Virginia Electric and Power Company, Surry Power Station, Unit Nos. 1 and 2; Exemption, 75486-75487 [E5-7546]

Download as PDF 75486 Federal Register / Vol. 70, No. 243 / Tuesday, December 20, 2005 / Notices as a result of Hurricane Katrina. Many of the elements of the Waterford 3 emergency response were implemented in the preparation, response, and restoration efforts for Hurricane Katrina. This includes activation of the Waterford 3, parish and state emergency response organizations, evacuation and re-entry of the population, environmental sampling, and assisting Waterford 3 in the plans for restart of the unit. The NRC staff considers the intent of the regulatory requirement is met by having conducted these series of drills and the emergency response to Hurricane Katrina. The NRC staff considers that these measures are adequate to maintain an acceptable level of emergency preparedness during this period, satisfying the underlying purposes of the rule. Therefore, the special circumstances of 10 CFR 50.12(a)(2)(ii) are satisfied. In addition, the staff has concluded that the above drills and exercises provide adequate protection of the public health and safety and are consistent with the common defense and security. Only temporary relief from the regulation is provided by the requested exemption, since Waterford 3 will resume their normal biennial exercise schedule in 2007. The licensee has made a good faith effort to comply with the regulation. The exemption is being sought by the licensee in response to a request by the State of Louisiana to postpone the exercise. Louisiana was unable to support the original schedule for the exercise due to a series of severe weather events. FEMA, in its letter dated October 14, 2005, to the State of Louisiana, stated, ‘‘* * * we concur that the Waterford-3 Radiological Emergency Preparedness (REP) Exercise currently scheduled for December 7, 2005, * * * should be postponed due to the effects of Hurricanes Katrina and Rita on the local infrastructure * * *.’’ The NRC staff, having considered the schedule and resource issues with those agencies that participate in and evaluate the offsite portion of the exercises, concludes that the licensee made a good faith effort to meet the requirements of the regulation. The NRC staff, therefore, concludes that the exemption request meets the special circumstances of 10 CFR 50.12(a)(2)(v) and should be granted. 4.0 Conclusion Accordingly, the Commission has determined that, pursuant to 10 CFR 50.12(a), the exemption is authorized by law, will not present an undue risk to the public health and safety, and is consistent with the common defense VerDate Aug<31>2005 19:23 Dec 19, 2005 Jkt 208001 and security. Additionally, special circumstances are present, which make conducting the exercise impracticable in 2005, and which allow the underlying purposes of the regulation to be served with a postponement. Therefore, the Commission hereby grants Entergy Operations, Inc. an exemption from the requirements of 10 CFR part 50, Appendix E, Sections IV.F.2.b and c for Waterford 3. Pursuant to 10 CFR 51.32, the Commission has determined that the granting of this exemption will not have a significant effect on the quality of the human environment (70 FR 73311). This exemption is effective upon issuance. Dated at Rockville, Maryland, this 13th day of December, 2005. For the Nuclear Regulatory Commission. Catherine Haney, Director, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation. [FR Doc. E5–7544 Filed 12–19–05; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [Docket Nos. 50–280 and 50–281] Virginia Electric and Power Company, Surry Power Station, Unit Nos. 1 and 2; Exemption 1.0 Background The Virginia Electric and Power Company (the licensee) is the holder of Renewed Facility Operating License Nos. DPR–32 and DPR–37 that authorizes operation of the Surry Power Station, Unit Nos. 1 and 2 (Surry). The license provides, among other things, that the facility is subject to all rules, regulations, and orders of the Nuclear Regulatory Commission (NRC, the Commission) now or hereafter in effect. The facility consists of a two pressurized-water reactors located in Surry County, Virginia. 2.0 Request/Action Section IV.F.2.b of Appendix E, to Title 10 of the Code of Federal Regulations (10 CFR) Part 50, requires the licensee at each site to conduct an exercise of its onsite emergency plan biennially. Section IV.F.2.c of Appendix E, to 10 CFR Part 50, states that the offsite plans for each site shall be exercised biennially with full participation by each offsite authority having a role under the plan. During such biennial full participation exercises, the NRC staff evaluates the onsite emergency preparedness PO 00000 Frm 00042 Fmt 4703 Sfmt 4703 activities, and the Federal Emergency Management Agency (FEMA) evaluates the offsite emergency preparedness activities, including interaction with its various State and local emergency management agencies. The licensee successfully conducted a full participation exercise at Surry on July 15, 2003. The licensee had scheduled a full participation Radiological Emergency Preparedness Exercise for December 6, 2005. Because the Virginia Department of Emergency Management (DEM) is currently constructing a new Emergency Operations Center (EOC) and this EOC is not scheduled to be fully operational until January 2, 2006, the Virginia DEM requested approval from FEMA to delay the emergency exercise until February 7, 2006, in order to allow the Virginia DEM to test its new EOC during the exercise at Surry. By letter dated May 20, 2005, FEMA approved Virginia DEM’s request to delay this exercise until the first week of February 2006. Under the current regulations, the licensee would have until December 31, 2005, to complete its next full participation exercise. The licensee plans to conduct a Federally observed full participation emergency exercise on February 7, 2006. Future full participation exercises will be scheduled biennially from the year 2005. By letter dated September 15, 2005, the licensee requested an exemption from the requirements of 10 CFR Part 50, Appendix E, Section IV.F.2.b and c regarding the biennial exercise and participation of the offsite response organizations during a biennial emergency exercise at Surry. Subsequently, the NRC staff has determined that the requirements of 10 CFR Part 50, Appendix E, Section IV.F.2.b and c are applicable to the circumstances of the licensee’s request and that an exemption from those requirements is appropriate. 