Environmental Impact Statement: Iron County, UT, 5407 [06-923]

Download as PDF Federal Register / Vol. 71, No. 21 / Wednesday, February 1, 2006 / Notices DEPARTMENT OF TRANSPORTATION Federal Highway Administration Environmental Impact Statement: Iron County, UT Federal Highway Administration (FHWA), DOT AGENCY: ACTION: Notice of termination. SUMMARY: The FHWA is issuing this notice to advise the public that the effort to prepare an Environmental Impact Statement (EIS) for transportation improvements to Cross Hollow Road, from I–15 to SR–56, located in Cedar City, Utah, will be terminated. FOR FURTHER INFORMATION CONTACT: Sandra A. Garcia-Aline, Transportation Engineer, FHWA, Utah Division, 2520 West 4700 South, Suite 9A, Salt Lake City, UT 84118, Telephone (801) 963– 0182; or Daryl Friant, Utah Department of Transportation (UDOT), 1345 South 350 West, Richfield, UT 84701, Telephone (435) 893–4714. The FHWA in cooperation with the UDOT and Cedar City have elected to terminate efforts to prepare an EIS for transportation improvements on Cross Hollow Road between I–15 and SR–56. The Notice of Intent for this project was originally published on March 10, 2005. Cedar City has recently elected not to use federal funds on the project. Therefore, no federal funds or federal action will be required for the revised project. The FHWA, in conjunction with the Utah Department of Transportation, has decided to discontinue efforts on this project. If you have any questions regarding the revised Cross Hollow Road project or would like to provide scoping comments, please contact Tamerha Maxwell, UDOT Project Manager, at (435) 865–5511. SUPPLEMENTARY INFORMATION: cchase on PROD1PC60 with NOTICES (Catalog of Federal and Domestic Assistance Program Number 20.205, Highway Research, Planning and Construction. The regulations implementing Executive Order 12372 regarding intergovernmental consultation on Federal programs and activities apply to this program.) Sandra A. Garcia-Aline, NEPA Manager, Federal Highway Administration, Salt Lake, Utah. [FR Doc. 06–923 Filed 1–31–06; 8:45 am] BILLING CODE 4910–22–M VerDate Aug<31>2005 17:49 Jan 31, 2006 Jkt 208001 5407 approximately 1.2 miles east of SR691. The actions by the Federal agencies, and Federal Highway Administration the laws under which such actions were taken, are described in the Final Notice of Final Federal Agency Actions Environmental Impact Statement (FEIS) on Proposed Highway in Ohio for the project, approved on June 30, 2005, in the FHWA Record of Decision AGENCY: Federal Highway (ROD) issued on August 19, 2005, and Administration (FHWA), DOT. in other documents in the FHWA ACTION: Notice of limitation on claims administrative record. The FEIS, ROD, for judicial review of actions by FHWA and other documents in the FHWA and other Federal agencies. administrative record file are available SUMMARY: This notice announces actions by contacting the FHWA or the Ohio Department of Transportation at the taken by the FHWA and other Federal addresses provided above. The FHWA agencies that are final within the FEIS and ROD can be viewed at the meaning of 23 U.S.C. 139(l)(1). The Nelsonville Public Library, the Athens actions relate to a proposed highway and Hocking County Engineer’s offices, project which would relocate U.S. 33 the Athens and Hocking County from Haydenville in Hocking County to Doanville in Athens County in the State Commissioners’ offices, the Nelsonville City Manager’s office, and the Hocking of Ohio. Those actions grant licenses, College President’s office. permits, and approvals for the project. This notice applies to all Federal DATES: By this notice, the FHWA is agency decisions as of the issuance date advising the public of final agency of this notice and all laws under which actions subject to 23 U.S.C. 139(l)(1). A such actions were taken, including but claim seeking judicial review of the not limited to: Federal agency actions on the highway 1. General: National Environmental project will be barred unless the claim Policy Act (NEPA) [42 U.S.C. 4321– is filed on or before July 31, 2006. If the 4351]; Federal-Aid Highway Act [23 Federal law that authorizes judicial review of a claim provides a time period U.S.C. 109]. 2. Air: Clean Air Act, 42 U.S.C. 7401– of less than 180 days for filing such claim, then that shorter time period still 7671(q). 3. Land: Land and Water Conservation applies. Fund (LWCF), 16 U.S.C. 4601–4604; FOR FURTHER INFORMATION CONTACT: Mr. Section 4(f) of the Department of David Snyder, P.E., Environmental Transportation Act of 1966 [49 U.S.C. Program Manager, Federal Highway 303]; Landscaping and Scenic Administration, 200 North High Street, Enhancement (Wildflowers), [23 U.S.C. Columbus, Ohio, 43215; telephone: 319]; National Forest Management Act (614) 280–6852; e-mail: (NFMA) of 1976 [16 U.S.C. 1600–1614]. David.Snyder@fhwa.dot.gov; FHWA 4. Wildlife: Endangered Species Act Ohio Division Office’s normal business [16 U.S.C. 1531–1544 and Section hours are 8 a.m. to 4:30 p.m. (eastern 1536], Marine Mammal Protection Act time). You may also contact Mr. Tim [16 U.S.C. 1361], Fish and Wildlife Hill, Ohio Department of Coordination Act [16 U.S.C. 661– Transportation, 1980 West Broad Street, 667(d)], Migratory Bird Treaty Act [16 Columbus, OH 43223; telephone: (624) U.S.C. 703–712]. 644–0377. 5. Historic and Cultural Resources: SUPPLEMENTARY INFORMATION: Notice is Section 106 of the National Historic hereby given that the FHWA and other Preservation Act of 1966, as amended Federal agencies have taken final agency [16 U.S.C. 470(f) et seq.]; Archeological actions by issuing licenses, permits, and Resources Protection Act of 1977 [16 approvals for the following highway U.S.C. 470(aa)–11]; Archeological and project in the State of Ohio: U.S. Route Historic Preservation Act [16 U.S.C. 33, from Haydenville in Hocking County 469–469(c)]; Native American Grave to Doanville in Athens County in the Protection and Repatriation Act State of Ohio. The project will be a 9 (NAGPRA) [25 U.S.C. 3001–3013]. mile long, four-lane divided controlled 6. Social and Economic: Civil Rights access highway on new location, also Act of 1964 [42 U.S.C. 2000(d)– known as the Nelsonville Bypass 2000(d)(1)]; American Indian Religious Project. It will begin northwest of Freedom Act [42 U.S.C. 1996]; Farmland Nelsonville adjacent to Haydenville. It Protection Policy Act (FPPA) [7 U.S.C. will then proceed in a northeasterly 4201–4209]. 7. Wetlands and Water Resources: direction north of Nelsonville and south Safe Drinking Water Act (SDWA), 42 of Buchtel. It will end at Doanville U.S.C. 300(f)–300(j)(6); Rivers and which is located just northwest of New Floodwood, tying back into the existing Harbors Act of 1899, 33 U.S.C. 401–406; Wild and Scenic Rivers Act, 16 U.S.C. 4-lane divided U.S. Route 33 DEPARTMENT OF TRANSPORTATION PO 00000 Frm 00176 Fmt 4703 Sfmt 4703 E:\FR\FM\01FEN1.SGM 01FEN1

