Pipeline Safety: Petition for Waiver; TransCanada Pipelines Limited, 52871-52873 [E6-14826]
Download as PDF
rwilkins on PROD1PC63 with NOTICES
Federal Register / Vol. 71, No. 173 / Thursday, September 7, 2006 / Notices
As to advanced air bags, and as
indicated above, Saleen has hired an
engineering project manager responsible
for air bag development, has been
working with engineers at Takata,
Autoliv, and Bosch in researching all of
the program requirements as well as
developing a test plan and component
designs for development of a system
compliant with the advanced air bag
requirement. Saleen is also working
with Kettering University in Flint
Michigan for additional research and
testing.
We have concluded that Saleen has
made good faith efforts to meet the
advanced air bag requirements. We note
that Saleen’s situation in needing
additional time to meet the advanced air
bag requirements, which apply to low
volume manufacturers beginning
September 1, 2006, is not unlike that of
several other low volume
manufacturers.
If the petition were denied, the sale of
S7 automobiles would cease
immediately. In evaluating Saleen’s
current situation, the agency finds that
to require immediate compliance with
Standard No. 208 would cause the
petitioner substantial economic
hardship. While Saleen also alters motor
vehicles, the S7 is the only model that
Saleen manufactures.
Traditionally, the agency has found
that the public interest is served in
affording continued employment to a
small volume manufacturer’s work force
and to those of its U.S.-sourced
component suppliers. The agency has
also found that the public interest is
served by affording the consumers a
wider variety of motor vehicles. In this
instance, denial of the petition would
put in jeopardy the jobs of 150 full time
employees at Saleen dedicated to the
design, manufacture, and certification of
the S7. Denial of the petition could also
affect the payrolls of U.S.-sourced
component suppliers.
The vehicle in question will be
manufactured in extremely limited
quantities. Saleen anticipates selling no
more than 25 of the vehicles per year in
the United States. The current
Manufacturer’s Suggested Retail Price is
$555,000. The vehicles are also driven
on an extremely limited basis. Saleen
stated that the vehicles generally do not
accrue more than 2,000 miles per year.
In light of these factors, the agency
anticipates that the S7 vehicles will
have a negligible impact on the overall
safety of U.S. highways. The agency also
notes that Saleen has indicated that the
vehicle subject to this petition complies
with all other applicable Federal motor
vehicle safety standards.
VerDate Aug<31>2005
19:26 Sep 06, 2006
Jkt 208001
We are granting Saleen a three-year
exemption from the advanced air bag
requirements, beginning September 1,
2006. As indicated above, we are also
granting that company an extension of
the exemption from the ‘‘basic’’ air bag
requirements for the first of the three
years. Saleen’s ability to utilize the final
two years of the exemption from the
advanced air bag requirements will be
dependent on whether it implements an
air bag system that enables the S7 to at
least meet FMVSS No. 208’s ‘‘basic’’ air
bag requirements.
Given the discussion presented above,
we conclude that Saleen has made
sufficient good faith efforts to comply
with FMVSS No. 208 to support these
exemptions for the prescribed time
periods, that requiring immediate
compliance would cause substantial
economic hardship, and that the
exemptions are in the public interest
and consistent with the Safety Act. We
note that while this document includes
some discussion of those good faith
efforts and economic hardship, NHTSA
has also considered additional
information submitted by Saleen which
has been determined to be confidential.
We should caution that manufacturers
that receive temporary exemptions
should not assume that the agency will
necessarily grant extensions. On this
basic issue, we note that Saleen cited in
its petition a particular sales rate that it
needs to sustain in order to continue to
fund the development of advanced air
bags for implementation by September
1, 2009. See p. 2 of Saleen’s petition.
The petitioner should not assume that if
it is unable to maintain a particular
sales rate or for other reasons does not
continue to fund the development of
advanced air bags, that the agency will
then grant an extension of the
exemption for advanced air bags
provided in this document.
