Pipeline Safety: Petition for Waiver; BOC Gases, 46570-46571 [05-15757]
Download as PDF
46570
Federal Register / Vol. 70, No. 153 / Wednesday, August 10, 2005 / Notices
procedures that can (1) be used to
approximate actual operations during
the commissioning of a new pumping
station or the installation of a new relief
valve, and (2) be used to determine,
during annual tests, whether a relief
valve is functioning properly. (P–02–4)
The recommendation arose from
NTSB’s evaluation of a test Olympic had
done to check the pilot of a pilotoperated pressure relief valve in a
pumping station at its new Bayview
products terminal. NTSB found the test
was inadequate to determine if the pilot
was configured properly or if it was
operating reliably. Furthermore, NTSB
concluded that the DOT regulations
governing the testing of relief valves and
other safety devices on hazardous liquid
pipelines provide insufficient guidance
to ensure that test protocols and
procedures will effectively indicate
malfunctions of pressure relief valves or
their pilot controls.2
According to NTSB’s accident
report 3—available online at https://
www.ntsb.gov/Publictn/P_Acc.htm—
Olympic installed pressure control
devices to protect the Bayview terminal
piping and components from
overpressure by the 16-inch pipeline.
These devices consisted of (1) a control
valve to throttle back the inflow of
product; (2) a downstream pilotoperated pressure relief valve designed
to divert excess product if a set pressure
was exceeded; and (3) upstream
remotely controlled block valves that
would stop the inflow if a pressure of
700 psig was reached inside the
terminal.
The report explains that the pilot of
the relief valve had been configured for
low-pressure operation, with a set point
of 100 psig. Consequently, during startup of the Bayview terminal, the relief
valve opened at a pressure lower than
intended. To correct the problem,
Olympic replaced the pilot spring (with
an identical spring) and increased the
set point to 700 psig. (Olympic did not
consult the valve manufacturer’s
specifications and was unaware that a
different piston, cover, and O-ring were
necessary for high-pressure
2 Under 49 CFR 195.262(c), the safety devices in
each new pumping station must be tested under
conditions approximating actual operations and
found to function properly before the pumping
station may be used. Also, under 49 CFR 195.428,
each pressure limiting device, relief valve, pressure
regulator, or other item of pressure control
equipment must be inspected and tested annually
to determine that it is functioning properly, is in
good mechanical condition, and is adequate from
the standpoint of capacity and reliability of
operation for the service in which it is used.
3 Pipeline Rupture and Subsequent Fire in
Bellingham, Washington, June 10, 1999, Pipeline
Accident Report NTSB/PAR–02/02, October 11,
2002.
VerDate jul<14>2003
15:02 Aug 09, 2005
Jkt 205001
configuration.) The pilot was then tested
in situ with a hydraulic pump rig to be
sure the pilot valve opened at the
correct pressure. Olympic used the same
test procedure it used to test relief
valves under DOT’s regulations.
The accident investigation disclosed
that increasing the set pressure of the
pilot had compressed the pilot spring so
much that rising inlet pressure could
not lift the piston, making operation of
the pilot completely unreliable.
Although the pilot set point apparently
had been tested, the test procedure did
not reveal that the pilot had been
configured for low-pressure operation
and thus would not consistently open at
the intended pressure. NTSB observed
that if the relief valve did not open
because of pilot malfunction and
downstream pressure rose above 700
psig, a block valve would close and
increase pressure in the 16-inch
pipeline, which is what happened in the
accident.
Advisory Bulletin (ADB–05–05)
OPS shares NTSB’s concern that
pipeline operators could be conducting
in-service tests that do not identify
unreliable pilot-operated pressure relief
valves. Therefore, we are issuing the
following advisory bulletin:
To: Operators of hazardous liquid
pipelines regulated by 49 CFR part 195.
Subject: Inspecting and testing pilotoperated pressure relief valves.
Purpose: To assure that pilot-operated
pressure relief valves function properly.
Advisory: Operators should review
their in-service inspection and test
procedures used on new, replaced, or
relocated pilot-operated pressure relief
valves and during the periodic
inspection and testing of these valves.
Operators can use the guidance stated
below to ensure the procedures
approximate actual operations and are
adequate to determine if the valves
functions properly.