3.0 Discussion Pursuant to 10 CFR 50.12(a)(1), the Commission may, upon application by any interested person or upon its own initiative, grant exemptions from the requirements of 10 CFR Part 50 when the exemptions are authorized by law, will not present an undue risk to public health or safety, and are consistent with the common defense and security. However, pursuant to 10 CFR 50.12(a)(2), the Commission will not consider granting an exemption unless special circumstances are present. Under 10 CFR 50.12(a)(2)(ii), special circumstances are present when application of the regulation in the E:\FR\FM\20DEN1.SGM 20DEN1 Federal Register / Vol. 70, No. 243 / Tuesday, December 20, 2005 / Notices particular circumstances would not serve the underlying purpose of the rule or is not necessary to achieve the underlying purpose of the rule. Under 10 CFR 50.12(a)(2)(v), special circumstances are present whenever the exemption would provide only temporary relief from the applicable regulation and the licensee or applicant has made good faith efforts to comply with the regulation. The underlying purpose for conducting a biennial exercise is to ensure that emergency response organization personnel are familiar with their duties and to test the adequacy of emergency plans. In order to accommodate the scheduling of full participation exercises, the NRC staff has allowed licensees to schedule the exercises at any time during the calendar biennium. Conducting the full participation exercise at Surry in calendar year 2006 places the exercise past the previously scheduled biennial calendar year of 2005. Since the last full participation exercise conducted at Surry on July 15, 2003, the licensee conducted Full Scale Plume exercises on April 13, 2004, and December 6, 2005, and also performed an unannounced plume phase exercise on August 25, 2004. In addition, four training exercises were conducted. The NRC staff considers the intent of this requirement met by having conducted these series of exercises and drills. The NRC staff considers these measures to be adequate to maintain an acceptable level of emergency preparedness during this period, satisfying the underlying purpose of the rule. Therefore, the special circumstances of 10 CFR 50.12(a)(2)(ii) are satisfied. Only temporary relief from the regulation is provided by the requested exemption since Surry will resume its normal biennial exercise schedule in 2007. The licensee has made a good faith effort to comply with the regulation. The exemption is being sought by the licensee in response to a request by the Virginia DEM to postpone the exercise. The Virginia DEM requested this delay to allow for the completion of the new EOC, which is not scheduled for completion until January 2, 2006. In its letter dated May 20, 2005, FEMA stated that it supports the schedule change from December 6, 2005, to the first week of February 2006. The NRC staff, having considered the schedule and resource issues with those agencies that participate in and evaluate the offsite portion of the full participation exercises, concludes that the licensee made a good faith effort to meet the requirements of the regulation. Therefore, the NRC staff concludes that VerDate Aug<31>2005 19:23 Dec 19, 2005 Jkt 208001 the exemption request meets the special circumstances of 10 CFR 50.12(a)(2)(v) and should be granted. 4.0 Conclusion Accordingly, the Commission has determined that, pursuant to 10 CFR 50.12(a), the exemption is authorized by law, will not present an undue risk to the public health and safety, and is consistent with the common defense and security. Also, special circumstances are present. Therefore, the Commission hereby grants the licensee an exemption from the requirements of 10 CFR Part 50, Appendix E, Section IV.F.2.b and c for Surry, Units 1 and 2. Pursuant to 10 CFR 51.32, the Commission has determined that the granting of this exemption will not have a significant effect on the quality of the human environment (70 FR 72666). This exemption is effective upon issuance. Dated at Rockville, Maryland, this 9th day of December 2005. For the Nuclear Regulatory Commission. Edwin M. Hackett, Acting Director, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation. [FR Doc. E5–7546 Filed 12–19–05; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [Docket No. 50–443] FPL Energy Seabrook, LLC, Seabrook Station Unit No. 1; Environmental Assessment and Finding of No Significant Impact The Nuclear Regulatory Commission (NRC or the Commission) is considering issuance of an amendment pursuant to Title 10 of the Code of Federal Regulations (10 CFR) part 50, for Facility Operating License No. NPF–86 issued to FPL Energy Seabrook, LLC (the licensee), for operation of Seabrook Station, Unit No. 1 (Seabrook), located in Rockingham County, New Hampshire. Therefore, as required by 10 CFR 51.21, the NRC is issuing this environmental assessment and finding of no significant impact. Environmental Assessment Identification of the Proposed Action The proposed action would extend the expiration date of the operating license for Seabrook from October 17, 2026, to March 15, 2030. The proposed action is in accordance with the licensee’s application for PO 00000 Frm 00043 Fmt 4703 Sfmt 4703 75487 amendment dated March 28, 2005, as supplemented September 23, 2005. The Need for the Proposed Action The current operating licensed term for Seabrook ends on October 17, 2026. This is 40 years from the date of the zero-power operating license, which was issued on October 17, 1986. The amendment would extend the expiration date of the operating license from October 17, 2026, to March 15, 2030. The extended date for termination of the operating license would be 40 years after issuance of the full-power operating license which was issued on March 15, 1990. This would allow the licensee to recapture approximately 41 months of additional plant operation for the unit. This proposed amendment is not a request for license renewal pursuant to 10 CFR Part 54. Environmental Impacts of the Proposed Action The NRC has completed its evaluation of the proposed action and concludes that there are no significant environmental considerations involved with the proposed action. The extension of the operating licenses does not affect the design or operation of the plant, does not involve any modifications to the plant or any increase in the licensed power for the plant, and will not create any new or unreviewed environmental impacts that were not considered in the Final Environmental Statement (FES) related to the operation of Seabrook, NUREG–0895, dated December 1982. The evaluations presented in the FES were of the environmental impacts of generating power at Seabrook and the basis for granting a 40-year operating license for Seabrook. The environmental impacts of the proposed action are based on the evaluations in the FES. It should be noted that the Seabrook license was amended on February 28, 2005, to allow an increase in maximum core power by 5.2% (from 3411 megawatts thermal (MWt) to 3587 MWt). The environmental assessment of the power uprate was published in the Federal Register on February 14, 2005 (70 FR 7525). The FES which, in general, assesses various impacts associated with operation of the facility in terms of annual impacts, and balances these against the anticipated annual energy production benefits. The offsite exposure from releases during postulated accidents has been previously evaluated in the Updated Final Safety Analysis Report (UFSAR) for Seabrook. The results are acceptable when compared with the criteria defined in 10 CFR Part 100, as E:\FR\FM\20DEN1.SGM 20DEN1

