Exelon Generating Company, LLC; Notice of Availability of the Final Environmental Impact Statement for an Early Site Permit (ESP) at the Exelon ESP Site, 42884-42885 [E6-12075]
Download as PDF
rwilkins on PROD1PC63 with NOTICES
42884
Federal Register / Vol. 71, No. 145 / Friday, July 28, 2006 / Notices
LEU fuel will not require additional
safety or security controls or conditions
beyond those already in place. The NRC
staff also finds that this increase in the
fuel possession limit is within the
normal possession limit for research
reactors.
The increased possession limit does
not allow operation with the fuel other
than that already authorized by the
license and TSs. This change does not
authorize conversion to the new LEU
fuel planned for conversion, i.e., 30
weight percent (Wt%) vice the currently
authorized 9 Wt%. (The authorization
for conversion will be the subject of an
ongoing separate evaluation). Therefore,
the radioactive fission product
inventory will not be increased by the
increased fuel possession limit and the
routine effluent or potential accident
release levels will not increase beyond
those already analyzed and accepted
under the current license and TSs.
Further, in accordance with the
existing TSs, reactor fuel will be stored
in a geometrical array where the
effective multiplication is less than 0.8
for all conditions of moderation.
Therefore, the potential for accidental
criticality is not increased with the
increased fuel possession limit.
The increase in the special nuclear
material possession limit does not
impact the security requirements for the
facility. In accordance with 10 CFR 73.2,
the increase possession would be
consistent with special nuclear material
of moderate strategic significance
(Category II). The licensee’s current
security plan meets or exceeds the
requirements for this level of material
under 10 CFR 73.67(d).
The license changes are to allow for
conversion in a manner that is timely to
support the non-proliferation goals of
the nation and allow continued research
and development in accordance with
the license and regulations. They do not
change the security plan requirements
which are consistent the provisions of
10 CFR 73.67(d) for special nuclear
material of moderate strategic
significance (Category II) in accordance
with 10 CFR 73.2, because the addition
of the LEU fuel is within the possession
limit for that category of material.
The inspection program has found
that the licensee has routinely used
such material safely and securely.
The licensee submitted a proposed
license condition in its June 13, 2006,
letter. The NRC staff noted several
changes from the proposed license
condition were needed to allow for
possession of the current material and
allow for receipt, but not use, of the new
LEU fuel. Specifically, the licensee’s
authority to receive additional HEU fuel
VerDate Aug<31>2005
17:47 Jul 27, 2006
Jkt 208001
is removed from License Condition
2.B.(2), and the amount of material
possessed under that license condition
was reduced from 17.0 to 12.0 kg.
Further, License Condition 2.B.(8) is
added to allow for the receipt and
possession, but not use, of the LEU fuel
for conversion. A telephone
conversation between the project
manager and the Associate Director of
the NSC TRIGA Research Reactor
facility on July 6, 2006, confirmed that
these differences were understood and
could be implemented consistent with
protecting the public health and safety.
Because the requested increased
possession limit may be possessed
safely and securely under the terms of
the existing TSs and security plan, the
increase in special nuclear material
possession limit as specified above is
acceptable to the NRC staff. Further, the
NRC staff has determined that the
public health and safety and the
common defense and security require
the licensee to receive and possess the
LEU fuel so that the LEU fuel may be
configured into fuel bundles to convert
from HEU fuel in accordance with the
schedule planned by the DOE to support
U.S. non-proliferation policies.
3.0 Environmental Consideration
In accordance with 10 CFR 51.10(d),
an Order is not subject to Section 102
of the National Environmental Policy
Act. The NRC staff notes, however, that
even if these changes were not being
imposed by an Order, the changes
would not require an environmental
impact statement or environmental
assessment. The license changes involve
use of a facility component located
within the restricted area as defined in
10 CFR part 20 or changes in inspection
and surveillance requirements. The NRC
staff has determined that the changes
involve no significant increase in the
amounts or types of any effluents that
may be released off site and no
significant increase in individual or
cumulative occupational radiation
exposure. Therefore, pursuant to 10 CFR
51.22(b), no environmental impact
statement or environmental assessment
is required.
