Federal Acquisition Regulation; FAR Case 2005-018, Contract Debts, 62230-62237 [06-8806]
Download as PDF
62230
Federal Register / Vol. 71, No. 205 / Tuesday, October 24, 2006 / Proposed Rules
post allowance to reflect the elimination
of that allowance from the Department
of States’ Standardized Regulations
(Government Civilians, Foreign Areas),
Chapter 230.
B. Regulatory Planning and Review
This is not a significant regulatory
action and, therefore, is subject to
review under Section 6(b) of Executive
Order 12866, Regulatory Planning and
Review, dated September 30, 1993. This
rule is not a major rule under 5 U.S.C.
804.
C. Regulatory Flexibility Act
Pursuant to requirements set forth in
the Regulatory Flexibility Act (RFA) (5
U.S.C. 601 et seq.), USAID has
considered the economic impact of the
rule and has determined that its
provisions would not have a significant
economic impact on a substantial
number of small entities.
D. Paperwork Reduction Act
The Paperwork Reduction Act does
not apply because the proposed changes
to the AIDAR do not impose
information collection requirements that
require the approval of the Office of
Management and Budget under 44
U.S.C. 3501 et seq.
List of Subjects in 48 CFR Part 7
Government procurement.
For the reasons set forth in the
preamble, the U. S. Agency for
International Development proposes to
amend 48 CFR part 7 as follows:
1. The authority citation for 48 CFR
part 7 continues to read as follows:
Authority: Sec. 621, Pub. L. 87–195, 75
Stat. 445, (22 U.S.C. 2381) as amended; E.O.
12163, Sept. 29, 1979, 44 FR 56673; 3 CFR
1979 Comp., p. 435.
PART 752—SOLICITATION
PROVISIONS AND CONTRACT
CLAUSES
2. Amend Section 752.7028 by
revising paragraph (a), removing and
reserving paragraph (e), and adding a
sentence at the end of paragraph (j)(1) to
read as follows:
§ 752.7028
Differential and allowances.
rmajette on PROD1PC67 with PROPOSALS1
*
*
*
*
*
(a) Post differential. Post differential
is an additional compensation for
service at places in foreign areas where
conditions of environment differ
substantially from conditions of
environment in the continental United
States and warrant additional
compensation as a recruitment and
retention incentive.
(1) In areas where post differential is
paid to USAID direct-hire employees,
VerDate Aug<31>2005
14:24 Oct 23, 2006
Jkt 211001
post differentials not to exceed the
percentage of salary as is provided such
USAID employees in accordance with
the Standardized Regulations
(Government civilians, Foreign Areas),
Chapter 500 (except the limitation
contained in Section 552, ‘‘Ceiling on
Payment’’) Tables—Chapter 900, as from
time to time amended, will be
reimbursable hereunder for employees
in respect to amounts earned during the
time such employees actually spend
overseas on work under this contract.
(See Standardized Regulation 510).
Payments for post differential are
limited to that percentage rate applied
to a maximum 40-hour work week,
regardless of whether the contracting
officer has authorized a work week in
excess of 40 hours. Exceptions to this
policy may be granted either by the
Mission Director or the Assistant
Administrator having program
responsibility for the project.
(2) When such post differential is
provided to regular employees of the
Contractor, it shall be payable beginning
on the date of arrival at the post of
assignment and continue, including
periods away from post on official
business, until the close of business on
the day of departure from post of
assignment en route to the United
States. Sick or vacation leave taken at or
away from the post of assignment will
not interrupt the continuity of the
assignment or require a discontinuance
of such post differential payments,
provided such leave is not taken within
the United States or the territories of the
United States. Post differential will not
be payable while the employee is away
from his/her post of assignment for
purposes of home leave. Short-term
employees shall be entitled to post
differential beginning with the fortythird (43rd) day at post.
*
*
*
*
*
(e) Reserved.
*
*
*
*
*
(j) (1) * * * Payments for danger pay
are limited to that percentage of basic
compensation as established by the
Standardized Regulations applied to a
maximum 40-hour work week,
regardless of whether the contracting
officer has authorized a work week in
excess of 40 hours. Exceptions to this
policy may be granted either by the
Mission Director or the Assistant
Administrator having program
responsibility for the project.
Dated: October 12, 2006.
Michael F. Walsh,
Procurement Executive.
[FR Doc. E6–17543 Filed 10–23–06; 8:45 am]
BILLING CODE 6116–01–P
PO 00000
Frm 00016
Fmt 4702
Sfmt 4702
DEPARTMENT OF DEFENSE
GENERAL SERVICES
ADMINISTRATION
NATIONAL AERONAUTICS AND
SPACE ADMINISTRATION
48 CFR Parts 12, 13, 32, 33, 36, 42, and
52
[FAR Case 2005–018]
RIN: 9000–AK59: Docket 2006–0020;
Sequence 11
Federal Acquisition Regulation; FAR
Case 2005–018, Contract Debts
Department of Defense (DoD),
General Services Administration (GSA),
and National Aeronautics and Space
Administration (NASA).
ACTION: Proposed rule.
AGENCIES:
SUMMARY: The Civilian Agency
Acquisition Council and the Defense
Acquisition Regulations Council
(Councils) are proposing to amend the
Federal Acquisition Regulation (FAR) to
revise the policies and procedures for
contract debts.
DATES: Interested parties should submit
written comments to the FAR
Secretariat on or before December 26,
2006 to be considered in the
formulation of a final rule.
ADDRESSES: Submit comments
identified by FAR case 2005–018 by any
of the following methods:
• Federal eRulemaking Portal: https://
www.regulations.gov. Search for any
document by first selecting the proper
document types and selecting ‘‘Federal
Acquisition Regulation’’ as the agency
of choice. At the ‘‘Keyword’’ prompt,
type in the FAR case number (for
example, FAR Case 2006–001) and click
on the ‘‘Submit’’ button. You may also
search for any document by clicking on
the ‘‘Advanced search/document
search’’ tab at the top of the screen,
selecting from the agency field ‘‘Federal
Acquisition Regulation’’, and typing the
FAR case number in the keyword field.
Select the ‘‘Submit’’ button.
• Fax: 202–501–4067.
• Mail: General Services
Administration, Regulatory Secretariat
(VIR), 1800 F Street, NW, Room 4035,
ATTN: Laurieann Duarte, Washington,
DC 20405.
Instructions: Please submit comments
only and cite FAR case 2005–018 in all
correspondence related to this case. All
comments received will be posted
without change to https://
www.regulations.gov, including any
personal and/or business confidential
information provided.
E:\FR\FM\24OCP1.SGM
24OCP1
Federal Register / Vol. 71, No. 205 / Tuesday, October 24, 2006 / Proposed Rules
Mr.
Jeremy Olson at (202) 501–3221 for
clarification of content. For information
pertaining to status or publication
schedules, contact the FAR Secretariat
at (202) 501–4755. Please cite FAR case
2005–018.
SUPPLEMENTARY INFORMATION:
rmajette on PROD1PC67 with PROPOSALS1
FOR FURTHER INFORMATION CONTACT:
A. Background
In 2003, the DoD Comptroller
established the DoD Accounts
Receivable Workgroup to evaluate the
processes and procedures for reporting
accounts receivables. This Workgroup
concluded that contracting officers may
not be properly reporting contract debts.
Based on the Workgroup’s
recommendations, DoD established a
Contract Debt Integrated Process Team
(IPT).
The mission of the IPT was to
evaluate the adequacy of DoD’s existing
controls and procedures for ensuring
that contract debts are identified and
recovered in a timely manner, properly
accounted for in DoD’s books and
records, and properly coordinated with
the appropriate Government Officials.
Contract debts result from compliance,
or a failure to comply, with the terms of
a contract and include debts identified
by auditors, contracting officers,
disbursing officials, and contractors. On
May 26, 2005, a final report was issued
that included a number of
recommended FAR changes to improve
contract debt controls and procedures,
and to ensure consistency within/
between existing regulations.
The Councils established this case to
evaluate the DoD recommendations. As
a result of this review, the Councils are
proposing the revisions discussed
below. In addition, the Councils are
considering whether the current
provisions regarding interest provisions
are sufficient. In particular, concerns
have been expressed over the current
timeline for computing interest. The
Councils agreed to defer this issue for
consideration to a later date (including
a possible public meeting).
1. Reorganize FAR Subpart 32.6.
Reorganizes FAR Subpart 32.6 to add
clarity and provide a logical sequence.
The Subpart has been reorganized as
follows:
32.600 Scope of subpart.
32.601 General.
32.602 Responsibilities.
32.603 Debt determination.
32.604 Demand for payment.
32.605 Final decisions.
32.606 Debt collection.
32.607 Installment payments and
deferment of collection.
32.607–1Installment payments.
32.607–2Deferment of collection.
VerDate Aug<31>2005
14:24 Oct 23, 2006
Jkt 211001
32.608Interest.
32.608–1Interest charges.
32.608–2Interest credits.
32.609 Delays in receipt of notices or
demands.
32.610 Compromising debts.
32.611 Contract clause.
2. Scope of Subpart. Revise FAR
32.600 to provide a more accurate
description of the scope of this FAR
subpart. FAR 32.6 prescribes policies
and procedures for identifying,
collecting, and deferring contract debts
(including interest, if applicable).
3. Responsible Official. Replace the
term ‘‘responsible official’’ with the
specific individual/organization
responsible for fulfilling the FAR
requirement. Some of the
responsibilities currently listed are
assigned to one individual/organization
(e.g., the Procuring Contracting Officer)
and other responsibilities are assigned
to another individual/organization (e.g.,
the payment office). To assure a clear
understanding of the process and
applicable duties, the proposed rule
specifies the responsible party for each
required action(e.g., the Procuring
Contracting Officer, the Administrative
Contracting Officer, the payment office,
etc.) rather than referring to all parties
as ‘‘responsible officials.’’
4. Contract Debt – General. Revise
FAR 32.601 to specify what constitutes
a contract debt, rather than how a
contract debt may arise. In addition,
amend this section to include payments
determined to be in excess of contract
limitations for commercial financing,
since such payments constitute a
contract debt.
5. Contract Debt Responsibilities –
Identifying, Demanding Payment,
Collecting, and Liquidating. Add a
section to clearly define the
responsibilities of the contracting officer
and the payment officials to assure an
efficient and non-duplicative process.
Under the proposed rule the––
(a) The contracting officer is
responsible for identifying a contract
debt and demanding payment of a
contract debt. The contracting officer is
prohibited from collecting contract
debts or otherwise liquidating contract
debts (e.g., offsetting the amount of the
debt against existing unpaid bills due
the contractor or allowing contractors to
retain contract debts to cover amounts
that may be payable to the contractor in
the future).
