Application for Presidential Permit; Montana Alberta Tie Ltd., 65891 [05-21741]
Download as PDF
Federal Register / Vol. 70, No. 210 / Tuesday, November 1, 2005 / Notices
Reporting and Recordkeeping Hour
Burden: Responses: 84. Burden Hours:
504.
Abstract: Recipients of grants under
the Parental Information and Resource
Center program must submit an annual
performance report that establishes
substantial progress toward meeting
their project objectives to receive a
continuation award.
Requests for copies of the information
collection submission for OMB review
may be accessed from https://
edicsweb.ed.gov, by selecting the
‘‘Browse Pending Collections’’ link and
by clicking on link number 2869. When
you access the information collection,
click on ‘‘Download Attachments ‘‘ to
view. Written requests for information
should be addressed to U.S. Department
of Education, 400 Maryland Avenue,
SW., Potomac Center, 9th Floor,
Washington, DC 20202–4700. Requests
may also be electronically mailed to the
Internet address OCIO_RIMG@ed.gov or
faxed to 202–245–6623. Please specify
the complete title of the information
collection when making your request.
Comments regarding burden and/or
the collection activity requirements
should be directed to Kathy Axt at her
e-mail address Kathy.Axt@ed.gov.
Individuals who use a
telecommunications device for the deaf
(TDD) may call the Federal Information
Relay Service (FIRS) at 1–800–877–
8339.
[FR Doc. 05–21737 Filed 10–31–05; 8:45 am]
BILLING CODE 4000–01–P
DEPARTMENT OF ENERGY
[OE Docket No. PP–305]
Application for Presidential Permit;
Montana Alberta Tie Ltd.
Office of Electricity Delivery
and Energy Reliability, DOE.
ACTION: Notice of application.
AGENCY:
SUMMARY: Montana Alberta Tie Ltd.
(MATL) has applied for a Presidential
permit to construct, operate, maintain,
and connect an electric transmission
line across the U.S. border with Canada.
DATES: Comments, protests, or requests
to intervene must be submitted on or
before December 1, 2005.
ADDRESSES: Comments, protests, or
requests to intervene should be
addressed as follows: Office of
Electricity Delivery and Energy
Reliability (OE–20), U.S. Department of
Energy, 1000 Independence Avenue,
SW., Washington, DC 20585–0350.
FOR FURTHER INFORMATION CONTACT:
Ellen Russell (Program Office) (202)
VerDate Aug<31>2005
15:39 Oct 31, 2005
Jkt 208001
586–9624 or Michael T. Skinker
(Program Attorney) (202) 586–2793.
The
construction, operation, maintenance,
and connection of facilities at the
international border of the United States
for the transmission of electric energy
between the United States and a foreign
country is prohibited in the absence of
a Presidential permit issued pursuant to
Executive Order (EO) 10485, as
amended by EO 12038.
On October 7, 2005, MATL, a
Canadian corporation, filed an
application with the Office of Electricity
Delivery and Energy Reliability (OE) of
the Department of Energy (DOE) for a
Presidential permit. MATL proposes to
construct a single-circuit 230-kilovolt
(230-kV) electric transmission line
across the U.S.-Canada international
border.
The MATL transmission line project
would connect the Alberta
Interconnected Electrical System and
NorthWestern Energy’s (NWE)
transmission system. NWE is a U.S.
investor-owned utility serving electric
customers in Montana, South Dakota
and Nebraska. The proposed
international transmission line would
originate at a new substation to be
constructed northeast of Lethbridge,
Alberta, Canada, cross the U.S.-Canada
international border directly north of
Cut Bank, Montana (west of Sweetgrass,
Montana) and extend approximately 125
miles into the U.S., terminating at an
existing 230-kV substation owned by
NWE north of Great Falls, Montana.
