Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments, 40495-40496 [E6-11194]

Download as PDF Federal Register / Vol. 71, No. 136 / Monday, July 17, 2006 / Notices comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. Comments, protests and interventions may be filed electronically via the Internet in lieu of paper; See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s web site under ‘‘efiling’’ link. The Commission strongly encourages electronic filing. s. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘RECOMMENDATIONS FOR TERMS AND CONDITIONS’’, ‘‘PROTEST’’, ‘‘COMPETING APPLICATION’’ OR ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission’s regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. A copy of any motion to intervene must also be served upon each representative of the Applicant specified in the particular application. t. Agency Comments—Federal, State, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. Magalie R. Salas, Secretary. [FR Doc. E6–11193 Filed 7–14–06; 8:45 am] rwilkins on PROD1PC63 with NOTICES BILLING CODE 6717–01–P VerDate Aug<31>2005 17:41 Jul 14, 2006 Jkt 208001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments July 10, 2006. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Preliminary Permit. b. Project No.: 12682–000. c. Date filed: June 2, 2006. d. Applicant: Greybull Valley Irrigation District. e. Name of Project: Greybull Valley Dam Project. f. Location: On Roach Gulch, in Park County, Wyoming, utilizing the Greybull Valley Dam owned by the applicant. Part of the project is located on lands administered by the U.S. Bureau of Land Management. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: William Schlenker, Greybull Valley Irrigation District, 989 Highway 20 West, P.O. Box 44, Emblem, WY 82422, (307) 762–3555. i. FERC Contact: Robert Bell, (202) 502–6062. j. Deadline for filing comments, protests, and motions to intervene: 60 days from the issuance date of this notice. All documents (original and eight copies) should be filed with: Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Please include the project number (P– 12682–000) on any comments or motions filed. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Project: The proposed project would consist of: (1) PO 00000 Frm 00027 Fmt 4703 Sfmt 4703 40495 An existing 1,320-foot-long, 150 foothigh zoned earthen dam, (2) a reservoir having a surface area of 900 acres and storage capacity of 33,169 acre-feet and normal water surface elevation of 4,953 feet msl, (3) a proposed intake structure, (4) a proposed powerhouse containing two generating units having a total installed capacity of 5 MW, (5) a proposed 3-mile-long 15, kV transmission line, and (6) appurtenant facilities. Applicant estimates that the average annual generation would be 10 GWh and would be sold to a local utility. l. This filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3676 or e-mail FERCONLINESUPPORT@FERC.GOV. For TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item h above. m. Competing Preliminary Permit— Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30(b) and 4.36. n. Competing Development Application—Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30(b) and 4.36. o. Notice of Intent—A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include E:\FR\FM\17JYN1.SGM 17JYN1 rwilkins on PROD1PC63 with NOTICES 40496 Federal Register / Vol. 71, No. 136 / Monday, July 17, 2006 / Notices an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice. p. Proposed Scope of Studies Under Permit—A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project. q. Comments, Protests, or Motions to Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. r. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘NOTICE OF INTENT TO FILE COMPETING APPLICATION’’, ‘‘COMPETING APPLICATION’’, ‘‘PROTEST’’, and ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission’s regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. An additional copy must be sent to Director, Division of Hydropower Administration and Compliance, Federal Energy Regulatory Commission, at the above-mentioned address. A copy of any notice of intent, competing application or motion to intervene must also be served upon each representative of the Applicant specified in the particular application. s. Agency Comments—Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be VerDate Aug<31>2005 17:41 Jul 14, 2006 Jkt 208001 obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. Magalie R. Salas, Secretary. [FR Doc. E6–11194 Filed 7–14–06; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments July 10, 2006. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Preliminary Permit. b. Project No.: 12694–000. c. Date filed: June 19, 2006. d. Applicant: Alaska Tidal Energy Company. e. Name of Project: Kachemak Bay Tidal Energy Project. f. Location: The project would be located on the Kachemak Bay in the southern part of Cook Inlet in Kenai Peninsula, Alaska. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contacts: Joseph A. Cannon, Pillsbury Winthrop Shaw Pittman LLP, 2300 N Street, NW., Washington, DC 20037, phone: (202) 663–8000, and Charles B. Cooper, TRC Environmental, Boott Mills South, 116 John St., Lowell, MA 01852, phone: (978) 656–3567. i. FERC Contact: Robert Bell, (202) 502–6062. j. Deadline for filing comments, protests, and motions to intervene: 60 days from the issuance date of this notice. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Project: The proposed project would consist of: (1) PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 50 to 200 Tidal In Stream Energy Conversion (TISEC) devices consisting of rotating propeller blades, (2) integrated generators with a capacity of 0.5 to 2.0 MW each, (3) anchoring systems, (4) mooring lines, (5) interconnection transmission lines, and (6) appurtenant facilities. The project is estimated to have an annual generation of 8.76 gigawatt-hours per-unit per-year, which would be sold to a local utility. l. Locations of Applications: A copy of the application is available for inspection and reproduction at the Commission in the Public Reference Room, located at 888 First Street NE., Room 2A, Washington DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1–866–208–3676 or e-mail FERCOnlineSupport@ferc.gov. For TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item h above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Competing Preliminary Permit— Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30(b) and 4.36. o. Competing Development Application—Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30(b) and 4.36. E:\FR\FM\17JYN1.SGM 17JYN1

