Crisp County Power Commission; Notice of Availability of Environmental Assessment, 4128-4129 [E6-841]

Download as PDF wwhite on PROD1PC61 with NOTICES 4128 Federal Register / Vol. 71, No. 16 / Wednesday, January 25, 2006 / Notices the Notice of Cancellation Filing of Kentucky Utilities Co. Filed Date: 01/05/2006. Accession Number: 20060105–5031. Comment Date: 5 p.m. eastern time on Monday, January 30, 2006. Docket Numbers: ER06–268–001. Applicants: Los Esteros Critical Energy Facility LLC. Description: Los Esteros Critical Energy Facility, LLC submits Attachment A—corrections to Rate Schedule No.130 of its Reliability MustRun Agreement with the California Independent System Operator Corp. Filed Date: 01/11/2006. Accession Number: 20060113–0142. Comment Date: 5 p.m. eastern time on Wednesday, February 1, 2006. Docket Numbers: ER06–332–001. Applicants: ISO New England Inc. Description: ISO New England Inc submits a page providing the missing text from its informational filing submitted on 12/15/05. Filed Date: 01/10/2006. Accession Number: 20060117–0220. Comment Date: 5 p.m. eastern time on Tuesday, January 31, 2006. Docket Numbers: ER06–472–000. Applicants: LG&E Energy Marketing Inc. Description: LG&E Energy Marketing , Inc submits an Agreement for Electric Service with Kenergy Corp. Filed Date: 01/11/2006. Accession Number: 20060113–0135. Comment Date: 5 p.m. eastern time on Wednesday, February 1, 2006. Docket Numbers: ER06–473–000. Applicants: Central Vermont Public Service Corporation. Description: Central Vermont Public Service Corp submits a non-conforming point-to-point service agreement under ISO New England Inc Tariff Schedule 20A. Filed Date: 01/11/2006. Accession Number: 20060113–0134. Comment Date: 5 p.m. eastern time on Wednesday, February 1, 2006. Docket Numbers: ER06–475–000. Applicants: Colorado Power Partners. Description: Colorado Power Partners submits revised sheets to its market based rate tariff, FERC Electric Tariff Volume No. 1. Filed Date: 01/11/2006. Accession Number: 20060117–0213. Comment Date: 5 p.m. eastern time on Wednesday, February 1, 2006. Docket Numbers: ER06–476–000. Applicants: Westar Energy, Inc. Description: Westar Energy, Inc submits a Notice of Cancellation of Supplement No.15, Service Schedule M under their First Revised Rate Schedule Federal Power Commission No. 93. VerDate Aug<31>2005 18:26 Jan 24, 2006 Jkt 208001 Filed Date: 01/11/2006. Accession Number: 20060117–0214. Comment Date: 5 p.m. eastern time on Wednesday, February 1, 2006. Docket Numbers: ER88–478–001; ER91–576–002. Applicants: Ocean State Power; Ocean State Power II. Description: Ocean State Power and Ocean State Power II report a change in status to reflect certain departures from the facts the Commission relied upon in granting market-based rate authority. Filed Date: 01/11/2006. Accession Number: 20060113–0138. Comment Date: 5 p.m. eastern time on Wednesday, February 1, 2006. Any person desiring to intervene or to protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214) on or before 5 p.m. eastern time on the specified comment date. It is not necessary to separately intervene again in a subdocket related to a compliance filing if you have previously intervened in the same docket. Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. In reference to filings initiating a new proceeding, interventions or protests submitted on or before the comment deadline need not be served on persons other and the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with Internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically should submit an original and 14 copies of the intervention or protest to the Federal Energy Regulatory Commission, 888 First St. NE., Washington, DC 20426. The filings in the above proceedings are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the web site that enables subscribers to receive e-mail PO 00000 Frm 00030 Fmt 4703 Sfmt 4703 notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov. or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Magalie R. Salas, Secretary. [FR Doc. E6–826 Filed 1–24–06; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 659–013] Crisp County Power Commission; Notice of Availability of Environmental Assessment January 18, 2006. In accordance with the National Environmental Policy Act of 1969, as amended, and the Federal Energy Regulatory Commission’s (Commission) regulations (18 CFR Part 380), Commission staff have prepared an environmental assessment (EA) that analyzes the environmental impacts of allowing Crisp Country Power Commission, licensee for the Lake Blackshear Hydroelectric Project (FERC No. 659), to amend the existing project boundary. The licensee proposes to amend the Lake Blackshear Project’s boundary to include a 3.2 acre increase in the lake surface area in association with a proposed subdivision on Lincolmpinch Cove. The proposed subdivision would include 16 lots and would extend the inlet to provide lake frontage to the proposed lots. The extension would be created by excavating wetland areas bordering the cove to a depth of approximately 4 feet below the normal water surface elevation of Lake Blackshear. The licensee proposes to maintain the project boundary at the 237-foot msl contour, and extend the boundary along this contour to encompass the