PacifiCorp; Notice of Authorization for Continued Project Operation, 27494 [E6-7167]
Download as PDF
27494
Federal Register / Vol. 71, No. 91 / Thursday, May 11, 2006 / Notices
link also provides access to the texts of
the formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service call eSubscription,
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries, and direct links
to the documents. Go to https://
www.ferc.gov/esubscribenow.htm.
Magalie R. Salas,
Secretary.
[FR Doc. E6–7192 Filed 5–10–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2111]
PacifiCorp; Notice of Authorization for
Continued Project Operation
cchase on PROD1PC60 with NOTICES
May 4, 2006.
On April 28, 2004, PacifiCorp,
licensee for the Swift No. 1
Hydroelectric Project, filed an
application for a new or subsequent
license pursuant to the Federal Power
Act (FPA) and the Commission’s
regulations thereunder. The Swift No. 1
Project is located on the Lewis River in
Skamania County, Washington.
The license for Project No. 2111 was
issued for a period ending April 30,
2006. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
VerDate Aug<31>2005
16:29 May 10, 2006
Jkt 208001
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2111
is issued to PacifiCorp for a period
effective May 1, 2006 through April 30,
2007, or until the issuance of a new
license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before April 30, 2007, notice
is hereby given that, pursuant to 18 CFR
16.18(c), an annual license under
section 15(a)(1) of the FPA is renewed
automatically without further order or
notice by the Commission, unless the
Commission orders otherwise. If the
project is not subject to section 15 of the
FPA, notice is hereby given that
PacifiCorp, is authorized to continue
operation of the Swift No. 1 Project until
such time as the Commission acts on its
application for a subsequent license.
Magalie R. Salas,
Secretary.
[FR Doc. E6–7167 Filed 5–10–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 935]
PacifiCorp; Notice of Authorization for
Continued Project Operation
May 4, 2006.
On April 28, 2004, PacifiCorp,
licensee for the Merwin Hydroelectric
Project, filed an application for a new or
subsequent license pursuant to the
Federal Power Act (FPA) and the
Commission’s regulations thereunder.
The Merwin Project is located on the
Lewis River in Clark and Cowlitz
County, Washington.
The license for Project No. 935 was
initially issued for a period ending
December 11, 2009. On April 8, 1999,
the Commission amended the license
and accelerated the Merwin project
expiration date to April 30, 2006.
Section 15(a)(1) of the FPA, 16 U.S.C.
808(a)(1), requires the Commission, at
the expiration of a license term, to issue
from year-to-year an annual license to
the then licensee under the terms and
conditions of the prior license until a
new license is issued, or the project is
otherwise disposed of as provided in
section 15 or any other applicable
section of the FPA. If the project’s prior
PO 00000
Frm 00046
Fmt 4703
Sfmt 4703
license waived the applicability of
section 15 of the FPA, then, based on
section 9(b) of the Administrative
Procedure Act, 5 U.S.C. 558(c), and as
set forth at 18 CFR 16.21(a), if the
licensee of such project has filed an
application for a subsequent license, the
licensee may continue to operate the
project in accordance with the terms
and conditions of the license after the
minor or minor part license expires,
until the Commission acts on its
application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 935 is
issued to PacifiCorp for a period
effective May 1, 2006 through April 30,
2007, or until the issuance of a new
license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before April 30, 2007, notice
is hereby given that, pursuant to 18 CFR
16.18(c), an annual license under
section 15(a)(1) of the FPA is renewed
automatically without further order or
notice by the Commission, unless the
Commission orders otherwise. If the
project is not subject to section 15 of the
FPA, notice is hereby given that
PacifiCorp, is authorized to continue
operation of the Merwin Project until
such time as the Commission acts on its
application for a subsequent license.
Magalie R. Salas,
Secretary.
[FR Doc. E6–7169 Filed 5–10–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Accepted for
Filing and Soliciting Comments,
Protests, and Motions To Intervene
May 3, 2006.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
Permit.
b. Project No.: 12660–000.
c. Date Filed: March 13, 2006.
d. Applicant: TDX Power, Inc.
E:\FR\FM\11MYN1.SGM
11MYN1
Agencies
[Federal Register Volume 71, Number 91 (Thursday, May 11, 2006)]
[Notices]
[Page 27494]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-7167]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2111]
PacifiCorp; Notice of Authorization for Continued Project
Operation
May 4, 2006.
On April 28, 2004, PacifiCorp, licensee for the Swift No. 1
Hydroelectric Project, filed an application for a new or subsequent
license pursuant to the Federal Power Act (FPA) and the Commission's
regulations thereunder. The Swift No. 1 Project is located on the Lewis
River in Skamania County, Washington.
The license for Project No. 2111 was issued for a period ending
April 30, 2006. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1),
requires the Commission, at the expiration of a license term, to issue
from year-to-year an annual license to the then licensee under the
terms and conditions of the prior license until a new license is
issued, or the project is otherwise disposed of as provided in section
15 or any other applicable section of the FPA. If the project's prior
license waived the applicability of section 15 of the FPA, then, based
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c),
and as set forth at 18 CFR 16.21(a), if the licensee of such project
has filed an application for a subsequent license, the licensee may
continue to operate the project in accordance with the terms and
conditions of the license after the minor or minor part license
expires, until the Commission acts on its application. If the licensee
of such a project has not filed an application for a subsequent
license, then it may be required, pursuant to 18 CFR 16.21(b), to
continue project operations until the Commission issues someone else a
license for the project or otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 2111 is issued to
PacifiCorp for a period effective May 1, 2006 through April 30, 2007,
or until the issuance of a new license for the project or other
disposition under the FPA, whichever comes first. If issuance of a new
license (or other disposition) does not take place on or before April
30, 2007, notice is hereby given that, pursuant to 18 CFR 16.18(c), an
annual license under section 15(a)(1) of the FPA is renewed
automatically without further order or notice by the Commission, unless
the Commission orders otherwise. If the project is not subject to
section 15 of the FPA, notice is hereby given that PacifiCorp, is
authorized to continue operation of the Swift No. 1 Project until such
time as the Commission acts on its application for a subsequent
license.
Magalie R. Salas,
Secretary.
[FR Doc. E6-7167 Filed 5-10-06; 8:45 am]