Pipeline Safety: Grant of Waiver; Maritimes & Northeast Pipeline, L.L.C., 39148-39151 [06-6107]
Download as PDF
39148
Federal Register / Vol. 71, No. 132 / Tuesday, July 11, 2006 / Notices
sroberts on PROD1PC70 with NOTICES
Headquarters and PHMSA Central
Region Office within 180 days after
completion of uprating.
A final report must be submitted to
PHMSA Headquarters and PHMSA
Central Regional Office upon
completion of the second ILI run for the
pipeline.
Integrity Management
24. Initial ILI: A baseline ILI must be
performed in association with this
waiver on the pipeline using a highresolution inline inspection technology
capable of detecting metal loss and
mechanical damage. The results of the
baseline ILI must be integrated with the
baseline CIS as described in criteria
number 16.
25. Future ILI: A second high
resolution MFL inspection must be
performed on the pipe subject to the
waiver following the baseline ILI and be
completed within the first reassessment
interval required by subpart O,
regardless of HCA classification. Future
ILI must be performed on a frequency
consistent with subpart O for the entire
pipeline covered by this waiver.
26. Direct Assessment Plan: Headers,
mainline valve bypasses, and other
sections covered by this waiver that
cannot accommodate ILI tools must be
part of a Direct Assessment plan or
other acceptable integrity monitoring
method.
27. Damage Prevention Program:
Common Ground Alliance’s damage
prevention best practices must be
incorporated into APL’s damage
prevention program.
28. Anomaly Evaluation and Repair:
Anomaly evaluations and repairs must
be performed based upon the following:
• For purposes of this criterion, the
Failure Pressure Ratio (FPR) is an
indication of the pipeline’s remaining
strength from an anomaly and is equal
to the predicted failure pressure divided
by the MAOP.
• Anomaly Response Time.
Æ Any anomaly with a FPR equal to
or less than 1.1 must be treated as an
‘‘immediate repair’’ per subpart O.
Æ Any anomaly with a FPR equal to
or less than 1.25 must be remediated
within 12 months per subpart O.
Æ Any anomaly with an FPR greater
than 1.25 must have a remediation
schedule per subpart O.
• Anomaly Repair Criteria.
Æ Segments operating at MAOP equal
to 80 percent stress level—Any anomaly
evaluated and found to have an FPR
equal to or less than 1.25 must be
repaired.
Æ Segments operating at MAOP equal
to 66 percent stress level—Any anomaly
evaluated and found to have an FPR
VerDate Aug<31>2005
16:49 Jul 10, 2006
Jkt 208001
equal to or less than 1.50 must be
repaired.
Æ Segments operating at MAOP equal
to 56 percent stress level—Any anomaly
evaluated and found to have an FPR
equal to or less than 1.80 must be
repaired.
a. All other pipe segments with
anomalies that are not repaired must be
reassessed according to subpart O and
ASME Standard B31.8S requirements.
Each anomaly not repaired must have a
corrosion growth rate and an ILI
tolerance assigned to it per the Gas IMP
to determine the maximum reinspection interval.
b. APL must confirm that the
remaining strength (R-STRENG)
effective area method, RSTRENG¥0.85dL, and B31G assessment
methods are valid for the pipe diameter,
wall thickness, grade, operating
pressure, operating stress level, and
operating temperature covered under
this waiver. If the assessment methods
are not valid, APL must submit a valid
method to PHMSA Central Region
Office. Until confirmation of the
previously mentioned anomaly
assessment calculations have been
performed, APL must use the most
conservative of the calculations for
anomaly evaluation.
c. Dents must be evaluated and
repaired in accordance with
§§ 192.309(b)(ii) and 192.933(d)(l)(ii).
29. Potential Impact Radius
Calculation Updates: If the pipeline
operating pressures and gas quality are
determined to be outside the parameters
of the C–FER Study, a new study with
the updated parameters must be
incorporated into the IMP.
If at anytime PHMSA determines the
effect of the waiver is inconsistent with
pipeline safety, PHMSA will revoke the
waiver at its sole discretion.
Authority: 49 U.S.C. 60118 (c) and 49 CFR
1.53.
Issued in Washington, DC, on July 5, 2006.
Theodore L. Willke,
Deputy Associate Administrator for Pipeline
Safety.
[FR Doc. 06–6106 Filed 7–6–06; 9:10 am]
BILLING CODE 4910–60–P
DEPARTMENT OF TRANSPORTATION
Pipeline and Hazardous Materials
Safety Administration
[Docket No. PHMSA–2006–23448; Notice 2]
Pipeline Safety: Grant of Waiver;
Maritimes & Northeast Pipeline, L.L.C.
Pipeline and Hazardous
Materials Safety Administration
(PHMSA); DOT.
AGENCY:
PO 00000
Frm 00100
Fmt 4703
Sfmt 4703
ACTION:
Grant of waiver.
SUMMARY: PHMSA is granting Maritimes
& Northeast Pipeline, L.L.C. (M&N) a
waiver of compliance from certain
PHMSA regulations for the United
States portion of its pipeline system.
This waiver increases the maximum
allowable operating pressure (MAOP)
for the pipeline. This waiver decision
also authorizes M&N to increase the
design factor for its compressor station
piping, grants relief from the strength
testing requirements for M&N’s
compressor station piping, grants relief
in establishing the MAOP of pipelines
operating above prescribed hoop
stresses, grants relief from the capacity
requirements of pressure limiting
stations, and authorizes M&N to
maintain the pressure rating of portions
of the waiver area subject to a change in
class location.
Before granting the waiver, PHMSA
performed a thorough technical review
of M&N’s application and supporting
documents. PHMSA requested and
received supplementary information on
numerous technical aspects of M&N’s
design, engineering, operations, and
maintenance practices. The materials
are available in docket PHMSA–2006–
23448 at https://dms.dot.gov. PHMSA
also sought comments from the public
and received positive feedback from
States along the pipeline and the
Technical Pipeline Safety Standards
Committee.
