Notice of Application for Transfer of License, and Soliciting Comments, Motions To Intervene, and Protests, 11612-11613 [E6-3204]
Download as PDF
erjones on PROD1PC68 with NOTICES
11612
Federal Register / Vol. 71, No. 45 / Wednesday, March 8, 2006 / Notices
Motions to intervene and protests may
be filed electronically via the Internet in
lieu of paper. The Commission strongly
encourages electronic filings. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov) under the ‘‘eFiling’’ link.
k. This application has been accepted,
and is ready for environmental analysis.
l. The existing project consists of: (1)
The Cooper Lake Dam, a 52-foot-high
earth-and-rockfilled structure; (2) the
2,620-acre, 5-mile-long Cooper Lake
Reservoir; (3) two vertical-shaft Francis
turbines with a total capacity of 19.38
megawatts; (4) an intake structure
located on Cooper Lake; (5) a tunnel and
penstock extending 10,686 feet east
from the intake to the powerhouse; a (6)
6.3-mile-long, 69-kV transmission line
from the powerhouse to Quartz Creek
Substation; and 90.4-mile-long, 115-kV
transmission line from the Quartz Creek
Substation to Anchorage.
A new dam is proposed to be
constructed on Stetson Creek to divert
water into Cooper Lake to provide flow
releases for fish habitat improvements
in Cooper Creek.
m. Chugach Electric filed on August
31, 2005, a Settlement Agreement on
behalf of itself, and the U.S. Forest
Service, U.S. Fish and Wildlife Service,
National Park Service, National Marine
Fisheries Service, Kenaitze Indian Tribe,
Alaska Department of Fish and Game,
Alaska Department of Natural
Resources, The Fish for Cooper Creek
Coalition, Alaska Flyfishers Association,
and the Alaska Center for the
Environment. The purpose of the
Settlement Agreement is to resolve
among the signatories all issues
associated with issuance of a new
license for the project regarding
economic and power considerations,
water quality and temperature, instream
flows, fish habitat, visual resources,
recreation and cultural resources. The
Parties to the Settlement jointly request
the Commission accept and incorporate
into any new license for the project, the
protection, mitigation, and
enhancement measures and proposed
license articles stated in the Settlement
Agreement.
n. A copy of the application and
settlement agreement is on file with the
Commission and is available for public
inspection. This filing is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC online support
VerDate Aug<31>2005
15:53 Mar 07, 2006
Jkt 208001
at ferconlinesupport@ferc.gov or tollfree at 1–866–208–3676, or for Text
Telephone (TTY) call (202) 502–8659. A
copy is also available for inspection and
reproduction at the address in item h
above.
o. Anyone may submit a protest or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210,
385.211, and 385.214. In determining
the appropriate action to take, the
Commission will consider all protests
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any protests or
motions to intervene must be received
on or before the specified deadline date
for the particular application.
All filings must (1) bear in all capital
letters the title ‘‘PROTEST’’ or
‘‘MOTION TO INTERVENE;’’ (2) set
forth in the heading the name of the
applicant and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
protesting or intervening; and (4)
otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005.
All comments, recommendations, terms
and conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requiremens
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. A copy of all other filings
in reference to this application must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Magalie R. Salas,
Secretary.
[FR Doc. E6–3201 Filed 3–7–06; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application for Transfer of
License, and Soliciting Comments,
Motions To Intervene, and Protests
February 28, 2006.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Transfer of
License.
b. Project No.: 2935–018.
c. Date Filed: February 1, 2006.
d. Applicants: Enterprise Mill, LLC
(transferor), Melaver/Enterprise Mill,
LLC (transferee).
e. Name and Location of Project: The
Enterprise Mill Project is located on the
Augusta Canal and Savannah River in
Richmond County, Georgia.
f. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
g. Applicant Contacts: For the
transferor: Clayton B. Boardman, III,
Enterprise Mill, LLC, 1450 Greene
Street, Suite 500, Augusta, GA 30901,
(706) 262–4005.
