FirstEnergy Nuclear Operating Company, Beaver Valley Power Station, Unit Nos. 1 and 2; Notice of Consideration of Approval of Transfer of Facility Operating Licenses and Conforming Amendments, and Opportunity for a Hearing, 44390-44391 [E5-4095]

Download as PDF 44390 Federal Register / Vol. 70, No. 147 / Tuesday, August 2, 2005 / Notices significant hazards consideration. No contrary determination has been made with respect to this specific license amendment application. In light of the generic determination reflected in 10 CFR 2.1315, no public comments with respect to significant hazards considerations are being solicited, notwithstanding the general comment procedures contained in 10 CFR 50.91. The filing of requests for hearing and petitions for leave to intervene, and written comments with regard to the license transfer application, are discussed below. Within 20 days of the date of publication of this notice, any person whose interest may be affected by the Commission’s action on the application may request a hearing and, if not the applicant, may petition for leave to intervene in a hearing proceeding on the Commission’s action. Requests for a hearing and petitions for leave to intervene should be filed in accordance with the Commission’s rules of practice set forth in Subpart C ‘‘Rules of General Applicability: Hearing Requests, Petitions to Intervene, Availability of Documents, Selection of Specific Hearing Procedures, Presiding Officer Powers, and General Hearing Management for NRC Adjudicatory Hearings,’’ of 10 CFR part 2. In particular, such requests and petitions must comply with the requirements set forth in 10 CFR 2.309. Untimely requests and petitions may be denied, as provided in 10 CFR 2.309(c)(1), unless good cause for failure to file on time is established. In addition, an untimely request or petition should address the factors that the Commission will also consider, in reviewing untimely requests or petitions, set forth in 10 CFR 2.309(c)(1)(i)–(viii). Requests for a hearing and petitions for leave to intervene should be served upon Thomas S. O’Neill, Vice President and Counsel, Exelon Nuclear, 4300 Winfield Road, Warrenville, Illinois 60555, telephone 630–657–3770, fax 630–657–4335, and e-mail thomas.oneill@exeloncorp.com; Jeffrie J. Keenan, Esq., PSEG Nuclear LLC, P.O. Box 236, N–21, Hancocks Bridge, New Jersey 08038, telephone 856–339–5429, fax 856–339–1234, and e-mail jeff.keenan@pseg.com; the General Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, e-mail address for filings regarding license transfer cases only: OGCLT@NRC.gov; and the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001, Attention: Rulemakings and Adjudications Staff, in accordance with 10 CFR 2.302 and 2.305. VerDate jul<14>2003 17:21 Aug 01, 2005 Jkt 205001 The Commission will issue a notice or order granting or denying a hearing request or intervention petition, designating the issues for any hearing that will be held and designating the Presiding Officer. A notice granting a hearing will be published in the Federal Register and served on the parties to the hearing. As an alternative to requests for hearing and petitions to intervene, within 30 days after the date of publication of this notice, persons may submit written comments regarding the license transfer application, as provided for in 10 CFR 2.1305. The Commission will consider and, if appropriate, respond to these comments, but such comments will not otherwise constitute part of the decisional record. Comments should be submitted to the Secretary, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001, Attention: Rulemakings and Adjudications Staff, and should cite the publication date and page number of this Federal Register notice. For further details with respect to this action, see the application dated March 3, 2005, (ML050670664) available for public inspection at the Commission’s Public Document Room (PDR), located at One White Flint North, Public File Area O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible electronically from the Agencywide Documents Access and Management System’s (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, https://www.nrc.gov/ reading-rm/adams.