric energy to QFs.
The statute provides that if the Commission finds that competing retail
electric suppliers are willing and able to sell and deliver electric
energy to a QF, and the electric utility is not required by state law
to sell electric energy in its service territory, the requirement to
sell should be terminated. The new Sec. 292.312 of the Commission's
regulations describes this process. The Final Rule makes no findings or
presumptions with respect to an electric utility's obligation to sell
electric energy to QFs.
E. Reinstatement of the Requirement To Sell Electric Energy to QFs
17. Finally, the Final Rule provides for applications to reinstate
the requirement of an electric utility to sell electric energy to QFs,
by showing that the conditions necessary for the removal of the
requirement to sell are no longer met. After notice and comment, the
Commission will issue an order within 90 days if the required showing
is made. Applications for reinstatement are addressed in the new Sec.
292.313 of the Commission's regulations.
F. Recovery of Prudently Incurred Costs Relating to QF Power Purchases
18. The Final Rule does not adopt new regulations implementing
section 210(m)(7), regarding an electric utility's recovery of
prudently incurred costs relating to purchases of electricity from QFs.
III. Background
A. History of Section 210 of PURPA
19. When Congress enacted section 210 of PURPA, it required the
Commission to prescribe such rules as the Commission determined
necessary to encourage cogeneration and small power production,
including rules requiring electric utilities to offer to purchase
electric energy from and sell
[[Page 64345]]
electric energy to QFs. Additionally, section 210 of PURPA authorized
the Commission to exempt QFs from certain federal and state laws and
regulations if necessary to encourage cogeneration and small power
production.
20. A cogeneration facility is defined in the Federal Power Act
(FPA) \10\ as a facility which produces electric energy and steam or
forms of useful energy (such as heat) which are used for industrial,
commercial, heating, or cooling purposes.\11\ Thus, cogeneration
facilities simultaneously produce two forms of useful energy, namely
electric energy and heat. Cogeneration facilities can use significantly
less fuel to produce electric energy and steam (or other forms of
energy) than would be needed to produce the two separately.
---------------------------------------------------------------------------
\10\ 16 U.S.C. 824 et seq.
\11\ Id. 796(18).
---------------------------------------------------------------------------
21. Small power production facilities, as defined in the FPA, use
biomass, waste, or renewable resources, including wind, solar energy
and water, to produce electric energy and have a power production
capacity which, together with any other facilities located at the same
site, is not greater than 80 megawatts.\12\ Reliance on these sources
of energy can reduce the need to consume fossil fuels to generate
electric power.
---------------------------------------------------------------------------
\12\ Id. 796(17)(A)(i)-(ii).
---------------------------------------------------------------------------
22. Prior to the enactment of PURPA, a cogenerator or small power
producer seeking to establish interconnected operation with a utility
faced three major obstacles. First, utilities were not generally
willing to purchase this electric output or were not willing to pay an
appropriate rate for that output. Second, utilities generally charged
discriminatorily high rates for back-up service to cogenerators and
small power producers. Third, a cogenerator or small power producer
which provided electric energy to a utility's grid ran the risk of
being considered a public utility and thus being subjected to extensive
state and federal regulation.
23. Section 210 of PURPA was designed to remove these obstacles.
Each electric utility is required under section 210 to offer to
purchase available electric energy from cogeneration and small power
production facilities which obtain qualifying status. The rates for
such purchases from QFs must be just and reasonable to the ratepayers
of the utility, in the public interest, and must not discriminate
against cogenerators or small power producers. Rates also must not
exceed the incremental cost to the electric utility of alternative
electric energy (also known as the electric utility's ``avoided
costs''). Section 210 also requires electric utilities to provide
electric energy to QFs at rates which are just and reasonable, in the
public interest, and which do not discriminate against cogenerators and
small power producers. Rates for the purchase of energy from and the
sale of energy to a QF are set by the appropriate state regulatory
authority or non-regulated utility pursuant to the Commission's
regulations, 18 CFR 292.301-308 (2006).
24. Since Congress enacted PURPA, electric utilities have
complained that their requirement to purchase from and sell to QFs, as
implemented by the Commission in 18 CFR 292.303(a)-(b), was not
economically beneficial and that they were purchasing energy they did
not need and selling energy they did not want to sell. In 1995, the
Commission clarified that determinations of the avoided-cost rate must
take into account all alternative sources including third-party
suppliers and an electric utility does not pay for electric energy it
does not need.\13\ In the past decade, with the development of exempt
wholesale generators (EWGs) introduced by the Energy Policy Act of
1992,\14\ the implementation of open access transmission via Order No.
