Central New York Oil and Gas Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Stagecoach Phase II Expansion Project and Request for Comments on Environmental Issues and Notice of Site Visit, 14882-14884 [E6-4239]
Download as PDF
14882
Federal Register / Vol. 71, No. 57 / Friday, March 24, 2006 / Notices
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Magalie R. Salas,
Secretary.
[FR Doc. E6–4240 Filed 3–23–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP06–64–000]
Central New York Oil and Gas
Company, LLC; Notice of Intent To
Prepare an Environmental Assessment
for the Proposed Stagecoach Phase II
Expansion Project and Request for
Comments on Environmental Issues
and Notice of Site Visit
wwhite on PROD1PC61 with NOTICES
March 17, 2006.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Stagecoach Phase II Expansion
Project, involving construction and
operation of facilities by Central New
York Oil and Gas, LLC (CNYOG) in
Tioga County, New York and Bradford
County, Pennsylvania.1 The EA will be
used by the Commission in its decisionmaking process to determine whether
the project is the public convenience
and necessity.
This notice announces the opening of
the scoping period that will be used to
gather environmental input from the
public and interested agencies on the
project. Your input will help the
Commission staff determine which
issues need to be evaluated in the EA.
Please note that the scoping period will
close on April 17, 2006.
An effort is being made to send this
notice to all individuals, organizations,
Native American Tribes, and
government entities interested in and/or
potentially affected by the proposed
project. This includes all landowners
who are potential right-of-way grantors,
whose property may be used
temporarily for project purposes, or who
own homes within distances defined in
the Commission’s regulations of certain
aboveground facilities. We encourage
government representatives to notify
their constituents of this planned
1 CNYOG’s application in Docket No. CP06–64–
000 was filed with the Commission under section
7 of the Natural Gas Act.
VerDate Aug<31>2005
18:26 Mar 23, 2006
Jkt 208001
project and encourage them to comment
on their areas of concern.
If you are a landowner receiving this
notice, you may be contacted by a
pipeline company representative about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The pipeline
company would seek to negotiate a
mutually acceptable agreement.
However, if the project is approved by
the Commission, that approval conveys
with it the right of eminent domain.
Therefore, if easement negotiations fail
to produce an agreement, the pipeline
company could initiate condemnation
proceedings in accordance with state
law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility on My Land? What Do I Need
to Know?’’ was attached to the project
notice (CNYOG) provided to
landowners. This fact sheet addresses a
number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is
available for viewing on the FERC
Internet Web site (https://www.ferc.gov).
Summary of the Proposed Project
The entire Stagecoach Storage Field
would consist of a total of six reservoirs
(‘‘pools’’), two of which and were
converted into storage reservoirs as part
of the original Stagecoach Phase I
construction, and four of which are
nearly depleted production reservoirs
and would be added to the Stagecoach
Storage Facility as part of the Phase II
Expansion Project. The existing
Stagecoach Storage Facility consists of
the Barnhart-Owen and Widell pools,
ten storage wells, seven observation
wells, about 12 miles of interconnecting
pipeline, and a central compressor
facility. The existing working storage
capacity is 13.25 Billion cubic feet (Bcf).
The Phase II Expansion Project would
develop the four remaining pools
(Lidell, Racht, Brenchley-Cook, and
Nichols-Mead pools) for an additional
working storage capacity estimated at 13
Bcf.
As part of the proposed expansion,
CNYOG would construct:
• An additional 12,000-horsepower
electric-drive centrifugal compressor
unit to be installed within the existing
Stagecoach Central Compressor Station
building;
• A power transformer and gas
cooling unit and other appurtenant
facilities to be installed within the
Central Compressor Station;
PO 00000
Frm 00051
Fmt 4703
Sfmt 4703
• A total of nine storage injection/
withdrawal wells; 2
• Approximately 7.3-miles of 6-inch, 8-inch-, and 20-inch-diameter
gathering pipeline and associated rightsof-way;
• Eight wellhead meter stations and
other appurtenant facilities, including
isolation valves, separators,
measurement and communication
equipment, and a 20-foot by 70-foot
building at each storage well site to
house equipment; and
• About 4.4 miles of access roads not
contained within pipeline or well
easements.
