Notice of Application for Non-Project Use of Project Lands and Waters and Soliciting Comments, Motions To Intervene, and Protests, 73228-73229 [E5-7140]

Download as PDF 73228 Federal Register / Vol. 70, No. 236 / Friday, December 9, 2005 / Notices environmental information provided by CIG and our staff. This preliminary list of issues may be changed based on your comments and our analysis. • Five Federally listed endangered or threatened species may occur in the proposed project area. • The Sanford Station is being reviewed by the State Historic Preservation Officer to determine whether the station should be considered a historic site. • Soil and possible groundwater contamination may exist at the site. Investigations concluded that hydrocarbon, mercury, and polychlorinated biphenyls exist in the soils, and asbestos, and lead-based paint are present in the building materials. Public Participation You can make a difference by providing us with your specific comments or concerns about the project. By becoming a commentor, your concerns will be addressed in the EA and considered by the Commission. You should focus on the potential environmental effects of the proposal, alternatives to the proposal, and measures to avoid or lessen environmental impact. The more specific your comments, the more useful they will be. Please carefully follow these instructions to ensure that your comments are received in time and properly recorded: • Send an original and two copies of your letter to: Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First St., NE., Room 1A, Washington, DC 20426. • Label one copy of the comments for the attention of Gas Branch 2. • Reference Docket No. CP06–17– 000. • Mail your comments so that they will be received in Washington, DC on or before January 3, 2006. The Commission strongly encourages electronic filing of any comments or interventions or protests to this proceeding. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site at https://www.ferc.gov under the ‘‘eFiling’’ link and the link to the User’s Guide. Before you can file comments you will need to create a free account which can be created online. We may mail the EA for comment. If you are interested in receiving it, please return the Information Request (Appendix 3). If you do not return the Information Request, you will be taken off the mailing list. VerDate Aug<31>2005 14:22 Dec 08, 2005 Jkt 208001 Becoming an Intervenor In addition to involvement in the EA scoping process, you may want to become an official party to the proceeding, or ‘‘intervenor.’’ To become an intervenor you must file a motion to intervene according to Rule 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.214). Intervenors have the right to seek rehearing of the Commission’s decision. Motions to Intervene should be electronically submitted using the Commission’s eFiling system at https://www.ferc.gov. Persons without Internet access should send an original and 14 copies of their motion to the Secretary of the Commission at the address indicated previously. Persons filing Motions to Intervene on or before the comment deadline indicated above must send a copy of the motion to the Applicant. All filings, including late interventions, submitted after the comment deadline must be served on the Applicant and all other intervenors identified on the Commission’s service list for this proceeding. Persons on the service list with e-mail addresses may be served electronically; others must be served a hard copy of the filing. Affected landowners and parties with environmental concerns may be granted intervenor status upon showing good cause by stating that they have a clear and direct interest in this proceeding which would not be adequately represented by any other parties. You do not need intervenor status to have your environmental comments considered. Environmental Mailing List An effort is being made to send this notice to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. This includes all landowners whose property may be used temporarily for project purposes, or who own homes within distances defined in the Commission’s regulations of certain aboveground facilities. Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at 1–866–208–FERC or on the FERC Internet Web site (www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number excluding the last three digits in the Docket Number field. Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, contact PO 00000 Frm 00035 Fmt 4703 Sfmt 4703 (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission now offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries and direct links to the documents. Go to https:// www.ferc.gov/esubscribenow.htm. Finally, public meetings or site visits will be posted on the Commission’s calendar located at https://www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Magalie R. Salas, Secretary. [FR Doc. E5–7089 Filed 12–8–05; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Application for Non-Project Use of Project Lands and Waters and Soliciting Comments, Motions To Intervene, and Protests December 2, 2005. Take notice that the following application has been filed with the Commission and is available for public inspection: a. Application Type: Non-Project Use of Project Lands And Waters. b. Project No: 2146–112. c. Date Filed: November 14, 2005. d. Applicant: Alabama Power Company. e. Name of Project: The Coosa River Project, which includes the Weiss Lake development. f. Location: The proposed action will take place at the Weiss Lake development at Kessler’s Subdivision on Three Mile Creek, which is located in Cherokee County, Alabama approximately 21 stream miles above the Weiss powerhouse. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a) 825(r) and sections 799 and 801. h. Applicant Contact: Mr. Keith E. Bryant, Sr. Engineer; Alabama Power Company Hydro Services; 600 18th Street North, Birmingham, AL 35203; (205) 257–1403. i. FERC Contact: Any questions on this notice should be addressed to E:\FR\FM\09DEN1.SGM 09DEN1 Federal Register / Vol. 70, No. 236 / Friday, December 9, 2005 / Notices Lesley Kordella at (202) 502–6406, or by e-mail: Lesley.Kordella@ferc.gov. j. Deadline for filing comments and/ or motions: January 3, 2006. All documents (original and eight copies) should be filed with: Ms. Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Please include the project number (P– 2146–112) on any comments or motions filed. Comments, protests, and interventions may be filed electronically via the internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. The Commission strongly encourages efilings. k. Description of Request: The licensee has requested Commission approval to construct a 22 slip boat house and boat ramp for use by individual owners of the Kessler subdivision on Three Mile Creek. The proposed dock structure and boat ramp would be located on a community access waterfront lot at the east end of the subdivision, which consists of approximately 90 feet of shoreline. The proposed boat dock would be constructed of treated lumber and supported on driven piles. The proposed boat ramp is to be a single land ramp constructed of concrete. Minimal grading is expected. There will be no septic tanks or field lines, or facilities for fueling or sewage pump out. There will be no dredging during construction and the boat dock structure will be built on site. l. Location of the Application: This filing is available for review at the Commission or may be viewed on the Commission’s Web site at https:// www.ferc.gov, using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY, contact (202) 502–8659. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the VerDate Aug<31>2005 14:22 Dec 08, 2005 Jkt 208001 Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘RECOMMENDATIONS FOR TERMS AND CONDITIONS’’, ‘‘PROTEST’’, OR ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. A copy of any motion to intervene must also be served upon each representative of the Applicant specified in the particular application. p. Agency Comments—Federal, State, and local agencies are invited to file comments on the described applications. A copy of the applications may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. Magalie R. Salas, Secretary. [FR Doc. E5–7140 Filed 12–8–05; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 9185–009] Flambeau Hydro, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions December 2, 2005. Take notice that the following hydroelectric license application has been filed with the Commission and is available for public inspection. a. Type of Application: Subsequent License. b. Project No.: P–9185–009. c. Date Filed: April 1, 2005. d. Applicant: Flambeau Hydro, LLC. e. Name of Project: Clam River Hydroelectric Project. f. Location: Located on the Clam River in Burnett County, Wisconsin. This project does not occupy federal lands. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Scott Klabunde, North American Hydro, Inc., P.O. Box PO 00000 Frm 00036 Fmt 4703 Sfmt 4703 73229 167, Neshkoro, WI 54960; 920–293– 4628 ext. 14. i. FERC Contact: Patrick Murphy, (202) 502–8755, patrick.murphy@ferc.gov. j. Deadline for filing comments, recommendations, terms and conditions, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from issuance date of this notice. All documents (original and eight copies) should be filed with: Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person whose name appears on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. Comments, recommendations, terms and conditions, and prescriptions may be filed electronically via the Internet in lieu of paper. The Commission strongly encourages electronic filings. See CFR 385.2001 (a)(1)(iii) and the instructions on the Commission’s Web site (https:// www.ferc.gov) under the ‘‘eFiling’’ link. k. This application has been accepted, and is ready for environmental analysis at this time. l. The existing Clam River Project consists of: (1) A 46-foot-high buttresstype concrete dam with a 54-foot-wide spillway with four sections, (three sections equipped with 8-inch-high stoplogs, and one section equipped with a 4-foot-high slide gate); (2) 898-footlong and 223-foot-long earthen dike connecting the left side and the right side of the concrete dam, respectively; (3) a 360-acre reservoir with a net storage capacity of 3,575 acre-feet at a normal water surface elevation of 898.6 feet mean sea level (msl); (4) two powerhouses built into the dam, containing three 400-kW turbine generating units with a total installed capacity of 1,200 kilowatt (kW); (5) a 100-foot-long, 2.4-kW transmission line; and (6) appurtenant facilities. The dam and existing project facilities are owned by Flambeau Hydro, LLC. m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the E:\FR\FM\09DEN1.SGM 09DEN1

