Notice of Application for Non-Project Use of Project Lands and Waters and Soliciting Comments, Motions To Intervene, and Protests, 73228-73229 [E5-7140]
Download as PDF
73228
Federal Register / Vol. 70, No. 236 / Friday, December 9, 2005 / Notices
environmental information provided by
CIG and our staff. This preliminary list
of issues may be changed based on your
comments and our analysis.
• Five Federally listed endangered or
threatened species may occur in the
proposed project area.
• The Sanford Station is being
reviewed by the State Historic
Preservation Officer to determine
whether the station should be
considered a historic site.
• Soil and possible groundwater
contamination may exist at the site.
Investigations concluded that
hydrocarbon, mercury, and
polychlorinated biphenyls exist in the
soils, and asbestos, and lead-based paint
are present in the building materials.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
By becoming a commentor, your
concerns will be addressed in the EA
and considered by the Commission. You
should focus on the potential
environmental effects of the proposal,
alternatives to the proposal, and
measures to avoid or lessen
environmental impact. The more
specific your comments, the more useful
they will be. Please carefully follow
these instructions to ensure that your
comments are received in time and
properly recorded:
• Send an original and two copies of
your letter to: Magalie R. Salas,
Secretary, Federal Energy Regulatory
Commission, 888 First St., NE., Room
1A, Washington, DC 20426.
• Label one copy of the comments for
the attention of Gas Branch 2.
• Reference Docket No. CP06–17–
000.
• Mail your comments so that they
will be received in Washington, DC on
or before January 3, 2006.
The Commission strongly encourages
electronic filing of any comments or
interventions or protests to this
proceeding. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site at
https://www.ferc.gov under the ‘‘eFiling’’ link and the link to the User’s
Guide. Before you can file comments
you will need to create a free account
which can be created online.
We may mail the EA for comment. If
you are interested in receiving it, please
return the Information Request
(Appendix 3). If you do not return the
Information Request, you will be taken
off the mailing list.
VerDate Aug<31>2005
14:22 Dec 08, 2005
Jkt 208001
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an official party to the
proceeding, or ‘‘intervenor.’’ To become
an intervenor you must file a motion to
intervene according to Rule 214 of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214). Intervenors
have the right to seek rehearing of the
Commission’s decision. Motions to
Intervene should be electronically
submitted using the Commission’s
eFiling system at https://www.ferc.gov.
Persons without Internet access should
send an original and 14 copies of their
motion to the Secretary of the
Commission at the address indicated
previously. Persons filing Motions to
Intervene on or before the comment
deadline indicated above must send a
copy of the motion to the Applicant. All
filings, including late interventions,
submitted after the comment deadline
must be served on the Applicant and all
other intervenors identified on the
Commission’s service list for this
proceeding. Persons on the service list
with e-mail addresses may be served
electronically; others must be served a
hard copy of the filing.
Affected landowners and parties with
environmental concerns may be granted
intervenor status upon showing good
cause by stating that they have a clear
and direct interest in this proceeding
which would not be adequately
represented by any other parties. You do
not need intervenor status to have your
environmental comments considered.
Environmental Mailing List
An effort is being made to send this
notice to all individuals, organizations,
and government entities interested in
and/or potentially affected by the
proposed project. This includes all
landowners whose property may be
used temporarily for project purposes,
or who own homes within distances
defined in the Commission’s regulations
of certain aboveground facilities.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the FERC
Internet Web site (www.ferc.gov) using
the eLibrary link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number excluding the
last three digits in the Docket Number
field. Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at 1–866–208–3676, or for TTY, contact
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
(202) 502–8659. The eLibrary link also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to https://
www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Magalie R. Salas,
Secretary.
[FR Doc. E5–7089 Filed 12–8–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application for Non-Project
Use of Project Lands and Waters and
Soliciting Comments, Motions To
Intervene, and Protests
December 2, 2005.
Take notice that the following
application has been filed with the
Commission and is available for public
inspection:
a. Application Type: Non-Project Use
of Project Lands And Waters.
b. Project No: 2146–112.
c. Date Filed: November 14, 2005.
d. Applicant: Alabama Power
Company.
e. Name of Project: The Coosa River
Project, which includes the Weiss Lake
development.
f. Location: The proposed action will
take place at the Weiss Lake
development at Kessler’s Subdivision
on Three Mile Creek, which is located
in Cherokee County, Alabama
approximately 21 stream miles above
the Weiss powerhouse.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a) 825(r) and sections
799 and 801.
h. Applicant Contact: Mr. Keith E.
