Notice of Application Accepting for Filing and Soliciting Motions To Intervene, Protests and Comments, 51772-51773 [E5-4735]
Download as PDF
51772
Federal Register / Vol. 70, No. 168 / Wednesday, August 31, 2005 / Notices
(5) a new 3.5-mile-long, 12.5 kV
transmission line to be interconnected
with the Puget Sound Energy’s
transmission lines at Lake Tyee; and (6)
appurtenant facilities. The proposed
project would operate in a run-of-river
mode. The estimated annual generation
is 11.7 million kWh. Generated power
would be sold to Puget Sound Energy.
i. Locations of Applications: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street NE.,
Room 2A, Washington, DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h.
above.
j. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
k. Competing Preliminary Permit—
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30(b) and 4.36.
l. Competing Development
Application—Any qualified
development applicant desiring to file a
competing development application
must submit to the Commission, on or
before a specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30(b) and 4.36.
m. Notice of Intent—A notice of intent
must specify the exact name, business
VerDate Aug<18>2005
16:33 Aug 30, 2005
Jkt 205001
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
n. Proposed Scope of Studies Under
Permit—A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
o. Comments, Protests, or Motions To
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper; See 18 CFR
385.2001 (a)(1)(iii) and the instructions
on the Commission’s Web site under ‘‘efiling’’ link. The Commission strongly
encourages electronic filing.
p. Filing and Service of Responsive
Documents—Any filings must bear in
all capital letters the title
‘‘COMMENTS’’,
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’, as
applicable, and the Project Number of
the particular application to which the
filing refers. Any of the above-named
documents must be filed by providing
the original and the number of copies
provided by the Commission’s
regulations to: The Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
A copy of any motion to intervene must
also be served upon each representative
of the Applicant specified in the
particular application.
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
q. Agency Comments—Federal, State,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E5–4734 Filed 8–30–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Accepting for
Filing and Soliciting Motions To
Intervene, Protests and Comments
August 23, 2005.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
Permit.
b. Project No.: 12596–000.
c. Date filed: June 8, 2005.
d. Applicant: Ophir Valley Land
Company, LLC.
e. Name of Project: Carbonero
Hydroelectric Project.
f. Location: On Carbonero Mine Adit,
near Ophir, San Miguel County,
Colorado, within the Uncompagre
National Forest. The mine is owned by
Glenn Pauls, Placerville, CO.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Vincent A.
Lamarra, Ph.D., Ecosystems Research
Institute, 975 S. Highway 89/91, Logan,
UT 84321, (435) 752–2580, or Glenn
Pauls, Ophir Valley Land Company,
LLC, P.O. Box 426, Placerville, CO
81430, (970) 728–3540.
i. FERC Contact: Etta Foster, (202)
502–8769.
j. Deadline for filing comments,
protests, and motions to intervene: 60
days from the issuance date of this
notice.
All documents (original and eight
copies) should be filed with Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
Please include the project number (P–
12596–000) on any comments, protests,
or motions filed.
k. Description of Project: The
proposed project would consist of: (1)
E:\FR\FM\31AUN1.SGM
31AUN1
Federal Register / Vol. 70, No. 168 / Wednesday, August 31, 2005 / Notices
An existing mine adit spillway; (2) a 24inch, 4,100-foot-long steel penstock; (3)
a powerhouse containing two units
having a total installed capacity of 500
kW; (4) a 200-foot-long tailrace; (5) a
new 15 kV transmission line; and (6)
appurtenant facilities. There are neither
dams nor reservoirs associated with this
proposed project.
The project would have an annual
generation of 1.34 GWh. The applicant
anticipates generated power will feed
into the nearby existing electrical grid
system and interconnect with an
existing distribution system in the town
of Ophir.
l. Location of Application: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street, NE.,
Room 2A, Washington, DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h.
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Competing Preliminary Permit—
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30(b) and 4.36.
o. Competing Development
Application—Any qualified
development applicant desiring to file a
competing development application
must submit to the Commission, on or
before a specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
VerDate Aug<18>2005
16:33 Aug 30, 2005
Jkt 205001
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30(b) and 4.36.
p. Notice of Intent—a notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
q. Proposed Scope of Studies under
Permit—A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper; See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under ‘‘efiling’’ link. The Commission strongly
encourages electronic filing.
s. Filing and Service of Responsive
Documents—Any filings must bear in
all capital letter the title
‘‘COMMENTS’’,
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’, as
applicable, and the Project Number of
the particular application to which the
filing refers. Any of the above-named
documents must be filed by providing
the original and the number of copies
provided by the Commission’s
regulations to: The Secretary, Federal
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
51773
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
A copy of any motion to intervene must
also be served upon each representative
of the Applicant specified in the
particular application.
t. Agency Comments—Federal, State,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E5–4735 Filed 8–30–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12608–000]
Alternatives Unlimited, Inc.; Notice of
Application Tendered for Filing With
the Commission, Soliciting Additional
Study Requests, and Establishing
Procedural Schedule for Licensing and
Deadline for Submission of Final
Amendments
August 23, 2005.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Exemption
From Licensing.
b. Project No.: P–12608–000.
c. Date Filed: August 15, 2005.
d. Applicant: Alternatives Unlimited,
Inc.
e. Name of Project: Alternatives
Hydro Power Project
f. Location: On the Mumford River in
the Town of Northbridge, Worcester
County, Massachusetts. The project does
not utilize lands of the United States.
g. Filed Pursuant to: Public Utilities
Regulatory Policies Act of 1978, 16
U.S.C. 2705, 2708.
h. Applicant Contact: Kathleen D.
