Onshore Oil and Gas Operations; Federal and Indian Oil and Gas Leases; Onshore Oil and Gas Order Number 1, Approval of Operations, 43349-43364 [05-14103]
Download as PDF
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
determined that it is not a ‘‘significant
energy action’’ under that order because
it is not a ‘‘significant regulatory action’’
under Executive Order 12866 and is not
likely to have a significant adverse effect
on the supply, distribution, or use of
energy. The Administrator of the Office
of Information and Regulatory Affairs
has not designated it as a significant
energy action. Therefore, it does not
require a Statement of Energy Effects
under Executive Order 13211.
Technical Standards
The National Technology Transfer
and Advancement Act (NTTAA) (15
U.S.C. 272 note) directs agencies to use
voluntary consensus standards in their
regulatory activities unless the agency
provides Congress, through the Office of
Management and Budget, with an
explanation of why using these
standards would be inconsistent with
applicable law or otherwise impractical.
Voluntary consensus standards are
technical standards (e.g., specifications
of materials, performance, design, or
operation; test methods; sampling
procedures; and related management
systems practices) that are developed or
adopted by voluntary consensus
standards bodies.
This proposed rule does not use
technical standards. Therefore, we did
not consider the use of voluntary
consensus standards.
Environment
We have analyzed this proposed rule
under Commandant Instruction
M16475.lD, which guides the Coast
Guard in complying with the National
Environmental Policy Act of 1969
(NEPA)(42 U.S.C. 4321–4370f), and
have concluded that there are no factors
in this case that would limit the use of
a categorical exclusion under section
2.B.2 of the Instruction. Therefore, this
rule is categorically excluded, under
figure 2–1, paragraph (34)(h), of the
Instruction, from further environmental
documentation. Special local
regulations issued in conjunction with a
regatta or marine parade permit are
specifically excluded from further
analysis and documentation under that
section.
Under figure 2–1, paragraph (34)(h),
of the Instruction, an ‘‘Environmental
Analysis Check List’’ and a ‘‘Categorical
Exclusion Determination’’ are not
required for this rule. Comments on this
section will be considered before we
make the final decision on whether to
categorically exclude this rule from
further environmental review.
VerDate jul<14>2003
17:42 Jul 26, 2005
Jkt 205001
List of Subjects in 33 CFR Part 100
Marine safety, Navigation (water),
Reporting and recordkeeping
requirements, Waterways.
For the reasons discussed in the
preamble, the Coast Guard proposes to
amend 33 CFR part 100 as follows:
PART 100—SAFETY OF LIFE ON
NAVIGABLE WATERS
1. The authority citation for part 100
continues to read as follows:
Authority: 33 U.S.C. 1233; Department of
Homeland Security Delegation No. 0170.1.
43349
Dated: July 2, 2005.
L.L. Hereth,
Rear Admiral, U.S. Coast Guard, Commander,
Fifth Coast Guard District.
[FR Doc. 05–14754 Filed 7–26–05; 8:45 am]
BILLING CODE 4910–15–P
DEPARTMENT OF AGRICULTURE
Forest Service
36 CFR Part 228
RIN 0596–AC20
DEPARTMENT OF THE INTERIOR
2. Add a temporary § 100.35–T05–075
to read as follows:
Bureau of Land Management
§ 100.35–T05–075
Cambridge, MD.
43 CFR Part 3160
Choptank River,
(a) Definitions: (1) Coast Guard Patrol
Commander means a commissioned,
warrant, or petty officer of the Coast
Guard who has been designated by the
Commander, Coast Guard Sector
Baltimore.
(2) Official Patrol means any vessel
assigned or approved by Commander,
Coast Guard Sector Baltimore with a
commissioned, warrant, or petty officer
on board and displaying a Coast Guard
ensign.
(3) Participant includes all vessels
participating in the 2005 Cambridge
Offshore Challenge under the auspices
of the Marine Event Permit issued to the
event sponsor and approved by
Commander, Coast Guard Sector
Baltimore.
(4) Regulated area includes all waters
of the Choptank River, from shoreline to
shoreline, bounded to the west by the
Route 50 Bridge and bounded to the east
by a line drawn along longitude 076° W,
between Goose Point, MD and
Oystershell Point, MD. All coordinates
reference Datum: NAD 1983.
(b) Special local regulations: (1)
Except for event participants and
persons or vessels authorized by the
Coast Guard Patrol Commander, no
person or vessel may enter or remain in
the regulated area.
(2) The operator of any vessel in the
regulated area shall:
(i) Stop the vessel immediately when
directed to do so by any Official Patrol.
(ii) Proceed as directed by any Official
Patrol.
(iii) Unless otherwise directed by the
Official Patrol, operate at a minimum
wake speed not to exceed six (6) knots.
(c) Enforcement period. This section
will be enforced from 9:30 a.m. to 5:30
p.m. on September 25, 2005.
PO 00000
Frm 00018
Fmt 4702
Sfmt 4702
[W0–610–411H12–24 1A]
RIN 1004–AD59
Onshore Oil and Gas Operations;
Federal and Indian Oil and Gas Leases;
Onshore Oil and Gas Order Number 1,
Approval of Operations
U.S. Forest Service,
Agriculture; Bureau of Land
Management, Interior.
ACTION: Joint proposed rule.
AGENCIES:
SUMMARY: This proposed rule would
revise existing Onshore Oil and Gas
Order Number 1, which was published
in the October 21, 1983, edition of the
Federal Register. The Order provides
the requirements necessary for the
approval of all proposed oil and gas
exploratory, development, or service
wells on all Federal and Indian (except
Osage tribe) onshore oil and gas leases,
including leases where the surface is
managed by the U.S. Forest Service (FS).
It also covers most approvals necessary
for subsequent well operations,
including abandonment. The revision is
necessary due to provisions of the 1987
Federal Onshore Oil and Gas Leasing
Reform Act (Reform Act), legal
opinions, court cases since the Order
was issued, and other policy and
procedural changes. The revised Order
would address the submittal of a
complete Application for Permit to Drill
or Deepen package (APD), including a
Drilling Plan, Surface Use Plan of
Operations, evidence of bond coverage
and Operator Certification.
DATES: Send your comments to reach
the Bureau of Land Management (BLM)
on or before August 26, 2005. The BLM
and the FS will not necessarily consider
any comments received after the above
date during its decision on the proposed
rule.
E:\FR\FM\27JYP1.SGM
27JYP1
43350
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
Mail: Director (630), Bureau
of Land Management, Eastern States
Office, 7450 Boston Boulevard,
Springfield, VA 22153.
Hand Delivery: 1620 L Street, NW.,
Suite 401, Washington, DC 20036.
E-mail:
comments_washington@blm.gov.
Federal eRulemaking Portal: https://
www.regulations.gov.