888, the advent of ISOs and RTOs and organized markets, the
Commission's new interconnection requirements, and increasing
competition in wholesale electric markets as well as some retail
electric markets, Congress has debated whether to repeal PURPA
altogether, or to revise it. The result is new section 210(m), which is
the subject of this rulemaking, and new section 210(n), which was
addressed in Docket No. RM05-36-000.\15\
---------------------------------------------------------------------------
\13\ Southern California Edison Company and San Diego Gas &
Electric Company, 70 FERC ] 61,215 at 61,677-78, reconsideration
denied, 71 FERC ] 61,269 at 62,078 (1995) (finding that the
determination of avoided cost must take into account ``all
sources'').
\14\ Energy Policy Act of 1992, Pub. L. No. 102-486, 106 Stat.
2776, (1993) (EPAct 1992). EPAct 1992 added a new section 32 to the
Public Utility Holding Company Act of 1935 (PUHCA) to permit a
category of sellers called EWGs to be exempt from PUHCA.
\15\ Revised Regulations Governing Small Power Production and
Cogeneration Facilities, Order No. 671, 71 FR 7852 (Feb. 15, 2006),
FERC Stats. & Regs. ] 31,203 (2006), order on reh'g, Order No. 671-
A, 71 FR 30585 (May 30, 2006), FERC Stats. & Regs. ] 31,219 (2006).
---------------------------------------------------------------------------
B. New Section 210(m)
25. Section 210(m) of PURPA is titled ``Termination of Mandatory
Purchase and Sale Requirements.'' The section revises the rights and
obligations between electric utilities and QFs. Section 210(m)(1)
requires the Commission to terminate the requirement of an electric
utility to enter into a new contract or obligation with the QF if it
finds that a QF has nondiscriminatory access to a market described in
section 210(m)(1)(A), (B) or (C). Section 210(m)(2) states that after
the date of enactment, no utility will be required to enter into a
contract to purchase from or sell to a new cogeneration facility,
unless the facility meets the criteria for new cogeneration facilities
established by the Commission in implementing section 210(n) of PURPA.
Section 210(m)(3) provides that an electric utility may file ``an
application for relief from the mandatory purchase obligation'' on a
service territory-wide basis and provides that the Commission must make
a final determination on such an application within 90 days of the
application. Section 210(m)(4) provides that a QF, a state agency, or
other affected person may apply for an order reinstating the electric
utility's ``obligation to purchase electric energy under this section''
upon a change in the market. Section 210(m)(5) provides for the
termination of the requirement that an electric utility enter into a
new contract or obligation to sell electric energy to a QF upon a
finding that specified competitive conditions exist. Section 210(m)(6)
provides that nothing in section 210(m) affects the rights or remedies
of any party under any contract or obligation in effect or pending
approval before the appropriate state regulatory authority or
nonregulated utility on the date of enactment of section 210(m). And
finally, section 210(m)(7) provides that the Commission shall issue and
enforce such regulations as are necessary to ensure that an electric
utility that purchases electric energy or capacity from a QF in
accordance with a legally enforceable obligation entered into or
imposed under section 210 of PURPA recovers all prudently incurred
costs associated with the purchase.
