EPAAR Prescription and Clause-Simplified Acquisition Procedures Financing, 12660-12661 [E6-3518]
Download as PDF
wwhite on PROD1PC61 with PROPOSALS
12660
Federal Register / Vol. 71, No. 48 / Monday, March 13, 2006 / Proposed Rules
notice from BLM to provide any
additional information necessary to
complete the APD, or the APD may be
returned to the operator.
(b) Within 30 days after the operator
has submitted a complete application,
including incorporating any changes
that resulted from the onsite inspection,
the BLM will:
(1) Approve the application, subject to
reasonable conditions of approval, if the
requirements of the NEPA, NHPA, ESA,
and other applicable law have been met
and, if on FS lands, FS has approved the
SUPO; or
(2) Notify the operator that it is
deferring action on the permit.
(c) The notice of deferral in paragraph
(b)(2) of this section must specify:
(1) Any action the operator could take
that would enable BLM (in consultation
with the FS if applicable) to issue a final
decision on the application. The FS will
notify the applicant of any action the
applicant could take that would enable
the FS to issue a final decision on the
SUPO on NFS lands. Actions may
include, but are not limited to,
assistance with:
(A) Data gathering; and
(B) Preparing analyses and
documents.
(2) If applicable, a list of actions that
BLM or the FS need to take before
making a final decision on the
application, including analysis required
by NEPA or other applicable law and a
schedule for completing these actions.
(d) The operator has two years from
the date of the notice under paragraph
(c)(1) of this section to take the action
specified in the notice. If all analyses
required by NEPA, NHPA, ESA, and
other applicable laws have been
completed, BLM (and the FS if
applicable), will make a decision on the
permit and the SUPO within 10 days of
receiving a report from the operator
addressing all of the issues or actions
specified in the notice under paragraph
(c)(1) of this section and certifying that
all required actions have been taken. If
the operator has not completed the
actions specified in the notice within
two years from the operator’s receipt of
the paragraph (c)(1) notice, BLM will
deny the permit.
(e) For APDs on NFS lands, the
decision to approve a SUPO or Master
Development Plan may be subject to FS
appeal procedures. Under current FS
appeal procedures, resolution of the
appeal may take up to 105 days before
that decision can be implemented. BLM
cannot approve an APD until the appeal
of the SUPO is resolved.
3. Further amend section VI. of the
Appendix following the regulatory text
of proposed rule by revising the last
VerDate Aug<31>2005
16:18 Mar 10, 2006
Jkt 208001
sentence of the first paragraph on page
43362 to read as follows:
This section also applies to lands with
Indian surface and Federal minerals.
The operator must address surface use
issues with the Bureau of Indian Affairs.
Dated: March 2, 2006.
Dale N. Bosworth,
Chief, USDA—Forest Service.
Dated: February 24, 2006.
Johnnie Burton,
Acting Assistant Secretary, Land and
Minerals Management.
[FR Doc. 06–2371 Filed 3–10–06; 8:45 am]
BILLING CODE 4310–84–P
ENVIRONMENTAL PROTECTION
AGENCY
48 CFR Parts 1532 and 1552
[FRL–8044–3]
EPAAR Prescription and Clause—
Simplified Acquisition Procedures
Financing
Environmental Protection
Agency (EPA).
ACTION: Proposed rule.
AGENCY:
SUMMARY: EPA is proposing to revise the
EPA Acquisition Regulation (EPAAR)
Subparts 1532 and 1552 to implement a
procedure for simplified acquisition
procedures financing. This proposed
EPAAR revision will add a prescription
and clause for contracting officers to use
when approving advance or interim
payments on simplified acquisitions.
The proposed prescription and clause
apply to commercial item orders at or
below the simplified acquisition
threshold. This action revises the
EPAAR, but does not impose any new
requirements on Agency contractors.
The procedure will allow contractors to
invoice for advance and interim
payments in accordance with standard
commercial practices when authorized
by the contracting officer and identified
in the clause payment schedule.
DATES: Interested parties should submit
comments in writing on or before May
12, 2006.
ADDRESSES: Submit your comments,
identified by Docket ID No. OARM–
2006–0126, by one of the following
methods:
• Federal eRulemaking Portal: https://
www.regulations.gov. Follow the on-line
instructions for submitting comments.
• Agency Web site: https://
www.epa.gov/edocket. EDOCKET, EPA’s
electronic public docket and comment
system, is EPA’s preferred method for
receiving comments. Follow the on-line
instructions for submitting comments.