The waiver is subject to and
conditional upon supplemental safety
criteria set forth in this notice. The
supplemental safety criteria address the
life-cycle management of the subject
pipeline and require M&N to adhere to
maintenance, inspection, monitoring,
control, and reporting standards
exceeding existing regulatory
requirements.
SUPPLEMENTARY INFORMATION:
Background
M&N requested a waiver of
compliance for the United States
portion of its pipeline system in Class
1, 2, and 3 locations to operate at stress
levels up to 80 percent, 67 percent, and
56 percent, respectively, of the
pipeline’s specified minimum yield
strength (SMYS). The current MAOP of
the pipeline system is 1,440 pounds per
square inch gauge (psig) and the waiver
would increase it to 1,600 psig.
Specifically, M&N requests a waiver of
compliance from the following
regulatory requirements:
• 49 CFR 192.111—Design factor (F)
for steel pipe;
E:\FR\FM\11JYN1.SGM
11JYN1
sroberts on PROD1PC70 with NOTICES
Federal Register / Vol. 71, No. 132 / Tuesday, July 11, 2006 / Notices
• 49 CFR 192.201—Required capacity
of pressure relieving and limiting
stations;
• 49 CFR 192.503—General
Requirements;
• 49 CFR 192.611—Change in class
location: Confirmation or revision of
maximum allowable operating pressure;
and
• 49 CFR 192.619—Maximum
allowable operating pressure: Steel or
plastic pipelines.
The proposed waiver applies to
approximately 203 miles of M&N’s 24inch diameter pipeline. This portion of
pipeline extends from M&N’s
Baileyville, Maine compressor station
near the United States/Canadian border
to Westbrook, Maine, and includes two
compressor stations.
The proposed waiver also applies to
approximately 100 miles of 30-inch
diameter pipeline. This portion of
pipeline is owned jointly in undivided
interest by M&N and Portland Natural
Gas Transmission System (PNGTS) and
is referred to as the ‘‘Joint Facilities
Mainline.’’ The pipeline extends from
Westbrook, Maine to Dracut,
Massachusetts. Specifically, the Joint
Facilities Mainline requests a waiver of
compliance from the following
regulatory requirements:
• 49 CFR 192.111—Design factor (F)
for steel pipe;
• 49 CFR 192.201—Required capacity
of pressure relieving and limiting
stations;
• 49 CFR 192.611—Change in class
location: Confirmation or revision of
maximum allowable operating pressure;
and
• 49 CFR 192.619—Maximum
allowable operating pressure: Steel or
plastic pipelines.
M&N placed its pipeline in service on
December 1, 1999. M&N Operating
Company, L.L.C., a wholly owned
subsidiary of Duke Energy Gas
Transmission, operates the pipeline.
The pipeline is 24-inch diameter, Grade
X–70 pipe with varying wall
thicknesses. M&N inspected 100 percent
of the pipeline’s girth welds using
radiography. The pipeline, including
girth welds, is coated with fusion
bonded epoxy. M&N tested the Class 1
and 2 pipelines to 125 percent of MAOP
and the Class 3 pipeline was tested to
150 percent of MAOP. In addition, M&N
performed an in-line inspection (ILI) of
its pipeline in 2002 and no anomalies
were detected.
The Joint Facilities Mainline was
placed in service on December 10, 1999.
This pipeline is 30 inches in diameter
and is constructed of Grade X–70 pipe
with varying wall thicknesses. M&N
inspected 100 percent of the pipeline’s
VerDate Aug<31>2005
16:49 Jul 10, 2006
Jkt 208001
girth welds using radiography, and the
pipeline, including girth welds, is
coated with fusion bonded epoxy. The
Joint Facilities Mainline tested the Class
1 and 2 pipelines to 125 percent of
MAOP, and the Class 3 pipeline was
tested to 150 percent of MAOP. M&N
performed an ILI of its 30-inch diameter
pipeline in 2001 and a number of
anomalies were detected. The anomalies
were the result of a cathodic protection
(CP) problem that M&N has resolved.
Pipeline System Analysis
M&N conducted evaluations of the
United States portion of its pipeline and
the Joint Facilities Mainline to confirm
whether the system could safely and
reliably operate at increased stress
levels. As part of its evaluation, M&N
analyzed and compared the threats
imposed on a pipeline operating at 72
percent of SMYS to those imposed on a
pipeline operating at 80 percent of
SMYS, including: (1) External corrosion;
(2) internal corrosion; (3) stress
corrosion cracking; (4) pipe
manufacturing; (5) construction; (6)
equipment; (7) immediate failure due to
puncture; (8) delayed failure due to
resident defects or damage; (9) incorrect
operation; and (10) weather/outside
factors. M&N asserts that any impacts
that could potentially threaten the
integrity of its pipeline as a
consequence of the pipeline operating at
higher stress levels have been addressed
and resolved.
M&N requested a waiver of
compliance from the regulatory
requirements at 49 CFR 192.111. This
regulation prescribes the design factor to
be used in the design formula in
§ 192.105. The design factors are found
in the following table:
Design factor (F)
Class location
1
2
3
4
................................................
................................................
................................................
................................................
0.72
0.60
0.50
0.40
M&N proposed a design factor of 80
percent of SMYS for Class 1, 67 percent
of SMYS for Class 2, and 56 percent of
SMYS for Class 3 locations.
M&N also requested a waiver from
§ 192.201(a)(2)(i) which states if the
MAOP is 60 psig or more, the pressure
may not exceed MAOP plus 10 percent,
or the pressure that produces a hoop
stress of 75 percent SMYS, whichever is
lower. M&N proposes to set the over
pressure protection for the waiver
sections to 104 percent of the pipeline’s
MAOP. This setting is based on the ratio
of 75 percent to 72 percent of SMYS.