Between the U.S.-Canada border and
Great Falls, the transmission line would
also connect to an existing substation
owned by Glacier Electric Cooperatives
in Cut Bank, Montana. A phase shifting
transformer would be installed at the
substation in Lethbridge, Alberta, to
control power flows between the two
regions.
MATL has indicated its intention to
operate the proposed facilities as a
merchant transmission line and make it
available for third-party use. MATL has
not applied to DOE under section 202(e)
of the Federal Power Act (FPA) (16
U.S.C. 824a(e)) for authorization to
export electric energy over the proposed
facilities. If DOE were to grant the
requested Presidential permit and
MATL were to subsequently construct
the proposed international transmission
line, any person wishing to export
electric energy to Canada utilizing those
facilities would need to obtain export
authority from DOE under section
202(e) of the FPA.
SUPPLEMENTARY INFORMATION:
PO 00000
Frm 00015
Fmt 4703
Sfmt 4703
65891
Procedural Matters
Any person desiring to become a
party to this proceeding or to be heard
by filing comments or protests to this
application should file a petition to
intervene, comment or protest at the
address provided above in accordance
with §§ 385.211 or 385.214 of the
FERC’s Rules of Practice and Procedures
(18 CFR 385.211, 385.214). Fifteen
copies of each petition and protest
should be filed with the DOE on or
before the date listed above.
Additional copies of such petitions to
intervene or protests also should be
filed directly with: Mr. Bob Williams,
Vice President Regulatory, Montana
Alberta Tie Ltd., Rocky Mountain Plaza,
Suite 800, 615 Macleod Trail SE.,
Calgary, Alberta, Canada AND Richard
P. Sparling, Alston & Bird LLP, 601
Pennsylvania Avenue NW., North
Building, 10th Floor, Washington, DC
20004–2601.
Before a Presidential permit may be
issued or amended, the DOE must
determine that the proposed action will
not adversely impact on the reliability
of the U.S. electric power supply
system. In addition, DOE must consider
the environmental impacts of the
proposed action (i.e., granting the
Presidential permit, with any conditions
and limitations, or denying the permit)
pursuant to the National Environmental
Policy Act (NEPA). DOE also must
obtain the concurrence of the Secretary
of State and the Secretary of Defense
before taking final action on a
Presidential permit application.
Copies of this application will be
made available, upon request, for public
inspection and copying at the address
provided above. In addition, the
application may be reviewed or
downloaded electronically at https://
www.fe.doe.gov/programs/
electricityregulation/. Upon reaching the
home page, select ‘‘Pending
Proceedings.’’
Dated: Issued in Washington, DC, on
October 26, 2005.
Anthony J. Como,
Director, Siting and Permitting, Office of
Electricity Delivery and Energy Reliability.
[FR Doc. 05–21741 Filed 10–31–05; 8:45 am]
BILLING CODE 6450–01–P
E:\FR\FM\01NON1.SGM
01NON1
Agencies
[Federal Register Volume 70, Number 210 (Tuesday, November 1, 2005)]
[Notices]
[Page 65891]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 05-21741]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[OE Docket No. PP-305]
Application for Presidential Permit; Montana Alberta Tie Ltd.
AGENCY: Office of Electricity Delivery and Energy Reliability, DOE.
ACTION: Notice of application.
-----------------------------------------------------------------------
SUMMARY: Montana Alberta Tie Ltd. (MATL) has applied for a Presidential
permit to construct, operate, maintain, and connect an electric
transmission line across the U.S. border with Canada.
DATES: Comments, protests, or requests to intervene must be submitted
on or before December 1, 2005.
ADDRESSES: Comments, protests, or requests to intervene should be
addressed as follows: Office of Electricity Delivery and Energy
Reliability (OE-20), U.S. Department of Energy, 1000 Independence
Avenue, SW., Washington, DC 20585-0350.
FOR FURTHER INFORMATION CONTACT: Ellen Russell (Program Office) (202)
586-9624 or Michael T. Skinker (Program Attorney) (202) 586-2793.