As to the specific paragraphs of
FMVSS No. 208 that will be covered by
the exemptions, we note that the
original exemption for Saleen cited
S4.1.5.3 of 49 CFR 571.208. On review,
we believe that it would be clearer to
cite both S4.1.5.1(a)(1) and S4.1.5.3. The
former paragraph requires passenger
cars, at each front outboard seating
position, to meet specified frontal crash
protection requirements ‘‘by means that
require no action by vehicle occupants.’’
S4.1.5.3 then requires that passenger
cars meet that requirement by means of
inflatable restraint systems. Since the
intent of the exemption is to exempt the
S7 from automatic crash protection
requirements, we believe that
S4.1.5.1(a)(1) should be cited. We note
that the S7 is still subject, among other
things, to S4.1.5.1(a)(3), which requires
PO 00000
Frm 00113
Fmt 4703
Sfmt 4703
52871
it to meet specified performance
requirements in a belted crash test. The
relevant paragraph for the advanced air
bag requirements is S14.2.
We also note that prospective
purchasers will be notified that the
vehicle is exempted from the air bag
requirements of Standard No. 208.
Under § 555.9(b), a manufacturer of an
exempted passenger car must affix
securely to the windshield or side
window of each exempted vehicle a
label containing a statement that the
vehicle conforms to all applicable
Federal motor vehicle safety standards
in effect on the date of manufacture
‘‘except for Standards Nos. [listing the
standards by number and title for which
an exemption has been granted]
exempted pursuant to NHTSA
Exemption No. lll.’’ This label
notifies prospective purchasers about
the exemption and its subject. Under
§ 555.9(c), this information must also be
included on the vehicle’s certification
label.
In accordance with 49 U.S.C.
30113(b)(3)(B)(i), Saleen S7 is granted
NHTSA Temporary Exemption No. EX
06–7, from S4.1.5.1(a)(1) and S4.1.5.3.
This exemption is effective September
1, 2006 to August 31, 2007. Saleen S7
is granted NHTSA Temporary
Exemption No. EX 06–8, from S14.2 of
§ 571.208. This exemption is effective
September 1, 2006 to August 31, 2009.
(49 U.S.C. 30113; delegations of authority at
49 CFR 1.50. and 501.8)
Issued on: August 31, 2006.
Nicole R. Nason,
Administrator.
[FR Doc. E6–14829 Filed 9–6–06; 8:45 am]
BILLING CODE 4910–59–P
DEPARTMENT OF TRANSPORTATION
Pipeline and Hazardous Materials
Safety Administration
[Docket No. PHMSA—2006–24058;
Notice 1]
Pipeline Safety: Petition for Waiver;
TransCanada Pipelines Limited
Pipeline and Hazardous
Materials Safety Administration
(PHMSA), Department of Transportation
(DOT).
ACTION: Notice; petition for waiver.
AGENCY:
SUMMARY: TransCanada Pipelines
Limited, operator of the Portland
Natural Gas Transmission System
(PNGTS), requests a waiver of
compliance from PHMSA regulations
for selected gas transmission pipeline
segments in Windham, Maine. These
E:\FR\FM\07SEN1.SGM
07SEN1
52872
Federal Register / Vol. 71, No. 173 / Thursday, September 7, 2006 / Notices
regulations require pipeline operators to
confirm or revise the maximum
allowable operating pressure (MAOP) of
a pipeline after a class location change.
DATES: Persons interested in submitting
written comments on the waiver
proposed in this notice must do so by
October 10, 2006. Comments filed late
will be considered as practicable.
ADDRESSES: You may submit written
comments by mailing or delivering an
original and two copies to the Dockets
Facility, U.S. Department of
Transportation, Room PL–401, 400
Seventh Street, SW., Washington, DC
20590–0001. The dockets facility is
open from 10 a.m. to 5 p.m., Monday
through Friday, except on Federal
holidays when the facility is closed.
Alternatively, you may submit written
comments to the docket electronically at
the following Web address: https://
dms.dot.gov.
