Port Barre Investments, L.L.C. (d/b/a Bobcat Gas Storage); Notice of Intent To Prepare an Environmental Assessment for the Proposed Bobcat Gas Storage Project and Request for Comments on Environmental Issues, 11606-11608 [E6-3194]
Download as PDF
11606
Federal Register / Vol. 71, No. 45 / Wednesday, March 8, 2006 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
Commission
[Project No. 11858–002]
[Docket No. CP06–66–000]
The Nevada Power Company, Inc.;
Elsinore Valley Municipal Water
District; California; Notice of Intention
To Hold Public Meetings for
Discussion of the Draft Environmental
Impact Statement for the Lake Elsinore
Advanced Pumped Storage Project
Port Barre Investments, L.L.C. (d/b/a
Bobcat Gas Storage); Notice of Intent
To Prepare an Environmental
Assessment for the Proposed Bobcat
Gas Storage Project and Request for
Comments on Environmental Issues
March 1, 2006.
erjones on PROD1PC68 with NOTICES
DEPARTMENT OF ENERGY
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of a
proposal by Port Barre Investments,
L.L.C. (d/b/a Bobcat Gas Storage
(Bobcat)) to construct a new salt cavern
natural gas storage facility in St. Landry
Parish, Louisiana.1 The Bobcat Gas
Storage Project would provide
approximately 12 billion cubic feet of
working natural gas storage capacity,
capable of injecting gas at maximum
rates of up to 900 million cubic feet per
day (MMcfd) and delivering gas at
maximum rates of up to 1,200 MMcfd.
The facilities would include two
solution mined storage caverns, a 37,880
horsepower (hp) compressor station, a
leaching plant, brine disposal facilities,
approximately 18.1 miles of pipeline,
and metering and regulating stations.
This notice announces the opening of
the scoping period that will be used to
gather environmental input from the
public and interested agencies on the
project. Please note that the scoping
comments are requested by March 31,
2006.
This notice is being sent to potentially
affected landowners; Federal, state, and
local government agencies; elected
officials; environmental and public
interest groups; Native American Tribes,
other interested parties; local libraries
and newspapers. State and local
government representatives are asked to
notify their constituents of this planned
project and encourage them to comment
on their areas of concern.
If you are a landowner receiving this
notice, you may be contacted by a
Bobcat company representative about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the project is
approved by the Commission, that
approval conveys with it the right of
On February 17, 2006, the
Commission staff delivered the Lake
Elsinore Advanced Pumped Storage
(LEAPS) Project Draft Environmental
Impact Statement (draft EIS) to the
Environmental Protection Agency and
mailed it to resource and land
management agencies, interested
organizations, and individuals.
The draft EIS was noticed in the
Federal Register on February 24, 2006,
(71 FR 9819) and comments are due
April 25, 2006. The draft EIS evaluates
the environmental consequences and
developmental benefits of issuing an
original license for building, operating
and maintaining the LEAPS Project,
located in Riverside County, California.
The project would occupy 2,412 acres of
federal lands, including lands managed
by the Cleveland National Forest.
Besides evaluating the applicant’s
proposal, the draft EIS evaluates a FERC
staff proposal and the no-action
alternative.
Two public meetings, which will be
recorded by an official stenographer, are
scheduled as follows.
Date: Tuesday, April 4, 2006.
Time: 7–10 p.m. (PST).
Place: San Juan Capistrano
Community Center, 25925 Camino del
Avion, San Juan Capistrano, CA 92675.
Date: Wednesday, April 5, 2006.
Time: 7–10 p.m. (PST).
Place: Lake Elsinore Cultural Center,
183 N. Main Street, Lake Elsinore, CA
92530.
At these meetings, resource agency
personnel and other interested persons
will have the opportunity to provide
oral and written comments and
recommendations regarding the DEIS for
the Commission’s public record.
For further information, please
contact Jim Fargo at e-mail address
james.fargo@ferc.gov, or by telephone at
(202) 502–6095.
