Exelon Generation Company, LLC, AmerGen Energy Company, LLC, Commonwealth Edison Company, Unicom Power Marketing, Inc., PECO, Energy Company, Exelon Energy Company, Exelon Edgar, LLC, Exelon West Medway, LLC, Exelon Wyman, LLC, Exelon New Boston, LLC, Exelon Framingham, LLC, and Exelon New England Power Marketing, L.P.; Notice of Institution of Proceeding and Refund Effective Date, 44603-44604 [05-15386]
Download as PDF
Federal Register / Vol. 70, No. 148 / Wednesday, August 3, 2005 / Notices
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Magalie R. Salas,
Secretary.
[FR Doc. 05–15395 Filed 8–2–05; 8:45 am]
BILLING CODE 6717–01–P
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
August 5, 2005.
Magalie R. Salas,
Secretary.
[FR Doc. E5–4187 Filed 8–2–05; 8:45 am]
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
BILLING CODE 6717–01–P
[Docket No. RP05–520–000]
Eastern Shore Natural Gas Company;
Notice of Penalty Sharing Report
July 29, 2005.
Take notice that on July 26, 2005,
Eastern Shore Natural Gas Company
(Eastern Shore) tendered for filing a
report detailing the distribution of
penalty revenue sharing amounts to
affected buyers.
Eastern Shore states that copies of the
filing have been served upon the
recipients of the refund and their
respective state commissions.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed in on or before the
date as indicated below. Anyone filing
an intervention or protest must serve a
copy of that document on the Applicant.
Anyone filing an intervention or protest
on or before the intervention or protest
date need not serve motions to intervene
or protests on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
VerDate jul<14>2003
15:22 Aug 02, 2005
Jkt 205001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. RP04–248–007 and RP04–251–
008]
44603
The Commission encourages
electronic submission of protests in lieu
of paper using the ‘‘eFiling’’ link at
https://www.ferc.gov. Persons unable to
file electronically should submit an
original and 14 copies of the protest to
the Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Magalie R. Salas,
Secretary.
[FR Doc. E5–4173 Filed 8–2–05; 8:45 am]
BILLING CODE 6717–01–P
El Paso Natural Gas Company; Notice
of Compliance Filing
DEPARTMENT OF ENERGY
July 29, 2005.
Take notice that on July 25, 2005, El
Paso Natural Gas Company (EPNG)
tendered for filing as part of its FERC
Gas Tariff, Second Revised Volume No.
1A, the following tariff sheets to become
effective May 1, 2005:
Second Substitute Original Sheet No. 136
Second Substitute Original Sheet No. 137
EPNG states that the filing is being
made in compliance with the
Commission Order dated May 27, 2005,
in the above listed proceeding. EPNG
states that these tariff sheets are revised
to suspend the Rate Schedule PAL
penalty provisions when EPNG is
unable to schedule PAL nominations.
EPNG states that copies of the filing
were served on parties on the official
service list in the above-captioned
proceedings.
Any person desiring to protest this
filing must file in accordance with Rule
211 of the Commission’s Rules of
Practice and Procedure (18 CFR
385.211). Protests to this filing will be
considered by the Commission in
determining the appropriate action to be
taken, but will not serve to make
protestants parties to the proceeding.
Such protests must be filed in
accordance with the provisions of
Section 154.210 of the Commission’s
regulations (18 CFR 154.210). Anyone
filing a protest must serve a copy of that
document on all the parties to the
proceeding.
PO 00000
Frm 00051
Fmt 4703
Sfmt 4703
Federal Energy Regulatory
Commission
[EL05–132–000]
Exelon Generation Company, LLC,
AmerGen Energy Company, LLC,
Commonwealth Edison Company,
Unicom Power Marketing, Inc., PECO,
Energy Company, Exelon Energy
Company, Exelon Edgar, LLC, Exelon
West Medway, LLC, Exelon Wyman,
LLC, Exelon New Boston, LLC, Exelon
Framingham, LLC, and Exelon New
England Power Marketing, L.P.; Notice
of Institution of Proceeding and
Refund Effective Date
July 7, 2005.
On July 5, 2005, the Commission
issued an order that instituted a
proceeding in Docket No. EL05–132–
000, pursuant to section 206 of the
Federal Power Act (FPA), 16 U.S.C.
824e, concerning the continued justness
and reasonableness of the market-based
rates charged by Exelon Corporation
(Exelon Generation Company, LLC) and
its affiliates, AmerGen Energy Company,
LLC, Commonwealth Edison Company,
Unicom Power Marketing, Inc., Exelon
Edgar, LLC, Exelon Framingham, LLC,
Exelon West Medway, LLC, Exelon
Wyman, LLC, and Exelon New Boston,
LLC, Exelon New England Power
Marketing, L.P., PECO Energy Company,
and Exelon Energy Company’s. Exelon
E:\FR\FM\03AUN1.SGM
03AUN1
44604
Federal Register / Vol. 70, No. 148 / Wednesday, August 3, 2005 / Notices
Corporation, et al, 112 FERC ¶61,027
(2005).
The refund effective date in Docket
No. EL05–132–000, established
pursuant to section 206(b) of the FPA,
will be 60 days from the date of
publication of this notice in the Federal
Register.
Magalie R. Salas,
Secretary.
