Public Utility District No. 1 of Chelan County, WA (Chelan PUD); Notice of Settlement Agreement, Soliciting Comments, and New Procedural Schedule, 16148 [E6-4593]
Download as PDF
16148
Federal Register / Vol. 71, No. 61 / Thursday, March 30, 2006 / Notices
If you have any questions about the
Coast Guard’s safety and security
assessment or its Letter of
Recommendation process, contact
Lieutenant Andy Meyers or Charlie
Johnson at Marine Safety Unit
Savannah, (912) 652–4353 or (912) 652–
4180 (fax).
In addition, the FERC now offers a
free service called eSubscription that
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. To register for this service,
go to https://www.ferc.gov/
esubscribenow.htm.
Public meetings or site visits will be
posted on the Commission’s calendar
located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Finally, SNG has established an
Internet Web site for this project at
https://www.elba3.com. The Web site
includes a description of the project,
additional maps of the project area, and
answers to frequently asked questions.
You can also request additional
information or provide comments
directly to SNG at (800) 793–4514.
Magalie R. Salas,
Secretary.
[FR Doc. E6–4654 Filed 3–29–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2145–060]
Public Utility District No. 1 of Chelan
County, WA (Chelan PUD); Notice of
Settlement Agreement, Soliciting
Comments, and New Procedural
Schedule
cprice-sewell on PROD1PC66 with NOTICES
March 23, 2006.
Take notice that the following
settlement agreement has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Final
Comprehensive Settlement Agreement.
b. Project No.: P–2145–060.
c. Date Filed: March 20, 2006.
d. Applicant: Public Utility District
No. 1 of Chelan County, Washington
(Chelan PUD).
e. Name of Project: Rocky Reach
Hydroelectric Project (Project).
f. Location: On the mid-Columbia
River, near the city of Wenatchee, in
VerDate Aug<31>2005
18:18 Mar 29, 2006
Jkt 208001
Chelan and Douglas Counties,
Washington.
g. Filed Pursuant to: Rule 602 of the
Commission’s Rules of Practice and
Procedure, 18 CFR 385.602.
h. Applicant Contact: Gregg
Carrington, Director of Hydro Services,
327 N. Wenatchee Avenue, Wenatchee,
WA 98801, (509) 661–4178,
gregg@chelanpud.org.
i. FERC Contact: Kim A. Nguyen,
(202) 502–6105, kim.nguyen@ferc.gov.
j. The deadline for filing comments on
the Settlement Agreement is 20 days
from the date of this notice, or April 12,
2006. The deadline for filing reply
comments is 30 days from the date of
this notice, or April 24, 2006.
All documents (original and eight
copies) should be filed with: Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
Comments may be filed electronically
via the Internet in lieu of paper. The
Commission strongly encourages
electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov) under the ‘‘e-Filing’’ link.
k. Chelan PUD filed the settlement
agreement on behalf of themselves and
the U.S. Fish and Wildlife Service, the
Washington Department of Ecology, the
U.S. National Park Service, the U.S.
Bureau of Land Management, the
Washington Department of Fish and
Wildlife, the Washington State Parks
and Recreation Commission, the City of
Entiat, the Entiat Coalition, and Alcoa
Power Generating, Inc. The purpose of
the settlement agreement is to resolve
among the signatories issues regarding
the relicensing of the Rocky Reach
Hydroelectric Project. The signatories
have agreed that the settlement
agreement is fair and reasonable and in
the public interest. On behalf of the
signatories, Chelan PUD requests that
the Commission approve the settlement
agreement and adopt it as part of a new
license without material modification.
l. A copy of the settlement agreement
is available for review at the
Commission in the Public Reference
Room or may be viewed on the
Commission’s Web site at https://
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
m. We are modifying our processing
schedule for the relicensing of the
Project. The schedule given in our
Notice on January 30, 2006 is replaced
with the following schedule:
Target Date: Issue Final
Environmental Impact Statement July,
2006; Ready for Commission Action
October, 2006.
Magalie R. Salas,
Secretary.