As part of the storage facility, CNYOG
also proposes to construct and operate
a 9.3-mile-long, 24-inch-diameter lateral
(North Lateral) from the existing
compressor station to the proposed
Millennium Pipeline located north of
the town of Owego, New York.3 Its
appurtenant facilities will include
measurement and regulation,
communication, isolation valves, and
pigging facilities.
The general location of CNYOG’s
proposed facilities is shown on the map
attached as appendix 1.4
Land Requirements for Construction
Construction of the proposed facilities
would require about 278.1 acres of land.
Of this acreage, 115.5 acres would be
permanently affected. The remaining
162.6 acres would be temporarily
impacted and allowed to revert to its
former use. Each of CNYOG’s nine test/
storage wells would temporarily disturb
about a 250-foot-radius area.
A 100-foot-wide construction right-ofway is proposed for the North Lateral
pipeline facilities, and a 50-foot-wide
construction right-of-way is proposed
for all pipeline laterals to the storage
wells. The North Lateral construction
2 Four of the wells (one in each of the Lidell,
Racht, Brenchley-Cook, and Nichols-Mead pools)
would be drilled during the late spring/early
summer of 2006 under the existing FERC
authorization for the Stagecoach Storage Facility
issued in 2001 (Docket No. CP00–62–000). The
remaining five storage wells would be located
within the Lidell Pool and would be drilled once
CNYOG receives any approval for the Phase II
Expansion Project.
3 The Millennium Pipeline Project was approved
by the Commission on September 19, 2002 in
Docket Nos. CP98–150–006 and –007. Construction
of the Millennium Pipeline has not commenced to
date.
4 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of all
appendices, other than Appendix 1 (map), are
available on the Commission’s Web site at the
‘‘eLibrary’’ link or from the Commission’s Public
Reference Room, 888 First Street, NE., Washington,
DC 20426, or call (202) 502–8371. For instructions
on connecting to eLibrary refer to the last page of
this notice. Copies of the appendices were sent to
all those receiving this notice in the mail.
E:\FR\FM\24MRN1.SGM
24MRN1
Federal Register / Vol. 71, No. 57 / Friday, March 24, 2006 / Notices
area parallels/crosses a New York State
Electric and Gas Company (NYSEG)
electric transmission line for about
2,852 feet. The North Lateral follows the
same general alignment as an existing
Columbia Gas pipeline across the
Susquehanna River north to the
proposed Millennium Pipeline
interconnect. CNYOG would maintain a
50-foot permanent right-of-way for
operation of the pipeline facilities.
wwhite on PROD1PC61 with NOTICES
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping’’. The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
Notice of Intent, the Commission staff
requests public comments on the scope
of the issues to address in the EA. All
comments received will be considered
during the preparation of the EA. State
and local government representatives
are encouraged to notify their
constituents of this proposed action and
encourage them to comment on their
areas of concern.
In the EA, we 5 will discuss impacts
that could occur as a result of the
construction and operation of the
proposed project. We will also evaluate
possible alternatives to the proposed
project or portions of the project, and
make recommendations on how to
lessen or avoid impacts on the various
resource areas. The EA we will discuss
impacts that could occur as a result of
the construction and operation of the
proposed project under these general
headings:
• Geology and soils.
• Land use.
• Water resources, fisheries, and
wetlands.
• Cultural resources.
• Vegetation and wildlife.
• Air quality and noise.
• Endangered and threatened species.
• Public safety.
Our independent analysis of the
issues will be presented in the EA. We
will also evaluate possible alternatives
to the proposed project or portions of
the project, and make recommendations
on how to lessen or avoid impacts on
the various resource areas.
5 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the
environmental staff of the Office of Energy Projects
(OEP).
VerDate Aug<31>2005
18:26 Mar 23, 2006
Jkt 208001
Depending on the comments received
during the scoping process, the EA may
be published and mailed to Federal,
State, and local government agencies;
public interest groups; Native American
tribes; interested individuals; affected
landowners, newspapers, libraries, and
the Commission’s official service list for
this proceeding. A 30-day comment
period will be allotted for review if the
EA is published. We will consider all
comments submitted in any
Commission Order that is issued for the
project.
To ensure your comments are
considered, please carefully follow the
instructions in the public participation
section below.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
By becoming a commenter, your
concerns will be addressed in the EA
and considered by the Commission.