(b) The payment office is responsible
for collecting payment of the contract
debt and liquidating the contract debt.
6. Contract Debt Determinations
Consolidate all discussions of contract
debt determinations in FAR 32.603,
Debt Determinations, including the
PO 00000
Frm 00017
Fmt 4702
Sfmt 4702
62231
responsibility of the contracting officer
in making debt determinations.
7. Tax Credit. Delete the current FAR
32.607 because the referenced tax credit
(Sec. 1481) was repealed on November
5, 1990, by Public Law 101–508.
8. Demand for Payment. Consolidate
all discussions of the demand for
payment in a single section, at FAR
32.604, Demand for Payment to include:
(a) A requirement to issue the demand
letter except in specific circumstances.
(b) A requirement that the demand
letter include accounting information to
enable the payment office to correctly
record the amounts in the proper
accounts.
(c) A requirement that the demand
letter include the amount of interest
owed under statutes that require interest
assessments from the date of
noncompliance to the date of repayment (CAS and TINA).
(d) A paragraph implementing the
requirements of 31 U.S.C. 3717(e)(1) and
the Debt Collection Improvement Act of
1996; and
(e) A paragraph addressing instances
where overpayments exist but a demand
for payment is not necessary.
9. Final Decisions. Consolidate all
discussions of final decisions in a single
section at FAR 32.605, Final Decisions,
to include:
(a) When a final decision must be
issued;
(b) A statement that the due date for
a demand letter is not extended simply
because a final decision is being issued;
(c) A need to obtain evidence of
receipt by the contractor to establish the
starting date for interest computations
and the statute of limitations.
10. Debt Collection. Consolidate all
discussions of debt collection in a single
section, at FAR 32.606, Debt Collection,
to include:
(a) The current requirements at
32.612;
(b) The current requirements for
transferring debts to the Department of
Treasury; and
(c) A requirement to assure the debt
is being collected by maintaining
communication between the contracting
officer and the payment office.
11. Installment Payments and
Deferment of Collection. Clarify
procedures for processing installment
payments and deferment of collection
requests.
12. Interest. Consolidate and simplify
all discussions of interest in a single
section at FAR 32.608, Interest, to
include:
(a) The substance of the current
language at 32.614;
(b) Computing interest on
overpayments.
E:\FR\FM\24OCP1.SGM
24OCP1
62232
Federal Register / Vol. 71, No. 205 / Tuesday, October 24, 2006 / Proposed Rules
Dated: October 6, 2006.
Ralph De Stefano,
Director, Contract Policy Division.
B. Regulatory Flexibility Act
13.401
The Councils do not expect this
proposed rule to have a significant
economic impact on a substantial
number of small entities within the
meaning of the Regulatory Flexibility
Act, 5 U.S.C. 601, et seq., because the
regulatory changes are predominantly
internal operating procedures for
contracting officers and will not
significantly change duties of small
entities under their contracts. An Initial
Regulatory Flexibility Analysis has,
therefore, not been performed. We invite
comments from small businesses and
other interested parties. The Councils
will consider comments from small
entities concerning the affected FAR
Part(s) 12, 13, 32, 33, 36, 42, and 52 in
accordance with 5 U.S.C. 610. Interested
parties must submit such comments
separately and should cite 5 U.S.C. 601,
et seq. (FAR case 2005–018), in
correspondence.
*
C. Paperwork Reduction Act
rmajette on PROD1PC67 with PROPOSALS1
13. FAR 12.215 and 32.008 –
Notification of Overpayment. Revise
FAR 32.008 to specifically state the
responsibilities of the contracting officer
when notified by the contractor of a
duplicate payment or that the
Government has otherwise overpaid. In
addition, amend FAR 12.215 to include
reference to the requirement in FAR
32.604.
14. FAR Contract Clauses – Payment.
Revise the contract clauses at FAR
52.212–4(i)(5)and (6); 52.232–25(d);
52.232–26(c); and FAR 52.232–27(l) to
assure that the contractor remits
payment to the payment office (rather
than the contracting officer) and the
payment office is able to properly
account for the remittance.
15. FAR 52.232–17, Interest. Revise
FAR 52.232–17 to conform with the
other proposed revisions.
This is not a significant regulatory
action and, therefore, was not subject to
review under Section 6(b) of Executive
Order 12866, Regulatory Planning and
Review, dated September 30, 1993. This
rule is not a major rule under 5 U.S.C.
804.
Subpart 32.6—Contract Debts
Sec.
32.600 Scope of subpart.
32.601 General.
32.602 Responsibilities.
32.603 Debt determination.
32.604 Demand for payment.
32.605 Final decisions.
32.606 Debt collection.
32.607 Installment payments and deferment
of collection.
32.607–1 Installment payments.
32.607–2 Deferment of collection.
32.608 Interest.
The Paperwork Reduction Act does
not apply because the proposed changes
to the FAR do not impose information
collection requirements that require the
approval of the Office of Management
and Budget under 44 U.S.C. 3501, et
seq.
List of Subjects in 48 CFR Parts 12, 13,
32, 33, 36, 42, and 52
Government procurement.
VerDate Aug<31>2005
14:24 Oct 23, 2006
Jkt 211001
Therefore, DoD, GSA, and NASA
propose amending 48 CFR parts 12, 13,
32, 33, 36, 42, and 52 as set forth below:
1. The authority citation for 48 CFR
parts 12, 13, 32, 33, 36, 42, and 52
continues to read as follows:
Authority: 40 U.S.C. 121(c); 10 U.S.C.
chapter 137; and 42 U.S.C. 2473(c).
PART 12—ACQUISITION OF
COMMERCIAL ITEMS
2. Revise section 12.215 to read as
follows:
12.215
Notification of Overpayment.
If the contractor notifies the
contracting officer of a duplicate
payment or that the Government has
otherwise overpaid, the contracting
officer shall follow the procedures at
32.604.
PART 13—SIMPLIFIED ACQUISITION
PROCEDURES
3. Revise section 13.401 (b) to read as
follows:
General.
*
*
*
*
(b) The contracting officer shall be
primarily responsible for determining
the amount of debts resulting from
failure of contractors to properly
replace, repair, or correct supplies lost,
damaged, or not conforming to purchase
requirements (see 32.602 and 32.603).
*
*
*
*
*
PART 32—CONTRACT FINANCING
4. Revise section 32.008 to read as
follows:
32.008
Notification of Overpayment.
If the contractor notifies the
contracting officer of a duplicate
payment or that the Government has
otherwise overpaid, the contracting
officer shall follow the procedures at
32.604.
5. Revise subpart 32.6 to read as
follows:
PO 00000
Frm 00018
Fmt 4702
Sfmt 4702
32.608–1 Interest charges.
32.608–2 Interest credits.
32.609 Delays in receipt of notices or
demands.
32.610 Compromising debts.
32.611 Contract clause.
32.600
Scope of Subpart.
This subpart prescribes policies and
procedures for identifying, collecting,
and deferring contract debts(including
interest, if applicable). Sections 32.607,
32.608, and 32.610 of this subpart do
not apply to claims against common
carriers for transportation overcharges
and freight and cargo losses (31 U.S.C.
3726).
32.601
General.
(a) Contract debts are amounts that—
(1) Have been paid to a contractor to
which the contractor is not currently
entitled under the terms and conditions
of the contract; or
(2) Are otherwise due from the
contractor under the terms and
conditions of the contract.(b) Contract
debts include, but are not limited to, the
following:
(1) Billing and price reductions
resulting from contract terms for price
redetermination or for determination of
prices under incentive type contracts.
(2) Price or cost reductions for
defective cost or pricing data.
(3) Financing payments determined to
be in excess of the contract limitations
at 52.232–16(a)(7), Progress Payments,
or 52.232–32(d)(2), Performance-Based
Payments, or any contract clause for
commercial item financing.
(4) Increases to financing payment
liquidation rates.
(5) Overpayments disclosed by
quarterly statements required under
price redetermination or incentive
contracts.
(6) Price adjustments resulting from
Cost Accounting Standards (CAS)
noncompliances or changes in cost
accounting practice.
(7) Reinspection costs for
nonconforming supplies or services.
(8) Duplicate or erroneous payments.
(9) Damages or excess costs related to
defaults in performance.
(10) Breach of contract obligations
concerning progress payments,
performance based payments, advance
payments, commercial item financing,
or Government-furnished property.
(11) Government expense of
correcting defects.
(12) Overpayments related to errors in
quantity or billing or deficiencies in
quality.
(13) Delinquency in contractor
payments due under agreements or
arrangements for deferral or
postponement of collections.
E:\FR\FM\24OCP1.SGM
24OCP1
Federal Register / Vol. 71, No. 205 / Tuesday, October 24, 2006 / Proposed Rules
(14) Reimbursement of amounts due
under 33.102(b)(3) and 33.104(h)(8).
32.602
Responsibilities.
(a) The contracting officer has primary
responsibility for identifying and
demanding payment of contract debts
except those resulting from errors made
by the payment office. The contracting
officer shall not collect contract debts or
otherwise agree to liquidate contract
debts (e.g. offset the amount of the debt
against existing unpaid bills due the
contractor, or allow contractors to retain
contract debts to cover amounts that
may become payable in future periods.
(b) The payment office has primary
responsibility for—
(1) Collecting contract debts identified
by contracting officers;
(2) Identifying and collecting
duplicate and erroneous payments; and
(3) Authorizing the liquidation of
contract debts in accordance with
agency procedures.
32.603
Debt determination.
(a) If the contracting officer has any
indication that a contractor owes money
to the Government under a contract, the
contracting officer shall determine
promptly whether an actual debt is due
and the amount. Any unnecessary delay
may contribute to—
(1) Loss of timely availability of the
funds to the program for which the
funds were initially provided;
(2) Increased difficulty in collecting
the debt; or
(3) Actual monetary loss to the
Government.
(b) The amount of indebtedness
determined unilaterally by the
contracting officer shall be an amount
that—
(1) Is based on the merits of the case;
and
(2) Is consistent with the contract
terms.
rmajette on PROD1PC67 with PROPOSALS1
32.604
Demand for payment.
(a) Except as provided in paragraph
(c) of this section, the contracting officer
shall take the following actions:
(1) Issue the demand for payment as
soon as the contracting officer has
determined that an actual debt is due
the Government and the amount.