[FR Doc. E6–4593 Filed 3–29–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Applications Accepted for
Filing and Soliciting Comments,
Motions To Intervene, and Protests
March 24, 2006.
Take notice that the following
hydroelectric applications have been
filed with the Commission and are
available for public inspection:
a. Type of Applications: Preliminary
Permit (Competing).
b. Applicants, Project Numbers, and
Dates Filed:
Wilkesboro Hydroelectric Company
LLC filed the application for Project No.
12642–000 on January 25, 2006.
Yadkin Hydropower LLC filed the
application for Project No. 12651–000
on February 9, 2006.
c. Name of the Project: W. Kerr Scott
Hydroelectric Project. The project
would be located on the Yadkin River
in Wilkes County, North Carolina. It
would use the U.S. Army Corps of
Engineers’ (Corps) existing W. Kerr
Scott Dam.
d. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
e. Applicants Contacts: For
Wilkesboro Hydroelectric Company: M.
Clifford Phillips, Wilkesboro
E:\FR\FM\30MRN1.SGM
30MRN1
Agencies
[Federal Register Volume 71, Number 61 (Thursday, March 30, 2006)]
[Notices]
[Page 16148]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-4593]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2145-060]
Public Utility District No. 1 of Chelan County, WA (Chelan PUD);
Notice of Settlement Agreement, Soliciting Comments, and New Procedural
Schedule
March 23, 2006.
Take notice that the following settlement agreement has been filed
with the Commission and is available for public inspection.
a. Type of Application: Final Comprehensive Settlement Agreement.
b. Project No.: P-2145-060.
c. Date Filed: March 20, 2006.
d. Applicant: Public Utility District No. 1 of Chelan County,
Washington (Chelan PUD).
e. Name of Project: Rocky Reach Hydroelectric Project (Project).
f. Location: On the mid-Columbia River, near the city of Wenatchee,
in Chelan and Douglas Counties, Washington.
g. Filed Pursuant to: Rule 602 of the Commission's Rules of
Practice and Procedure, 18 CFR 385.602.
h. Applicant Contact: Gregg Carrington, Director of Hydro Services,
327 N. Wenatchee Avenue, Wenatchee, WA 98801, (509) 661-4178,
gregg@chelanpud.org.
i. FERC Contact: Kim A. Nguyen, (202) 502-6105,
kim.nguyen@ferc.gov.
j. The deadline for filing comments on the Settlement Agreement is
20 days from the date of this notice, or April 12, 2006. The deadline
for filing reply comments is 30 days from the date of this notice, or
April 24, 2006.
All documents (original and eight copies) should be filed with:
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
Comments may be filed electronically via the Internet in lieu of
paper. The Commission strongly encourages electronic filings. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site (https://www.ferc.gov) under the ``e-Filing'' link.
k. Chelan PUD filed the settlement agreement on behalf of
themselves and the U.S. Fish and Wildlife Service, the Washington
Department of Ecology, the U.S. National Park Service, the U.S. Bureau
of Land Management, the Washington Department of Fish and Wildlife, the
Washington State Parks and Recreation Commission, the City of Entiat,
the Entiat Coalition, and Alcoa Power Generating, Inc. The purpose of
the settlement agreement is to resolve among the signatories issues
regarding the relicensing of the Rocky Reach Hydroelectric Project. The
signatories have agreed that the settlement agreement is fair and
reasonable and in the public interest. On behalf of the signatories,
Chelan PUD requests that the Commission approve the settlement
agreement and adopt it as part of a new license without material
modification.
l. A copy of the settlement agreement is available for review at
the Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1-
866-208-3676, or for TTY (202) 502-8659. A copy is also available for
inspection and reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
m. We are modifying our processing schedule for the relicensing of
the Project. The schedule given in our Notice on January 30, 2006 is
replaced with the following schedule:
Target Date: Issue Final Environmental Impact Statement July, 2006;
Ready for Commission Action October, 2006.
Magalie R. Salas,
Secretary.
[FR Doc. E6-4593 Filed 3-29-06; 8:45 am]