Your comments should focus on the
potential environmental effects of the
proposal, reasonable alternatives to the
proposal (including alternative locations
and routes), and measures to avoid or
lessen environmental impact. The more
specific your comments, the more useful
they will be. Please carefully follow
these instructions to ensure that your
comments are received in time and
properly recorded:
• Send an original and two copies of
your letter to: Magalie R. Salas,
Secretary, Federal Energy Regulatory
Commission, 888 First St., NE., Room
1A, Washington, DC 20426.
• Label one copy of the comments for
the attention of Gas Branch 1.
• Reference Docket No. CP06–64–
000.
• Mail your comments so that they
will be received in Washington, DC, on
or before April 17, 2006.
Please note that the Commission
encourages electronic filing of
comments. See 18 Code of Federal
Regulations (CFR) 385.2001(a)(1)(iii)
and the instructions on the
Commission’s Internet Web site at
https://www.ferc.gov under the ‘‘eFiling’’
link and the link to the User’s Guide.
Prepare your submission in the same
manner as you would if filing on paper
and save it to a file on your hard drive.
Before you can file comments you will
need to create an account by clicking on
‘‘Login to File’’ and then ‘‘New User
Account.’’ You will be asked to select
the type of filing you are making. This
filing is considered a ‘‘Comment on
Filing.’’
PO 00000
Frm 00052
Fmt 4703
Sfmt 4703
14883
Public Meeting
In addition to or in lieu of sending
written comments, we invite you to
attend the public scoping meeting we
will conduct in the project area. The
location for this meeting is listed below.
The meeting is scheduled for Tuesday,
April 4, 2006 from 7 p.m. to 10 p.m.
Owego Treadway Inn, 1100 State
Route 17C, Owego, NY 13827. (607)
687–4500.
Public scoping meetings are designed
to provide State and local agencies,
interested groups, affected landowners,
and the general public with another
opportunity to offer comments on the
project. Interested groups and
individuals are encouraged to attend the
meeting and to present comments on the
environmental issues they believe
should be addressed in the EA.
Site Visit
On April 5, 2006, the FERC staff will
conduct a site visit of the Stagecoach
Storage Facility. The purpose of the visit
will be to inspect both the existing
storage facility and the proposed
Stagecoach Phase II Expansion Project.
We will view the proposed storage field
expansion, well sites, and associated
pipeline routes. Representatives of
CNYOG will be accompanying the FERC
staff.
All interested parties may attend the
site visit on April 5, 2006. Those
planning to attend must provide their
own transportation. If you are interested
in attending the site visit, please meet
at 8 a.m. in the lobby of the Owego
Treadway Inn at the address listed
above.
Becoming an Intervener
In addition to involvement in the EA
scoping process, you may want to
become an official party to the
proceeding, or ‘‘intervener’’. To become
an intervener you must file a motion to
intervene according to Rule 214 of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214). Interveners
have the right to seek rehearing of the
Commission’s decision. Motions to
Intervene should be electronically
submitted using the Commission’s
eFiling system at https://www.ferc.gov.
Persons without Internet access should
send an original and 14 copies of their
motion to the Secretary of the
Commission at the address indicated
previously. Persons filing Motions to
Intervene on or before the comment
deadline indicated above must send a
copy of the motion to the Applicant. All
filings, including late interventions,
submitted after the comment deadline
must be served on the Applicant and all
E:\FR\FM\24MRN1.SGM
24MRN1
14884
Federal Register / Vol. 71, No. 57 / Friday, March 24, 2006 / Notices
other interveners identified on the
Commission’s service list for this
proceeding. Persons on the service list
with e-mail addresses may be served
electronically; others must be served a
hard copy of the filing. Please refer to
Appendix 2 if you would like more
information on how to intervene in
Commission proceedings.
Affected landowners and parties with
environmental concerns may be granted
intervener status upon showing good
cause by stating that they have a clear
and direct interest in this proceeding
which would not be adequately
represented by any other parties. You do
not need intervener status to have your
environmental comments considered.
Environmental Mailing List
If you do not want to remain on our
mailing list, please return the Remove
From Mailing List Form included in
Appendix 3. If you return this form, you
will be removed from the Commission’s
environmental mailing list.
wwhite on PROD1PC61 with NOTICES
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs
at 1–866–208 FERC (3372) or on the
FERC Internet Web site (https://
www.ferc.gov). Using the ‘‘eLibrary’’
link, select ‘‘General Search’’ from the
eLibrary menu, enter the selected date
range and ‘‘Docket Number’’ (i.e., CP06–
64–000), and follow the instructions.