(2) Issue a demand for payment even
if—
(i) The debt is or will be the subject
of a bilateral modification;
(ii) The contractor is otherwise
obligated to pay the money under the
existing contract terms; or
(iii) The contractor has agreed to
repay the debt.
(3) Issue the demand for payment as
a part of the final decision, if a final
decision is required by 32.605(a).
VerDate Aug<31>2005
14:24 Oct 23, 2006
Jkt 211001
(b) The demand for payment shall
include the following:
(1) A description of the debt,
including the debt amount.
(2) A distribution of the principal
amount of the debt by line(s) of
accounting subject to the following:
(i) If the debt affects multiple lines of
accounting, the contracting officer shall,
to the maximum extent practicable,
identify all affected lines of accounting.
If it is not practicable to identify all
affected lines of accounting, the
contracting officer may select
representative lines of accounting in
accordance with paragraph (b)(2)(ii) of
this section.
(ii) In selecting representative lines of
accounting, the contracting officer
shall—
(A) Consider the affected departments
or agencies, years of appropriations, and
the predominant types of
appropriations;
(B) Not distribute to any line of
accounting an amount of the principal
in excess of the total obligation for the
line of accounting; and
(iii) Include the lines of accounting
even if the associated funds are expired
or cancelled. While cancelled funds will
be deposited in a miscellaneous receipt
account of the Treasury if collected, the
funds are tracked under the closed year
appropriation(s) to comply with the
Anti-Deficiency Act.
(iv) If the debt affects multiple
contracts and the lines of accounting are
not readily available, the contracting
officer shall—
(A) Issue the demand for payment
without the distribution of the principal
amount to the affected lines of
accounting;
(B) Include a statement in the demand
for payment advising when the
distribution will be provided; and
(C) Provide the distribution by the
date identified in the demand for
payment.
(3) The basis for and amount of any
accrued interest or penalty.
(4)(i) For debts resulting from specific
contract terms (e.g., debts resulting from
incentive clause provisions, Quarterly
Limitation on Payments Statement, Cost
Accounting Standards, price reduction
for defective pricing), a notification
stating that payment should be made
promptly, and that interest is due in
accordance with the terms of the
contract. Interest shall be computed
from the date specified in the applicable
contract clause until repayment by the
contractor. The interest rate shall be the
rate specified in the applicable contract
clause.
(ii) For all other contract debts, a
notification stating that any amounts not
PO 00000
Frm 00019
Fmt 4702
Sfmt 4702
62233
paid within 30 days from the date of the
demand for payment will bear interest.
Interest shall be computed from the date
of the demand for payment until
repayment by the contractor. The
interest rate shall be the interest rate
established by the Secretary of the
Treasury, as provided in Section 611 of
the Contract Disputes Act of 1978
(Public Law 95–563), which is
applicable to the period in which the
amount becomes due, and then at the
rate applicable for each six-month
period as established by the Secretary
until the amount is paid.
(iii) In the case of a debt arising from
a price reduction for defective pricing,
or as specifically set forth in a Cost
Accounting Standards (CAS) clause in
the contract, interest is computed from
the date of overpayment by the
Government until repayment by the
contractor at the underpayment rate
established by the Secretary of the
Treasury, for the periods affected, under
26 U.S.C. 6621(a)(2).
(5) A statement advising the
contractor—
(i) To contact the contracting officer if
the contractor believes the debt is
invalid or the amount is incorrect; and
(ii) To remit a check payable to the
‘‘Treasurer of the United States’’
annotated with the contract number
along with a copy of the demand for
payment to the payment office
identified in the contract or as otherwise
specified in the demand letter in
accordance with agency procedures.
(6) Notification that the payment
office may offset the debt against any
payments otherwise due the contractor.
(7) Notification that the debt is subject
to administrative charges in accordance
with the requirements of 31 U.S.C.
3717(e) and the Debt Collection
Improvement Act of 1996.
(8) A notification that the contractor
may submit a request for installment
payments or deferment of collection if
immediate payment is not practicable or
if the amount is disputed.
(c) Except as provided in paragraph
(d) of this section, the contracting officer
should not issue a demand for payment
if the contracting officer only becomes
aware of the debt when the contractor—
(1) Provides a lump sum payment or
submits a credit invoice. (A credit
invoice is a contractor’s request to
liquidate the debt against existing
unpaid bills due the contractor); or
(2) Notifies the contracting officer that
the payment office overpaid on an
invoice payment. When the contractor
provides the notification, the
contracting officer shall notify the
payment office of the overpayment.
E:\FR\FM\24OCP1.SGM
24OCP1
62234
Federal Register / Vol. 71, No. 205 / Tuesday, October 24, 2006 / Proposed Rules
(d) If a demand for payment was not
issued as provided for in paragraph (c)
of this section, the contracting officer
shall issue a demand for payment no
sooner than 30 days after the contracting
officer becomes aware of the debt
unless—
(i) The contractor has liquidated the
debt;
(ii) The contractor has requested an
installment payment agreement; or
(iii) The payment office has issued a
demand for payment.
(e) The contracting officer shall—
(1) Furnish a copy of the demand for
payment to the contractor by certified
mail, return receipt requested, or by any
other method that provides evidence of
receipt; and
(2) Forward a copy of the demand to
the payment office.
32.605
Final decisions.
(a) The contracting officer shall issue
a final decision as required by 33.211 if–
(1) The contracting officer and the
contractor are unable to reach agreement
on the existence or amount of a debt in
a timely manner;
(2) The contractor fails to liquidate a
debt previously demanded by the
contracting officer within the timeline
specified in the demand for payment
unless the amounts were not repaid
because the contractor has requested an
installment payment agreement; or
(3) The contractor requests a
deferment of collection on a debt
previously demanded by the contracting
officer (see 32.607–2).
(b) If a demand for payment was
previously issued for the debt, the
demand for payment included in the
final decision shall identify the same
due date as the original demand for
payment.
(c) The contracting officer shall–
(1) Furnish the decision to the
contractor by certified mail, return
receipt requested, or by any other
method that provides evidence of
receipt; and
(2) Forward a copy to the payment
office identified in the contract.
rmajette on PROD1PC67 with PROPOSALS1
32.606
Debt collection.
(a) If the contractor has not liquidated
the debt within 30 days of the date due
or requested installment payments or
deferment of collection, the payment
office initiates withholding of principal,
interest, penalties, and administrative
charges. In the event the contract is
assigned under the Assignment of
Claims Act of 1940 (31 U.S.C. 3727 and
41 U.S.C. 15), the rights of the assignee
will be scrupulously respected and
withholding of payments shall be
consistent with those rights. For
VerDate Aug<31>2005
14:24 Oct 23, 2006
Jkt 211001
additional information on assignment of
claims, see Subpart 32.8.
(b) As provided for in the Debt
Collection Improvement Act of 1996,
payment offices are required to transfer
any debt that is delinquent more than
180 days to the Department of Treasury
for collection.
(c) The contracting officer shall
periodically follow up with the payment
office to determine whether the debt has
been collected and credited to the
correct appropriation(s).
32.607 Installment payments and
deferment of collection.
(a) The contracting officer shall not
approve or deny a contractor’s request
for installment payments or deferment
of collections. The office designated in
agency procedures is responsible for
approving or denying requests for
installment payments or deferment of
collections.
(b) If a contractor has not appealed the
debt or filed an action under the
Disputes clause of the contract and the
contractor has submitted a proposal for
debt deferment or installment
payments–
(1) The office designated in agency
procedures may arrange for deferment/
installment payments if the contractor is
unable to pay at once in full or the
contractor’s operations under national
defense contracts would be seriously
impaired. The arrangement shall
include appropriate covenants and
securities and should be limited to the
shortest practicable maturity; and
(2) The deferment/installment
agreement shall include a specific
schedule or plan for payment. It should
permit the Government to make
periodic financial reviews of the
contractor and to require payments
earlier than required by the agreement if
the Government considers the
contractor’s ability to pay improved. It
should also provide for required stated
or measurable payments on the
occurrence of specific events or
contingencies that improve the
contractor’s ability to pay.
(c) If not already applicable under the
contract terms, interest on contract debt
shall be made an element of any
agreement entered into an installment
payment or deferment of collection
agreement.
32.607–1
Installment payments.
If a contractor requests an installment
payment agreement, the contracting
officer shall notify the contractor to
send a written request for installment
payments to the office designated in
agency procedures.
PO 00000
Frm 00020
Fmt 4702
Sfmt 4702
32.607–2
Deferment of collection.
(a) All requests for deferment of
collection must be submitted in writing
to the contracting officer.
(1) If the contractor has appealed the
debt under the procedures of the
Disputes clause of the contract, the
information with the request for
deferment may be limited to an
explanation of—
(i) The contractor’s financial
condition; and
(ii) Whether deferment of the debt
collection is advisable to avoid possible
overcollection.
(2) If there is no appeal pending or
action filed under the Disputes clause of
the contract, the following information
about the contractor should be
submitted with the request:
(i) Financial condition.
(ii) Contract backlog.
(iii) Projected cash receipts and
requirements.
(iv) The feasibility of immediate
payment of the debt.
(v) The probable effect on operations
of immediate payment in full.
(vi) Whether deferment of the debt
collection is advisable to avoid possible
over collection.
(b) Upon receipt of the contractor’s
written request, the contracting officer
shall promptly provide a notification to
the payment office and advise the
payment office that the contractor’s
request is under consideration. Prompt
notification is required to ensure that
the payment office does not begin
collection while the deferment request
is being considered.
(c)(1) The contracting officer shall
forward the following to the office
designated in agency procedures for a
decision:
(i) A copy of the contractor’s request
for a deferment of collection.
(ii) A written recommendation on the
request and the basis for the
recommendation including the
advisability of deferment to avoid
possible overcollections.
(iii) A statement as to whether the
contractor has an appeal pending or
action filed under the Disputes clause of
the contract and the docket number if
the appeal has been filed.
(iv) A copy of the contracting officer’s
final decision (see 32.605).
(2) The contracting officer should
consider any information necessary to
develop a recommendation on the
deferment request.
(d) The office designated in agency
procedures may authorize a deferment
pending the resolution of appeal to
avoid possible overcollections. The
agency is required to use current year
unexpired funds to pay interest on
overcollections.
E:\FR\FM\24OCP1.SGM
24OCP1
rmajette on PROD1PC67 with PROPOSALS1
Federal Register / Vol. 71, No. 205 / Tuesday, October 24, 2006 / Proposed Rules
(e) Deferments pending disposition of
appeal may be granted to small business
concerns and financially weak
contractors, with a reasonable balance of
the need for Government security
against loss and undue hardship on the
contractor.
