Federal Register / Vol. 71, No. 78 / Monday, April 24, 2006 / Notices
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
q. Comments, protests and
interventions may be filed electronically
via the Internet in lieu of paper. See, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site at https://www.ferc.gov under the ‘‘eFiling’’ link.
Magalie R. Salas,
Secretary.
[FR Doc. E6–6047 Filed 4–21–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Accepted for
Filing and Soliciting Motions To
Intervene, Protests, and Comments
rmajette on PROD1PC67 with NOTICES
April 17, 2006.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
Permit.
b. Project No.: 12656–000.
c. Date filed: February 22, 2006.
d. Applicant: Samaria Water and
Irrigation Company.
e. Name of Project: Samaria
Hydroelectric Project.
f. Location: Dry Pine Canyon, Rose
Bud Canyon, Thomas Davis Canyon
Tributary to Samaria Creek in Oneida
County, Idaho.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. David Reel,
Samaria Water and Irrigation Company,
5176 South 4400 West, Malad, ID 83252,
(208) 766–2828, drr@atcnet.net.
i. FERC Contact: Patricia W. Gillis at
(202) 502–8735.
j. Deadline for filing comments,
protests, and motions to intervene: 60
days from the issuance date of this
notice.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
VerDate Aug<31>2005
14:56 Apr 21, 2006
Jkt 208001
k. Description of Project: The
proposed project would consist of: (1)
Replacing the existing drop, divert the
flows from Dry Pine Canyon, Rose Bud
Canyon and Thomas Davis Canyon
through approximately 9,000 feet of 12inch diameter pipe, into a common 15
to 18 inch diameter penstock
approximately 13,300 feet in length, (2)
one proposed generating unit with an
installed capacity of 350 kilowatts, (3)
proposed 0.1 mile tail race canal to
Samaria Creek, (4) proposed 1000 feet of
12.5 kV transmission lines, and (5)
appurtenant facilities. The proposed
project would have an average annual
generation of 1,200,000 kilowatt-hours,
which would be sold to a local utility.
l. Locations of Applications: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street, NE.,
Room 2A, Washington DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Competing Preliminary Permit:
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30(b) and 4.36.
o. Competing Development
Application: Any qualified development
applicant desiring to file a competing
development application must submit to
the Commission, on or before a
specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
21011
application allows an interested person
to file the competing application no
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30(b) and 4.36.
p. Notice of Intent: A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
q. Proposed Scope of Studies Under
Permit: A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper; See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under ‘‘efiling’’ link. The Commission strongly
encourages electronic filing.
s. Filing and Service of Responsive
Documents: Any filings must bear in all
capital letters the title ‘‘COMMENTS’’,
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’, ‘‘PROTEST’’,
‘‘COMPETING APPLICATION’’, or
‘‘MOTION TO INTERVENE’’, as
applicable, and the Project Number of
the particular application to which the
filing refers. Any of the above-named
documents must be filed by providing
the original and the number of copies
E:\FR\FM\24APN1.SGM
24APN1
21012
Federal Register / Vol. 71, No. 78 / Monday, April 24, 2006 / Notices
provided by the Commission’s
regulations to: The Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
A copy of any motion to intervene must
also be served upon each representative
of the Applicant specified in the
particular application.
t. Agency Comments: Federal, state,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E6–6049 Filed 4–21–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Accepted for
Filing and Soliciting Motions To
Intervene, Protests, and Comments
rmajette on PROD1PC67 with NOTICES
April 17, 2006.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
Permit.
b. Project No.: 12662–000.
c. Date filed: March 21, 2006.
d. Applicant: Renewable Resources,
Inc.
e. Name of Project: Swift River Mill
Project.
f. Location: The project would be
located on the Pawcatuck River, in
Washington County, Rhode Island. The
project would not occupy Federal or
Tribal lands. The existing dam is owned
by the applicant.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. John R.
Lavigne, Renewable Resources, Inc., c/o
The H.L. Turner Group, Inc., 27 Locke
Road, Concord, NH 03301–5417, (603)
228–1122.
i. FERC Contact: Robert Bell, (202)
502–6062.
j. Deadline for filing comments,
protests, and motions to intervene: 60
days from the issuance date of this
notice.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
VerDate Aug<31>2005
14:56 Apr 21, 2006
Jkt 208001
to serve a copy of that document on
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. Description of Project: The
proposed project would consist of: (1)
The existing 112-foot-long, 10-foot-high
concrete gravity dam, (2) an existing
impoundment having a surface area of
36 acres, with a storage capacity 204
acre-feet and normal water surface
elevation of 9,800 feet national
geographic vertical datum, (3) two
existing 10-foot-wide, 40-foot-long
concrete flumes, which join to form a
16.5-foot wide, 100-foot-long concrete
flume, (4) an existing powerhouse
containing two new generating units
having a total installed capacity of 339
kilowatts, (5) an existing granite tailrace,
(6) a proposed underground
transmission line 300 feet long, and (7)
appurtenant facilities. The project
would have an annual generation of
2.97 gigawatt hours, which would be
sold to a local utility.
l. Locations of Applications: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street, NE.,
Room 2A, Washington DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h.
