FPL Energy Seabrook, LLC, Seabrook Station Unit No. 1; Environmental Assessment and Finding of No Significant Impact, 75487-75488 [E5-7515]
Download as PDF
Federal Register / Vol. 70, No. 243 / Tuesday, December 20, 2005 / Notices
particular circumstances would not
serve the underlying purpose of the rule
or is not necessary to achieve the
underlying purpose of the rule. Under
10 CFR 50.12(a)(2)(v), special
circumstances are present whenever the
exemption would provide only
temporary relief from the applicable
regulation and the licensee or applicant
has made good faith efforts to comply
with the regulation.
The underlying purpose for
conducting a biennial exercise is to
ensure that emergency response
organization personnel are familiar with
their duties and to test the adequacy of
emergency plans. In order to
accommodate the scheduling of full
participation exercises, the NRC staff
has allowed licensees to schedule the
exercises at any time during the
calendar biennium. Conducting the full
participation exercise at Surry in
calendar year 2006 places the exercise
past the previously scheduled biennial
calendar year of 2005.
Since the last full participation
exercise conducted at Surry on July 15,
2003, the licensee conducted Full Scale
Plume exercises on April 13, 2004, and
December 6, 2005, and also performed
an unannounced plume phase exercise
on August 25, 2004. In addition, four
training exercises were conducted. The
NRC staff considers the intent of this
requirement met by having conducted
these series of exercises and drills. The
NRC staff considers these measures to
be adequate to maintain an acceptable
level of emergency preparedness during
this period, satisfying the underlying
purpose of the rule. Therefore, the
special circumstances of 10 CFR
50.12(a)(2)(ii) are satisfied.
Only temporary relief from the
regulation is provided by the requested
exemption since Surry will resume its
normal biennial exercise schedule in
2007. The licensee has made a good
faith effort to comply with the
regulation. The exemption is being
sought by the licensee in response to a
request by the Virginia DEM to postpone
the exercise. The Virginia DEM
requested this delay to allow for the
completion of the new EOC, which is
not scheduled for completion until
January 2, 2006. In its letter dated May
20, 2005, FEMA stated that it supports
the schedule change from December 6,
2005, to the first week of February 2006.
The NRC staff, having considered the
schedule and resource issues with those
agencies that participate in and evaluate
the offsite portion of the full
participation exercises, concludes that
the licensee made a good faith effort to
meet the requirements of the regulation.
Therefore, the NRC staff concludes that
VerDate Aug<31>2005
19:23 Dec 19, 2005
Jkt 208001
the exemption request meets the special
circumstances of 10 CFR 50.12(a)(2)(v)
and should be granted.
4.0 Conclusion
Accordingly, the Commission has
determined that, pursuant to 10 CFR
50.12(a), the exemption is authorized by
law, will not present an undue risk to
the public health and safety, and is
consistent with the common defense
and security. Also, special
circumstances are present. Therefore,
the Commission hereby grants the
licensee an exemption from the
requirements of 10 CFR Part 50,
Appendix E, Section IV.F.2.b and c for
Surry, Units 1 and 2.
Pursuant to 10 CFR 51.32, the
Commission has determined that the
granting of this exemption will not have
a significant effect on the quality of the
human environment (70 FR 72666).
This exemption is effective upon
issuance.
Dated at Rockville, Maryland, this 9th day
of December 2005.
For the Nuclear Regulatory Commission.
Edwin M. Hackett,
Acting Director, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. E5–7546 Filed 12–19–05; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–443]
FPL Energy Seabrook, LLC, Seabrook
Station Unit No. 1; Environmental
Assessment and Finding of No
Significant Impact
The Nuclear Regulatory Commission
(NRC or the Commission) is considering
issuance of an amendment pursuant to
Title 10 of the Code of Federal
Regulations (10 CFR) part 50, for
Facility Operating License No. NPF–86
issued to FPL Energy Seabrook, LLC (the
licensee), for operation of Seabrook
Station, Unit No. 1 (Seabrook), located
in Rockingham County, New
Hampshire. Therefore, as required by 10
CFR 51.21, the NRC is issuing this
environmental assessment and finding
of no significant impact.