(f) Contracts and arrangements for
deferment shall not provide that a claim
of the Government will not become due
and payable pending mutual agreement
on the amount of the claim or, in the
case of a dispute, until the decision is
reached.
(g) At a minimum, the deferment
agreement shall contain the following:
(1) A description of the debt.
(2) The date of first demand for
payment.
(3) Notice of an interest charge, in
conformity with FAR 32.608 and the
FAR clause at 52.232–17, Interest; or, in
the case of a debt arising from a
defective pricing or a CAS
noncompliance overpayment, interest,
as prescribed by the applicable Price
Reduction for Defective Cost or Pricing
Data or CAS clause.
(4) Identification of the office to
which the contractor is to send debt
payments.
(5) A requirement for the contractor to
submit financial information requested
by the Government and for reasonable
access to the contractor’s records and
property by Government
representatives.
(6) Provision for the Government to
terminate the deferment agreement and
accelerate the maturity of the debt if the
contractor defaults or if bankruptcy or
insolvency proceedings are instituted by
or against the contractor.
(7) Protective requirements that are
considered by the Government to be
prudent and feasible in the specific
circumstances. The coverage of
protective terms at 32.409 and 32.501–
5 may be used as a guide.
(h) If a contractor appeal of the debt
determination is pending, the deferment
agreement shall also include a
requirement that the contractor shall —;
(1) Diligently prosecute the appeal;
and
(2) Pay the debt in full when the
appeal is decided, or when the parties
reach agreement on the debt amount.
(i) The deferment agreement may
provide for the right to make early
payments without prejudice, for refund
of overpayments, and for crediting of
interest.
(j) Actions filed by contractors under
the Disputes clause shall not suspend or
delay collection. Until the action is
decided, deferments shall only be
granted if, within 30 days after the filing
of such action, the contractor presents to
VerDate Aug<31>2005
14:24 Oct 23, 2006
Jkt 211001
the office designated in agency
procedures a good and sufficient bond,
or other acceptable collateral, in the
amount of the claim, and the deferment
is approved by the office designated in
agency procedures. Any amount
collected by the Government in excess
of the amount found to be due on appeal
under the Disputes clause of the
contract shall be refunded to the
contractor with interest thereon from
the date of collection by the
Government until the date the monies
are remitted to the contractor at the
annual rate established by the Secretary
of Treasury under Public Law 92–41.
Simple interest shall be calculated to
reflect each 6-month period change in
the rates established by the Secretary.
32.608
Interest.
32.608–1
Interest charges.
(a) Unless specified otherwise in the
FAR clause at 52.232–17—
(1) Interest charges shall apply to any
contract debt unpaid after 30 days from
the issuance of a demand for payment
or from any earlier date specified in the
contract unless—
(i) The contract is a kind excluded
under 32.611; or
(ii) The contract or debt has been
exempted from interest charges under
agency procedures.
(2) The interest charge shall be at the
rate established by the Secretary of the
Treasury under Public Law 92–41 for
the period in which the amount
becomes due. The interest charge shall
be computed for the actual number of
calendar days involved beginning on the
due date and ending on—
(i) The date on which the designated
office receives payment from the
contractor;
(ii) The date of issuance of a
Government check to the contractor
from which an amount otherwise
payable has been withheld as a credit
against the contract debt; or
(iii) The date on which an amount
withheld and applied to the contract
debt would otherwise have become
payable to the contractor.
(b) If not already applicable under the
contract terms, interest on contract debt
shall be made an element of any
agreement entered into on installment
payment and deferment of collection
agreements.
32.608–2
Interest credits.
(a) An equitable interest credit shall
be applied under the following
circumstances:
(1) When the amount of debt initially
determined is subsequently reduced;
e.g., through a successful appeal.
PO 00000
Frm 00021
Fmt 4702
Sfmt 4702
62235
(2) When the collection procedures
followed in a given case result in an
over collection of the debt due.
(3) When the responsible official
determines that the Government has
unduly delayed payments to the
contractor on the same contract at some
time during the period to which the
interest charge applied, provided an
interest penalty was not paid for such
late payment.
(b) Any appropriate interest credits
shall be computed under the following
procedures:
(1) Interest at the rate under paragraph
(b) of the FAR clause at 52.232–17 and
32.608–1(a)(2) shall be charged on the
reduced debt from the date specified in
the first demand made for payment of
the higher debt.
(2) Interest may not be reduced for
any time between the due date under
the demand and the period covered by
a deferment of collection, unless the
contract includes an interest clause; e.g.,
the clause prescribed in 32.611.
(3) Interest shall not be credited in an
amount that, when added to other
amounts refunded or released to the
contractor, exceeds the total amount
that has been collected, or withheld for
the purpose of collecting the debt. This
limitation shall be further reduced by
the amount of any limitation applicable
under paragraph (b)(2) of this
subsection.
32.609 Delays in receipt of notices or
demands.
If interest is accrued based on the date
of the demand letter and delivery of the
demand letter is delayed by the
Government (e.g., undue delay after
dating at the originating office or delays
in the mail), the date of the debt and
accrual of interest shall be extended to
a time that is fair and reasonable under
the particular circumstances.
32.610
Compromising debts.
For debts under $100,000, excluding
interest, if further collection is not
practicable or would cost more than the
amount of recovery, the designated
agency official may compromise the
debt. Compromise is authorized by the
Federal Claims Collection Act (31 U.S.C.
3711). Compromise shall conform to
Federal Claims Collection Standards 31
CFR part 900), and agency regulations.
Unless specifically authorized by
agency procedures, contracting officers
can not compromise debts.
32.611
Contract clause.
(a) The contracting officer shall insert
the clause at 52.232-17, Interest, in
solicitations and contracts unless it is
contemplated that the contract will be
E:\FR\FM\24OCP1.SGM
24OCP1
62236
Federal Register / Vol. 71, No. 205 / Tuesday, October 24, 2006 / Proposed Rules
in one or more of the following
categories:
(1) Contracts at or below the
simplified acquisition threshold.
(2) Contracts with Government
agencies.
(3) Contracts with a State or local
government or instrumentality.
(4) Contracts with a foreign
government or instrumentality.
(5) Contracts without any provision
for profit or fee with a nonprofit
organization.
(6) Contracts described in Subpart 5.5,
Paid Advertisements.
(7) Any other exceptions authorized
under agency procedures.
(b) The contracting officer may insert
the FAR clause at 52.232–17, Interest, in
solicitations and contracts when it is
contemplated that the contract will be
in any of the categories specified in
32.611(a).
PART 33—PROTESTS, DISPUTES,
AND APPEALS
33.208
[Amended]
6. Amend section 33.208(b) by
removing ‘‘32.614’ and adding ‘‘32.608’’
in its place.
33.211
[Amended]
7. Amend section 33.211(a)(vi)by
removing ‘‘32.610(b)’’ and adding
‘‘32.604 and 32.605’’ in its place.
PART 36—CONSTRUCTION AND
ARCHITECT-ENGINEER CONTRACTS
36.608
[Amended]
8. Amend section 36.608 in the fourth
sentence by removing ‘‘collect’’ and
adding ‘‘issue a demand for payment of
the amount due’’ in its place.
PART 42—CONTRACT
ADMINISTRATION AND AUDIT
SERVICES
9. Amend section 42.302 by revising
paragraph (a)(17) to read as follows:
42.302
Contract administration functions.
(a) * * *
(17) Analyze quarterly limitation on
payments statements and take action in
accordance with Subpart 32.6 to recover
overpayments from the contractor.
*
*
*
*
*
rmajette on PROD1PC67 with PROPOSALS1
PART 52—SOLICITATION PROVISIONS
AND CONTRACT CLAUSES
10. Amend section 52.212–4 by
revising the date of the clause and
paragraph (i)(5); and adding paragraph
(i)(6) to read as follows:
52.212–4 Contract Terms and
Conditions—Commercial Items.
*
*
*
VerDate Aug<31>2005
*
*
14:24 Oct 23, 2006
Jkt 211001
CONTRACT TERMS AND CONDITIONS—
COMMERCIAL ITEMS–(DATE)
*
*
*
*
*
(i) * * *
(5) Overpayments. If the Contractor
becomes aware of a duplicate contract
financing or invoice payment or that the
Government has otherwise overpaid on
a contract financing or invoice payment,
the Contractor shall take the following
actions:
(i) Remit the overpayment amount to
the payment office cited in the contract
along with a description of the
overpayment including the—
(A) Circumstances of the overpayment
(e.g., duplicate payment, erroneous
payment, liquidation errors, date(s) of
overpayment);
(B) Affected contract number and
delivery order number if applicable;
(C) Affected contract line item or
subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance
and supporting documentation to the
Contracting Officer.
(6) Interest. (i) All amounts that
become payable by the Contractor to the
Government under this contract shall
bear simple interest from the date due
until paid unless paid within 30 days of
becoming due. The interest rate shall be
the interest rate established by the
Secretary of the Treasury as provided in
Section 611 of the Contract Disputes Act
of 1978 (Public Law 95–563), which is
applicable to the period in which the
amount becomes due, as provided in
paragraph (b) of this clause and then at
the rate applicable for each six-month
period as fixed by the Secretary until
the amount is paid.
(ii) Amounts shall be due at the
earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written
demand for payment consistent with
this contract, including any demand for
payment resulting from a default
termination.
(iii) The interest charge shall be
computed for the actual number of
calendar days involved beginning on the
due date and ending on—
(A) The date on which the designated
office receives payment from the
Contractor;
(B) The date of issuance of a
Government check to the Contractor
from which an amount otherwise
payable has been withheld as a credit
against the contract debt; or
(C) The date on which an amount
withheld and applied to the contract
debt would otherwise have become
payable to the Contractor.
(iv) The interest charge made under
this clause may be reduced under the
PO 00000
Frm 00022
Fmt 4702
Sfmt 4702
procedures prescribed in 32.608–2 of
the Federal Acquisition Regulation in
effect on the date of this contract.
*
*
*
*
*
11. Revise section 52.232–17 to read
as follows:
52.232–17
Interest.
As prescribed in 32.611(a) and (b),
insert the following clause:
INTEREST (DATE)
(a) Except as otherwise provided in
this contract under a Price Reduction for
Defective Cost or Pricing Data clause or
a Cost Accounting Standards clause, all
amounts that become payable by the
Contractor to the Government under this
contract shall bear simple interest from
the date due until paid unless paid
within 30 days of becoming due. The
interest rate shall be the interest rate
established by the Secretary of the
Treasury as provided in Section 611 of
the Contract Disputes Act of 1978
(Public Law 95–563), which is
applicable to the period in which the
amount becomes due, as provided in
paragraph (b) of this clause, and then at
the rate applicable for each six-month
period as fixed by the Secretary until
the amount is paid.