PO 00000
Frm 00027
Fmt 4702
Sfmt 4702
• E-mail: oei.docket@epa.gov.
• Surface Mail: EPA Docket Center,
Environmental Protection Agency,
Mailcode: 28221T, 1200 Pennsylvania
Ave., NW., Washington, DC 20460.
Attention Docket ID No. OARM–2006–
0126.
Instructions: Direct your comments to
Docket ID No. EPA’s policy is that all
comments received will be included in
the public docket without change and
may be made available online at
https://www.epa.gov/edocket, including
any personal information provided,
unless the comment includes
information claimed to be Confidential
Business Information (CBI) or other
information whose disclosure is
restricted by statute. Do not submit
information that you consider to be CBI
or otherwise protected through
EDOCKET, regulations.gov, or e-mail.
The EPA EDOCKET and the federal
regulations.gov Web sites are
‘‘anonymous access’’ systems, which
means EPA will not know your identity
or contact information unless you
provide it in the body of your comment.
If you send an e-mail comment directly
to EPA without going through
EDOCKET or regulations.gov, your
e-mail address will be automatically
captured and included as part of the
comment that is placed in the public
docket and made available on the
Internet. If you submit an electronic
comment, EPA recommends that you
include your name and other contact
information in the body of your
comment and with any disk or CD–ROM
you submit. If EPA cannot read your
comment due to technical difficulties
and cannot contact you for clarification,
EPA may not be able to consider your
comment. Electronic files should avoid
the use of special characters, any form
of encryption, and be free of any defects
or viruses. For additional information
about EPA’s public docket visit
EDOCKET on-line or see the Federal
Register of May 31, 2002 (67 FR 38102).
Docket: All documents in the docket
are listed in the EDOCKET index at
https://www.epa.gov/edocket. Although
listed in the index, some information is
not publicly available, i.e., CBI or other
information whose disclosure is
restricted by statute. Certain other
material, such as copyrighted material,
is not placed on the Internet and will be
publicly available only in hard copy
form. Publicly available docket
materials are available either
electronically in EDOCKET or in hard
copy at the OEI Docket, EPA/DC, EPA
West, Room B102, 1301 Constitution
Ave., NW., Washington, DC. The Public
Reading Room is open from 8:30 a.m. to
4:30 p.m., Monday through Friday,
E:\FR\FM\13MRP1.SGM
13MRP1
Federal Register / Vol. 71, No. 48 / Monday, March 13, 2006 / Proposed Rules
excluding legal holidays. The telephone
number for the Public Reading Room is
(202) 566–1744, and the telephone
number for the OEI Docket is (202) 566–
1752).
FOR FURTHER INFORMATION CONTACT:
Tiffany Schermerhorn, Policy, Training
and Oversight Division, Office of
Acquisition Management, Mail Code
3802R, Environmental Protection
Agency, 1200 Pennsylvania Ave., NW.,
Washington, DC 20460; e-mail address:
schermerhorn.tiffany@epa.gov,
telephone (202) 564–9902.
SUPPLEMENTARY INFORMATION:
I. General Information
The proposed EPAAR additions are
necessary so that contracting officers
may provide simplified acquisition
procedures financing that is appropriate
or customary in the commercial
marketplace when purchasing
commercial items at or below the
simplified acquisition threshold. It does
not impose any new requirements
regarding submission of invoices or
vouchers since Agency contractors
currently submit invoices or vouchers
for payment of orders. The EPAAR
changes are consistent with the Federal
Acquisition Regulation.
as defined by the Small Business
Administration’s (SBA) regulations at 13
CFR 121.201; (2) a small governmental
jurisdiction that is a government of a
city, county, town, school district or
special district with a population of less
than 50,000; and (3) a small
organization that is any not-for-profit
enterprise which is independently
owned and operated and is not
dominant in its field.
After considering the economic
impacts of today’s proposed rule on
small entities, I certify that this action
will not have a significant economic
impact on a substantial number of small
entities. This proposed rule will not
impose any new requirements on small
entities.
List of Subjects in 48 CFR Parts 1532
and 1552
Government procurement.
Dated: February 15, 2006.
Judy S. Davis,
Director, Office of Acquisition Management.
II. Statutory and Executive Order
Reviews
For the reasons set forth in the
Preamble, Chapter 15 of Title 48 Code
of Federal Regulations, parts 1532 and
1552 are proposed to be amended as
follows:
1. The authority citation for 48 CFR
parts 1532 and 1552 continues to read
as follows:
A. Executive Order 12866
Authority: Sec. 205(c), 63 Stat. 390 as
amended, 40 U.S.C. 486(c).
