Virginia Electric and Power Company, Surry Power Station, Unit Nos. 1 and 2; Exemption, 75486-75487 [E5-7546]
Download as PDF
75486
Federal Register / Vol. 70, No. 243 / Tuesday, December 20, 2005 / Notices
as a result of Hurricane Katrina. Many
of the elements of the Waterford 3
emergency response were implemented
in the preparation, response, and
restoration efforts for Hurricane Katrina.
This includes activation of the
Waterford 3, parish and state emergency
response organizations, evacuation and
re-entry of the population,
environmental sampling, and assisting
Waterford 3 in the plans for restart of
the unit.
The NRC staff considers the intent of
the regulatory requirement is met by
having conducted these series of drills
and the emergency response to
Hurricane Katrina. The NRC staff
considers that these measures are
adequate to maintain an acceptable level
of emergency preparedness during this
period, satisfying the underlying
purposes of the rule. Therefore, the
special circumstances of 10 CFR
50.12(a)(2)(ii) are satisfied. In addition,
the staff has concluded that the above
drills and exercises provide adequate
protection of the public health and
safety and are consistent with the
common defense and security.
Only temporary relief from the
regulation is provided by the requested
exemption, since Waterford 3 will
resume their normal biennial exercise
schedule in 2007. The licensee has
made a good faith effort to comply with
the regulation. The exemption is being
sought by the licensee in response to a
request by the State of Louisiana to
postpone the exercise. Louisiana was
unable to support the original schedule
for the exercise due to a series of severe
weather events. FEMA, in its letter
dated October 14, 2005, to the State of
Louisiana, stated, ‘‘* * * we concur that
the Waterford-3 Radiological Emergency
Preparedness (REP) Exercise currently
scheduled for December 7, 2005, * * *
should be postponed due to the effects
of Hurricanes Katrina and Rita on the
local infrastructure * * *.’’
The NRC staff, having considered the
schedule and resource issues with those
agencies that participate in and evaluate
the offsite portion of the exercises,
concludes that the licensee made a good
faith effort to meet the requirements of
the regulation. The NRC staff, therefore,
concludes that the exemption request
meets the special circumstances of 10
CFR 50.12(a)(2)(v) and should be
granted.
4.0 Conclusion
Accordingly, the Commission has
determined that, pursuant to 10 CFR
50.12(a), the exemption is authorized by
law, will not present an undue risk to
the public health and safety, and is
consistent with the common defense
VerDate Aug<31>2005
19:23 Dec 19, 2005
Jkt 208001
and security. Additionally, special
circumstances are present, which make
conducting the exercise impracticable in
2005, and which allow the underlying
purposes of the regulation to be served
with a postponement. Therefore, the
Commission hereby grants Entergy
Operations, Inc. an exemption from the
requirements of 10 CFR part 50,
Appendix E, Sections IV.F.2.b and c for
Waterford 3.
Pursuant to 10 CFR 51.32, the
Commission has determined that the
granting of this exemption will not have
a significant effect on the quality of the
human environment (70 FR 73311).
This exemption is effective upon
issuance.
Dated at Rockville, Maryland, this 13th day
of December, 2005.
For the Nuclear Regulatory Commission.
Catherine Haney,
Director, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. E5–7544 Filed 12–19–05; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–280 and 50–281]
Virginia Electric and Power Company,
Surry Power Station, Unit Nos. 1 and
2; Exemption
1.0 Background
The Virginia Electric and Power
Company (the licensee) is the holder of
Renewed Facility Operating License
Nos. DPR–32 and DPR–37 that
authorizes operation of the Surry Power
Station, Unit Nos. 1 and 2 (Surry). The
license provides, among other things,
that the facility is subject to all rules,
regulations, and orders of the Nuclear
Regulatory Commission (NRC, the
Commission) now or hereafter in effect.
The facility consists of a two
pressurized-water reactors located in
Surry County, Virginia.
