Washington Puget Sound Energy, Inc.; Notice of Availability of a Final Environmental Impact Statement for the Baker River Hydroelectric Project, 54645 [E6-15384]
Download as PDF
Federal Register / Vol. 71, No. 180 / Monday, September 18, 2006 / Notices
and 385.214) on or before 5 p.m. Eastern
time on the specified comment date. It
is not necessary to separately intervene
again in a subdocket related to a
compliance filing if you have previously
intervened in the same docket. Protests
will be considered by the Commission
in determining the appropriate action to
be taken, but will not serve to make
protestants parties to the proceeding.
Anyone filing a motion to intervene or
protest must serve a copy of that
document on the Applicant. In reference
to filings initiating a new proceeding,
interventions or protests submitted on
or before the comment deadline need
not be served on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First St., NE., Washington, DC
20426.
The filings in the above proceedings
are accessible in the Commission’s
eLibrary system by clicking on the
appropriate link in the above list. They
are also available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
eSubscription link on the Web site that
enables subscribers to receive e-mail
notification when a document is added
to a subscribed dockets(s). For
assistance with any FERC Online
service, please e-mail
FERCOnlineSupport@ferc.gov or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Magalie R. Salas,
Secretary.
[FR Doc. E6–15431 Filed 9–15–06; 8:45 am]
cprice-sewell on PROD1PC66 with NOTICES
BILLING CODE 6717–01–P
VerDate Aug<31>2005
14:48 Sep 15, 2006
Jkt 208001
For Further Information Contact:
Steve Hocking at (202) 502–8753 or at
steve.hocking@ferc.gov.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Magalie R. Salas,
Secretary.
[FR Doc. E6–15384 Filed 9–15–06; 8:45 am]
[Project No. 2150–033]
Washington Puget Sound Energy, Inc.;
Notice of Availability of a Final
Environmental Impact Statement for
the Baker River Hydroelectric Project
September 8, 2006.
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s (Commission)
regulations, 18 CFR Part 380 (Order No.
486, 52 FR 47897), the Office of Energy
Projects has reviewed the application
for a license for the Baker River
Hydroelectric Project (FERC No. 2150–
033), located on the Baker River in
Whatcom and Skagit Counties,
Washington and has prepared a Final
Environmental Impact Statement (EIS)
for the project. The final EIS was
prepared in cooperation with the U.S.
Army Corps of Engineers pursuant to 40
CFR 1501.6 of the National
Environmental Policy Act. The Baker
River Project occupies 5,207 acres of
lands within the Mt. Baker-Snoqualmie
National Forest managed by the U.S.
Forest Service.
The final EIS, contains staff
evaluations of the applicant’s proposal
and the alternatives for relicensing the
Baker River Project. The final EIS
documents the views of governmental
agencies, non-governmental
organizations, affected Indian tribes, the
public, the license applicant, and
Commission staff.
A copy of the final EIS is available for
review in the Commission’s Public
Reference Branch, Room 2A, located at
888 First Street, NE., Washington, DC
20426. The final EIS also may be viewed
on the Commission’s Web site at https://
www.ferc.gov under the eLibrary link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY, (202)
502–8659.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
54645
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP00–006–014]
Gulfstream Natural Gas System, LLC;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Gulfstream Natural Gas
System, LLC’S Phase III Pipeline
Project and Notice of Site Visit and
Request for Comments on
Environmental Issues
September 8, 2006.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Gulfstream Natural Gas System,
LLC’s (Gulfstream) application for its
Phase III Pipeline Project. Gulfstream
proposes to amend its existing Phase III
authorization under the FERC certificate
granted October 8, 2003 by modifying
the route and pipeline diameter. In this
filing, Gulfstream proposes to construct,
own and operate a 34.3-mile segment of
30-inch gas pipeline extending from its
existing Station 712 in Martin County,
Florida to a newly constructed Station
705 that would connect to the proposed
Florida Power & Light Company (FPL)
2,220 megawatt (MW) gas turbine West
County Energy Center (WCEC) in Palm
Beach County, Florida. Gulfstream has
executed firm service agreement with
FPL to deliver 345,000 decatherms per
day (Dth/d) of natural gas to the WCEC
for a primary term of 23 years.
The FPL WCEC is a nonjurisdictional
facility under FERC regulations. The
facility is being licensed by the Florida
Department of Environmental Protection
Siting Office under the jurisdiction of
the Florida Power Plant Siting Act.
This notice announces the opening of
the scoping period that will be used to
gather environmental input from the
public and interested agencies on the
project. Scoping comments are
requested by October 9, 2006.
With this notice, the staff of the FERC
is asking other Federal, State, local and
tribal agencies with jurisdiction and/or
special expertise with respect to
environmental issues to cooperate with
E:\FR\FM\18SEN1.SGM
18SEN1
Agencies
[Federal Register Volume 71, Number 180 (Monday, September 18, 2006)]
[Notices]
[Page 54645]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-15384]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2150-033]
Washington Puget Sound Energy, Inc.; Notice of Availability of a
Final Environmental Impact Statement for the Baker River Hydroelectric
Project
September 8, 2006.
In accordance with the National Environmental Policy Act of 1969
and the Federal Energy Regulatory Commission's (Commission)
regulations, 18 CFR Part 380 (Order No. 486, 52 FR 47897), the Office
of Energy Projects has reviewed the application for a license for the
Baker River Hydroelectric Project (FERC No. 2150-033), located on the
Baker River in Whatcom and Skagit Counties, Washington and has prepared
a Final Environmental Impact Statement (EIS) for the project. The final
EIS was prepared in cooperation with the U.S. Army Corps of Engineers
pursuant to 40 CFR 1501.6 of the National Environmental Policy Act. The
Baker River Project occupies 5,207 acres of lands within the Mt. Baker-
Snoqualmie National Forest managed by the U.S. Forest Service.
The final EIS, contains staff evaluations of the applicant's
proposal and the alternatives for relicensing the Baker River Project.
The final EIS documents the views of governmental agencies, non-
governmental organizations, affected Indian tribes, the public, the
license applicant, and Commission staff.
A copy of the final EIS is available for review in the Commission's
Public Reference Branch, Room 2A, located at 888 First Street, NE.,
Washington, DC 20426. The final EIS also may be viewed on the
Commission's Web site at https://www.ferc.gov under the eLibrary link.
Enter the docket number excluding the last three digits in the docket
number field to access the document. For assistance, contact FERC
Online Support at FERCOnlineSupport@ferc.gov or toll-free at (866) 208-
3676, or for TTY, (202) 502-8659.
You may also register online at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
For Further Information Contact: Steve Hocking at (202) 502-8753 or
at steve.hocking@ferc.gov.
Magalie R. Salas,
Secretary.
[FR Doc. E6-15384 Filed 9-15-06; 8:45 am]