Magalie R. Salas,
Secretary.
[FR Doc. E6–3212 Filed 3–7–06; 8:45 am]
BILLING CODE 6717–01–P
VerDate Aug<31>2005
15:53 Mar 07, 2006
Jkt 208001
February 28, 2006.
1 Bobcat’s application was filed with the
Commission under section 7 of the Natural Gas Act
and Part 157 of the Commission’s regulations.
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
eminent domain. Therefore, if easement
negotiations fail to produce an
agreement, the natural gas company
could initiate condemnation
proceedings in accordance with state
law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC Web site (https://
www.ferc.gov). This fact sheet addresses
a number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings.
Summary of the Proposed Project
Bobcat proposes to construct, own,
and operate a high-deliverability natural
gas storage project on an 84-acre parcel
of land leased by Bobcat, located about
2.2 miles east of the Town of Port Barre,
Louisiana. Two caverns would be
solution mined in the Port Barre Salt
Dome in four phases, over an
approximate five-year time span. The
project would include construction of
the following:
(1) Gas Storage Site, including:
• Eight (8) 4,735 horsepower
compressors, dehydration and
appurtenant facilities (Bobcat
Compressor Station);
• A leaching plant;
• 0.5 mile of non-jurisdictional
electric distribution line;
• 2 freshwater and 2 cavern wells;
and
• 0.5 mile of 16-inch-diameter
freshwater pipeline.
(2) Brine Disposal Site, including
three brine disposal wells;
(3) 1.5 miles of 16-inch-diameter brine
disposal pipeline;
(4) 16.1 miles of 24-inch-diameter
natural gas pipeline and appurtenances;
and
(5) 5 interstate and 1 intrastate
pipeline system interconnects, each
with a regulator/meter station.
The location of the project facilities is
shown in Appendix 1.2
Land Requirements for Construction
Construction of the proposed facilities
would require about 261.9 acres of land.
Following construction, about 104.3
acres would be maintained as new
aboveground facility sites and right-of2 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of all
appendices, other than appendix 1 (maps), are
available on the Commission’s Web site at the
‘‘eLibrary’’ link or from the Commission’s Public
Reference Room, 888 First Street, NE., Washington,
DC 20426, or call (202) 502–8371. For instructions
on connecting to eLibrary refer to the last page of
this notice. Copies of the appendices were sent to
all those receiving this notice in the mail.
E:\FR\FM\08MRN1.SGM
08MRN1
Federal Register / Vol. 71, No. 45 / Wednesday, March 8, 2006 / Notices
way. The remaining 157.6 acres of land
would be restored and allowed to revert
to its former use.
The EA Process
We 3 are preparing this EA to comply
with the National Environmental Policy
Act (NEPA) which requires the
Commission to take into account the
environmental impacts that could result
from an action whenever it considers
the issuance of a Certificate of Public
Convenience and Necessity. NEPA also
requires us to discover and address
concerns the public may have about
proposals. This process is referred to as
‘‘scoping’’. The main goal of the scoping
process is to focus the analysis in the
EA on the important environmental
issues. By this Notice of Intent, the
Commission staff requests public
comments on the scope of the issues to
address in the EA. All comments
received are considered during the
preparation of the EA.
By this notice, we are also asking
Federal, state, and local agencies with
jurisdiction and/or special expertise
with respect to environmental issues to
formally cooperate with us in the
preparation of the EA. Agencies that
would like to request cooperating status
should follow the instructions for filing
comments below.
Our independent analysis of the
issues will be in the EA. Depending on
the comments received during the
scoping process, the EA may be
published and mailed to Federal, state,
and local agencies, public interest
groups, interested individuals, affected
landowners, newspapers, libraries, and
the Commission’s official service list for
this proceeding. A comment period will
be allotted for review if the EA is
published. We will consider all
comments on the EA before we make
our recommendations to the
Commission.
erjones on PROD1PC68 with NOTICES
Currently Identified Environmental
Issues
In the EA, we will discuss impacts
that could occur as a result of the
construction and operation of the
project. We will also evaluate
reasonable alternatives to the proposed
project or portions of the project.
