Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 5832-5833 [E6-1451]
Download as PDF
hsrobinson on PROD1PC70 with NOTICES
5832
Federal Register / Vol. 71, No. 23 / Friday, February 3, 2006 / Notices
Average annual generation would be
2,500,000 kilowatt-hours.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits,
in the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h above.
Register online at https://
www.ferc.gov/docs-filings/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Any qualified applicant desiring to
file a competing application must
submit to the Commission on or before
the specified deadline date for the
particular application, a competing
development application, or a notice of
intent to file such an application.
Submission of a timely notice of intent
allows an interested person to file the
competing development application no
later than 120 days after the specified
deadline date for the particular
application. Applications for
preliminary permits will not be
accepted in response to this notice.
A notice of intent must specify the
exact name, business address, and
telephone number of the prospective
applicant, and must include an
unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
Rules of Practice and Procedure, 18 CFR
385.210, 385.211, and 385.214. In
determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
The Commission directs, pursuant to
section 4.34(b) of the Regulations (see
VerDate Aug<31>2005
15:00 Feb 02, 2006
Jkt 208001
Order No. 533 issued May 8, 1991, 56
FR 23108, May 20, 1991) that all
comments, recommendations, terms and
conditions, and prescriptions
concerning the application be filed with
the Commission within 60 days from
the issuance date of this notice. All
reply comments must be filed with the
Commission within 105 days from the
date of this notice.
All filings must (1) bear in all capital
letters the title ‘‘PROTEST,’’ ‘‘MOTION
TO INTERVENE,’’ ‘‘NOTICE OF
INTENT TO FILE COMPETING
APPLICATION,’’ or ‘‘COMPETING
APPLICATION,’’ ‘‘COMMENTS,’’
‘‘REPLY COMMENTS,’’
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, recommendations, terms and
conditions, or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. A copy of all other filings
in reference to this application must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
o. Scoping Process: The Commission
intends to prepare an Environmental
Assessment (EA) on the project in
accordance with the National
Environmental Policy Act.2 The EA will
consider both site-specific and
cumulative environmental impacts and
reasonable alternatives to the proposed
action.
Commission staff does not propose to
conduct any on-site scoping meetings at
this time. Instead, we will solicit
comments, recommendations,
information, and alternatives in the
Scoping Document (SD).3
2 One EA will be prepared for the Mill Coulee
Drops Project and two other projects proposed to be
constructed on nearby canals, the Lower Turnbull
Drop Project No. 12597 and the Upper Turnbull
Drop Project No. 12598.
3 One SD has been prepared for the Mill Coulee
Drops Project, the Lower Turnbull Drop Project, and
the Upper Turnbull Drop Project.
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
Copies of the SD outlining the subject
areas to be addressed in the EA were
distributed to the parties on the
Commission’s mailing list. Copies of the
SD may be viewed on the Web at
https://www.ferc.gov using the
‘‘eLibrary’’ link (see item m above).
Magalie R. Salas,
Secretary.
[FR Doc. E6–1445 Filed 2–2–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Ready for
Environmental Analysis and Soliciting
Comments, Recommendations, Terms
and Conditions, and Prescriptions
January 26, 2006.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Major License.
b. Project No.: 11945–001.
c. Date Filed: June 30, 2004.
d. Applicant: Symbiotics, LLC.
e. Name of Project: Dorena Lake Dam
Hydroelectric Project.
f. Location: On the Row River, near
the Town of Cottage Grove, Lane
County, Oregon. The project would
occupy less than 1 acre of Federal lands
administered by the U.S. Army Corps of
Engineers.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Brent L. Smith,
Symbiotics, LLC, P.O. Box 535, Rigby,
Idaho 83442; telephone (208) 745–0834
or by e-mail at
bsmith@nwpwrservices.com.
i. FERC Contact: Dianne Rodman;
telephone (202) 502–6077 or by e-mail
at dianne.rodman@ferc.gov.
