Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests, 74803-74804 [E5-7430]
Download as PDF
Federal Register / Vol. 70, No. 241 / Friday, December 16, 2005 / Notices
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: January 27, 2006.
All documents (original and eight
copies) should be filed with: Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
Additional study requests and
requests for cooperating agency status
may be filed electronically via the
Internet in lieu of paper. The
Commission strongly encourages
electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov) under the ‘‘e-Filing’’ link.
m. The application is not ready for
environmental analysis at this time.
n. The proposed project would be
built at the Spring Valley Canal’s Upper
Turnbull drop structure, which is a
reinforced concrete structure 1,102 feet
long, with a total drop of 101.6 feet. The
applicant proposes to construct: (1) A
check structure, consisting of a spillway
gate panel anchored to a ballast concrete
structure spanning the full width of the
canal floor between new concrete
abutment walls; (2) an intake structure
to divert flows from the left side of the
canal; (3) 84-inch-diameter, 1,100-feetlong steel or polyethylene penstock that
would be completely buried; (4) a
powerhouse containing two horizontal
Francis turbines and one generator with
a rated output of 4.1 MW; (5) a draft
tube and tailrace discharging flows into
the canal about 40 feet downstream of
the drop structure’s existing stilling
basin; (6) a 1.3-mile-long, 12.5-kilovolt
(kV) transmission line; (7) a switchyard;
and (8) a 1.7-mile-long, 69-kV
transmission line extending from the
switchyard to interconnect with an
existing Sun River Electric Cooperative
transmission line. The project would
use flows as they are provided in
VerDate Aug<31>2005
19:37 Dec 15, 2005
Jkt 208001
accordance with the needs of the
Greenfield Irrigation District, which
operates the canal. The project would
not impound water and would be
operated strictly as a run-of-river plant.
Average annual generation would be
11,200,000 kilowatt-hours.
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. With this notice, we are initiating
consultation with the Montana State
Historic Preservation Officer (SHPO), as
required by (106, National Historic
Preservation Act, and the regulations of
the Advisory Council on Historic
Preservation, 36, CFR, at § 800.4.
q. Procedural schedule: We are
currently reviewing the application for
adequacy. This schedule allows 30 days
for the correction of any deficiencies
and the submittal of any additional
information needed. If deficiencies and
additional information needs require
more time, the schedule will be revised
accordingly.
Issue Deficiency Letter December
2005.
Issue Acceptance Letter January 2006.
January 2006.
Issue Scoping Document for
comments January 2006.
Notice of application is ready for
environmental analysis February 2006.
Notice of the availability of the EA
June 2006.
Ready for Commission’s decision on
the application July 2006.
Magalie R. Salas,
Secretary.
[FR Doc. E5–7429 Filed 12–15–05; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
74803
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Tendered for
Filing With the Commission and
Soliciting Additional Study Requests
December 12, 2005.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Minor
License.
b. Project No.: 12599–002.1
c. Date filed: November 28, 2005.
d. Applicant: Wade Jacobsen.
e. Name of Project: Mill Coulee Drops
Hydroelectric Project.
f. Location: On the Mill Coulee Canal,
in Cascade County, Montana, about 4
miles west of Fairfield, Montana. The
project would occupy in part on lands
of the United States administered by the
Bureau of Reclamation.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a) through 825(r).
h. Applicant Contact: Ted Sorenson,
Sorenson Engineering, 5203 South 11th
East, Idaho Falls, ID 83404, (208) 522–
8069.
i. FERC Contact: Dianne Rodman,
(202) 502–6077,
Dianne.rodman@ferc.gov.
j. Cooperating agencies: We are asking
Federal, state, local, and tribal agencies
with jurisdiction and/or special
expertise with respect to environmental
issues to cooperate with us in the
preparation of the environmental
document. Agencies who would like to
request cooperating status should follow
the instructions for filing comments
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
1 The Mill Coulee Drops Project No. 12599 would
be located at the sites of the Mill Coulee Lower
Project No. 12536 and the Mill Coulee Upper
Project No. 12537, for which the applicant holds
preliminary permits.
E:\FR\FM\16DEN1.SGM
16DEN1
74804
Federal Register / Vol. 70, No. 241 / Friday, December 16, 2005 / Notices
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: January 27, 2006.