C. NOPR
26. On January 19, 2006, the Commission issued a NOPR containing
its proposal to implement section 210(m) of PURPA. Generally, the
Commission proposed to incorporate the language of section 210(m) in
its regulations. While section 210(m) permits electric utilities to
file applications for relief from the mandatory purchase requirement,
and requires the Commission to act on such applications within 90 days,
the Commission determined in the NOPR that it is appropriate to act
generically as much as possible. Specifically, section 210(m)(1)(A) is
most suitable for
[[Page 64346]]
such a generic implementation and the Commission proposed to make
generic findings that certain markets meet the section 210(m)(1)(A)
criteria. The NOPR concluded that the most reasonable interpretation of
section 210(m)(1)(A) is that it was crafted to apply to regions in
which ISOs and RTOs administer auction-based day ahead and real time
wholesale markets for the sale of electric energy; and wholesale
markets for long-term sales of capacity and electric energy are that
these are available to participants/QFs in these markets.\16\ The
Commission proposed in the NOPR that it would make a generic finding
that the Midwest ISO, PJM, ISO-NE, and NYISO provide markets that meet
the requirements of section 210(m)(1)(A) and therefore utilities that
are members of those ISOs or RTOs meet the criteria for relieving those
electric utilities of the requirement to enter into new contracts or
obligations with QFs.\17\ Because the Commission proposed to make a
generic finding with respect to 210(m)(1)(A), the Commission proposed
that the electric utilities that are members of these four RTO/ISOs
submit a compliance filing instead of filing applications for relief of
the purchase requirement pursuant to 210(m)(3). In the compliance
filing, the electric utility would demonstrate: (1) Membership in the
RTO/ISO; (2) that the Commission has made a final finding that the RTO/
ISO it is a member of provides nondiscriminatory access to a section
210(m)(1)(A) market; (3) a list of all potentially affected QFs; and
(4) the QFs have the rights to request service under the OATT.\18\
---------------------------------------------------------------------------
\16\ NOPR at P 14.
\17\ Id. at P 22-28.
\18\ Id. at P 40. We note that, since the time comments were
filed in this proceeding, the Commission has issued a NOPR proposing
amendments to the OATT. Preventing Undue Discrimination and
Preference in Transmission Service, 71 FR 32636 (2006), FERC Stats.
& Regs. ] 32,603 (2006).
---------------------------------------------------------------------------
27. The Commission concluded that QFs have nondiscriminatory access
to transmission and interconnection if they have access to utilities
providing service under an Order No. 888 OATT (or to utilities
providing service under a Commission-accepted reciprocity tariff) and
interconnection services pursuant to the Commission's interconnection
rules.\19\ The Commission also proposed, however, that there be a
rebuttable presumption that a utility provides nondiscriminatory access
if it has an open access transmission tariff in compliance with our pro
forma OATT (or a Commission-approved reciprocity tariff) and that QFs
or any other affected party should be allowed to rebut that
presumption, for example, by providing specific and credible evidence
that the QF does not have nondiscriminatory access to wholesale
markets.\20\ The Commission noted that improper implementation of an
OATT is more properly the subject of a complaint.
---------------------------------------------------------------------------
\19\ Id. at P 20.
\20\ Id. at P 31.
---------------------------------------------------------------------------
28. Further, the Commission proposed in the NOPR that other
markets, i.e., both non-auction-based markets and non-RTO/ISO markets
described in section 210(m)(1)(B) and (C), would not be addressed
generically in this rulemaking but would be addressed on a case-by-case
basis in response to applications filed pursuant to the Commission's
implementation of section 210(m)(3) of PURPA, i.e., pursuant to the
proposed Sec. 292.310 of the Commission's regulations.\21\ The
Commission proposed that subsequent changes to market conditions in all
markets, i.e., markets described subparagraphs (A), (B) and (C) also
would be handled on a case-by-case basis as well. Applications for
termination of the requirement to enter into new contracts or
obligations to purchase from QFs in markets described in subparagraphs
(B) and (C) would be addressed pursuant to the proposed Sec. 292.310
of the Commission's regulations. An application to reinstate the
requirement that a utility enter in the new contracts or obligations to
purchase from QFs, alleging subsequent changes to market conditions,
would be addressed pursuant to the proposed Sec. 292.311 of the
Commission's regulations. The Commission noted that it must make a
finding regarding an application for relief of the purchase requirement
and that the finding must be made within 90 days of the date of such
application. The Commission stated that it expected an application for
relief to be fully supported by documentation upon which the required
finding can be made.\22\
---------------------------------------------------------------------------
\21\ Id. at P 29-30.
\22\ The Commission interprets the 90-day period to begin upon
receipt of a completed application.
---------------------------------------------------------------------------
29. Of the approximately 2,000 pages of comments the Commission has
received to its NOPR, a large portion of the comments focused on the
standards applicable to utilities within the ``Day 2'' RTO/ISOs and the
procedures for utilities within ``Day 2'' markets to claim relief from
the purchase requirement. Based on careful consideration of the
comments submitted in response to the NOPR, the Commission adopts a
Final Rule that makes certain modifications and clarifications to the
approach in the NOPR.