(b) Amounts shall be due at the
earliest of the following dates:
(1) The date fixed under this contract.
(2) The date of the first written
demand for payment consistent with
this contract, including any demand for
payment resulting from a default
termination.
(c) The interest charge shall be
computed for the actual number of
calendar days involved beginning on the
due date and ending on—
(1) The date on which the designated
office receives payment from the
Contractor;
(2) The date of issuance of a
Government check to the Contractor
from which an amount otherwise
payable has been withheld as a credit
against the contract debt; or
(3) The date on which an amount
withheld and applied to the contract
debt would otherwise have become
payable to the Contractor.
(d) The interest charge made under
this clause may be reduced under the
procedures prescribed in 32.608–2 of
the Federal Acquisition Regulation in
effect on the date of this contract.
12. Amend section 52.232–25 by
revising the date of the clause and
paragraph (d) to read as follows:
52.232–25
Prompt Payment.
*
*
*
*
*
PROMPT PAYMENT (DATE)
*
E:\FR\FM\24OCP1.SGM
*
*
24OCP1
*
*
Federal Register / Vol. 71, No. 205 / Tuesday, October 24, 2006 / Proposed Rules
(d) Overpayments. If the Contractor
becomes aware of a duplicate contract
financing or invoice payment or that the
Government has otherwise overpaid on
a contract financing or invoice payment,
the Contractor shall—
(1) Remit the overpayment amount to
the payment office cited in the contract
along with a description of the
overpayment including the—
(i) Circumstances of the overpayment
(e.g., duplicate payment, erroneous
payment, liquidation errors, date(s) of
overpayment);
(ii) Affected contract number and
delivery order number if applicable;
(iii) Affected contract line item or
subline item, if applicable; and
(iv) Contractor point of contact.
(2) Provide a copy of the remittance
and supporting documentation to the
Contracting Officer.
(End of clause)
13. Amend section 52.232–26 by
revising the date of the clause and
paragraph (c) to read as follows:
rmajette on PROD1PC67 with PROPOSALS1
*
*
*
VerDate Aug<31>2005
*
*
14:24 Oct 23, 2006
Jkt 211001
PROMPT PAYMENT FOR FIXED-PRICE
ARCHITECT-ENGINEER CONTRACTS
(DATE)
52.232–27 Prompt Payment for
Construction Contracts.
*
PROMPT PAYMENT FOR CONSTRUCTION
CONTRACTS (DATE)
*
*
*
*
(c) Overpayments. If the Contractor
becomes aware of a duplicate contract
financing or invoice payment or that the
Government has otherwise overpaid on
a contract financing or invoice payment,
the Contractor shall—
(1) Remit the overpayment amount to
the payment office cited in the contract
along with a description of the
overpayment including the—
(i) Circumstances of the overpayment
(e.g., duplicate payment, erroneous
payment, liquidation errors, date(s) of
overpayment);
(ii) Affected contract number and
delivery order number if applicable;
(iii) Affected contract line item or
subline item, if applicable; and
(iv) Contractor point of contact.
(2) Provide a copy of the remittance
and supporting documentation to the
Contracting Officer.
(End of clause)
52.232–26 Prompt Payment for Fixed-Price
Architect-Engineer Contracts.
62237
14. Amend section 52.232–27 by
revising the date of the clause and
paragraph (l) to read as follows:
PO 00000
Frm 00023
Fmt 4702
Sfmt 4702
*
*
*
*
*
*
*
*
*
*
(l) Overpayments. If the Contractor
becomes aware of a duplicate contract
financing or invoice payment or that the
Government has otherwise overpaid on
a contract financing or invoice payment,
the Contractor shall—
(1) Remit the overpayment amount to
the payment office cited in the contract
along with a description of the
overpayment including the—
(i) Circumstances of the overpayment
(e.g., duplicate payment, erroneous
payment, liquidation errors, date(s) of
overpayment);
(ii) Affected contract number and
delivery order number if applicable;
(iii) Affected contract line item or
subline item, if applicable; and
(iv) Contractor point of contact.
(2) Provide a copy of the remittance
and supporting documentation to the
Contracting Officer.
(End of clause)
[FR Doc. 06–8806 Filed 10–23–06; 8:45 am]
BILLING CODE 6820–EP–S
E:\FR\FM\24OCP1.SGM
24OCP1
Agencies
[Federal Register Volume 71, Number 205 (Tuesday, October 24, 2006)]
[Proposed Rules]
[Pages 62230-62237]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 06-8806]
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
GENERAL SERVICES ADMINISTRATION
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
48 CFR Parts 12, 13, 32, 33, 36, 42, and 52
[FAR Case 2005-018]
RIN: 9000-AK59: Docket 2006-0020; Sequence 11
Federal Acquisition Regulation; FAR Case 2005-018, Contract Debts
AGENCIES: Department of Defense (DoD), General Services Administration
(GSA), and National Aeronautics and Space Administration (NASA).
ACTION: Proposed rule.
-----------------------------------------------------------------------
SUMMARY: The Civilian Agency Acquisition Council and the Defense
Acquisition Regulations Council (Councils) are proposing to amend the
Federal Acquisition Regulation (FAR) to revise the policies and
procedures for contract debts.
DATES: Interested parties should submit written comments to the FAR
Secretariat on or before December 26, 2006 to be considered in the
formulation of a final rule.
ADDRESSES: Submit comments identified by FAR case 2005-018 by any of
the following methods:
Federal eRulemaking Portal: https://www.regulations.gov.
Search for any document by first selecting the proper document types
and selecting ``Federal Acquisition Regulation'' as the agency of
choice. At the ``Keyword'' prompt, type in the FAR case number (for
example, FAR Case 2006-001) and click on the ``Submit'' button. You may
also search for any document by clicking on the ``Advanced search/
document search'' tab at the top of the screen, selecting from the
agency field ``Federal Acquisition Regulation'', and typing the FAR
case number in the keyword field. Select the ``Submit'' button.
Fax: 202-501-4067.
Mail: General Services Administration, Regulatory
Secretariat (VIR), 1800 F Street, NW, Room 4035, ATTN: Laurieann
Duarte, Washington, DC 20405.
Instructions: Please submit comments only and cite FAR case 2005-
018 in all correspondence related to this case. All comments received
will be posted without change to https://www.regulations.gov, including
any personal and/or business confidential information provided.
[[Page 62231]]
FOR FURTHER INFORMATION CONTACT: Mr. Jeremy Olson at (202) 501-3221
for clarification of content. For information pertaining to status or
publication schedules, contact the FAR Secretariat at (202) 501-4755.
Please cite FAR case 2005-018.
SUPPLEMENTARY INFORMATION:
A. Background
In 2003, the DoD Comptroller established the DoD Accounts
Receivable Workgroup to evaluate the processes and procedures for
reporting accounts receivables. This Workgroup concluded that
contracting officers may not be properly reporting contract debts.
Based on the Workgroup's recommendations, DoD established a Contract
Debt Integrated Process Team (IPT).
The mission of the IPT was to evaluate the adequacy of DoD's
existing controls and procedures for ensuring that contract debts are
identified and recovered in a timely manner, properly accounted for in
DoD's books and records, and properly coordinated with the appropriate
Government Officials. Contract debts result from compliance, or a
failure to comply, with the terms of a contract and include debts
identified by auditors, contracting officers, disbursing officials, and
contractors. On May 26, 2005, a final report was issued that included a
number of recommended FAR changes to improve contract debt controls and
procedures, and to ensure consistency within/between existing
regulations.
The Councils established this case to evaluate the DoD
recommendations. As a result of this review, the Councils are proposing
the revisions discussed below. In addition, the Councils are
considering whether the current provisions regarding interest
provisions are sufficient. In particular, concerns have been expressed
over the current timeline for computing interest. The Councils agreed
to defer this issue for consideration to a later date (including a
possible public meeting).
1. Reorganize FAR Subpart 32.6. Reorganizes FAR Subpart 32.6 to add
clarity and provide a logical sequence. The Subpart has been
reorganized as follows:
32.600 Scope of subpart.
32.601 General.
32.602 Responsibilities.
32.603 Debt determination.
32.604 Demand for payment.
32.605 Final decisions.
32.606 Debt collection.
32.607 Installment payments and deferment of collection.
32.607-1Installment payments.
32.607-2Deferment of collection.
32.608Interest.
32.608-1Interest charges.
32.608-2Interest credits.
32.609 Delays in receipt of notices or demands.
32.610 Compromising debts.
32.611 Contract clause.
2. Scope of Subpart. Revise FAR 32.600 to provide a more accurate
description of the scope of this FAR subpart. FAR 32.6 prescribes
policies and procedures for identifying, collecting, and deferring
contract debts (including interest, if applicable).
3. Responsible Official. Replace the term ``responsible official''
with the specific individual/organization responsible for fulfilling
the FAR requirement. Some of the responsibilities currently listed are
assigned to one individual/organization (e.g., the Procuring
Contracting Officer) and other responsibilities are assigned to another
individual/organization (e.g., the payment office). To assure a clear
understanding of the process and applicable duties, the proposed rule
specifies the responsible party for each required action(e.g., the
Procuring Contracting Officer, the Administrative Contracting Officer,
the payment office, etc.) rather than referring to all parties as
``responsible officials.''
4. Contract Debt - General. Revise FAR 32.601 to specify what
constitutes a contract debt, rather than how a contract debt may arise.
In addition, amend this section to include payments determined to be in
excess of contract limitations for commercial financing, since such
payments constitute a contract debt.
5. Contract Debt Responsibilities - Identifying, Demanding Payment,
Collecting, and Liquidating. Add a section to clearly define the
responsibilities of the contracting officer and the payment officials
to assure an efficient and non-duplicative process. Under the proposed
rule the--
(a) The contracting officer is responsible for identifying a
contract debt and demanding payment of a contract debt. The contracting
officer is prohibited from collecting contract debts or otherwise
liquidating contract debts (e.g., offsetting the amount of the debt
against existing unpaid bills due the contractor or allowing
contractors to retain contract debts to cover amounts that may be
payable to the contractor in the future).
(b) The payment office is responsible for collecting payment of the
contract debt and liquidating the contract debt.
6. Contract Debt Determinations Consolidate all discussions of
contract debt determinations in FAR 32.603, Debt Determinations,
including the responsibility of the contracting officer in making debt
determinations.