PO 00000
Frm 00101
Fmt 4703
Sfmt 4703
39149
M&N also requested a waiver from the
requirements of § 192.503(c) for the 203mile section of its 24-inch pipeline,
which limits the maximum allowable
hoop stress to 80 percent of the
pipeline’s SMYS if air, natural gas, or
inert gas is used as the test medium.
M&N desires to test its compressor
station piping to 82 percent of SMYS.
M&N did not request a waiver from this
section of the regulations for the Joint
Facilities Mainline.
Section 192.611 requires an operator
to confirm or revise the MAOP of its
pipeline if the hoop stress
corresponding to the established MAOP
of a segment of pipeline is not
commensurate with the present class
location. M&N notes that any future
class location changes may result in
separate waiver requests.
Finally, M&N requested relief from
§ 192.619, which establishes the test
factor requirements for pipelines, but
does not reference a test factor for
pipelines operating at 80 percent SMYS.
All class locations in the M&N pipeline
system have been tested to the most
conservative requirements listed in
§ 192.619, including 1.25 for class 1,
1.25 for class 2, and 1.5 for class 3. M&N
asserts conformity with ASME B31.8
testing requirements in which the test
factor is established at 1.25 for pipelines
operating at 80 percent SMYS.
Comments on the Waiver
On March 22, 2006, PHMSA
published a notice of intent to consider
the waiver and solicited public
comments. On May 15, 2006, PHMSA
extended the public comment period to
June 16, 2006. PHMSA received 29
comments.
Seven commenters supported the
waiver and provided conditions for
approval, which PHMSA addressed in
the supplemental safety criteria. Five
commenters raised technical concerns.
These issues included design limitation
of railroad crossings to 60 percent of
SMYS and concerns about increased
pipeline operating pressure and blasting
operations. PHMSA notes that the M&N
pipeline operating stress levels at
railroad crossings meet current railroad
guidelines and will continue to conform
to the requirements after increasing the
pressure on the pipeline (uprating). The
conditions later described in this waiver
require M&N to have an acceptable plan
to monitor and mitigate the affects of
ground movement on the pipeline.
Issues include monitoring of blasting
operations adjacent to the pipeline.
Seventeen commenters opposed the
waiver because of concerns about the
increase in the impact radius of the
pipeline after the pressure uprating. The
E:\FR\FM\11JYN1.SGM
11JYN1
39150
Federal Register / Vol. 71, No. 132 / Tuesday, July 11, 2006 / Notices
supplemental safety criteria established
by PHMSA address the increased
impact radius. The remaining
commenters raised issues outside the
scope of this waiver request, such as
compensation and aesthetics.
Grant of Waiver
PHMSA considered M&N’s waiver
request and whether its proposal will
yield an equivalent or greater degree of
safety than that currently provided by
the regulations. PHMSA published its
notice of intent to consider waiver and
solicited comments on March 22, 2006
(71 FR 14575).
Based on M&N’s application for
waiver for its new pipeline and
PHMSA’s extensive technical analysis
and favorable feedback from the
impacted States and Technical Pipeline
Safety Standards Committee, PHMSA
hereby grants M&N’s waiver request
provided M&N, or a successor operator,
complies with the following
supplemental safety criteria:
Pipe and Material Quality
sroberts on PROD1PC70 with NOTICES
1. Fracture Control Plan: M&N must
implement an overall fracture control
plan addressing fracture initiation,
propagation, and Charpy arrest values.
The fracture initiation, propagation, and
arrest plan must account for the entire
range of temperatures, pressures, and
gas compositions planned for the
pipeline.
2. Fittings: All pressure rated fittings
and components (including flanges,
valves, gaskets, pressure vessels and
compressors) must have a pressure
rating commensurate with the MAOP
and class location of the pipeline.
Designed fittings (including tees, elbows
and caps) must have the same design
factors as the adjacent pipe.
3. Station Design Factor: M&N may
use a design factor not exceeding 0.56
for existing compressor and meter
stations. New compressor and meter
stations must be designed using a design
factor of 0.50 per § 192.111.
4. Temperature Control: The
compressor station discharge
temperature must be limited to 120°
Fahrenheit or a temperature below the
maximum long term operating
temperature for the pipe coating.
5. Overpressure Protection: Mainline
pipeline overpressure protection must
limit pressure to a maximum of 104
percent MAOP.
Supervisory Control and Data
Acquisition (SCADA)
6. SCADA System: M&N must use a
SCADA system to provide remote
monitoring of the pipeline system.
VerDate Aug<31>2005
16:49 Jul 10, 2006
Jkt 208001
7. Mainline Valve Control: Mainline
valves that reside on either side of
pipeline segment containing a High
Consequence Area (HCA) where
personnel response time to the valve
exceeds one (1) hour must be remotely
controlled by the SCADA system. The
SCADA system must be capable of
opening and closing the valve and
monitoring the valve position, upstream
pressure and downstream pressure. As
an alternative to remote control
mainline valves, M&N may implement a
leak detection system.
8. SCADA Set Point Review: M&N
must implement a detailed procedure to
establish and maintain accurate SCADA
set points to ensure the pipeline
operates within acceptable design limits
at all times.
Operations and Maintenance
9. Leak Reporting: M&N must notify
the PHMSA Eastern Regional Office as
soon as practicable of any nonreportable leaks occurring on the
pipeline covered by their waiver.
