Pacific Gas and Electric; Notice of Application Tendered for Filing With the Commission, Soliciting Additional Study Requests, and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 45386-45387 [E5-4199]
Download as PDF
45386
Federal Register / Vol. 70, No. 150 / Friday, August 5, 2005 / Notices
Reservoir; (2) Slab Creek Penstock—A
40-foot-long, 24-inch diameter steel
penstock that passes through the dam
and connects Slab Creek Reservoir with
Slab Creek Powerhouse; (3) Slab Creek
Powerhouse—The powerhouse, which
is located at the base of Slab Creek Dam
and utilizes minimum stream flow
releases, has one turbine with a rated
capacity at best gate opening of 450 kW,
and one generator rated at 485 kW, with
a total powerhouse maximum capability
of 400 kW; (4) White Rock Tunnel—an
approximately 20- to 24-foot-diameter
modified horseshoe tunnel 4.9-milelong and has a surge shaft that connects
Slab Creek Reservoir with White Rock
Penstock; (5) White Rock Penstock—A 9
to 15-foot-diameter, 0.3-mile-long
aboveground steel penstock that
connects White Rock Tunnel to White
Rock Powerhouse; (6) White Rock
Powerhouse—The powerhouse is
equipped with two turbines, one rated
at 112,976 kW and the other at 120,000
kW at best gate opening, and two
generators, rated at 109,250 kW and
133,000 kW, with total powerhouse
maximum capability of 224,000 kW; and
(7) Transmission Lines—There are two
230 kV overhead transmission lines and
one 12 kV distribution line. The two
transmission lines, both 21.8 miles in
length, connect the White Rock
switchyard to SMUD’s Folsom Junction.
The 600-foot-long 12 kV Slab Creek tap
line connects the Slab Creek
Powerhouse to the junction with Pacific
Gas and Electric Company’s 12-kV
distribution line.
SMUD’s Proposed Action includes the
addition of the Iowa Hill Development.
The development would be composed
of the following features: (1) Iowa Hill
Reservoir—A new off-stream, rock filled
earthen dike of varying height
depending on natural terrain (maximum
height 280 feet) and 5,900 feet in
circumference with a geotextile liner on
the reservoir floor and inside surface of
the dike; (2) Iowa Hill Tunnel—A new
underground water conduit extending
from Iowa Hill Reservoir and connecting
to Slab Creek Reservoir, and comprised
of: a 1,120-foot-long, 19.02-footdiameter, concrete-lined vertical shaft; a
1,110-foot-long, 19.02-foot-diameter
concrete-lined high pressure tunnel; a
250-foot-long, 15.74-foot-diameter, steellined high pressure tunnel; a 150-footlong, 12.45-foot-diameter, steel
manifold; three 180-foot-long, 7.87-footdiameter, steel penstocks; three 450foot-long, 12.46-foot-diameter draft tube
extensions; a 150-foot-long, 17.22-footdiameter steel manifold; and a 1,230foot-long, 20.93-foot-diameter, concretelined low pressure tunnel; (3) Iowa Hill
VerDate jul<14>2003
15:34 Aug 04, 2005
Jkt 205001
Powerhouse—A new underground
powerhouse along the Iowa Hill Tunnel
that would include three variable speed
turbines each with a nominal rating of
133 MW, and a three generators each
rated at 170 MW as a pump motor. The
powerhouse would have a maximum
capability of 400 MW; (4) Iowa Hill
Switchyard—A new Iowa Hill
Switchyard; and (5) Transmission
Line—A new 230 kV transmission line
that would connect the Iowa Hill
Switchyard to the existing CaminoWhite Rock Transmission Line. SMUD
anticipates that from the time a new
project license is issued by FERC and
accepted by SMUD, seven years would
be required to complete the engineering,
procurement, and construction of the
Iowa Hill Development.
In addition, as part of the License
Application, SMUD proposes to exclude
from the project description and FERC
Project Boundary certain transmission
line sections included in the current
license and FERC Project Boundary. The
excluded sections are: (1) A 9.3-mile
long section of 230 kV line from Folsom
Junction to Orangevale Substation; (2) a
17.8-mile long section of 230 kV line
from Folsom Junction to Hedge
Substation; and (3) a 1.9-mile long
section of 230 kV line from Folsom
Junction to Lake Substation.
n. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site
at: https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits
in the docket number field (P–2101), to
access the document. For assistance,
contact FERC Online Support at
FERCOnlineSupport@ferc.gov, or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h above. You may also
register online at: https://www.ferc.gov/
esubscribenow.htm to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
o. With this notice, we are initiating
consultation with the California State
Historic Preservation Officer (SHPO), as
required by section 106, National
Historic Preservation Act, and the
regulations of the Advisory Council on
Historic Preservation, 36 CFR 800.4.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
Hydro Licensing Schedule. Revisions to
the schedule will be made if the
Commission determines it necessary to
do so:
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
Milestone
Issue Acceptance/Deficiency
Letter and request Additional Information, if needed.