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions is 60 days
from the issuance of this notice; reply
comments are due 105 days from the
issuance date of this notice.
All documents (original and eight
copies) should be filed with: Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
E:\FR\FM\03FEN1.SGM
03FEN1
5833
Federal Register / Vol. 71, No. 23 / Friday, February 3, 2006 / Notices
hsrobinson on PROD1PC70 with NOTICES
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
Comments, recommendations, terms
and conditions, and prescriptions may
be filed electronically via the Internet in
lieu of paper. The Commission strongly
encourages electronic filings. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov) under the ‘‘eFiling’’ link.
k. This application has been accepted
and is now ready for environmental
analysis.
l. The proposed project would utilize
the U.S. Army Corps of Engineers’
existing Dorena Lake dam and reservoir,
and would consist of the following
facilities: (1) A 9-foot-diameter steel
pipe, about 350 feet long, extending
from the reservoir through the north
dam abutment; (2) a new powerhouse,
near the existing spillway stilling basin
250 feet downstream from the concrete
section of the dam, having a total
installed capacity of 8,300 kilowatts; (3)
a new concrete-lined channel
discharging flows into the river channel
immediately below the existing stilling
basin; (4) a new valve house near the
existing stilling basin; (5) a new 15kilovolt underground transmission line,
about 500 feet long; and (6) appurtenant
facilities. The average annual generation
is estimated to be 17.5 gigawatthours.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h above.
All filings must (1) bear in all capital
letters the title ‘‘COMMENTS’’, ‘‘REPLY
COMMENTS’’,
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b), and
385.2010.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Public notice of the filing of the
initial development application, which
has already been given, established the
due date for filing competing
applications or notices of intent. Under
the Commission’s regulations, any
competing development application
must be filed in response to and in
compliance with public notice of the
initial development application. No
competing applications or notices of
intent may be filed in response to this
notice.
Magalie R. Salas,
Secretary.
[FR Doc. E6–1451 Filed 2–2–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. RM98–1–000]
Records Governing Off-the-Record
Communications; Public Notice
January 27, 2006.
This constitutes notice, in accordance
with 18 CFR 385.2201(b), of the receipt
of prohibited and exempt off-the-record
communications.
Order No. 607 (64 FR 51222,
September 22, 1999) requires
Commission decisional employees, who
make or receive a prohibited or exempt
off-the-record communication relevant
to the merits of a contested proceeding,
to deliver to the Secretary of the
Commission, a copy of the
communication, if written, or a
summary of the substance of any oral
communication.
Prohibited communications are
included in a public, non-decisional file
associated with, but not a part of, the
decisional record of the proceeding.
Unless the Commission determines that
the prohibited communication and any
responses thereto should become a part
of the decisional record, the prohibited
off-the-record communication will not
be considered by the Commission in
reaching its decision. Parties to a
proceeding may seek the opportunity to
respond to any facts or contentions
made in a prohibited off-the-record
communication, and may request that
the Commission place the prohibited
communication and responses thereto
in the decisional record. The
Commission will grant such a request
only when it determines that fairness so
requires. Any person identified below as
having made a prohibited off-the-record
communication shall serve the
document on all parties listed on the
official service list for the applicable
proceeding in accordance with Rule
2010, 18 CFR 385.2010.
Exempt off-the-record
communications are included in the
decisional record of the proceeding,
unless the communication was with a
cooperating agency as described by 40
CFR 1501.6, made under 18 CFR
385.2201(e)(1)(v).
The following is a list of off-therecord communications recently
received by the Secretary of the
Commission. The communications
listed are grouped by docket numbers in
ascending order. These filings are
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the eLibrary
link. Enter the docket number,
excluding the last three digits, in the
docket number field to access the
document. For assistance, please contact
FERC, Online Support at
FERCOnlineSupport@ferc.gov or toll
free at (866) 208–3676, or for TTY,
contact (202) 502–8659.
