BJ Energy LLC; Notice of Issuance of Order, 48382 [E5-4469]
Download as PDF
48382
Federal Register / Vol. 70, No. 158 / Wednesday, August 17, 2005 / Notices
o. Procedural schedule and final
amendments: At this time we do not
anticipate the need for preparing a draft
environmental assessment (EA).
Recipients will have 60 days to provide
the Commission with any written
comments on the EA. All comments
filed with the Commission will be
considered in the Order taking final
action on the license applications.
However, should substantive comments
requiring re-analysis be received on the
EA document, we would consider
preparing a subsequent EA document.
The application will be processed
according to the following Hydro
Licensing Schedule. Revisions to the
schedule will be made as appropriate.
Issue Acceptance letter or Deficiency
Letter and request Additional
Information, if needed—September
2005.
Notice soliciting final terms and
conditions—December 2005.
Notice of the Availability of the EA—
July 2006.
Ready for Commission’s decision on the
application—November 2006.
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5–4471 Filed 8–16–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. ER05–1097–000, ER05–1097–
001]
BJ Energy LLC; Notice of Issuance of
Order
August 11, 2005.
BJ Energy LLC (BJ Energy) filed an
application for market-based rate
authority, with an accompanying rate
tariff. The proposed rate tariff provides
for the sales of capacity, energy and
ancillary services at market-based rates.
BJ Energy also requested waiver of
various Commission regulations. In
particular, BJ Energy requested that the
Commission grant blanket approval
under 18 CFR part 34 of all future
issuances of securities and assumptions
of liability by BJ Energy.
On August 11, 2005, pursuant to
delegated authority, the Director,
Division of Tariffs and Market
Development—South, granted the
request for blanket approval under part
VerDate jul<14>2003
13:34 Aug 16, 2005
Jkt 205001
34. The Director’s order also stated that
the Commission would publish a
separate notice in the Federal Register
establishing a period of time for the
filing of protests. Accordingly, any
person desiring to be heard or to protest
the blanket approval of issuances of
securities or assumptions of liability by
BJ Energy should file a motion to
intervene or protest with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure. 18 CFR 385.211, 385.214
(2004).
Notice is hereby given that the
deadline for filing motions to intervene
or protest is September 12, 2005.
Absent a request to be heard in
opposition by the deadline above, BJ
Energy is authorized to issue securities
and assume obligations or liabilities as
a guarantor, indorser, surety, or
otherwise in respect of any security of
another person; provided that such
issuance or assumption is for some
lawful object within the corporate
purposes of BJ Energy, compatible with
the public interest, and is reasonably
necessary or appropriate for such
purposes.
The Commission reserves the right to
require a further showing that neither
public nor private interests will be
adversely affected by continued
approval of BJ Energy’s issuances of
securities or assumptions of liability.
Copies of the full text of the Director’s
Order are available from the
Commission’s Public Reference Room,
888 First Street, NE., Washington, DC
20426. The Order may also be viewed
on the Commission’s Web site at
https://www.ferc.gov, using the eLibrary
link. Enter the docket number excluding
the last three digits in the docket
number filed to access the document.
Comments, protests, and interventions
may be filed electronically via the
Internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. The Commission
strongly encourages electronic filings.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5–4469 Filed 8–16–05; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00014
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. PR05–18–000]
Bridgeline Gas Distribution LLC;
Notice of Cost and Revenue Study
August 11, 2005.
Take notice that on August 3, 2005,
Bridgeline Gas Distribution LLC
(Bridgeline) tendered for filing a cost
and revenue study for the 12-month
period ended March 31, 2005, in
compliance with the Commission Order,
issued September 23, 2003, in Docket
No. PR02–14–001.
Bridgeline states that copies of the
filing were served on parties on the
official service list in the abovecaptioned proceeding.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
date as indicated below. Anyone filing
an intervention or protest must serve a
copy of that document on the Applicant.
Anyone filing an intervention or protest
on or before the intervention or protest
date need not serve motions to intervene
or protests on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
E:\FR\FM\17AUN1.SGM
17AUN1
Agencies
[Federal Register Volume 70, Number 158 (Wednesday, August 17, 2005)]
[Notices]
[Page 48382]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-4469]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. ER05-1097-000, ER05-1097-001]
BJ Energy LLC; Notice of Issuance of Order
August 11, 2005.
BJ Energy LLC (BJ Energy) filed an application for market-based
rate authority, with an accompanying rate tariff. The proposed rate
tariff provides for the sales of capacity, energy and ancillary
services at market-based rates. BJ Energy also requested waiver of
various Commission regulations. In particular, BJ Energy requested that
the Commission grant blanket approval under 18 CFR part 34 of all
future issuances of securities and assumptions of liability by BJ
Energy.
On August 11, 2005, pursuant to delegated authority, the Director,
Division of Tariffs and Market Development--South, granted the request
for blanket approval under part 34. The Director's order also stated
that the Commission would publish a separate notice in the Federal
Register establishing a period of time for the filing of protests.
Accordingly, any person desiring to be heard or to protest the blanket
approval of issuances of securities or assumptions of liability by BJ
Energy should file a motion to intervene or protest with the Federal
Energy Regulatory Commission, 888 First Street, NE., Washington, DC
20426, in accordance with Rules 211 and 214 of the Commission's Rules
of Practice and Procedure. 18 CFR 385.211, 385.214 (2004).
Notice is hereby given that the deadline for filing motions to
intervene or protest is September 12, 2005.
Absent a request to be heard in opposition by the deadline above,
BJ Energy is authorized to issue securities and assume obligations or
liabilities as a guarantor, indorser, surety, or otherwise in respect
of any security of another person; provided that such issuance or
assumption is for some lawful object within the corporate purposes of
BJ Energy, compatible with the public interest, and is reasonably
necessary or appropriate for such purposes.
The Commission reserves the right to require a further showing that
neither public nor private interests will be adversely affected by
continued approval of BJ Energy's issuances of securities or
assumptions of liability.
Copies of the full text of the Director's Order are available from
the Commission's Public Reference Room, 888 First Street, NE.,
Washington, DC 20426. The Order may also be viewed on the Commission's
Web site at https://www.ferc.gov, using the eLibrary link. Enter the
docket number excluding the last three digits in the docket number
filed to access the document. Comments, protests, and interventions may
be filed electronically via the Internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
under the ``e-Filing'' link. The Commission strongly encourages
electronic filings.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5-4469 Filed 8-16-05; 8:45 am]
BILLING CODE 6717-01-P