All written comments should identify
the docket and notice number stated in
the heading of this notice. Anyone who
wants confirmation of mailed comments
must include a self-addressed stamped
postcard. To file written comments
electronically, after logging on to https://
dms.dot.gov, click on ‘‘Comment/
Submissions.’’ You can also read
comments and other material in the
docket at https://dms.dot.gov. General
information about our pipeline safety
program is available at https://
phmsa.dot.gov.
Anyone is able to search the
electronic form of all comments
received in any of our dockets by the
name of the individual submitting the
comment (or signing the comment, if
submitted on behalf of an association,
business, labor union, etc.). You may
review DOT’s complete Privacy Act
Statement in the Federal Register
published on April 11, 2000 (65 FR
19477) or you may visit https://
dms.dot.gov.
FOR FURTHER INFORMATION CONTACT:
James Reynolds by phone at 202–366–
2786, by fax at 202–366–4566, by mail
at DOT, PHMSA, 400 Seventh Street,
SW., Room 2103, Washington, DC,
20590, or by e-mail at
james.reynolds@dot.gov.
PNGTS
requests a waiver from compliance with
49 CFR 192.611 for selected gas
transmission pipeline segments in
Windham, Maine. Specifically, PNGTS
requests a waiver from the requirement
to revise the MAOP or upgrade the
pipeline segments after a class location
change. If this waiver is granted, PNGTS
will conduct risk control activities that
include: (1) Internal pipeline inspection
rwilkins on PROD1PC63 with NOTICES
SUPPLEMENTARY INFORMATION:
VerDate Aug<31>2005
18:11 Sep 06, 2006
Jkt 208001
using geometry and magnetic flux
leakage in-line inspection tools; (2)
annual close interval cathodic
protection surveys; (3) direct current
voltage gradient (DCVG) surveys; (4)
direct assessment on anomalies; (5)
additional aerial patrols; and (6)
installation of buried excavation
warning tape over the pipeline. PNGTS
asserts that these alternative risk control
activities will provide an equal or
higher level of safety than currently
provided by the pipeline safety
regulations.
Federal pipeline safety regulations at
§ 192.611 require a gas pipeline operator
to confirm or revise the MAOP of its
pipeline if the hoop stress
corresponding to the established MAOP
of a segment of pipeline is not
commensurate with the present class
location and the segment is in
satisfactory physical condition.
PNGTS’s waiver request involves two
locations on its 24-inch pipeline in
Windham, Maine. Both locations were
hydrotested to 1846 pounds per square
inch gauge (psig) in December of 1998:
Location 1: Consists of 785 feet of
Class 1 pipe, 24-inch outside diameter,
0.343-inch wall, American Petroleum
Institute (API) 5L/Grade X70 steel pipe,
and 2128 feet of Class 3 pipe, 24-inch
outside diameter, 0.494-inch wall, API
5L/Grade X70 steel pipe, for a total
length of 2913 feet of pipe.
Location 2: Consists of 4766 feet of
Class 1 pipe, 24-inch outside diameter,
0.343-inch wall, and API 5L/Grade X70
steel pipe.
With regard to location 1, PNGTS
requests this waiver because the
development or conversion of an active
gravel pit in an industrial park will
change the 785 feet of Class 1 to Class
3 pipe. With regard to location 2,
PNGTS requests the waiver because the
development of a residential
subdivision is expected to change the
entire 4766 feet of Class 1 to Class 3
pipe. Therefore, both locations will
change from Class 1 to Class 3. The
pipelines were constructed during 1998
and 1999 and began operating on March
10, 1999; according to PNGTS, these
pipelines are in excellent condition.
PNGTS performs an annual close
interval survey (CIS) on 15% to 20% of
its pipeline system and in the summer
of 2000, PNGTS performed a base line
CIS of its entire pipeline system. This
CIS revealed zero low potentials or
anomalies at the requested waiver
locations. PNGTS also performed a
baseline high-resolution magnetic flux
leakage internal inspection (smart pig)
on its mainline in November of 2002.
