Revision of Land Management Plan, Dixie and Fishlake National Forests, Located in Southwest Utah., 44884-44885 [05-15424]
Download as PDF
44884
Federal Register / Vol. 70, No. 149 / Thursday, August 4, 2005 / Notices
additional treatments could be done to
maintain satisfactory conditions.
• Reduce fuels to levels consistent
with Forest Plan guidelines on acreage
outside of the Wildland Urban Interface
(WUI).
• Conduct prescribed burning to
reduce hazardous fuels on 24,141
treated acres and 9,149 non-treated
acres.
• Maintain 56 miles of fuelbreaks
(2,140 acres—included in thinning acres
above) by removing all limbs lower than
5 feet and by removing most trees less
than 9″ diameter (except in limited areas
to be managed for trees less than 9″ in
diameter).
• Close or re-close all roads within
the project area except: Hwy 98A, Hwy
67, Forest Roads: 461, two short roads
to J.L. Lookout Tower, roads in Jacob
Lake Campground & Group Area, ADOT
yard access road, 2098, 2284, 2333,
2366, 246, 246E, 246L, 246LA, 246T,
247, 248, 248A to bottom of canyon,
249, 249E, 257, 257G, 260, 264, 264H,
279, 279A, 280, 282, 282A, 282F, 3709,
3726, 3730, 3847, 3878, 3894, 3911,
3917A, 3989, 461, 461B, 461G, 461I,
461N, 462, 482, 482G, 482M, 487, 487A,
579, 579A, 603, 603E, 628, 628C, 634,
636, 639, 800, 800B, 800K, 8116, 9603,
9303M, 9604, 9607N, D155, D202, D261,
D282, D284, D627, D447, D475, D476,
D674, D679, D684, D688, D689, and
D738.
Possible Alternatives
The District considered an alternative
to the proposed action on November 14,
2001. This alternative limits vegetative
manipulation to ponderosa pine trees,
12 inches d.b.h. and less with no hazard
tree removal.
Responsible Official
Michael R. Williams—800 6th Street,
Williams, AZ 86046–2899.
Nature of Decision To Be Made
Given the purpose and need, the
Kaibab National Forest, Forest
Supervisor will review the proposed
action, the other alternatives, and their
impacts to the resources in order to
make the following decisions:
(1) Whether or not the Jacob Ryan
Vegetation Management project will
proceed as proposed in the Proposed
Action.
(2) Whether or not the Jacob Ryan
Vegetation Management project will
proceed as described in one of the
alternatives to the Proposed Action.
(3) Which mitigation measures are
necessary to reduce project effects.
Scoping Process
The proposal was first listed in the
October 2000 Schedule of Proposed
VerDate jul<14>2003
16:23 Aug 03, 2005
Jkt 205001
Actions. In addition, as part of the
public involvement process, the District
initiated discussions with key
stakeholders with the objective of
collaboratively defining old growth
characteristics and identifying potential
treatment activities that could be
‘‘tested’’ within old growth vegetation as
part of the Jacob Ryan Vegetation
Management project in the summer of
1998. After receiving public comments,
we clarified the proposal.
Preliminary Issues
The Forest identified 3 significant
issues during scoping. These issues are:
(1) Managing only 20% of the Plateau
for old growth will result in the lost
opportunity to develop additional old
growth.
(2) The proposed WUI treatment area
is too large, and will remove more trees
than necessary for the protection
needed.
(3) Livestock grazing in the Jacob
Ryan area may affect the ability to reach
the ecosystem goal of meadow
restoration.
Comment Requested
This notice of intent initiates the
Environmental Impact Statement
Process for the Jacob Ryan Vegetation
Management project.
Early Notice of Important of Public
Participation in Subsequent
Environmental Review: A draft
environmental impact statement will be
prepared for comment. The comment
period on the draft environmental
impact statement will be 45 days from
the date the Environmental Protection
Agency publishes the notice of
availability in the Federal Register.
The Forest Service believes, at this
early stage, it is important to give
reviewers notice of several court rulings
related to public participation in the
environmental review process. First,
reviewers of draft environmental impact
statements must structure their
participation in the environmental
review of the proposal so that it is
meaningful and alerts an agency to the
reviewer’s position and contentions.
Vermont Yankee Nuclear Power Corp. v.
NRDC, 435 U.S. 519, 553 (1978). Also,
environmental objections that could be
raised at the draft environmental impact
statement stage but that are not raised
until after completion of the final
environmental impact statement may be
waived or dismissed by the courts. City
of Angoon v. Hodel, 803 F.2d 1016,
1022 (9th Cir. 1986) and Wisconsin
Heritages, Inc. v. Harris, 490 F. Supp.
