p. With this notice, we are initiating
consultation with the Iowa State
Historic Preservation Officer (SHPO), as
required by section 106, National
Historic Preservation Act, and the
regulations of the Advisory Council on
Historic Preservation, 36 CFR 800.4.
q. Procedural schedule and final
amendments: The application will be
processed according to the following
Hydro Licensing Schedule. Revisions to
the schedule will be made as
appropriate. The Commission staff
proposes to issue one environmental
assessment rather than issue a draft and
final EA. Comments, terms and
conditions, recommendations,
prescriptions, and reply comments, if
any, will be addressed in an EA. Staff
intends to give at least 30 days for
entities to comment on the EA, and will
take into consideration all comments
received on the EA before final action is
taken on the license application.
Issue Acceptance or Deficiency Letter—
May 2006
Issue Scoping Document—June 2006
Notice of application is ready for
environmental analysis—August 2006
Notice of the availability of the EA—
February 2007
Ready for Commission’s decision on the
application—April 2007
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Magalie R. Salas,
Secretary.
[FR Doc. E6–5294 Filed 4–10–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Accepting for
Filing and Soliciting Motions To
Intervene, Protests and Comments
wwhite on PROD1PC61 with NOTICES
April 5, 2006.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
Permit.
b. Project No.: 12615–000.
c. Date filed: September 29, 2005.
d. Applicant: Alaska Power &
Telephone Company.
e. Name of Project: Soule River Water
Project.
VerDate Aug<31>2005
19:37 Apr 10, 2006
Jkt 208001
f. Location: On the Soule River,
within the Ketchikan Recording District,
First Judicial District, near Hyder, AK.
The project would be on federal land
within the Tongass National Forest.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Robert S.
Grimm, President, Alaska Power &
Telephone Company, P.O. Box 3222,
Port Townsend, WA 98368, (360) 385–
1733 x 120.
i. FERC Contact: Etta Foster, (202)
502–8769.
j. Deadline for filing comments,
protests, and motions to intervene: 60
days from the issuance date of this
notice.
All documents (original and eight
copies) should be filed with Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
Please include the project number (P–
12615–000) on any comments, protests,
or motions filed.
k. Description of Project: The
proposed project would consist of: (1) A
proposed concrete dam with a
maximum height of 150–200 feet; (2) a
proposed storage reservoir with a
normal water surface area of 917 acres,
a gross storage capacity of
approximately 74,000 acre-feet and an
active storage capacity of approximately
60,000 acre-feet; (3) a proposed 12-footdiameter, 12,100-foot-long tunnel; (4) a
proposed powerhouse containing 2
generating units with a total installed
capacity of 42 MW; (5) an open channel
tailrace; (6) a 35-kV submarine cable
approximately 9.72 miles long
connected to an interconnection with
the existing transmission system in
Hyder, and (7) appurtenant facilities.
The project would have an estimated
annual generation of approximately 155
giga-watt hours. The applicant plans to
sell the capacity and generated energy
either to BC Hydro, or an electric utility
in the United States after wheeling over
the BC Hydro transmission system.
l. Location of Application: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street, NE.,
Room 2A, Washington, DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
PO 00000
Frm 00054
Fmt 4703
Sfmt 4703
18321
reproduction at the address in item h.
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Competing Preliminary Permit:
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30(b) and 4.36.
o. Competing Development
Application: Any qualified development
applicant desiring to file a competing
development application must submit to
the Commission, on or before a
specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30(b) and 4.36.
p. Notice of Intent: A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
q. Proposed Scope of Studies under
Permit: A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to
Intervene: Anyone may submit
E:\FR\FM\11APN1.SGM
11APN1
18322
Federal Register / Vol. 71, No. 69 / Tuesday, April 11, 2006 / Notices
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper; See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s web site under ‘‘efiling’’ link. The Commission strongly
encourages electronic filing.
s. Filing and Service of Responsive
Documents: Any filings must bear in all
capital letter the title ‘‘COMMENTS’’,
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’, ‘‘PROTEST’’,
‘‘MOTION TO INTERVENE’’, ‘‘NOTICE
OF INTENT’’, or ‘‘COMPETING
APPLICATION’’, as applicable, and the
Project Number of the particular
application to which the filing refers.