Agencies

[Federal Register Volume 70, Number 243 (Tuesday, December 20, 2005)]
[Notices]
[Pages 75486-75487]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-7546]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-280 and 50-281]


Virginia Electric and Power Company, Surry Power Station, Unit 
Nos. 1 and 2; Exemption

1.0 Background

    The Virginia Electric and Power Company (the licensee) is the 
holder of Renewed Facility Operating License Nos. DPR-32 and DPR-37 
that authorizes operation of the Surry Power Station, Unit Nos. 1 and 2 
(Surry). The license provides, among other things, that the facility is 
subject to all rules, regulations, and orders of the Nuclear Regulatory 
Commission (NRC, the Commission) now or hereafter in effect.
    The facility consists of a two pressurized-water reactors located 
in Surry County, Virginia.

2.0 Request/Action

    Section IV.F.2.b of Appendix E, to Title 10 of the Code of Federal 
Regulations (10 CFR) Part 50, requires the licensee at each site to 
conduct an exercise of its onsite emergency plan biennially. Section 
IV.F.2.c of Appendix E, to 10 CFR Part 50, states that the offsite 
plans for each site shall be exercised biennially with full 
participation by each offsite authority having a role under the plan. 
During such biennial full participation exercises, the NRC staff 
evaluates the onsite emergency preparedness activities, and the Federal 
Emergency Management Agency (FEMA) evaluates the offsite emergency 
preparedness activities, including interaction with its various State 
and local emergency management agencies. The licensee successfully 
conducted a full participation exercise at Surry on July 15, 2003.
    The licensee had scheduled a full participation Radiological 
Emergency Preparedness Exercise for December 6, 2005. Because the 
Virginia Department of Emergency Management (DEM) is currently 
constructing a new Emergency Operations Center (EOC) and this EOC is 
not scheduled to be fully operational until January 2, 2006, the 
Virginia DEM requested approval from FEMA to delay the emergency 
exercise until February 7, 2006, in order to allow the Virginia DEM to 
test its new EOC during the exercise at Surry. By letter dated May 20, 
2005, FEMA approved Virginia DEM's request to delay this exercise until 
the first week of February 2006. Under the current regulations, the 
licensee would have until December 31, 2005, to complete its next full 
participation exercise. The licensee plans to conduct a Federally 
observed full participation emergency exercise on February 7, 2006. 
Future full participation exercises will be scheduled biennially from 
the year 2005.
    By letter dated September 15, 2005, the licensee requested an 
exemption from the requirements of 10 CFR Part 50, Appendix E, Section 
IV.F.2.b and c regarding the biennial exercise and participation of the 
offsite response organizations during a biennial emergency exercise at 
Surry. Subsequently, the NRC staff has determined that the requirements 
of 10 CFR Part 50, Appendix E, Section IV.F.2.b and c are applicable to 
the circumstances of the licensee's request and that an exemption from 
those requirements is appropriate.