Exempt:
Docket number
Date received
1. CP04–223–000 .....................................................................................................................
CP04–293–000 ......................................................................................................................
CP04–36–000 ........................................................................................................................
CP04–41–000.
2. CP05–130–000 .....................................................................................................................
1–18–06 .............
.......................
.......................
Hon. Jack Reed.
Hon. Patrick J. Kennedy.
Hon. James R. Langevin.
1–24–06 .............
Robert F. Gore.
VerDate Aug<31>2005
15:00 Feb 02, 2006
Jkt 208001
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
E:\FR\FM\03FEN1.SGM
03FEN1
Presenter or requester
Agencies
[Federal Register Volume 71, Number 23 (Friday, February 3, 2006)]
[Notices]
[Pages 5832-5833]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-1451]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Application Ready for Environmental Analysis and
Soliciting Comments, Recommendations, Terms and Conditions, and
Prescriptions
January 26, 2006.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Major License.
b. Project No.: 11945-001.
c. Date Filed: June 30, 2004.
d. Applicant: Symbiotics, LLC.
e. Name of Project: Dorena Lake Dam Hydroelectric Project.
f. Location: On the Row River, near the Town of Cottage Grove, Lane
County, Oregon. The project would occupy less than 1 acre of Federal
lands administered by the U.S. Army Corps of Engineers.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Brent L. Smith, Symbiotics, LLC, P.O. Box
535, Rigby, Idaho 83442; telephone (208) 745-0834 or by e-mail at
bsmith@nwpwrservices.com.
i. FERC Contact: Dianne Rodman; telephone (202) 502-6077 or by e-
mail at dianne.rodman@ferc.gov.
j. Deadline for filing comments, recommendations, terms and
conditions, and prescriptions is 60 days from the issuance of this
notice; reply comments are due 105 days from the issuance date of this
notice.
All documents (original and eight copies) should be filed with:
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that
[[Page 5833]]
may affect the responsibilities of a particular resource agency, they
must also serve a copy of the document on that resource agency.
Comments, recommendations, terms and conditions, and prescriptions
may be filed electronically via the Internet in lieu of paper. The
Commission strongly encourages electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
(https://www.ferc.gov) under the ``e-Filing'' link.
k. This application has been accepted and is now ready for
environmental analysis.
l. The proposed project would utilize the U.S. Army Corps of
Engineers' existing Dorena Lake dam and reservoir, and would consist of
the following facilities: (1) A 9-foot-diameter steel pipe, about 350
feet long, extending from the reservoir through the north dam abutment;
(2) a new powerhouse, near the existing spillway stilling basin 250
feet downstream from the concrete section of the dam, having a total
installed capacity of 8,300 kilowatts; (3) a new concrete-lined channel
discharging flows into the river channel immediately below the existing
stilling basin; (4) a new valve house near the existing stilling basin;
(5) a new 15-kilovolt underground transmission line, about 500 feet
long; and (6) appurtenant facilities. The average annual generation is
estimated to be 17.5 gigawatthours.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1-
866-208-3676, or for TTY, (202) 502-8659. A copy is also available for
inspection and reproduction at the address in item h above.
All filings must (1) bear in all capital letters the title
``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS,'' ``TERMS AND
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person submitting the filing; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicant. Each filing must be
accompanied by proof of service on all persons listed on the service
list prepared by the Commission in this proceeding, in accordance with
18 CFR 4.34(b), and 385.2010.
You may also register online at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
n. Public notice of the filing of the initial development
application, which has already been given, established the due date for
filing competing applications or notices of intent. Under the
Commission's regulations, any competing development application must be
filed in response to and in compliance with public notice of the
initial development application. No competing applications or notices
of intent may be filed in response to this notice.
Magalie R. Salas,
Secretary.
[FR Doc. E6-1451 Filed 2-2-06; 8:45 am]