Carolina Power & Light Company, Brunswick Steam Electric Plant, Units 1 and 2; Notice of Withdrawal of Applications for Amendments to Facility Operating Licenses, 54586-54587 [E5-5022]
Download as PDF
54586
Federal Register / Vol. 70, No. 178 / Thursday, September 15, 2005 / Notices
applicant on a material issue of law or
fact.1 Contentions shall be limited to
matters within the scope of the action
under consideration. The contention
must be one that, if proven, would
entitle the requestor/petitioner to relief.
A requestor/petitioner who fails to
satisfy these requirements with respect
to at least one contention will not be
permitted to participate as a party.
The Commission requests that each
contention be given a separate numeric
or alpha designation within one of the
following groups: (1) Technical
(primarily related to safety concerns);
(2) environmental; or (3) miscellaneous.
As specified in 10 CFR 2.309, if two
or more requestors/petitioners seek to
co-sponsor a contention or propose
substantially the same contention, the
requestors/petitioners will be required
to jointly designate a representative who
shall have the authority to act for the
requestors/petitioners with respect to
that contention.
Those permitted to intervene become
parties to the proceeding, subject to any
limitations in the order granting leave to
intervene, and have the opportunity to
participate fully in the conduct of the
hearing. A request for a hearing or a
petition for leave to intervene must be
filed by: (1) First class mail addressed
to the Office of the Secretary of the
Commission, U.S. Nuclear Regulatory
Commission, Washington, DC, 20555–
0001, Attention: Rulemaking and
Adjudications Staff; (2) courier, express
mail, and expedited delivery services:
Office of the Secretary, Sixteenth Floor,
One White Flint North, 11555 Rockville
Pike, Rockville, Maryland, 20852,
Attention: Rulemaking and
Adjudications Staff; (3) E-mail
addressed to the Office of the Secretary,
U.S. Nuclear Regulatory Commission,
HEARINGDOCKET@NRC.GOV; or (4)
facsimile transmission addressed to the
Office of the Secretary, U.S. Nuclear
Regulatory Commission, Washington,
DC, Attention: Rulemakings and
Adjudications Staff at 301–415–1101,
verification number is 301–415–1966.2
A copy of the request for hearing and
petition for leave to intervene must also
be sent to the Office of the General
1 To the extent that the application contains
attachments and supporting documents that are not
publicly available because they are asserted to
contain safeguards or proprietary information,
petitioners desiring access to this information
should contact the applicant or applicant’s counsel
to discuss the need for a protection order.
2 If the request/petition is filed by e-mail or
facsimile, an original and two copies of the
document must be mailed within 2 (two) business
days thereafter to the Secretary, U.S. Nuclear
Regulatory Commission, Washington, DC 20555–
0001; Attention: Rulemaking and Adjudications
Staff.
VerDate Aug<18>2005
15:03 Sep 14, 2005
Jkt 205001
Counsel, U.S. Nuclear Regulatory
Commission, Washington, DC, 20555–
0001, and it is requested that copies be
transmitted either by means of facsimile
transmission to 301–415–3725 or by email to OGCMailCenter@nrc.gov. A copy
of the request for hearing and petition
for leave to intervene should also be
sent to the attorney for the applicant,
Kathryn M. Sutton, Esquire, Morgan,
Lewis, & Bockius LLP, 1111
Pennsylvania Avenue, NW.,
Washington, DC, 20004.
Non-timely requests and/or petitions
and contentions will not be entertained
absent a determination by the
Commission, the presiding officer, or
the Atomic Safety and Licensing Board
that the petition, request and/or
contentions should be granted based on
a balancing of the factors specified in 10
CFR 2.309(a)(1)(I)–(viii).
Detailed information about the license
renewal process can be found under the
Nuclear Reactors icon at https://
www.nrc.gov/reactors/operating/
licensing/renewal.html on the NRC’s
Web site. Copies of the application to
renew the operating license for Oyster
Creek Nuclear Generating Station are
available for public inspection at the
Commission’s PDR, located at One
White Flint North, 11555 Rockville
Pike, First Floor, Rockville, Maryland
20852–2738, and at https://www.nrc.gov/
reactors/operating/licensing/renewal/
applications.html, the NRC’s Web site
while the application is under review.