Environmental Assessment
Identification of the Proposed Action
The proposed action would extend
the expiration date of the operating
license for Seabrook from October 17,
2026, to March 15, 2030.
The proposed action is in accordance
with the licensee’s application for
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
75487
amendment dated March 28, 2005, as
supplemented September 23, 2005.
The Need for the Proposed Action
The current operating licensed term
for Seabrook ends on October 17, 2026.
This is 40 years from the date of the
zero-power operating license, which
was issued on October 17, 1986. The
amendment would extend the
expiration date of the operating license
from October 17, 2026, to March 15,
2030. The extended date for termination
of the operating license would be 40
years after issuance of the full-power
operating license which was issued on
March 15, 1990. This would allow the
licensee to recapture approximately 41
months of additional plant operation for
the unit. This proposed amendment is
not a request for license renewal
pursuant to 10 CFR Part 54.
Environmental Impacts of the Proposed
Action
The NRC has completed its evaluation
of the proposed action and concludes
that there are no significant
environmental considerations involved
with the proposed action. The extension
of the operating licenses does not affect
the design or operation of the plant,
does not involve any modifications to
the plant or any increase in the licensed
power for the plant, and will not create
any new or unreviewed environmental
impacts that were not considered in the
Final Environmental Statement (FES)
related to the operation of Seabrook,
NUREG–0895, dated December 1982.
The evaluations presented in the FES
were of the environmental impacts of
generating power at Seabrook and the
basis for granting a 40-year operating
license for Seabrook. The environmental
impacts of the proposed action are
based on the evaluations in the FES. It
should be noted that the Seabrook
license was amended on February 28,
2005, to allow an increase in maximum
core power by 5.2% (from 3411
megawatts thermal (MWt) to 3587
MWt). The environmental assessment of
the power uprate was published in the
Federal Register on February 14, 2005
(70 FR 7525).
The FES which, in general, assesses
various impacts associated with
operation of the facility in terms of
annual impacts, and balances these
against the anticipated annual energy
production benefits.
The offsite exposure from releases
during postulated accidents has been
previously evaluated in the Updated
Final Safety Analysis Report (UFSAR)
for Seabrook. The results are acceptable
when compared with the criteria
defined in 10 CFR Part 100, as
E:\FR\FM\20DEN1.SGM
20DEN1
75488
Federal Register / Vol. 70, No. 243 / Tuesday, December 20, 2005 / Notices
documented in the Commission’s Safety
Evaluation Report, NUREG–0896, dated
March 1983, and its nine supplements.
As a result of this action there is no
change in the types, frequency, or
consequences of design-basis accidents.
The NRC staff has concluded that the
impacts associated with the addition of
approximately 41 months to the license
expiration date are not significantly
different from the operating license
duration assessed in the Seabrook FES.
Therefore, the staff concluded that the
FES sufficiently addresses the
environmental impacts associated with
a full 40-year operating period for
Seabrook.
The annual occupational exposure of
workers at the plant, station employees
and contractors, is reported in the
Annual Operating Report submitted by
the licensee. The lowest exposure value
is for a year without a refueling outage,
and the highest value is for a year with
a refueling outage. In Section 5.9.3.1.1
of the FES, the average occupational
exposure for a pressurized water reactor
was reported as 440 person-rems.
Therefore, the expected annual
occupational exposure for the proposed
extended period of operation does not
change previous conclusions presented
in the FES on occupational exposure.
The offsite exposure from releases
during routine operations has been
previously evaluated in Section 5.9.3 of
the FES. During the low-power license,
the plant was restricted to no more than
five percent of rated power for no longer
than 0.75 effective full power hours, and
the generation of radioactivity at the
plant was significantly smaller than
would have occurred if the plant were
at full-power operation. Therefore, the
addition of approximately 41 months of
operation that the licensee has
requested does not change previous
conclusions presented in the FES on
annual public doses.