Notice asking for final terms
and conditions.
Notice of the availability of
the draft EIS.
Notice of the availability of
the final EIS.
Ready for Commission’s decision on the application.
Tentative date
November
2005.
April 2006.
December
2006.
June 2007.
August 2007.
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice soliciting final terms
and conditions.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5–4198 Filed 8–4–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2155]
Pacific Gas and Electric; Notice of
Application Tendered for Filing With
the Commission, Soliciting Additional
Study Requests, and Establishing
Procedural Schedule for Relicensing
and a Deadline for Submission of Final
Amendments
July 28, 2005.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New major
license.
b. Project No.: 2155.
c. Date Filed: July 15, 2005.
d. Applicant: Pacific Gas and Electric
Company.
e. Name of Project: Chili Bar Project.
f. Location: On the South Fork
American River in El Dorado, near
Placerville, California. The project
affects 48 acres of Federal land
administered by the Bureau of Land
Management.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Randal S.
Livingston, Power Generation Senior
Director, Pacific Gas and Electric
Company, P.O. Box 770000, Mail Code:
N11E, San Francisco, CA 94177.
i. FERC Contact: Jim Fargo, (202) 502–
6095 or James.Fargo@ferc.gov.
j. Cooperating Agencies: We are
asking Federal, state, local, and tribal
E:\FR\FM\05AUN1.SGM
05AUN1
Federal Register / Vol. 70, No. 150 / Friday, August 5, 2005 / Notices
agencies with jurisdiction and/or
special expertise with respect to
environmental issues to cooperate with
us in the preparation of the
environmental document. Agencies who
would like to request cooperating status
should follow the instructions for filing
comments described in item l below.
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for Filing Additional
Study Requests and Requests for
Cooperating Agency Status: September
15, 2005.
All Documents (Original and Eight
Copies) Should be Filed With: Magalie
R. Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
Additional study requests and
requests for cooperating agency status
may be filed electronically via the
Internet in lieu of paper. The
Commission strongly encourages
electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov) under the ‘‘e-Filing’’ link.
m. This application is not ready for
environmental analysis at this time.
n. The existing Chili Bar Project
consists of: (1) A 120-foot-high concrete
gravity dam; (2) a 110-acre reservoir
with a useable storage of 1,339 acre-feet;
(3) a powerhouse with one 7-MW unit
and (4) appurtenant facilities. The
applicant estimates that the total
average annual generation would be
33,500 megawatt hours. All generated
power is utilized within the applicant’s
electric utility system.
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
VerDate jul<14>2003
15:34 Aug 04, 2005
Jkt 205001
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at http:/
/www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. With this notice, we are initiating
consultation with the California State
Historic Preservation Officer (SHPO), as
required by (106, National Historic
Preservation Act, and the regulations of
the Advisory Council on Historic
Preservation, 36 CFR 800.4.
q. Procedural Schedule and Final
Amendments: The application will be
processed according to the following
Hydro Licensing Schedule. Revisions to
the schedule will be made as
appropriate.
Issue Acceptance/Deficiency Letter and
request additional information, if needed,
November 2005.
Issue Scoping Document for comments,
December 2005.
Notice of application is ready for
environmental analysis, April 2006.
Notice of the availability of the draft EIS,
December 2006.
Notice of the availability of the final FEIS,
June 2007.
Ready for Commission’s decision on the
application, August 2007.
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5–4199 Filed 8–4–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2170–029–AK]
Chugach Electric Association; Notice
of Scoping Meetings and Site Visit and
Soliciting Scoping Comments
July 28, 2005.
Take notice that the following
hydroelectric application has been filed
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
45387
with Commission and is available for
public inspection:
a. Type of Application: New major
license.
b. Project No: 2170–029.
c. Date filed: April 22, 2005.
d. Applicant: Chugach Electric
Association.
e. Name of Project: Cooper Lake
Hydroelectric Project.
f. Location: On Cooper Lake,
approximately 4.8 river miles from the
mouth of Cooper Creek in south central
Alaska on the Kenai Peninsula, 55 air
miles south of Anchorage.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Burke Wick,
Chugach Electric Association, 5601
Minnesota Drive, Anchorage, Alaska
99519. (907) 762–4779.
i. FERC Contact: David Turner (202)
502–6091 or david.turner@ferc.gov.
j. Deadline for filing scoping
comments: October 10, 2005.