1334, 1338 (E.D. Wis. 1980). Because of
these court rulings, it is very important
that those interested in this proposed
PO 00000
Frm 00002
Fmt 4703
Sfmt 4703
action participate by the close of the 45day comment period so that substantive
comments and objections are made
available to the Forest Service at a time
when it can meaningfully consider them
and respond to them in the final
environmental impact statement.
To assist the Forest Service in
identifying and considering issues and
concerns on the proposed action,
comments on the draft environmental
impact statement should be as specific
as possible. It is also helpful if
comments refer to specific pages or
chapters of the draft statement.
Comments may also address the
adequacy of the draft environmental
impact statement or the merits of the
alternatives formulated and discussed in
the statement. Reviewers may wish to
refer to the Council on Environmental
Quality Regulations for implementing
the procedural provisions of the
National Environmental Policy Act at 40
CFR 1503.3 in addressing these points.
Comments received, including the
names and addresses of those who
comment, will be considered part of the
public record on this proposal and will
be available for public inspection.
(Authority: 40 CFR 1501.7 and 1508.22;
Forest Service Handbook 1909.15, Section
21)
Dated: July 27, 2005.
Jill Leonard,
District Ranger.
[FR Doc. 05–15400 Filed 8–3–05; 8:45 am]
BILLING CODE 3410–11–M
DEPARTMENT OF AGRICULTURE
Forest Service
Revision of Land Management Plan,
Dixie and Fishlake National Forests,
Located in Southwest Utah.
Forest Service, USDA.
Notice of adjustment to Federal
Register Notice of Vol. 67, No. 90, p.
31178, May 9, 2002, and Vol. 67, No. 91,
p. 31761, May 10, 2002, and transition
to the 2005 Planning Rule at 36 CFR 219
(FR Vol. 70, No. 3./January 5, 2005,
1023).
AGENCY:
ACTION:
SUMMARY: The Dixie and Fishlake
National Forests will exercise their
option to adjust the land management
plan revision process from compliance
with the 1982 planning regulations, to
conform with new planning regulations
adopted in January 2005.
This adjustment will have the
following effects:
1. The new rule redefines forest plans
to be more strategic and flexible to
E:\FR\FM\04AUN1.SGM
04AUN1
44885
Federal Register / Vol. 70, No. 149 / Thursday, August 4, 2005 / Notices
better facilitate adaptive management
and public collaboration.
2. The new rule focuses more on the
goals of ecological, social, and economic
sustainability and less on prescriptive
means of producing goods and services.
3. The Responsible Official who will
approve the final plan will now be the
Forest Supervisor instead of the
Regional Forester.
4. The forests will establish an
environmental management system (per
ISO 14001:2004(E)) prior to completion
of the revised forest plan.
5. The emphasis of public
involvement will be a collaborative
effort between the public and the Forest
Service to incorporate the most
desirable management options into a
single broadly supported management
direction package that will become the
Forest Plan.
6. Administrative review will change
from a post-decision appeals process to
a predecision objection process.
Public Involvement:
There has been a great deal of public
participation and collaborative work on
this planning process over the past few
years, including more than 75 public
meetings. Results of this work and a
preliminary proposed action are
available for review and comment.
Current information and details of
public participation opportunities are
posted on our Web site: https://
www.fs.fed.us/r4/dixie/projects/FParea/
HomePage.htm. Contact Ellen Row at
(435) 896–9233, or email at,
ellenrow@fs.fed.us to be placed on our
mailing list.
ADDRESSES: Mailing address: Dixie and
Fishlake Forest Plan Revision, 115 E 900
North, Richfield UT, 84701.
FOR FURTHER INFORMATION CONTACT:
Frank Fay, Planning Team Leader,
Fishlake National Forest, (435) 896–
9233 or email: ffay@fs.fed.us; or view
our Web site at https://www.fs.fed.us/r4/
dixie/projects/FParea/HomePage.htm.
DATES: Transition is effective
immediately upon publication of this
notice in the Federal Register.
Responsible Officials: Robert A.
Russell, Forest Supervisor, Cedar City,
Dixie National Forest, 1789 N.
Wedgewood Lane, Cedar City UT,
84720. Mary C. Erickson, Forest
Supervisor, Richfield, Fishlake National
Forest, 115 E 900 North, Richfield UT,
84701.
SUPPLEMENTARY INFORMATION: The Dixie
and Fishlake National Forests are
separate administrative units with
separate forest plans. However, due to
similar ecology, interested publics, and
financial resources, the two forest plans
are being revised with a single planning
VerDate jul<14>2003
16:23 Aug 03, 2005
Jkt 205001
team. In May of 2002, the forests
formally initiated a land management
plan revision process with publication
of a notice of intent to prepare an
environmental impact statement for
plan revision. The forests began an
extensive public participation and
collaboration process. The planning
team has been working on
comprehensive analyses of conditions
and trends for the ecological, social and
economic components of the plan area
and related scales of analysis.