Guidance: The procedures should
provide for the following:
(a) During installation, review the
valve purchase order (or comparable
documentation), valve name-plate, and
manufacturer’s specifications. Verify
that the valve is:
(1) Compatible with the material and
maximum operating pressure of the
pipeline;
(2) Compatible with or protected from
environmental attack or damage;
(3) Compatible with the hazardous
liquid transported at all anticipated
operating temperatures and pressures;
(4) In conformity with the
manufacturer’s specifications for the
valve model and type of service, and
PO 00000
Frm 00100
Fmt 4703
Sfmt 4703
with the purchase order (or comparable
documentation);
(5) Configured according to the
manufacturer’s specifications for the
pilot and in-line valves; and
(6) Operable at the set pressure (i.e.,
activation of the pilot valve opens the
in-line valve).
(b) If the pilot assembly of a
previously installed valve is
reconfigured or repaired ‘‘
(1) Do the work according to the
manufacturer’s specifications;
(2) Test the valve to ensure it is
operable at the set pressure (i.e.,
activation of the pilot valve opens the
in-line valve) or, if testing the in-line
valve would be unsafe or
environmentally hazardous, tests the
pilot valve according to paragraph (d)
below; and
(3) Document the work.
(c) Verify that the valve set pressure
is consistent with ‘‘
(1) The design or configuration of the
pilot valve and in-line valve; and
(2) Use of the valve as a primary
overpressure protection device or as a
backup safety relief device.
(d) Test the pilot valve at least twice
and verify that it activates consistently
at the intended set pressure.
(e) During periodic inspections and
tests, review the valve installation to
determine if it has been modified since
the last inspection. If so, verify that the
pilot sensor and valve inlet and
discharge piping are properly sized and
placed and that the installation is
consistent with the intended design.
(f) Document all verifications, and
sign, date, and keep for the operating
life of the valve all documentation.
Issued in Washington, DC, on August 4,
2005.
Stacey Gerard,
Associate Administrator for Pipeline Safety.
[FR Doc. 05–15758 Filed 8–9–05; 8:45 am]
BILLING CODE 4910–60–P
DEPARTMENT OF TRANSPORTATION
Pipeline and Hazardous Materials
Safety Administration
[Docket No. PHMSA–05–21314; Notice 1]
Pipeline Safety: Petition for Waiver;
BOC Gases
Office of Pipeline Safety (OPS),
Pipeline and Hazardous Materials Safety
Administration (PHMSA), U.S.
Department of Transportation (DOT).
ACTION: Notice; Petition for Waiver;
Correction.
AGENCY:
SUMMARY: PHMSA is correcting a
petition for waiver published in the
E:\FR\FM\10AUN1.SGM
10AUN1
Federal Register / Vol. 70, No. 153 / Wednesday, August 10, 2005 / Notices
Federal Register on July 14, 2005 (70 FR
40780). That petition, from BOC Gases
(BOC), requested a waiver from the
pipeline safety standards at 49 CFR
195.306(c)(5) to allow the use of inert
gas or carbon dioxide as the test
medium for pressure testing an existing
carbon dioxide pipeline. This notice
corrects the supplementary information
of that publication, which referred to a
gas pipeline safety regulation when it
should have referred to a hazardous
liquid pipeline safety regulation.
FOR FURTHER INFORMATION CONTACT:
James Reynolds by phone at 202–366–
2786, by fax at 202–366–4566, by mail
at DOT, PHMSA Office of Pipeline
Safety, 400 7th Street, SW., Washington,
DC 20590, or by e-mail at
james.reynolds@.dot.gov.
Correction
In the Federal Register of July 14,
2005, in FR Doc. 05–13864, on page
40781, in the first column, correct the
first paragraph of the SUPPLEMENTARY
INFORMATION caption to read:
SUPPLEMENTARY INFORMATION: The
hazardous liquid pipeline safety
regulation at 49 CFR 195.306(c)(5)
allows an operator of a carbon dioxide
pipeline to use inert gas or carbon
dioxide as the test medium if the pipe
involved is new pipe having a
longitudinal joint factor of 1.00.
Issued in Washington, DC on August 1,
2005.
Joy Kadnar,
Director of Engineering and Emergency
Support.