All documents (original and eight
copies) should be filed with: Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
Additional study requests and
requests for cooperating agency status
may be filed electronically via the
Internet in lieu of paper. The
Commission strongly encourages
electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov) under the ‘‘e-Filing’’ link.
m. The application is not ready for
environmental analysis at this time.
n. The proposed project would be
built at the Mill Coulee Canal’s Upper
and Lower Mill Coulee drop structures,
which are reinforced concrete structures
290 and 190 feet long, respectively. The
total drop for the two structures is 101.6
feet. The applicant proposes to
construct: (1) A check structure,
consisting of a spillway gate panel
anchored to a ballast concrete structure
spanning the full width of the canal
floor between new concrete abutment
walls, upstream from the concrete
transition of the Upper Mill Coulee
chute drop; (2) an intake structure to
divert flows from the left side of the
canal; (3) a 48-inch-diameter, 1,400-feetlong pre-stressed concrete, tape-coated
steel, or polyethylene penstock that
would be completely buried; (4) a
powerhouse containing one horizontal
Francis turbine and one generator with
a rated output of 1.05 MW; (5) a draft
tube and 2,650-feet-long tailrace
discharging flows into the canal below
the Lower Mill Coulee drop structure;
(6) a switchyard immediately adjacent
to the powerhouse; and (7) a 0.7-milelong, 69-kV transmission line extending
from the switchyard to interconnect
with an existing Sun River Electric
Cooperative transmission line. The
project would use flows as they are
provided in accordance with the needs
of the Greenfield Irrigation District,
which operates the canal. The project
VerDate Aug<31>2005
19:37 Dec 15, 2005
Jkt 208001
would not impound water and would be
operated strictly as a run-of-river plant.
Average annual generation would be
2,430,000 kilowatt-hours.
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. With this notice, we are initiating
consultation with the Montana State
Historic Preservation Officer (SHPO), as
required by § 106, National Historic
Preservation Act, and the regulations of
the Advisory Council on Historic
Preservation, 36, CFR, at § 800.4.
q. Procedural schedule: We are
currently reviewing the application for
adequacy. This schedule allows 30 days
for the correction of any deficiencies
and the submittal of any additional
information needed. If deficiencies and
additional information needs require
more time, the schedule will be revised
accordingly.
Issue Deficiency Letter, December
2005.
Issue Acceptance Letter, January
2006.
Issue Scoping Document 1 for
comments, January 2006.
Notice of application is ready for
environmental analysis, February 2006.
Notice of the availability of the EA,
June 2006.
Ready for Commission’s decision on
the application, July 2006.
Magalie R. Salas,
Secretary.
[FR Doc. E5–7430 Filed 12–15–05; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. AD06–2–000]
Assessment of Demand Response
Resources; Notice of Technical
Conference on Demand Response and
Advanced Metering
December 12, 2005.
Take notice that on Wednesday,
January 25, 2005, at 9 a.m. (EST), staff
of the Federal Energy Regulatory
Commission will convene a technical
conference on demand response and
advanced metering regarding issues
raised by the Energy Policy Act of 2005
(EPAct 2005) section 1252(e)(3).1 The
technical conference will be held in the
Commission Meeting Room at the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426. The conference will be open for
the public to attend and advance
registration is not required. This will be
a staff conference, but Commissioners
may attend. In the coming weeks, an
additional notice of this technical
conference will be issued finalizing the
agenda and participation on the
proposed panels.
A free webcast of this event will be
available through www.ferc.gov.
Anyone with Internet access who
desires to view this event can do so by
navigating to https://www.ferc.gov’s
Calendar of Events and locating this
event in the Calendar. The event will
contain a link to its webcast. The
Capitol Connection provides technical
support for the webcasts. It also offers
access to this event via television in the
Washington, DC area and via phone
bridge for a fee. Visit https://
www.CapitolConnection.org or contact
Danelle Perkowski or David Reininger at
the Capitol Connection 703–993–3100
for information about this service.
Commission conferences are
accessible under section 508 of the
Rehabilitation Act of 1973. For
accessibility accommodations please
send an e-mail to accessibility@ferc.gov
or call toll free 866–208–3372 (voice) or
202–208–1659 (TTY), or send a FAX to
202–208–2106 with the required
accommodations.
For further information on the
technical conference, please contact:
David Kathan (Technical Information),
Office of Markets, Tariffs and Rates,
Federal Energy Regulatory
Commission, 888 First Street, NE.,
1 Energy Policy Act of 2005, Pub. L. No. 109–58,
§ 1252(e)(3), 119 Stat. 594, (2005) (EPAct section
1252(e)(3)).