Two minor anomalies were identified
during the inspection and were later
PO 00000
Frm 00114
Fmt 4703
Sfmt 4703
excavated and investigated during the
summer of 2005.
PNGTS’s mainline valves (MLV) are
equipped with remote controlled valve
actuators. Each valve assembly contains
an upstream and downstream pressure
transmitter that communicates with
PNGTS’s supervisory control and data
acquisition (SCADA) system and Gas
Control Center. The primary
communication method is through a
satellite link with a backup modem
system. If PNGTS’s SCADA system
detects operating pressures outside the
pre-established pressure limits, the
system activates an alarm which notifies
the gas control operator. The gas control
operator has the capability of operating
the MLV remotely or isolating the
pipeline completely.
PNGTS proposes to perform
alternative risk control activities rather
than lowering the MAOP of the system
or replacing the two segments of Class
1 pipe (totaling 5551 feet). PNGTS
believes that the following alternative
risk control activities are consistent
with pipeline safety and will maintain
or exceed the margin of safety and
environmental protection provided by
49 CFR § 192.611:
1. Perform a cathodic protection CIS
on the requested waiver segments. The
cathodic protection CIS will be
performed annually and include 1000
feet upstream and downstream of the
requested waiver segments.
2. Perform a DCVG survey on the
requested waiver segments of the
pipeline. PNGTS proposes to include an
additional 1000 feet of pipeline in its
survey. The additional 1000 feet of
pipeline is located upstream and
downstream of the requested waiver
segments.
3. Perform a direct assessment on all
anomalies or corrosion indications
identified by the internal inspection
survey or the cathodic protection CIS.
The direct assessment will be performed
on the requested waiver segments
regardless of size or depth of anomaly
indication, and include an additional
1000 feet of pipe upstream and
downstream of the requested waiver
segments.
4. Perform weekly aerial patrols over
the entire PNGTS 24-inch mainline and
12-inch lateral pipeline. Aerial patrols
will also observe pipeline surface
conditions for indications of
construction activity that could affect
the safe operation of the pipeline. In
addition, and at a minimum, PNGTS
will also perform quarterly road
crossing patrols and leak surveys using
leak detection equipment at all road
crossings located within the requested
waiver segments and all corresponding
E:\FR\FM\07SEN1.SGM
07SEN1
Federal Register / Vol. 71, No. 173 / Thursday, September 7, 2006 / Notices
rwilkins on PROD1PC63 with NOTICES
Class 3 locations over the entire length
of the requested waiver segments.
5. Install buried excavation warning
tape over the pipelines, and throughout
the entire requested waiver segments, to
further alert excavators of the existence
of PNGTS’s pipelines.
Finally, PNGTS believes the
additional cathodic protection CIS will
VerDate Aug<31>2005
18:11 Sep 06, 2006
Jkt 208001
insure the integrity of the cathodic
protection and fusion bond epoxy
coating systems, thereby minimizing the
risk of future corrosion and maximizing
the opportunity for prompt
identification of corrosion-related
deficiencies.
Issued in Washington, DC on August 30,
2006.
Jeffrey D. Wiese,
Acting Deputy Associate Administrator for
Pipeline Safety.
[FR Doc. E6–14826 Filed 9–6–06; 8:45 am]
BILLING CODE 4910–60–P
Authority: 49 U.S.C. 60118(c) and 2015;
and 49 CFR 1.53.
PO 00000
Frm 00115
Fmt 4703
Sfmt 4703
52873
E:\FR\FM\07SEN1.SGM
07SEN1
Agencies
[Federal Register Volume 71, Number 173 (Thursday, September 7, 2006)]
[Notices]
[Pages 52871-52873]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-14826]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Pipeline and Hazardous Materials Safety Administration
[Docket No. PHMSA--2006-24058; Notice 1]
Pipeline Safety: Petition for Waiver; TransCanada Pipelines
Limited
AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA),
Department of Transportation (DOT).