IV. Discussion
A. Section 210(m)(1)
30. The new PURPA section 210(m)(1) amends the statutory
requirement that electric utilities purchase electric energy from QFs
and states that:
* * * No electric utility shall be required to enter into a new
contract or obligation to purchase electric energy from a qualifying
cogeneration facility or a qualifying small power production
facility under this section if the Commission finds that the
qualifying cogeneration facility or qualifying small power
production facility has nondiscriminatory access to--
(A)(i) Independently administered, auction-based day ahead and real
time wholesale markets for the sale of electric energy; and (ii)
wholesale markets for long-term sales of capacity and electric
energy; or
(B)(i) Transmission and interconnection services that are provided
by a Commission-approved regional transmission entity and
administered pursuant to an open access transmission tariff that
affords nondiscriminatory treatment to all customers; and (ii)
competitive wholesale markets that provide a meaningful opportunity
to sell capacity, including long-term and short-term sales, and
electric energy, including long-term, short-term and real-time
sales, to buyers other than the utility to which the qualifying
facility is interconnected. In determining whether a meaningful
opportunity to sell exists, the Commission shall consider, among
other factors, evidence of transactions within the relevant market;
or
(C) Wholesale markets for the sale of capacity and electric energy
that are, at a minimum, of comparable competitive quality as markets
described in subparagraphs (A) and (B).
1. Three Standards for Relief
a. NOPR
31. Section 210(m)(1) defines under what conditions the Commission
must relieve an electric utility of the obligation to enter into a new
contract or obligation to purchase electric energy from a QF.
Essentially, section 210(m)(1) establishes three different standards
for relief from the purchase requirement depending on whether: (1)
Electric utilities are members of ``Day 2'' RTO/ISOs; (2) electric
utilities are members of ``Day 1'' RTO/ISOs; and (3) electric utilities
are in neither ``Day 2'' nor ``Day 1'' RTO/ISOs. The NOPR interpreted
the language of section 210(m)(1) as to what conditions must exist for
the three types of markets and sought comments.
32. The NOPR explained that the first standard for relief is
established in section 210(m)(1)(A) of section 210(m)(1), which applies
to ``Day 2'' markets with wholesale bilateral long-
[[Page 64347]]
term contracts for the sale of capacity and electric energy available
to participants. The Commission indicated that, under section
210(m)(1)(A)(ii), there was no requirement, given the statutory
language, to consider ``evidence of transactions within the relevant
market'' when determining whether QFs have nondiscriminatory access to
``wholesale markets for long-term sales of capacity and electric
energy.'' The Commission suggested that Congress presumed QFs, which
have ``nondiscriminatory access to'' ISO and RTO regions with auction-
based day ahead and real time markets, have nondiscriminatory access to
long-term sales of electric energy and capacity wholesale markets
outside the interconnected utility. The Commission proposed to find
that Midwest ISO, PJM, ISO-NE, and NYISO meet the requirements of
section 210(m)(1)(A).
33. The second standard for relief is established in section
210(m)(1)(B), which the Commission found to be intended to apply in
``Day 1'' RTO/ISOs, i.e., those that do not have both auction-based day
ahead and real time markets. Section 210(m)(1)(B) provides for
termination of the requirement that an electric utility enter into a
new contract or obligation to purchase electric energy from a QF so
long as there is (i) a Commission-approved regional transmission entity
providing nondiscriminatory transmission and interconnection services;
and (ii) ``competitive wholesale markets that provide a meaningful
opportunity'' to sell capacity and energy on both a short- and long-
term basis and energy on a real-time basis (emphasis added) to buyers
other than the utility to which the QF is interconnected. In the NOPR,
the Commission stated that ``meaningful opportunity'' is to be
determined by the Commission after considering, among other factors,
``evidence of transactions within the relevant market.'' The Commission
indicated that taken together, the terms ``competitive,'' ``meaningful
opportunity'' and ``evidence of transactions'' suggest that Congress
intended that termination of the purchase requirement in a ``Day 1''
market only if it could be established that QFs had opportunities to
make long-term and short-term sales of capacity and long-term, short-
term and real-time sales of energy into competitive wholesale markets.
34. The third standard for relief is established in section
210(m)(1)(C) of section 210(m)(1). Under this standard, the purchase
requirement is removed in wholesale markets for the sale of capacity
and electric energy that are, ``at a minimum,'' of comparable
competitive quality as markets described in subparagraphs (A) and (B).