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS, should contact the NRC PDR Reference staff by telephone at 1–800–397–4209, 301– 415–4737 or by e-mail to pdr@nrc.gov. Dated in Rockville, Maryland this 26th day of July 2005. For the Nuclear Regulatory Commission. George F. Wunder, Senior Project Manager, Section 2, Project Directorate I, Division of Licensing Project Management, Office of Nuclear Reactor Regulation. [FR Doc. E5–4102 Filed 8–1–05; 8:45 am] BILLING CODE 7590–01–P PO 00000 Frm 00068 Fmt 4703 Sfmt 4703 NUCLEAR REGULATORY COMMISSION [Docket Nos. 50–334 and 50–412] FirstEnergy Nuclear Operating Company, Beaver Valley Power Station, Unit Nos. 1 and 2; Notice of Consideration of Approval of Transfer of Facility Operating Licenses and Conforming Amendments, and Opportunity for a Hearing The U.S. Nuclear Regulatory Commission (the Commission) is considering the issuance of an order under 10 CFR 50.80 approving the direct transfer of Facility Operating Licenses Nos. DPR–66 and NPF–73 for the Beaver Valley Power Station, Unit Nos. 1 (BVPS 1) and 2 (BVPS 2), respectively, to the extent held by Ohio Edison Company (Ohio Edison) regarding its non-leased interests in BVPS 2, the Cleveland Electric Illuminating Company (Cleveland Electric) and the Toledo Edison Company (Toledo Edison). The transfer would be to FirstEnergy Nuclear Generation Corporation (FENGenCo). The Commission is further considering amending the licenses for administrative purposes to reflect the proposed transfer. According to an application for approval dated June 1, 2005, as supplemented by letter dated July 15, 2005, filed by FirstEnergy Nuclear Operating Company (FENOC), on behalf of Ohio Edison, Cleveland Electric, Toledo Edison and FENGenCo, FENGenCo would assume Ohio Edison’s 35 percent undivided ownership interest in BVPS 1 and 20.22 percent undivided ownership interest in BVPS 2, Cleveland Electric’s 24.47 percent undivided ownership interest in BVPS 2, and Toledo Edison’s 1.65 percent undivided ownership interest in BVPS 2 following approval of the proposed license transfers. FENOC, currently the licensed operator of BVPS 1 and BVPS 2, would remain so and continue to be responsible for the operation and maintenance of BVPS 1 and BVPS 2. Ohio Edison’s 21.66 percent leased interest in BVPS 2 and Toledo Edison’s 18.26 percent leased interest in BVPS 2 would not be changed. No physical changes to the BVPS 1 and BVPS 2 facilities or operational changes are being proposed in the application. The proposed conforming amendments would delete references to Ohio Edison from the license of BVPS 1 and references to Cleveland Electric from the license of BVPS 2, and add references to FENGenCo to licenses of both BVPS 1 and BVPS 2, as appropriate. E:\FR\FM\02AUN1.SGM 02AUN1 Federal Register / Vol. 70, No. 147 / Tuesday, August 2, 2005 / Notices Pursuant to 10 CFR 50.80, no license, or any right thereunder, shall be transferred, directly or indirectly, through transfer of control of the license, unless the Commission shall give its consent in writing. The Commission will approve an application for the direct transfer of a license, if the Commission determines that the proposed transferee is qualified to hold the license, and that the transfer is otherwise consistent with applicable provisions of law, regulations, and orders issued by the Commission pursuant thereto. Before issuance of the proposed conforming license amendments, the Commission will have made findings required by the Atomic Energy Act of 1954, as amended (the Act), and the Commission’s regulations. As provided in 10 CFR 2.1315, unless otherwise determined by the Commission with regard to a specific application, the Commission has determined that any amendment to the license of a utilization facility which does no more than conform the license to reflect the transfer action involves no significant hazards consideration. No contrary determination has been made with respect to this specific license amendment application. In light of the generic determination reflected in 10 CFR 2.1315, no public comments with respect to significant hazards considerations are being solicited, notwithstanding the general comment procedures contained in 10 CFR 50.91. The filing of requests for hearing and petitions for leave to intervene, and written comments with regard to the license transfer application, are discussed below. Within 20 days from the date of publication of this notice, any person whose interest may be affected by the Commission’s action on the application may request a hearing and, if not the applicant, may petition for leave to intervene in a hearing proceeding on the Commission’s action. Requests for a hearing and petitions for leave to intervene should be filed in accordance with the Commission’s rules of practice set forth in Subpart C, ‘‘Rules of General Applicability: Hearing Requests, Petitions to Intervene, Availability of Documents, Selection of Specific Hearing Procedures, Presiding Officer Powers, and General Hearing Management for NRC Adjudicatory Hearings,’’ of 10 CFR Part 2. In particular, such requests and petitions must comply with the