additional area that would be excavated and inundated in association with the construction of the subdivision. In addition to excavating the cove area, the developer would dredge a 4-foot-deep by 40-foot-wide channel from Lake Blackshear to the cove to allow water from the lake to fill the cove. A copy of the EA is attached to a Commission order titled ‘‘Order Approving Change in Project Boundary,’’ which was issued on January 13, 2006, and is available for review and reproduction at the Commission’s Public Reference Room, E:\FR\FM\25JAN1.SGM 25JAN1 Federal Register / Vol. 71, No. 16 / Wednesday, January 25, 2006 / Notices located at 888 First Street, NE., Room 2A, Washington, DC 20426. The EA may also be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘elibrary’’ link. Enter the docket number (prefaced by P-) and excluding the last three digits, in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY, contact (202) 502–8659. Magalie R. Salas, Secretary. [FR Doc. E6–841 Filed 1–24–06; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Application for Surrender of License and Soliciting Comments, Motions To Intervene, and Protests wwhite on PROD1PC61 with NOTICES January 18, 2006. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Application Type: Surrender of License (5 MW or Less). b. Project No.: 11392–008. c. Date Filed: August 17, 2005. d. Applicant: J&T Hydro Company. e. Name of Project: Ramseur Project. f. Location: Located on the Deep River, Randolph County, North Carolina. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Ms. Joann Hill, J&T Hydro Company, 7540 Burgess Kivett Road, Ramseur, NC 27316. i. FERC Contact: Christopher Yeakel, (202) 502–8132. j. Deadline for filing responsive documents: February 21, 2006. k. Description of Proposed Action: The existing project consists of: (1) An 11-foot-high, 434-foot-long stone masonry dam; (2) a reservoir with a surface area of about 33 acres; (3) a 1,300 foot-long power canal; (4) an existing two-story brick masonry powerhouse that previously contained two generators rated at 150 kW each for a total installed capacity of 300 kW; (5) a 226 foot-long tailrace; (6) a 112-footlong, 2.4-kilovolt overhead transmission line; and (7) appurtenant equipment. The licensee would like to surrender its license. The generating equipment has been removed and sold. l. Locations of Application: A copy of the information is available for VerDate Aug<31>2005 18:26 Jan 24, 2006 Jkt 208001 inspection and reproduction at the Commission in the Public Reference Room, located at 888 First Street, NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number, here P–11392, in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3676 or e-mail FERCOnlineSupport@ferc.gov. For TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item h above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘REPLY COMMENTS’’, ‘‘RECOMMENDATIONS FOR TERMS AND CONDITIONS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and eight copies to: Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. An additional copy must be sent to the Director, Division of Hydropower Administration and Compliance, Federal Energy Regulatory Commission, at the above-mentioned address. A copy of any motion to intervene must also be served upon each representative of the Applicant specified in the particular application. p. Agency Comments—Federal, state, and local agencies are invited to file comments on the described applications. A copy of the applications may be obtained by agencies directly from the Applicant. If any agency does not file comments within the time PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 4129 specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. q. Comments, protests and interventions may be filed electronically via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site at https://www.ferc.gov under the ‘‘e-Filing’’ link. Magalie R. Salas, Secretary. [FR Doc. E6–839 Filed 1–24–06; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Application for Non-Project Use of Project Lands and Waters January 18, 2006. Take notice that the following application has been filed with the Commission and is available for public inspection: a. Application Type: Non-Project Use of Project Lands and Waters. b. Project No: 2413–073. c. Date Filed: November 22, 2005. d. Applicant: Georgia Power Company. e. Name of Project: Wallace Dam Project. f. Location: The proposed development is located on Lake Oconee in Putnam County, Georgia. This project does not occupy any federal or tribal lands. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r) and 799 and 801. h. Applicant Contact: Mr. Lee B. Glenn, Georgia Power Company, 125 Wallace Dam Road NE., Eatonton, GA 31024, (706) 485–8704. i. FERC Contact: Any questions on this notice should be addressed to Shana High at (202) 502–8764. j. Deadline for filing comments and or motions: February 21, 2006. All documents (original and eight copies) should be filed with: Ms. Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington DC 20426. Please include the project number (P– 2413–073) on any comments or motions filed. Comments, protests, and interventions may be filed electronically via the internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. The E:\FR\FM\25JAN1.SGM 25JAN1