10. Annual Reporting: Annually,
following approval of the waiver, M&N
must report the following:
• The results of any ILI or direct
assessments performed within the
waiver area during the previous year;
• Any new integrity threats identified
with the waiver area during the
previous year;
• Any encroachment in the waiver
area, including the number of new
residences or public gathering areas;
• Any reportable incidents associated
with the waiver area containing the
waiver location that occurred during the
previous year;
• Any leaks on the pipeline in the
waiver area that occurred during the
previous year;
• List of all repairs on the pipeline
made in the waiver area during the
previous year;
• On-going damage prevention
initiatives on the pipeline in the waiver
area and a discussion of their success;
and
• Any company mergers,
acquisitions, transfers of assets, or other
events affecting the regulatory
responsibility of the company operating
the pipeline to which this waiver
applies.
11. Pipeline Inspection: The pipeline
must be capable of passing ILI. All
headers and other segments covered
under the waiver that do not allow the
passage of an internal inspection device
must have a corrosion mitigation plan.
12. Gas Quality Monitoring and
Control: A gas quality monitoring and
mitigation program must have the
ability to restrict constituents that
PO 00000
Frm 00102
Fmt 4703
Sfmt 4703
promote internal corrosion to not
exceed the following limits:
• H2S (4 grains maximum);
• CO2 (3 percent maximum);
• H2O (less than or equal to 7 pounds
per million standard cubic feet and no
free water); and,
• Other deleterious constituents that
may impact the integrity of the pipeline
must be minimized.
13. Gas Quality Control Equipment:
Filters/separators must be installed at
locations where needed to comply with
the above gas quality requirements and
meet M&N’s gas tariff.
14. Control of Liquids: Gas quality
monitoring equipment must be installed
to permit the operator to manage the
introduction of contaminants and free
liquids into the pipeline.
15. Corrosion Mitigation Plan: M&N
must submit an external corrosion
mitigation plan as summarized in its
waiver petition.
16. Initial Close Interval Survey: An
initial baseline Close Interval Survey
(CIS) must be completed in concert with
the baseline ILI indicated in American
Petroleum Institute (API) supplementary
requirement 21 and as detailed in its
waiver petition.
17. Verification of Cathodic
Protection: A CIS must be performed in
concert with ILI in accordance with 49
CFR part 192, subpart O reassessment
intervals for all HCA pipeline mileage.
If any annual test point readings fall
below subpart I requirements,
remediation must be performed and
must include a CIS on either side of the
affected test point.
18. Pipeline Markers: The pipeline
must employ line-of-sight markings in
the waiver area except in agricultural
areas, subject to Federal Energy
Regulatory Commission permits or
environmental permits and local
restrictions.
19. Pipeline Patrolling: The pipeline
must be patrolled at least monthly to
inspect for excavation activities, ground
movement, washouts, leakage, and/or
other activities and conditions affecting
the safe operation of the pipeline.
20. Monitoring of Ground Movement:
An effective monitoring/mitigation plan
must be in place to monitor for and
mitigate issues of unstable soil and
ground movement.
21. Uprating Plan Review and
Approval: The uprating plan must be
submitted to the PHMSA Eastern
Regional Office for review and approval
before the uprating plan is executed.
22. Preliminary Criteria Reporting: A
preliminary report describing the
results, completion dates and status of
the supplementary requirements must
be completed and submitted to PHMSA
E:\FR\FM\11JYN1.SGM
11JYN1
Federal Register / Vol. 71, No. 132 / Tuesday, July 11, 2006 / Notices
sroberts on PROD1PC70 with NOTICES
Headquarters and PHMSA Eastern
Regional Office prior to commencing the
uprating of the pipeline system.
23. Criteria Completion Reporting: A
report describing results, completion
dates and status of the outstanding
supplementary requirements must be
submitted to PHMSA Headquarters and
PHMSA Eastern Regional Office within
180 days after the uprating is
completed. A final report must be
submitted upon completion of the
second ILI run for the pipeline.
Integrity Management
24. Initial ILI: A baseline ILI must be
performed in association with M&N’s
waiver petition on the pipeline using a
high resolution Magnetic Flux Leakage
(MFL) tool and a geometry tool before
uprating the pipeline. The results of the
baseline ILI must be integrated with the
baseline CIS as described in criteria
number 16.
25. Future ILI: A second highresolution MFL ILI must be performed
on pipe subject to this waiver following
the baseline ILI and must be completed
within the first reassessment interval
required by subpart O, regardless of
HCA classification. Future ILI
inspections must be performed on a
frequency consistent with subpart O for
the entire pipeline covered by this
waiver.
26. Direct Assessment Plan: Headers,
mainline valve bypasses, and other
sections covered by this waiver that
cannot accommodate ILI tools must be
part of a Direct Assessment (DA) plan or
other acceptable integrity monitoring
method.
27. Damage Prevention Program:
Common Ground Alliance’s damage
prevention best practices must be
incorporated into the Maritimes and
Northeast damage prevention program.
28. Anomaly Evaluation and Repair:
Anomaly evaluations and repairs must
be performed based upon the following:
• For purposes of this criteria, the
Failure Pressure Ratio (FPR) is an
indication of the pipeline’s remaining
strength from an anomaly and is equal
to the predicted failure pressure divided
by the MAOP.
• Anomaly Response Time.
Æ Any anomaly with a FPR equal to
or less than 1.1 must be treated as an
‘‘immediate’’ per subpart O.
Æ Any anomaly with an FPR equal
to or less than 1.25 must be repaired
within 12 months per subpart O.
Æ Any anomaly with an FPR greater
than 1.25 must have a repair schedule
according to subpart O.
• Anomaly Repair Criteria.
Æ Segments operating at MAOP
equal to 80 percent stress level—Any
VerDate Aug<31>2005
16:49 Jul 10, 2006
Jkt 208001
anomaly evaluated and found to have an
FPR equal to or less than 1.25 must be
repaired.
Æ Segments operating at MAOP
equal to 66 percent stress level—Any
anomaly evaluated and found to have an
FPR equal to or less than 1.50 must be
repaired.