4.0 Conclusion
The NRC staff has concluded, on the
basis of the considerations discussed
above, that (1) The proposal by the
licensee for possession of LEU fuel is
consistent with and in furtherance of
the requirements of 10 CFR 50.64, (2)
there is reasonable assurance that the
health and safety of the public will not
be endangered by the proposed
activities; and (3) such activities will be
conducted in compliance with the
PO 00000
Frm 00090
Fmt 4703
Sfmt 4703
Commission’s regulations and will not
be inimical to the common defense and
security or the health and safety of the
public. Accordingly, it is concluded that
an enforcement order as described
above should be issued pursuant to 10
CFR 50.64(c)(3).
Dated: July 21, 2006.
M. Mendonca.
Principal Contributor:
[FR Doc. E6–12105 Filed 7–27–06; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 52–007]
Exelon Generating Company, LLC;
Notice of Availability of the Final
Environmental Impact Statement for an
Early Site Permit (ESP) at the Exelon
ESP Site
Notice is hereby given that the U.S.
Nuclear Regulatory Commission (NRC,
the Commission) has published
NUREG–1815, ‘‘Environmental Impact
Statement for an Early Site Permit (ESP)
at the Exelon ESP Site: Final Report.’’
The site is located near the town of
Clinton in DeWitt County, Illinois. The
application for the ESP was submitted
by letter dated September 25, 2003,
pursuant to Title 10 of the Code of
Federal Regulations part 52 (10 CFR Part
52). The application included a site
redress plan in accordance with 10 CFR
52.17(c) and 52.25. If the site redress
plan is incorporated in an approved
ESP, then the applicant may carry out
certain site preparation work and
preliminary construction activities. A
notice of receipt and availability of the
application, which included the
environmental report (ER), was
published in the Federal Register on
October 24, 2003 (68 FR 61020). A
notice of acceptance for docketing of the
application for the ESP was published
in the Federal Register on October 30,
2003 (68 FR 61835). A notice of intent
to prepare an environmental impact
statement and to conduct the scoping
process was published in the Federal
Register on November 25, 2003 (68 FR
66130). A notice of availability of the
draft EIS was published in the Federal
Register on March 10, 2005 (70 FR
12022).
The purpose of this notice is to inform
the public that NUREG–1815,
‘‘Environmental Impact Statement for an
Early Site Permit (ESP) at the Exelon
ESP Site: Final Report,’’ Volumes 1 and
2, is available for public inspection in
the NRC Public Document Room (PDR)
located at One White Flint North, 11555
E:\FR\FM\28JYN1.SGM
28JYN1
Federal Register / Vol. 71, No. 145 / Friday, July 28, 2006 / Notices
Rockville Pike (first floor), Rockville,
Maryland, 20852, or from the Publicly
Available Records (PARS) component of
NRC’s Agencywide Documents Access
and Management System (ADAMS), and
will also be placed directly on the NRC
Web site at https://www.nrc.gov. ADAMS
is accessible from the NRC Web site at
https://www.nrc.gov/reading-rm/
adams.html (the Public Electronic
Reading Room). Persons who do not
have access to ADAMS, or who
encounter problems in accessing the
documents located in ADAMS, should
contact the PDR reference staff at 1–
800–397–4209, 301–415–4737, or by email to pdr@nrc.gov. In addition, the
Vespasian Warner Public Library,
located at 310 North Quincy Street,
Clinton, Illinois 61727, has agreed to
make the FEIS available for public
inspection.
For Further Information Contact:
Thomas J. Kenyon, New Reactors
Environmental Projects Branch,
Division of New Reactor Licensing, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001. Mr.
Kenyon may be contacted by telephone
at (301) 415–1120 or by e-mail at
https://www.ClintonEIS.gov.
Dated at Rockville, Maryland, this 20th day
of July 2006.
For the Nuclear Regulatory Commission.
David B. Matthews,
Director, Division of New Reactor Licensing
Office of Nuclear Reactor Regulation.
[FR Doc. E6–12075 Filed 7–27–06; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
rwilkins on PROD1PC63 with NOTICES
Final Regulatory Guide; Issuance,
Availability
The U.S. Nuclear Regulatory
Commission (NRC) has issued a revision
to an existing guide in the agency’s
Regulatory Guide Series. This series has
been developed to describe and make
available to the public such information
as methods that are acceptable to the
NRC staff for implementing specific
parts of the NRC’s regulations,
techniques that the staff uses in
evaluating specific problems or
postulated accidents, and data that the
staff needs in its review of applications
for permits and licenses.