ACTION: Notice; petition for waiver.
-----------------------------------------------------------------------
SUMMARY: TransCanada Pipelines Limited, operator of the Portland
Natural Gas Transmission System (PNGTS), requests a waiver of
compliance from PHMSA regulations for selected gas transmission
pipeline segments in Windham, Maine. These
[[Page 52872]]
regulations require pipeline operators to confirm or revise the maximum
allowable operating pressure (MAOP) of a pipeline after a class
location change.
DATES: Persons interested in submitting written comments on the waiver
proposed in this notice must do so by October 10, 2006. Comments filed
late will be considered as practicable.
ADDRESSES: You may submit written comments by mailing or delivering an
original and two copies to the Dockets Facility, U.S. Department of
Transportation, Room PL-401, 400 Seventh Street, SW., Washington, DC
20590-0001. The dockets facility is open from 10 a.m. to 5 p.m., Monday
through Friday, except on Federal holidays when the facility is closed.
Alternatively, you may submit written comments to the docket
electronically at the following Web address: https://dms.dot.gov.
All written comments should identify the docket and notice number
stated in the heading of this notice. Anyone who wants confirmation of
mailed comments must include a self-addressed stamped postcard. To file
written comments electronically, after logging on to https://
dms.dot.gov, click on ``Comment/Submissions.'' You can also read
comments and other material in the docket at https://dms.dot.gov.
General information about our pipeline safety program is available at
https://phmsa.dot.gov.
Anyone is able to search the electronic form of all comments
received in any of our dockets by the name of the individual submitting
the comment (or signing the comment, if submitted on behalf of an
association, business, labor union, etc.). You may review DOT's
complete Privacy Act Statement in the Federal Register published on
April 11, 2000 (65 FR 19477) or you may visit https://dms.dot.gov.
FOR FURTHER INFORMATION CONTACT: James Reynolds by phone at 202-366-
2786, by fax at 202-366-4566, by mail at DOT, PHMSA, 400 Seventh
Street, SW., Room 2103, Washington, DC, 20590, or by e-mail at
james.reynolds@dot.gov.
SUPPLEMENTARY INFORMATION: PNGTS requests a waiver from compliance with
49 CFR 192.611 for selected gas transmission pipeline segments in
Windham, Maine. Specifically, PNGTS requests a waiver from the
requirement to revise the MAOP or upgrade the pipeline segments after a
class location change. If this waiver is granted, PNGTS will conduct
risk control activities that include: (1) Internal pipeline inspection
using geometry and magnetic flux leakage in-line inspection tools; (2)
annual close interval cathodic protection surveys; (3) direct current
voltage gradient (DCVG) surveys; (4) direct assessment on anomalies;
(5) additional aerial patrols; and (6) installation of buried
excavation warning tape over the pipeline. PNGTS asserts that these
alternative risk control activities will provide an equal or higher
level of safety than currently provided by the pipeline safety
regulations.
Federal pipeline safety regulations at Sec. 192.611 require a gas
pipeline operator to confirm or revise the MAOP of its pipeline if the
hoop stress corresponding to the established MAOP of a segment of
pipeline is not commensurate with the present class location and the
segment is in satisfactory physical condition.
PNGTS's waiver request involves two locations on its 24-inch
pipeline in Windham, Maine. Both locations were hydrotested to 1846
pounds per square inch gauge (psig) in December of 1998:
Location 1: Consists of 785 feet of Class 1 pipe, 24-inch outside
diameter, 0.343-inch wall, American Petroleum Institute (API) 5L/Grade
X70 steel pipe, and 2128 feet of Class 3 pipe, 24-inch outside
diameter, 0.494-inch wall, API 5L/Grade X70 steel pipe, for a total
length of 2913 feet of pipe.