[FR Doc. 05–15757 Filed 8–9–05; 8:45 am]
BILLING CODE 4910–60–P
DEPARTMENT OF TRANSPORTATION
Surface Transportation Board
[STB Docket No. AB–6 (Sub–No. 429X) and
AB–882 (Sub–No. 1X)]
BNSF Railway Company—
Abandonment Exemption—in Ramsey
County, MN; Minnesota Commercial
Railway Company—Discontinuance of
Service Exemption—in Ramsey
County, MN
BNSF Railway Company (BNSF) and
Minnesota Commercial Railway
Company (MNNR) (collectively,
applicants) have jointly filed a notice of
exemption under 49 CFR 1152 subpart
F—Exempt Abandonments and
Discontinuances of Service for BNSF to
abandon, and MNNR to discontinue
service over, a 0.67-mile line of railroad
between milepost 7.19, a point
approximately 100 feet north of
VerDate jul<14>2003
15:02 Aug 09, 2005
Jkt 205001
Interstate Highway I–694 in White Bear
Township, and milepost 6.52, a point
approximately 50 feet north of Beam
Avenue in Maplewood, in Ramsey
County, MN.1
BNSF and MNNR have certified that:
(1) No traffic has moved over the line for
at least 2 years; (2) any overhead traffic
on the line can be rerouted over other
lines; (3) no formal complaint filed by
a user of rail service on the line (or by
a state or local government entity acting
on behalf of such user) regarding
cessation of service over the line either
is pending with the Surface
Transportation Board or with any U.S.
District Court or has been decided in
favor of complainant within the 2-year
period; and (4) the requirements at 49
CFR 1105.7 (environmental reports), 49
CFR 1105.8 (historic reports), 49 CFR
1105.11 (transmittal letter), 49 CFR
1105.12 (newspaper publication), and
49 CFR 1152.50(d)(1) (notice to
governmental agencies) have been met.
As a condition to this exemption, any
employee adversely affected by the
abandonment or discontinuance shall be
protected under Oregon Short Line R.
Co.—Abandonment—Goshen, 360 I.C.C.
91 (1979). To address whether this
condition adequately protects affected
employees, a petition for partial
revocation under 49 U.S.C. 10502(d)
must be filed.
Provided no formal expression of
intent to file an offer of financial
assistance (OFA) has been received, this
exemption will be effective on
September 9, 2005,2 unless stayed
pending reconsideration. Petitions to
stay that do not involve environmental
issues,3 formal expressions of intent to
file an OFA under 49 CFR
1152.27(c)(2),4 and trail use/rail banking
1 By memorandum to the Board’s Section of
Environmental Analysis (SEA) dated June 24, 2005,
MNNR amended its environmental and historic
report in the above proceedings to reflect the correct
location of the rail line and right-of-way. According
to MNNR, the rail line is located in the City of
Maplewood, MN, and in White Bear Township, not
White Bear Lake, MN, and the outer portions of the
right-of-way may be located in the municipalities of
Vadnais Heights, MN, and White Bear Lake.
2 In their notice filed on July 21, 2005, applicants
proposed a consummation date of August 30, 2005.
In a letter filed on July 28, 2005, applicants indicate
that the correct consummation date is September 9,
2005, which is the earliest the exemption could
become effective under 49 CFR 1152.50(d)(2).
3 The Board will grant a stay if an informed
decision on environmental issues (whether raised
by a party or by SEA in its independent
investigation) cannot be made before the
exemption’s effective date. See Exemption of Outof-Service Rail Lines, 5 I.C.C.2d 377 (1989). Any
request for a stay should be filed as soon as possible
so that the Board may take appropriate action before
the exemption’s effective date.
4 Each OFA must be accompanied by the filing
fee, which currently is set at $1,200. See 49 CFR
1002.2(f)(25).
PO 00000
Frm 00101
Fmt 4703
Sfmt 4703
46571
requests under 49 CFR 1152.29 must be
filed by August 19, 2005. Petitions to
reopen or requests for public use
conditions under 49 CFR 1152.28 must
be filed by August 30, 2005, with the:
Surface Transportation Board, 1925 K
Street, NW., Washington, DC 20423–
0001.