For assistance with access to eLibrary,
the helpline can be reached at 1–866–
208–3676, TTY (202) 502–8659, or at
FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC Internet Web
site also provides access to the texts of
formal documents issued by the
Commission, such as orders, notices,
and rule makings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to https://
www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Magalie R. Salas,
Secretary.
[FR Doc. E6–4239 Filed 3–23–06; 8:45 am]
BILLING CODE 6717–01–P
VerDate Aug<31>2005
18:26 Mar 23, 2006
Jkt 208001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP06–53–000]
Eastern Shore Natural Gas Company;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed 2006–2008 Expansion
Project and Request for Comments on
Environmental Issues
March 15, 2006.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) is preparing an
environmental assessment (EA) that will
discuss the environmental impacts of
Eastern Shore Natural Gas Company’s
(ESNG) proposed 2006–2008 Expansion
Project involving construction and
operation of natural gas pipeline
facilities in Chester County,
Pennsylvania, and New Castle, Kent,
and Sussex Counties, Delaware.1 This
EA will be used by the Commission in
its decision-making process to
determine whether the project is in the
public convenience and necessity.
If you are a landowner receiving this
notice, you may be contacted by a
pipeline company representative about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The pipeline
company would seek to negotiate a
mutually acceptable agreement.
However, if the project is approved by
the Commission, that approval conveys
with it the right of eminent domain.
Therefore, if easement negotiations fail
to produce an agreement, the pipeline
company could initiate condemnation
proceedings in accordance with state
law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC Internet Web site (https://
www.ferc.gov). This fact sheet addresses
a number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings.
Summary of the Proposed Project
The purpose of ESNG’s project is to
increase the capacity of its existing
pipeline system to accommodate
growing demand within its market area.
To meet this demand, ESNG would
construct about 55 miles of various
diameter pipeline and two new meter
1 ESNG’s application was filed with the
Commission under section 7 of the Natural Gas Act
and Part 157 of the Commission’s regulations.
PO 00000
Frm 00053
Fmt 4703
Sfmt 4703
stations. Specifically, ESNG proposes to
add 15.0 miles of mainline pipeline,
40.0 miles of looping pipeline and
appurtenant facilities. The project is
composed of seven segments and
includes:
• Segment 1 (Chester County, PA)—
About 1.5 miles of 16-inch-diameter
pipeline, looping ESNG’s existing 8inch-diameter Parkesburg mainline;
• Segment 1A (Chester County, PA)—
About 0.6 mile of 16-inch-diameter
pipeline, looping ESNG’s two existing
pipelines;
• Segment 2 (New Castle and Kent
Counties, DE)—About 23.8 miles of 16inch-diameter pipeline, looping ESNG’s
existing 10-inch-diameter Hockessin
mainline;
• Segment 3 (New Castle County,
DE)—About 6.1 miles of 10-inchdiameter pipeline, looping ESNG’s
existing 6-inch-diameter Parkesburg
mainline;
• Segment 4 (Sussex County, DE)—
About 4.0 miles of 10-inch-diameter
pipeline, looping ESNG’s existing 6inch-diameter Parkesburg mainline;
• Segment 5 (Sussex County, DE)—
About 4.0 miles of 10-inch-diameter
pipeline, looping ESNG’s existing 6inch-diameter Cambridge/Easton
mainline; and
• Segment 6 (Sussex County, DE)—
About 15.0 miles of 6-inch-diameter
pipeline to tie into an existing ESNG 6inch-diameter pipeline upstream and
extend southerly to Millsboro, DE.
ESNG also proposes to construct two
new metering stations located at
Mileposts 10.4 and 15.0 as part of
Segment 6.
The general locations of the project
facilities are shown in Appendix 1.2
Land Requirements for Construction
Construction of the proposed facilities
would require about 752.46 acres of
land including some of ESNG’s existing
permanent easement. Following
construction, about 1.52 acres would be
maintained for new permanent
easement and operation of the
aboveground facility sites. The
remaining 750.94 acres of land would be
restored and allowed to revert to its
former use.
2 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of all
appendices, other than Appendix 1 (maps), are
available on the Commission’s Web site at the
‘‘eLibrary’’ link or from the Commission’s Public
Reference Room, 888 First Street, NE., Washington,
DC 20426, or call (202) 502–8371. For instructions
on connecting to eLibrary refer to the last page of
this notice. Copies of the appendices were sent to
all those receiving this notice in the mail.