Location 2: Consists of 4766 feet of Class 1 pipe, 24-inch outside
diameter, 0.343-inch wall, and API 5L/Grade X70 steel pipe.
With regard to location 1, PNGTS requests this waiver because the
development or conversion of an active gravel pit in an industrial park
will change the 785 feet of Class 1 to Class 3 pipe. With regard to
location 2, PNGTS requests the waiver because the development of a
residential subdivision is expected to change the entire 4766 feet of
Class 1 to Class 3 pipe. Therefore, both locations will change from
Class 1 to Class 3. The pipelines were constructed during 1998 and 1999
and began operating on March 10, 1999; according to PNGTS, these
pipelines are in excellent condition.
PNGTS performs an annual close interval survey (CIS) on 15% to 20%
of its pipeline system and in the summer of 2000, PNGTS performed a
base line CIS of its entire pipeline system. This CIS revealed zero low
potentials or anomalies at the requested waiver locations. PNGTS also
performed a baseline high-resolution magnetic flux leakage internal
inspection (smart pig) on its mainline in November of 2002. Two minor
anomalies were identified during the inspection and were later
excavated and investigated during the summer of 2005.
PNGTS's mainline valves (MLV) are equipped with remote controlled
valve actuators. Each valve assembly contains an upstream and
downstream pressure transmitter that communicates with PNGTS's
supervisory control and data acquisition (SCADA) system and Gas Control
Center. The primary communication method is through a satellite link
with a backup modem system. If PNGTS's SCADA system detects operating
pressures outside the pre-established pressure limits, the system
activates an alarm which notifies the gas control operator. The gas
control operator has the capability of operating the MLV remotely or
isolating the pipeline completely.
PNGTS proposes to perform alternative risk control activities
rather than lowering the MAOP of the system or replacing the two
segments of Class 1 pipe (totaling 5551 feet). PNGTS believes that the
following alternative risk control activities are consistent with
pipeline safety and will maintain or exceed the margin of safety and
environmental protection provided by 49 CFR Sec. 192.611:
1. Perform a cathodic protection CIS on the requested waiver
segments. The cathodic protection CIS will be performed annually and
include 1000 feet upstream and downstream of the requested waiver
segments.
2. Perform a DCVG survey on the requested waiver segments of the
pipeline. PNGTS proposes to include an additional 1000 feet of pipeline
in its survey. The additional 1000 feet of pipeline is located upstream
and downstream of the requested waiver segments.
3. Perform a direct assessment on all anomalies or corrosion
indications identified by the internal inspection survey or the
cathodic protection CIS. The direct assessment will be performed on the
requested waiver segments regardless of size or depth of anomaly
indication, and include an additional 1000 feet of pipe upstream and
downstream of the requested waiver segments.
4. Perform weekly aerial patrols over the entire PNGTS 24-inch
mainline and 12-inch lateral pipeline. Aerial patrols will also observe
pipeline surface conditions for indications of construction activity
that could affect the safe operation of the pipeline. In addition, and
at a minimum, PNGTS will also perform quarterly road crossing patrols
and leak surveys using leak detection equipment at all road crossings
located within the requested waiver segments and all corresponding
[[Page 52873]]
Class 3 locations over the entire length of the requested waiver
segments.
5. Install buried excavation warning tape over the pipelines, and
throughout the entire requested waiver segments, to further alert
excavators of the existence of PNGTS's pipelines.
Finally, PNGTS believes the additional cathodic protection CIS will
insure the integrity of the cathodic protection and fusion bond epoxy
coating systems, thereby minimizing the risk of future corrosion and
maximizing the opportunity for prompt identification of corrosion-
related deficiencies.
Authority: 49 U.S.C. 60118(c) and 2015; and 49 CFR 1.53.
Issued in Washington, DC on August 30, 2006.
Jeffrey D. Wiese,
Acting Deputy Associate Administrator for Pipeline Safety.
[FR Doc. E6-14826 Filed 9-6-06; 8:45 am]
BILLING CODE 4910-60-P