Little Wood River Ranch II William Arkoosh; Notice of Availability of Final Environmental Assessment, 48697 [E5-4521]
Download as PDF
Federal Register / Vol. 70, No. 160 / Friday, August 19, 2005 / Notices
Applicants: Pacific Gas & Electric
Company.
Description: Pacific Gas & Electric
Company submits revised
interconnection agreement between
Pacific gas and Electric Company and
Modesto Irrigation District.
Filed Date: 08/03/2005.
Accession Number: 20050811–0266.
Comment Date: 5 p.m. eastern time on
Wednesday, August 24, 2005.
Docket Numbers: ER05–1288–000.
Applicants: Wheelabrator North
Andover Inc.
Description: Petition of Wheelabrator
North Andover Inc. for order accepting
market-based rate tariff for filing,
granting waiver of certain Commission
regulations; and granting certain blanket
approvals.
Filed Date: 08/03/2005.
Accession Number: 20050805–0169.
Comment Date: 5 p.m. eastern time on
Wednesday, August 24, 2005.
Any person desiring to intervene or to
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s Rules of
Practice and Procedure (18 CFR 385.211
and 385.214) on or before 5 p.m. eastern
time on the specified comment date. It
is not necessary to separately intervene
again in a subdocket related to a
compliance filing if you have previously
intervened in the same docket. Protests
will be considered by the Commission
in determining the appropriate action to
be taken, but will not serve to make
protestants parties to the proceeding.
Anyone filing a motion to intervene or
protest must serve a copy of that
document on the Applicant. In reference
to filings initiating a new proceeding,
interventions or protests submitted on
or before the comment deadline need
not be served on persons other and the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First St., NE., Washington, DC
20426.
The filings in the above proceedings
are accessible in the Commission’s
VerDate jul<14>2003
16:47 Aug 18, 2005
Jkt 205001
48697
eLibrary system by clicking on the
appropriate link in the above list. They
are also available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
eSubscription link on the Web site that
enables subscribers to receive e-mail
notification when a document is added
to a subscribed dockets(s). For
assistance with any FERC Online
service, please e-mail
FERCOnlineSupport@ferc.gov. or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
For further information, contact Gaylord
Hoisington at (202) 502–6032.
Magalie R. Salas,
Secretary.
[FR Doc. E5–4521 Filed 8–18–05; 8:45 am]
Linda Mitry,
Deputy Secretary.
[FR Doc. E5–4539 Filed 8–18–05; 8:45 am]
Wyoming Interstate Company, Ltd.;
Notice of Availability of the Final
Environmental Impact Statement for
the Proposed Piceance Basin
Expansion Project
BILLING CODE 6717–01–P
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP05–54–000]
August 12, 2005.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12063–001 Idaho]
Little Wood River Ranch II William
Arkoosh; Notice of Availability of Final
Environmental Assessment
August 12, 2005.
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s (Commission)
regulations, 18 CFR part 380 (Order No.
486, 52 F.R. 47897), the Office of Energy
Projects has reviewed the application
and prepared the enclosed
Environmental Assessment (EA) for an
original license for William Arkoosh’s
Little Wood River Ranch II
Hydroelectric Project. The proposed
project would be located on the Little
Wood River, 6 miles west of the town
of Shoshone, Lincoln County, Idaho.
The proposed project would be located
entirely on private lands owned by
William Arkoosh. The EA contains the
staff’s analysis of the potential
environmental impacts of the proposed
project and concludes that licensing the
project, with appropriate environmental
protective measures, would not
constitute a major federal action that
would significantly affect the quality of
the human environment.
A copy of the EA is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, call 1–866–208–3676 or for
TTY, (202) 502–8659.
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
The environmental staff of the Federal
Energy Regulatory Commission (FERC
or Commission) has prepared a final
Environmental Impact Statement (EIS)
on the interstate natural gas pipeline
transmission facilities proposed by
Wyoming Interstate Company, Ltd.
(WIC) in the above-referenced docket.
The final EIS was prepared to satisfy
the requirements of the National
Environmental Policy Act. Its purpose is
to inform the Commission, the public,
and other permitting agencies about the
potential adverse and beneficial
environmental impacts associated with
the proposed Piceance Basin Expansion
Project (Piceance Project) and its
alternatives, and to recommend
practical, reasonable, and appropriate
mitigation measures which would avoid
or reduce any significant adverse
impacts to the maximum extent
practicable and, where feasible, to less
than significant levels. The final EIS
concludes that the proposed project,
with appropriate mitigating measures as
recommended, would have limited
adverse environmental impact.
The Piceance Project involves the
construction and operation of a new
interstate natural gas pipeline system
that would extend between the existing
Colorado Interstate Gas Company (CIG)
Greasewood Compressor Station in Rio
Blanco County, Colorado, and the
existing CIG Wamsutter Compressor
Station in Sweetwater County,
Wyoming.1 The final EIS assesses the
potential environmental effects of the
construction and operation of the
following facilities in Colorado and
Wyoming:
• About 141.8 miles of 24-inchdiameter new pipeline with 89.9 miles
located in Colorado (Rio Blanco and
1 Both WIC and CIG are affiliates owned by El
Paso Corporation.
E:\FR\FM\19AUN1.SGM
19AUN1
Agencies
[Federal Register Volume 70, Number 160 (Friday, August 19, 2005)]
[Notices]
[Page 48697]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-4521]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12063-001 Idaho]
Little Wood River Ranch II William Arkoosh; Notice of
Availability of Final Environmental Assessment
August 12, 2005.
In accordance with the National Environmental Policy Act of 1969
and the Federal Energy Regulatory Commission's (Commission)
regulations, 18 CFR part 380 (Order No. 486, 52 F.R. 47897), the Office
of Energy Projects has reviewed the application and prepared the
enclosed Environmental Assessment (EA) for an original license for
William Arkoosh's Little Wood River Ranch II Hydroelectric Project. The
proposed project would be located on the Little Wood River, 6 miles
west of the town of Shoshone, Lincoln County, Idaho. The proposed
project would be located entirely on private lands owned by William
Arkoosh. The EA contains the staff's analysis of the potential
environmental impacts of the proposed project and concludes that
licensing the project, with appropriate environmental protective
measures, would not constitute a major federal action that would
significantly affect the quality of the human environment.
A copy of the EA is available for review at the Commission in the
Public Reference Room or may be viewed on the Commission's Web site at
https://www.ferc.gov using the ``eLibrary'' link. Enter the docket
number excluding the last three digits in the docket number field to
access the document. For assistance, call 1-866-208-3676 or for TTY,
(202) 502-8659.
For further information, contact Gaylord Hoisington at (202)
502-6032.
Magalie R. Salas,
Secretary.
[FR Doc. E5-4521 Filed 8-18-05; 8:45 am]