Hervol, Beals and Thomas, Inc.,
Reservoir Corporate Center, 144
Turnpike Road (Road 9), Southborough,
MA 01772–6232, (508) 366–0560.
i. FERC Contact: Stefanie Harris, (202)
502–6653 or stefanie.harris@ferc.gov.
j. Cooperating Agencies: We are
asking Federal, State, and local agencies
and Indian tribes with jurisdiction and/
or special expertise with respect to
E:\FR\FM\31AUN1.SGM
31AUN1
Agencies
[Federal Register Volume 70, Number 168 (Wednesday, August 31, 2005)]
[Notices]
[Pages 51772-51773]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-4735]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Application Accepting for Filing and Soliciting Motions
To Intervene, Protests and Comments
August 23, 2005.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary Permit.
b. Project No.: 12596-000.
c. Date filed: June 8, 2005.
d. Applicant: Ophir Valley Land Company, LLC.
e. Name of Project: Carbonero Hydroelectric Project.
f. Location: On Carbonero Mine Adit, near Ophir, San Miguel County,
Colorado, within the Uncompagre National Forest. The mine is owned by
Glenn Pauls, Placerville, CO.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. Vincent A. Lamarra, Ph.D., Ecosystems
Research Institute, 975 S. Highway 89/91, Logan, UT 84321, (435) 752-
2580, or Glenn Pauls, Ophir Valley Land Company, LLC, P.O. Box 426,
Placerville, CO 81430, (970) 728-3540.
i. FERC Contact: Etta Foster, (202) 502-8769.
j. Deadline for filing comments, protests, and motions to
intervene: 60 days from the issuance date of this notice.
All documents (original and eight copies) should be filed with
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426. Please include the project
number (P-12596-000) on any comments, protests, or motions filed.
k. Description of Project: The proposed project would consist of:
(1)
[[Page 51773]]
An existing mine adit spillway; (2) a 24-inch, 4,100-foot-long steel
penstock; (3) a powerhouse containing two units having a total
installed capacity of 500 kW; (4) a 200-foot-long tailrace; (5) a new
15 kV transmission line; and (6) appurtenant facilities. There are
neither dams nor reservoirs associated with this proposed project.
The project would have an annual generation of 1.34 GWh. The
applicant anticipates generated power will feed into the nearby
existing electrical grid system and interconnect with an existing
distribution system in the town of Ophir.
l. Location of Application: A copy of the application is available
for inspection and reproduction at the Commission in the Public
Reference Room, located at 888 First Street, NE., Room 2A, Washington,
DC 20426, or by calling (202) 502-8371. This filing may also be viewed
on the Commission's Web site at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, call toll-free 1-866-208-3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item
h. above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Competing Preliminary Permit--Anyone desiring to file a
competing application for preliminary permit for a proposed project
must submit the competing application itself, or a notice of intent to
file such an application, to the Commission on or before the specified
comment date for the particular application (see 18 CFR 4.36).
Submission of a timely notice of intent allows an interested person to
file the competing preliminary permit application no later than 30 days
after the specified comment date for the particular application. A
competing preliminary permit application must conform with 18 CFR
4.30(b) and 4.36.
o. Competing Development Application--Any qualified development
applicant desiring to file a competing development application must
submit to the Commission, on or before a specified comment date for the
particular application, either a competing development application or a
notice of intent to file such an application. Submission of a timely
notice of intent to file a development application allows an interested
person to file the competing application no later than 120 days after
the specified comment date for the particular application. A competing
license application must conform with 18 CFR 4.30(b) and 4.36.
p. Notice of Intent--a notice of intent must specify the exact
name, business address, and telephone number of the prospective
applicant, and must include an unequivocal statement of intent to
submit, if such an application may be filed, either a preliminary
permit application or a development application (specify which type of
application). A notice of intent must be served on the applicant(s)
named in this public notice.
q. Proposed Scope of Studies under Permit--A preliminary permit, if
issued, does not authorize construction. The term of the proposed
preliminary permit would be 36 months. The work proposed under the
preliminary permit would include economic analysis, preparation of
preliminary engineering plans, and a study of environmental impacts.
Based on the results of these studies, the Applicant would decide
whether to proceed with the preparation of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to Intervene--Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
Comments, protests and interventions may be filed electronically
via the Internet in lieu of paper; See 18 CFR 385.2001(a)(1)(iii) and
the instructions on the Commission's Web site under ``e-filing'' link.
The Commission strongly encourages electronic filing.
s. Filing and Service of Responsive Documents--Any filings must
bear in all capital letter the title ``COMMENTS'', ``RECOMMENDATIONS
FOR TERMS AND CONDITIONS'', ``PROTEST'', or ``MOTION TO INTERVENE'', as
applicable, and the Project Number of the particular application to
which the filing refers. Any of the above-named documents must be filed
by providing the original and the number of copies provided by the
Commission's regulations to: The Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE., Washington, DC 20426. A copy of any
motion to intervene must also be served upon each representative of the
Applicant specified in the particular application.
t. Agency Comments--Federal, State, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the applicant. If
an agency does not file comments within the time specified for filing
comments, it will be presumed to have no comments. One copy of an
agency's comments must also be sent to the Applicant's representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E5-4735 Filed 8-30-05; 8:45 am]