7. Tax Credit. Delete the current FAR 32.607 because the referenced
tax credit (Sec. 1481) was repealed on November 5, 1990, by Public Law
101-508.
8. Demand for Payment. Consolidate all discussions of the demand
for payment in a single section, at FAR 32.604, Demand for Payment to
include:
(a) A requirement to issue the demand letter except in specific
circumstances.
(b) A requirement that the demand letter include accounting
information to enable the payment office to correctly record the
amounts in the proper accounts.
(c) A requirement that the demand letter include the amount of
interest owed under statutes that require interest assessments from the
date of noncompliance to the date of re-payment (CAS and TINA).
(d) A paragraph implementing the requirements of 31 U.S.C.
3717(e)(1) and the Debt Collection Improvement Act of 1996; and
(e) A paragraph addressing instances where overpayments exist but a
demand for payment is not necessary.
9. Final Decisions. Consolidate all discussions of final decisions
in a single section at FAR 32.605, Final Decisions, to include:
(a) When a final decision must be issued;
(b) A statement that the due date for a demand letter is not
extended simply because a final decision is being issued;
(c) A need to obtain evidence of receipt by the contractor to
establish the starting date for interest computations and the statute
of limitations.
10. Debt Collection. Consolidate all discussions of debt collection
in a single section, at FAR 32.606, Debt Collection, to include:
(a) The current requirements at 32.612;
(b) The current requirements for transferring debts to the
Department of Treasury; and
(c) A requirement to assure the debt is being collected by
maintaining communication between the contracting officer and the
payment office.
11. Installment Payments and Deferment of Collection. Clarify
procedures for processing installment payments and deferment of
collection requests.
12. Interest. Consolidate and simplify all discussions of interest
in a single section at FAR 32.608, Interest, to include:
(a) The substance of the current language at 32.614;
(b) Computing interest on overpayments.
[[Page 62232]]
13. FAR 12.215 and 32.008 - Notification of Overpayment. Revise FAR
32.008 to specifically state the responsibilities of the contracting
officer when notified by the contractor of a duplicate payment or that
the Government has otherwise overpaid. In addition, amend FAR 12.215 to
include reference to the requirement in FAR 32.604.
14. FAR Contract Clauses - Payment. Revise the contract clauses at
FAR 52.212-4(i)(5)and (6); 52.232-25(d); 52.232-26(c); and FAR 52.232-
27(l) to assure that the contractor remits payment to the payment
office (rather than the contracting officer) and the payment office is
able to properly account for the remittance.
15. FAR 52.232-17, Interest. Revise FAR 52.232-17 to conform with
the other proposed revisions.
This is not a significant regulatory action and, therefore, was not
subject to review under Section 6(b) of Executive Order 12866,
Regulatory Planning and Review, dated September 30, 1993. This rule is
not a major rule under 5 U.S.C. 804.
B. Regulatory Flexibility Act
The Councils do not expect this proposed rule to have a significant
economic impact on a substantial number of small entities within the
meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq.,
because the regulatory changes are predominantly internal operating
procedures for contracting officers and will not significantly change
duties of small entities under their contracts. An Initial Regulatory
Flexibility Analysis has, therefore, not been performed. We invite
comments from small businesses and other interested parties. The
Councils will consider comments from small entities concerning the
affected FAR Part(s) 12, 13, 32, 33, 36, 42, and 52 in accordance with
5 U.S.C. 610. Interested parties must submit such comments separately
and should cite 5 U.S.C. 601, et seq. (FAR case 2005-018), in
correspondence.
C. Paperwork Reduction Act
The Paperwork Reduction Act does not apply because the proposed
changes to the FAR do not impose information collection requirements
that require the approval of the Office of Management and Budget under
44 U.S.C. 3501, et seq.
List of Subjects in 48 CFR Parts 12, 13, 32, 33, 36, 42, and 52
Government procurement.
Dated: October 6, 2006.
Ralph De Stefano,
Director, Contract Policy Division.
Therefore, DoD, GSA, and NASA propose amending 48 CFR parts 12, 13,
32, 33, 36, 42, and 52 as set forth below:
1. The authority citation for 48 CFR parts 12, 13, 32, 33, 36, 42,
and 52 continues to read as follows:
Authority: 40 U.S.C. 121(c); 10 U.S.C. chapter 137; and 42
U.S.C. 2473(c).
PART 12--ACQUISITION OF COMMERCIAL ITEMS
2. Revise section 12.215 to read as follows:
12.215 Notification of Overpayment.
If the contractor notifies the contracting officer of a duplicate
payment or that the Government has otherwise overpaid, the contracting
officer shall follow the procedures at 32.604.
PART 13--SIMPLIFIED ACQUISITION PROCEDURES
3. Revise section 13.401 (b) to read as follows:
13.401 General.
* * * * *
(b) The contracting officer shall be primarily responsible for
determining the amount of debts resulting from failure of contractors
to properly replace, repair, or correct supplies lost, damaged, or not
conforming to purchase requirements (see 32.602 and 32.603).
* * * * *
PART 32--CONTRACT FINANCING
4. Revise section 32.008 to read as follows:
32.008 Notification of Overpayment.
If the contractor notifies the contracting officer of a duplicate
payment or that the Government has otherwise overpaid, the contracting
officer shall follow the procedures at 32.604.
5. Revise subpart 32.6 to read as follows:
Subpart 32.6--Contract Debts
Sec.
32.600 Scope of subpart.
32.601 General.
32.602 Responsibilities.
32.603 Debt determination.
32.604 Demand for payment.
32.605 Final decisions.
32.606 Debt collection.
32.607 Installment payments and deferment of collection.
32.607-1 Installment payments.
32.607-2 Deferment of collection.
32.608 Interest.
32.608-1 Interest charges.
32.608-2 Interest credits.
32.609 Delays in receipt of notices or demands.
32.610 Compromising debts.
32.611 Contract clause.
32.600 Scope of Subpart.
This subpart prescribes policies and procedures for identifying,
collecting, and deferring contract debts(including interest, if
applicable). Sections 32.607, 32.608, and 32.610 of this subpart do not
apply to claims against common carriers for transportation overcharges
and freight and cargo losses (31 U.S.C. 3726).
32.601 General.
(a) Contract debts are amounts that--
(1) Have been paid to a contractor to which the contractor is not
currently entitled under the terms and conditions of the contract; or
(2) Are otherwise due from the contractor under the terms and
conditions of the contract.(b) Contract debts include, but are not
limited to, the following:
(1) Billing and price reductions resulting from contract terms for
price redetermination or for determination of prices under incentive
type contracts.
(2) Price or cost reductions for defective cost or pricing data.
(3) Financing payments determined to be in excess of the contract
limitations at 52.232-16(a)(7), Progress Payments, or 52.232-32(d)(2),
Performance-Based Payments, or any contract clause for commercial item
financing.
(4) Increases to financing payment liquidation rates.
(5) Overpayments disclosed by quarterly statements required under
price redetermination or incentive contracts.
(6) Price adjustments resulting from Cost Accounting Standards
(CAS) noncompliances or changes in cost accounting practice.
(7) Reinspection costs for nonconforming supplies or services.
(8) Duplicate or erroneous payments.
(9) Damages or excess costs related to defaults in performance.
(10) Breach of contract obligations concerning progress payments,
performance based payments, advance payments, commercial item
financing, or Government-furnished property.
(11) Government expense of correcting defects.
(12) Overpayments related to errors in quantity or billing or
deficiencies in quality.
(13) Delinquency in contractor payments due under agreements or
arrangements for deferral or postponement of collections.
[[Page 62233]]
(14) Reimbursement of amounts due under 33.102(b)(3) and
33.104(h)(8).
32.602 Responsibilities.
(a) The contracting officer has primary responsibility for
identifying and demanding payment of contract debts except those
resulting from errors made by the payment office. The contracting
officer shall not collect contract debts or otherwise agree to
liquidate contract debts (e.g. offset the amount of the debt against
existing unpaid bills due the contractor, or allow contractors to
retain contract debts to cover amounts that may become payable in
future periods.
(b) The payment office has primary responsibility for--
(1) Collecting contract debts identified by contracting officers;
(2) Identifying and collecting duplicate and erroneous payments;
and
(3) Authorizing the liquidation of contract debts in accordance
with agency procedures.
32.603 Debt determination.
(a) If the contracting officer has any indication that a contractor
owes money to the Government under a contract, the contracting officer
shall determine promptly whether an actual debt is due and the amount.
Any unnecessary delay may contribute to--
(1) Loss of timely availability of the funds to the program for
which the funds were initially provided;
(2) Increased difficulty in collecting the debt; or
(3) Actual monetary loss to the Government.
(b) The amount of indebtedness determined unilaterally by the
contracting officer shall be an amount that--
(1) Is based on the merits of the case; and
(2) Is consistent with the contract terms.
32.604 Demand for payment.
(a) Except as provided in paragraph (c) of this section, the
contracting officer shall take the following actions:
(1) Issue the demand for payment as soon as the contracting officer
has determined that an actual debt is due the Government and the
amount.
(2) Issue a demand for payment even if--
(i) The debt is or will be the subject of a bilateral modification;
(ii) The contractor is otherwise obligated to pay the money under
the existing contract terms; or
(iii) The contractor has agreed to repay the debt.
(3) Issue the demand for payment as a part of the final decision,
if a final decision is required by 32.605(a).
(b) The demand for payment shall include the following:
(1) A description of the debt, including the debt amount.
(2) A distribution of the principal amount of the debt by line(s)
of accounting subject to the following:
(i) If the debt affects multiple lines of accounting, the
contracting officer shall, to the maximum extent practicable, identify
all affected lines of accounting. If it is not practicable to identify
all affected lines of accounting, the contracting officer may select
representative lines of accounting in accordance with paragraph
(b)(2)(ii) of this section.
(ii) In selecting representative lines of accounting, the
contracting officer shall--
(A) Consider the affected departments or agencies, years of
appropriations, and the predominant types of appropriations;
(B) Not distribute to any line of accounting an amount of the
principal in excess of the total obligation for the line of accounting;
and
(iii) Include the lines of accounting even if the associated funds
are expired or cancelled. While cancelled funds will be deposited in a
miscellaneous receipt account of the Treasury if collected, the funds
are tracked under the closed year appropriation(s) to comply with the
Anti-Deficiency Act.
(iv) If the debt affects multiple contracts and the lines of
accounting are not readily available, the contracting officer shall--
(A) Issue the demand for payment without the distribution of the
principal amount to the affected lines of accounting;
(B) Include a statement in the demand for payment advising when the
distribution will be provided; and
(C) Provide the distribution by the date identified in the demand
for payment.