FOR FURTHER INFORMATION CONTACT:
James Burd at (202) 452–5017 or Ian
Senio at (202) 452–5049 at BLM or Barry
Burkhardt at (801) 625–5157 at the
Forest Service. Persons who use a
telecommunications device for the deaf
(TDD) may contact these persons
through the Federal Information Relay
Service (FIRS) at 1–800–877–8339, 24
hours a day, 7 days a week.
SUPPLEMENTARY INFORMATION:
ADDRESSES:
I. Public Comment Procedures
II. Background
III. Discussion of Proposed Rule
IV. Procedural Matters
I. Public Comment Procedures
A. How Do I File Comments?
You may submit your comments by
any one of several methods:
• You may mail your comments to:
Director (630), Bureau of Land
Management, Eastern States Office, 7450
Boston Boulevard, Springfield, Virginia
22153, Attention: RIN 1004–AD59.
• You may deliver comments to 1620
L Street NW., Suite 401, Washington,
DC 20036.
• You may e-mail your comment to:
comments_washington@blm.gov
(Include ‘‘Attn: AD59’’ in the subject
line).
Please make your comments on the
proposed rule as specific as possible,
confine them to issues pertinent to the
proposed rule, and explain the reason
for any changes you recommend. Where
possible, your comments should
reference the specific section or
paragraph of the proposal that you are
addressing.
The Department of the Interior and
the FS may not necessarily consider or
include in the Administrative Record
for the final rule comments that we
receive after the close of the comment
period (see DATES) or comments
delivered to an address other than those
listed above (see ADDRESSES).
B. May I Review Comments Others
Submit?
BLM intends to post all comments on
the internet. If you are requesting that
your comment remain confidential, do
not send us your comment at the direct
internet address or the e-mail address
because we immediately post all
VerDate jul<14>2003
17:42 Jul 26, 2005
Jkt 205001
comments we receive on the internet.
Also, comments, including names and
street addresses of respondents, will be
available for public review at the
address listed under ‘‘ADDRESSES:
Personal or messenger delivery’’ during
regular business hours (7:45 a.m. to 4:15
p.m.), Monday through Friday, except
holidays.
Individual respondents may request
confidentiality, which we will honor to
the extent allowable by law. If you wish
to withhold your name or address,
except for the city or town, you must
state this prominently at the beginning
of your comment. We will make all
submissions from organizations or
businesses, and from individuals
identifying themselves as
representatives or officials of
organizations or businesses, available
for public inspection in their entirety.
II. Background
The regulations at 43 Code of Federal
Regulations (CFR) part 3160, Onshore
Oil and Gas Operations, in section
3164.1 provide for the issuance of
Onshore Oil and Gas Orders to
‘‘implement and supplement’’ the
regulations in part 3160. Also, 36 CFR
228.105 provides for the issuance of FS
Onshore Orders or for the co-signing of
Orders with BLM. Although they are not
codified in the CFR, all onshore orders
are issued using notice and comment
rulemaking and, when issued in final
form, apply nationwide to all Federal
and Indian (except the Osage Tribe)
onshore oil and gas leases. The table in
43 CFR 3164.1(b) lists existing Orders.
This proposed rule would revise
existing Onshore Oil and Gas Order
Number 1 (the Order) which
supplements primarily 43 CFR 3162.3
and 3162.5. 43 CFR 3162.3 covers
conduct of operations, applications to
drill on a lease, subsequent well
operations, other miscellaneous lease
operations, and abandonment. Section
3162.5 covers environmental and safety
obligations. The FS would adopt the
Order which would supplement 36 CFR
part 228 subpart E. The existing Order
has been in effect since November 21,
1983. For further information, see the
October 21, 1983 Federal Register at 48
FR 48916.
III. Discussion of the Proposed Rule
There are four primary reasons the
Order is being revised:
1. The 1987 Reform Act, which
amended the Mineral leasing Act, 30
U.S.C. 181 et seq., included two
significant changes affecting APD
processing on Federal leases. The first
important change is the addition of a
provision for public notification of a
PO 00000
Frm 00019
Fmt 4702
Sfmt 4702
proposed action before APD approval or
substantial modification of the terms of
a Federal lease.
The second important change the Act
made is the assignment of authority to
the FS to approve and regulate the
surface disturbing activity associated
with oil and gas wells on National
Forest System (NFS) lands. Where NFS
lands are involved, a Surface Use Plan
of Operations, included in an APD, is
now approved by the FS. The FS also
approves surface disturbing aspects of
related and subsequent operations. The
FS has actively participated in this
revision, and is a cosigner of this Order.
The Order would apply to FS review of
oil and gas surface operations.
2. In response to protests to two
Resource Management Plans in April
1988, the Office of the Solicitor of the
Department of the Interior issued two
memorandums related to oil and gas
issues. The first and most far-reaching
(issued by the Associate Solicitor,
Energy and Resources on April 1, 1988,
titled ‘‘Legal Responsibilities of BLM for
Oil and Gas Leasing and Operations on
Split Estate Lands’’), concerned BLM
responsibilities on Federal leases
overlain by private surface (split-estate).
In this memorandum the Solicitor’s
Office opined that the National
Environmental Policy Act (NEPA), the
Endangered Species Act (ESA), and the
National Historic Preservation Act
(NHPA) require BLM to regulate
exploration, development, and
abandonment on Federal leases on splitestate lands in essentially the same
manner as a lease overlain by Federal
surface. The memorandum also stated
that while a private owner’s wishes
should be considered in decisions, they
do not overrule requirements of these
statutes and their implementing
regulations.
The second memorandum (issued by
the Assistant Solicitor, Onshore
Minerals, Division of Energy and
Resources on April 4, 1988, titled ‘‘Legal
Responsibilities of BLM for Oil and Gas
Leasing and Operations under the
National Historic Preservation Act’’)
lays out in more detail BLM’s
responsibilities under NHPA,
elucidating further the discussion on
cultural resources in the first opinion.
The pertinent requirements of existing
Order Number 1 do not fully conform to
the memorandums issued by the
Solicitor’s Office in 1988.
3. The existing Order does not
adequately address BLM Rights-of-Way
or FS Special Use Authorizations which
are often required for off-lease facilities
or those activities outside of lands
committed to a unitized area. This has
led to confusion and delays on the part
E:\FR\FM\27JYP1.SGM
27JYP1
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
of both the agencies and industry.
Under the existing Order, APD approval
is often delayed pending completion
and approval of a Right-of-Way or
Special Use Authorization. We intend
for the proposal to eliminate or reduce
this delay. The proposed rule provides
for early identification of any needed
Right-of-Way or Special Use
Authorization, allows for conducting a
single environmental analysis for the
APD and Right-of-Way or Special Use
Authorization, and permits concurrent
approval of the Right-of-Way or Special
Use Authorization with the APD. On
NFS lands, the FS will approve off-lease
activities directly related to the drilling
and production of the well as part of the
Surface Use Plan of Operations instead
of through issuing a separate Special
Use Authorization. Please specifically
comment on the provisions in the
proposal (see proposed Section V.