The Commission explained that although this provision is not clear on
its face, its reference to subparagraphs (A) and (B) requires the
Commission to be mindful, in interpreting the provision, of the two
types of requirements that are embodied in those sections, i.e., (1)
nondiscriminatory access to transmission and interconnection services,
and (2) competitive short-term and long-term markets that provide a
meaningful opportunity to sell to buyers other than the utility to
which the QF is interconnected.
b. Comments
35. ELCON, AWEA, Caithness and Public Interest Organizations
(PIOs),\23\ for example, state that Congress did not repeal the
mandatory purchase requirement and that the Commission has a continuing
obligation to promote QF development. This, they contend, can only be
accomplished by assuring that markets meet criteria that guarantee that
QFs will enter into contracts with electric utilities of similar
quality to those that they received prior to the enactment of section
210(m) of PURPA before the mandatory purchase obligation can be
terminated. ELCON appears to suggest that there is only one standard
for relief from the purchase requirement: ``assurance of a competitive
market.'' \24\ In essence, ELCON argues that sections 210(m)(1)(A), (B)
and (C) establish a single standard for terminating the mandatory
purchase obligation. ELCON states that section 210(m) authorizes the
Commission to grant relief from the purchase requirement ``if and only
if a viable market exists.'' \25\ ELCON expresses its concern that
because discrimination continues and the markets are flawed,
competition and on-site generation will be discouraged. AWEA and
Caithness state that the Commission should grant relief from the
purchase requirement only in markets which are ``sufficiently
competitive.'' \26\ EPSA argues that the mandatory purchase requirement
can be terminated only where the Commission finds that the ``economic
and technical equivalent to mandatory purchase is available through a
competitive market.''\27\ PIOs argue that electric utilities have to
demonstrate that QFs do, in fact, have physical and economic access to
all of the required markets on a nondiscriminatory basis. The American
Chemistry Council contends that the mandatory purchase requirement can
be terminated only in those situations where wholesale markets have
evolved to ensure the long-term commercial viability of QFs which
enables QFs to attract investment capital and facilitates QF
development; the American Chemistry Council urges the Commission to
interpret section 210(m)(1) in such a manner.
---------------------------------------------------------------------------
\23\ The PIOs filing these comments are the Center for Energy
Efficiency & Renewable Technologies, Delaware Division of the Public
Advocate, Environmental Law & Policy Center, Interwest Energy
Alliance, Izaak Walton League of America, Natural Resources Defense
Council, Northwest Energy Coalition, Office of the Ohio Consumers'
Counsel, Pace Energy Project, Project for Sustainable FERC Energy
Policy, West Wind Wires, and Western Resource Advocates.
\24\ ELCON Comments at 8.
\25\ Id.
\26\ AWEA Comments at 2.
\27\ EPSA Comments at 9.
---------------------------------------------------------------------------
36. NPRA reminds the Commission that the main purpose of
cogeneration is not to serve the needs of an electric power grid or
``market,'' but, rather, it is to serve the interconnecting industrial
thermal and electrical load. Consequently, NPRA argues that the
operation of these facilities may require different market features
than are required by utility electric generation or merchant
generation. NPRA argues that Congress intended to terminate the ``must
take'' requirement only when it can be demonstrated that an electric
market supports not only the role of merchant power, but the retention
and encouragement of cogeneration. In other words, while a market may
prove an efficient and viable alternative for a merchant plant, it does
not necessarily ensure that it is an efficient and viable alternative
for sales of power by a cogeneration facility.
c. Commission Determination
37. We disagree with commenters' interpretation of the statutory
standard for relief from the requirement that an electric utility enter
into a new contract or obligation to purchase electric energy from a
QF. There is nothing in section 210(m) to suggest that Congress
intended to ensure a QF's commercial viability. Nor does the statute
require the Commission to find that the ``economic and technical
equivalent to mandatory purchase is available through a competitive
market'' before it terminates the requirement that an electric utility
enter into a new contract or obligation to purchase electric energy
from QFs. Although we certainly agree with the QF commenters that
Congress did not repeal the mandatory purchase requirement in its
entirety, Congress clearly left the Commission with no choice but to
eliminate the mandatory purchase requirement for utilities operating in
certain markets upon
[[Page 64348]]
certain findings being made. The fact is that the language of section
210(m)(1) provides that an electric utility shall be relieved of the
requirement to purchase from a QF if the Commission makes certain
findings, which findings do not include a determination that the
``economic and technical equivalent to mandatory purchase is available
through a competitive market.'' This is not what section 210(m) says,
nor would it make any sense to infer such an interpretation.