Any of the above-named documents
must be filed by providing the original
and the number of copies provided by
the Commission’s regulations to: The
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426. A copy of any
motion to intervene must also be served
upon each representative of the
Applicant specified in the particular
application.
t. Agency Comments: Federal, state,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E6–5305 Filed 4–10–06; 8:45 am]
wwhite on PROD1PC61 with NOTICES
BILLING CODE 6717–01–P
VerDate Aug<31>2005
19:37 Apr 10, 2006
Jkt 208001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Accepting for
Filing and Soliciting Motions to
Intervene, Protests and Comments
April 5, 2006.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
Permit.
b. Project No.: 12633–000.
c. Date filed: December 21, 2005.
d. Applicant: SV Hydro LLC.
e. Name of Project: Saylorville
Hydroelectric Project.
f. Location: On the Des Moines River,
Polk County, Iowa, utilizing Federal
lands administrated by the U.S. Army
Corps of Engineers. The existing dam is
owned by the U.S. Army Corps of
Engineers.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)—825(r).
h. Applicant Contact: Mr. Douglas A.
Spaulding, Spaulding Consultants, LLC,
1433 Utica Avenue South, Suite 162,
Minneapolis, MN 55416, (952) 544–
8133.
i. FERC Contact: Etta Foster, (202)
502–8769.
j. Deadline for filing comments,
protests, and motions to intervene: 60
days from the issuance date of this
notice.
All documents (original and eight
copies) should be filed with Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
Please include the project number (P–
12633–000) on any comments, protests,
or motions filed.
k. Description of Project: The
proposed project would consist of the
existing U.S. Army Corps of Engineers’
Saylorville Dam and would consist of:
(1) Thirty-six 280–kW submersible bulbtype turbine generator units mounted on
three independent movable racks for a
total installed capacity of 10 MW; (2) a
raceway consisting of six 4,160-volt
buried cables and a 100 pair direct
buried control cable; (3) a 30-foot-square
generator control building, (4) a
switchyard; (5) a proposed 7,000-footlong,13.8–kV transmission line; and (6)
appurtenant facilities.
The project would have an estimated
annual generation of approximately 50
gigawatt-hours. The applicant plans to
sell the generated energy.
l. Location of Application: A copy of
the application is available for
PO 00000
Frm 00055
Fmt 4703
Sfmt 4703
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street, NE.,
Room 2A, Washington, DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h.
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Competing Preliminary Permit:
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30(b) and 4.36.
o. Competing Development
Application: Any qualified development
applicant desiring to file a competing
development application must submit to
the Commission, on or before a
specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30(b) and 4.36.
p. Notice of Intent: A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
E:\FR\FM\11APN1.SGM
11APN1
Agencies
[Federal Register Volume 71, Number 69 (Tuesday, April 11, 2006)]
[Notices]
[Pages 18321-18322]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-5305]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Application Accepting for Filing and Soliciting Motions
To Intervene, Protests and Comments
April 5, 2006.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary Permit.
b. Project No.: 12615-000.
c. Date filed: September 29, 2005.
d. Applicant: Alaska Power & Telephone Company.
e. Name of Project: Soule River Water Project.
f. Location: On the Soule River, within the Ketchikan Recording
District, First Judicial District, near Hyder, AK. The project would be
on federal land within the Tongass National Forest.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. Robert S. Grimm, President, Alaska Power
& Telephone Company, P.O. Box 3222, Port Townsend, WA 98368, (360) 385-
1733 x 120.
i. FERC Contact: Etta Foster, (202) 502-8769.
j. Deadline for filing comments, protests, and motions to
intervene: 60 days from the issuance date of this notice.