B. Paperwork Reduction Act
This action does not impose an
information collection burden under the
provisions of the Paperwork Reduction
Act, 44 U.S.C. 3501 et seq. This rule
does not impose any new information
collection or other requirements on
Agency contractors.
wwhite on PROD1PC61 with PROPOSALS
C. Regulatory Flexibility Act
The Regulatory Flexibility Act (RFA)
generally requires an agency to prepare
a regulatory flexibility analysis of any
rule subject to notice and comment
rulemaking requirements under the
Administrative Procedure Act or any
other statute unless the agency certifies
that the rule will not have a significant
economic impact on a substantial
number of small entities. Small entities
include small businesses, small
organizations, and small governmental
jurisdictions.
For purposes of assessing the impacts
of today’s rule on small entities, small
entity is defined as: (1) A small business
16:18 Mar 10, 2006
officer shall submit a recommendation
for approval of financing terms, along
with the supporting rationale for the
action, to one level above the
contracting officer. Simplified
acquisition contracting officers (SACO)
shall forward recommendations through
their OAM Advisors to one level above
the contracting officer.
(d) Supporting rationale. Regardless
of dollar value, the contracting officer
shall document the file with supporting
rationale demonstrating that the
purchase meets the conditions of FAR
32.202–1(b)(1), (3) and (4).
(e) Administration. Regardless of
dollar value, the contracting officer is
responsible for ensuring that supplies or
services have been delivered. The
contracting officer shall document the
file with evidence of receipt of supplies
or services throughout the order period
as appropriate to the acquisition.
(f) Clause. The contracting officer
shall insert the clause at 1552.232–74,
Payments—Simplified Acquisition
Procedures Financing, in solicitations
and orders that will provide simplified
acquisition procedures financing.
PART 1552—SOLICITATION
PROVISIONS AND CONTRACT
CLAUSES
Jkt 208001
PART 1532—CONTRACT FINANCING
3. Add section 1552.232–74 to read as
follows.
2. Add section 1532.003 to read as
follows.
1552.232–74 Payments—Simplified
Acquisition Procedures Financing.
1532.003 Simplified acquisition
procedures financing.
It has been determined that this rule
is not a ‘‘significant regulatory action’’
under the terms of Executive Order
12866 and is therefore not subject to
OMB review.
VerDate Aug<31>2005
12661
As prescribed in 1532.003, insert the
following clause in solicitations and
orders that will provide simplified
acquisition procedures financing.
(a) Scope. This subpart provides for
authorization of advance and interim
payments on commercial item orders
not exceeding the simplified acquisition
threshold. Advance payments are
payments that are made prior to
performance. Interim payments are
payments that are made during the
order period according to a payment
schedule.
(b) Procedures for micropurchases.
Contracting officers may authorize
advance and interim payments on
orders for commercial items only at or
below the micro-purchase threshold.
(c) Procedures for purchases
exceeding micropurchase threshold.
Contracting officers must secure
approval at one level above the
contracting officer, on a case-by-case
basis, for advance and interim payments
on orders for commercial items
exceeding the micropurchase threshold
and not exceeding the simplified
acquisition threshold. The contracting
PO 00000
Frm 00028
Fmt 4702
Sfmt 4702
PAYMENTS—SIMPLIFIED ACQUISITION
PROCEDURES FINANCING (XXX 2006)
Simplified acquisition procedures
financing in the form of llllll
[contracting officer insert advance (prior to
performance) and/or interim (according to
payment schedule] payment(s) will be
provided under this commercial item order
in accordance with the payment schedule
below. If both advance and interim payments
are to be made, the payment schedule shown
below will specify the type of payment
provided for each line item.
The Government shall pay the contractor
as follows upon the submission of invoices
or vouchers approved by the project officer:
llllllll[insert payment schedule].
[FR Doc. E6–3518 Filed 3–10–06; 8:45 am]
BILLING CODE 6560–50–P
E:\FR\FM\13MRP1.SGM
13MRP1
Agencies
[Federal Register Volume 71, Number 48 (Monday, March 13, 2006)]
[Proposed Rules]
[Pages 12660-12661]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-3518]
=======================================================================
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
48 CFR Parts 1532 and 1552
[FRL-8044-3]
EPAAR Prescription and Clause--Simplified Acquisition Procedures
Financing
AGENCY: Environmental Protection Agency (EPA).