Competitive markets do not, by definition, impose ``mandatory''
purchase obligations on buyers. Buyers choose among differing sellers
based on their relative cost, reliability, etc. The QFs making this
argument therefore ignore the relevant statutory language and, in doing
so, reargue the debate before Congress when it enacted section 210(m).
38. The most reasonable interpretation of section 210(m)(1) is that
Congress, in setting forth discrete tests for three different types of
markets, was requiring the Commission to differentiate among these
markets, and the differing circumstances they present, in determining
whether a utility must be relieved of the mandatory purchase
obligation. Although the statute is ambiguous in certain respects, it
clearly reflects Congressional intent that the Commission differentiate
among these three markets in making its determination regarding whether
to terminate the purchase obligation. This approach not only reflects a
natural reading of the words of the statute, it also is reasonable
given the nature of the determination being made. There is little
debate in this proceeding that Day 2 organized markets, as a general
matter, provide greater opportunities for QFs (and other independent
generators) to compete than unorganized markets because of the
existence of day-ahead and real-time energy markets that allow all
competing generators to submit bids to participate in the market on a
nondiscriminatory basis. Although other markets--including ``Day 1''
markets and non-organized markets--also provide opportunities for
independent generators to compete, it is not surprising that Congress
would find that, as a general matter, they have less formalized
structures for doing so and, hence, utilities seeking relief from the
purchase obligation in those markets would bear a heavier evidentiary
burden to obtain relief. The Commission cannot, as some commenters in
effect ask us to do, simply collapse the three discrete tests into one
test that requires an electric utility to demonstrate that a QF will
remain economically viable if the purchase requirement is eliminated.
This would make the three different statutory standards meaningless.
2. The Nondiscriminatory Access Requirement of Section 210(m)(1) and
the OATT
a. NOPR
39. Section 210(m)(1) provides for termination of the requirement
for an electric utility to enter into a new contract or obligation to
purchase from a QF if the QF has ``nondiscriminatory access'' to a
wholesale market described in section 210(m)(1)(A), (B), or (C). In the
NOPR, the Commission proposed that there be a rebuttable presumption
that a utility provides nondiscriminatory access if it has an Order No.
888 OATT (or a utility providing service under a Commission-approved
reciprocity tariff). The Commission stated that QFs or any other party
should be allowed to rebut that presumption, but that improper
implementation of an OATT is more properly the subject of a complaint
to ensure that the OATT is properly implemented.
b. Comments
40. ELCON and virtually every other commenter from the QF industry
argue that the Commission erred in the NOPR by proposing a rebuttable
presumption that a utility provides ``nondiscriminatory access'' to the
market conditions identified in section 210(m)(1)(A), (B), or (C) if it
has an OATT in compliance with the Commission's pro forma OATT, or a
Commission-approved reciprocity tariff. They argue that the proposal
reflects an overly simplified interpretation of the statute's
``nondiscriminatory access'' requirement and that the mere existence of
transmission rights under an OATT does not necessarily ensure that QFs
have nondiscriminatory access to markets. ELCON and the QF industry
argue that barriers that discriminate against QFs could exist
notwithstanding the adoption of an OATT. The California Cogeneration
Council (CCC), for instance, states that these barriers could be
present in ISO policies that make it more difficult or burdensome for
QFs to participate in a market as compared with other types of
generators or market participants. ELCON and the QF industry argue that
section 210(m)(1) requires the Commission to consider such potential
barriers, and to evaluate whether QFs truly have nondiscriminatory
access to alternative markets, before concluding that the requirements
of section 210(m)(1) have been met.
41. In addition, ELCON and the QF industry state that the
Commission has recognized that the intent of Order No. 888 concerning
nondiscriminatory access to transmission has not been fully realized;
first in Order No. 2000 \28\ and more recently in the NOPR on
Preventing Undue Discrimination and Preference in Transmission
Service.\29\
---------------------------------------------------------------------------
\28\ Regional Transmission Organizations, Order No. 2000, 65 FR
809 (Jan. 6, 2000), FERC Stats. & Regs. P 31,089 (1999), order on
reh'g, Order No. 2000-A, 65 FR. 12,088 (Mar. 8, 2000), FERC Stats. &
Regs. P 31,092 (2000), aff'd sub nom. Pub. Util. Dist. No. 1 of
Snohomish County, Washington v. FERC, 272--F.3d--607 (D.C. Cir.