The first phase of public participation
was focused primarily on development
of ‘‘vision’’ statements, desired
conditions, management issues, and
suitable land uses to be incorporated
into the preliminary proposed action.
Over sixty community meetings were
conducted in this effort. During the
second phase, the planning team met
with the public to review the content of
the preliminary proposal and to get
feedback as to its desirability and
feasibility. The review and feedback
phase is ongoing. The planning team
will draft a summary of findings from
the analyses of ecological, social, and
economic conditions in the form of a
Comprehensive Evaluation Report.
Many of these analyses have already
been developed with and reviewed by
public participants. We are still
accepting feedback on the preliminary
proposed action and the analyses. We
will use these comments to further
modify the plan proposal. The planning
team will take additional collaborative
steps to finish the draft plan
components and to identify potential
options. Remaining work includes
drafting a summary of condition and
trend analyses, plan components for
formal review and comment, a
monitoring program, and an
environmental management system.
This is an open planning process with
numerous opportunities for the public
to obtain information, provide
comment, or participate in collaborative
stakeholder activities. The focal points
of future collaborative work will be: (1)
Review and adjustment of the
preliminary proposed action (2)
identification and development of
management objectives to assist in
attaining or maintaining desired
conditions, (3) formulation of guidelines
to serve as operational controls to help
ensure projects move toward or
maintain desired conditions, and (4)
development of the plan monitoring
framework and environmental
management system to guide adaptive
management. We expect to complete
this phase of collaboration by early Fall
of 2005. Our remaining forest plan
PO 00000
Frm 00003
Fmt 4703
Sfmt 4703
revision schedule will be approximately
as follows:
Release of Draft Forest Plan and
start of 90-day public comment
period.
Release of Final Plans and start
of 30-day objection period.
Final decision and start of plan
implementation.
Winter
2005–06
Summer
2006
Fall 2006
Please see our website to review
proposed management direction in
progress and other details.
Dated: July 25, 2005.
Robert A. Russell,
Forest Supervisor, Dixie National Forest.
Dated: July 22, 2005.
Mary C. Erickson,
Forest Supervisor, Fishlake National Forest.
[FR Doc. 05–15424 Filed 8–3–05; 8:45 am]
BILLING CODE 3410–ES–M
DEPARTMENT OF AGRICULTURE
Forest Service
Plumas County Resource Advisory
Committee (RAC)
Forest Service, USDA.
Notice of meeting.
AGENCY:
ACTION:
SUMMARY: The Plumas County Resource
Advisory Committee (RAC) will hold a
meeting on August 5, 2005, in Portola,
CA. The primary purpose of the meeting
is to review Plumas National Forest
Supervisor Cycle 5 project funding
decisions, in addition to presentations
on national RAC survey findings and
various recreation topics. RAC project
funding recommendations were made at
a prior meeting on June 8. A short field
trip will follow.
DATES AND ADDRESSES: The August 5,
2005 meeting will take place from 9–12
at the Eastern Plumas Hospital
Education Center, 500 1st Street,
Portola, CA. Additionally, a short field
trip to the Plumas Eureka Estates
thinning project will take place from 1–
2:30, convening at the Beckwourth
Ranger District office at 23 Mohawk
Highway Road, Blairsden, CA.
FOR FURTHER INFORMATION CONTACT: Lee
Anne Schramel Taylor, Forest
Coordinator, USDA, Plumas National
Forest, P.O. Box 11500/159 Lawrence
Street, Quincy, CA 95971; (530) 283–
7850; or by e-mail eataylor@fs.fed.us.
SUPPLEMENTARY INFORMATION: Agenda
items for the August 5 meeting include:
(1) Review Forest Supervisor Cycle 5
funding decisions; (2) Review Corridor
project, discuss, and make a
recommendation, (3) Presentation:
national RAC survey findings, (4)
E:\FR\FM\04AUN1.SGM
04AUN1
Agencies
[Federal Register Volume 70, Number 149 (Thursday, August 4, 2005)]
[Notices]
[Pages 44884-44885]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 05-15424]
-----------------------------------------------------------------------
DEPARTMENT OF AGRICULTURE
Forest Service
Revision of Land Management Plan, Dixie and Fishlake National
Forests, Located in Southwest Utah.
AGENCY: Forest Service, USDA.
ACTION: Notice of adjustment to Federal Register Notice of Vol. 67,
No. 90, p. 31178, May 9, 2002, and Vol. 67, No. 91, p. 31761, May 10,
2002, and transition to the 2005 Planning Rule at 36 CFR 219 (FR Vol.
70, No. 3./January 5, 2005, 1023).
-----------------------------------------------------------------------
SUMMARY: The Dixie and Fishlake National Forests will exercise their
option to adjust the land management plan revision process from
compliance with the 1982 planning regulations, to conform with new
planning regulations adopted in January 2005.