A copy of any petition filed with the
Board should be sent to applicants’
representatives: for BNSF, Sidney L.
Strickland, Jr., Sidney L. Strickland and
Associates, PLLC, 3050 K Street, NW.,
Suite 101, Washington, DC 20007–5108;
for MNNR, Thomas F. McFarland,
Thomas F. McFarland, P.C., 208 South
LaSalle Street, Suite 1890, Chicago, IL
60604–1112.
If the verified notice contains false or
misleading information, the exemption
is void ab initio.
Applicants have filed environmental
and historic reports which address the
effects, if any, of the abandonment and
discontinuance on the environment and
historic resources. SEA will issue an
environmental assessment (EA) by
August 15, 2005. Interested persons may
obtain a copy of the EA by writing to
SEA (Room 500, Surface Transportation
Board, Washington, DC 20423–0001) or
by calling SEA, at (202) 565–1539.
(Assistance for the hearing impaired is
available through the Federal
Information Relay Service (FIRS) at 1–
800–877–8339.) Comments on
environmental and historic preservation
matters must be filed within 15 days
after the EA becomes available to the
public.
Environmental, historic preservation,
public use, or trail use/rail banking
conditions will be imposed, where
appropriate, in a subsequent decision.
Pursuant to the provisions of 49 CFR
1152.29(e)(2), BNSF shall file a notice of
consummation with the Board to signify
that it has exercised the authority
granted and fully abandoned the line. If
consummation has not been effected by
BNSF’s filing of a notice of
consummation by August 10, 2006, and
there are no legal or regulatory barriers
to consummation, the authority to
abandon will automatically expire.
Board decisions and notices are
available on our Web site at https://
www.stb.dot.gov.
Decided: August 3, 2005.
By the Board, David M. Konschnik,
Director, Office of Proceedings.
Vernon A. Williams,
Secretary.
[FR Doc. 05–15761 Filed 8–9–05; 8:45 am]
BILLING CODE 4915–01–P
E:\FR\FM\10AUN1.SGM
10AUN1
Agencies
[Federal Register Volume 70, Number 153 (Wednesday, August 10, 2005)]
[Notices]
[Pages 46570-46571]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 05-15757]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Pipeline and Hazardous Materials Safety Administration
[Docket No. PHMSA-05-21314; Notice 1]
Pipeline Safety: Petition for Waiver; BOC Gases
AGENCY: Office of Pipeline Safety (OPS), Pipeline and Hazardous
Materials Safety Administration (PHMSA), U.S. Department of
Transportation (DOT).
ACTION: Notice; Petition for Waiver; Correction.
-----------------------------------------------------------------------
SUMMARY: PHMSA is correcting a petition for waiver published in the
[[Page 46571]]
Federal Register on July 14, 2005 (70 FR 40780). That petition, from
BOC Gases (BOC), requested a waiver from the pipeline safety standards
at 49 CFR 195.306(c)(5) to allow the use of inert gas or carbon dioxide
as the test medium for pressure testing an existing carbon dioxide
pipeline. This notice corrects the supplementary information of that
publication, which referred to a gas pipeline safety regulation when it
should have referred to a hazardous liquid pipeline safety regulation.
FOR FURTHER INFORMATION CONTACT: James Reynolds by phone at 202-366-
2786, by fax at 202-366-4566, by mail at DOT, PHMSA Office of Pipeline
Safety, 400 7th Street, SW., Washington, DC 20590, or by e-mail at
james.reynolds@.dot.gov.
Correction
In the Federal Register of July 14, 2005, in FR Doc. 05-13864, on
page 40781, in the first column, correct the first paragraph of the
SUPPLEMENTARY INFORMATION caption to read:
SUPPLEMENTARY INFORMATION: The hazardous liquid pipeline safety
regulation at 49 CFR 195.306(c)(5) allows an operator of a carbon
dioxide pipeline to use inert gas or carbon dioxide as the test medium
if the pipe involved is new pipe having a longitudinal joint factor of
1.00.
Issued in Washington, DC on August 1, 2005.
Joy Kadnar,
Director of Engineering and Emergency Support.
[FR Doc. 05-15757 Filed 8-9-05; 8:45 am]
BILLING CODE 4910-60-P