requirements set forth in 10 CFR 2.309. Untimely requests and petitions may be denied, as provided in 10 CFR 2.309(c)(1), unless good cause for failure to file on time is VerDate jul<14>2003 17:21 Aug 01, 2005 Jkt 205001 established. In addition, an untimely request or petition should address the factors that the Commission will also consider, in reviewing untimely requests or petitions, set forth in 10 CFR 2.309(c)(1)(I)–(viii). Requests for a hearing and petitions for leave to intervene should be served upon David W. Jankins, Esq., FirstEnergy Corp., 76 South Main Street, Mail Stop A–Go–18, Akron, OH 44308, tel: (330) 384–5037, and e-mail: djenkins@firstenergycorp.com; the General Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001 (e-mail address for filings regarding license transfer cases only: OGCLT@NRC.gov); and the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001, Attention: Rulemakings and Adjudications Staff, in accordance with 10 CFR 2.302 and 2.305. The Commission will issue a notice or order granting or denying a hearing request or intervention petition, designating the issues for any hearing that will be held and designating the Presiding Officer. A notice granting a hearing will be published in the Federal Register and served on the parties to the hearing. As an alternative to requests for hearing and petitions to intervene, within 30 days from the date of publication of this notice, persons may submit written comments regarding the license transfer application, as provided for in 10 CFR 2.1305. The Commission will consider and, if appropriate, respond to these comments, but such comments will not otherwise constitute part of the decisional record. Comments should be submitted to the Secretary, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001, Attention: Rulemakings and Adjudications Staff, and should cite the publication date and page number of this Federal Register notice. For further details with respect to this action, see the application dated June 1, 2005, and the supplemental letter dated July 15, 2005, available for public inspection at the Commission’s Public Document Room (PDR), located at One White Flint North, Public File Area O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible electronically from the Agencywide Documents Access and Management System’s (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, https://www.nrc.gov/reading-rm/ adams.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents PO 00000 Frm 00069 Fmt 4703 Sfmt 4703 44391 located in ADAMS, should contact the NRC PDR Reference staff by telephone at 1–800–397–4209, 301–415–4737 or by e-mail to pdr@nrc.gov. Dated at Rockville, Maryland this 27th day of July 2005. For the Nuclear Regulatory Commission. William A. Macon, Jr., Project Manager, Section 2, Project Directorate III, Division of Licensing Project Management, Office of Nuclear Reactor Regulation. [FR Doc. E5–4095 Filed 8–1–05; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [Docket No. 50–346] FirstEnergy Nuclear Operating Company, Davis-Besse Nuclear Power Station, Unit No. 1; Notice of Consideration of Approval of Transfer of Facility Operating License and Conforming Amendment, and Opportunity for a Hearing The U.S. Nuclear Regulatory Commission (the Commission) is considering the issuance of an order under 10 CFR 50.80 approving the transfer of Facility Operating License No. NPF–3 for the Davis-Besse Nuclear Power Station, Unit No. 1 (Davis-Besse), to the extent held by the Cleveland Electric Illuminating Company (Cleveland Electric) and the Toledo Edison Company (Toledo Edison). The transfer would be to FirstEnergy Nuclear Generation Corporation (FENGenCo). The Commission is further considering amending the license, which contains antitrust license conditions, to reflect the proposed transfer. According to an application for approval dated June 1, 2005, as supplemented by letter dated July 15, 2005, filed by FirstEnergy Nuclear Operating Company (FENOC), on behalf of Cleveland Electric, Toledo Edison and FENGenCo, FENGenCo would assume Cleveland Electric’s 51.38 percent undivided ownership interest in Davis-Besse and Toledo Edison’s 48.62 percent undivided ownership interest in Davis-Besse following approval of the proposed license transfers. FENOC, currently the licensed operator of DavisBesse, would remain so and continue to be responsible for the operation and maintenance of Davis-Besse. No physical changes to the Davis-Besse facility or operational changes are being proposed in the application. The proposed conforming amendment generally would replace references to Cleveland Electric and Toledo Electric E:\FR\FM\02AUN1.SGM 02AUN1