Rights-of-Way (R/W) ‘‘Special Use
Authorization (SUA)) that would
expedite Right-of-Way or Special Use
Authorization approvals. We are
interested in suggestions of other
methods BLM and the FS could
incorporate to expedite approval of
energy projects.
4. Existing Order Number 1 is over 20
years old. Conditions, regulations,
policies, procedures, and requirements
have been altered, added, and
eliminated since the Order was issued.
BLM is in the process of reviewing field
office practices and the preliminary
findings from that review were
considered in the proposed revisions to
the Order. BLM has reorganized the
Order to follow the review and approval
process and the processing timeframes
for each step are now in one section.
Also, split estate operations are
discussed in more detail.
43351
BLM encourages operators to employ
best management practices when they
develop their APDs. Best management
practices are innovative, dynamic, and
economically feasible mitigation
measures applied on a site-specific basis
to reduce, prevent, or avoid adverse
environmental or social impacts. BLM
field offices incorporate appropriate best
management practices into proposed
APDs and associated on and off-lease
Rights-of-Way approvals after required
NEPA evaluation. They can then be
included in approved APDs as
Conditions of Approval. Typical best
management practices can currently be
found on BLM’s Web site at https://
www.blm.gov/nhp/300/wo310/O&G/
Ops/operations.html.
The following chart explains the
major changes between the existing
Order and the proposed Order.
Existing order
Proposed order
Substantive changes
Introduction .......................................
I. Introduction ................................
A. Authority
I. Accountability ................................
IV. General Operating Requirements.
None .................................................
I.B. Purpose ..................................
None .................................................
I.C. Scope .....................................
None .................................................
II. Definitions .................................
II. Special Situations .........................
IV. General Operating Requirements.
A. Surveying and Staking .................
III. Drilling Operations
III.E. 1. Surveying, Staking, and
Inventories.
B. Material to be Filed ......................
1. Notice of Staking
2. Application for Permit to Drill
C. Conferences and Inspections ......
D. Processing Time Frames
None ..............................................
III.F. Notice of Staking
E. Cultural Resources Clearance .....
F. Threatened and Endangered
Species Clearance and Other Critical Environmental Concerns
IV. General Operating Requirements.
The proposed rule would add a discussion of the authority for issuing
Orders and the requirements of the Federal Onshore Oil and Gas
Leasing Reform Act. The rule would eliminate the discussion of
summary information related to other sections in this Order because they are redundant of this proposed section.
The rule would revise the accountability items and special situations
in the existing Order and move them to Section IV. General Requirements.
The rule would add a new section describing the purpose of the
Order.
The rule would add a short section describing the extent to which the
Order applies.
The rule would add a section that defines key terms to ensure consistent understanding of the terms. Terms that are defined in other
regulations or Orders are not repeated here. The rule defines the
meaning of ‘‘Complete APD’’ for clarification and to ensure consistent application of these terms. Please see the more detailed
discussion below. The rule would also add a definition of the new
‘‘Master Development Plan.’’ Utilizing a Master Development Plan
would provide for environmental analysis and approval of field development or multiple proposed wells as a single approval. ‘‘Days’’
are defined as calendar days. The existing Order uses both ‘‘business days’’ and ‘‘calendar days.’’
The rule would amend the accountability items and special situations
in the existing Order and move them to Section IV. General Requirements.
The rule would move the Surveying and Staking provisions to Section III.E. and include new information related to more current surveying technology. Maps would be required in both paper and
electronic geospatial database format. The rule also contains a
provision that the operator make an effort to obtain approval from
the surface owner before entering private lands. This provision
does not require approval before entry, only a good faith effort to
obtain approval.
The information in existing Section III.A. would be incorporated into
proposed Sections III.E. Required Components of a Complete
APD Package and III.F. Notice of Staking option is retained.
The requirements for, and scheduling of, onsite inspections and the
overall processing timeframes would be incorporated into a new
section on processing. The new section would consolidate all references to processing issues into one section.
Information pertaining to cultural resources, threatened and endangered species, watershed protection, and safety would be moved
to Section IV. General Operating Requirements.
VerDate jul<14>2003
17:42 Jul 26, 2005
III.C.2. Processing .........................
Jkt 205001
PO 00000
Frm 00020
Fmt 4702
Sfmt 4702
E:\FR\FM\27JYP1.SGM
27JYP1
43352
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
Existing order
Proposed order
Substantive changes
G. Components of a Complete Application for Permit to Drill.
III.E. Components of a Complete
ADP Package.
IV. Subsequent Operations ..............
VIII. Subsequent Operations/Sundry Notice.
A. Production Facilities .....................
None ..............................................
B. Other Operations .........................
C. Emergency Repairs .....................
D. Environmental Review .................
VIII.A. Surface Disturbing Operations.
VIII.B. Emergency Repairs ...........
None ..............................................
V. Well-Abandonment .......................
XI. Abandonment ..........................
None .................................................
V. Rights-of-Way (R/W)—Special
Use Authorization (SUA).
VI. Water Well Conversion ...............
IX. Well Conversions ....................
VII. Privately Owned Surface ...........
A. Federal oil and gas leases
B. Indian oil and gas cases
VI. Operating on Lands with Private/State Surface and Federal
or Indian Oil and Gas.
VII. Leases for Indian Oil and Gas
Some of the information contained in the first subsections of existing
Section III.G. would be moved into the Drilling Plan (i.e., item 3.e.)
in the proposed Order and duplication eliminated. The requirements would be unchanged.
The rule would delete language in the existing Order that addresses
well conversions because it would be addressed in Section IX. of
the proposed Order.
The rule would incorporate information relative to production facilities
into other sections.
The rule would make minor editorial changes especially to incorporate FS approval of subsequent surface disturbing activities.
There would be no substantive change to these provisions.
The rule would delete this section since the information would be
covered in proposed Section III.C.2. Processing.
The rule would divide this section into two subsections; A) Plugging
and B) Reclamation. The rule would also incorporate additional information and make clearer the reclamation subsection.
The rule would add this section to explain when the BLM or FS may
require a Right-of-Way or Special Use Authorization and how
these authorizations would be incorporated into the APD approval
process.
The rule would add a paragraph to address conversion to a class II
injection well and would clarify the process to convert a well to a
water well.
