Southwest Power Pool, Inc.; Notice of Institution of Proceeding and Refund Effective Date, 47799 [E6-13763]

Download as PDF Federal Register / Vol. 71, No. 160 / Friday, August 18, 2006 / Notices protests on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible online at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Magalie R. Salas, Secretary. [FR Doc. E6–13759 Filed 8–17–06; 8:45 am] BILLING CODE 6717–01–P Any person desiring to file comments on this information should file with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). All such comments should be filed on or before the comment date. Comments may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘eFiling’’ link. The Commission strongly encourages electronic filings. Comment Date: August 22, 2006. Magalie R. Salas, Secretary. [FR Doc. E6–13807 Filed 8–17–06; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket Nos. EL06–83–000] DEPARTMENT OF ENERGY Southwest Power Pool, Inc.; Notice of Institution of Proceeding and Refund Effective Date Federal Energy Regulatory Commission August 1, 2006. Notice of Filing August 1, 2006. Regional Transmission Organizations. Bangor Hydro-Electric Company, et al. New York Independent System Operator, Inc., et al. PJM Interconnection, L.L.C., et al. PJM Interconnection, L.L.C ISO New England, Inc. New York Independent System Operator, Inc.. RT01–99–000, RT01–99– 001,RT01–99– 002 and RT01–99–003. RT01–86–000, RT01–86–001 and RT01–86–002. RT01–95–000, RT01–95–001 and RT01–95–002. RT01–2–000, RT01–2–001, RT01–2–002 and RT01–2–003. RT01–98–000. RT02–3–000. On July 28, 2006, the Commission issued an order that instituted a proceeding in Docket No. EL06–83–000, pursuant to section 206 of the Federal Power Act (FPA), 16 U.S.C. 824e (2005), to provide a forum for Southwest Power Pool (SPP) to address its assertions that its projected native load needs justify a restriction on the rollover rights of its transmission customer, Southwestern Public Service Company. Southwest Power Pool, Inc., 116 FERC ¶ 61,092 (2006). The refund effective date in Docket No. EL06–83–000, established pursuant to section 206(b) of the FPA, will be the date of publication of this notice in the Federal Register. Magalie R. Salas, Secretary. [FR Doc. E6–13763 Filed 8–17–06; 8:45 am] jlentini on PROD1PC65 with NOTICES BILLING CODE 6717–01–P Take notice that PJM Interconnection, L.L.C., New York Independent System Operator, Inc. and ISO New England, Inc. have posted on their Internet Web sites charts and information updating their progress on the resolution of ISO seams. VerDate Aug<31>2005 19:21 Aug 17, 2006 Jkt 208001 PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 47799 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL06–92–000] Tri-County Electric Cooperative, Inc.; Xcel Energy Services Inc.; Southwestern Public Service Company; Notice of Petition for Declaratory Order August 1, 2006. Take notice that on July 28, 2006, TriCounty Electric Cooperative, Inc. (TriCounty), Xcel Energy Services Inc., and Southwestern Public Service Company (SPS) (collectively ‘‘Petitioners’’) filed a joint petition for declaratory order for a finding that: (i) SPS alone is subject to the Commission’s jurisdiction under the Federal Power Act (FPA) and (ii) disclaiming jurisdiction over Tri-County in connection with the disposition by SPS of certain distribution assets to TriCounty. Alternatively, petitioners request that the Commission grant TriCounty waivers of otherwise applicable section of the FPA. The Petitioners state that a copy was served upon the Kansas Corporation Commission, the Oklahoma Corporation Commission, and the Public Utility Commission of Texas. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. On or before the comment date, it is not necessary to serve motions to intervene or protests on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible online at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to E:\FR\FM\18AUN1.SGM 18AUN1

Agencies

[Federal Register Volume 71, Number 160 (Friday, August 18, 2006)]
[Notices]
[Page 47799]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-13763]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. EL06-83-000]


Southwest Power Pool, Inc.; Notice of Institution of Proceeding 
and Refund Effective Date

August 1, 2006.
    On July 28, 2006, the Commission issued an order that instituted a 
proceeding in Docket No. EL06-83-000, pursuant to section 206 of the 
Federal Power Act (FPA), 16 U.S.C. 824e (2005), to provide a forum for 
Southwest Power Pool (SPP) to address its assertions that its projected 
native load needs justify a restriction on the rollover rights of its 
transmission customer, Southwestern Public Service Company. Southwest 
Power Pool, Inc., 116 FERC ] 61,092 (2006).
    The refund effective date in Docket No. EL06-83-000, established 
pursuant to section 206(b) of the FPA, will be the date of publication 
of this notice in the Federal Register.

Magalie R. Salas,
Secretary.
 [FR Doc. E6-13763 Filed 8-17-06; 8:45 am]
BILLING CODE 6717-01-P