Agencies

[Federal Register Volume 70, Number 236 (Friday, December 9, 2005)]
[Notices]
[Pages 73228-73229]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-7140]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Notice of Application for Non-Project Use of Project Lands and 
Waters and Soliciting Comments, Motions To Intervene, and Protests

December 2, 2005.
    Take notice that the following application has been filed with the 
Commission and is available for public inspection:
    a. Application Type: Non-Project Use of Project Lands And Waters.
    b. Project No: 2146-112.
    c. Date Filed: November 14, 2005.
    d. Applicant: Alabama Power Company.
    e. Name of Project: The Coosa River Project, which includes the 
Weiss Lake development.
    f. Location: The proposed action will take place at the Weiss Lake 
development at Kessler's Subdivision on Three Mile Creek, which is 
located in Cherokee County, Alabama approximately 21 stream miles above 
the Weiss powerhouse.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a) 825(r) 
and sections 799 and 801.
    h. Applicant Contact: Mr. Keith E. Bryant, Sr. Engineer; Alabama 
Power Company Hydro Services; 600 18th Street North, Birmingham, AL 
35203; (205) 257-1403.
    i. FERC Contact: Any questions on this notice should be addressed 
to

[[Page 73229]]

Lesley Kordella at (202) 502-6406, or by e-mail: 
Lesley.Kordella@ferc.gov.
    j. Deadline for filing comments and/or motions: January 3, 2006.
    All documents (original and eight copies) should be filed with: Ms. 
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE., Washington, DC 20426. Please include the project 
number (P-2146-112) on any comments or motions filed. Comments, 
protests, and interventions may be filed electronically via the 
internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and the 
instructions on the Commission's Web site under the ``e-Filing'' link. 
The Commission strongly encourages e-filings.
    k. Description of Request: The licensee has requested Commission 
approval to construct a 22 slip boat house and boat ramp for use by 
individual owners of the Kessler subdivision on Three Mile Creek. The 
proposed dock structure and boat ramp would be located on a community 
access waterfront lot at the east end of the subdivision, which 
consists of approximately 90 feet of shoreline. The proposed boat dock 
would be constructed of treated lumber and supported on driven piles. 
The proposed boat ramp is to be a single land ramp constructed of 
concrete. Minimal grading is expected. There will be no septic tanks or 
field lines, or facilities for fueling or sewage pump out. There will 
be no dredging during construction and the boat dock structure will be 
built on site.
    l. Location of the Application: This filing is available for review 
at the Commission or may be viewed on the Commission's Web site at 
https://www.ferc.gov, using the ``eLibrary'' link. Enter the docket 
number excluding the last three digits in the docket number field to 
access the document. For assistance, contact FERC Online Support at 
FERCOnlineSupport@ferc.gov or toll-free at (866) 208-3676, or for TTY, 
contact (202) 502-8659.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene--Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    o. Filing and Service of Responsive Documents--Any filings must 
bear in all capital letters the title ``COMMENTS'', ``RECOMMENDATIONS 
FOR TERMS AND CONDITIONS'', ``PROTEST'', OR ``MOTION TO INTERVENE'', as 
applicable, and the Project Number of the particular application to 
which the filing refers. A copy of any motion to intervene must also be 
served upon each representative of the Applicant specified in the 
particular application.
    p. Agency Comments--Federal, State, and local agencies are invited 
to file comments on the described applications. A copy of the 
applications may be obtained by agencies directly from the Applicant. 
If an agency does not file comments within the time specified for 
filing comments, it will be presumed to have no comments. One copy of 
an agency's comments must also be sent to the Applicant's 
representatives.

Magalie R. Salas,
Secretary.
[FR Doc. E5-7140 Filed 12-8-05; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.