2001).
\29\ See supra note 15.
---------------------------------------------------------------------------
42. EPSA, Reliant and PIOs add that any tariff for transmission and
interconnection services must incorporate changes consistent with the
Commission's pro-competitive policies of Order No. 2000 and any further
improvements determined as part of the notice of inquiry (NOI). EPSA
argues that only then will the transmission and interconnection
services be provided on a nondiscriminatory, pro-competitive basis.
43. Dow Chemical Company (Dow) states that there are numerous
instances in which QFs effectively have no access to organized markets
or to transmission services regardless of whether the utilities to
which they are interconnected technically participate in organized
markets or provide transmission and interconnection services on an open
access basis. Dow states that instead, in such instances, the only
entity physically capable of acquiring QF output is the utility with
which the QF is interconnected. American Forest & Paper states that
market rules designed for merchant generation are often highly
discriminatory to QFs which, because of the thermal needs of a
cogeneration QF's thermal host, have limited dispatchability and must
often be operated in base load configurations. American Forest & Paper
states that market rules designed around the dispatchability of
resources which do not have attendant manufacturing facility
obligations may discriminate unnecessarily and unreasonably against
QFs. Council of Industrial Boiler Owners (CIBO) state that by finding
that an OATT is sufficient to ensure nondiscriminatory access to
markets, the Commission fails to consider the operational differences
faced by QFs.
44. In addition, Commenters argue that the NOPR's proposal that
there be a rebuttable presumption that a utility provides
nondiscriminatory access if it
[[Page 64349]]
has an OATT is in essence an irrebuttable presumption. ELCON and the
American Chemistry Council state that although the Commission
characterizes the presumption as ``rebuttable,'' it also states that
the presumption ``cannot be rebutted by an argument that the utility
has not properly implemented or administered its OATT.''
45. ELCON argues that it will be difficult for the Commission to
sustain on judicial review an irrebuttable presumption that the OATT
provides nondiscriminatory transmission access for all QFs when its own
NOI recognizes the continuation of patterns of abuse--if anything
exacerbated as transmission owners feel the pressure of competition
from independent generation. ELCON states that the concern over
potential discrimination will only be exacerbated in a scenario like
the Entergy Independent Coordinator of Transmission (ICT) where the
utility and not the RTO provide service. ELCON states that while the
problem of discrimination in transmission is pervasive, a fortiori, QFs
of whatever size connected at distribution voltage do not have access
to markets. ELCON states that the scenario of QFs connected at
distribution voltage and the circumstances of small QFs illustrate why
generic conclusions are inappropriate.
46. Further, Occidental Chemical Corporation (Occidental) argues
that the Commission's conclusion that a complaint, rather than the
application proceeding, is the only vehicle available to address a QF's
concern that the OATT is being administered or implemented in a
discriminatory manner is inconsistent with the plain language of the
statute. Occidental states that a QF cannot provide meaningful comments
on whether an electric utility's application meets the
nondiscriminatory showing required by statute, if the QF is barred from
raising issues regarding discriminatory administration or
implementation of the OATT and can only raise such issues in a separate
complaint proceeding. In addition, Occidental argues that it is unclear
how the Commission could make a determination that QFs have
nondiscriminatory access under an electric utility's OATT if the
Commission bars, from the outset, all evidence that the OATT is being
administered or implemented in a discriminatory manner.
47. PJM is concerned with the Commission's presumption for both
section 210(m)(1)(B) and (C) that having an Order No. 888 OATT on file
is enough to establish a presumption of nondiscriminatory access to the
grid. PJM states that rather, the Commission should analyze particular
facts and circumstances relative to concerns raised with potential
access to the marketplace for QFs.
48. EEI, Allegheny Power, Alliant, Entergy, National Grid and PSNM/
TNP agree with the NOPR's proposal. EEI states that QF commenters raise
no compelling evidence that access provided pursuant to Commission-
approved OATTs is deficient. EEI states that nondiscriminatory access
is the standard set by Congress in EPAct 2005, and Congress was fully
aware when it used this standard that the OATT is the mechanism for
achieving nondiscriminatory access. Allegheny joins EEI in stating that
the Commission should make a generic finding that QF access pursuant to
a Commission-approved OATT meets the ``nondiscriminatory access'' test
of section 210(m) for all markets, whether centrally organized and
administered or not.