This section would change the provisions regarding compensation to
surface owners to that which is required by the authority that
granted the surface patent. It would incorporate the latest policy
requiring a statement from the operator regarding whether or not
there is surface owner agreement. If the operator cannot reach an
agreement with the surface owner, the operator must provide a
bond for the benefit of the surface owner. The bond must must be
sufficient to compensate the surface owner in an amount established by the original land patent or statute authorizing the patent.
VIII. Reports and Activities Required
After Well Completion.
None.
X. Variances ..................................
The rule would move the the requirements to submit completion or
recompletion reports to Section IV. General Requirements.
XII. Appeal Procedures .................
The rule would add a new section
to explain how an operator may
request a variance from a requirement of the Order or a
waiver, exemption, or modification of a lease stipulation and
appeals from denials of those
requests..
The rule would add a new section
to identify the various appeal
processes and the timeframes
associated with certain FS appeals. This section would also
clarify that the incorporation of a
FS approved Surface Use Plan
of Operations into the approval
of an APD is not subject to protest to BLM or appeal to IBLA..
Discussion of Major Changes
Definition of Complete APD
The most significant change in the
proposed rule is that it would eliminate
the term ‘‘Technically and
Administratively Complete’’ and replace
it with a clear definition of ‘‘Complete
APD.’’ This new definition is consistent
with the common practice in many field
offices and would require all field
offices to adopt the same convention.
The new definition would bring needed
VerDate jul<14>2003
17:42 Jul 26, 2005
Jkt 205001
consistency to the approval process.
BLM previously considered defining
Administratively and Technically
complete separately, but decided to
abandon this distinction because of the
difficulty in separating the two concepts
and in potential delays that might be
caused in processing APDs in certain
circumstances.
The Reform Act requires each APD
(except on Indian lands) to be posted for
public review for 30 days. BLM, and the
Surface Managing Entity if appropriate,
PO 00000
Frm 00021
Fmt 4702
Sfmt 4702
will post the required parts of the APD
immediately after receiving the
application, therefore the 30 days will
commence immediately after the APD or
Notice of Staking is filed. No decision
can be made before the end of the 30
day posting period. This is not a change
to existing practice. When possible, a
copy will be posted electronically on
the internet.
Under the proposed process, BLM
would review the APD package, consult
with FS if appropriate, and within 10
E:\FR\FM\27JYP1.SGM
27JYP1
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
days of the filing determine if the
package contains all the documents and
information sufficient and necessary for
processing. If the APD package did not
contain the minimum documentation
and information, BLM or the FS would
notify the operator about the
deficiencies. If an incomplete package
were to contain sufficient information to
continue processing, BLM or the FS
would process the package to the point
where continued processing would
either be impractical or impossible
without additional information.
Generally, a ‘‘complete’’ determination
would follow after the applicant
submits any additional material.
Under the proposal, within 10 days of
receiving an APD package or a Notice of
Staking, BLM will establish a future
date for an onsite inspection. Under the
existing Order, the onsite is held within
15 days of filing. Under this proposal,
BLM and/or the FS would hold the
onsite inspection as soon as practical
after filing. Providing more flexibility in
scheduling the onsite inspection will
allow BLM to take into account weather
conditions and the availability of the
operator and agency staff, as well as the
surface owner if split estate is involved.
It is both agencies’ intent to hold the
onsite as soon as possible and normally
within 15 days after filing. The agencies
recognize that conducting this event so
soon after filing may be difficult, but we
consider it, nevertheless, desirable and
necessary.
The proposal makes BLM, rather than
the operator, responsible for inviting
surface owners to participate in onsite
inspections.
BLM would initiate the review of the
APD package as soon as practical after
filing by the operator. Some deficiencies
are difficult to detect and may not be
evident until the onsite inspection.
Therefore, a determination of
completeness may be delayed beyond
10 days after filing. Under this proposed
Order, BLM may notify the operator of
any remaining deficiencies and any
other changes necessary within 7 days
after the onsite inspection.
The operator is encouraged to respond
to BLM requests for additional
information or to correct deficiencies
within 45 days of the request. Faster
response times by the operator will help
to expedite the review process. BLM
envisions that the operator may be
asked for additional information on
more than one occasion. The technical
review of the APD package is made by
many different specialists. In an effort to
expedite the approval process, BLM will
not wait to compile a complete list of all
deficiencies in a particular application.
Instead, BLM will provide requests for
VerDate jul<14>2003
17:42 Jul 26, 2005
Jkt 205001
additional information to the operator as
soon as BLM or FS staff identifies a
specific deficiency. Waiting to notify the
operator of separate issues may
unnecessarily slow the approval
process.
Under the proposed Order, after the
operator provides all requested
information, BLM would determine if
the package is complete, that is, that the
data submitted is accurate, complete,
meets BLM standards where applicable,
and fully describes the proposed action.
A complete package must contain the
information listed in 43 CFR 3162.3–1
and 43 CFR 3164.1, as appropriate, and
the information this Order would
require. A complete application does
not include a cultural or wildlife
inventory, NEPA documentation, or
other materials that are not
requirements of the sections cited above
or in this Order. It is the policy of BLM
and FS to begin the NEPA analysis and
other inventories as soon as sufficient
information is present to support the
work.
It is the intent of BLM and the FS to
process APDs within 30 days after the
APD package is complete. However,
other regulatory requirements, such as
those in the NEPA, NHPA, and ESA,
may result in further delay. Neither
BLM nor the FS can make a final
decision on any APD or Surface Use
Plan of Operations until these regulatory
requirements are completed.
Compliance in some cases may depend
on actions taken by other agencies over
which BLM and the FS have no
administrative control. Therefore,
neither BLM nor the FS can commit to
processing all APDs within a given time,
but intend to process all APDs within
the minimum time necessary to meet all
regulatory requirements. This is
consistent with existing policy and
practice. The existing Order, effective in
1983, says that ‘‘the 30-day time frame
for completion of the APD process may
sometimes be exceeded where it is
necessary to prepare an EA. * * *’’
BLM did not routinely prepare EAs for
each APD in 1983 because they were
categorically excluded from NEPA
analysis until 1992. We now conduct
some form of NEPA analysis for all
submitted APD packages. In addition,
since the 1983 Order, NHPA and ESA
requirements have become more
extensive. With these added regulatory
requirements, it is not realistic for BLM
to commit to processing all APDs in 30
days.
Drilling and Surface Use Plans
This proposal would make specific
changes to the drilling and surface use
plans as follows:
PO 00000
Frm 00022
Fmt 4702
Sfmt 4702
43353
The former 8-point Drilling Program
(also referred to as the Subsurface Use
Plan) would be replaced with a 9-point
Drilling Plan. This proposal would
expand the required description in the
existing Order addressing the
anticipated casing program, and add a
new requirement to the Drilling Plan to
address the type and amount of cement
operators propose to use in setting each
casing string.