We have already identified several
issues that we think deserve attention
based on a preliminary review of the
proposed facilities and the
environmental information provided by
Bobcat. This preliminary list of issues
3 ’’We’’, ‘‘us’’, and ‘‘our’’ refer to the
environmental staff of the Office of Energy Projects
(OEP).
VerDate Aug<31>2005
15:53 Mar 07, 2006
Jkt 208001
may be changed based on your
comments and our analysis.
Project-related impact on:
• Noise sensitive areas (i.e.,
residences) located in proximity to
construction operations and the
proposed compressor facility;
• 12.0 acres of wetlands;
• 171.5 acres of agricultural land;
• 3 federally-listed threatened and
endangered species potentially in the
project area;
• 7 waterbody crossings; and
• The Chicot sole source aquifer.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
By becoming a commentor, your
concerns will be addressed in the EA
and considered by the Commission. You
should focus on the potential
environmental effects of the proposal,
alternatives to the proposal (including
alternative locations and routes), and
measures to avoid or lessen
environmental impact. The more
specific your comments, the more useful
they will be. Please carefully follow
these instructions to ensure that your
comments are received in time and
properly recorded:
• Send an original and two copies of
your letter to: Magalie R. Salas,
Secretary, Federal Energy Regulatory
Commission, 888 First St., NE., Room
1A, Washington, DC 20426.
• Label one copy of the comments for
the attention of Gas Branch 3.
• Reference Docket Number CP06–
66–000.
• Mail your comments so that they
will be received in Washington, DC on
or before March 31, 2006.
Please note that the Commission
strongly encourages electronic filing of
any comments or interventions or
protests to this proceeding. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site at
https://www.ferc.gov under the ‘‘eFiling’’ link and the link to the User’s
Guide. Before you can file comments,
you will need to create and account
which can be created online.
Site Visit
On March 21, 2006, the OEP staff will
conduct a pre-certification site visit of
the planned Bobcat Gas Storage Project.
We will view the proposed facility
locations and pipeline route.
Examination will be by automobile and
on foot. Representatives of Bobcat will
be accompanying the OEP staff.
All interested parties may attend.
Those planning to attend must provide
their own transportation and should
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
11607
meet at 9 a.m. (CST) in the lobby of the
Holiday Inn, 5696 I–49 North Service
Road, Opelousas, Louisiana on March
21, 2006.
For additional information, please
contact the Commission’s Office of
External Affairs at 1–866–208–FERC
(3372).
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an official party to the
proceeding known as an ‘‘intervenor’’.
Intervenors play a more formal role in
the process. Among other things,
intervenors have the right to receive
copies of case-related Commission
documents and filings by other
intervenors. Likewise, each intervenor
must send one electronic copy (using
the Commission’s eFiling system) or 14
paper copies of its filings to the
Secretary of the Commission and must
send a copy of its filings to all other
parties on the Commission’s service list
for this proceeding. If you want to
become an intervenor you must file a
motion to intervene according to Rule
214 of the Commission’s Rules of
Practice and Procedure (18 CFR
385.214, see Appendix 2).4 Only
intervenors have the right to seek
rehearing of the Commission’s decision.
Affected landowners and parties with
environmental concerns may be granted
intervenor status upon showing good
cause by stating that they have a clear
and direct interest in this proceeding
which would not be adequately
represented by any other parties. You do
not need intervenor status to have your
environmental comments considered.