2.0 Request/Action
Section IV.F.2.b of Appendix E, to
Title 10 of the Code of Federal
Regulations (10 CFR) Part 50, requires
the licensee at each site to conduct an
exercise of its onsite emergency plan
biennially. Section IV.F.2.c of Appendix
E, to 10 CFR Part 50, states that the
offsite plans for each site shall be
exercised biennially with full
participation by each offsite authority
having a role under the plan. During
such biennial full participation
exercises, the NRC staff evaluates the
onsite emergency preparedness
PO 00000
Frm 00042
Fmt 4703
Sfmt 4703
activities, and the Federal Emergency
Management Agency (FEMA) evaluates
the offsite emergency preparedness
activities, including interaction with its
various State and local emergency
management agencies. The licensee
successfully conducted a full
participation exercise at Surry on July
15, 2003.
The licensee had scheduled a full
participation Radiological Emergency
Preparedness Exercise for December 6,
2005. Because the Virginia Department
of Emergency Management (DEM) is
currently constructing a new Emergency
Operations Center (EOC) and this EOC
is not scheduled to be fully operational
until January 2, 2006, the Virginia DEM
requested approval from FEMA to delay
the emergency exercise until February 7,
2006, in order to allow the Virginia
DEM to test its new EOC during the
exercise at Surry. By letter dated May
20, 2005, FEMA approved Virginia
DEM’s request to delay this exercise
until the first week of February 2006.
Under the current regulations, the
licensee would have until December 31,
2005, to complete its next full
participation exercise. The licensee
plans to conduct a Federally observed
full participation emergency exercise on
February 7, 2006. Future full
participation exercises will be
scheduled biennially from the year
2005.
By letter dated September 15, 2005,
the licensee requested an exemption
from the requirements of 10 CFR Part
50, Appendix E, Section IV.F.2.b and c
regarding the biennial exercise and
participation of the offsite response
organizations during a biennial
emergency exercise at Surry.
Subsequently, the NRC staff has
determined that the requirements of 10
CFR Part 50, Appendix E, Section
IV.F.2.b and c are applicable to the
circumstances of the licensee’s request
and that an exemption from those
requirements is appropriate.
3.0 Discussion
Pursuant to 10 CFR 50.12(a)(1), the
Commission may, upon application by
any interested person or upon its own
initiative, grant exemptions from the
requirements of 10 CFR Part 50 when
the exemptions are authorized by law,
will not present an undue risk to public
health or safety, and are consistent with
the common defense and security.
However, pursuant to 10 CFR
50.12(a)(2), the Commission will not
consider granting an exemption unless
special circumstances are present.
Under 10 CFR 50.12(a)(2)(ii), special
circumstances are present when
application of the regulation in the
E:\FR\FM\20DEN1.SGM
20DEN1
Federal Register / Vol. 70, No. 243 / Tuesday, December 20, 2005 / Notices
particular circumstances would not
serve the underlying purpose of the rule
or is not necessary to achieve the
underlying purpose of the rule. Under
10 CFR 50.12(a)(2)(v), special
circumstances are present whenever the
exemption would provide only
temporary relief from the applicable
regulation and the licensee or applicant
has made good faith efforts to comply
with the regulation.
The underlying purpose for
conducting a biennial exercise is to
ensure that emergency response
organization personnel are familiar with
their duties and to test the adequacy of
emergency plans. In order to
accommodate the scheduling of full
participation exercises, the NRC staff
has allowed licensees to schedule the
exercises at any time during the
calendar biennium. Conducting the full
participation exercise at Surry in
calendar year 2006 places the exercise
past the previously scheduled biennial
calendar year of 2005.