We would replace the former 13-point
Surface Use Program (or Plan) with a 12point Surface Use Plan of Operations.
We would remove the former point 13
of the Surface Use Plan of Operations
‘‘Operator Certification’’ and make it a
separate component of the APD
package. This change makes it clear that
the Operator Certification covers the
entire APD package and not just the
Surface Use Plan of Operations.
The 13-point Surface Use Plan is
currently codified in Forest Service
Regulations at 36 CFR 228 Subpart E,
Appendix A. Under this rule, Appendix
A would be deleted. Although it would
not be codified in 36 CFR, section III.E.
of the proposed Order would apply to
surface use operations on NFS lands.
That proposed section defines the
components of a complete Surface Use
Plan of Operations or Master
Development Plan. The rule would also
revise 36 CFR 228.105(a)(1) to direct
operators to submit surface use plans or
Master Development Plans in
accordance with the proposed Order, or
other applicable onshore orders.
Master Development Plans
This proposal would establish a new
approval process for multiple well
proposals called a Master Development
Plan. This process would be used by an
operator to submit plans for field
development or a multiple well program
in lieu of several individual APDs.
These proposals could be addressed
in a single NEPA analysis and approval.
This process would facilitate the
consideration of cumulative effects early
in the process and enable broad
application of identified mitigation
measures, while minimizing or
significantly reducing the cumulative
timeframe for approval. We also
anticipate that this approval will lead to
better planning of field development
which will minimize adverse
environmental impacts.
The proposed rule envisions the APD
as an application for a proposed action
that is impacted by other analytical
requirements such as the NHPA and the
ESA. The documents other statutes
require are not part of a complete APD
package. This proposal also explains the
approval process for certain subsequent
E:\FR\FM\27JYP1.SGM
27JYP1
43354
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
well operations. The revised Order
would describe the relationship
between the APD package and any
application for an associated BLM
Right-of-Way or FS Special Use
Authorization that may be required.
This Order would replace the 1983
Order incorporated by the FS into its oil
and gas regulations.
Bonding
This proposal would also clarify that
BLM authority to require additional
bond in 43 CFR 3104.5 applies to offlease facilities required to further
development of the lease, such as the
large impoundments being created in
Wyoming for produced water from
Federal and nonfederal coalbed natural
gas wells. BLM is obligated by the
Reform Act to require sufficient bond to
insure ‘‘the restoration of any lands or
surface waters adversely affected by
lease operations after the abandonment
or cessation of oil and gas operations on
the lease’’ 30 U.S.C. 226(g). An Assistant
Solicitor’s memorandum of July 19,
2004, concluded that BLM has the
authority to require additional bond for
such facilities and that the current
regulation does not limit BLM to
increasing the required amount of an
existing bond. Accordingly, the
proposal does not represent a change in
the regulatory scheme.
Provisions in the final Order will
supersede any inconsistent provisions
of existing regulations, inasmuch as
they will constitute a later exercise of
Administrative Procedure Act
rulemaking. To the maximum extent
practical, we will identify such
inconsistencies and include conforming
amendments to titles 36 or 43, or both,
of the CFR in the final rule.
IV. Procedural Matters
Executive Order 12866, Regulatory
Planning and Review
These proposed regulations are not a
significant regulatory action and are not
subject to review by Office of
Management and Budget (OMB) under
Executive Order 12866. OMB makes the
final determination under the Executive
Order. These proposed regulations will
not have an effect of $100 million or
more on the economy. They will not
adversely affect in a material way the
economy, productivity, competition,
jobs, the environment, public health or
safety, or state, local, or tribal
governments or communities. These
proposed regulations will not create a
serious inconsistency or otherwise
interfere with an action taken or
planned by another agency. These
proposed regulations do not alter the
VerDate jul<14>2003
17:42 Jul 26, 2005
Jkt 205001
budgetary effects of entitlements, grants,
user fees, or loan programs or the right
or obligations of their recipients; nor do
they raise novel legal or policy issues.
The revisions this rule would make to
the Order primarily involve changes to
BLM and FS administrative processes.
For example, changes to the term
‘‘Administratively and Technically
Complete’’ only pertain to the process
BLM and the FS would use to review
APD packages and would not have any
significant economic impact. Other
changes, such as the proposal to add a
provision for the use of a Master
Development Plan, may improve
processing and predictability of
operations due to better advance
planning of field development.
Clarifying that our authority to require
additional bond applies to off-lease
facilities would have no economic
impact since BLM already has the
authority under the existing regulatory
scheme to require this bond. Also, as a
result of more clear rules, operators will
have a better understanding of BLM and
FS requirements, processes, and
timelines leading to reduction in delays
in processing and possible
administrative cost savings for BLM, the
FS, and operators.
Regulatory Flexibility Act
Congress enacted the Regulatory
Flexibility Act of 1980 (RFA), as
amended, 5 U.S.C. 601–612, to ensure
that Government regulations do not
unnecessarily or disproportionately
burden small entities. The RFA requires
a regulatory flexibility analysis if a rule
would have a significant economic
impact, either detrimental or beneficial,
on a substantial number of small
entities. For the purposes of this
analysis, we will assume that all entities
(all lessees and operators) that may be
impacted by these regulations are small
entities.
The rule principally deals with the
requirements necessary for the approval
of all proposed oil and gas exploratory,
development, or service wells on all
Federal and Indian (except Osage tribe)
onshore oil and gas leases. These
changes are not significantly different
from the existing Order and primarily
consist of changes to BLM and FS
administrative processes that would not
significantly impact operators or lessees.
As a result of more clear rules, operators
will have a better understanding of BLM
and FS requirements, processes, and
timelines leading to a reduction in
delays in processing and some
administrative cost savings for BLM, the
FS, and operators. Therefore, BLM and
the FS have determined that under the
RFA this proposed rule would not have
PO 00000
Frm 00023
Fmt 4702
Sfmt 4702
a significant economic impact on a
substantial number of small entities.
The use of best management practices
in conditions of approval for a permit to
drill is not new. BLM currently uses
them as conditions of approval and
therefore this provision will have no
economic impact on small entities.
The bonding provision in the rule
would not impact small entities since
the provisions merely reflect existing
authority. As stated earlier, an Assistant
Solicitor’s opinion of July 19, 2004,
concluded that BLM has the authority to
require additional bond for such
facilities and that the current regulation
does not limit BLM to increasing the
required amount of an existing bond.
Accordingly, the proposal does not
represent a change in the regulatory
scheme.
Small Business Regulatory Enforcement
Fairness Act
These proposed regulations are not a
‘‘major rule’’ as defined at 5 U.S.C.
