Federal Register / Vol. 71, No. 5 / Monday, January 9, 2006 / Notices
Commission’s jurisdiction over the
facilities, rates, services, or operations
(referred to as the Eldorado—Spraberry
facilities) it would purchase from
Northern. Northern states that Targa
would integrate the Eldorado—
Spraberry facilities into Targa’s
gathering system and offer gathering
service to existing customers as well as
to other parties who request service on
these facilities.
Any questions regarding this
application should be directed to
Michael T. Loeffler, Director,
Certificates and Government Affairs for
Northern, 1111 South 103rd Street,
Omaha, Nebraska 68124, at (402) 398–
7103 or Dan Middlebrooks, Director Gas
Supply—Texas, Targa Texas Field
Services LP, 1000 Louisiana Street,
Suite 4700, Houston, Texas 77002, at
(713) 584–1047.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
VerDate Aug<31>2005
15:31 Jan 06, 2006
Jkt 208001
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link.
Comment Date: January 19, 2006.
Magalie R. Salas,
Secretary.
[FR Doc. E6–51 Filed 1–6–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP05–410–001]
Northern Natural Gas Company; Notice
of Amendment of Application
December 29, 2005.
Take notice that on December 23,
2005 Northern Natural Gas Company
(Northern), 1111 South 103rd Street,
Omaha, Nebraska 68124, filed with the
Federal Energy Regulatory Commission
an application under section 7 of the
Natural Gas Act (NGA) to amend its
original application pending
Commission approval in Docket No.
CP05–410–000, all as more fully set
forth in the application which is on file
with the Commission and open to
public inspection. This filing may be
also viewed on the Web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, call (202) 502–8659 or TTY,
(202) 208–3676.
Northern states it is amending its
original application requesting
authorization to install the water
handling facilities to increase the
storage capacity at its Redfield Storage
PO 00000
Frm 00015
Fmt 4703
Sfmt 4703
Field in Dallas County, Iowa, pursuant
to section 7 of the NGA. This
amendment is in addition to the
authorization requested in the original
application filed September 2, 2005.
Any questions regarding this
amendment should be directed to
Michael T. Loeffler, Director of
Certificates for Northern, 1111 South
103rd Street, Omaha, Nebraska 68124,
(402) 398–7103 or Bret Fritch, Senior
Regulatory Analyst, at (402) 398–7140.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
E:\FR\FM\09JAN1.SGM
09JAN1
Federal Register / Vol. 71, No. 5 / Monday, January 9, 2006 / Notices
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link.
Comment Date: January 5, 2006.
Magalie R. Salas,
Secretary.
[FR Doc. E6–54 Filed 1–6–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
cprice-sewell on PROD1PC66 with NOTICES
December 28, 2005.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER04–691–068.
Applicants: Midwest Independent
Transmission System Operator, Inc.
Description: Midwest Independent
Transmission System Operator, Inc
submits Substitute Third Revised Sheet
50 et al to FERC Electric Tariff, Third
Revised Volume No. 1.
Filed Date: 12/20/2005.
Accession Number: 20051223–0010.
Comment Date: 5 p.m. Eastern Time
on Tuesday, January 10, 2006.
Docket Numbers: ER05–143–003.
Applicants: Reliant Energy Florida,
LLC.
Description: Reliant Energy Florida
LLC clarifies the change in contracted
status of its Indian River Generating
Facility.
Filed Date: 12/20/2005.
Accession Number: 20051222–0054.
Comment Date: 5 p.m. Eastern Time
on Tuesday, January 10, 2006.
Docket Numbers: ER05–1495–001.
Applicants: American Electric Power
Service Corporation.
Description: American Electric Power
Service Corp as agent for Appalachian
Power Co submits its compliance filing.
Filed Date: 12/19/2005.
Accession Number: 20051221–0094.
Comment Date: 5 p.m. Eastern Time
on Monday, January 9, 2006.
Docket Numbers: ER06–71–001.
VerDate Aug<31>2005
15:31 Jan 06, 2006
Jkt 208001
Applicants: Southwestern Public
Service Company.
Description: Southwestern Public
Service Co submits revisions to their
FERC Electric Rate Schedule No. 118.
Filed Date: 12/09/2005.
Accession Number: 20051214–0016.
Comment Date: 5 p.m. Eastern Time
on Monday, January 9, 2006.
Docket Numbers: ER06–109–001.
Applicants: Southwest Power Pool,
Inc.
Description: Southwest Power Pool
Inc submits an executed service
agreement for long-term firm point to
point transmission service with
Southwestern Public Service Co et al.
Filed Date: 12/19/2005.
Accession Number: 20051221–0091.
Comment Date: 5 p.m. Eastern Time
on Thursday, January 5, 2006.
Docket Numbers: ER06–116–001.
Applicants: Entergy Services, Inc.
Description: Entergy Services Inc
submits on behalf of Entergy Gulf States
Inc, Exhibit C to the Rate Schedules
providing for cost-based power sales for
full requirements service to the City of
Caldwell et al.
Filed Date: 12/20/2005.
Accession Number: 20051222–0052.
Comment Date: 5 p.m. Eastern Time
on Tuesday, January 10, 2006.
Docket Numbers: ER06–117–000.
Applicants: FirstEnergy Solutions
Corp.
Description: Notice of appearance of
Michael L Kurtz, and Kurt J Boehm as
counsel for Mittal Steel USA ISG, Inc.
Filed Date: 12/20/2005.
Accession Number: 20051222–0062.
Comment Date: 5 p.m. Eastern Time
on Tuesday, January 10, 2006.