(3) The basis for and amount of any accrued interest or penalty.
(4)(i) For debts resulting from specific contract terms (e.g.,
debts resulting from incentive clause provisions, Quarterly Limitation
on Payments Statement, Cost Accounting Standards, price reduction for
defective pricing), a notification stating that payment should be made
promptly, and that interest is due in accordance with the terms of the
contract. Interest shall be computed from the date specified in the
applicable contract clause until repayment by the contractor. The
interest rate shall be the rate specified in the applicable contract
clause.
(ii) For all other contract debts, a notification stating that any
amounts not paid within 30 days from the date of the demand for payment
will bear interest. Interest shall be computed from the date of the
demand for payment until repayment by the contractor. The interest rate
shall be the interest rate established by the Secretary of the
Treasury, as provided in Section 611 of the Contract Disputes Act of
1978 (Public Law 95-563), which is applicable to the period in which
the amount becomes due, and then at the rate applicable for each six-
month period as established by the Secretary until the amount is paid.
(iii) In the case of a debt arising from a price reduction for
defective pricing, or as specifically set forth in a Cost Accounting
Standards (CAS) clause in the contract, interest is computed from the
date of overpayment by the Government until repayment by the contractor
at the underpayment rate established by the Secretary of the Treasury,
for the periods affected, under 26 U.S.C. 6621(a)(2).
(5) A statement advising the contractor--
(i) To contact the contracting officer if the contractor believes
the debt is invalid or the amount is incorrect; and
(ii) To remit a check payable to the ``Treasurer of the United
States'' annotated with the contract number along with a copy of the
demand for payment to the payment office identified in the contract or
as otherwise specified in the demand letter in accordance with agency
procedures.
(6) Notification that the payment office may offset the debt
against any payments otherwise due the contractor.
(7) Notification that the debt is subject to administrative charges
in accordance with the requirements of 31 U.S.C. 3717(e) and the Debt
Collection Improvement Act of 1996.
(8) A notification that the contractor may submit a request for
installment payments or deferment of collection if immediate payment is
not practicable or if the amount is disputed.
(c) Except as provided in paragraph (d) of this section, the
contracting officer should not issue a demand for payment if the
contracting officer only becomes aware of the debt when the
contractor--
(1) Provides a lump sum payment or submits a credit invoice. (A
credit invoice is a contractor's request to liquidate the debt against
existing unpaid bills due the contractor); or
(2) Notifies the contracting officer that the payment office
overpaid on an invoice payment. When the contractor provides the
notification, the contracting officer shall notify the payment office
of the overpayment.
[[Page 62234]]
(d) If a demand for payment was not issued as provided for in
paragraph (c) of this section, the contracting officer shall issue a
demand for payment no sooner than 30 days after the contracting officer
becomes aware of the debt unless--
(i) The contractor has liquidated the debt;
(ii) The contractor has requested an installment payment agreement;
or
(iii) The payment office has issued a demand for payment.
(e) The contracting officer shall--
(1) Furnish a copy of the demand for payment to the contractor by
certified mail, return receipt requested, or by any other method that
provides evidence of receipt; and
(2) Forward a copy of the demand to the payment office.
32.605 Final decisions.
(a) The contracting officer shall issue a final decision as
required by 33.211 if-
(1) The contracting officer and the contractor are unable to reach
agreement on the existence or amount of a debt in a timely manner;
(2) The contractor fails to liquidate a debt previously demanded by
the contracting officer within the timeline specified in the demand for
payment unless the amounts were not repaid because the contractor has
requested an installment payment agreement; or
(3) The contractor requests a deferment of collection on a debt
previously demanded by the contracting officer (see 32.607-2).
(b) If a demand for payment was previously issued for the debt, the
demand for payment included in the final decision shall identify the
same due date as the original demand for payment.
(c) The contracting officer shall-
(1) Furnish the decision to the contractor by certified mail,
return receipt requested, or by any other method that provides evidence
of receipt; and
(2) Forward a copy to the payment office identified in the
contract.
32.606 Debt collection.
(a) If the contractor has not liquidated the debt within 30 days of
the date due or requested installment payments or deferment of
collection, the payment office initiates withholding of principal,
interest, penalties, and administrative charges. In the event the
contract is assigned under the Assignment of Claims Act of 1940 (31
U.S.C. 3727 and 41 U.S.C. 15), the rights of the assignee will be
scrupulously respected and withholding of payments shall be consistent
with those rights. For additional information on assignment of claims,
see Subpart 32.8.
(b) As provided for in the Debt Collection Improvement Act of 1996,
payment offices are required to transfer any debt that is delinquent
more than 180 days to the Department of Treasury for collection.
(c) The contracting officer shall periodically follow up with the
payment office to determine whether the debt has been collected and
credited to the correct appropriation(s).
32.607 Installment payments and deferment of collection.
(a) The contracting officer shall not approve or deny a
contractor's request for installment payments or deferment of
collections. The office designated in agency procedures is responsible
for approving or denying requests for installment payments or deferment
of collections.
(b) If a contractor has not appealed the debt or filed an action
under the Disputes clause of the contract and the contractor has
submitted a proposal for debt deferment or installment payments-
(1) The office designated in agency procedures may arrange for
deferment/installment payments if the contractor is unable to pay at
once in full or the contractor's operations under national defense
contracts would be seriously impaired. The arrangement shall include
appropriate covenants and securities and should be limited to the
shortest practicable maturity; and
(2) The deferment/installment agreement shall include a specific
schedule or plan for payment. It should permit the Government to make
periodic financial reviews of the contractor and to require payments
earlier than required by the agreement if the Government considers the
contractor's ability to pay improved. It should also provide for
required stated or measurable payments on the occurrence of specific
events or contingencies that improve the contractor's ability to pay.
(c) If not already applicable under the contract terms, interest on
contract debt shall be made an element of any agreement entered into an
installment payment or deferment of collection agreement.
32.607-1 Installment payments.
If a contractor requests an installment payment agreement, the
contracting officer shall notify the contractor to send a written
request for installment payments to the office designated in agency
procedures.
32.607-2 Deferment of collection.
(a) All requests for deferment of collection must be submitted in
writing to the contracting officer.
(1) If the contractor has appealed the debt under the procedures of
the Disputes clause of the contract, the information with the request
for deferment may be limited to an explanation of--
(i) The contractor's financial condition; and
(ii) Whether deferment of the debt collection is advisable to avoid
possible overcollection.
(2) If there is no appeal pending or action filed under the
Disputes clause of the contract, the following information about the
contractor should be submitted with the request:
(i) Financial condition.
(ii) Contract backlog.
(iii) Projected cash receipts and requirements.
(iv) The feasibility of immediate payment of the debt.
(v) The probable effect on operations of immediate payment in full.
(vi) Whether deferment of the debt collection is advisable to avoid
possible over collection.
(b) Upon receipt of the contractor's written request, the
contracting officer shall promptly provide a notification to the
payment office and advise the payment office that the contractor's
request is under consideration. Prompt notification is required to
ensure that the payment office does not begin collection while the
deferment request is being considered.
(c)(1) The contracting officer shall forward the following to the
office designated in agency procedures for a decision:
(i) A copy of the contractor's request for a deferment of
collection.
(ii) A written recommendation on the request and the basis for the
recommendation including the advisability of deferment to avoid
possible overcollections.
(iii) A statement as to whether the contractor has an appeal
pending or action filed under the Disputes clause of the contract and
the docket number if the appeal has been filed.
(iv) A copy of the contracting officer's final decision (see
32.605).
(2) The contracting officer should consider any information
necessary to develop a recommendation on the deferment request.
(d) The office designated in agency procedures may authorize a
deferment pending the resolution of appeal to avoid possible
overcollections. The agency is required to use current year unexpired
funds to pay interest on overcollections.
[[Page 62235]]
(e) Deferments pending disposition of appeal may be granted to
small business concerns and financially weak contractors, with a
reasonable balance of the need for Government security against loss and
undue hardship on the contractor.
(f) Contracts and arrangements for deferment shall not provide that
a claim of the Government will not become due and payable pending
mutual agreement on the amount of the claim or, in the case of a
dispute, until the decision is reached.
(g) At a minimum, the deferment agreement shall contain the
following:
(1) A description of the debt.
(2) The date of first demand for payment.
(3) Notice of an interest charge, in conformity with FAR 32.608 and
the FAR clause at 52.232-17, Interest; or, in the case of a debt
arising from a defective pricing or a CAS noncompliance overpayment,
interest, as prescribed by the applicable Price Reduction for Defective
Cost or Pricing Data or CAS clause.
(4) Identification of the office to which the contractor is to send
debt payments.
(5) A requirement for the contractor to submit financial
information requested by the Government and for reasonable access to
the contractor's records and property by Government representatives.
(6) Provision for the Government to terminate the deferment
agreement and accelerate the maturity of the debt if the contractor
defaults or if bankruptcy or insolvency proceedings are instituted by
or against the contractor.
(7) Protective requirements that are considered by the Government
to be prudent and feasible in the specific circumstances. The coverage
of protective terms at 32.409 and 32.501-5 may be used as a guide.
(h) If a contractor appeal of the debt determination is pending,
the deferment agreement shall also include a requirement that the
contractor shall --;
(1) Diligently prosecute the appeal; and
(2) Pay the debt in full when the appeal is decided, or when the
parties reach agreement on the debt amount.
(i) The deferment agreement may provide for the right to make early
payments without prejudice, for refund of overpayments, and for
crediting of interest.
(j) Actions filed by contractors under the Disputes clause shall
not suspend or delay collection. Until the action is decided,
deferments shall only be granted if, within 30 days after the filing of
such action, the contractor presents to the office designated in agency
procedures a good and sufficient bond, or other acceptable collateral,
in the amount of the claim, and the deferment is approved by the office
designated in agency procedures. Any amount collected by the Government
in excess of the amount found to be due on appeal under the Disputes
clause of the contract shall be refunded to the contractor with
interest thereon from the date of collection by the Government until
the date the monies are remitted to the contractor at the annual rate
established by the Secretary of Treasury under Public Law 92-41. Simple
interest shall be calculated to reflect each 6-month period change in
the rates established by the Secretary.
32.608 Interest.
32.608-1 Interest charges.
(a) Unless specified otherwise in the FAR clause at 52.232-17--
(1) Interest charges shall apply to any contract debt unpaid after
30 days from the issuance of a demand for payment or from any earlier
date specified in the contract unless--
(i) The contract is a kind excluded under 32.611; or
(ii) The contract or debt has been exempted from interest charges
under agency procedures.