804(2). For the reasons stated in the
RFA discussion, this proposed rule
would not have an annual effect on the
economy greater than $100 million; it
would not result in major cost or price
increases for consumers, industries,
government agencies, or regions; and it
would not have significant adverse
effects on competition, employment,
investment, productivity, innovation, or
the ability of U.S.-based enterprises to
compete with foreign-based enterprises.
Unfunded Mandates Reform Act
These proposed regulations do not
impose an unfunded mandate on state,
local, or tribal governments or the
private sector of more than $100 million
per year; nor do these proposed
regulations have a significant or unique
effect on state, local, or tribal
governments or the private sector. This
proposed rule would primarily involve
changes to BLM’s and the FS’s
administrative processes that would not
have any significant effect monetarily,
or otherwise, on the entities listed.
Therefore, BLM and the FS are not
required to prepare a statement
containing the information required by
the Unfunded Mandates Reform Act (2
U.S.C. 1531 et seq.).
Executive Order 12630, Governmental
Actions and Interference With
Constitutionally Protected Property
Rights (Takings)
The proposed rule does not represent
a government action capable of
interfering with constitutionally
protected property rights. This proposed
rule has no potential to effect property
rights as the changes it would make to
E:\FR\FM\27JYP1.SGM
27JYP1
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
existing procedures primarily involve
changes to BLM’s and the FS’s
administrative processes. Therefore, the
Department of the Interior and the
Department of Agriculture have
determined that the rule would not
cause a taking of private property or
require further discussion of takings
implications under this Executive
Order.
the Paperwork Reduction Act of 1995
(44 U.S.C. 3501 et seq.), we submitted
a copy of the proposed information
collection requirements to the OMB for
review. The OMB approved the
information collection requirements
under Control Number 1004–0137,
which expires on March 31, 2007.
Executive Order 13132, Federalism
The proposed rule will not have a
substantial direct effect on the states, on
the relationship between the national
government and the states, or on the
distribution of power and
responsibilities among the various
levels of government. The proposal will
not have any effect on any of the items
listed. As stated above, the rule
principally deals with the requirements
necessary for the approval of all
proposed oil and gas exploratory,
development, or service wells on all
Federal and Indian (except Osage tribe)
onshore oil and gas leases. In other
words, the rule affects the relationship
between operators, lessees, and BLM
and the FS and would not impact states.
Therefore, in accordance with Executive
Order 13132, BLM has determined that
this proposed rule does not have
sufficient Federalism implications to
warrant preparation of a Federalism
Assessment.
BLM and the FS have prepared an
environmental assessment (EA) and
have found that the proposed rule
would not constitute a major Federal
action significantly affecting the quality
of the human environment under
section 102(2)(C) of the NEPA, 42 U.S.C.
4332(2)(C). A detailed statement under
NEPA is not required. BLM has placed
the EA and the Finding of No
Significant Impact on file in the BLM
Administrative Record at the address
specified in the ADDRESSES section.
The proposed revisions to Order 1
would not impact the environment
significantly. For the most part, the
revisions would involve changes to
BLM’s and the FS’s administrative
processes. For example, replacing the
term ‘‘Administratively and Technically
Complete’’ with the term ‘‘Complete
APD’’ only changes the process BLM
would use to review APD packages and
would not have any impact on the
environment whatsoever. Other
changes, such as the proposal to add
provisions for the use of a Master
Development Plan, may actually
provide improved environmental
protection due to better advance
planning of field development. The use
of best management practices can lead
to reduced environmental damage. Also,
the procedural and clarifying changes
would have no meaningful impact of
any kind on the physical or economic
environment. Any environmental effects
of APDs on Federal lands are analyzed
on a case-by-case basis.
Executive Order 13175, Consultation
and Coordination With Indian Tribal
Governments
BLM approves proposed operations
on all Indian (except Osage) onshore oil
and gas leases and agreements. BLM has
begun consultation on the proposed
revisions to the Order and will continue
to consult with Tribes during the formal
comment period on the rule.
Executive Order 12988, Civil Justice
Reform
Under Executive Order 12988, the
Office of the Solicitor has determined
that this proposed rule would not
unduly burden the judicial system and
that it meets the requirements of
sections 3(a) and 3(b)(2) of the Order.
We have reviewed these regulations to
eliminate drafting errors and ambiguity.
They have been written to minimize
litigation, provide clear legal standards
for affected conduct rather than general
standards, and promote simplification.
Drafting the regulations in clear
language and working closely with legal
counsel assists in all of these areas.
Paperwork Reduction Act
These regulations contain information
collection requirements. As required by
VerDate jul<14>2003
17:42 Jul 26, 2005
Jkt 205001
National Environmental Policy Act
Executive Order 13211, Actions
Concerning Regulations That
Significantly Affect Energy Supply,
Distribution, or Use
In accordance with Executive Order
13211, BLM has determined that the
proposed rule will not have substantial
direct effects on the energy supply,
distribution or use, including a shortfall
in supply or price increase. This rule
would clarify the administrative
processes involved in approving an APD
and more clearly lay out the timeline for
processing applications. It is not clear to
what extent clarification of the rules
will save BLM, the FS, or operators
administrative cost, but we anticipate
that the cost savings will be minimal, as
PO 00000
Frm 00024
Fmt 4702
Sfmt 4702
43355
will any direct effects on the energy
supply, distribution or use.
Clarity of the Regulations
Executive Order 12866 requires each
agency to write regulations that are
simple and easy to understand. We
invite your comments on how to make
these proposed regulations easier to
understand, including answers to
questions such as the following:
1. Are the requirements in the
proposed regulations clearly stated?
2. Do the proposed regulations
contain technical language or jargon that
interferes with their clarity?
3. Does the format of the proposed
regulations (grouping and order of
sections, use of headings, paragraphing,
etc.) aid or reduce their clarity?
4. Would the regulations be easier to
understand if they were divided into
more (but shorter) sections?
5. Is the description of the proposed
regulations in the SUPPLEMENTARY
INFORMATION section of this preamble
helpful in understanding the proposed
regulations? How could this description
be more helpful in making the proposed
regulations easier to understand?
Please send any comments you have
on the clarity of the regulations to the
address specified in the ADDRESSES
section.
Authors
The principal authors of this rule are:
James Burd of the BLM Washington
Office; Bo Brown of the BLM Alaska
State Office; Brian Pruiett of the BLM
Buffalo, Wyoming Field Office; Gary
Stephens of the BLM New Mexico State
Office; Hank Szymanski of the BLM
Colorado State Office; Howard Clevinger
of the BLM Vernal, Utah Field Office;
Roy Swalling of the Montana State
Office; and Barry Burkhardt of the FS
Intermountain Regional Office, Ogden,
Utah, and assisted by the staff of BLM’s
Regulatory Affairs Group and the
Department of the Interior’s Office of the
Solicitor.