For instructions on connecting to eLibrary refer
to the last page of this notice. Copies of the
appendices were sent to all those receiving this
notice in the mail.
E:\FR\FM\24MRN1.SGM
24MRN1
Agencies
[Federal Register Volume 71, Number 57 (Friday, March 24, 2006)]
[Notices]
[Pages 14882-14884]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-4239]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP06-64-000]
Central New York Oil and Gas Company, LLC; Notice of Intent To
Prepare an Environmental Assessment for the Proposed Stagecoach Phase
II Expansion Project and Request for Comments on Environmental Issues
and Notice of Site Visit
March 17, 2006.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Stagecoach Phase II Expansion
Project, involving construction and operation of facilities by Central
New York Oil and Gas, LLC (CNYOG) in Tioga County, New York and
Bradford County, Pennsylvania.\1\ The EA will be used by the Commission
in its decision-making process to determine whether the project is the
public convenience and necessity.
---------------------------------------------------------------------------
\1\ CNYOG's application in Docket No. CP06-64-000 was filed with
the Commission under section 7 of the Natural Gas Act.
---------------------------------------------------------------------------
This notice announces the opening of the scoping period that will
be used to gather environmental input from the public and interested
agencies on the project. Your input will help the Commission staff
determine which issues need to be evaluated in the EA. Please note that
the scoping period will close on April 17, 2006.
An effort is being made to send this notice to all individuals,
organizations, Native American Tribes, and government entities
interested in and/or potentially affected by the proposed project. This
includes all landowners who are potential right-of-way grantors, whose
property may be used temporarily for project purposes, or who own homes
within distances defined in the Commission's regulations of certain
aboveground facilities. We encourage government representatives to
notify their constituents of this planned project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this notice, you may be contacted
by a pipeline company representative about the acquisition of an
easement to construct, operate, and maintain the proposed facilities.
The pipeline company would seek to negotiate a mutually acceptable
agreement. However, if the project is approved by the Commission, that
approval conveys with it the right of eminent domain. Therefore, if
easement negotiations fail to produce an agreement, the pipeline
company could initiate condemnation proceedings in accordance with
state law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility on My Land? What Do I Need to Know?'' was attached to the
project notice (CNYOG) provided to landowners. This fact sheet
addresses a number of typically asked questions, including the use of
eminent domain and how to participate in the Commission's proceedings.
It is available for viewing on the FERC Internet Web site (https://
www.ferc.gov).
Summary of the Proposed Project
The entire Stagecoach Storage Field would consist of a total of six
reservoirs (``pools''), two of which and were converted into storage
reservoirs as part of the original Stagecoach Phase I construction, and
four of which are nearly depleted production reservoirs and would be
added to the Stagecoach Storage Facility as part of the Phase II
Expansion Project. The existing Stagecoach Storage Facility consists of
the Barnhart-Owen and Widell pools, ten storage wells, seven
observation wells, about 12 miles of interconnecting pipeline, and a
central compressor facility. The existing working storage capacity is
13.25 Billion cubic feet (Bcf).
The Phase II Expansion Project would develop the four remaining
pools (Lidell, Racht, Brenchley-Cook, and Nichols-Mead pools) for an
additional working storage capacity estimated at 13 Bcf.
As part of the proposed expansion, CNYOG would construct:
An additional 12,000-horsepower electric-drive centrifugal
compressor unit to be installed within the existing Stagecoach Central
Compressor Station building;
A power transformer and gas cooling unit and other
appurtenant facilities to be installed within the Central Compressor
Station;
A total of nine storage injection/withdrawal wells; \2\
---------------------------------------------------------------------------
\2\ Four of the wells (one in each of the Lidell, Racht,
Brenchley-Cook, and Nichols-Mead pools) would be drilled during the
late spring/early summer of 2006 under the existing FERC
authorization for the Stagecoach Storage Facility issued in 2001
(Docket No. CP00-62-000). The remaining five storage wells would be
located within the Lidell Pool and would be drilled once CNYOG
receives any approval for the Phase II Expansion Project.