Æ Segments operating at MAOP
equal to 56 percent stress level—Any
anomaly evaluated and found to have an
FPR equal to or less than 1.80 must be
repaired.
a. All other pipe segments with
anomalies not repaired must be
reassessed according to subpart O and
American Society of Mechanical
Engineers (ASME) standard B31.8S
requirements. Each anomaly not
repaired must have a corrosion growth
rate and ILI tool tolerance assigned per
the Gas Integrity Management Program
(IMP) to determine the maximum reinspection interval.
b. Operators must confirm the
remaining strength (R-STRENG)
effective area method, R-STRENG—
0.85dL, and ASME B31G assessment
methods are valid for their pipe
diameter, wall thickness, grade,
operating pressure, operating stress
level, and operating temperature. If it is
not valid, M&N must submit a valid
evaluation method to PHMSA. Until
confirmation of the previously
mentioned anomaly assessment
calculations has been performed, M&N
must use the most conservative of the
calculations for anomaly evaluation.
c. Dents must be evaluated and
repaired per §§ 192.309(b)(ii) and
192.933(d)(l)(ii).
29. Potential Impact Radius
Calculation Updates: If the pipeline
operating pressures and gas quality are
determined to be outside the parameters
of the C–FER Study, a new study with
the uprated parameters must be
incorporated into the IMP.
If at anytime PHMSA determines the
effect of the waiver is inconsistent with
pipeline safety, PHMSA will revoke the
waiver at its sole discretion.
Authority: 49 U.S.C. 60118 (c) and 49 CFR
1.53.
Issued in Washington, DC, on July 5, 2006.
Theodore L. Willke,
Deputy Associate Administrator for Pipeline
Safety.
[FR Doc. 06–6107 Filed 7–6–06; 9:10 am]
BILLING CODE 4910–60–P
PO 00000
Frm 00103
Fmt 4703
Sfmt 4703
39151
DEPARTMENT OF THE TREASURY
Internal Revenue Service
Open Meeting of the Area 4 Taxpayer
Advocacy Panel (Including the States
of Illinois, Indiana, Kentucky, Michigan,
Ohio, Tennessee, and Wisconsin)
Internal Revenue Service (IRS),
Treasury.
ACTION: Notice.
AGENCY:
SUMMARY: An open meeting of the Area
4 Taxpayer Advocacy Panel will be
conducted (via teleconference). The
Taxpayer Advocacy Panel is soliciting
public comment, ideas, and suggestions
on improving customer service at the
Internal Revenue Service.
DATES: The meeting will be held
Tuesday, July 25, 2006, at 11 a.m.,
Central Time.
FOR FURTHER INFORMATION CONTACT:
Mary Ann Delzer at 1–888–912–1227, or
(414) 231–2360.
SUPPLEMENTARY INFORMATION: Notice is
hereby given pursuant to Section
10(a)(2) of the Federal Advisory
Committee Act, 5 U.S.C. App. (1988)
that a meeting of the Area 4 Taxpayer
Advocacy Panel will be held Tuesday,
July 25, 2006, at 11 a.m., Central Time
via a telephone conference call. You can
submit written comments to the panel
by faxing the comments to (414) 231–
2363, or by mail to Taxpayer Advocacy
Panel, Stop 1006MIL, 310 West
Wisconsin Avenue, Milwaukee, WI
53203–2221, or you can contact us at
https://www.improveirs.org. This
meeting is not required to be open to the
public, but because we are always
interested in community input we will
accept public comments. Please contact
Mary Ann Delzer at 1–888–912–1227 or
(414) 231–2360 for dial-in information.
The agenda will include the
following: Various IRS issues.
Dated: July 7, 2006.
John Fay,
Acting Director, Taxpayer Advocacy Panel.
[FR Doc. 06–6169 Filed 7–7–06; 3:20 pm]
BILLING CODE 4830–01–P
DEPARTMENT OF THE TREASURY
Internal Revenue Service
Open Meeting of the Area 7 Taxpayer
Advocacy Panel (Including the States
of Alaska, California, Hawaii, and
Nevada)
Internal Revenue Service (IRS),
Treasury.
ACTION: Notice.
AGENCY:
E:\FR\FM\11JYN1.SGM
11JYN1
Agencies
[Federal Register Volume 71, Number 132 (Tuesday, July 11, 2006)]
[Notices]
[Pages 39148-39151]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 06-6107]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Pipeline and Hazardous Materials Safety Administration
[Docket No. PHMSA-2006-23448; Notice 2]
Pipeline Safety: Grant of Waiver; Maritimes & Northeast Pipeline,
L.L.C.
AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA);
DOT.
ACTION: Grant of waiver.
-----------------------------------------------------------------------
SUMMARY: PHMSA is granting Maritimes & Northeast Pipeline, L.L.C. (M&N)
a waiver of compliance from certain PHMSA regulations for the United
States portion of its pipeline system. This waiver increases the
maximum allowable operating pressure (MAOP) for the pipeline. This
waiver decision also authorizes M&N to increase the design factor for
its compressor station piping, grants relief from the strength testing
requirements for M&N's compressor station piping, grants relief in
establishing the MAOP of pipelines operating above prescribed hoop
stresses, grants relief from the capacity requirements of pressure
limiting stations, and authorizes M&N to maintain the pressure rating
of portions of the waiver area subject to a change in class location.
Before granting the waiver, PHMSA performed a thorough technical
review of M&N's application and supporting documents. PHMSA requested
and received supplementary information on numerous technical aspects of
M&N's design, engineering, operations, and maintenance practices. The
materials are available in docket PHMSA-2006-23448 at https://
dms.dot.gov. PHMSA also sought comments from the public and received
positive feedback from States along the pipeline and the Technical
Pipeline Safety Standards Committee.