All documents (original and eight
copies) should be filed with: Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
Scoping comments may be filed
electronically via the Internet in lieu of
paper. The Commission strongly
encourages electronic filings. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov) under the ‘‘eFiling’’ link.
k. This application is not ready for
environmental analysis at this time.
l. The existing project consists of: (1)
The Cooper Lake Dam, a 52-foot-high
earth-and-rockfilled structure; (2) the
2,910-acre, 5-mile-long Cooper Lake
Reservoir; (3) two vertical-shaft Francis
turbines with a total capacity of 19.38
megawatts; (4) an intake structure
located on Cooper Lake; (5) a tunnel and
penstock extending 10,686 feet east
from the intake to the powerhouse; (6)
a 6.3-mile-long, 69-kV transmission line
from the powerhouse to Quartz Creek
Substation; and 90.4-mile-long, 115-kV
transmission line from the Quartz Creek
Substation to Anchorage.
m. A copy of the application is
available for review at the Commission
E:\FR\FM\05AUN1.SGM
05AUN1
Agencies
[Federal Register Volume 70, Number 150 (Friday, August 5, 2005)]
[Notices]
[Pages 45386-45387]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-4199]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2155]
Pacific Gas and Electric; Notice of Application Tendered for
Filing With the Commission, Soliciting Additional Study Requests, and
Establishing Procedural Schedule for Relicensing and a Deadline for
Submission of Final Amendments
July 28, 2005.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New major license.
b. Project No.: 2155.
c. Date Filed: July 15, 2005.
d. Applicant: Pacific Gas and Electric Company.
e. Name of Project: Chili Bar Project.
f. Location: On the South Fork American River in El Dorado, near
Placerville, California. The project affects 48 acres of Federal land
administered by the Bureau of Land Management.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Randal S. Livingston, Power Generation Senior
Director, Pacific Gas and Electric Company, P.O. Box 770000, Mail Code:
N11E, San Francisco, CA 94177.
i. FERC Contact: Jim Fargo, (202) 502-6095 or James.Fargo@ferc.gov.
j. Cooperating Agencies: We are asking Federal, state, local, and
tribal
[[Page 45387]]
agencies with jurisdiction and/or special expertise with respect to
environmental issues to cooperate with us in the preparation of the
environmental document. Agencies who would like to request cooperating
status should follow the instructions for filing comments described in
item l below.
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for Filing Additional Study Requests and Requests for
Cooperating Agency Status: September 15, 2005.
All Documents (Original and Eight Copies) Should be Filed With:
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
Additional study requests and requests for cooperating agency
status may be filed electronically via the Internet in lieu of paper.
The Commission strongly encourages electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
(https://www.ferc.gov) under the ``e-Filing'' link.
m. This application is not ready for environmental analysis at this
time.
n. The existing Chili Bar Project consists of: (1) A 120-foot-high
concrete gravity dam; (2) a 110-acre reservoir with a useable storage
of 1,339 acre-feet; (3) a powerhouse with one 7-MW unit and (4)
appurtenant facilities. The applicant estimates that the total average
annual generation would be 33,500 megawatt hours. All generated power
is utilized within the applicant's electric utility system.
o. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1-
866-208-3676, or for TTY, (202) 502-8659. A copy is also available for
inspection and reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
p. With this notice, we are initiating consultation with the
California State Historic Preservation Officer (SHPO), as required by
(106, National Historic Preservation Act, and the regulations of the
Advisory Council on Historic Preservation, 36 CFR 800.4.
q. Procedural Schedule and Final Amendments: The application will
be processed according to the following Hydro Licensing Schedule.
Revisions to the schedule will be made as appropriate.
Issue Acceptance/Deficiency Letter and request additional
information, if needed, November 2005.
Issue Scoping Document for comments, December 2005.
Notice of application is ready for environmental analysis, April
2006.
Notice of the availability of the draft EIS, December 2006.
Notice of the availability of the final FEIS, June 2007.
Ready for Commission's decision on the application, August 2007.
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5-4199 Filed 8-4-05; 8:45 am]
BILLING CODE 6717-01-P