ACTION: Proposed rule.
-----------------------------------------------------------------------
SUMMARY: EPA is proposing to revise the EPA Acquisition Regulation
(EPAAR) Subparts 1532 and 1552 to implement a procedure for simplified
acquisition procedures financing. This proposed EPAAR revision will add
a prescription and clause for contracting officers to use when
approving advance or interim payments on simplified acquisitions. The
proposed prescription and clause apply to commercial item orders at or
below the simplified acquisition threshold. This action revises the
EPAAR, but does not impose any new requirements on Agency contractors.
The procedure will allow contractors to invoice for advance and interim
payments in accordance with standard commercial practices when
authorized by the contracting officer and identified in the clause
payment schedule.
DATES: Interested parties should submit comments in writing on or
before May 12, 2006.
ADDRESSES: Submit your comments, identified by Docket ID No. OARM-2006-
0126, by one of the following methods:
Federal eRulemaking Portal: https://www.regulations.gov.
Follow the on-line instructions for submitting comments.
Agency Web site: https://www.epa.gov/edocket. EDOCKET,
EPA's electronic public docket and comment system, is EPA's preferred
method for receiving comments. Follow the on-line instructions for
submitting comments.
E-mail: oei.docket@epa.gov.
Surface Mail: EPA Docket Center, Environmental Protection
Agency, Mailcode: 28221T, 1200 Pennsylvania Ave., NW., Washington, DC
20460. Attention Docket ID No. OARM-2006-0126.
Instructions: Direct your comments to Docket ID No. EPA's policy is
that all comments received will be included in the public docket
without change and may be made available online at https://www.epa.gov/
edocket, including any personal information provided, unless the
comment includes information claimed to be Confidential Business
Information (CBI) or other information whose disclosure is restricted
by statute. Do not submit information that you consider to be CBI or
otherwise protected through EDOCKET, regulations.gov, or e-mail. The
EPA EDOCKET and the federal regulations.gov Web sites are ``anonymous
access'' systems, which means EPA will not know your identity or
contact information unless you provide it in the body of your comment.
If you send an e-mail comment directly to EPA without going through
EDOCKET or regulations.gov, your e-mail address will be automatically
captured and included as part of the comment that is placed in the
public docket and made available on the Internet. If you submit an
electronic comment, EPA recommends that you include your name and other
contact information in the body of your comment and with any disk or
CD-ROM you submit. If EPA cannot read your comment due to technical
difficulties and cannot contact you for clarification, EPA may not be
able to consider your comment. Electronic files should avoid the use of
special characters, any form of encryption, and be free of any defects
or viruses. For additional information about EPA's public docket visit
EDOCKET on-line or see the Federal Register of May 31, 2002 (67 FR
38102).
Docket: All documents in the docket are listed in the EDOCKET index
at https://www.epa.gov/edocket. Although listed in the index, some
information is not publicly available, i.e., CBI or other information
whose disclosure is restricted by statute. Certain other material, such
as copyrighted material, is not placed on the Internet and will be
publicly available only in hard copy form. Publicly available docket
materials are available either electronically in EDOCKET or in hard
copy at the OEI Docket, EPA/DC, EPA West, Room B102, 1301 Constitution
Ave., NW., Washington, DC. The Public Reading Room is open from 8:30
a.m. to 4:30 p.m., Monday through Friday,
[[Page 12661]]
excluding legal holidays. The telephone number for the Public Reading
Room is (202) 566-1744, and the telephone number for the OEI Docket is
(202) 566-1752).
FOR FURTHER INFORMATION CONTACT: Tiffany Schermerhorn, Policy, Training
and Oversight Division, Office of Acquisition Management, Mail Code
3802R, Environmental Protection Agency, 1200 Pennsylvania Ave., NW.,
Washington, DC 20460; e-mail address: schermerhorn.tiffany@epa.gov,
telephone (202) 564-9902.
SUPPLEMENTARY INFORMATION:
I. General Information
The proposed EPAAR additions are necessary so that contracting
officers may provide simplified acquisition procedures financing that
is appropriate or customary in the commercial marketplace when
purchasing commercial items at or below the simplified acquisition
threshold. It does not impose any new requirements regarding submission
of invoices or vouchers since Agency contractors currently submit
invoices or vouchers for payment of orders. The EPAAR changes are
consistent with the Federal Acquisition Regulation.
II. Statutory and Executive Order Reviews
A. Executive Order 12866
It has been determined that this rule is not a ``significant
regulatory action'' under the terms of Executive Order 12866 and is
therefore not subject to OMB review.
