Southern Natural Gas Company; Florida Gas Transmission Company; Notice of Availability of the Final Environmental Impact Statement for the Proposed Cypress Pipeline Project and Phase VII Expansion Project, 19495-19496 [E6-5561]
Download as PDF
Federal Register / Vol. 71, No. 72 / Friday, April 14, 2006 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP05–388–000; CP06–1–000]
Southern Natural Gas Company;
Florida Gas Transmission Company;
Notice of Availability of the Final
Environmental Impact Statement for
the Proposed Cypress Pipeline Project
and Phase VII Expansion Project
April 7, 2006.
wwhite on PROD1PC65 with NOTICES
The staff of the Federal Energy
Regulatory Commission (Commission or
FERC) has prepared a final
environmental impact statement (EIS)
on the natural gas pipeline facilities
proposed by Southern Natural Gas
Company (Southern) and Florida Gas
Transmission Company (FGT) in the
above-referenced dockets. Southern’s
Cypress Pipeline Project would be
located in various counties in southern
Georgia and northern Florida. FGT’s
Phase VII Expansion Project (FGT
Expansion Project) would be located in
various counties in northern and central
Florida.
The final EIS was prepared to satisfy
the requirements of the National
Environmental Policy Act (NEPA). The
FERC staff concludes that the proposed
projects, with the appropriate mitigation
measures as recommended, would have
limited adverse environmental impact.
The U.S. Army Corps of Engineers
(COE) has participated as a cooperating
agency in the preparation of the EIS
because the projects would require
permits pursuant to section 404 of the
Clean Water Act (33 United States Code
(U.S.C.) 1344) and section 10 of the
Rivers and Harbors Act (33 U.S.C. 403).
The COE would adopt the EIS per Title
40 Code of Federal Regulations Part
1506.3 if, after an independent review of
the document, it concludes that its
comments and suggestions have been
satisfied.
The final EIS addresses the potential
environmental effects of the
construction and operation of the
following facilities:
Cypress Pipeline Project
• About 166.9 miles of new 24-inchdiameter mainline pipeline (mainline)
in Effingham, Chatham, Bryan, Liberty,
Long, McIntosh, Glynn, Camden, and
Charlton Counties, Georgia, and Nassau,
Duval, and Clay Counties, Florida;
• About 9.8 miles of new 30-inchdiameter pipeline loop (loop) 1 in
1 A loop is a segment of pipeline that is usually
installed adjacent to an existing pipeline and
connected to it at both ends. The loop allows more
gas to be moved through the system.
VerDate Aug<31>2005
16:37 Apr 13, 2006
Jkt 208001
Chatham and Effingham Counties,
Georgia;
• About 0.1 mile of 12-inch-diameter
lateral pipeline in Duval County,
Florida;
• Three new 10,350 horsepower (hp)
gas-turbine-driven compressor stations
in Liberty and Glynn Counties, Georgia,
and in Nassau County, Florida;
• Four new meter stations in Glynn
County, Georgia, and in Nassau, Duval,
and Clay Counties, Florida;
• Modifications at two existing meter
stations in Chatham and Cobb Counties,
Georgia, and expansion of one meter
station in Effingham County, Georgia;
• 16 new block valves including 14
associated with the new mainline and
two associated with the new loop; and
• Four new pig 2 launcher/receiver
facilities, including two in Effingham
County, Georgia, one in Glynn County,
Georgia, and one in Clay County,
Florida, each collocated with new or
existing meter stations or new
compressor station sites.
Southern proposes to construct its
pipeline facilities in three phases.
Construction of Phase I would begin in
October 2006 and be in service by May
2007. Construction of Phase II would
begin in fall 2008 and be in service by
May 2009. Construction of Phase III
would begin in fall 2009 and be in
service by May 2010.
FGT Phase VII Expansion Project
• About 32.6 miles of new 36-inchdiameter pipeline in three separate
loops in Gilchrist, Levy, and Hernando
Counties, Florida;
• Replacement and upgrades to
existing compressors for a net increase
of about 7,800 hp at FGT’s Compressor
Station no. 26 in Citrus County, Florida;
• Replacement of an existing
compressor to add about 2,000 hp at
FGT’s existing Compressor Station no.