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Competing Preliminary Permit:
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
PO 00000
Frm 00044
Fmt 4703
Sfmt 4703
preliminary permit application must
conform with 18 CFR 4.30(b) and 4.36.
o. Competing Development
Application: Any qualified development
applicant desiring to file a competing
development application must submit to
the Commission, on or before a
specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30(b) and 4.36.
p. Notice of Intent: A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
q. Proposed Scope of Studies under
Permit: A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s web site under ‘‘e-
E:\FR\FM\24APN1.SGM
24APN1
Agencies
[Federal Register Volume 71, Number 78 (Monday, April 24, 2006)]
[Notices]
[Pages 21011-21012]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-6049]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Application Accepted for Filing and Soliciting Motions
To Intervene, Protests, and Comments
April 17, 2006.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary Permit.
b. Project No.: 12656-000.
c. Date filed: February 22, 2006.
d. Applicant: Samaria Water and Irrigation Company.
e. Name of Project: Samaria Hydroelectric Project.
f. Location: Dry Pine Canyon, Rose Bud Canyon, Thomas Davis Canyon
Tributary to Samaria Creek in Oneida County, Idaho.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. David Reel, Samaria Water and Irrigation
Company, 5176 South 4400 West, Malad, ID 83252, (208) 766-2828,
drr@atcnet.net.
i. FERC Contact: Patricia W. Gillis at (202) 502-8735.
j. Deadline for filing comments, protests, and motions to
intervene: 60 days from the issuance date of this notice.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person in the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
k. Description of Project: The proposed project would consist of:
(1) Replacing the existing drop, divert the flows from Dry Pine Canyon,
Rose Bud Canyon and Thomas Davis Canyon through approximately 9,000
feet of 12-inch diameter pipe, into a common 15 to 18 inch diameter
penstock approximately 13,300 feet in length, (2) one proposed
generating unit with an installed capacity of 350 kilowatts, (3)
proposed 0.1 mile tail race canal to Samaria Creek, (4) proposed 1000
feet of 12.5 kV transmission lines, and (5) appurtenant facilities. The
proposed project would have an average annual generation of 1,200,000
kilowatt-hours, which would be sold to a local utility.
l. Locations of Applications: A copy of the application is
available for inspection and reproduction at the Commission in the
Public Reference Room, located at 888 First Street, NE., Room 2A,
Washington DC 20426, or by calling (202) 502-8371. This filing may also
be viewed on the Commission's Web site at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, call toll-free 1-866-208-3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item h
above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Competing Preliminary Permit: Anyone desiring to file a
competing application for preliminary permit for a proposed project
must submit the competing application itself, or a notice of intent to
file such an application, to the Commission on or before the specified
comment date for the particular application (see 18 CFR 4.36).
Submission of a timely notice of intent allows an interested person to
file the competing preliminary permit application no later than 30 days
after the specified comment date for the particular application. A
competing preliminary permit application must conform with 18 CFR
4.30(b) and 4.36.
o. Competing Development Application: Any qualified development
applicant desiring to file a competing development application must
submit to the Commission, on or before a specified comment date for the
particular application, either a competing development application or a
notice of intent to file such an application. Submission of a timely
notice of intent to file a development application allows an interested
person to file the competing application no later than 120 days after
the specified comment date for the particular application. A competing
license application must conform with 18 CFR 4.30(b) and 4.36.
p. Notice of Intent: A notice of intent must specify the exact
name, business address, and telephone number of the prospective
applicant, and must include an unequivocal statement of intent to
submit, if such an application may be filed, either a preliminary
permit application or a development application (specify which type of
application). A notice of intent must be served on the applicant(s)
named in this public notice.
q. Proposed Scope of Studies Under Permit: A preliminary permit, if
issued, does not authorize construction. The term of the proposed
preliminary permit would be 36 months. The work proposed under the
preliminary permit would include economic analysis, preparation of
preliminary engineering plans, and a study of environmental impacts.
Based on the results of these studies, the Applicant would decide
whether to proceed with the preparation of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
Comments, protests and interventions may be filed electronically
via the Internet in lieu of paper; See 18 CFR 385.2001(a)(1)(iii) and
the instructions on the Commission's Web site under ``e-filing'' link.
The Commission strongly encourages electronic filing.
s. Filing and Service of Responsive Documents: Any filings must
bear in all capital letters the title ``COMMENTS'', ``RECOMMENDATIONS
FOR TERMS AND CONDITIONS'', ``PROTEST'', ``COMPETING APPLICATION'', or
``MOTION TO INTERVENE'', as applicable, and the Project Number of the
particular application to which the filing refers. Any of the above-
named documents must be filed by providing the original and the number
of copies
[[Page 21012]]
provided by the Commission's regulations to: The Secretary, Federal
Energy Regulatory Commission, 888 First Street, NE., Washington, DC
20426. A copy of any motion to intervene must also be served upon each
representative of the Applicant specified in the particular
application.
t. Agency Comments: Federal, state, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the Applicant. If
an agency does not file comments within the time specified for filing
comments, it will be presumed to have no comments. One copy of an
agency's comments must also be sent to the Applicant's representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E6-6049 Filed 4-21-06; 8:45 am]