PJM Interconnection, LLC; PJM Interconnection, LLC; District of Columbia Public Service Commission; PJM Interconnection, LLC; PJM Interconnection, LLC; American Electric Power Service Corporation; Supplemental Notice Regarding RPM Technical Conference, 6474 [E6-1701]
Download as PDF
6474
Federal Register / Vol. 71, No. 26 / Wednesday, February 8, 2006 / Notices
on the Commission’s Web site under ‘‘efiling’’ link. The Commission strongly
encourages electronic filing.
s. Filing and Service of Responsive
Documents: Any filings must bear in all
capital letters the title ‘‘COMMENTS’’,
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’, as
applicable, and the Project Number of
the particular application to which the
filing refers. Any of the above-named
documents must be filed by providing
the original and the number of copies
provided by the Commission’s
regulations to: The Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
A copy of any motion to intervene must
also be served upon each representative
of the Applicant specified in the
particular application.
t. Agency Comments: Federal, state,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E6–1670 Filed 2–7–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP05–130–000; CP05–132–
000; CP05–395–000; CP06–26–000; CP05–
131–000 (Not consolidated)]
Dominion Cove Point LNG, L.P.,
Dominion Cove Point LNG, L.P.,
Dominion Cove Point LNG, L.P.,
Dominion Transmission, Inc.; Notice of
Procedural Conference and Order on
Late Interventions
rmajette on PROD1PC67 with NOTICES1
February 2, 2006.
The Commission has received a
number of pleadings in this proceeding
regarding the quality of the natural gas
delivered, and proposed to be delivered,
to Washington Gas Light Company
(WGL), from the liquefied natural gas
(LNG) import terminal owned and
operated by Dominion Cove Point LNG,
LP (Cove Point), and the potential
effects of the proposed expansion and
modification of Cove Point’s LNG
import terminal on certain facilities
VerDate Aug<31>2005
15:26 Feb 07, 2006
Jkt 208001
owned by WGL.1 The Commission staff
has determined that discussing with the
parties the issues raised in these various
pleadings would assist staff in
evaluating these matters.
Accordingly, a Procedural Conference
will be held at the Commission’s offices
in Washington, DC, on February 22,
2006, commencing at 10 a.m., in order
that the parties and the Commission
Staff can discuss the pleadings filed and
the procedural options for continued
timely processing of Cove Point’s
requests for expansion and modification
of its LNG import terminal.
Participants at the conference should
come prepared to discuss the
relationship, if any, between Cove
Point’s proposal to expand and modify
its LNG import terminal in the
captioned proceedings and the problems
on WGL’s system which WGL alleges
are associated with the quality of
natural gas delivered from the Cove
Point import terminal. As part of this
discussion, participants should be
prepared to provide information which
shows that the alleged impacts on
WGL’s ability to provide safe and
reliable services to its customers are
either substantially related to the
introduction of natural gas from Cove
Point’s LNG import terminal into Cove
Point’s pipeline and interconnecting
pipelines and delivered to WGL, or are
substantially related to other factors and
that such problems have occurred prior
to the introduction of LNG into Cove
Point’s pipeline and interconnecting
pipelines.
The Commission, pursuant to Rule
214(d)(3)(i) of the Commission’s Rules
of Practice and Procedure, hereby grants
the motions to intervene out of time
listed in the Appendix to this Notice for
the limited purpose of participating in
the Procedural Conference. The
Commission reserves the right to grant
or deny further party status of any late
intervenor, as appropriate.
FERC conferences are accessible
under section 508 of the Rehabilitation
Act of 1973. For accessibility
accommodations please send an e-mail
to accessibility@ferc.gov or call toll free
(866) 208-3372 (voice) or (202) 208–
1659 (TTY), or send a fax to (202) 208–
2106 with the required
accommodations.
Magalie R. Salas,
Secretary.