The proposed action will not
significantly increase the probability or
consequences of accidents, no changes
are being made in the types of effluents
that may be released off site, and there
is no significant increase in
occupational or public radiation
exposure. Therefore, there are no
significant radiological environmental
impacts associated with the proposed
action.
With regard to potential
nonradiological impacts, the proposed
action does not have a potential to affect
any historic sites. It does not affect
nonradiological plant effluents and has
no other environmental impact.
Therefore, there are no significant
nonradiological environmental impacts
associated with the proposed action.
VerDate Aug<31>2005
19:23 Dec 19, 2005
Jkt 208001
Accordingly, the NRC concluded that
there are no significant environmental
impacts associated with the proposed
action.
Environmental Impacts of the
Alternatives to the Proposed Action
As an alternative to the proposed
action, the staff considered denial of the
proposed action (i.e., the ‘‘no-action’’
alternative). Denial of the application
would result in no change in current
environmental impacts. The
environmental impacts of the proposed
action and the alternative action are
similar.
For the Nuclear Regulatory Commission.
Darrell J. Roberts,
Branch Chief, Plant Licensing Branch I–2,
Division of Operating Reactor Licensing,
Office of Nuclear Reactor Regulation.
[FR Doc. E5–7515 Filed 12–19–05; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
Sunshine Act; Notice of Meetings
The action does not involve the use of
any different resource than those
previously considered in the FES for
Seabrook.
AGENCY HOLDING THE MEETINGS: Nuclear
Regulatory Commission.
DATES: Weeks of December 19, 26, 2005,
January 2, 9, 16, 23, 2006.
PLACE: Commissioners’ Conference
Room, 11555 Rockville Pike, Rockville,
Maryland.
STATUS: Public and Closed.
Agencies and Persons Consulted
Matters To Be Considered:
On December 8, 2005, the staff
consulted with the New Hampshire
State official, Mr. Mike Nawoj, and the
Massachusetts State official, Mr. James
Muckerheid, regarding the
environmental impact of the proposed
action. The State officials had no
comments.
Week of December 19, 2005
Finding of No Significant Impact
There are no meetings scheduled for
the Week of January 2, 2006.
Alternative Use of Resources
On the basis of the environmental
assessment, the NRC concluded that the
proposed action will not have a
significant effect on the quality of the
human environment. Accordingly, the
NRC has determined not to prepare an
environmental impact statement for the
proposed action.
For further details with respect to the
proposed action, see the licensee’s letter
dated March 28, 2005 as supplemented
September 23, 2005. Documents may be
examined, and/or copied for a fee, at the
NRC’s Public Document Room (PDR),
located at One White Flint North, Public
File Area O1 F21, 11555 Rockville Pike
(first floor), Rockville, Maryland.
Publicly available records will be
accessible electronically from the
Agencywide Documents Access and
Management System (ADAMS) Public
Electronic Reading Room on the Internet
at the NRC Web site, https://
www.nrc.gov/reading-rm/adams.html.
Persons who do not have access to
ADAMS or who encounter problems in
accessing the documents located in
ADAMS, should contact the NRC PDR
reference staff by telephone at 1–800–
397–4209 or 301–415–4737, or by e-mail
to pdr@nrc.gov.
Dated at Rockville, Maryland, this 6th day
of December 2005.
PO 00000
Frm 00044
Fmt 4703
Sfmt 4703
There are no meetings scheduled for
the Week of December 19, 2005.
Week of December 26, 2005—Tentative
There are no meetings scheduled for
the Week of December 26, 2005.
Week of January 2, 2006—Tentative
Week of January 9, 2006—Tentative
Tuesday, January 10, 2006
9:30 a.m.—Briefing on International
Research and Bilateral Agreements.
(Contact: Roman Shaffer, 301–415–
7606).