3.0 Discussion

    Pursuant to 10 CFR 50.12(a)(1), the Commission may, upon 
application by any interested person or upon its own initiative, grant 
exemptions from the requirements of 10 CFR Part 50 when the exemptions 
are authorized by law, will not present an undue risk to public health 
or safety, and are consistent with the common defense and security. 
However, pursuant to 10 CFR 50.12(a)(2), the Commission will not 
consider granting an exemption unless special circumstances are 
present. Under 10 CFR 50.12(a)(2)(ii), special circumstances are 
present when application of the regulation in the

[[Page 75487]]

particular circumstances would not serve the underlying purpose of the 
rule or is not necessary to achieve the underlying purpose of the rule. 
Under 10 CFR 50.12(a)(2)(v), special circumstances are present whenever 
the exemption would provide only temporary relief from the applicable 
regulation and the licensee or applicant has made good faith efforts to 
comply with the regulation.
    The underlying purpose for conducting a biennial exercise is to 
ensure that emergency response organization personnel are familiar with 
their duties and to test the adequacy of emergency plans. In order to 
accommodate the scheduling of full participation exercises, the NRC 
staff has allowed licensees to schedule the exercises at any time 
during the calendar biennium. Conducting the full participation 
exercise at Surry in calendar year 2006 places the exercise past the 
previously scheduled biennial calendar year of 2005.
    Since the last full participation exercise conducted at Surry on 
July 15, 2003, the licensee conducted Full Scale Plume exercises on 
April 13, 2004, and December 6, 2005, and also performed an unannounced 
plume phase exercise on August 25, 2004. In addition, four training 
exercises were conducted. The NRC staff considers the intent of this 
requirement met by having conducted these series of exercises and 
drills. The NRC staff considers these measures to be adequate to 
maintain an acceptable level of emergency preparedness during this 
period, satisfying the underlying purpose of the rule. Therefore, the 
special circumstances of 10 CFR 50.12(a)(2)(ii) are satisfied.
    Only temporary relief from the regulation is provided by the 
requested exemption since Surry will resume its normal biennial 
exercise schedule in 2007. The licensee has made a good faith effort to 
comply with the regulation. The exemption is being sought by the 
licensee in response to a request by the Virginia DEM to postpone the 
exercise. The Virginia DEM requested this delay to allow for the 
completion of the new EOC, which is not scheduled for completion until 
January 2, 2006. In its letter dated May 20, 2005, FEMA stated that it 
supports the schedule change from December 6, 2005, to the first week 
of February 2006.
    The NRC staff, having considered the schedule and resource issues 
with those agencies that participate in and evaluate the offsite 
portion of the full participation exercises, concludes that the 
licensee made a good faith effort to meet the requirements of the 
regulation. Therefore, the NRC staff concludes that the exemption 
request meets the special circumstances of 10 CFR 50.12(a)(2)(v) and 
should be granted.

4.0 Conclusion

    Accordingly, the Commission has determined that, pursuant to 10 CFR 
50.12(a), the exemption is authorized by law, will not present an undue 
risk to the public health and safety, and is consistent with the common 
defense and security. Also, special circumstances are present. 
Therefore, the Commission hereby grants the licensee an exemption from 
the requirements of 10 CFR Part 50, Appendix E, Section IV.F.2.b and c 
for Surry, Units 1 and 2.
    Pursuant to 10 CFR 51.32, the Commission has determined that the 
granting of this exemption will not have a significant effect on the 
quality of the human environment (70 FR 72666).
    This exemption is effective upon issuance.

    Dated at Rockville, Maryland, this 9th day of December 2005.

    For the Nuclear Regulatory Commission.
Edwin M. Hackett,
 Acting Director, Division of Operating Reactor Licensing, Office of 
Nuclear Reactor Regulation.
[FR Doc. E5-7546 Filed 12-19-05; 8:45 am]
BILLING CODE 7590-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.