The NRC maintains an Agencywide
Documents Access and Management
System (ADAMS), which provides text
and image files of NRC’s public
documents. These documents may be
accessed through the NRC’s Public
Electronic Reading Room on the Internet
at https://www.nrc.gov/reading-rm/
adams.html under ADAMS accession
number ML052080172. Persons who do
not have access to ADAMS or who
encounter problems in accessing the
documents located in ADAMS may
contact the NRC Public Document Room
(PDR) Reference staff by telephone at 1–
800–397–4209, 301–415–4737, or by email to pdr@nrc.gov.
The staff has verified that a copy of
the license renewal application is also
available to local residents near the
Oyster Creek Nuclear Generating Station
at the Lacey Public Library, 10 East
Lacey Road, Forked River, NJ 08731.
Dated at Rockville, Maryland, this 9th day
of September, 2005.
PO 00000
Frm 00067
Fmt 4703
Sfmt 4703
For the Nuclear Regulatory Commission.
Samson S. Lee,
Acting Program Director, License Renewal
and Environmental Impacts Program,
Division of Regulatory Improvement
Programs, Office of Nuclear Reactor
Regulation.
[FR Doc. E5–5024 Filed 9–14–05; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–325 AND 50–324]
Carolina Power & Light Company,
Brunswick Steam Electric Plant, Units
1 and 2; Notice of Withdrawal of
Applications for Amendments to
Facility Operating Licenses
The U.S. Nuclear Regulatory
Commission (the Commission) has
granted the request of Carolina Power &
Light Company (the licensee) to
withdraw its November 12, 2002,
application, as supplemented on March
5, 2004, for proposed amendments to
Facility Operating License No. DPR–71
and Facility Operating License No.
DPR–62 for Brunswick Steam Electric
Plant, Units 1 and 2, respectively,
located in Brunswick County, North
Carolina.
The proposed amendments would
have revised the Technical
Specifications, as necessary, to support
an expansion of the core flow operating
range (i.e., Maximum Extended Load
Line Limit Analysis Plus (MELLLA+)).
As part of the MELLLA+
implementation, Carolina Power & Light
Company would implement the Detect
and Suppress Solution-Confirmation
Density (DSS–CD) approach to
automatically detect and suppress
neutronic/thermal-hydraulic
instabilities.
The Commission had previously
issued a Notice of Consideration of
Issuance of Amendment published in
the Federal Register on February 18,
2003 (68 FR 7813), and renoticed on
April 27, 2004 (69 FR 22880). However,
by letter dated August 25, 2005, the
licensee withdrew the proposed change.
For further details with respect to this
action, see the application for
amendments dated November 12, 2002,
as supplemented March 5, 2004, and the
licensee’s letter dated August 25, 2005,
which withdrew the application for
license amendments. Documents may be
examined, and/or copied for a fee, at the
NRC’s Public Document Room (PDR),
located at One White Flint North, Public
File Area 01 F21, 11555 Rockville Pike
(first floor), Rockville, Maryland.
Publicly available records will be
E:\FR\FM\15SEN1.SGM
15SEN1
Federal Register / Vol. 70, No. 178 / Thursday, September 15, 2005 / Notices
accessible electronically from the
Agencywide Documents Access and
Management Systems (ADAMS) Public
Electronic Reading Room on the Internet
at the NRC Web site, https://
www.nrc.gov/reading-rm/adams/html.
Persons who do not have access to
ADAMS or who encounter problems in
accessing the documents located in
ADAMS, should contact the NRC PDR
Reference staff by telephone at 1–800–
397–4209, or 301–415–4737 or by e-mail
to pdr@nrc.gov.
Dated at Rockville, Maryland, this 8th day
of September 2005.
For the Nuclear Regulatory Commission.
Brenda L. Mozafari,
Senior Project Manager, Section 2, Project
Directorate II, Division of Licensing Project
Management, Office of Nuclear Reactor
Regulation.
[FR Doc. E5–5022 Filed 9–14–05; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–213]
Connecticut Yankee Atomic Power
Company, Haddam Neck Plant; Partial
Exemption from Requirements of 10
CFR Part 50 Appendix A, Criterion 1,
10 CFR Part 50 Appendix B, Criterion
XVII, and 10 CFR 50.59(d)(3)
1.0 Background
Connecticut Yankee Atomic Power
Company (CY) is the licensee and
holder of Facility Operating License No.