Agencies

[Federal Register Volume 70, Number 147 (Tuesday, August 2, 2005)]
[Notices]
[Pages 44390-44391]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-4095]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-334 and 50-412]


FirstEnergy Nuclear Operating Company, Beaver Valley Power 
Station, Unit Nos. 1 and 2; Notice of Consideration of Approval of 
Transfer of Facility Operating Licenses and Conforming Amendments, and 
Opportunity for a Hearing

    The U.S. Nuclear Regulatory Commission (the Commission) is 
considering the issuance of an order under 10 CFR 50.80 approving the 
direct transfer of Facility Operating Licenses Nos. DPR-66 and NPF-73 
for the Beaver Valley Power Station, Unit Nos. 1 (BVPS 1) and 2 (BVPS 
2), respectively, to the extent held by Ohio Edison Company (Ohio 
Edison) regarding its non-leased interests in BVPS 2, the Cleveland 
Electric Illuminating Company (Cleveland Electric) and the Toledo 
Edison Company (Toledo Edison). The transfer would be to FirstEnergy 
Nuclear Generation Corporation (FENGenCo). The Commission is further 
considering amending the licenses for administrative purposes to 
reflect the proposed transfer.
    According to an application for approval dated June 1, 2005, as 
supplemented by letter dated July 15, 2005, filed by FirstEnergy 
Nuclear Operating Company (FENOC), on behalf of Ohio Edison, Cleveland 
Electric, Toledo Edison and FENGenCo, FENGenCo would assume Ohio 
Edison's 35 percent undivided ownership interest in BVPS 1 and 20.22 
percent undivided ownership interest in BVPS 2, Cleveland Electric's 
24.47 percent undivided ownership interest in BVPS 2, and Toledo 
Edison's 1.65 percent undivided ownership interest in BVPS 2 following 
approval of the proposed license transfers. FENOC, currently the 
licensed operator of BVPS 1 and BVPS 2, would remain so and continue to 
be responsible for the operation and maintenance of BVPS 1 and BVPS 2. 
Ohio Edison's 21.66 percent leased interest in BVPS 2 and Toledo 
Edison's 18.26 percent leased interest in BVPS 2 would not be changed. 
No physical changes to the BVPS 1 and BVPS 2 facilities or operational 
changes are being proposed in the application.
    The proposed conforming amendments would delete references to Ohio 
Edison from the license of BVPS 1 and references to Cleveland Electric 
from the license of BVPS 2, and add references to FENGenCo to licenses 
of both BVPS 1 and BVPS 2, as appropriate.

[[Page 44391]]