Frm 00046
Fmt 4703
Sfmt 4703
E:\FR\FM\16DEN1.SGM
16DEN1
Agencies
[Federal Register Volume 70, Number 241 (Friday, December 16, 2005)]
[Notices]
[Pages 74803-74804]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-7430]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Application Tendered for Filing With the Commission and
Soliciting Additional Study Requests
December 12, 2005.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Minor License.
b. Project No.: 12599-002.\1\
---------------------------------------------------------------------------
\1\ The Mill Coulee Drops Project No. 12599 would be located at
the sites of the Mill Coulee Lower Project No. 12536 and the Mill
Coulee Upper Project No. 12537, for which the applicant holds
preliminary permits.
---------------------------------------------------------------------------
c. Date filed: November 28, 2005.
d. Applicant: Wade Jacobsen.
e. Name of Project: Mill Coulee Drops Hydroelectric Project.
f. Location: On the Mill Coulee Canal, in Cascade County, Montana,
about 4 miles west of Fairfield, Montana. The project would occupy in
part on lands of the United States administered by the Bureau of
Reclamation.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a) through
825(r).
h. Applicant Contact: Ted Sorenson, Sorenson Engineering, 5203
South 11th East, Idaho Falls, ID 83404, (208) 522-8069.
i. FERC Contact: Dianne Rodman, (202) 502-6077,
Dianne.rodman@ferc.gov.
j. Cooperating agencies: We are asking Federal, state, local, and
tribal agencies with jurisdiction and/or special expertise with respect
to environmental issues to cooperate with us in the preparation of the
environmental document. Agencies who would like to request cooperating
status should follow the instructions for filing comments described in
item l below. Cooperating agencies should note the Commission's policy
that agencies that cooperate in the preparation of the environmental
document cannot also intervene. See, 94 FERC ] 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and
[[Page 74804]]
serve a copy of the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: January 27, 2006.
All documents (original and eight copies) should be filed with:
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
Additional study requests and requests for cooperating agency
status may be filed electronically via the Internet in lieu of paper.
The Commission strongly encourages electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
(https://www.ferc.gov) under the ``e-Filing'' link.
m. The application is not ready for environmental analysis at this
time.
n. The proposed project would be built at the Mill Coulee Canal's
Upper and Lower Mill Coulee drop structures, which are reinforced
concrete structures 290 and 190 feet long, respectively. The total drop
for the two structures is 101.6 feet. The applicant proposes to
construct: (1) A check structure, consisting of a spillway gate panel
anchored to a ballast concrete structure spanning the full width of the
canal floor between new concrete abutment walls, upstream from the
concrete transition of the Upper Mill Coulee chute drop; (2) an intake
structure to divert flows from the left side of the canal; (3) a 48-
inch-diameter, 1,400-feet-long pre-stressed concrete, tape-coated
steel, or polyethylene penstock that would be completely buried; (4) a
powerhouse containing one horizontal Francis turbine and one generator
with a rated output of 1.05 MW; (5) a draft tube and 2,650-feet-long
tailrace discharging flows into the canal below the Lower Mill Coulee
drop structure; (6) a switchyard immediately adjacent to the
powerhouse; and (7) a 0.7-mile-long, 69-kV transmission line extending
from the switchyard to interconnect with an existing Sun River Electric
Cooperative transmission line. The project would use flows as they are
provided in accordance with the needs of the Greenfield Irrigation
District, which operates the canal. The project would not impound water
and would be operated strictly as a run-of-river plant. Average annual
generation would be 2,430,000 kilowatt-hours.
o. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1-
866-208-3676, or for TTY, (202) 502-8659. A copy is also available for
inspection and reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
p. With this notice, we are initiating consultation with the
Montana State Historic Preservation Officer (SHPO), as required by
Sec. 106, National Historic Preservation Act, and the regulations of
the Advisory Council on Historic Preservation, 36, CFR, at Sec. 800.4.
q. Procedural schedule: We are currently reviewing the application
for adequacy. This schedule allows 30 days for the correction of any
deficiencies and the submittal of any additional information needed. If
deficiencies and additional information needs require more time, the
schedule will be revised accordingly.
Issue Deficiency Letter, December 2005.
Issue Acceptance Letter, January 2006.
Issue Scoping Document 1 for comments, January 2006.
Notice of application is ready for environmental analysis, February
2006.
Notice of the availability of the EA, June 2006.
Ready for Commission's decision on the application, July 2006.
Magalie R. Salas,
Secretary.
[FR Doc. E5-7430 Filed 12-15-05; 8:45 am]
BILLING CODE 6717-01-P