This meeting will be webcast live at
the Web address: https://www.nrc.gov.
Wednesday, January 11, 2006
9:30 a.m.—Meeting with Advisory
Committee on Nuclear Waste
(ACNW). (Contact: John Larkins,
301–415–7360).
This meeting will be webcast live at
the Web address: https://www.nrc.gov.
Thursday, January 12, 2006
9:30 a.m.—Discussion of Security Issues
(Closed—Ex. 1 & 2).
Week of January 16, 2006—Tentative
Thursday, January 19, 2006
1:30 p.m.—Discussion of Security Issues
(Closed—Ex. 1 & 3).
Week of January 23, 2006—Tentative
There are no meetings scheduled for
the Week of January 23, 2006.
* The schedule for Commission
meetings is subject to change on short
E:\FR\FM\20DEN1.SGM
20DEN1
Agencies
[Federal Register Volume 70, Number 243 (Tuesday, December 20, 2005)]
[Notices]
[Pages 75487-75488]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-7515]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-443]
FPL Energy Seabrook, LLC, Seabrook Station Unit No. 1;
Environmental Assessment and Finding of No Significant Impact
The Nuclear Regulatory Commission (NRC or the Commission) is
considering issuance of an amendment pursuant to Title 10 of the Code
of Federal Regulations (10 CFR) part 50, for Facility Operating License
No. NPF-86 issued to FPL Energy Seabrook, LLC (the licensee), for
operation of Seabrook Station, Unit No. 1 (Seabrook), located in
Rockingham County, New Hampshire. Therefore, as required by 10 CFR
51.21, the NRC is issuing this environmental assessment and finding of
no significant impact.
Environmental Assessment
Identification of the Proposed Action
The proposed action would extend the expiration date of the
operating license for Seabrook from October 17, 2026, to March 15,
2030.
The proposed action is in accordance with the licensee's
application for amendment dated March 28, 2005, as supplemented
September 23, 2005.
The Need for the Proposed Action
The current operating licensed term for Seabrook ends on October
17, 2026. This is 40 years from the date of the zero-power operating
license, which was issued on October 17, 1986. The amendment would
extend the expiration date of the operating license from October 17,
2026, to March 15, 2030. The extended date for termination of the
operating license would be 40 years after issuance of the full-power
operating license which was issued on March 15, 1990. This would allow
the licensee to recapture approximately 41 months of additional plant
operation for the unit. This proposed amendment is not a request for
license renewal pursuant to 10 CFR Part 54.
Environmental Impacts of the Proposed Action
The NRC has completed its evaluation of the proposed action and
concludes that there are no significant environmental considerations
involved with the proposed action. The extension of the operating
licenses does not affect the design or operation of the plant, does not
involve any modifications to the plant or any increase in the licensed
power for the plant, and will not create any new or unreviewed
environmental impacts that were not considered in the Final
Environmental Statement (FES) related to the operation of Seabrook,
NUREG-0895, dated December 1982. The evaluations presented in the FES
were of the environmental impacts of generating power at Seabrook and
the basis for granting a 40-year operating license for Seabrook. The
environmental impacts of the proposed action are based on the
evaluations in the FES. It should be noted that the Seabrook license
was amended on February 28, 2005, to allow an increase in maximum core
power by 5.2% (from 3411 megawatts thermal (MWt) to 3587 MWt). The
environmental assessment of the power uprate was published in the
Federal Register on February 14, 2005 (70 FR 7525).
The FES which, in general, assesses various impacts associated with
operation of the facility in terms of annual impacts, and balances
these against the anticipated annual energy production benefits.
The offsite exposure from releases during postulated accidents has
been previously evaluated in the Updated Final Safety Analysis Report
(UFSAR) for Seabrook. The results are acceptable when compared with the
criteria defined in 10 CFR Part 100, as
[[Page 75488]]
documented in the Commission's Safety Evaluation Report, NUREG-0896,
dated March 1983, and its nine supplements. As a result of this action
there is no change in the types, frequency, or consequences of design-
basis accidents.