The waiver is subject to and conditional upon supplemental safety
criteria set forth in this notice. The supplemental safety criteria
address the life-cycle management of the subject pipeline and require
M&N to adhere to maintenance, inspection, monitoring, control, and
reporting standards exceeding existing regulatory requirements.
SUPPLEMENTARY INFORMATION:
Background
M&N requested a waiver of compliance for the United States portion
of its pipeline system in Class 1, 2, and 3 locations to operate at
stress levels up to 80 percent, 67 percent, and 56 percent,
respectively, of the pipeline's specified minimum yield strength
(SMYS). The current MAOP of the pipeline system is 1,440 pounds per
square inch gauge (psig) and the waiver would increase it to 1,600
psig. Specifically, M&N requests a waiver of compliance from the
following regulatory requirements:
49 CFR 192.111--Design factor (F) for steel pipe;
[[Page 39149]]
49 CFR 192.201--Required capacity of pressure relieving
and limiting stations;
49 CFR 192.503--General Requirements;
49 CFR 192.611--Change in class location: Confirmation or
revision of maximum allowable operating pressure; and
49 CFR 192.619--Maximum allowable operating pressure:
Steel or plastic pipelines.
The proposed waiver applies to approximately 203 miles of M&N's 24-
inch diameter pipeline. This portion of pipeline extends from M&N's
Baileyville, Maine compressor station near the United States/Canadian
border to Westbrook, Maine, and includes two compressor stations.
The proposed waiver also applies to approximately 100 miles of 30-
inch diameter pipeline. This portion of pipeline is owned jointly in
undivided interest by M&N and Portland Natural Gas Transmission System
(PNGTS) and is referred to as the ``Joint Facilities Mainline.'' The
pipeline extends from Westbrook, Maine to Dracut, Massachusetts.
Specifically, the Joint Facilities Mainline requests a waiver of
compliance from the following regulatory requirements:
49 CFR 192.111--Design factor (F) for steel pipe;
49 CFR 192.201--Required capacity of pressure relieving
and limiting stations;
49 CFR 192.611--Change in class location: Confirmation or
revision of maximum allowable operating pressure; and
49 CFR 192.619--Maximum allowable operating pressure:
Steel or plastic pipelines.
M&N placed its pipeline in service on December 1, 1999. M&N
Operating Company, L.L.C., a wholly owned subsidiary of Duke Energy Gas
Transmission, operates the pipeline. The pipeline is 24-inch diameter,
Grade X-70 pipe with varying wall thicknesses. M&N inspected 100
percent of the pipeline's girth welds using radiography. The pipeline,
including girth welds, is coated with fusion bonded epoxy. M&N tested
the Class 1 and 2 pipelines to 125 percent of MAOP and the Class 3
pipeline was tested to 150 percent of MAOP. In addition, M&N performed
an in-line inspection (ILI) of its pipeline in 2002 and no anomalies
were detected.
The Joint Facilities Mainline was placed in service on December 10,
1999. This pipeline is 30 inches in diameter and is constructed of
Grade X-70 pipe with varying wall thicknesses. M&N inspected 100
percent of the pipeline's girth welds using radiography, and the
pipeline, including girth welds, is coated with fusion bonded epoxy.
The Joint Facilities Mainline tested the Class 1 and 2 pipelines to 125
percent of MAOP, and the Class 3 pipeline was tested to 150 percent of
MAOP. M&N performed an ILI of its 30-inch diameter pipeline in 2001 and
a number of anomalies were detected. The anomalies were the result of a
cathodic protection (CP) problem that M&N has resolved.
Pipeline System Analysis
M&N conducted evaluations of the United States portion of its
pipeline and the Joint Facilities Mainline to confirm whether the
system could safely and reliably operate at increased stress levels. As
part of its evaluation, M&N analyzed and compared the threats imposed
on a pipeline operating at 72 percent of SMYS to those imposed on a
pipeline operating at 80 percent of SMYS, including: (1) External
corrosion; (2) internal corrosion; (3) stress corrosion cracking; (4)
pipe manufacturing; (5) construction; (6) equipment; (7) immediate
failure due to puncture; (8) delayed failure due to resident defects or
damage; (9) incorrect operation; and (10) weather/outside factors. M&N
asserts that any impacts that could potentially threaten the integrity
of its pipeline as a consequence of the pipeline operating at higher
stress levels have been addressed and resolved.
M&N requested a waiver of compliance from the regulatory
requirements at 49 CFR 192.111. This regulation prescribes the design
factor to be used in the design formula in Sec. 192.105. The design
factors are found in the following table:
------------------------------------------------------------------------
Design
Class location factor (F)
------------------------------------------------------------------------
1.......................................................... 0.72
2.......................................................... 0.60
3.......................................................... 0.50
4.......................................................... 0.40
------------------------------------------------------------------------
M&N proposed a design factor of 80 percent of SMYS for Class 1, 67
percent of SMYS for Class 2, and 56 percent of SMYS for Class 3
locations.
M&N also requested a waiver from Sec. 192.201(a)(2)(i) which
states if the MAOP is 60 psig or more, the pressure may not exceed MAOP
plus 10 percent, or the pressure that produces a hoop stress of 75
percent SMYS, whichever is lower. M&N proposes to set the over pressure
protection for the waiver sections to 104 percent of the pipeline's
MAOP. This setting is based on the ratio of 75 percent to 72 percent of
SMYS.
M&N also requested a waiver from the requirements of Sec.
192.503(c) for the 203-mile section of its 24-inch pipeline, which
limits the maximum allowable hoop stress to 80 percent of the
pipeline's SMYS if air, natural gas, or inert gas is used as the test
medium. M&N desires to test its compressor station piping to 82 percent
of SMYS. M&N did not request a waiver from this section of the
regulations for the Joint Facilities Mainline.