24 in Gilchrist County, Florida;
• Miscellaneous modifications and
upgrades to existing compressors with
no increases in hp at FGT’s Compressor
Station nos. 16, 17, and in Bradford,
Marion, and Hillsborough Counties,
Florida, respectively;
• A new interconnection with
Southern’s new mainline in Clay
County, Florida;
• Modifications to five existing
metering and/or regulation stations in
Clay, Polk, Bradford, and Duval
Counties, Florida; and
• New remote blowdown piping
associated with the new pipeline loops
at two locations in Levy County and two
locations in Hernando County, Florida.
2 A pig is an internal tool that can be used to
clean and dry a pipeline and/or to inspect it for
damage or corrosion.
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
19495
FGT proposes to construct its pipeline
facilities in two phases. Construction of
Phase I would begin in October 2006
and be in service by May 2007. Phase
II is planned to begin in October 2008
and be in service by May 2009.
The final EIS has been placed in the
public files of the FERC and the COE
and is available for public inspection at:
Federal Energy Regulatory
Commission, Public Reference Room,
888 First Street, NE., Room 2A,
Washington, DC 20426. 202–502–8371.
U.S. Army Corps of Engineers,
Jacksonville District, 701 San Marco
Boulevard, Jacksonville, Florida 32207.
904–232–1472.
A limited number of copies are
available from the FERC’s Public
Reference Room identified above. In
addition, copies of the final EIS have
been mailed to Federal, state, and local
government agencies; elected officials;
Native American tribes; local libraries
and newspapers; intervenors in the
FERC’s proceeding; individuals who
provided scoping comments; and
affected landowners and individuals.
In accordance with the Council on
Environmental Quality’s (CEQ)
regulations implementing the NEPA, no
agency decision on a proposed action
may be made until 30 days after the U.S.
Environmental Protection Agency
publishes a notice of availability of a
final EIS. However, the CEQ regulations
provide an exception to this rule when
an agency decision is subject to a formal
internal appeal process which allows
other agencies or the public to make
their views known. In such cases, the
agency decision may be made at the
same time the notice of the final EIS is
published, allowing both periods to run
concurrently. The Commission’s
decisions for these proposed actions are
subject to a 30-day rehearing period.
Additional information about the
projects is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC (3372) or on the
FERC Internet Web site (https://
www.ferc.gov). Using the ‘‘eLibrary’’
link, select ‘‘General Search’’ from the
eLibrary menu, enter the selected date
range and ‘‘Docket Number,’’ excluding
the last three digits in the Docket
Number field (i.e., CP05–388 and/or
CP06–1), and follow the instructions.
You may also search using the phrase
‘‘Cypress Pipeline Project’’ or ‘‘FGT
Phase VII Expansion Project’’ in the
‘‘Text Search’’ field. For assistance with
access to eLibrary, the helpline can be
reached at 1–866–208–3676, TTY (202)
502–8659, or at
FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC Internet Web
site also provides access to the texts of
E:\FR\FM\14APN1.SGM
14APN1
19496
Federal Register / Vol. 71, No. 72 / Friday, April 14, 2006 / Notices
formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
that allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries, and direct links
to the documents. To register for this
service, go to https://www.ferc.gov/
esubscribenow.htm.
Information concerning the
involvement of the COE is available
from Jon Soderberg at 202–761–7763.
Wednesday, April 26, 2006, 7 p.m.
Holiday Inn Hotel & Suites, 838
Westwood Blvd., Price, UT 84501. (435)
637–8880.
This notice is being sent to affected
landowners; Federal, State, and local
government representatives and
agencies; environmental and public
interest groups; Native American tribes;
other interested parties in this
proceeding; and local libraries and
newspapers. We encourage government
representatives to notify their
constituents of this planned project and
encourage them to comment on their
areas of concern.
Magalie R. Salas,
Secretary.