DPR–61 for the Haddam Neck Plant
(HNP), a permanently shutdown
decommissioning nuclear plant.
Although permanently shutdown, this
facility is still subject to all rules,
regulations, and orders of the U.S.
Nuclear Regulatory Commission (NRC).
On December 5, 1996, CY notified
NRC that operations had permanently
ceased and that all fuel had been
permanently removed from the reactor.
On July 7, 2000, CY submitted its
License Termination Plan (LTP), which
the NRC approved on November 25,
2002.
CY began actively decommissioning
HNP in April 1999, through a contract
with Bechtel Power Corporation. In June
2003, CY began managing the
decommissioning using staff
augmentation and subcontractors for
speciality work.
The nuclear reactor and all associated
systems and components necessary for
the safe generation of power have been
removed from the facility and disposed
or sold off-site. Additionally, the
structures necessary for safe power
VerDate Aug<18>2005
15:03 Sep 14, 2005
Jkt 205001
generation are either demolished or in
an advanced state of demolition. There
are no safety-related structures, systems
and components (SSCs) remaining at the
HNP. Transfer of the spent fuel (SF) and
greater-than-Class C (GTCC) waste from
the SF pool to the HNP Independent
Spent Fuel Storage Installation (ISFSI)
was completed on March 30, 2005, but
the SF pool has not yet been drained, so
it is not ready for demolition.
On February 16, 2005, CY filed a
request for NRC approval of an
exemption from the recordkeeping
requirements of 10 CFR Part 50
Appendix A, Criterion 1, 10 CFR Part 50
Appendix B, Criterion XVII, and 10 CFR
50.59(d)(3).
2.0
Request/Action
Pursuant to the requirements of 10
CFR 50.12, CY requested the following
exemption, to the extent necessary, from
the record retention requirements of:
(1) 10 CFR Part 50 Appendix A,
Criterion 1, which requires certain
records be retained ‘‘throughout the life
of the unit’’;
(2) 10 CFR Part 50 Appendix B,
Section XVII, which requires certain
records be retained consistent with
applicable regulatory requirements for a
duration established by the licensee;
and
(3) 10 CFR Part 50.59(d)(3), which
requires certain records be maintained
until ‘‘termination of a license issued
pursuant to’’ Part 50.
CY proposes to eliminate these
records when: (1) The nuclear power
unit and associated support systems no
longer exist for SSCs associated with
safe power generation, or (2) spent
nuclear fuel has been completely
transferred from the spent fuel pool and
the building is ready for demolition.
CY is not requesting any exemption
associated with record keeping
requirements for storage of spent fuel at
its ISFSI under 10 CFR Part 50 or the
general license requirements of 10 CFR
Part 72.
Most of these records are for SSCs that
have been removed from HNP and
disposed of offsite. Disposal of these
records will not adversely impact the
ability to meet other NRC regulatory
requirements for the retention of records
[e.g., 10 CFR 50.54(a), (p), (q), and (bb);
10 CFR 50.59(d); 10 CFR 50.57(g)].
These regulatory requirements ensure
that records from operation and
decommissioning activities are
maintained for safe decommissioning,
spent nuclear fuel storage, completion
and verification of final site survey, and
license termination.
PO 00000
Frm 00068
Fmt 4703
Sfmt 4703
54587
3.0 Discussion
NRC licensees are required to
maintain their records according to the
NRC regulatory recordkeeping
requirements. Pursuant to the
requirements of 10 CFR 50.12, ‘‘Specific
Exemptions,’’ CY filed a request for a
partial exemption from the NRC
recordkeeping requirements contained
in 10 CFR Part 50 Appendix A, Criterion
1, 10 CFR Part 50 Appendix B, Criterion
XVII, and 10 CFR 50.59 (d)(3). The NRC
recordkeeping requirements at issue in
CY’s request for exemption are as
follows.
10 CFR Part 50, Appendix A,
‘‘General Design Criteria for Nuclear
Power Plants,’’ establishes the necessary
design, fabrication, construction,
testing, and performance requirements
for structures, systems, and components
important to safety. Specifically, CY
requests an exemption from Criterion 1,
‘‘Quality standards and records,’’ which
states in part:
Appropriate records of the design,
fabrication, erection, and testing of
structures, systems, and components
important to safety shall be maintained by or
under the control of the nuclear power unit
licensee throughout the life of the unit.