The NRC staff has concluded that the impacts associated with the
addition of approximately 41 months to the license expiration date are
not significantly different from the operating license duration
assessed in the Seabrook FES. Therefore, the staff concluded that the
FES sufficiently addresses the environmental impacts associated with a
full 40-year operating period for Seabrook.
The annual occupational exposure of workers at the plant, station
employees and contractors, is reported in the Annual Operating Report
submitted by the licensee. The lowest exposure value is for a year
without a refueling outage, and the highest value is for a year with a
refueling outage. In Section 5.9.3.1.1 of the FES, the average
occupational exposure for a pressurized water reactor was reported as
440 person-rems. Therefore, the expected annual occupational exposure
for the proposed extended period of operation does not change previous
conclusions presented in the FES on occupational exposure.
The offsite exposure from releases during routine operations has
been previously evaluated in Section 5.9.3 of the FES. During the low-
power license, the plant was restricted to no more than five percent of
rated power for no longer than 0.75 effective full power hours, and the
generation of radioactivity at the plant was significantly smaller than
would have occurred if the plant were at full-power operation.
Therefore, the addition of approximately 41 months of operation that
the licensee has requested does not change previous conclusions
presented in the FES on annual public doses.
The proposed action will not significantly increase the probability
or consequences of accidents, no changes are being made in the types of
effluents that may be released off site, and there is no significant
increase in occupational or public radiation exposure. Therefore, there
are no significant radiological environmental impacts associated with
the proposed action.
With regard to potential nonradiological impacts, the proposed
action does not have a potential to affect any historic sites. It does
not affect nonradiological plant effluents and has no other
environmental impact. Therefore, there are no significant
nonradiological environmental impacts associated with the proposed
action.
Accordingly, the NRC concluded that there are no significant
environmental impacts associated with the proposed action.
Environmental Impacts of the Alternatives to the Proposed Action
As an alternative to the proposed action, the staff considered
denial of the proposed action (i.e., the ``no-action'' alternative).
Denial of the application would result in no change in current
environmental impacts. The environmental impacts of the proposed action
and the alternative action are similar.
Alternative Use of Resources
The action does not involve the use of any different resource than
those previously considered in the FES for Seabrook.
Agencies and Persons Consulted
On December 8, 2005, the staff consulted with the New Hampshire
State official, Mr. Mike Nawoj, and the Massachusetts State official,
Mr. James Muckerheid, regarding the environmental impact of the
proposed action. The State officials had no comments.
Finding of No Significant Impact
On the basis of the environmental assessment, the NRC concluded
that the proposed action will not have a significant effect on the
quality of the human environment. Accordingly, the NRC has determined
not to prepare an environmental impact statement for the proposed
action.
For further details with respect to the proposed action, see the
licensee's letter dated March 28, 2005 as supplemented September 23,
2005. Documents may be examined, and/or copied for a fee, at the NRC's
Public Document Room (PDR), located at One White Flint North, Public
File Area O1 F21, 11555 Rockville Pike (first floor), Rockville,
Maryland. Publicly available records will be accessible electronically
from the Agencywide Documents Access and Management System (ADAMS)
Public Electronic Reading Room on the Internet at the NRC Web site,
https://www.nrc.gov/reading-rm/adams.html. Persons who do not have
access to ADAMS or who encounter problems in accessing the documents
located in ADAMS, should contact the NRC PDR reference staff by
telephone at 1-800-397-4209 or 301-415-4737, or by e-mail to
pdr@nrc.gov.
Dated at Rockville, Maryland, this 6th day of December 2005.
For the Nuclear Regulatory Commission.
Darrell J. Roberts,
Branch Chief, Plant Licensing Branch I-2, Division of Operating Reactor
Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. E5-7515 Filed 12-19-05; 8:45 am]
BILLING CODE 7590-01-P