SUPPLEMENTARY INFORMATION: The construction, operation, maintenance,
and connection of facilities at the international border of the United
States for the transmission of electric energy between the United
States and a foreign country is prohibited in the absence of a
Presidential permit issued pursuant to Executive Order (EO) 10485, as
amended by EO 12038.
On October 7, 2005, MATL, a Canadian corporation, filed an
application with the Office of Electricity Delivery and Energy
Reliability (OE) of the Department of Energy (DOE) for a Presidential
permit. MATL proposes to construct a single-circuit 230-kilovolt (230-
kV) electric transmission line across the U.S.-Canada international
border.
The MATL transmission line project would connect the Alberta
Interconnected Electrical System and NorthWestern Energy's (NWE)
transmission system. NWE is a U.S. investor-owned utility serving
electric customers in Montana, South Dakota and Nebraska. The proposed
international transmission line would originate at a new substation to
be constructed northeast of Lethbridge, Alberta, Canada, cross the
U.S.-Canada international border directly north of Cut Bank, Montana
(west of Sweetgrass, Montana) and extend approximately 125 miles into
the U.S., terminating at an existing 230-kV substation owned by NWE
north of Great Falls, Montana. Between the U.S.-Canada border and Great
Falls, the transmission line would also connect to an existing
substation owned by Glacier Electric Cooperatives in Cut Bank, Montana.
A phase shifting transformer would be installed at the substation in
Lethbridge, Alberta, to control power flows between the two regions.
MATL has indicated its intention to operate the proposed facilities
as a merchant transmission line and make it available for third-party
use. MATL has not applied to DOE under section 202(e) of the Federal
Power Act (FPA) (16 U.S.C. 824a(e)) for authorization to export
electric energy over the proposed facilities. If DOE were to grant the
requested Presidential permit and MATL were to subsequently construct
the proposed international transmission line, any person wishing to
export electric energy to Canada utilizing those facilities would need
to obtain export authority from DOE under section 202(e) of the FPA.
Procedural Matters
Any person desiring to become a party to this proceeding or to be
heard by filing comments or protests to this application should file a
petition to intervene, comment or protest at the address provided above
in accordance with Sec. Sec. 385.211 or 385.214 of the FERC's Rules of
Practice and Procedures (18 CFR 385.211, 385.214). Fifteen copies of
each petition and protest should be filed with the DOE on or before the
date listed above.
Additional copies of such petitions to intervene or protests also
should be filed directly with: Mr. Bob Williams, Vice President
Regulatory, Montana Alberta Tie Ltd., Rocky Mountain Plaza, Suite 800,
615 Macleod Trail SE., Calgary, Alberta, Canada AND Richard P.
Sparling, Alston & Bird LLP, 601 Pennsylvania Avenue NW., North
Building, 10th Floor, Washington, DC 20004-2601.
Before a Presidential permit may be issued or amended, the DOE must
determine that the proposed action will not adversely impact on the
reliability of the U.S. electric power supply system. In addition, DOE
must consider the environmental impacts of the proposed action (i.e.,
granting the Presidential permit, with any conditions and limitations,
or denying the permit) pursuant to the National Environmental Policy
Act (NEPA). DOE also must obtain the concurrence of the Secretary of
State and the Secretary of Defense before taking final action on a
Presidential permit application.
Copies of this application will be made available, upon request,
for public inspection and copying at the address provided above. In
addition, the application may be reviewed or downloaded electronically
at https://www.fe.doe.gov/programs/electricityregulation/. Upon reaching
the home page, select ``Pending Proceedings.''
Dated: Issued in Washington, DC, on October 26, 2005.
Anthony J. Como,
Director, Siting and Permitting, Office of Electricity Delivery and
Energy Reliability.
[FR Doc. 05-21741 Filed 10-31-05; 8:45 am]
BILLING CODE 6450-01-P