Environmental Mailing List
If you wish to remain on our
environmental mailing list, please
return the Information Request Form
included in Appendix 2. If you do not
return this form, you will be removed
from our mailing list.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the FERC
Internet Web site (https://www.ferc.gov)
using the eLibrary link. Click on the
eLibrary link, click on ‘‘General Search’’
and enter the docket number excluding
the last three digits in the Docket
Number field. Be sure you have selected
an appropriate date range. For
assistance, please contact FERC Online
4 Interventions may also be filed electronically via
the Internet in lieu of paper. See the previous
discussion on filing comments electronically.
E:\FR\FM\08MRN1.SGM
08MRN1
11608
Federal Register / Vol. 71, No. 45 / Wednesday, March 8, 2006 / Notices
Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TYY,
contact (202) 502–8659. The eLibrary
link also provides access to the texts of
formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to https://
www.ferc.gov/esubscribenow.htm.
Magalie R. Salas,
Secretary.
[FR Doc. E6–3194 Filed 3–7–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Accepted for
Filing and Soliciting Motions To
Intervene, Protests, and Comments
erjones on PROD1PC68 with NOTICES
February 28, 2006.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
Permit.
b. Project No.: 12636–000.
c. Date filed: January 3, 2006.
d. Applicant: Mohawk Hydro
Corporation.
e. Name of Project: Middle Mohawk
Project.
f. Location: On the Mohawk River, in
Montgomery and Schenectady Counties,
New York. The existing facilities are
owned by New York State Canal
Corporation.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. James A.
Besha, P.E., Albany Engineering
Corporation, Agent for Mohawk Hydro
Corp., 455 New Karner Road, Albany,
NY 12205, (518) 456–7712.
i. FERC Contact: Robert Bell (202)
219–2806.
j. Deadline for filing motions to
intervene, protests and comments: 60
days from the issuance date of this
notice.
All documents (original and eight
copies) should be filed with: Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
VerDate Aug<31>2005
15:53 Mar 07, 2006
Jkt 208001
Street, NE., Washington, DC 20426.
Comments, motions to intervene, and
protests may be electronically filed via
the Internet in lieu of paper. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site at
https://www.ferc.fed.us/efi/doorbell.htm.
Please include the project number (P–
12636–000) on any comments or
motions filed.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. Description of Project: The
proposed run-of-river project would
consist of the following eight
Developments:
Lock #8 Development: (1) An existing
530-foot-long, 14-foot-high bridge type
dam constructed primarily of steel, (2)
an existing reservoir having a surface
area of 336 acres, with a storage capacity
of 3,360 acre-feet and a normal water
surface elevation of 224 feet USGS, (3)
a proposed intake structure, (4) two
proposed powerhouses containing 18
generating units having a total installed
capacity of 6 MW, (5) a proposed 1,800foot-long, 34.5 kV transmission line, and
(6) appurtenant facilities.
The development would have an
annual generation of 16 gigawatt-hours
which would be sold to a local utility.
Lock #9 Development: (1) An existing
530-foot-long, 15-foot-high bridge type
dam constructed primarily of steel, (2)
an existing reservoir having a surface
area of 428 acres, with a storage capacity
of 4,280 acre-feet and a normal water
surface elevation of 239 feet USGS, (3)
a proposed intake structure, (4) two
proposed powerhouses containing 18
generating units having a total installed
capacity of 6 MW, (5) a proposed 200foot-long, 13.2 kV transmission line, and
(6) appurtenant facilities.
The development would have an
annual generation of 17.6 gigawatthours which would be sold to a local
utility.
Lock #10 Development: (1) An
existing 500-foot-long, 15-foot-high
bridge type dam constructed primarily
of steel, (2) an existing reservoir having
a surface area of 414 acres, with a
storage capacity of 4,140 acre-feet and a
normal water surface elevation of 254
feet USGS, (3) a proposed intake
structure, (4) two proposed
powerhouses containing 18 generating
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
units having a total installed capacity of
6 MW, (5) a proposed 1,500-foot-long,
115 kV transmission line, and (6)
appurtenant facilities.
The development would have an
annual generation of 17.3 gigawatthours which would be sold to a local
utility.