Agencies

[Federal Register Volume 71, Number 21 (Wednesday, February 1, 2006)]
[Notices]
[Page 5407]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 06-923]



[[Page 5407]]

-----------------------------------------------------------------------

DEPARTMENT OF TRANSPORTATION

Federal Highway Administration


Environmental Impact Statement: Iron County, UT

AGENCY: Federal Highway Administration (FHWA), DOT

ACTION: Notice of termination.

-----------------------------------------------------------------------

SUMMARY: The FHWA is issuing this notice to advise the public that the 
effort to prepare an Environmental Impact Statement (EIS) for 
transportation improvements to Cross Hollow Road, from I-15 to SR-56, 
located in Cedar City, Utah, will be terminated.

FOR FURTHER INFORMATION CONTACT: Sandra A. Garcia-Aline, Transportation 
Engineer, FHWA, Utah Division, 2520 West 4700 South, Suite 9A, Salt 
Lake City, UT 84118, Telephone (801) 963-0182; or Daryl Friant, Utah 
Department of Transportation (UDOT), 1345 South 350 West, Richfield, UT 
84701, Telephone (435) 893-4714.

SUPPLEMENTARY INFORMATION: The FHWA in cooperation with the UDOT and 
Cedar City have elected to terminate efforts to prepare an EIS for 
transportation improvements on Cross Hollow Road between I-15 and SR-
56. The Notice of Intent for this project was originally published on 
March 10, 2005. Cedar City has recently elected not to use federal 
funds on the project. Therefore, no federal funds or federal action 
will be required for the revised project. The FHWA, in conjunction with 
the Utah Department of Transportation, has decided to discontinue 
efforts on this project. If you have any questions regarding the 
revised Cross Hollow Road project or would like to provide scoping 
comments, please contact Tamerha Maxwell, UDOT Project Manager, at 
(435) 865-5511.

(Catalog of Federal and Domestic Assistance Program Number 20.205, 
Highway Research, Planning and Construction. The regulations 
implementing Executive Order 12372 regarding intergovernmental 
consultation on Federal programs and activities apply to this 
program.)

Sandra A. Garcia-Aline,
NEPA Manager, Federal Highway Administration, Salt Lake, Utah.
[FR Doc. 06-923 Filed 1-31-06; 8:45 am]
BILLING CODE 4910-22-M