Section 192.611 requires an operator to confirm or revise the MAOP
of its pipeline if the hoop stress corresponding to the established
MAOP of a segment of pipeline is not commensurate with the present
class location. M&N notes that any future class location changes may
result in separate waiver requests.
Finally, M&N requested relief from Sec. 192.619, which establishes
the test factor requirements for pipelines, but does not reference a
test factor for pipelines operating at 80 percent SMYS. All class
locations in the M&N pipeline system have been tested to the most
conservative requirements listed in Sec. 192.619, including 1.25 for
class 1, 1.25 for class 2, and 1.5 for class 3. M&N asserts conformity
with ASME B31.8 testing requirements in which the test factor is
established at 1.25 for pipelines operating at 80 percent SMYS.
Comments on the Waiver
On March 22, 2006, PHMSA published a notice of intent to consider
the waiver and solicited public comments. On May 15, 2006, PHMSA
extended the public comment period to June 16, 2006. PHMSA received 29
comments.
Seven commenters supported the waiver and provided conditions for
approval, which PHMSA addressed in the supplemental safety criteria.
Five commenters raised technical concerns. These issues included design
limitation of railroad crossings to 60 percent of SMYS and concerns
about increased pipeline operating pressure and blasting operations.
PHMSA notes that the M&N pipeline operating stress levels at railroad
crossings meet current railroad guidelines and will continue to conform
to the requirements after increasing the pressure on the pipeline
(uprating). The conditions later described in this waiver require M&N
to have an acceptable plan to monitor and mitigate the affects of
ground movement on the pipeline. Issues include monitoring of blasting
operations adjacent to the pipeline.
Seventeen commenters opposed the waiver because of concerns about
the increase in the impact radius of the pipeline after the pressure
uprating. The
[[Page 39150]]
supplemental safety criteria established by PHMSA address the increased
impact radius. The remaining commenters raised issues outside the scope
of this waiver request, such as compensation and aesthetics.
Grant of Waiver
PHMSA considered M&N's waiver request and whether its proposal will
yield an equivalent or greater degree of safety than that currently
provided by the regulations. PHMSA published its notice of intent to
consider waiver and solicited comments on March 22, 2006 (71 FR 14575).
Based on M&N's application for waiver for its new pipeline and
PHMSA's extensive technical analysis and favorable feedback from the
impacted States and Technical Pipeline Safety Standards Committee,
PHMSA hereby grants M&N's waiver request provided M&N, or a successor
operator, complies with the following supplemental safety criteria:
Pipe and Material Quality
1. Fracture Control Plan: M&N must implement an overall fracture
control plan addressing fracture initiation, propagation, and Charpy
arrest values. The fracture initiation, propagation, and arrest plan
must account for the entire range of temperatures, pressures, and gas
compositions planned for the pipeline.
2. Fittings: All pressure rated fittings and components (including
flanges, valves, gaskets, pressure vessels and compressors) must have a
pressure rating commensurate with the MAOP and class location of the
pipeline. Designed fittings (including tees, elbows and caps) must have
the same design factors as the adjacent pipe.
3. Station Design Factor: M&N may use a design factor not exceeding
0.56 for existing compressor and meter stations. New compressor and
meter stations must be designed using a design factor of 0.50 per Sec.
192.111.
4. Temperature Control: The compressor station discharge
temperature must be limited to 120[deg] Fahrenheit or a temperature
below the maximum long term operating temperature for the pipe coating.
5. Overpressure Protection: Mainline pipeline overpressure
protection must limit pressure to a maximum of 104 percent MAOP.
Supervisory Control and Data Acquisition (SCADA)
6. SCADA System: M&N must use a SCADA system to provide remote
monitoring of the pipeline system.
7. Mainline Valve Control: Mainline valves that reside on either
side of pipeline segment containing a High Consequence Area (HCA) where
personnel response time to the valve exceeds one (1) hour must be
remotely controlled by the SCADA system. The SCADA system must be
capable of opening and closing the valve and monitoring the valve
position, upstream pressure and downstream pressure. As an alternative
to remote control mainline valves, M&N may implement a leak detection
system.
8. SCADA Set Point Review: M&N must implement a detailed procedure
to establish and maintain accurate SCADA set points to ensure the
pipeline operates within acceptable design limits at all times.
Operations and Maintenance
9. Leak Reporting: M&N must notify the PHMSA Eastern Regional
Office as soon as practicable of any non-reportable leaks occurring on
the pipeline covered by their waiver.
10. Annual Reporting: Annually, following approval of the waiver,
M&N must report the following:
The results of any ILI or direct assessments performed
within the waiver area during the previous year;
Any new integrity threats identified with the waiver area
during the previous year;
Any encroachment in the waiver area, including the number
of new residences or public gathering areas;
Any reportable incidents associated with the waiver area
containing the waiver location that occurred during the previous year;
Any leaks on the pipeline in the waiver area that occurred
during the previous year;
List of all repairs on the pipeline made in the waiver
area during the previous year;
On-going damage prevention initiatives on the pipeline in
the waiver area and a discussion of their success; and
Any company mergers, acquisitions, transfers of assets, or
other events affecting the regulatory responsibility of the company
operating the pipeline to which this waiver applies.
11. Pipeline Inspection: The pipeline must be capable of passing
ILI. All headers and other segments covered under the waiver that do
not allow the passage of an internal inspection device must have a
corrosion mitigation plan.
12. Gas Quality Monitoring and Control: A gas quality monitoring
and mitigation program must have the ability to restrict constituents
that promote internal corrosion to not exceed the following limits:
H2S (4 grains maximum);
CO2 (3 percent maximum);
H2O (less than or equal to 7 pounds per million
standard cubic feet and no free water); and,
Other deleterious constituents that may impact the
integrity of the pipeline must be minimized.
13. Gas Quality Control Equipment: Filters/separators must be
installed at locations where needed to comply with the above gas
quality requirements and meet M&N's gas tariff.