B. Paperwork Reduction Act
This action does not impose an information collection burden under
the provisions of the Paperwork Reduction Act, 44 U.S.C. 3501 et seq.
This rule does not impose any new information collection or other
requirements on Agency contractors.
C. Regulatory Flexibility Act
The Regulatory Flexibility Act (RFA) generally requires an agency
to prepare a regulatory flexibility analysis of any rule subject to
notice and comment rulemaking requirements under the Administrative
Procedure Act or any other statute unless the agency certifies that the
rule will not have a significant economic impact on a substantial
number of small entities. Small entities include small businesses,
small organizations, and small governmental jurisdictions.
For purposes of assessing the impacts of today's rule on small
entities, small entity is defined as: (1) A small business as defined
by the Small Business Administration's (SBA) regulations at 13 CFR
121.201; (2) a small governmental jurisdiction that is a government of
a city, county, town, school district or special district with a
population of less than 50,000; and (3) a small organization that is
any not-for-profit enterprise which is independently owned and operated
and is not dominant in its field.
After considering the economic impacts of today's proposed rule on
small entities, I certify that this action will not have a significant
economic impact on a substantial number of small entities. This
proposed rule will not impose any new requirements on small entities.
List of Subjects in 48 CFR Parts 1532 and 1552
Government procurement.
Dated: February 15, 2006.
Judy S. Davis,
Director, Office of Acquisition Management.
For the reasons set forth in the Preamble, Chapter 15 of Title 48
Code of Federal Regulations, parts 1532 and 1552 are proposed to be
amended as follows:
1. The authority citation for 48 CFR parts 1532 and 1552 continues
to read as follows:
Authority: Sec. 205(c), 63 Stat. 390 as amended, 40 U.S.C.
486(c).
PART 1532--CONTRACT FINANCING
2. Add section 1532.003 to read as follows.
1532.003 Simplified acquisition procedures financing.
(a) Scope. This subpart provides for authorization of advance and
interim payments on commercial item orders not exceeding the simplified
acquisition threshold. Advance payments are payments that are made
prior to performance. Interim payments are payments that are made
during the order period according to a payment schedule.
(b) Procedures for micropurchases. Contracting officers may
authorize advance and interim payments on orders for commercial items
only at or below the micro-purchase threshold.
(c) Procedures for purchases exceeding micropurchase threshold.
Contracting officers must secure approval at one level above the
contracting officer, on a case-by-case basis, for advance and interim
payments on orders for commercial items exceeding the micropurchase
threshold and not exceeding the simplified acquisition threshold. The
contracting officer shall submit a recommendation for approval of
financing terms, along with the supporting rationale for the action, to
one level above the contracting officer. Simplified acquisition
contracting officers (SACO) shall forward recommendations through their
OAM Advisors to one level above the contracting officer.
(d) Supporting rationale. Regardless of dollar value, the
contracting officer shall document the file with supporting rationale
demonstrating that the purchase meets the conditions of FAR 32.202-
1(b)(1), (3) and (4).
(e) Administration. Regardless of dollar value, the contracting
officer is responsible for ensuring that supplies or services have been
delivered. The contracting officer shall document the file with
evidence of receipt of supplies or services throughout the order period
as appropriate to the acquisition.
(f) Clause. The contracting officer shall insert the clause at
1552.232-74, Payments--Simplified Acquisition Procedures Financing, in
solicitations and orders that will provide simplified acquisition
procedures financing.
PART 1552--SOLICITATION PROVISIONS AND CONTRACT CLAUSES
3. Add section 1552.232-74 to read as follows.
1552.232-74 Payments--Simplified Acquisition Procedures Financing.
As prescribed in 1532.003, insert the following clause in
solicitations and orders that will provide simplified acquisition
procedures financing.
PAYMENTS--SIMPLIFIED ACQUISITION PROCEDURES FINANCING (XXX 2006)
Simplified acquisition procedures financing in the form of ----
-------- [contracting officer insert advance (prior to performance)
and/or interim (according to payment schedule] payment(s) will be
provided under this commercial item order in accordance with the
payment schedule below. If both advance and interim payments are to
be made, the payment schedule shown below will specify the type of
payment provided for each line item.
The Government shall pay the contractor as follows upon the
submission of invoices or vouchers approved by the project officer:
----------------[insert payment schedule].
[FR Doc. E6-3518 Filed 3-10-06; 8:45 am]
BILLING CODE 6560-50-P