[FR Doc. E6–5561 Filed 4–13–06; 8:45 am]
Questar proposes to increase the
capacity of its southern transmission
system by approximately 170,000
dekatherms per day. More specifically,
Questar seeks authority to:
• Construct approximately 53 miles
of 24-inch-diameter pipeline and
ancillary facilities to loop Questar’s
existing Main Line (ML) No. 40 by
extending its ML 104 from its
easternmost terminus at Soldier Creek
in Carbon County to the Green River
Block Valve in Uintah County;
• Construct approximately 5 miles of
24-inch-diameter pipeline to loop its
ML 104 between its existing Oak
Springs Compressor Station (Oak
Springs) and Fausett Junction in Carbon
County; and
• Restage/reconfigure Oak Springs
and Questar’s existing Blind Canyon
Compressor Station (Blind Canyon) and
modify other existing facilities,
including yard and station piping,
cooling equipment, valves and
launcher/receiver facilities at Oak
Spring, Blind Canyon, and Questar’s
Thistle Creek Compressor Station in
Utah County.
• Seek the modification of metering
and gas separation facilities by Kern
River Gas Transmission Company (Kern
River) at its interconnect with the ML
104 Pipeline near Goshen, Utah, which
serves as a receipt point for volumes
delivered by Questar to Kern River at
this location.
Location maps depicting Questar’s
proposed facilities and alternate routes
are provided in Appendix 1.2
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. PF06–18–000]
Questar Pipeline Company; Notice of
Intent To Prepare an Environmental
Assessment for the Proposed
Southern System Expansion Project II,
Request for Comments on
Environmental Issues and Notice of
Scoping Meeting
wwhite on PROD1PC65 with NOTICES
April 7, 2006.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
Questar Pipeline Company’s (Questar)
planned Southern System Expansion
Project II located in Utah, Carbon,
Duchesne, and Uintah Counties, Utah.
This notice announces the opening of
the scoping process we 1 will use to
gather input from the public and
interested agencies on the project. Your
input will help the Commission staff
determine which issues need to be
evaluated in the EA. Please note that the
scoping period will close on May 12,
2006.
Comments may be submitted in
written form or presented verbally at the
public meeting detailed below. Further
details on how to submit written
comments are provided in the public
participation section of this notice. In
lieu of sending written comments, you
are invited to attend the public scoping
meeting that is scheduled as follows:
1 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Office of Energy Projects.
VerDate Aug<31>2005
16:37 Apr 13, 2006
Jkt 208001
Summary of the Proposed Project
2 The appendices referenced in this notice are not
being printed in the Federal Register. Copies are
available on the Commission’s Web site (excluding
maps) at the ‘‘eLibrary’’ link or from the
Commission’s Public Reference Room or call (202)
502–8371. For instructions on connecting to
eLibrary refer to the end of this notice. Copies of
the appendices were sent to all those receiving this
notice in the mail.
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
Currently Identified Environmental
Issues
At this time no formal application has
been filed with the FERC. For this
project, the FERC staff has initiated its
NEPA review prior to receiving the
application. The purpose of our NEPA
Pre-Filing Process is to involve
interested stakeholders early in project
planning and to identify and resolve
issues before an application is filed with
the FERC.
We have already identified several
issues that we think deserve attention
based on a preliminary review of the
proposed facilities, environmental
information provided by Questar,
discussions with staff of the Bureau of
Land Management, and comments
gathered from concerned citizens at
Questar’s open house held on March 28,
2006. This preliminary list of issues
may be changed based on your
comments and our analysis.
• Potential effect on perennial
streams and intermittent streams
crossed by or close to the route;
• Potential effect on vegetation and
wildlife resources, including critical big
game ranges and sage grouse habitat;
• Potential effect on endangered and
threatened species;
• Potential effect on historic and
prehistoric sites;
• Potential effect on recreation and
public interest areas, including traffic
impacts along the Nine Mile Canyon
Scenic Backcountry Byway;
• Potential visual effect of the
pipeline corridor;
The EA Process
The FERC will use the EA to consider
the environmental impact that could
result if it issues Questar a Certificate of
Public Convenience and Necessity.