Since the last full participation
exercise conducted at Surry on July 15,
2003, the licensee conducted Full Scale
Plume exercises on April 13, 2004, and
December 6, 2005, and also performed
an unannounced plume phase exercise
on August 25, 2004. In addition, four
training exercises were conducted. The
NRC staff considers the intent of this
requirement met by having conducted
these series of exercises and drills. The
NRC staff considers these measures to
be adequate to maintain an acceptable
level of emergency preparedness during
this period, satisfying the underlying
purpose of the rule. Therefore, the
special circumstances of 10 CFR
50.12(a)(2)(ii) are satisfied.
Only temporary relief from the
regulation is provided by the requested
exemption since Surry will resume its
normal biennial exercise schedule in
2007. The licensee has made a good
faith effort to comply with the
regulation. The exemption is being
sought by the licensee in response to a
request by the Virginia DEM to postpone
the exercise. The Virginia DEM
requested this delay to allow for the
completion of the new EOC, which is
not scheduled for completion until
January 2, 2006. In its letter dated May
20, 2005, FEMA stated that it supports
the schedule change from December 6,
2005, to the first week of February 2006.
The NRC staff, having considered the
schedule and resource issues with those
agencies that participate in and evaluate
the offsite portion of the full
participation exercises, concludes that
the licensee made a good faith effort to
meet the requirements of the regulation.
Therefore, the NRC staff concludes that
VerDate Aug<31>2005
19:23 Dec 19, 2005
Jkt 208001
the exemption request meets the special
circumstances of 10 CFR 50.12(a)(2)(v)
and should be granted.
4.0 Conclusion
Accordingly, the Commission has
determined that, pursuant to 10 CFR
50.12(a), the exemption is authorized by
law, will not present an undue risk to
the public health and safety, and is
consistent with the common defense
and security. Also, special
circumstances are present. Therefore,
the Commission hereby grants the
licensee an exemption from the
requirements of 10 CFR Part 50,
Appendix E, Section IV.F.2.b and c for
Surry, Units 1 and 2.
Pursuant to 10 CFR 51.32, the
Commission has determined that the
granting of this exemption will not have
a significant effect on the quality of the
human environment (70 FR 72666).
This exemption is effective upon
issuance.
Dated at Rockville, Maryland, this 9th day
of December 2005.
For the Nuclear Regulatory Commission.
Edwin M. Hackett,
Acting Director, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. E5–7546 Filed 12–19–05; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–443]
FPL Energy Seabrook, LLC, Seabrook
Station Unit No. 1; Environmental
Assessment and Finding of No
Significant Impact
The Nuclear Regulatory Commission
(NRC or the Commission) is considering
issuance of an amendment pursuant to
Title 10 of the Code of Federal
Regulations (10 CFR) part 50, for
Facility Operating License No. NPF–86
issued to FPL Energy Seabrook, LLC (the
licensee), for operation of Seabrook
Station, Unit No. 1 (Seabrook), located
in Rockingham County, New
Hampshire. Therefore, as required by 10
CFR 51.21, the NRC is issuing this
environmental assessment and finding
of no significant impact.
Environmental Assessment
Identification of the Proposed Action
The proposed action would extend
the expiration date of the operating
license for Seabrook from October 17,
2026, to March 15, 2030.
The proposed action is in accordance
with the licensee’s application for
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
75487
amendment dated March 28, 2005, as
supplemented September 23, 2005.
The Need for the Proposed Action
The current operating licensed term
for Seabrook ends on October 17, 2026.
This is 40 years from the date of the
zero-power operating license, which
was issued on October 17, 1986. The
amendment would extend the
expiration date of the operating license
from October 17, 2026, to March 15,
2030. The extended date for termination
of the operating license would be 40
years after issuance of the full-power
operating license which was issued on
March 15, 1990. This would allow the
licensee to recapture approximately 41
months of additional plant operation for
the unit. This proposed amendment is
not a request for license renewal
pursuant to 10 CFR Part 54.