List of Subjects
36 CFR Part 228
Environmental protection; Mines;
National forests; Oil and gas
exploration; Public lands-mineral
resources; Public lands-rights-of-way;
Reporting and recordkeeping
requirements; Surety bonds; Wilderness
areas.
43 CFR part 3160
Administrative practice and
procedure; Government contracts;
Indians-lands; Mineral royalties; Oil and
gas exploration; Penalties; Public lands-
E:\FR\FM\27JYP1.SGM
27JYP1
43356
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
mineral resources; Reporting and
recordkeeping requirements.
36 CFR Chapter II
For the reasons set out in the joint
preamble, the FS proposes to amend 36
CFR part 228 as follows:
PART 228—MINERALS
1. The authority citation for part 228
continues to read as follows:
Authority: 30 Stat. 35 and 36, as amended
(16 U.S.C. 478, 551); 41 Stat. 437, as
amended, sec. 5102(d), 101 Stat. 1330–256
(30 U.S.C. 226); 61 Stat. 681, as amended (30
U.S.C. 601); 61 Stat. 914, as amended (30
U.S.C. 352); 69 Stat. 368, as amended (30
U.S.C. 611); and 94 Stat. 2400.
2. Revise § 228.105(a)(1) to read as
follows:
§ 228.105 Issuance of onshore orders and
notices to lessees.
(a) * * *
(1) Operators shall submit surface use
plans of operations or Master
Development Plans in accordance with
the applicable Onshore Oil and Gas
Order. Approval of a Master
Development Plan constitutes approval
of any surface use plan of operations
submitted as a part of, or consistent
with, the approved Master Development
Plan.
*
*
*
*
*
3. Revise § 228.107(c) to read as
follows:
§ 228.107 Review of surface use plan of
operations.
*
*
*
*
*
(c) The authorized Forest officer will
give public notice of the decision on a
plan and include in that notice whether
the decision may be appealed under the
applicable Forest Service appeal
procedures.
*
*
*
*
*
Appendix A to Subpart E of Part 228
[Removed]
4. Remove Appendix A to Subpart E
of Part 228.
Dated: August 26, 2004.
Sally D. Collins,
Acting Chief, USDA—Forest Service.
Editorial Note: This document was
received at the Office of the Federal Register
on July 13, 2005.
43 CFR Chapter II
For the reasons set out in the joint
preamble, the Bureau of Land
Management proposes to amend 43 CFR
part 3160 as follows:
PART 3160—ONSHORE OIL AND GAS
OPERATIONS
1. The authority citation for part 3160
continues to read as follows:
Authority: 25 U.S.C. 396d and 2107; 30
U.S.C. 189, 306, 359, and 1751; and 43 U.S.C.
1732(b), 1733, and 1740.
2. Amend § 3164.1(b) by revising the
first entry in the chart as follows:
§ 3164.1
*
Onshore Oil and Gas Orders.
*
*
(b) * * *
*
*
Order No.
Subject
Effective date
Federal
Register
reference
Supersedes
1. .........................
Approval of operations ...
[insert 60 days after date of publication of final rule] ................................
70 FR * * *
NTL–6
Editorial Note: This document was
received at the Office of the Federal Register
on July 13, 2005.
The following Order would be
implemented by the BLM and FS, but will
not be codified in the Code of Federal
Regulations.
V. Rights-of-Way and Special Use
Authorizations
VI. Operating on Lands with Private/State
Surface and Federal or Indian Oil and
Gas
VII. Leases for Indian Oil and Gas
A. Approval of Operations
B. Surface Use
VIII. Subsequent Operations and Sundry
Notices
A. Surface Disturbing Operations
B. Emergency Repairs
IX. Well Conversions
X. Variances
XI. Abandonment
A. Plugging
B. Reclamation
XII. Appeal Procedures
Attachment I—Sample Format for Notice of
Staking
Onshore Oil and Gas Order Number 1
Onshore Oil and Gas Order Number 1
Approval of Operations
I. Introduction
A. Authority
B. Purpose
C. Scope
II. Definitions
III. Application for Permit to Drill (APD)
A. Where to File
B. Early Notification
C. APD Posting and Processing
D. Valid Period of Approved APD
E. Components of a Complete APD Package
F. Notice of Staking Option
G. Approval of APDs
IV. General Operating Requirements
Approval of Operations
*
*
*
*
*
Appendix—Text of Oil and Gas
Onshore Order
Note —This appendix will not appear in
the BLM regulations in 43 Code of Federal
Regulations.
Dated: August 26, 2004.
Rebecca W. Watson,
Assistant Secretary, Land and Minerals
Management.
VerDate jul<14>2003
17:42 Jul 26, 2005
Jkt 205001
I. Introduction
A. Authority
The Secretaries of the Interior and
Agriculture have authority under various
Federal and Indian mineral leasing laws, as
defined in 30 U.S.C. 1702, to manage oil and
gas operations. The Secretary of the Interior
has delegated this authority to the BLM,
which has issued onshore oil and gas
operating regulations codified at part 3160 of
Title 43 of the Code of Federal Regulations.
The operating regulations at 43 CFR 3164.1
authorize BLM’s Director to issue Onshore
PO 00000
Frm 00025
Fmt 4702
Sfmt 4700
Oil and Gas Orders when necessary to
implement and supplement the operating
regulations. The section also states that all
such Orders are binding on the operator(s) of
Federal and Indian onshore oil and gas leases
(except the Osage Tribe). For leases on Indian
lands, the delegation to BLM appears at 25
CFR parts 211, 212, 213, 225, and 227.
The Secretary of Agriculture has authority
under the Federal Onshore Oil and Gas
Leasing Reform Act of 1987 (Pub. L. 100–203)
(Leasing Reform Act) to regulate surface
disturbing activities on NFS lands. This
authority has been delegated to the FS. Its
regulatory authority is at Title 36 CFR,
Chapter II, including, but not limited to, part
228 Subpart E, part 251 Subpart B, and part
261. Section 228.105 of 36 CFR authorizes
the Chief of the FS to issue, or cosign with
the Director, BLM, Onshore Oil and Gas
Orders necessary to implement and
supplement the operating regulations. The FS
is responsible only for approving and
administering surface disturbing activities on
NFS lands and appeals related to FS
decisions or approvals.
B. Purpose
The purpose of this Order is to state the
application requirements for the approval of
all proposed oil and gas and service wells,
certain subsequent well operations, and
abandonment.
C. Scope
This Order applies to all onshore leases of
Federal and Indian oil and gas (except those
of the Osage Tribe), and Federally-approved
E:\FR\FM\27JYP1.SGM
27JYP1
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
unit or communitization agreements. It also
applies to Indian Mineral Development Act
agreements. References in this Order to leases
means unit or communitization agreements,
as applicable.