For the transferee: Denis Blackburn,
CFO, Melaver/Enterprise Mill, LLC, 114
Barnard Street, Suite 2B, Savannah, GA
31401, (912) 236–0781.
h. FERC Contact: Robert Bell at (202)
502–6062.
i. Deadline for Filing Comments,
Protests, and Motions to Intervene: 30
days from issuance date.
All documents (original and eight
copies) should be filed with: Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
Comments, protests, and interventions
may be filed electronically via the
Internet in lieu of paper. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. The Commission
strongly encourages electronic filings.
Please include the Project Number on
any comments or motions filed.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing a document with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the documents
on that resource agency.
j. Description of Application: The
Applicants seek Commission approval
E:\FR\FM\08MRN1.SGM
08MRN1
erjones on PROD1PC68 with NOTICES
Federal Register / Vol. 71, No. 45 / Wednesday, March 8, 2006 / Notices
to transfer the license for the Enterprise
Mill Project from the Enterprise Mill,
LLC to Melaver/Enterprise Mill, LLC.
k. This filing is available for review at
the Commission in the Public Reference
Room or may be viewed on the
Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number (P–2935) in the
docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the addresses in item g
above.
l. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
m. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, 385.211,
385.214. In determining the appropriate
action to take, the Commission will
consider all protests or other comments
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
n. Filing and Service of Responsive
Documents: Any filings must bear in all
capital letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’, as applicable, and the
Project Number of the particular
application to which the filing refers.
Any of the above-named documents
must be filed by providing the original
and eight copies to: The Secretary,
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426. A copy of any motion to
intervene must also be served upon each
representative of the Applicants
specified in the particular application.
o. Agency Comments: Federal, state,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicants. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
VerDate Aug<31>2005
15:53 Mar 07, 2006
Jkt 208001
agency’s comments must also be sent to
the Applicants’ representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E6–3204 Filed 3–7–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Accepted for
Filing and Soliciting Comments,
Motions To Intervene, Protests,
Recommendations, and Terms and
Conditions
March 1, 2006.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Conduit
Exemption.
b. Project No.: 12649–000.
c. Date filed: January 30, 2006.
d. Applicant: East Bay Municipal
Utility District.
e. Name of Project: Briones Energy
Recovery Project.
f. Location: The Briones Energy
Recovery Project would be located in
the existing pipeline, which supplies
the Orinda Water Treatment Plant in
Contra Costa County, California.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791a–825r.
h. Applicant Contact: Mr. Dennis
Diemer, East Bay Municipal Utility
District, 375 Eleventh Street, Oakland,
CA 94607, (866) 403–2683.
i. FERC Contact: Robert Bell, (202)
502–6062.
j. Status of Environmental Analysis:
This application is ready for
environmental analysis at this time, and
the Commission is requesting
comments, reply comments,
recommendations, terms and
conditions, and prescriptions.
k. Deadline for filing responsive
documents: The Commission directs,
pursuant to section 4.34(b) of the
Regulations (see Order No. 533 issued
May 8, 1991, 56 FR 23108, May 20,
1991) that all comments, motions to
intervene, protests, recommendations,
terms and conditions, and prescriptions
concerning the application be filed with
the Commission by April 30, 2006. All
reply comments must be filed with the
Commission by May 15, 2006.
Comments, protests, and
interventions may be filed electronically
via the Internet in lieu of paper: See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
PO 00000
Frm 00041
Fmt 4703
Sfmt 4703
11613
site under the ‘‘e-Filing’’ link. The
Commission strongly encourages
electronic filings.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
l. Description of Project: The proposed
small conduit hydroelectric project
would consist of a proposed 1-megawatt
generating unit in the 36-inch diameter
pipe at the Briones Pumping Plant. The
average annual energy production
would be 1,364 megawatt-hours.
m. This filing is available for review
and reproduction at the Commission in
the Public Reference Room, Room 2A,
888 First Street, NE., Washington, DC
20426. The filing may also be viewed on
the Web at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number, P–12644, in the docket number
field to access the document. For
assistance, call toll-free 1–866–208–
3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for review and reproduction at
the address in item h above.
n. Development Application: Any
qualified applicant desiring to file a
competing application must submit to
the Commission, on or before the
specified deadline date for the
particular application, a competing
development application, or a notice of
intent to file such an application.