Environmental Impacts of the Proposed
Action
The NRC has completed its evaluation
of the proposed action and concludes
that there are no significant
environmental considerations involved
with the proposed action. The extension
of the operating licenses does not affect
the design or operation of the plant,
does not involve any modifications to
the plant or any increase in the licensed
power for the plant, and will not create
any new or unreviewed environmental
impacts that were not considered in the
Final Environmental Statement (FES)
related to the operation of Seabrook,
NUREG–0895, dated December 1982.
The evaluations presented in the FES
were of the environmental impacts of
generating power at Seabrook and the
basis for granting a 40-year operating
license for Seabrook. The environmental
impacts of the proposed action are
based on the evaluations in the FES. It
should be noted that the Seabrook
license was amended on February 28,
2005, to allow an increase in maximum
core power by 5.2% (from 3411
megawatts thermal (MWt) to 3587
MWt). The environmental assessment of
the power uprate was published in the
Federal Register on February 14, 2005
(70 FR 7525).
The FES which, in general, assesses
various impacts associated with
operation of the facility in terms of
annual impacts, and balances these
against the anticipated annual energy
production benefits.
The offsite exposure from releases
during postulated accidents has been
previously evaluated in the Updated
Final Safety Analysis Report (UFSAR)
for Seabrook. The results are acceptable
when compared with the criteria
defined in 10 CFR Part 100, as
E:\FR\FM\20DEN1.SGM
20DEN1
Agencies
[Federal Register Volume 70, Number 243 (Tuesday, December 20, 2005)]
[Notices]
[Pages 75486-75487]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-7546]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-280 and 50-281]
Virginia Electric and Power Company, Surry Power Station, Unit
Nos. 1 and 2; Exemption
1.0 Background
The Virginia Electric and Power Company (the licensee) is the
holder of Renewed Facility Operating License Nos. DPR-32 and DPR-37
that authorizes operation of the Surry Power Station, Unit Nos. 1 and 2
(Surry). The license provides, among other things, that the facility is
subject to all rules, regulations, and orders of the Nuclear Regulatory
Commission (NRC, the Commission) now or hereafter in effect.
The facility consists of a two pressurized-water reactors located
in Surry County, Virginia.
2.0 Request/Action
Section IV.F.2.b of Appendix E, to Title 10 of the Code of Federal
Regulations (10 CFR) Part 50, requires the licensee at each site to
conduct an exercise of its onsite emergency plan biennially. Section
IV.F.2.c of Appendix E, to 10 CFR Part 50, states that the offsite
plans for each site shall be exercised biennially with full
participation by each offsite authority having a role under the plan.
During such biennial full participation exercises, the NRC staff
evaluates the onsite emergency preparedness activities, and the Federal
Emergency Management Agency (FEMA) evaluates the offsite emergency
preparedness activities, including interaction with its various State
and local emergency management agencies. The licensee successfully
conducted a full participation exercise at Surry on July 15, 2003.
The licensee had scheduled a full participation Radiological
Emergency Preparedness Exercise for December 6, 2005. Because the
Virginia Department of Emergency Management (DEM) is currently
constructing a new Emergency Operations Center (EOC) and this EOC is
not scheduled to be fully operational until January 2, 2006, the
Virginia DEM requested approval from FEMA to delay the emergency
exercise until February 7, 2006, in order to allow the Virginia DEM to
test its new EOC during the exercise at Surry. By letter dated May 20,
2005, FEMA approved Virginia DEM's request to delay this exercise until
the first week of February 2006. Under the current regulations, the
licensee would have until December 31, 2005, to complete its next full
participation exercise. The licensee plans to conduct a Federally
observed full participation emergency exercise on February 7, 2006.
Future full participation exercises will be scheduled biennially from
the year 2005.
By letter dated September 15, 2005, the licensee requested an
exemption from the requirements of 10 CFR Part 50, Appendix E, Section
IV.F.2.b and c regarding the biennial exercise and participation of the
offsite response organizations during a biennial emergency exercise at
Surry. Subsequently, the NRC staff has determined that the requirements
of 10 CFR Part 50, Appendix E, Section IV.F.2.b and c are applicable to
the circumstances of the licensee's request and that an exemption from
those requirements is appropriate.