Agencies

[Federal Register Volume 71, Number 136 (Monday, July 17, 2006)]
[Notices]
[Pages 40495-40496]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-11194]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Notice of Application Accepted for Filing and Soliciting Motions 
To Intervene, Protests, and Comments

July 10, 2006.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Preliminary Permit.
    b. Project No.: 12682-000.
    c. Date filed: June 2, 2006.
    d. Applicant: Greybull Valley Irrigation District.
    e. Name of Project: Greybull Valley Dam Project.
    f. Location: On Roach Gulch, in Park County, Wyoming, utilizing the 
Greybull Valley Dam owned by the applicant. Part of the project is 
located on lands administered by the U.S. Bureau of Land Management.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: William Schlenker, Greybull Valley Irrigation 
District, 989 Highway 20 West, P.O. Box 44, Emblem, WY 82422, (307) 
762-3555.
    i. FERC Contact: Robert Bell, (202) 502-6062.
    j. Deadline for filing comments, protests, and motions to 
intervene: 60 days from the issuance date of this notice.
    All documents (original and eight copies) should be filed with: 
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE., Washington, DC 20426. Comments, protests, and 
interventions may be filed electronically via the Internet in lieu of 
paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the 
Commission's Web site under the ``e-Filing'' link. The Commission 
strongly encourages electronic filings. Please include the project 
number (P-12682-000) on any comments or motions filed.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person in the official service list for the 
project. Further, if an intervenor files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. Description of Project: The proposed project would consist of: 
(1) An existing 1,320-foot-long, 150 foot-high zoned earthen dam, (2) a 
reservoir having a surface area of 900 acres and storage capacity of 
33,169 acre-feet and normal water surface elevation of 4,953 feet msl, 
(3) a proposed intake structure, (4) a proposed powerhouse containing 
two generating units having a total installed capacity of 5 MW, (5) a 
proposed 3-mile-long 15, kV transmission line, and (6) appurtenant 
facilities.
    Applicant estimates that the average annual generation would be 10 
GWh and would be sold to a local utility.
    l. This filing is available for review at the Commission in the 
Public Reference Room or may be viewed on the Commission's Web site at 
https://www.ferc.gov using the ``eLibrary'' link. Enter the docket 
number excluding the last three digits in the docket number field to 
access the document. For assistance, call toll-free 1-866-208-3676 or 
e-mail FERCONLINESUPPORT@FERC.GOV. For TTY, call (202) 502-8659. A copy 
is also available for inspection and reproduction at the address in 
item h above.
    m. Competing Preliminary Permit--Anyone desiring to file a 
competing application for preliminary permit for a proposed project 
must submit the competing application itself, or a notice of intent to 
file such an application, to the Commission on or before the specified 
comment date for the particular application (see 18 CFR 4.36). 
Submission of a timely notice of intent allows an interested person to 
file the competing preliminary permit application no later than 30 days 
after the specified comment date for the particular application. A 
competing preliminary permit application must conform with 18 CFR 
4.30(b) and 4.36.
    n. Competing Development Application--Any qualified development 
applicant desiring to file a competing development application must 
submit to the Commission, on or before a specified comment date for the 
particular application, either a competing development application or a 
notice of intent to file such an application. Submission of a timely 
notice of intent to file a development application allows an interested 
person to file the competing application no later than 120 days after 
the specified comment date for the particular application. A competing 
license application must conform with 18 CFR 4.30(b) and 4.36.
    o. Notice of Intent--A notice of intent must specify the exact 
name, business address, and telephone number of the prospective 
applicant, and must include

[[Page 40496]]

an unequivocal statement of intent to submit, if such an application 
may be filed, either a preliminary permit application or a development 
application (specify which type of application). A notice of intent 
must be served on the applicant(s) named in this public notice.
    p. Proposed Scope of Studies Under Permit--A preliminary permit, if 
issued, does not authorize construction. The term of the proposed 
preliminary permit would be 36 months. The work proposed under the 
preliminary permit would include economic analysis, preparation of 
preliminary engineering plans, and a study of environmental impacts. 
Based on the results of these studies, the Applicant would decide 
whether to proceed with the preparation of a development application to 
construct and operate the project.
    q. Comments, Protests, or Motions to Intervene--Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    r. Filing and Service of Responsive Documents--Any filings must 
bear in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT 
TO FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', 
``PROTEST'', and ``MOTION TO INTERVENE'', as applicable, and the 
Project Number of the particular application to which the filing 
refers. Any of the above-named documents must be filed by providing the 
original and the number of copies provided by the Commission's 
regulations to: The Secretary, Federal Energy Regulatory Commission, 
888 First Street, NE., Washington, DC 20426. An additional copy must be 
sent to Director, Division of Hydropower Administration and Compliance, 
Federal Energy Regulatory Commission, at the above-mentioned address. A 
copy of any notice of intent, competing application or motion to 
intervene must also be served upon each representative of the Applicant 
specified in the particular application.
    s. Agency Comments--Federal, state, and local agencies are invited 
to file comments on the described application. A copy of the 
application may be obtained by agencies directly from the Applicant. If 
an agency does not file comments within the time specified for filing 
comments, it will be presumed to have no comments. One copy of an 
agency's comments must also be sent to the Applicant's representatives.

Magalie R. Salas,
Secretary.
 [FR Doc. E6-11194 Filed 7-14-06; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.