Lock #11 Development: (1) An
existing 588-foot-long, 12-foot-high
bridge type dam constructed primarily
of steel, (2) an existing reservoir having
a surface area of 414 acres, with a
storage capacity of 4,140 acre-feet and a
normal water surface elevation of 266
feet USGS, (3) a proposed intake
structure, (4) two proposed
powerhouses containing 18 generating
units having a total installed capacity of
6 MW, (5) a proposed 700-foot-long,
34.5 kV transmission line, and (6)
appurtenant facilities.
The development would have an
annual generation of 16.1 gigawatthours which would be sold to a local
utility.
Lock #12 Development: (1) An
existing 460-foot-long, 11-foot-high
bridge type dam constructed primarily
of steel, (2) an existing reservoir having
a surface area of 737 acres, with a
storage capacity of 7,370 acre-feet and a
normal water surface elevation of 277
feet USGS, (3) a proposed intake
structure, (4) two proposed
powerhouses containing 18 generating
units having a total installed capacity of
6 MW, (5) a proposed 400-foot-long,
13.2 kV transmission line, and (6)
appurtenant facilities.
The development would have an
annual generation of 11.7 gigawatthours which would be sold to a local
utility.
Lock #13 Development: (1) An
existing 370-foot-long, 8-foot-high
bridge type dam constructed primarily
of steel, (2) an existing reservoir having
a surface area of 464 acres, with a
storage capacity of 4,640 acre-feet and a
normal water surface elevation of 285
feet USGS, (3) a proposed intake
structure, (4) a proposed powerhouse
containing 9 generating units having a
total installed capacity of 3 MW, (5) a
proposed 200-foot-long, 13.2 kV
transmission line, and (6) appurtenant
facilities.
The development would have an
annual generation of 7.3 gigawatt-hours
which would be sold to a local utility.
Lock #14 Development: (1) An
existing 430-foot-long, 8-foot-high
bridge type dam constructed primarily
of steel, (2) an existing reservoir having
a surface area of 219 acres, with a
storage capacity of 2,190 acre-feet and a
normal water surface elevation of 293
feet USGS, (3) a proposed intake
E:\FR\FM\08MRN1.SGM
08MRN1
Agencies
[Federal Register Volume 71, Number 45 (Wednesday, March 8, 2006)]
[Notices]
[Pages 11606-11608]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-3194]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP06-66-000]
Port Barre Investments, L.L.C. (d/b/a Bobcat Gas Storage); Notice
of Intent To Prepare an Environmental Assessment for the Proposed
Bobcat Gas Storage Project and Request for Comments on Environmental
Issues
February 28, 2006.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of a proposal by Port Barre
Investments, L.L.C. (d/b/a Bobcat Gas Storage (Bobcat)) to construct a
new salt cavern natural gas storage facility in St. Landry Parish,
Louisiana.\1\ The Bobcat Gas Storage Project would provide
approximately 12 billion cubic feet of working natural gas storage
capacity, capable of injecting gas at maximum rates of up to 900
million cubic feet per day (MMcfd) and delivering gas at maximum rates
of up to 1,200 MMcfd. The facilities would include two solution mined
storage caverns, a 37,880 horsepower (hp) compressor station, a
leaching plant, brine disposal facilities, approximately 18.1 miles of
pipeline, and metering and regulating stations.
---------------------------------------------------------------------------
\1\ Bobcat's application was filed with the Commission under
section 7 of the Natural Gas Act and Part 157 of the Commission's
regulations.
---------------------------------------------------------------------------
This notice announces the opening of the scoping period that will
be used to gather environmental input from the public and interested
agencies on the project. Please note that the scoping comments are
requested by March 31, 2006.
This notice is being sent to potentially affected landowners;
Federal, state, and local government agencies; elected officials;
environmental and public interest groups; Native American Tribes, other
interested parties; local libraries and newspapers. State and local
government representatives are asked to notify their constituents of
this planned project and encourage them to comment on their areas of
concern.