[FR Doc. E6–1700 Filed 2–7–06; 8:45 am]
BILLING CODE 6717–01–P
1 A list of pleadings that relate to these gas quality
issues is in the Appendix to this Notice.
PO 00000
Frm 00030
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. ER05–1410–000, EL05–148–
000, ER06–456–000, EL05–145–000, ER06–
309–000, ER06–406–000, EL06–50–000 (not
consolidated)]
PJM Interconnection, LLC; PJM
Interconnection, LLC; District of
Columbia Public Service Commission;
PJM Interconnection, LLC; PJM
Interconnection, LLC; American
Electric Power Service Corporation;
Supplemental Notice Regarding RPM
Technical Conference
February 2, 2006.
The Commission will hold a technical
conference on February 3, 2006, on the
matters raised by the Reliability Pricing
Model (RPM) filed by PJM
Interconnection, LLC (PJM) in Docket
Nos. ER05–1410–000 and EL05–148–
000 (February 3 RPM conference).1 The
additional docket numbers are added
because filings in those proceedings
contain issues that may arise in the
course of discussions regarding RPM.
These proceedings are not
consolidated. Once the February 3, 2006
RPM conference is completed and all
documents related to that conference are
filed, parties should not combine issues
relating to these separate proceedings in
a single filing. Parties should file future
pleadings relating to PJM’s filing in
Docket Nos. ER05–1410–000 and EL05–
148–000 in those dockets only, and
similarly, should file future pleadings
related to the proceedings in Docket
Nos. ER06–456–000, EL05–145–000,
ER06–309–000, ER06–406–000, and
EL06–50–000 in those dockets
respectively.
Magalie R. Salas,
Secretary.
[FR Doc. E6–1701 Filed 2–7–06; 8:45 am]
BILLING CODE 6717–01–P
1 See Notice of Commission Technical Conference
(December 28, 2005) and Supplemental Notice of
Commission Technical Conference (January 19,
2006) in Docket Nos. ER05–1410–000 and EL05–
148–000.
E:\FR\FM\08FEN1.SGM
08FEN1
Agencies
[Federal Register Volume 71, Number 26 (Wednesday, February 8, 2006)]
[Notices]
[Page 6474]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-1701]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. ER05-1410-000, EL05-148-000, ER06-456-000, EL05-145-000,
ER06-309-000, ER06-406-000, EL06-50-000 (not consolidated)]
PJM Interconnection, LLC; PJM Interconnection, LLC; District of
Columbia Public Service Commission; PJM Interconnection, LLC; PJM
Interconnection, LLC; American Electric Power Service Corporation;
Supplemental Notice Regarding RPM Technical Conference
February 2, 2006.
The Commission will hold a technical conference on February 3,
2006, on the matters raised by the Reliability Pricing Model (RPM)
filed by PJM Interconnection, LLC (PJM) in Docket Nos. ER05-1410-000
and EL05-148-000 (February 3 RPM conference).\1\ The additional docket
numbers are added because filings in those proceedings contain issues
that may arise in the course of discussions regarding RPM.
---------------------------------------------------------------------------
\1\ See Notice of Commission Technical Conference (December 28,
2005) and Supplemental Notice of Commission Technical Conference
(January 19, 2006) in Docket Nos. ER05-1410-000 and EL05-148-000.
---------------------------------------------------------------------------
These proceedings are not consolidated. Once the February 3, 2006
RPM conference is completed and all documents related to that
conference are filed, parties should not combine issues relating to
these separate proceedings in a single filing. Parties should file
future pleadings relating to PJM's filing in Docket Nos. ER05-1410-000
and EL05-148-000 in those dockets only, and similarly, should file
future pleadings related to the proceedings in Docket Nos. ER06-456-
000, EL05-145-000, ER06-309-000, ER06-406-000, and EL06-50-000 in those
dockets respectively.
Magalie R. Salas,
Secretary.
[FR Doc. E6-1701 Filed 2-7-06; 8:45 am]
BILLING CODE 6717-01-P