Flambeau Hydro, LLC; Notice Soliciting Scoping Comments, 57595 [E5-5390]
Download as PDF
Federal Register / Vol. 70, No. 190 / Monday, October 3, 2005 / Notices
filing’’ link. The Commission strongly
encourages electronic filing.
r. Filing and Service of Responsive
Documents—Any filings must bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘NOTICE OF INTENT
TO FILE COMPETING APPLICATION’’,
‘‘COMPETING APPLICATION’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’, as applicable, and the
Project Number of the particular
application to which the filing refers.
Any of the above-named documents
must be filed by providing the original
and the number of copies provided by
the Commission’s regulations to: The
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426. An additional
copy must be sent to Director, Division
of Hydropower Administration and
Compliance, Federal Energy Regulatory
Commission, at the above-mentioned
address. A copy of any notice of intent,
competing application or motion to
intervene must also be served upon each
representative of the Applicant
specified in the particular application.
s. Agency Comments—Federal, State,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E5–5376 Filed 9–30–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 9185–009]
Flambeau Hydro, LLC; Notice
Soliciting Scoping Comments
September 26, 2005.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
License.
b. Project No.: P–9185–009.
c. Date filed: April 1, 2005.
d. Applicant: Flambeau Hydro, LLC.
e. Name of Project: Clam River
Hydroelectric Project.
f. Location: On the Clam River in
Burnett County, near Danbury,
VerDate Aug<31>2005
17:26 Sep 30, 2005
Jkt 205001
Wisconsin. The project does not occupy
Federal lands.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Scott Klabunde,
North American Hydro, Inc., P.O. Box
167, Neshkoro, WI 54960; 920–293–
4628 ext. 14.
i. FERC Contact: Patrick Murphy,
(202) 502–8755 or
patrick.murphy@ferc.gov.
j. Deadline for filing scoping
comments: October 31, 2005.
All documents (original and eight
copies) should be filed with: Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
Scoping comments may be filed
electronically via the Internet in lieu of
paper. The Commission strongly
encourages electronic filings. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov) under the
‘‘eFiling’’ link.
k. This application is not ready for
environmental analysis at this time.
l. The existing Clam River Project
consists of: (1) A 46-foot-high buttress
type concrete dam concrete with a 54foot-wide spillway with four sections,
three sections equipped with 8-inchhigh stoplogs, and one section equipped
with a 4-foot-high slide gate; (2) an 898foot-long and 223-foot-long earthen
dikes connecting the left side and the
right side of the concrete dam,
respectively; (3) a 360-acre reservoir
with a net storage capacity of 3,575 acrefeet with a water surface elevation of
898.9 feet msl; (4) two powerhouses
integral to the dam containing three
turbine generating units with a total
installed capacity of 1,200 kW; (5) a
100-foot-long, 2.4-kilovolt transmission
line; and (6) appurtenant facilities. The
applicant estimates that the total
average annual generation would be
4,903 megawatt hours.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
57595
the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h above.
n. You may also register online at
https://www.ferc.gov.esubscribernow.htm
to be notified via e-mail of new filings
and issuances related to this or other
pending projects. For assistance, contact
FERC Online Support.
o. Scoping Process: The Commission
staff intends to prepare an
Environmental Assessment (EA) for the
Clam River Hydroelectric Project in
accordance with the National
Environmental Policy Act. The EA will
consider both site-specific and
cumulative environmental impacts and
reasonable alternatives to the proposed
action.
Commission staff does not propose to
conduct any on-site scoping meetings at
this time. Instead, we will solicit
comments, recommendations,
information, and alternatives in the
Scoping Document (SD).
Copies of the SD outlining the subject
areas to be addressed in the EA were
distributed to the parties on the
Commission’s mailing list. Copies of the
SD may be viewed on the Web at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call 1–866–
208–3676 or for TTY, (202) 502–8659.
Magalie R. Salas,
Secretary.
[FR Doc. E5–5390 Filed 9–30–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 7758–004]
Holyoke No. 4 Project; Notice of
Application Ready for Environmental
Analysis and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions
September 27, 2005.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
License.
b. Project No.: P–7758–004.
c. Date Filed: February 25, 2005.
E:\FR\FM\03OCN1.SGM
03OCN1
Agencies
[Federal Register Volume 70, Number 190 (Monday, October 3, 2005)]
[Notices]
[Page 57595]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-5390]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 9185-009]
Flambeau Hydro, LLC; Notice Soliciting Scoping Comments
September 26, 2005.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Subsequent License.
b. Project No.: P-9185-009.
c. Date filed: April 1, 2005.
d. Applicant: Flambeau Hydro, LLC.
e. Name of Project: Clam River Hydroelectric Project.
f. Location: On the Clam River in Burnett County, near Danbury,
Wisconsin. The project does not occupy Federal lands.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Scott Klabunde, North American Hydro, Inc.,
P.O. Box 167, Neshkoro, WI 54960; 920-293-4628 ext. 14.
i. FERC Contact: Patrick Murphy, (202) 502-8755 or
patrick.murphy@ferc.gov.
j. Deadline for filing scoping comments: October 31, 2005.
All documents (original and eight copies) should be filed with:
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
Scoping comments may be filed electronically via the Internet in
lieu of paper. The Commission strongly encourages electronic filings.
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's
Web site (https://www.ferc.gov) under the ``eFiling'' link.
k. This application is not ready for environmental analysis at this
time.
l. The existing Clam River Project consists of: (1) A 46-foot-high
buttress type concrete dam concrete with a 54-foot-wide spillway with
four sections, three sections equipped with 8-inch-high stoplogs, and
one section equipped with a 4-foot-high slide gate; (2) an 898-foot-
long and 223-foot-long earthen dikes connecting the left side and the
right side of the concrete dam, respectively; (3) a 360-acre reservoir
with a net storage capacity of 3,575 acre-feet with a water surface
elevation of 898.9 feet msl; (4) two powerhouses integral to the dam
containing three turbine generating units with a total installed
capacity of 1,200 kW; (5) a 100-foot-long, 2.4-kilovolt transmission
line; and (6) appurtenant facilities. The applicant estimates that the
total average annual generation would be 4,903 megawatt hours.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1-
866-208-3676, or for TTY, (202) 502-8659. A copy is also available for
inspection and reproduction at the address in item h above.
n. You may also register online at https://
www.ferc.gov.esubscribernow.htm to be notified via e-mail of new
filings and issuances related to this or other pending projects. For
assistance, contact FERC Online Support.
o. Scoping Process: The Commission staff intends to prepare an
Environmental Assessment (EA) for the Clam River Hydroelectric Project
in accordance with the National Environmental Policy Act. The EA will
consider both site-specific and cumulative environmental impacts and
reasonable alternatives to the proposed action.
Commission staff does not propose to conduct any on-site scoping
meetings at this time. Instead, we will solicit comments,
recommendations, information, and alternatives in the Scoping Document
(SD).
Copies of the SD outlining the subject areas to be addressed in the
EA were distributed to the parties on the Commission's mailing list.
Copies of the SD may be viewed on the Web at https://www.ferc.gov using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, call 1-866-208-3676 or for TTY, (202) 502-8659.
Magalie R. Salas,
Secretary.
[FR Doc. E5-5390 Filed 9-30-05; 8:45 am]
BILLING CODE 6717-01-P