Bryant, Sr. Engineer; Alabama Power
Company Hydro Services; 600 18th
Street North, Birmingham, AL 35203;
(205) 257–1403.
i. FERC Contact: Any questions on
this notice should be addressed to
E:\FR\FM\09DEN1.SGM
09DEN1
Federal Register / Vol. 70, No. 236 / Friday, December 9, 2005 / Notices
Lesley Kordella at (202) 502–6406, or by
e-mail: Lesley.Kordella@ferc.gov.
j. Deadline for filing comments and/
or motions: January 3, 2006.
All documents (original and eight
copies) should be filed with: Ms.
Magalie R. Salas, Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
Please include the project number (P–
2146–112) on any comments or motions
filed. Comments, protests, and
interventions may be filed electronically
via the internet in lieu of paper. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site under the ‘‘e-Filing’’ link. The
Commission strongly encourages efilings.
k. Description of Request: The
licensee has requested Commission
approval to construct a 22 slip boat
house and boat ramp for use by
individual owners of the Kessler
subdivision on Three Mile Creek. The
proposed dock structure and boat ramp
would be located on a community
access waterfront lot at the east end of
the subdivision, which consists of
approximately 90 feet of shoreline. The
proposed boat dock would be
constructed of treated lumber and
supported on driven piles. The
proposed boat ramp is to be a single
land ramp constructed of concrete.
Minimal grading is expected. There will
be no septic tanks or field lines, or
facilities for fueling or sewage pump
out. There will be no dredging during
construction and the boat dock structure
will be built on site.
l. Location of the Application: This
filing is available for review at the
Commission or may be viewed on the
Commission’s Web site at https://
www.ferc.gov, using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY,
contact (202) 502–8659.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
VerDate Aug<31>2005
14:22 Dec 08, 2005
Jkt 208001
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
o. Filing and Service of Responsive
Documents—Any filings must bear in
all capital letters the title
‘‘COMMENTS’’,
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’, ‘‘PROTEST’’, OR
‘‘MOTION TO INTERVENE’’, as
applicable, and the Project Number of
the particular application to which the
filing refers. A copy of any motion to
intervene must also be served upon each
representative of the Applicant
specified in the particular application.
p. Agency Comments—Federal, State,
and local agencies are invited to file
comments on the described
applications. A copy of the applications
may be obtained by agencies directly
from the Applicant. If an agency does
not file comments within the time
specified for filing comments, it will be
presumed to have no comments. One
copy of an agency’s comments must also
be sent to the Applicant’s
representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E5–7140 Filed 12–8–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 9185–009]
Flambeau Hydro, LLC; Notice of
Application Ready for Environmental
Analysis and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions
December 2, 2005.
Take notice that the following
hydroelectric license application has
been filed with the Commission and is
available for public inspection.
a. Type of Application: Subsequent
License.
b. Project No.: P–9185–009.
c. Date Filed: April 1, 2005.
d. Applicant: Flambeau Hydro, LLC.
e. Name of Project: Clam River
Hydroelectric Project.
f. Location: Located on the Clam River
in Burnett County, Wisconsin. This
project does not occupy federal lands.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Scott Klabunde,
North American Hydro, Inc., P.O. Box
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
73229
167, Neshkoro, WI 54960; 920–293–
4628 ext. 14.
i. FERC Contact: Patrick Murphy,
(202) 502–8755,
patrick.murphy@ferc.gov.
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions: 60 days
from the issuance date of this notice;
reply comments are due 105 days from
issuance date of this notice.