---------------------------------------------------------------------------
Approximately 7.3-miles of 6-inch-, 8-inch-, and 20-inch-
diameter gathering pipeline and associated rights-of-way;
Eight wellhead meter stations and other appurtenant
facilities, including isolation valves, separators, measurement and
communication equipment, and a 20-foot by 70-foot building at each
storage well site to house equipment; and
About 4.4 miles of access roads not contained within
pipeline or well easements.
As part of the storage facility, CNYOG also proposes to construct
and operate a 9.3-mile-long, 24-inch-diameter lateral (North Lateral)
from the existing compressor station to the proposed Millennium
Pipeline located north of the town of Owego, New York.\3\ Its
appurtenant facilities will include measurement and regulation,
communication, isolation valves, and pigging facilities.
---------------------------------------------------------------------------
\3\ The Millennium Pipeline Project was approved by the
Commission on September 19, 2002 in Docket Nos. CP98-150-006 and -
007. Construction of the Millennium Pipeline has not commenced to
date.
---------------------------------------------------------------------------
The general location of CNYOG's proposed facilities is shown on the
map attached as appendix 1.\4\
---------------------------------------------------------------------------
\4\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies of all appendices, other
than Appendix 1 (map), are available on the Commission's Web site at
the ``eLibrary'' link or from the Commission's Public Reference
Room, 888 First Street, NE., Washington, DC 20426, or call (202)
502-8371. For instructions on connecting to eLibrary refer to the
last page of this notice. Copies of the appendices were sent to all
those receiving this notice in the mail.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would require about 278.1
acres of land. Of this acreage, 115.5 acres would be permanently
affected. The remaining 162.6 acres would be temporarily impacted and
allowed to revert to its former use. Each of CNYOG's nine test/storage
wells would temporarily disturb about a 250-foot-radius area.
A 100-foot-wide construction right-of-way is proposed for the North
Lateral pipeline facilities, and a 50-foot-wide construction right-of-
way is proposed for all pipeline laterals to the storage wells. The
North Lateral construction
[[Page 14883]]
area parallels/crosses a New York State Electric and Gas Company
(NYSEG) electric transmission line for about 2,852 feet. The North
Lateral follows the same general alignment as an existing Columbia Gas
pipeline across the Susquehanna River north to the proposed Millennium
Pipeline interconnect. CNYOG would maintain a 50-foot permanent right-
of-way for operation of the pipeline facilities.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
to discover and address concerns the public may have about proposals.
This process is referred to as ``scoping''. The main goal of the
scoping process is to focus the analysis in the EA on the important
environmental issues. By this Notice of Intent, the Commission staff
requests public comments on the scope of the issues to address in the
EA. All comments received will be considered during the preparation of
the EA. State and local government representatives are encouraged to
notify their constituents of this proposed action and encourage them to
comment on their areas of concern.
In the EA, we \5\ will discuss impacts that could occur as a result
of the construction and operation of the proposed project. We will also
evaluate possible alternatives to the proposed project or portions of
the project, and make recommendations on how to lessen or avoid impacts
on the various resource areas. The EA we will discuss impacts that
could occur as a result of the construction and operation of the
proposed project under these general headings:
---------------------------------------------------------------------------
\5\ ``We'', ``us'', and ``our'' refer to the environmental staff
of the Office of Energy Projects (OEP).
---------------------------------------------------------------------------
Geology and soils.
Land use.
Water resources, fisheries, and wetlands.
Cultural resources.
Vegetation and wildlife.
Air quality and noise.
Endangered and threatened species.
Public safety.
Our independent analysis of the issues will be presented in the EA.
We will also evaluate possible alternatives to the proposed project or
portions of the project, and make recommendations on how to lessen or
avoid impacts on the various resource areas.
Depending on the comments received during the scoping process, the
EA may be published and mailed to Federal, State, and local government
agencies; public interest groups; Native American tribes; interested
individuals; affected landowners, newspapers, libraries, and the
Commission's official service list for this proceeding. A 30-day
comment period will be allotted for review if the EA is published. We
will consider all comments submitted in any Commission Order that is
issued for the project.
To ensure your comments are considered, please carefully follow the
instructions in the public participation section below.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. By becoming a commenter, your
concerns will be addressed in the EA and considered by the Commission.