All documents (original and eight copies) should be filed with
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426. Please include the project
number (P-12615-000) on any comments, protests, or motions filed.
k. Description of Project: The proposed project would consist of:
(1) A proposed concrete dam with a maximum height of 150-200 feet; (2)
a proposed storage reservoir with a normal water surface area of 917
acres, a gross storage capacity of approximately 74,000 acre-feet and
an active storage capacity of approximately 60,000 acre-feet; (3) a
proposed 12-foot-diameter, 12,100-foot-long tunnel; (4) a proposed
powerhouse containing 2 generating units with a total installed
capacity of 42 MW; (5) an open channel tailrace; (6) a 35-kV submarine
cable approximately 9.72 miles long connected to an interconnection
with the existing transmission system in Hyder, and (7) appurtenant
facilities.
The project would have an estimated annual generation of
approximately 155 giga-watt hours. The applicant plans to sell the
capacity and generated energy either to BC Hydro, or an electric
utility in the United States after wheeling over the BC Hydro
transmission system.
l. Location of Application: A copy of the application is available
for inspection and reproduction at the Commission in the Public
Reference Room, located at 888 First Street, NE., Room 2A, Washington,
DC 20426, or by calling (202) 502-8371. This filing may also be viewed
on the Commission's Web site at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, call toll-free 1-866-208-3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item
h. above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Competing Preliminary Permit: Anyone desiring to file a
competing application for preliminary permit for a proposed project
must submit the competing application itself, or a notice of intent to
file such an application, to the Commission on or before the specified
comment date for the particular application (see 18 CFR 4.36).
Submission of a timely notice of intent allows an interested person to
file the competing preliminary permit application no later than 30 days
after the specified comment date for the particular application. A
competing preliminary permit application must conform with 18 CFR
4.30(b) and 4.36.
o. Competing Development Application: Any qualified development
applicant desiring to file a competing development application must
submit to the Commission, on or before a specified comment date for the
particular application, either a competing development application or a
notice of intent to file such an application. Submission of a timely
notice of intent to file a development application allows an interested
person to file the competing application no later than 120 days after
the specified comment date for the particular application. A competing
license application must conform with 18 CFR 4.30(b) and 4.36.
p. Notice of Intent: A notice of intent must specify the exact
name, business address, and telephone number of the prospective
applicant, and must include an unequivocal statement of intent to
submit, if such an application may be filed, either a preliminary
permit application or a development application (specify which type of
application). A notice of intent must be served on the applicant(s)
named in this public notice.
q. Proposed Scope of Studies under Permit: A preliminary permit, if
issued, does not authorize construction. The term of the proposed
preliminary permit would be 36 months. The work proposed under the
preliminary permit would include economic analysis, preparation of
preliminary engineering plans, and a study of environmental impacts.
Based on the results of these studies, the Applicant would decide
whether to proceed with the preparation of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to Intervene: Anyone may submit
[[Page 18322]]
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
Comments, protests and interventions may be filed electronically
via the Internet in lieu of paper; See 18 CFR 385.2001(a)(1)(iii) and
the instructions on the Commission's web site under ``e-filing'' link.
The Commission strongly encourages electronic filing.
s. Filing and Service of Responsive Documents: Any filings must
bear in all capital letter the title ``COMMENTS'', ``RECOMMENDATIONS
FOR TERMS AND CONDITIONS'', ``PROTEST'', ``MOTION TO INTERVENE'',
``NOTICE OF INTENT'', or ``COMPETING APPLICATION'', as applicable, and
the Project Number of the particular application to which the filing
refers. Any of the above-named documents must be filed by providing the
original and the number of copies provided by the Commission's
regulations to: The Secretary, Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC 20426. A copy of any motion to
intervene must also be served upon each representative of the Applicant
specified in the particular application.
t. Agency Comments: Federal, state, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the applicant. If
an agency does not file comments within the time specified for filing
comments, it will be presumed to have no comments. One copy of an
agency's comments must also be sent to the Applicant's representatives.