Docket Numbers: ER06–229–001.
Applicants: Safeway Inc.
Description: Safeway, Inc’s sumbits
Rate Schedule No.1 in accordance with
FERC Order 614 guidelines.
Filed Date: 12/20/2005.
Accession Number: 20051223–0009.
Comment Date: 5 p.m. Eastern Time
on Tuesday, January 10, 2006.
Docket Numbers: ER06–246–000.
Applicants: Allegheny Power.
Description: Allegheny Power submits
a notice of cancellation of the
Interconnection & Operating Agreement
with Mill Run Windpower, LLC.
Filed Date: 11/23/2005.
Accession Number: 20051129–0128.
Comment Date: 5 p.m. Eastern Time
on Thursday, January 5, 2006.
Docket Numbers: ER06–247–000.
Applicants: Allegheny Power.
Description: Allegheny Power submits
a notice of cancellation of the Power
Resale Agreement, dated as of 3/18/87
PO 00000
Frm 00016
Fmt 4703
Sfmt 4703
1421
between Monongahela Power Co & West
Penn Power Co et al.
Filed Date: 11/23/2005.
Accession Number: 20051129–0129.
Comment Date: 5 p.m. Eastern Time
on Thursday, January 5, 2006.
Docket Numbers: ER06–248–000.
Applicants: Allegheny Power.
Description: Allegheny Power submits
a notice of cancellation of the
Interconnection and Operating
Agreement with Industrial Power
Generating Corp for Mountain View etc.
Filed Date: 11/23/2005.
Accession Number: 20051129–0130.
Comment Date: 5 p.m. Eastern Time
on Thursday, January 5, 2006.
Docket Numbers: ER06–343–000.
Applicants: Northeast Utilities
Service Company.
Description: Northeast Utilities
Service Co submits a Notice of
Cancellation of NU Companies Service
Agreement No.13 under ISO New
England, Inc’s FERC Electric Tariff No.
3.
Filed Date: 12/19/2005.
Accession Number: 20051221–0035.
Comment Date: 5 p.m. Eastern Time
on Monday, January 9, 2006.
Docket Numbers: ER06–344–000.
Applicants: Southwest Power Pool.
Description: Southwest Power Pool,
Inc submits revisions to Attachment AD
of its Open Access Transmission Tariff
to modify the Tariff Administration
Agreement w/Southwestern Power
Administration.
Filed Date: 12/19/2005.
Accession Number: 20051221–0036.
Comment Date: 5 p.m. Eastern Time
on Monday, January 09, 2006.
Docket Numbers: ER06–345–000.
Applicants: Arizona Public Service
Company.
Description: Arizona Public Service
Co’s compliance filing, in response to
FERC’s Order 2006–A.
Filed Date: 12/20/2005.
Accession Number: 20051222–0077.
Comment Date: 5 p.m. Eastern Time
on Tuesday, January 10, 2006.
Docket Numbers: ER06–346–000.
Applicants: Desert Generation &
Transmission Co-operative, Inc.
Description: Deseret Generation &
Transmission Co-operative, Inc submits
an Agreement for Large Industrial Rate
with Bridger Valley Electric
Association.
Filed Date: 12/19/2005.
Accession Number: 20051221–0038.
Comment Date: 5 p.m. Eastern Time
on Monday, January 09, 2006.
Docket Numbers: ER06–347–000.
Applicants: Arizona Public Service
Company.
E:\FR\FM\09JAN1.SGM
09JAN1
Agencies
[Federal Register Volume 71, Number 5 (Monday, January 9, 2006)]
[Notices]
[Pages 1420-1421]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-54]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP05-410-001]
Northern Natural Gas Company; Notice of Amendment of Application
December 29, 2005.
Take notice that on December 23, 2005 Northern Natural Gas Company
(Northern), 1111 South 103rd Street, Omaha, Nebraska 68124, filed with
the Federal Energy Regulatory Commission an application under section 7
of the Natural Gas Act (NGA) to amend its original application pending
Commission approval in Docket No. CP05-410-000, all as more fully set
forth in the application which is on file with the Commission and open
to public inspection. This filing may be also viewed on the Web at
https://www.ferc.gov using the ``eLibrary'' link. Enter the docket
number excluding the last three digits in the docket number field to
access the document. For assistance, call (202) 502-8659 or TTY, (202)
208-3676.
Northern states it is amending its original application requesting
authorization to install the water handling facilities to increase the
storage capacity at its Redfield Storage Field in Dallas County, Iowa,
pursuant to section 7 of the NGA. This amendment is in addition to the
authorization requested in the original application filed September 2,
2005.
Any questions regarding this amendment should be directed to
Michael T. Loeffler, Director of Certificates for Northern, 1111 South
103rd Street, Omaha, Nebraska 68124, (402) 398-7103 or Bret Fritch,
Senior Regulatory Analyst, at (402) 398-7140.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below, file with the Federal Energy
Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 14 copies of filings made with the Commission and must mail a
copy to the applicant and to every other party in the proceeding. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be
[[Page 1421]]
required to serve copies of filed documents on all other parties.
However, the non-party commenters will not receive copies of all
documents filed by other parties or issued by the Commission (except
for the mailing of environmental documents issued by the Commission)
and will not have the right to seek court review of the Commission's
final order.
Comments, protests and interventions may be filed electronically
via the Internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and
the instructions on the Commission's Web site under the ``e-Filing''
link.
Comment Date: January 5, 2006.
Magalie R. Salas,
Secretary.
[FR Doc. E6-54 Filed 1-6-06; 8:45 am]
BILLING CODE 6717-01-P