This notice formally announces our
preparation of the EA and the beginning
of the process referred to as ‘‘scoping.’’
We are soliciting input from the public
and interested agencies to help us focus
the analysis in the EA on the potentially
significant environmental issues related
to the proposed action.
Our independent analysis of the
issues will be included in an EA that
will be prepared for the project. Our
evaluation will also include possible
alternatives to the proposed project or
portions of the project, and we will
make recommendations on how to
lessen or avoid impacts on the various
resource areas of concern.
The EA will be mailed to Federal,
State, and local government agencies;
elected officials; environmental and
public interest groups; Native American
tribes; affected landowners; other
E:\FR\FM\14APN1.SGM
14APN1
Agencies
[Federal Register Volume 71, Number 72 (Friday, April 14, 2006)]
[Notices]
[Pages 19495-19496]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-5561]
[[Page 19495]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP05-388-000; CP06-1-000]
Southern Natural Gas Company; Florida Gas Transmission Company;
Notice of Availability of the Final Environmental Impact Statement for
the Proposed Cypress Pipeline Project and Phase VII Expansion Project
April 7, 2006.
The staff of the Federal Energy Regulatory Commission (Commission
or FERC) has prepared a final environmental impact statement (EIS) on
the natural gas pipeline facilities proposed by Southern Natural Gas
Company (Southern) and Florida Gas Transmission Company (FGT) in the
above-referenced dockets. Southern's Cypress Pipeline Project would be
located in various counties in southern Georgia and northern Florida.
FGT's Phase VII Expansion Project (FGT Expansion Project) would be
located in various counties in northern and central Florida.
The final EIS was prepared to satisfy the requirements of the
National Environmental Policy Act (NEPA). The FERC staff concludes that
the proposed projects, with the appropriate mitigation measures as
recommended, would have limited adverse environmental impact.
The U.S. Army Corps of Engineers (COE) has participated as a
cooperating agency in the preparation of the EIS because the projects
would require permits pursuant to section 404 of the Clean Water Act
(33 United States Code (U.S.C.) 1344) and section 10 of the Rivers and
Harbors Act (33 U.S.C. 403). The COE would adopt the EIS per Title 40
Code of Federal Regulations Part 1506.3 if, after an independent review
of the document, it concludes that its comments and suggestions have
been satisfied.
The final EIS addresses the potential environmental effects of the
construction and operation of the following facilities:
Cypress Pipeline Project
About 166.9 miles of new 24-inch-diameter mainline
pipeline (mainline) in Effingham, Chatham, Bryan, Liberty, Long,
McIntosh, Glynn, Camden, and Charlton Counties, Georgia, and Nassau,
Duval, and Clay Counties, Florida;
About 9.8 miles of new 30-inch-diameter pipeline loop
(loop) \1\ in Chatham and Effingham Counties, Georgia;
---------------------------------------------------------------------------
\1\ A loop is a segment of pipeline that is usually installed
adjacent to an existing pipeline and connected to it at both ends.
The loop allows more gas to be moved through the system.
---------------------------------------------------------------------------
About 0.1 mile of 12-inch-diameter lateral pipeline in
Duval County, Florida;
Three new 10,350 horsepower (hp) gas-turbine-driven
compressor stations in Liberty and Glynn Counties, Georgia, and in
Nassau County, Florida;
Four new meter stations in Glynn County, Georgia, and in
Nassau, Duval, and Clay Counties, Florida;
Modifications at two existing meter stations in Chatham
and Cobb Counties, Georgia, and expansion of one meter station in
Effingham County, Georgia;
16 new block valves including 14 associated with the new
mainline and two associated with the new loop; and
Four new pig \2\ launcher/receiver facilities, including
two in Effingham County, Georgia, one in Glynn County, Georgia, and one
in Clay County, Florida, each collocated with new or existing meter
stations or new compressor station sites.
---------------------------------------------------------------------------
\2\ A pig is an internal tool that can be used to clean and dry
a pipeline and/or to inspect it for damage or corrosion.