(2) The interest charge shall be at the rate established by the
Secretary of the Treasury under Public Law 92-41 for the period in
which the amount becomes due. The interest charge shall be computed for
the actual number of calendar days involved beginning on the due date
and ending on--
(i) The date on which the designated office receives payment from
the contractor;
(ii) The date of issuance of a Government check to the contractor
from which an amount otherwise payable has been withheld as a credit
against the contract debt; or
(iii) The date on which an amount withheld and applied to the
contract debt would otherwise have become payable to the contractor.
(b) If not already applicable under the contract terms, interest on
contract debt shall be made an element of any agreement entered into on
installment payment and deferment of collection agreements.
32.608-2 Interest credits.
(a) An equitable interest credit shall be applied under the
following circumstances:
(1) When the amount of debt initially determined is subsequently
reduced; e.g., through a successful appeal.
(2) When the collection procedures followed in a given case result
in an over collection of the debt due.
(3) When the responsible official determines that the Government
has unduly delayed payments to the contractor on the same contract at
some time during the period to which the interest charge applied,
provided an interest penalty was not paid for such late payment.
(b) Any appropriate interest credits shall be computed under the
following procedures:
(1) Interest at the rate under paragraph (b) of the FAR clause at
52.232-17 and 32.608-1(a)(2) shall be charged on the reduced debt from
the date specified in the first demand made for payment of the higher
debt.
(2) Interest may not be reduced for any time between the due date
under the demand and the period covered by a deferment of collection,
unless the contract includes an interest clause; e.g., the clause
prescribed in 32.611.
(3) Interest shall not be credited in an amount that, when added to
other amounts refunded or released to the contractor, exceeds the total
amount that has been collected, or withheld for the purpose of
collecting the debt. This limitation shall be further reduced by the
amount of any limitation applicable under paragraph (b)(2) of this
subsection.
32.609 Delays in receipt of notices or demands.
If interest is accrued based on the date of the demand letter and
delivery of the demand letter is delayed by the Government (e.g., undue
delay after dating at the originating office or delays in the mail),
the date of the debt and accrual of interest shall be extended to a
time that is fair and reasonable under the particular circumstances.
32.610 Compromising debts.
For debts under $100,000, excluding interest, if further collection
is not practicable or would cost more than the amount of recovery, the
designated agency official may compromise the debt. Compromise is
authorized by the Federal Claims Collection Act (31 U.S.C. 3711).
Compromise shall conform to Federal Claims Collection Standards 31 CFR
part 900), and agency regulations. Unless specifically authorized by
agency procedures, contracting officers can not compromise debts.
32.611 Contract clause.
(a) The contracting officer shall insert the clause at 52.232-17,
Interest, in solicitations and contracts unless it is contemplated that
the contract will be
[[Page 62236]]
in one or more of the following categories:
(1) Contracts at or below the simplified acquisition threshold.
(2) Contracts with Government agencies.
(3) Contracts with a State or local government or instrumentality.
(4) Contracts with a foreign government or instrumentality.
(5) Contracts without any provision for profit or fee with a
nonprofit organization.
(6) Contracts described in Subpart 5.5, Paid Advertisements.
(7) Any other exceptions authorized under agency procedures.
(b) The contracting officer may insert the FAR clause at 52.232-17,
Interest, in solicitations and contracts when it is contemplated that
the contract will be in any of the categories specified in 32.611(a).
PART 33--PROTESTS, DISPUTES, AND APPEALS
33.208 [Amended]
6. Amend section 33.208(b) by removing ``32.614' and adding
``32.608'' in its place.
33.211 [Amended]
7. Amend section 33.211(a)(vi)by removing ``32.610(b)'' and adding
``32.604 and 32.605'' in its place.
PART 36--CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS
36.608 [Amended]
8. Amend section 36.608 in the fourth sentence by removing
``collect'' and adding ``issue a demand for payment of the amount due''
in its place.
PART 42--CONTRACT ADMINISTRATION AND AUDIT SERVICES
9. Amend section 42.302 by revising paragraph (a)(17) to read as
follows:
42.302 Contract administration functions.
(a) * * *
(17) Analyze quarterly limitation on payments statements and take
action in accordance with Subpart 32.6 to recover overpayments from the
contractor.
* * * * *
PART 52--SOLICITATION PROVISIONS AND CONTRACT CLAUSES
10. Amend section 52.212-4 by revising the date of the clause and
paragraph (i)(5); and adding paragraph (i)(6) to read as follows:
52.212-4 Contract Terms and Conditions--Commercial Items.
* * * * *
CONTRACT TERMS AND CONDITIONS--COMMERCIAL ITEMS-(DATE)
* * * * *
(i) * * *
(5) Overpayments. If the Contractor becomes aware of a duplicate
contract financing or invoice payment or that the Government has
otherwise overpaid on a contract financing or invoice payment, the
Contractor shall take the following actions:
(i) Remit the overpayment amount to the payment office cited in the
contract along with a description of the overpayment including the--
(A) Circumstances of the overpayment (e.g., duplicate payment,
erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number if
applicable;
(C) Affected contract line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation
to the Contracting Officer.
(6) Interest. (i) All amounts that become payable by the Contractor
to the Government under this contract shall bear simple interest from
the date due until paid unless paid within 30 days of becoming due. The
interest rate shall be the interest rate established by the Secretary
of the Treasury as provided in Section 611 of the Contract Disputes Act
of 1978 (Public Law 95-563), which is applicable to the period in which
the amount becomes due, as provided in paragraph (b) of this clause and
then at the rate applicable for each six-month period as fixed by the
Secretary until the amount is paid.
(ii) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment consistent
with this contract, including any demand for payment resulting from a
default termination.
(iii) The interest charge shall be computed for the actual number
of calendar days involved beginning on the due date and ending on--
(A) The date on which the designated office receives payment from
the Contractor;
(B) The date of issuance of a Government check to the Contractor
from which an amount otherwise payable has been withheld as a credit
against the contract debt; or
(C) The date on which an amount withheld and applied to the
contract debt would otherwise have become payable to the Contractor.
(iv) The interest charge made under this clause may be reduced
under the procedures prescribed in 32.608-2 of the Federal Acquisition
Regulation in effect on the date of this contract.
* * * * *
11. Revise section 52.232-17 to read as follows:
52.232-17 Interest.
As prescribed in 32.611(a) and (b), insert the following clause:
INTEREST (DATE)
(a) Except as otherwise provided in this contract under a Price
Reduction for Defective Cost or Pricing Data clause or a Cost
Accounting Standards clause, all amounts that become payable by the
Contractor to the Government under this contract shall bear simple
interest from the date due until paid unless paid within 30 days of
becoming due. The interest rate shall be the interest rate established
by the Secretary of the Treasury as provided in Section 611 of the
Contract Disputes Act of 1978 (Public Law 95-563), which is applicable
to the period in which the amount becomes due, as provided in paragraph
(b) of this clause, and then at the rate applicable for each six-month
period as fixed by the Secretary until the amount is paid.
(b) Amounts shall be due at the earliest of the following dates:
(1) The date fixed under this contract.
(2) The date of the first written demand for payment consistent
with this contract, including any demand for payment resulting from a
default termination.
(c) The interest charge shall be computed for the actual number of
calendar days involved beginning on the due date and ending on--
(1) The date on which the designated office receives payment from
the Contractor;
(2) The date of issuance of a Government check to the Contractor
from which an amount otherwise payable has been withheld as a credit
against the contract debt; or
(3) The date on which an amount withheld and applied to the
contract debt would otherwise have become payable to the Contractor.
(d) The interest charge made under this clause may be reduced under
the procedures prescribed in 32.608-2 of the Federal Acquisition
Regulation in effect on the date of this contract.
12. Amend section 52.232-25 by revising the date of the clause and
paragraph (d) to read as follows:
52.232-25 Prompt Payment.
* * * * *
PROMPT PAYMENT (DATE)
* * * * *
[[Page 62237]]
(d) Overpayments. If the Contractor becomes aware of a duplicate
contract financing or invoice payment or that the Government has
otherwise overpaid on a contract financing or invoice payment, the
Contractor shall--
(1) Remit the overpayment amount to the payment office cited in the
contract along with a description of the overpayment including the--
(i) Circumstances of the overpayment (e.g., duplicate payment,
erroneous payment, liquidation errors, date(s) of overpayment);
(ii) Affected contract number and delivery order number if
applicable;
(iii) Affected contract line item or subline item, if applicable;
and
(iv) Contractor point of contact.
(2) Provide a copy of the remittance and supporting documentation
to the Contracting Officer.
(End of clause)
13. Amend section 52.232-26 by revising the date of the clause and
paragraph (c) to read as follows:
52.232-26 Prompt Payment for Fixed-Price Architect-Engineer Contracts.
* * * * *
PROMPT PAYMENT FOR FIXED-PRICE ARCHITECT-ENGINEER CONTRACTS (DATE)
* * * * *
(c) Overpayments. If the Contractor becomes aware of a duplicate
contract financing or invoice payment or that the Government has
otherwise overpaid on a contract financing or invoice payment, the
Contractor shall--
(1) Remit the overpayment amount to the payment office cited in the
contract along with a description of the overpayment including the--
(i) Circumstances of the overpayment (e.g., duplicate payment,
erroneous payment, liquidation errors, date(s) of overpayment);
(ii) Affected contract number and delivery order number if
applicable;
(iii) Affected contract line item or subline item, if applicable;
and
(iv) Contractor point of contact.
(2) Provide a copy of the remittance and supporting documentation
to the Contracting Officer.
(End of clause)
14. Amend section 52.232-27 by revising the date of the clause and
paragraph (l) to read as follows:
52.232-27 Prompt Payment for Construction Contracts.
* * * * *
PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (DATE)
* * * * *
(l) Overpayments. If the Contractor becomes aware of a duplicate
contract financing or invoice payment or that the Government has
otherwise overpaid on a contract financing or invoice payment, the
Contractor shall--
(1) Remit the overpayment amount to the payment office cited in the
contract along with a description of the overpayment including the--
(i) Circumstances of the overpayment (e.g., duplicate payment,
erroneous payment, liquidation errors, date(s) of overpayment);
(ii) Affected contract number and delivery order number if
applicable;
(iii) Affected contract line item or subline item, if applicable;
and
(iv) Contractor point of contact.
(2) Provide a copy of the remittance and supporting documentation
to the Contracting Officer.
(End of clause)
[FR Doc. 06-8806 Filed 10-23-06; 8:45 am]
BILLING CODE 6820-EP-S