All documents (original and eight
copies) should be filed with: Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
Comments, recommendations, terms
and conditions, and prescriptions may
be filed electronically via the Internet in
lieu of paper. The Commission strongly
encourages electronic filings. See CFR
385.2001 (a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov) under the ‘‘eFiling’’ link.
k. This application has been accepted,
and is ready for environmental analysis
at this time.
l. The existing Clam River Project
consists of: (1) A 46-foot-high buttresstype concrete dam with a 54-foot-wide
spillway with four sections, (three
sections equipped with 8-inch-high
stoplogs, and one section equipped with
a 4-foot-high slide gate); (2) 898-footlong and 223-foot-long earthen dike
connecting the left side and the right
side of the concrete dam, respectively;
(3) a 360-acre reservoir with a net
storage capacity of 3,575 acre-feet at a
normal water surface elevation of 898.6
feet mean sea level (msl); (4) two
powerhouses built into the dam,
containing three 400-kW turbine
generating units with a total installed
capacity of 1,200 kilowatt (kW); (5) a
100-foot-long, 2.4-kW transmission line;
and (6) appurtenant facilities. The dam
and existing project facilities are owned
by Flambeau Hydro, LLC.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number
excluding the last three digits in the
E:\FR\FM\09DEN1.SGM
09DEN1
Agencies
[Federal Register Volume 70, Number 236 (Friday, December 9, 2005)]
[Notices]
[Pages 73228-73229]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-7140]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Application for Non-Project Use of Project Lands and
Waters and Soliciting Comments, Motions To Intervene, and Protests
December 2, 2005.
Take notice that the following application has been filed with the
Commission and is available for public inspection:
a. Application Type: Non-Project Use of Project Lands And Waters.
b. Project No: 2146-112.
c. Date Filed: November 14, 2005.
d. Applicant: Alabama Power Company.
e. Name of Project: The Coosa River Project, which includes the
Weiss Lake development.
f. Location: The proposed action will take place at the Weiss Lake
development at Kessler's Subdivision on Three Mile Creek, which is
located in Cherokee County, Alabama approximately 21 stream miles above
the Weiss powerhouse.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a) 825(r)
and sections 799 and 801.
h. Applicant Contact: Mr. Keith E. Bryant, Sr. Engineer; Alabama
Power Company Hydro Services; 600 18th Street North, Birmingham, AL
35203; (205) 257-1403.
i. FERC Contact: Any questions on this notice should be addressed
to
[[Page 73229]]
Lesley Kordella at (202) 502-6406, or by e-mail:
Lesley.Kordella@ferc.gov.
j. Deadline for filing comments and/or motions: January 3, 2006.
All documents (original and eight copies) should be filed with: Ms.
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426. Please include the project
number (P-2146-112) on any comments or motions filed. Comments,
protests, and interventions may be filed electronically via the
internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and the
instructions on the Commission's Web site under the ``e-Filing'' link.
The Commission strongly encourages e-filings.
k. Description of Request: The licensee has requested Commission
approval to construct a 22 slip boat house and boat ramp for use by
individual owners of the Kessler subdivision on Three Mile Creek. The
proposed dock structure and boat ramp would be located on a community
access waterfront lot at the east end of the subdivision, which
consists of approximately 90 feet of shoreline. The proposed boat dock
would be constructed of treated lumber and supported on driven piles.
The proposed boat ramp is to be a single land ramp constructed of
concrete. Minimal grading is expected. There will be no septic tanks or
field lines, or facilities for fueling or sewage pump out. There will
be no dredging during construction and the boat dock structure will be
built on site.
l. Location of the Application: This filing is available for review
at the Commission or may be viewed on the Commission's Web site at
https://www.ferc.gov, using the ``eLibrary'' link. Enter the docket
number excluding the last three digits in the docket number field to
access the document. For assistance, contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll-free at (866) 208-3676, or for TTY,
contact (202) 502-8659.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene--Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
o. Filing and Service of Responsive Documents--Any filings must
bear in all capital letters the title ``COMMENTS'', ``RECOMMENDATIONS
FOR TERMS AND CONDITIONS'', ``PROTEST'', OR ``MOTION TO INTERVENE'', as
applicable, and the Project Number of the particular application to
which the filing refers. A copy of any motion to intervene must also be
served upon each representative of the Applicant specified in the
particular application.
p. Agency Comments--Federal, State, and local agencies are invited
to file comments on the described applications. A copy of the
applications may be obtained by agencies directly from the Applicant.
If an agency does not file comments within the time specified for
filing comments, it will be presumed to have no comments. One copy of
an agency's comments must also be sent to the Applicant's
representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E5-7140 Filed 12-8-05; 8:45 am]
BILLING CODE 6717-01-P