Download as PDF Federal Register / Vol. 71, No. 45 / Wednesday, March 8, 2006 / Notices comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, 385.214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents: Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘RECOMMENDATIONS FOR TERMS AND CONDITIONS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. A copy of any motion to intervene must also be served upon each representative of the Applicant specified in the particular application. p. Agency Comments: Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. q. Comments, protests and interventions may be filed electronically via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site at https://www.ferc.gov under the ‘‘eFiling’’ link. Magalie R. Salas, Secretary. [FR Doc. E6–3214 Filed 3–7–06; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket Nos. ER06–459–000, ER01–688– 002] IPP Energy LLC; Notice of Issuance of Order erjones on PROD1PC68 with NOTICES March 2, 2006. IPP Energy LLC (IPP) filed an application for market-based rate authority, with an accompanying rate schedule. The proposed market-based rate schedule provides for the sale of energy, capacity and ancillary at market- VerDate Aug<31>2005 15:53 Mar 07, 2006 Jkt 208001 based rates. IPP also requested waiver of various Commission regulations. In particular, IPP requested that the Commission grant blanket approval under 18 CFR part 34 of all future issuances of securities and assumptions of liability by IPP. On March 1, 2006, pursuant to delegated authority, the Director, Division of Tariffs and Market Development—West, granted the request for blanket approval under part 34. The Director’s order also stated that the Commission would publish a separate notice in the Federal Register establishing a period of time for the filing of protests. Accordingly, any person desiring to be heard or to protest the blanket approval of issuances of securities or assumptions of liability by IPP should file a motion to intervene or protest with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure. 18 CFR 385.211, 385.214 (2004). Notice is hereby given that the deadline for filing motions to intervene or protest is March 31, 2006. Absent a request to be heard in opposition by the deadline above, IPP is authorized to issue securities and assume obligations or liabilities as a guarantor, indorser, surety, or otherwise in respect of any security of another person; provided that such issuance or assumption is for some lawful object within the corporate purposes of IPP, compatible with the public interest, and is reasonably necessary or appropriate for such purposes. The Commission reserves the right to require a further showing that neither public nor private interests will be adversely affected by continued approval of IPP’s issuances of securities or assumptions of liability. Copies of the full text of the Director’s Order are available from the Commission’s Public Reference Room, 888 First Street, NE., Washington, DC 20426. The Order may also be viewed on the Commission’s Web site at https:// www.ferc.gov, using the eLibrary link. Enter the docket number excluding the last three digits in the docket number filed to access the document. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the PO 00000 Frm 00027 Fmt 4703 Sfmt 4703 11599 ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Magalie R. Salas, Secretary. [FR Doc. E6–3274 Filed 3–7–06; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. RP06–233–000] Iroquois Gas Transmission System, L.P.; Notice of Proposed Changes in FERC Gas Tariff February 28, 2006. Take notice that on February 24, 2006, Iroquois Gas Transmission System, L.P. (Iroquois) tendered for filing as part of its FERC Gas Tariff, First Revised Volume No. 1, First Revised Sheet No. 107D, to be effective on March 26, 2006. Iroquois proposes to remove language contained in section 28.22 of the General Terms and Conditions of its tariff that is related to shipper requests for discounts. Iroquois believes removal of such language is consistent with the Commission’s Second Order on Remand issued in Williston Basin Interstate Pipeline Company, 110 FERC ¶ 61,210 (2005). Iroquois states that copies of its filing were served on all jurisdictional customers and interested state regulatory agencies and all parties to the proceeding. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed in accordance with the provisions of section 154.210 of the Commission’s regulations (18 CFR 154.210). Anyone filing an intervention or protest must serve a copy of that document on the Applicant. Anyone filing an intervention or protest on or before the intervention or protest date need not serve motions to intervene or protests on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. E:\FR\FM\08MRN1.SGM 08MRN1

Agencies

[Federal Register Volume 71, Number 45 (Wednesday, March 8, 2006)]
[Notices]
[Page 11599]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-3274]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. ER06-459-000, ER01-688-002]


IPP Energy LLC; Notice of Issuance of Order

March 2, 2006.
    IPP Energy LLC (IPP) filed an application for market-based rate 
authority, with an accompanying rate schedule. The proposed market-
based rate schedule provides for the sale of energy, capacity and 
ancillary at market-based rates. IPP also requested waiver of various 
Commission regulations. In particular, IPP requested that the 
Commission grant blanket approval under 18 CFR part 34 of all future 
issuances of securities and assumptions of liability by IPP.
    On March 1, 2006, pursuant to delegated authority, the Director, 
Division of Tariffs and Market Development--West, granted the request 
for blanket approval under part 34. The Director's order also stated 
that the Commission would publish a separate notice in the Federal 
Register establishing a period of time for the filing of protests. 
Accordingly, any person desiring to be heard or to protest the blanket 
approval of issuances of securities or assumptions of liability by IPP 
should file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426, in 
accordance with Rules 211 and 214 of the Commission's Rules of Practice 
and Procedure. 18 CFR 385.211, 385.214 (2004).
    Notice is hereby given that the deadline for filing motions to 
intervene or protest is March 31, 2006.
    Absent a request to be heard in opposition by the deadline above, 
IPP is authorized to issue securities and assume obligations or 
liabilities as a guarantor, indorser, surety, or otherwise in respect 
of any security of another person; provided that such issuance or 
assumption is for some lawful object within the corporate purposes of 
IPP, compatible with the public interest, and is reasonably necessary 
or appropriate for such purposes.
    The Commission reserves the right to require a further showing that 
neither public nor private interests will be adversely affected by 
continued approval of IPP's issuances of securities or assumptions of 
liability.
    Copies of the full text of the Director's Order are available from 
the Commission's Public Reference Room, 888 First Street, NE., 
Washington, DC 20426. The Order may also be viewed on the Commission's 
Web site at https://www.ferc.gov, using the eLibrary link. Enter the 
docket number excluding the last three digits in the docket number 
filed to access the document. Comments, protests, and interventions may 
be filed electronically via the Internet in lieu of paper. See, 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's Web site 
under the ``e-Filing'' link. The Commission strongly encourages 
electronic filings.

Magalie R. Salas,
Secretary.
[FR Doc. E6-3274 Filed 3-7-06; 8:45 am]
BILLING CODE 6717-01-P