14. Control of Liquids: Gas quality monitoring equipment must be
installed to permit the operator to manage the introduction of
contaminants and free liquids into the pipeline.
15. Corrosion Mitigation Plan: M&N must submit an external
corrosion mitigation plan as summarized in its waiver petition.
16. Initial Close Interval Survey: An initial baseline Close
Interval Survey (CIS) must be completed in concert with the baseline
ILI indicated in American Petroleum Institute (API) supplementary
requirement 21 and as detailed in its waiver petition.
17. Verification of Cathodic Protection: A CIS must be performed in
concert with ILI in accordance with 49 CFR part 192, subpart O
reassessment intervals for all HCA pipeline mileage. If any annual test
point readings fall below subpart I requirements, remediation must be
performed and must include a CIS on either side of the affected test
point.
18. Pipeline Markers: The pipeline must employ line-of-sight
markings in the waiver area except in agricultural areas, subject to
Federal Energy Regulatory Commission permits or environmental permits
and local restrictions.
19. Pipeline Patrolling: The pipeline must be patrolled at least
monthly to inspect for excavation activities, ground movement,
washouts, leakage, and/or other activities and conditions affecting the
safe operation of the pipeline.
20. Monitoring of Ground Movement: An effective monitoring/
mitigation plan must be in place to monitor for and mitigate issues of
unstable soil and ground movement.
21. Uprating Plan Review and Approval: The uprating plan must be
submitted to the PHMSA Eastern Regional Office for review and approval
before the uprating plan is executed.
22. Preliminary Criteria Reporting: A preliminary report describing
the results, completion dates and status of the supplementary
requirements must be completed and submitted to PHMSA
[[Page 39151]]
Headquarters and PHMSA Eastern Regional Office prior to commencing the
uprating of the pipeline system.
23. Criteria Completion Reporting: A report describing results,
completion dates and status of the outstanding supplementary
requirements must be submitted to PHMSA Headquarters and PHMSA Eastern
Regional Office within 180 days after the uprating is completed. A
final report must be submitted upon completion of the second ILI run
for the pipeline.
Integrity Management
24. Initial ILI: A baseline ILI must be performed in association
with M&N's waiver petition on the pipeline using a high resolution
Magnetic Flux Leakage (MFL) tool and a geometry tool before uprating
the pipeline. The results of the baseline ILI must be integrated with
the baseline CIS as described in criteria number 16.
25. Future ILI: A second high-resolution MFL ILI must be performed
on pipe subject to this waiver following the baseline ILI and must be
completed within the first reassessment interval required by subpart O,
regardless of HCA classification. Future ILI inspections must be
performed on a frequency consistent with subpart O for the entire
pipeline covered by this waiver.
26. Direct Assessment Plan: Headers, mainline valve bypasses, and
other sections covered by this waiver that cannot accommodate ILI tools
must be part of a Direct Assessment (DA) plan or other acceptable
integrity monitoring method.
27. Damage Prevention Program: Common Ground Alliance's damage
prevention best practices must be incorporated into the Maritimes and
Northeast damage prevention program.
28. Anomaly Evaluation and Repair: Anomaly evaluations and repairs
must be performed based upon the following:
For purposes of this criteria, the Failure Pressure Ratio
(FPR) is an indication of the pipeline's remaining strength from an
anomaly and is equal to the predicted failure pressure divided by the
MAOP.
Anomaly Response Time.
[cir] Any anomaly with a FPR equal to or less than 1.1 must be
treated as an ``immediate'' per subpart O.
[cir] Any anomaly with an FPR equal to or less than 1.25 must be
repaired within 12 months per subpart O.
[cir] Any anomaly with an FPR greater than 1.25 must have a repair
schedule according to subpart O.
Anomaly Repair Criteria.
[cir] Segments operating at MAOP equal to 80 percent stress
level--Any anomaly evaluated and found to have an FPR equal to or less
than 1.25 must be repaired.
[cir] Segments operating at MAOP equal to 66 percent stress
level--Any anomaly evaluated and found to have an FPR equal to or less
than 1.50 must be repaired.
[cir] Segments operating at MAOP equal to 56 percent stress
level--Any anomaly evaluated and found to have an FPR equal to or less
than 1.80 must be repaired.
a. All other pipe segments with anomalies not repaired must be
reassessed according to subpart O and American Society of Mechanical
Engineers (ASME) standard B31.8S requirements. Each anomaly not
repaired must have a corrosion growth rate and ILI tool tolerance
assigned per the Gas Integrity Management Program (IMP) to determine
the maximum re-inspection interval.
b. Operators must confirm the remaining strength (R-STRENG)
effective area method, R-STRENG--0.85dL, and ASME B31G assessment
methods are valid for their pipe diameter, wall thickness, grade,
operating pressure, operating stress level, and operating temperature.
If it is not valid, M&N must submit a valid evaluation method to PHMSA.
Until confirmation of the previously mentioned anomaly assessment
calculations has been performed, M&N must use the most conservative of
the calculations for anomaly evaluation.
c. Dents must be evaluated and repaired per Sec. Sec.
192.309(b)(ii) and 192.933(d)(l)(ii).
29. Potential Impact Radius Calculation Updates: If the pipeline
operating pressures and gas quality are determined to be outside the
parameters of the C-FER Study, a new study with the uprated parameters
must be incorporated into the IMP.
If at anytime PHMSA determines the effect of the waiver is
inconsistent with pipeline safety, PHMSA will revoke the waiver at its
sole discretion.
Authority: 49 U.S.C. 60118 (c) and 49 CFR 1.53.
Issued in Washington, DC, on July 5, 2006.
Theodore L. Willke,
Deputy Associate Administrator for Pipeline Safety.
[FR Doc. 06-6107 Filed 7-6-06; 9:10 am]
BILLING CODE 4910-60-P