If you are a landowner receiving this notice, you may be contacted
by a Bobcat company representative about the acquisition of an easement
to construct, operate, and maintain the proposed facilities. The
company would seek to negotiate a mutually acceptable agreement.
However, if the project is approved by the Commission, that approval
conveys with it the right of eminent domain. Therefore, if easement
negotiations fail to produce an agreement, the natural gas company
could initiate condemnation proceedings in accordance with state law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' is available for
viewing on the FERC Web site (https://www.ferc.gov). This fact sheet
addresses a number of typically asked questions, including the use of
eminent domain and how to participate in the Commission's proceedings.
Summary of the Proposed Project
Bobcat proposes to construct, own, and operate a high-
deliverability natural gas storage project on an 84-acre parcel of land
leased by Bobcat, located about 2.2 miles east of the Town of Port
Barre, Louisiana. Two caverns would be solution mined in the Port Barre
Salt Dome in four phases, over an approximate five-year time span. The
project would include construction of the following:
(1) Gas Storage Site, including:
Eight (8) 4,735 horsepower compressors, dehydration and
appurtenant facilities (Bobcat Compressor Station);
A leaching plant;
0.5 mile of non-jurisdictional electric distribution line;
2 freshwater and 2 cavern wells; and
0.5 mile of 16-inch-diameter freshwater pipeline.
(2) Brine Disposal Site, including three brine disposal wells;
(3) 1.5 miles of 16-inch-diameter brine disposal pipeline;
(4) 16.1 miles of 24-inch-diameter natural gas pipeline and
appurtenances; and
(5) 5 interstate and 1 intrastate pipeline system interconnects,
each with a regulator/meter station.
The location of the project facilities is shown in Appendix 1.\2\
---------------------------------------------------------------------------
\2\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies of all appendices, other
than appendix 1 (maps), are available on the Commission's Web site
at the ``eLibrary'' link or from the Commission's Public Reference
Room, 888 First Street, NE., Washington, DC 20426, or call (202)
502-8371. For instructions on connecting to eLibrary refer to the
last page of this notice. Copies of the appendices were sent to all
those receiving this notice in the mail.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would require about 261.9
acres of land. Following construction, about 104.3 acres would be
maintained as new aboveground facility sites and right-of-
[[Page 11607]]
way. The remaining 157.6 acres of land would be restored and allowed to
revert to its former use.
The EA Process
We \3\ are preparing this EA to comply with the National
Environmental Policy Act (NEPA) which requires the Commission to take
into account the environmental impacts that could result from an action
whenever it considers the issuance of a Certificate of Public
Convenience and Necessity. NEPA also requires us to discover and
address concerns the public may have about proposals. This process is
referred to as ``scoping''. The main goal of the scoping process is to
focus the analysis in the EA on the important environmental issues. By
this Notice of Intent, the Commission staff requests public comments on
the scope of the issues to address in the EA. All comments received are
considered during the preparation of the EA.
---------------------------------------------------------------------------
\3\ ''We'', ``us'', and ``our'' refer to the environmental staff
of the Office of Energy Projects (OEP).
---------------------------------------------------------------------------
By this notice, we are also asking Federal, state, and local
agencies with jurisdiction and/or special expertise with respect to
environmental issues to formally cooperate with us in the preparation
of the EA. Agencies that would like to request cooperating status
should follow the instructions for filing comments below.
Our independent analysis of the issues will be in the EA. Depending
on the comments received during the scoping process, the EA may be
published and mailed to Federal, state, and local agencies, public
interest groups, interested individuals, affected landowners,
newspapers, libraries, and the Commission's official service list for
this proceeding. A comment period will be allotted for review if the EA
is published. We will consider all comments on the EA before we make
our recommendations to the Commission.
Currently Identified Environmental Issues
In the EA, we will discuss impacts that could occur as a result of
the construction and operation of the project. We will also evaluate
reasonable alternatives to the proposed project or portions of the
project.