Submission of a timely notice of intent
allows an interested person to file the
competing development application no
later than 120 days after the specified
deadline date for the particular
application. Applications for
preliminary permits will not be
accepted in response to this notice.
o. Notice of Intent: A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit a competing development
application. A notice of intent must be
served on the applicant(s) named in this
public notice.
p. Protests or Motions to Intervene:
Anyone may submit a protest or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210,
385.211, and 385.214. In determining
the appropriate action to take, the
E:\FR\FM\08MRN1.SGM
08MRN1
Agencies
[Federal Register Volume 71, Number 45 (Wednesday, March 8, 2006)]
[Notices]
[Pages 11612-11613]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-3204]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Application for Transfer of License, and Soliciting
Comments, Motions To Intervene, and Protests
February 28, 2006.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Application Type: Transfer of License.
b. Project No.: 2935-018.
c. Date Filed: February 1, 2006.
d. Applicants: Enterprise Mill, LLC (transferor), Melaver/
Enterprise Mill, LLC (transferee).
e. Name and Location of Project: The Enterprise Mill Project is
located on the Augusta Canal and Savannah River in Richmond County,
Georgia.
f. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
g. Applicant Contacts: For the transferor: Clayton B. Boardman,
III, Enterprise Mill, LLC, 1450 Greene Street, Suite 500, Augusta, GA
30901, (706) 262-4005.
For the transferee: Denis Blackburn, CFO, Melaver/Enterprise Mill,
LLC, 114 Barnard Street, Suite 2B, Savannah, GA 31401, (912) 236-0781.
h. FERC Contact: Robert Bell at (202) 502-6062.
i. Deadline for Filing Comments, Protests, and Motions to
Intervene: 30 days from issuance date.
All documents (original and eight copies) should be filed with:
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426. Comments, protests, and
interventions may be filed electronically via the Internet in lieu of
paper. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the
Commission's Web site under the ``e-Filing'' link. The Commission
strongly encourages electronic filings. Please include the Project
Number on any comments or motions filed.
The Commission's Rules of Practice and Procedure require all
intervenors filing a document with the Commission to serve a copy of
that document on each person on the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the documents on that resource agency.
j. Description of Application: The Applicants seek Commission
approval
[[Page 11613]]
to transfer the license for the Enterprise Mill Project from the
Enterprise Mill, LLC to Melaver/Enterprise Mill, LLC.
k. This filing is available for review at the Commission in the
Public Reference Room or may be viewed on the Commission's Web site at
https://www.ferc.gov using the ``eLibrary'' link. Enter the docket
number (P-2935) in the docket number field to access the document. For
assistance, call toll-free 1-866-208-3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is
also available for inspection and reproduction at the addresses in item
g above.
l. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
m. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210,
385.211, 385.214. In determining the appropriate action to take, the
Commission will consider all protests or other comments filed, but only
those who file a motion to intervene in accordance with the
Commission's Rules may become a party to the proceeding. Any comments,
protests, or motions to intervene must be received on or before the
specified comment date for the particular application.
n. Filing and Service of Responsive Documents: Any filings must
bear in all capital letters the title ``COMMENTS'', ``PROTEST'', or
``MOTION TO INTERVENE'', as applicable, and the Project Number of the
particular application to which the filing refers. Any of the above-
named documents must be filed by providing the original and eight
copies to: The Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426. A copy of any motion to
intervene must also be served upon each representative of the
Applicants specified in the particular application.
o. Agency Comments: Federal, state, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the Applicants.
If an agency does not file comments within the time specified for
filing comments, it will be presumed to have no comments. One copy of
an agency's comments must also be sent to the Applicants'
representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E6-3204 Filed 3-7-06; 8:45 am]
BILLING CODE 6717-01-P