This adjustment will have the following effects:
1. The new rule redefines forest plans to be more strategic and
flexible to
[[Page 44885]]
better facilitate adaptive management and public collaboration.
2. The new rule focuses more on the goals of ecological, social,
and economic sustainability and less on prescriptive means of producing
goods and services.
3. The Responsible Official who will approve the final plan will
now be the Forest Supervisor instead of the Regional Forester.
4. The forests will establish an environmental management system
(per ISO 14001:2004(E)) prior to completion of the revised forest plan.
5. The emphasis of public involvement will be a collaborative
effort between the public and the Forest Service to incorporate the
most desirable management options into a single broadly supported
management direction package that will become the Forest Plan.
6. Administrative review will change from a post-decision appeals
process to a predecision objection process.
Public Involvement:
There has been a great deal of public participation and
collaborative work on this planning process over the past few years,
including more than 75 public meetings. Results of this work and a
preliminary proposed action are available for review and comment.
Current information and details of public participation opportunities
are posted on our Web site: https://www.fs.fed.us/r4/dixie/projects/
FParea/HomePage.htm. Contact Ellen Row at (435) 896-9233, or email at,
ellenrow@fs.fed.us to be placed on our mailing list.
ADDRESSES: Mailing address: Dixie and Fishlake Forest Plan Revision,
115 E 900 North, Richfield UT, 84701.
FOR FURTHER INFORMATION CONTACT: Frank Fay, Planning Team Leader,
Fishlake National Forest, (435) 896-9233 or email: ffay@fs.fed.us; or
view our Web site at https://www.fs.fed.us/r4/dixie/projects/FParea/
HomePage.htm.
DATES: Transition is effective immediately upon publication of this
notice in the Federal Register.
Responsible Officials: Robert A. Russell, Forest Supervisor, Cedar
City, Dixie National Forest, 1789 N. Wedgewood Lane, Cedar City UT,
84720. Mary C. Erickson, Forest Supervisor, Richfield, Fishlake
National Forest, 115 E 900 North, Richfield UT, 84701.
SUPPLEMENTARY INFORMATION: The Dixie and Fishlake National Forests are
separate administrative units with separate forest plans. However, due
to similar ecology, interested publics, and financial resources, the
two forest plans are being revised with a single planning team. In May
of 2002, the forests formally initiated a land management plan revision
process with publication of a notice of intent to prepare an
environmental impact statement for plan revision. The forests began an
extensive public participation and collaboration process. The planning
team has been working on comprehensive analyses of conditions and
trends for the ecological, social and economic components of the plan
area and related scales of analysis.
The first phase of public participation was focused primarily on
development of ``vision'' statements, desired conditions, management
issues, and suitable land uses to be incorporated into the preliminary
proposed action. Over sixty community meetings were conducted in this
effort. During the second phase, the planning team met with the public
to review the content of the preliminary proposal and to get feedback
as to its desirability and feasibility. The review and feedback phase
is ongoing. The planning team will draft a summary of findings from the
analyses of ecological, social, and economic conditions in the form of
a Comprehensive Evaluation Report. Many of these analyses have already
been developed with and reviewed by public participants. We are still
accepting feedback on the preliminary proposed action and the analyses.
We will use these comments to further modify the plan proposal. The
planning team will take additional collaborative steps to finish the
draft plan components and to identify potential options. Remaining work
includes drafting a summary of condition and trend analyses, plan
components for formal review and comment, a monitoring program, and an
environmental management system.
This is an open planning process with numerous opportunities for
the public to obtain information, provide comment, or participate in
collaborative stakeholder activities. The focal points of future
collaborative work will be: (1) Review and adjustment of the
preliminary proposed action (2) identification and development of
management objectives to assist in attaining or maintaining desired
conditions, (3) formulation of guidelines to serve as operational
controls to help ensure projects move toward or maintain desired
conditions, and (4) development of the plan monitoring framework and
environmental management system to guide adaptive management. We expect
to complete this phase of collaboration by early Fall of 2005. Our
remaining forest plan revision schedule will be approximately as
follows:
------------------------------------------------------------------------
------------------------------------------------------------------------
Release of Draft Forest Plan and start of Winter 2005-06
90-day public comment period.
Release of Final Plans and start of 30-day Summer 2006
objection period.
Final decision and start of plan Fall 2006
implementation.
------------------------------------------------------------------------
Please see our website to review proposed management direction in
progress and other details.
Dated: July 25, 2005.
Robert A. Russell,
Forest Supervisor, Dixie National Forest.
Dated: July 22, 2005.
Mary C. Erickson,
Forest Supervisor, Fishlake National Forest.
[FR Doc. 05-15424 Filed 8-3-05; 8:45 am]
BILLING CODE 3410-ES-M