Agencies

[Federal Register Volume 71, Number 16 (Wednesday, January 25, 2006)]
[Notices]
[Pages 4128-4129]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-841]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 659-013]


Crisp County Power Commission; Notice of Availability of 
Environmental Assessment

January 18, 2006.
    In accordance with the National Environmental Policy Act of 1969, 
as amended, and the Federal Energy Regulatory Commission's (Commission) 
regulations (18 CFR Part 380), Commission staff have prepared an 
environmental assessment (EA) that analyzes the environmental impacts 
of allowing Crisp Country Power Commission, licensee for the Lake 
Blackshear Hydroelectric Project (FERC No. 659), to amend the existing 
project boundary. The licensee proposes to amend the Lake Blackshear 
Project's boundary to include a 3.2 acre increase in the lake surface 
area in association with a proposed subdivision on Lincolmpinch Cove. 
The proposed subdivision would include 16 lots and would extend the 
inlet to provide lake frontage to the proposed lots. The extension 
would be created by excavating wetland areas bordering the cove to a 
depth of approximately 4 feet below the normal water surface elevation 
of Lake Blackshear. The licensee proposes to maintain the project 
boundary at the 237-foot msl contour, and extend the boundary along 
this contour to encompass the additional area that would be excavated 
and inundated in association with the construction of the subdivision. 
In addition to excavating the cove area, the developer would dredge a 
4-foot-deep by 40-foot-wide channel from Lake Blackshear to the cove to 
allow water from the lake to fill the cove.
    A copy of the EA is attached to a Commission order titled ``Order 
Approving Change in Project Boundary,'' which was issued on January 13, 
2006, and is available for review and reproduction at the Commission's 
Public Reference Room,

[[Page 4129]]

located at 888 First Street, NE., Room 2A, Washington, DC 20426. The EA 
may also be viewed on the Commission's Web site at https://www.ferc.gov 
using the ``elibrary'' link. Enter the docket number (prefaced by P-) 
and excluding the last three digits, in the docket number field to 
access the document. For assistance, contact FERC Online Support at 
FERCOnlineSupport@ferc.gov or toll-free at (866) 208-3676, or for TTY, 
contact (202) 502-8659.

Magalie R. Salas,
Secretary.
[FR Doc. E6-841 Filed 1-24-06; 8:45 am]
BILLING CODE 6717-01-P