Your comments should focus on the potential environmental effects of
the proposal, reasonable alternatives to the proposal (including
alternative locations and routes), and measures to avoid or lessen
environmental impact. The more specific your comments, the more useful
they will be. Please carefully follow these instructions to ensure that
your comments are received in time and properly recorded:
Send an original and two copies of your letter to: Magalie
R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First
St., NE., Room 1A, Washington, DC 20426.
Label one copy of the comments for the attention of Gas
Branch 1.
Reference Docket No. CP06-64-000.
Mail your comments so that they will be received in
Washington, DC, on or before April 17, 2006.
Please note that the Commission encourages electronic filing of
comments. See 18 Code of Federal Regulations (CFR) 385.2001(a)(1)(iii)
and the instructions on the Commission's Internet Web site at https://
www.ferc.gov under the ``eFiling'' link and the link to the User's
Guide. Prepare your submission in the same manner as you would if
filing on paper and save it to a file on your hard drive. Before you
can file comments you will need to create an account by clicking on
``Login to File'' and then ``New User Account.'' You will be asked to
select the type of filing you are making. This filing is considered a
``Comment on Filing.''
Public Meeting
In addition to or in lieu of sending written comments, we invite
you to attend the public scoping meeting we will conduct in the project
area. The location for this meeting is listed below. The meeting is
scheduled for Tuesday, April 4, 2006 from 7 p.m. to 10 p.m.
Owego Treadway Inn, 1100 State Route 17C, Owego, NY 13827. (607)
687-4500.
Public scoping meetings are designed to provide State and local
agencies, interested groups, affected landowners, and the general
public with another opportunity to offer comments on the project.
Interested groups and individuals are encouraged to attend the meeting
and to present comments on the environmental issues they believe should
be addressed in the EA.
Site Visit
On April 5, 2006, the FERC staff will conduct a site visit of the
Stagecoach Storage Facility. The purpose of the visit will be to
inspect both the existing storage facility and the proposed Stagecoach
Phase II Expansion Project. We will view the proposed storage field
expansion, well sites, and associated pipeline routes. Representatives
of CNYOG will be accompanying the FERC staff.
All interested parties may attend the site visit on April 5, 2006.
Those planning to attend must provide their own transportation. If you
are interested in attending the site visit, please meet at 8 a.m. in
the lobby of the Owego Treadway Inn at the address listed above.
Becoming an Intervener
In addition to involvement in the EA scoping process, you may want
to become an official party to the proceeding, or ``intervener''. To
become an intervener you must file a motion to intervene according to
Rule 214 of the Commission's Rules of Practice and Procedure (18 CFR
385.214). Interveners have the right to seek rehearing of the
Commission's decision. Motions to Intervene should be electronically
submitted using the Commission's eFiling system at https://www.ferc.gov.
Persons without Internet access should send an original and 14 copies
of their motion to the Secretary of the Commission at the address
indicated previously. Persons filing Motions to Intervene on or before
the comment deadline indicated above must send a copy of the motion to
the Applicant. All filings, including late interventions, submitted
after the comment deadline must be served on the Applicant and all
[[Page 14884]]
other interveners identified on the Commission's service list for this
proceeding. Persons on the service list with e-mail addresses may be
served electronically; others must be served a hard copy of the filing.
Please refer to Appendix 2 if you would like more information on how to
intervene in Commission proceedings.
Affected landowners and parties with environmental concerns may be
granted intervener status upon showing good cause by stating that they
have a clear and direct interest in this proceeding which would not be
adequately represented by any other parties. You do not need intervener
status to have your environmental comments considered.
Environmental Mailing List
If you do not want to remain on our mailing list, please return the
Remove From Mailing List Form included in Appendix 3. If you return
this form, you will be removed from the Commission's environmental
mailing list.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs at 1-866-208 FERC (3372) or on
the FERC Internet Web site (https://www.ferc.gov). Using the
``eLibrary'' link, select ``General Search'' from the eLibrary menu,
enter the selected date range and ``Docket Number'' (i.e., CP06-64-
000), and follow the instructions. For assistance with access to
eLibrary, the helpline can be reached at 1-866-208-3676, TTY (202) 502-
8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC
Internet Web site also provides access to the texts of formal documents
issued by the Commission, such as orders, notices, and rule makings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at https://www.ferc.gov/EventCalendar/
EventsList.aspx along with other related information.
Magalie R. Salas,
Secretary.
[FR Doc. E6-4239 Filed 3-23-06; 8:45 am]
BILLING CODE 6717-01-P