Revision 2 of Regulatory Guide 1.92,
entitled ‘‘Combining Modal Responses
and Spatial Components in Seismic
Response Analysis,’’ provides licensees
and applicants with improved guidance
concerning methods that the NRC staff
considers acceptable for combining
modal responses and spatial
VerDate Aug<31>2005
17:47 Jul 27, 2006
Jkt 208001
components in seismic response
analysis of nuclear power plant (NPP)
structures, systems, and components
(SSCs) that are important to safety. As
defined in Appendix A, ‘‘General
Design Criteria for Nuclear Power
Plants,’’ to Title 10, part 50, of the Code
of Federal Regulations (10 CFR part 50),
Criterion 2, ‘‘Design Bases for Protection
Against Natural Phenomena,’’ requires,
in part, that SSCs that are important to
safety must be designed to withstand
the effects of natural phenomena (such
as earthquakes) without losing their
capability to perform their respective
safety functions. Such SSCs must also
be designed to accommodate the effects
of, and be compatible with, the
environmental conditions associated
with normal operation and postulated
accidents. Appendix S, ‘‘Earthquake
Engineering Criteria for Nuclear Power
Plants,’’ to 10 CFR part 50 specifies, in
part, requirements for implementing
General Design Criterion 2 with respect
to earthquakes.1
For several decades, the nuclear
industry fulfilled Criterion 2 using the
response spectrum method and the time
history method for seismic analysis and
design of NPP SSCs. Then, in 1976, the
NRC issued Revision 1 of Regulatory
Guide 1.92, which described then up-todate guidance for using the response
spectrum and time history methods.
Since that time, research in the United
States has resulted in improved
methods that yield more accurate
estimates of SSC seismic response,
while reducing unnecessary
conservatism. In view of those
improvements, Revision 2 of Regulatory
Guide 1.92 describes methods that the
NRC staff finds acceptable for
combining modal responses and spatial
components in seismic response
analysis.
The NRC staff initially published
Revision 2 of Regulatory Guide 1.92 as
DG–1108, dated August 2001. The staff
subsequently considered stakeholders’
feedback on DG–1108, incorporated the
necessary changes, and again solicited
public comment on the revised guide by
publishing a Federal Register notice (70
FR 7777) concerning Draft Regulatory
Guide DG–1127 on February 15, 2005.
Following the closure of the public
1 Appendix S to 10 CFR part 50 applies to
applicants for a design certification or combined
license pursuant to 10 CFR part 52, ‘‘Early Site
Permits; Standard Design Certifications; and
Combined Licenses for Nuclear Power Plants,’’ or
a construction permit or operating license pursuant
to 10 CFR part 50 after January 10, 1997. However,
the earthquake engineering criteria in Section VI of
Appendix A to 10 CFR part 100 continue to apply
for either an operating license applicant or an
operating license holder whose construction permit
was issued before January 10, 1997.
PO 00000
Frm 00091
Fmt 4703
Sfmt 4703
42885
comment period on April 15, 2005, the
staff considered all stakeholder
comments in the course of preparing
Revision 2 of Regulatory Guide 1.92.
The staff’s responses to all comments
received are available in the NRC’s
Agencywide Documents Access and
Management System (ADAMS) at
https://www.nrc.gov/reading-rm/
adams.html, under Accession
#ML061630344.
The NRC staff encourages and
welcomes comments and suggestions in
connection with improvements to
published regulatory guides, as well as
items for inclusion in regulatory guides
that are currently being developed. You
may submit comments by any of the
following methods.
Mail comments to: Rules and
Directives Branch, Office of
Administration, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001.
Hand-deliver comments to: Rules and
Directives Branch, Office of
Administration, U.S. Nuclear Regulatory
Commission, 11555 Rockville Pike,
Rockville, Maryland 20852, between
7:30 a.m. and 4:15 p.m. on Federal
workdays.
Fax comments to: Rules and
Directives Branch, Office of
Administration, U.S. Nuclear Regulatory
Commission at (301) 415–5144.
Requests for technical information
about Revision 2 of Regulatory Guide
1.92 may be directed to Dr. T.Y. Chang,
at (301) 415–6450 or via e-mail to
TYC@nrc.gov.