3.0 Discussion
Pursuant to 10 CFR 50.12(a)(1), the Commission may, upon
application by any interested person or upon its own initiative, grant
exemptions from the requirements of 10 CFR Part 50 when the exemptions
are authorized by law, will not present an undue risk to public health
or safety, and are consistent with the common defense and security.
However, pursuant to 10 CFR 50.12(a)(2), the Commission will not
consider granting an exemption unless special circumstances are
present. Under 10 CFR 50.12(a)(2)(ii), special circumstances are
present when application of the regulation in the
[[Page 75487]]
particular circumstances would not serve the underlying purpose of the
rule or is not necessary to achieve the underlying purpose of the rule.
Under 10 CFR 50.12(a)(2)(v), special circumstances are present whenever
the exemption would provide only temporary relief from the applicable
regulation and the licensee or applicant has made good faith efforts to
comply with the regulation.
The underlying purpose for conducting a biennial exercise is to
ensure that emergency response organization personnel are familiar with
their duties and to test the adequacy of emergency plans. In order to
accommodate the scheduling of full participation exercises, the NRC
staff has allowed licensees to schedule the exercises at any time
during the calendar biennium. Conducting the full participation
exercise at Surry in calendar year 2006 places the exercise past the
previously scheduled biennial calendar year of 2005.
Since the last full participation exercise conducted at Surry on
July 15, 2003, the licensee conducted Full Scale Plume exercises on
April 13, 2004, and December 6, 2005, and also performed an unannounced
plume phase exercise on August 25, 2004. In addition, four training
exercises were conducted. The NRC staff considers the intent of this
requirement met by having conducted these series of exercises and
drills. The NRC staff considers these measures to be adequate to
maintain an acceptable level of emergency preparedness during this
period, satisfying the underlying purpose of the rule. Therefore, the
special circumstances of 10 CFR 50.12(a)(2)(ii) are satisfied.
Only temporary relief from the regulation is provided by the
requested exemption since Surry will resume its normal biennial
exercise schedule in 2007. The licensee has made a good faith effort to
comply with the regulation. The exemption is being sought by the
licensee in response to a request by the Virginia DEM to postpone the
exercise. The Virginia DEM requested this delay to allow for the
completion of the new EOC, which is not scheduled for completion until
January 2, 2006. In its letter dated May 20, 2005, FEMA stated that it
supports the schedule change from December 6, 2005, to the first week
of February 2006.
The NRC staff, having considered the schedule and resource issues
with those agencies that participate in and evaluate the offsite
portion of the full participation exercises, concludes that the
licensee made a good faith effort to meet the requirements of the
regulation. Therefore, the NRC staff concludes that the exemption
request meets the special circumstances of 10 CFR 50.12(a)(2)(v) and
should be granted.
4.0 Conclusion
Accordingly, the Commission has determined that, pursuant to 10 CFR
50.12(a), the exemption is authorized by law, will not present an undue
risk to the public health and safety, and is consistent with the common
defense and security. Also, special circumstances are present.
Therefore, the Commission hereby grants the licensee an exemption from
the requirements of 10 CFR Part 50, Appendix E, Section IV.F.2.b and c
for Surry, Units 1 and 2.
Pursuant to 10 CFR 51.32, the Commission has determined that the
granting of this exemption will not have a significant effect on the
quality of the human environment (70 FR 72666).
This exemption is effective upon issuance.
Dated at Rockville, Maryland, this 9th day of December 2005.
For the Nuclear Regulatory Commission.
Edwin M. Hackett,
Acting Director, Division of Operating Reactor Licensing, Office of
Nuclear Reactor Regulation.
[FR Doc. E5-7546 Filed 12-19-05; 8:45 am]
BILLING CODE 7590-01-P