We have already identified several issues that we think deserve
attention based on a preliminary review of the proposed facilities and
the environmental information provided by Bobcat. This preliminary list
of issues may be changed based on your comments and our analysis.
Project-related impact on:
Noise sensitive areas (i.e., residences) located in
proximity to construction operations and the proposed compressor
facility;
12.0 acres of wetlands;
171.5 acres of agricultural land;
3 federally-listed threatened and endangered species
potentially in the project area;
7 waterbody crossings; and
The Chicot sole source aquifer.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. By becoming a commentor, your
concerns will be addressed in the EA and considered by the Commission.
You should focus on the potential environmental effects of the
proposal, alternatives to the proposal (including alternative locations
and routes), and measures to avoid or lessen environmental impact. The
more specific your comments, the more useful they will be. Please
carefully follow these instructions to ensure that your comments are
received in time and properly recorded:
Send an original and two copies of your letter to: Magalie
R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First
St., NE., Room 1A, Washington, DC 20426.
Label one copy of the comments for the attention of Gas
Branch 3.
Reference Docket Number CP06-66-000.
Mail your comments so that they will be received in
Washington, DC on or before March 31, 2006.
Please note that the Commission strongly encourages electronic
filing of any comments or interventions or protests to this proceeding.
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's
Web site at https://www.ferc.gov under the ``e-Filing'' link and the
link to the User's Guide. Before you can file comments, you will need
to create and account which can be created online.
Site Visit
On March 21, 2006, the OEP staff will conduct a pre-certification
site visit of the planned Bobcat Gas Storage Project. We will view the
proposed facility locations and pipeline route. Examination will be by
automobile and on foot. Representatives of Bobcat will be accompanying
the OEP staff.
All interested parties may attend. Those planning to attend must
provide their own transportation and should meet at 9 a.m. (CST) in the
lobby of the Holiday Inn, 5696 I-49 North Service Road, Opelousas,
Louisiana on March 21, 2006.
For additional information, please contact the Commission's Office
of External Affairs at 1-866-208-FERC (3372).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an official party to the proceeding known as an
``intervenor''. Intervenors play a more formal role in the process.
Among other things, intervenors have the right to receive copies of
case-related Commission documents and filings by other intervenors.
Likewise, each intervenor must send one electronic copy (using the
Commission's eFiling system) or 14 paper copies of its filings to the
Secretary of the Commission and must send a copy of its filings to all
other parties on the Commission's service list for this proceeding. If
you want to become an intervenor you must file a motion to intervene
according to Rule 214 of the Commission's Rules of Practice and
Procedure (18 CFR 385.214, see Appendix 2).\4\ Only intervenors have
the right to seek rehearing of the Commission's decision.
---------------------------------------------------------------------------
\4\ Interventions may also be filed electronically via the
Internet in lieu of paper. See the previous discussion on filing
comments electronically.
---------------------------------------------------------------------------
Affected landowners and parties with environmental concerns may be
granted intervenor status upon showing good cause by stating that they
have a clear and direct interest in this proceeding which would not be
adequately represented by any other parties. You do not need intervenor
status to have your environmental comments considered.
Environmental Mailing List
If you wish to remain on our environmental mailing list, please
return the Information Request Form included in Appendix 2. If you do
not return this form, you will be removed from our mailing list.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at 1-866-208-FERC or on the
FERC Internet Web site (https://www.ferc.gov) using the eLibrary link.
Click on the eLibrary link, click on ``General Search'' and enter the
docket number excluding the last three digits in the Docket Number
field. Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online
[[Page 11608]]
Support at FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676,
or for TYY, contact (202) 502-8659. The eLibrary link also provides
access to the texts of formal documents issued by the Commission, such
as orders, notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Magalie R. Salas,
Secretary.
[FR Doc. E6-3194 Filed 3-7-06; 8:45 am]
BILLING CODE 6717-01-P