    Pursuant to 10 CFR 50.80, no license, or any right thereunder, 
shall be transferred, directly or indirectly, through transfer of 
control of the license, unless the Commission shall give its consent in 
writing. The Commission will approve an application for the direct 
transfer of a license, if the Commission determines that the proposed 
transferee is qualified to hold the license, and that the transfer is 
otherwise consistent with applicable provisions of law, regulations, 
and orders issued by the Commission pursuant thereto.
    Before issuance of the proposed conforming license amendments, the 
Commission will have made findings required by the Atomic Energy Act of 
1954, as amended (the Act), and the Commission's regulations.
    As provided in 10 CFR 2.1315, unless otherwise determined by the 
Commission with regard to a specific application, the Commission has 
determined that any amendment to the license of a utilization facility 
which does no more than conform the license to reflect the transfer 
action involves no significant hazards consideration. No contrary 
determination has been made with respect to this specific license 
amendment application. In light of the generic determination reflected 
in 10 CFR 2.1315, no public comments with respect to significant 
hazards considerations are being solicited, notwithstanding the general 
comment procedures contained in 10 CFR 50.91.
    The filing of requests for hearing and petitions for leave to 
intervene, and written comments with regard to the license transfer 
application, are discussed below.
    Within 20 days from the date of publication of this notice, any 
person whose interest may be affected by the Commission's action on the 
application may request a hearing and, if not the applicant, may 
petition for leave to intervene in a hearing proceeding on the 
Commission's action. Requests for a hearing and petitions for leave to 
intervene should be filed in accordance with the Commission's rules of 
practice set forth in Subpart C, ``Rules of General Applicability: 
Hearing Requests, Petitions to Intervene, Availability of Documents, 
Selection of Specific Hearing Procedures, Presiding Officer Powers, and 
General Hearing Management for NRC Adjudicatory Hearings,'' of 10 CFR 
Part 2. In particular, such requests and petitions must comply with the 
requirements set forth in 10 CFR 2.309. Untimely requests and petitions 
may be denied, as provided in 10 CFR 2.309(c)(1), unless good cause for 
failure to file on time is established. In addition, an untimely 
request or petition should address the factors that the Commission will 
also consider, in reviewing untimely requests or petitions, set forth 
in 10 CFR 2.309(c)(1)(I)-(viii).
    Requests for a hearing and petitions for leave to intervene should 
be served upon David W. Jankins, Esq., FirstEnergy Corp., 76 South Main 
Street, Mail Stop A-Go-18, Akron, OH 44308, tel: (330) 384-5037, and e-
mail: djenkins@firstenergycorp.com; the General Counsel, U.S. Nuclear 
Regulatory Commission, Washington, DC 20555-0001 (e-mail address for 
filings regarding license transfer cases only: OGCLT@NRC.gov); and the 
Secretary of the Commission, U.S. Nuclear Regulatory Commission, 
Washington, DC 20555-0001, Attention: Rulemakings and Adjudications 
Staff, in accordance with 10 CFR 2.302 and 2.305.
    The Commission will issue a notice or order granting or denying a 
hearing request or intervention petition, designating the issues for 
any hearing that will be held and designating the Presiding Officer. A 
notice granting a hearing will be published in the Federal Register and 
served on the parties to the hearing.
    As an alternative to requests for hearing and petitions to 
intervene, within 30 days from the date of publication of this notice, 
persons may submit written comments regarding the license transfer 
application, as provided for in 10 CFR 2.1305. The Commission will 
consider and, if appropriate, respond to these comments, but such 
comments will not otherwise constitute part of the decisional record. 
Comments should be submitted to the Secretary, U.S. Nuclear Regulatory 
Commission, Washington, DC 20555-0001, Attention: Rulemakings and 
Adjudications Staff, and should cite the publication date and page 
number of this Federal Register notice.
    For further details with respect to this action, see the 
application dated June 1, 2005, and the supplemental letter dated July 
15, 2005, available for public inspection at the Commission's Public 
Document Room (PDR), located at One White Flint North, Public File Area 
O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. 
Publicly available records will be accessible electronically from the 
Agencywide Documents Access and Management System's (ADAMS) Public 
Electronic Reading Room on the Internet at the NRC Web site, https://
www.nrc.gov/reading-rm/adams.html. Persons who do not have access to 
ADAMS or who encounter problems in accessing the documents located in 
ADAMS, should contact the NRC PDR Reference staff by telephone at 1-
800-397-4209, 301-415-4737 or by e-mail to pdr@nrc.gov.

    Dated at Rockville, Maryland this 27th day of July 2005.

    For the Nuclear Regulatory Commission.
William A. Macon, Jr.,
Project Manager, Section 2, Project Directorate III, Division of 
Licensing Project Management, Office of Nuclear Reactor Regulation.
[FR Doc. E5-4095 Filed 8-1-05; 8:45 am]
BILLING CODE 7590-01-P