[FR Doc. 05–15386 Filed 8–2–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project 11301–010]
Fall Line Hydro Company, Inc.; Notice
Rejecting Request for Rehearing
July 29, 2005.
On July 18, 2005, Fall Line Hydro
Company, Inc. filed a request for
rehearing of a June 8, 2005, Commission
staff order denying extension of time to
commence construction for the Carters
Reregulation Dam Project No. 11301.
The project is located at the U.S. Army
Corps of Engineers’ Carters Reregulation
Dam and Reservoir on the Cossawattee
River near the town of Calhoun, in
Murray County, Georgia.
Pursuant to section 313(a) of the
Federal Power Act, 16 U.S.C. 8251(a), an
aggrieved party must filed a request for
rehearing within thirty days after the
issuance of the Commission’s Order, in
this case no, later than July 8, 2005.
Because the 30-day rehearing deadline
is statutory based it cannot be extended
and Fall Line Hydro Company, Inc.’s
request for rehearing must be rejected as
untimely.
This notice constitutes final agency
action. Requests for rehearing by the
Commission of this rejection notice may
be filed within 30 days of the date of
issuance of this notice, pursuant to 18
CFR 385.712.
Magalie R. Salas,
Secretary.
[FR Doc. E5–4164 Filed 8–2–05; 8:45 am]
BILLING CODE 6717–01–P
VerDate jul<14>2003
15:22 Aug 02, 2005
Jkt 205001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. RP05–519–000]
Florida Gas Transmission Company;
Notice of Proposed Changes in FERC
Gas Tariff
July 29, 2005.
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Take notice that on July 22, 2005,
Florida Gas Transmission Company
(FGT) tendered for filing as part of its
FERC Gas Tariff, Third Revised Volume
No. 1, the following tariff sheets, to
become effective August 1, 2005:
Magalie R. Salas,
Secretary.
[FR Doc. E5–4185 Filed 8–2–05; 8:45 am]
Seventy-First Revised Sheet No. 8A,
Sixty-Third Revised Sheet No. 8A.01,
Sixty-Third Revised Sheet No. 8A.02,
Twenty-Third Revised Sheet No. 8A.04,
Sixty-Sixth Revised Sheet No. 8B,
Fifty-Ninth Revised Sheet No. 8B.01,
Fifteenth Revised Sheet No. 8B.02.
DEPARTMENT OF ENERGY
FGT states that the tariff sheets listed
above are being filed pursuant to section
27.A.2.b of the general terms and
conditions of FGT’s tariff, which
provides for flex adjustments to FGT’s
base fuel reimbursement charge
percentage.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed in accordance
with the provisions of Section 154.210
of the Commission’s regulations (18 CFR
154.210). Anyone filing an intervention
or protest must serve a copy of that
document on the Applicant. Anyone
filing an intervention or protest on or
before the intervention or protest date
need not serve motions to intervene or
protests on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
PO 00000
Frm 00052
Fmt 4703
Sfmt 4703
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
[Project No. 7264]
Fox River Paper Company, N.E.W.
Hydro, Inc.; Notice of Authorization for
Continued Project Operation
July 7, 2005.
On January 22, 2003, Fox River Paper
Company and N.E.W. Hydro, Inc.,
licensees for the Middle Appleton Dam
Project No. 7264, filed an application for
a new or subsequent license pursuant to
the Federal Power Act (FPA) and the
Commission’s regulations thereunder.
Project No. 7264 is located on the Fox
River in Outagamie County, Wisconsin.
The license for Project No. 7264 was
issued for a period ending June 30,
2005. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year to year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
E:\FR\FM\03AUN1.SGM
03AUN1
Agencies
[Federal Register Volume 70, Number 148 (Wednesday, August 3, 2005)]
[Notices]
[Pages 44603-44604]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 05-15386]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[EL05-132-000]
Exelon Generation Company, LLC, AmerGen Energy Company, LLC,
Commonwealth Edison Company, Unicom Power Marketing, Inc., PECO, Energy
Company, Exelon Energy Company, Exelon Edgar, LLC, Exelon West Medway,
LLC, Exelon Wyman, LLC, Exelon New Boston, LLC, Exelon Framingham, LLC,
and Exelon New England Power Marketing, L.P.; Notice of Institution of
Proceeding and Refund Effective Date
July 7, 2005.
On July 5, 2005, the Commission issued an order that instituted a
proceeding in Docket No. EL05-132-000, pursuant to section 206 of the
Federal Power Act (FPA), 16 U.S.C. 824e, concerning the continued
justness and reasonableness of the market-based rates charged by Exelon
Corporation (Exelon Generation Company, LLC) and its affiliates,
AmerGen Energy Company, LLC, Commonwealth Edison Company, Unicom Power
Marketing, Inc., Exelon Edgar, LLC, Exelon Framingham, LLC, Exelon West
Medway, LLC, Exelon Wyman, LLC, and Exelon New Boston, LLC, Exelon New
England Power Marketing, L.P., PECO Energy Company, and Exelon Energy
Company's. Exelon
[[Page 44604]]
Corporation, et al, 112 FERC ]61,027 (2005).
The refund effective date in Docket No. EL05-132-000, established
pursuant to section 206(b) of the FPA, will be 60 days from the date of
publication of this notice in the Federal Register.
Magalie R. Salas,
Secretary.
[FR Doc. 05-15386 Filed 8-2-05; 8:45 am]
BILLING CODE 6717-01-P