Specifically, Equitrans proposes to
construct and operate 69.9 miles of new
20-inch diameter pipeline and related
facilities (the Big Sandy Pipeline
Project) that will provide a direct
connection between the Big Sandy
Compression Station in Langley,
Kentucky, and a proposed new
interconnection with Tennessee Gas
Pipeline Company’s Broad Run Lateral
in Carter County, Kentucky. Equitrans
also proposes to install three (3) 3,000
horsepower (hp) electrically-driven
compressor units at the outlet of the
existing Kentucky Hydrocarbon
Compressor Station in Langley. In
addition, Equitrans proposes to install a
meter station and launcher, pressure
regulation facilities and a receiver at the
terminus of the pipeline. Equitrans
estimates that the proposed facilities
will cost $150,371,210.
Any questions about this application
should be directed to David K. Dewey,
Vice President & General Counsel,
Equitrans, L.P., 225 North Shore Drive,
Pittsburgh, PA 15212, at 412–395–2566
or fax 412–395–3311.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
listed below, file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of this filing and all
subsequent filings made with the
Commission and must mail a copy of all
filings to the applicant and to every
other party in the proceeding. Only
parties to the proceeding can ask for
court review of Commission orders in
the proceeding.
However, other persons do not have
to intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
VerDate Aug<31>2005
17:08 May 23, 2006
Jkt 208001
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to this project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons may also wish to comment
further only on the environmental
review of this project. Environmental
commenters will be placed on the
Commission’s environmental mailing
list, will receive copies of
environmental documents issued by the
Commission, and will be notified of
meetings associated with the
Commission’s environmental review
process. Those persons, organizations,
and agencies who submitted comments
during the NEPA Pre-Filing Process in
Docket No. PF06–12–000 are already on
the Commission staff’s environmental
mailing list for the proceeding in the
above dockets and may file additional
comments on or before the below listed
comment date. Environmental
commenters will not be required to
serve copies of filed documents on all
other parties. However, environmental
commenters are also not parties to the
proceeding and will not receive copies
of all documents filed by other parties
or non-environmental documents issued
by the Commission. Further, they will
not have the right to seek court review
of any final order by Commission in this
proceeding.
The Commission strongly encourages
electronic filings of comments, protests,
and interventions via the Internet in lieu
of paper. See 18 CFR 385.2001(a)(1)(iii)
and the instructions on the
Commission’s Web site (https://
www.ferc.gov) under the ‘‘e-Filing’’ link.
Comment Date: June 8, 2006.
Magalie R. Salas,
Secretary.
[FR Doc. E6–7957 Filed 5–23–06; 8:45 am]
BILLING CODE 6717–01–P
29931
support of its application filed on
February 7, 2006.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant and
all the parties in this proceeding.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on May 24, 2006.
Magalie R. Salas,
Secretary.
[FR Doc. E6–7883 Filed 5–23–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
Commission
[Docket No. EG06–36–000]
ExTex LaPorte Limited Partnership;
Notice of Application for Commission
Determination of Exempt Wholesale
Generator Status
May 16, 2006.
Take notice that on March 31, 2006,
ExTex LaPorte Limited Partnership
(ExTex LaPorte) tendered for filing
additional information and analysis in
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
[Docket Nos. ER06–745–000; ER06–745–
001]
MASSPOWER; Notice of Issuance of
Order
May 17, 2006.
MASSPOWER filed an application for
market-based rate authority, with an
accompanying tariff. The proposed
market-based rate tariff provides for the
sale of energy, capacity and ancillary
E:\FR\FM\24MYN1.SGM
24MYN1
jlentini on PROD1PC65 with NOTICES
29932
Federal Register / Vol. 71, No. 100 / Wednesday, May 24, 2006 / Notices
services at market-based rates.
MASSPOWER also requested waiver of
various Commission regulations. In
particular, MASSPOWER requested that
the Commission grant blanket approval
under 18 CFR part 34 of all future
issuances of securities and assumptions
of liability by MASSPOWER.
On May 12, 2006, pursuant to
delegated authority, the Director,
Division of Tariffs and Market
Development—West, granted the
request for blanket approval under part
34. The Director’s order also stated that
the Commission would publish a
separate notice in the Federal Register
establishing a period of time for the
filing of protests. Accordingly, any
person desiring to be heard or to protest
the blanket approval of issuances of
securities or assumptions of liability by
MASSPOWER should file a motion to
intervene or protest with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure. 18 CFR 385.211, 385.214
(2004).
Notice is hereby given that the
deadline for filing motions to intervene
or protest is June 12, 2006.
Absent a request to be heard in
opposition by the deadline above,
MASSPOWER is authorized to issue
securities and assume obligations or
liabilities as a guarantor, indorser,
surety, or otherwise in respect of any
security of another person; provided
that such issuance or assumption is for
some lawful object within the corporate
purposes of MASSPOWER, compatible
with the public interest, and is
reasonably necessary or appropriate for
such purposes.
The Commission reserves the right to
require a further showing that neither
public nor private interests will be
adversely affected by continued
approval of MASSPOWER’s issuances of
securities or assumptions of liability.
Copies of the full text of the Director’s
Order are available from the
Commission’s Public Reference Room,
888 First Street, NE., Washington, DC
20426. The Order may also be viewed
on the Commission’s Web site at https://
www.ferc.gov, using the eLibrary link.
Enter the docket number excluding the
last three digits in the docket number
filed to access the document.