10 CFR Part 50, Appendix B, ‘‘Quality
Assurance Criteria for Nuclear Power
Plants and Fuel Reprocessing Plants,’’
establishes quality assurance
requirements for the design,
construction, and operation of
structures, systems, and components
that prevent or mitigate the
consequences of postulated accidents
that could cause undue risk to the
health and safety of the public.
Specifically, CY requests an exemption
from Criterion XVII, ‘‘Quality Assurance
Records’’, which states:
Sufficient records shall be maintained to
furnish evidence of activities affecting
quality. The records shall include at least the
following: Operating logs and the results of
reviews, inspections, tests, audits,
monitoring of work performance, and
materials analyses. The records shall also
include closely-related data such as
qualifications of personnel, procedures, and
equipment. Inspection and test records shall,
as a minimum, identify the inspector or data
recorder, the type of observation, the results,
the acceptability, and the action taken in
connection with any deficiencies noted.
Records shall be identifiable and retrievable.
Consistent with applicable regulatory
requirements, the applicant shall establish
requirements concerning record retention,
such as duration, location, and assigned
responsibility.
CY also requests an exemption from
10 CFR 50.59(d)(3), which states: ‘‘The
records of changes in the facility must
be maintained until the termination of
a license issued pursuant to this part or
E:\FR\FM\15SEN1.SGM
15SEN1
Agencies
[Federal Register Volume 70, Number 178 (Thursday, September 15, 2005)]
[Notices]
[Pages 54586-54587]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-325 AND 50-324]
Carolina Power & Light Company, Brunswick Steam Electric Plant,
Units 1 and 2; Notice of Withdrawal of Applications for Amendments to
Facility Operating Licenses
The U.S. Nuclear Regulatory Commission (the Commission) has granted
the request of Carolina Power & Light Company (the licensee) to
withdraw its November 12, 2002, application, as supplemented on March
5, 2004, for proposed amendments to Facility Operating License No. DPR-
71 and Facility Operating License No. DPR-62 for Brunswick Steam
Electric Plant, Units 1 and 2, respectively, located in Brunswick
County, North Carolina.
The proposed amendments would have revised the Technical
Specifications, as necessary, to support an expansion of the core flow
operating range (i.e., Maximum Extended Load Line Limit Analysis Plus
(MELLLA+)). As part of the MELLLA+ implementation, Carolina Power &
Light Company would implement the Detect and Suppress Solution-
Confirmation Density (DSS-CD) approach to automatically detect and
suppress neutronic/thermal-hydraulic instabilities.
The Commission had previously issued a Notice of Consideration of
Issuance of Amendment published in the Federal Register on February 18,
2003 (68 FR 7813), and renoticed on April 27, 2004 (69 FR 22880).
However, by letter dated August 25, 2005, the licensee withdrew the
proposed change.
For further details with respect to this action, see the
application for amendments dated November 12, 2002, as supplemented
March 5, 2004, and the licensee's letter dated August 25, 2005, which
withdrew the application for license amendments. Documents may be
examined, and/or copied for a fee, at the NRC's Public Document Room
(PDR), located at One White Flint North, Public File Area 01 F21, 11555
Rockville Pike (first floor), Rockville, Maryland. Publicly available
records will be
[[Page 54587]]
accessible electronically from the Agencywide Documents Access and
Management Systems (ADAMS) Public Electronic Reading Room on the
Internet at the NRC Web site, https://www.nrc.gov/reading-rm/adams/html.
Persons who do not have access to ADAMS or who encounter problems in
accessing the documents located in ADAMS, should contact the NRC PDR
Reference staff by telephone at 1-800-397-4209, or 301-415-4737 or by
e-mail to pdr@nrc.gov.
Dated at Rockville, Maryland, this 8th day of September 2005.
For the Nuclear Regulatory Commission.
Brenda L. Mozafari,
Senior Project Manager, Section 2, Project Directorate II, Division of
Licensing Project Management, Office of Nuclear Reactor Regulation.
[FR Doc. E5-5022 Filed 9-14-05; 8:45 am]
BILLING CODE 7590-01-P