---------------------------------------------------------------------------
Southern proposes to construct its pipeline facilities in three
phases. Construction of Phase I would begin in October 2006 and be in
service by May 2007. Construction of Phase II would begin in fall 2008
and be in service by May 2009. Construction of Phase III would begin in
fall 2009 and be in service by May 2010.
FGT Phase VII Expansion Project
About 32.6 miles of new 36-inch-diameter pipeline in three
separate loops in Gilchrist, Levy, and Hernando Counties, Florida;
Replacement and upgrades to existing compressors for a net
increase of about 7,800 hp at FGT's Compressor Station no. 26 in Citrus
County, Florida;
Replacement of an existing compressor to add about 2,000
hp at FGT's existing Compressor Station no. 24 in Gilchrist County,
Florida;
Miscellaneous modifications and upgrades to existing
compressors with no increases in hp at FGT's Compressor Station nos.
16, 17, and in Bradford, Marion, and Hillsborough Counties, Florida,
respectively;
A new interconnection with Southern's new mainline in Clay
County, Florida;
Modifications to five existing metering and/or regulation
stations in Clay, Polk, Bradford, and Duval Counties, Florida; and
New remote blowdown piping associated with the new
pipeline loops at two locations in Levy County and two locations in
Hernando County, Florida.
FGT proposes to construct its pipeline facilities in two phases.
Construction of Phase I would begin in October 2006 and be in service
by May 2007. Phase II is planned to begin in October 2008 and be in
service by May 2009.
The final EIS has been placed in the public files of the FERC and
the COE and is available for public inspection at:
Federal Energy Regulatory Commission, Public Reference Room, 888
First Street, NE., Room 2A, Washington, DC 20426. 202-502-8371.
U.S. Army Corps of Engineers, Jacksonville District, 701 San Marco
Boulevard, Jacksonville, Florida 32207. 904-232-1472.
A limited number of copies are available from the FERC's Public
Reference Room identified above. In addition, copies of the final EIS
have been mailed to Federal, state, and local government agencies;
elected officials; Native American tribes; local libraries and
newspapers; intervenors in the FERC's proceeding; individuals who
provided scoping comments; and affected landowners and individuals.
In accordance with the Council on Environmental Quality's (CEQ)
regulations implementing the NEPA, no agency decision on a proposed
action may be made until 30 days after the U.S. Environmental
Protection Agency publishes a notice of availability of a final EIS.
However, the CEQ regulations provide an exception to this rule when an
agency decision is subject to a formal internal appeal process which
allows other agencies or the public to make their views known. In such
cases, the agency decision may be made at the same time the notice of
the final EIS is published, allowing both periods to run concurrently.
The Commission's decisions for these proposed actions are subject to a
30-day rehearing period.
Additional information about the projects is available from the
Commission's Office of External Affairs, at 1-866-208-FERC (3372) or on
the FERC Internet Web site (https://www.ferc.gov). Using the
``eLibrary'' link, select ``General Search'' from the eLibrary menu,
enter the selected date range and ``Docket Number,'' excluding the last
three digits in the Docket Number field (i.e., CP05-388 and/or CP06-1),
and follow the instructions. You may also search using the phrase
``Cypress Pipeline Project'' or ``FGT Phase VII Expansion Project'' in
the ``Text Search'' field. For assistance with access to eLibrary, the
helpline can be reached at 1-866-208-3676, TTY (202) 502-8659, or at
FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC Internet Web
site also provides access to the texts of
[[Page 19496]]
formal documents issued by the Commission, such as orders, notices, and
rulemakings.
In addition, the Commission now offers a free service called
eSubscription that allows you to keep track of all formal issuances and
submittals in specific dockets. This can reduce the amount of time you
spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. To register for this service, go to https://www.ferc.gov/
esubscribenow.htm.
Information concerning the involvement of the COE is available from
Jon Soderberg at 202-761-7763.
Magalie R. Salas,
Secretary.
[FR Doc. E6-5561 Filed 4-13-06; 8:45 am]