Comments, protests, and interventions
may be filed electronically via the
VerDate Aug<31>2005
17:08 May 23, 2006
Jkt 208001
Internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. The Commission
strongly encourages electronic filings.
Magalie R. Salas,
Secretary.
[FR Doc. E6–7894 Filed 5–23–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP06–276–000]
Mississippi Hub, LLC; Notice of
Petition
May 16, 2006.
Take notice that on May 11, 2006
Mississippi Hub, LLC (MS Hub), 2707
N. Kensington St. Arlington, VA 22207,
filed a petition for Exemption of
Temporary Acts and Operations from
Certificate Requirements, pursuant to
Rule 207(a)(5) of the Commission’s
Rules of Practice and Procedure (18 CFR
385.207(a)(5)), and section 7(c)(1)(B) of
the Natural Gas Act (15 U.S.C.
717(c)(1)(B)), seeking approval of an
exemption from certificate requirements
to perform temporary activities related
to drilling a test well and performing
other activities to assess the feasibility
of developing an underground natural
gas storage facility in Simpson County,
Mississippi, all as more fully set forth in
the application which is on file with the
Commission and open to public
inspection. The filing may also be
viewed on the Web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@gerc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Any questions regarding the petition
should be directed to J. Gordon
Pennington, Attorney at Law,
Mississippi Hub, LLC (‘‘MS Hub’’), 2707
N. Kensington St. Arlington, VA 22207,
Phone: 03–533–7638 or e-mail
Pennington5@verizon.net.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
should, on or before the comment date,
file with the Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426, a motion to
intervene in accordance with the
requirements of the Commission’s Rules
of Practice and Procedure (18 CFR
385.214 or 385.211) and the Regulations
under the NGA (18 CFR 157.10). A
person obtaining party status will be
placed on the service list maintained by
the Secretary of the Commission and
will receive copies of all documents
filed by the applicant and by all other
parties. A party must submit 14 copies
of filings made with the Commission
and must mail a copy to the applicant
and to every other party in the
proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
Persons who wish to comment only
on the environmental review of this
project, or in support of or in opposition
to this project, should submit an
original and two copies of their
comments to the Secretary of the
Commission. Environmental
commenters will be placed on the
Commission’s environmental mailing
list, will receive copies of the
environmental documents, and will be
notified of meetings associated with the
Commission’s environmental review
process. Environmental commenters
will not be required to serve copies of
filed documents on all other parties.
The Commission’s rules require that
persons filing comments in opposition
to the project provide copies of their
protests only to the applicant. However,
the non-party commenters will not
receive copies of all documents filed by
other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests,
and interventions via the Internet in lieu
of paper. See 18 CFR 385.2001(a)(1)(iii)
and the instructions on the
Commission’s Web site (https://
www.ferc.gov) under the ‘‘e-Filing’’ link.
Comment Date: May 26, 2006.
Magalie R. Salas,
Secretary.
[FR Doc. E6–7882 Filed 5–23–06; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\24MYN1.SGM
24MYN1
Agencies
[Federal Register Volume 71, Number 100 (Wednesday, May 24, 2006)]
[Notices]
[Pages 29931-29932]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-7894]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. ER06-745-000; ER06-745-001]
MASSPOWER; Notice of Issuance of Order
May 17, 2006.
MASSPOWER filed an application for market-based rate authority,
with an accompanying tariff. The proposed market-based rate tariff
provides for the sale of energy, capacity and ancillary
[[Page 29932]]
services at market-based rates. MASSPOWER also requested waiver of
various Commission regulations. In particular, MASSPOWER requested that
the Commission grant blanket approval under 18 CFR part 34 of all
future issuances of securities and assumptions of liability by
MASSPOWER.
On May 12, 2006, pursuant to delegated authority, the Director,
Division of Tariffs and Market Development--West, granted the request
for blanket approval under part 34. The Director's order also stated
that the Commission would publish a separate notice in the Federal
Register establishing a period of time for the filing of protests.
Accordingly, any person desiring to be heard or to protest the blanket
approval of issuances of securities or assumptions of liability by
MASSPOWER should file a motion to intervene or protest with the Federal
Energy Regulatory Commission, 888 First Street, NE., Washington, DC
20426, in accordance with Rules 211 and 214 of the Commission's Rules
of Practice and Procedure. 18 CFR 385.211, 385.214 (2004).
Notice is hereby given that the deadline for filing motions to
intervene or protest is June 12, 2006.
Absent a request to be heard in opposition by the deadline above,
MASSPOWER is authorized to issue securities and assume obligations or
liabilities as a guarantor, indorser, surety, or otherwise in respect
of any security of another person; provided that such issuance or
assumption is for some lawful object within the corporate purposes of
MASSPOWER, compatible with the public interest, and is reasonably
necessary or appropriate for such purposes.
The Commission reserves the right to require a further showing that
neither public nor private interests will be adversely affected by
continued approval of MASSPOWER's issuances of securities or
assumptions of liability.
Copies of the full text of the Director's Order are available from
the Commission's Public Reference Room, 888 First Street, NE.,
Washington, DC 20426. The Order may also be viewed on the Commission's
Web site at https://www.ferc.gov, using the eLibrary link. Enter the
docket number excluding the last three digits in the docket number
filed to access the document. Comments, protests, and interventions may
be filed electronically via the Internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
under the ``e-Filing'' link. The Commission strongly encourages
electronic filings.
Magalie R. Salas,
Secretary.
[FR Doc. E6-7894 Filed 5-23-06; 8:45 am]