49. EEI states that the fact that the Commission is considering
updating Order No. 888 through its ongoing NOI does not mean that
reliance on the OATT as the current benchmark for nondiscriminatory
access is inappropriate. EEI states that at this preliminary stage of
the Commission's inquiry into whether changes to the OATT should be
required, it is premature to predict what the Commission may or may not
finally conclude with respect to the OATT. EEI states that by basing so
much of their argument on the Commission's consideration of reforms to
Order No. 888, QF commenters are in essence converting a Commission NOI
into a Commission final rule. EEI states that even if the Commission
fine tunes the OATT, it would not mean that existing open access
practices pursuant to Commission-approved OATT are discriminatory. EEI
states that if the Commission does ultimately require changes, QFs--
like any other generator--will reap the benefit of those enhancements.
50. EEI further argues that where issues regarding implementation
or administration of a particular OATT arise, a complaint pursuant to
section 206 of the FPA is the established mechanism available to QFs
(or any other generator or transmission customer) to raise such
concerns. It states that in a complaint proceeding, the Commission has
the ability to remedy any denial of open access that results from
improper administration of an OATT, but that ability is not present
under PURPA section 210(m), where the Commission's only authority is to
reject an application for termination of the mandatory purchase
requirement.
51. EEI argues against the QFs' claim that the Commission has made
the presumption of nondiscriminatory access under an OATT essentially
irrebuttable. It states that as the NOPR provides, QFs or any other
party will be afforded the opportunity to provide ``specific and
credible evidence that the QF does not have nondiscriminatory access to
wholesale markets.''
c. Commission Determination
52. Under section 210(m)(1), the Commission must find that the QF
has ``nondiscriminatory access'' to the wholesale markets described in
section 210(m)(1)(A), (B), or (C) in order to terminate the requirement
that an electric utility enter into a new contract or obligation to
purchase electric energy from a QF. The Commission proposed in the NOPR
that there be a rebuttable presumption that a utility provides the
nondiscriminatory access required in section 210(m)(1) if it has an
open access transmission tariff in compliance with our pro forma OATT
(or a Commission-approved reciprocity tariff). However, the Commission
also proposed that QFs or any other affected party should be allowed to
rebut that presumption, for example, by providing specific and credible
evidence that the QF does not have nondiscriminatory access to
wholesale markets.
53. The Commission reaffirms the determination in the NOPR that
only issues not related to the provision of open access transmission
under the OATT may be raised to rebut the nondiscriminatory access
presumption. We disagree with arguments of ELCON and Occidental that a
QF should be able to litigate open access implementation issues in the
context of 90-day QF applications or that, as Occidental claims, use of
complaint proceedings to address OATT implementation is inconsistent
with the language of the statute. We also reject arguments that,
because the Commission issued a NOPR to reform the OATT, that we can no
longer adopt a presumption that a Commission-approved OATT meets the
requirements of section 210(m) regarding nondiscriminatory transmission
access.\30\ As we have
[[Page 64350]]
found in market-based rate proceedings and other contexts, a
transmission owner that has an OATT on file has met the obligation set
forth in Order No. 888 to provide nondiscriminatory transmission
access. Until we issue a Final Rule in RM05-25-000 that modifies Order
No. 888, no more is required. Further, the FPA provides specific
mechanisms, complaints under FPA section 206 or 306, to address
allegations that a particular utility is not properly administering the
OATT. We take very seriously allegations that a transmission owner is
violating its OATT, but there are established statutory procedures for
addressing such allegations. PURPA section 210(m) does not change this
statutory framework.\31\
---------------------------------------------------------------------------
\30\ In this regard we note that the rulemaking to reform the
OATT is intended to remedy the ``opportunity'' for undue
discrimination; the Commission did not base its institution of the
rulemaking in Docket No. RM05-25-000 on any finding that the OATT
allows actual discrimination. To the extent that ELCON argues that,
through the NOPR process, the Commission has recognized ``the
continuation of patterns of abuse,'' ELCON mischaracterizes the
basis of the OATT rulemaking.
\31\ In fact, PURPA section 210(m) provides a compressed 90-day
time frame in which the Commission, after notice and opportunity for
comment, must act on applications. This provides a clear indication
that Congress did not intend hearing or lengthy proceedings in order
to make a determination of whether the electric utility must be
relieved of