Regulatory guides are available for
inspection or downloading through the
NRC’s public Web site in the Regulatory
Guides document collection of the
NRC’s Electronic Reading Room at
https://www.nrc.gov/reading-rm/doccollections/. Electronic copies of
Revision 2 of Regulatory Guide 1.92 are
also available in the NRC’s Agencywide
Documents Access and Management
System (ADAMS) at https://
www.nrc.gov/reading-rm/adams.html,
under Accession #ML053250475.
In addition, regulatory guides are
available for inspection at the NRC’s
Public Document Room (PDR), which is
located at 11555 Rockville Pike,
Rockville, Maryland; the PDR’s mailing
address is USNRC PDR, Washington, DC
20555–0001. The PDR can also be
reached by telephone at (301) 415–4737
or (800) 397–4205, by fax at (301) 415–
3548, and by e-mail to PDR@nrc.gov.
Requests for single copies of draft or
final guides (which may be reproduced)
or for placement on an automatic
distribution list for single copies of
future draft guides in specific divisions
should be made in writing to the U.S.
E:\FR\FM\28JYN1.SGM
28JYN1
Agencies
[Federal Register Volume 71, Number 145 (Friday, July 28, 2006)]
[Notices]
[Pages 42884-42885]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-12075]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 52-007]
Exelon Generating Company, LLC; Notice of Availability of the
Final Environmental Impact Statement for an Early Site Permit (ESP) at
the Exelon ESP Site
Notice is hereby given that the U.S. Nuclear Regulatory Commission
(NRC, the Commission) has published NUREG-1815, ``Environmental Impact
Statement for an Early Site Permit (ESP) at the Exelon ESP Site: Final
Report.'' The site is located near the town of Clinton in DeWitt
County, Illinois. The application for the ESP was submitted by letter
dated September 25, 2003, pursuant to Title 10 of the Code of Federal
Regulations part 52 (10 CFR Part 52). The application included a site
redress plan in accordance with 10 CFR 52.17(c) and 52.25. If the site
redress plan is incorporated in an approved ESP, then the applicant may
carry out certain site preparation work and preliminary construction
activities. A notice of receipt and availability of the application,
which included the environmental report (ER), was published in the
Federal Register on October 24, 2003 (68 FR 61020). A notice of
acceptance for docketing of the application for the ESP was published
in the Federal Register on October 30, 2003 (68 FR 61835). A notice of
intent to prepare an environmental impact statement and to conduct the
scoping process was published in the Federal Register on November 25,
2003 (68 FR 66130). A notice of availability of the draft EIS was
published in the Federal Register on March 10, 2005 (70 FR 12022).
The purpose of this notice is to inform the public that NUREG-1815,
``Environmental Impact Statement for an Early Site Permit (ESP) at the
Exelon ESP Site: Final Report,'' Volumes 1 and 2, is available for
public inspection in the NRC Public Document Room (PDR) located at One
White Flint North, 11555
[[Page 42885]]
Rockville Pike (first floor), Rockville, Maryland, 20852, or from the
Publicly Available Records (PARS) component of NRC's Agencywide
Documents Access and Management System (ADAMS), and will also be placed
directly on the NRC Web site at https://www.nrc.gov. ADAMS is accessible
from the NRC Web site at https://www.nrc.gov/reading-rm/adams.html (the
Public Electronic Reading Room). Persons who do not have access to
ADAMS, or who encounter problems in accessing the documents located in
ADAMS, should contact the PDR reference staff at 1-800-397-4209, 301-
415-4737, or by e-mail to pdr@nrc.gov. In addition, the Vespasian
Warner Public Library, located at 310 North Quincy Street, Clinton,
Illinois 61727, has agreed to make the FEIS available for public
inspection.
For Further Information Contact: Thomas J. Kenyon, New Reactors
Environmental Projects Branch, Division of New Reactor Licensing, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001. Mr. Kenyon
may be contacted by telephone at (301) 415-1120 or by e-mail at https://
www.ClintonEIS.gov.
Dated at Rockville, Maryland, this 20th day of July 2006.
For the Nuclear Regulatory Commission.
David B. Matthews,
Director, Division of New Reactor Licensing Office of Nuclear Reactor
Regulation.
[FR Doc. E6-12075 Filed 7-27-06; 8:45 am]
BILLING CODE 7590-01-P