II. Definitions
As used in this Order, the following
definitions apply:
Blooie Line means a discharge line used in
conjunction with a rotating head in drilling
operations when air or gas is used as the
circulating medium.
Complete APD means that BLM and the
Surface Managing Entity, if appropriate, have
determined that the information in the APD
package is accurate and addresses all BLM
requirements. The APD package must
contain:
• A completed Form 3160–3 (Application
for Permit to Drill or Reenter) (see 43 CFR
3162.3–1(d)),
• A well plat certified by a registered
surveyor with a surveyor’s original stamp
(see Section III.E.1. of this Order),
• A Drilling Plan (see 43 CFR 3162.3–1(d)
and Section III.E.2. of this Order),
• A Surface Use Plan of Operations (see 43
CFR 3162.3–1(d) and Section III.E.3. of this
Order),
• Evidence of bond coverage (see 43 CFR
3162.3–1(d) and Section III.E.5. of this
Order),
• Operator certification (see Section III.E.6.
of this Order),
• An original signature, which may be an
electronic signature that meets BLM
standards (see Section III.E.6. of this Order),
and
• Other information that may be required
by Order or Notice (see 43 CFR 3162.3–
1(d)(4)).
All maps and plats required as part of the
APD must be submitted in both hard copy
and geospatial database formats. BLM or the
Surface Managing Entity, as appropriate, will
review the APD package and determine that
all information in the drilling plan, the
surface use plan of operations, bonding
requirements, and other information that
BLM may require (43 CFR 3162.3–1(d)(4)),
including the well location plat and
geospatial databases, completely describe the
proposed action. A complete APD is not
defined to include cultural, wildlife, or other
inventories that may be required or an
environmental assessment or environmental
impact statement that may be required by the
NEPA.
Condition of Approval (COA) means a sitespecific requirement included in an
approved APD or Sundry Notice that may
limit or amend the specific actions proposed
by the operator. Conditions of Approval
minimize, mitigate, or prevent impacts to
public lands or other resources. Best
management practices may be incorporated
as a Condition of Approval.
Days means all calendar days including
holidays.
Drilling Plan means those documents an
operator submits as part of an APD package
or as a supplement to an approved plan of
operations detailing the proposed drilling
operations and containing the information
required by 43 CFR 3160 and applicable
Orders.
VerDate jul<14>2003
17:42 Jul 26, 2005
Jkt 205001
Emergency Repairs means actions
necessary to correct an unforeseen problem
that could cause or threaten immediate
substantial adverse impact on public health
and safety or the environment.
Geospatial Database means a set of
georeferenced computer data that contains
both spatial and attribute data. The spatial
data defines the geometry of the object and
the attribute data defines all other
characteristics.
Indian lands means any lands or interest
in lands of an Indian tribe or an Indian
allottee held in trust by the United States or
which is subject to Federal restriction against
alienation.
Indian Oil and Gas means any oil and gas
interest of an Indian tribe or on allotted lands
where the interest is held in trust by the
United States or is subject to Federal
restrictions against alienation. It does not
include minerals subject to the provisions of
section 3 of the Act of June 28, 1906 (34 Stat.
539), but does include oil and gas on lands
administered by the United States under
section 14(g) of Public Law 92–203, as
amended.
Master Development Plan means
information common to multiple planned
wells, including drilling plans, surface use
plans of operations, and plans for future
production.
National Forest System Lands means those
Federal lands administered by the U.S. Forest
Service, such as the National Forests and the
National Grasslands.
Onsite Inspection means an inspection of
the proposed drill pad, access road, flowline
route, and any associated Right-of-Way or
Special Use Authorization needed for
support facilities, conducted before the
approval of the APD or Surface Use Plan of
Operations and construction activities.
Reclamation means returning disturbed
land as near to its predisturbed condition as
is reasonably practical.
Split Estate means lands where the surface
is owned by an entity or person other than
the owner of the Federal or Indian oil and
gas.
Surface Managing Entity means any
Federal or state agency having jurisdiction
over the surface, or a private owner of the
surface, overlying Federal or Indian oil and
gas.
Variance means an approved alternative to
a provision or standard of an Order, Notice
to Lessee, or other requirement (see 43 CFR
3101.1–4).
III. Application for Permit To Drill (APD)
An Application for Permit to Drill or
Reenter (APD), on Form 3160–3, is required
for each proposed well, and for reentry and
deepening of existing wells (including
disposal and service wells), to develop an
onshore lease for Federal or Indian oil and
gas.
A. Where To File
The operator must file an APD, Sundry
Notice, or other required document in the
BLM field office having jurisdiction over the
lands described in the application. As an
alternative to filing in a local BLM office, an
operator may file an APD using BLM’s
PO 00000
Frm 00026
Fmt 4702
Sfmt 4700
43357
electronic commerce application for oil and
gas permitting and reporting. Contact the
local BLM field office for details before using
the electronic commerce application.
B. Early Notification
The operator should contact BLM and any
applicable Surface Managing Entity,
including all private surface owners, to
request an initial planning conference as
soon as the operator has identified a potential
area of development. Early notification is
voluntary, but it allows the involved Surface
Managing Entity to apprise the prospective
operator of any unusual conditions on the
lease area. Early notification also provides
both the Surface Managing Entity and the
prospective operator with the earliest
possible identification of time-sensitive
requirements and determination of potential
areas of conflict. The prospective operator
should have a map of the proposed project
available for Surface Managing Entity review
to determine if a cultural or wildlife
inventory or other information may be
required.
C. APD Posting and Processing
1. Posting
The Mineral Leasing Act, 30 U.S.C. 181 et
seq., as amended, requires BLM and the
Federal Surface Managing Entity, if other
than BLM, to provide at least 30 days public
notice before BLM or the FS may approve an
APD or Master Development Plan on a
Federal oil and gas lease. Posting is not
required for Indian leases.
BLM will post the APD notice in an area
of the BLM field office having jurisdiction
that is readily accessible to the public and,
when possible, electronically on the internet.
If the surface is managed by a Federal agency
other than BLM, that agency also is required
to post the notice for 30 days. The posted
notice is for informational purposes only and
is not an appealable decision. The purpose of
the posting is to give any interested party
notification that a Federal approval of
mineral development has been requested.
BLM or the FS will not post confidential
information.
If the operator subsequently moves the
proposed location of the well, reposting of
the proposal for an additional 30-day period
may be necessary if BLM or the FS
determines that the change is significant.
2. Processing
The timeframes established in this
subsection apply to both individual APDs
and to the multiple APDs included in Master
Development Plans.
(a) Within 10 days of receiving an APD
package, BLM, in consultation with the FS,
if appropriate, will notify the operator as to
whether or not the APD is complete and will
request additional information and correction
of any deficiencies if necessary. If there is
enough information to begin processing the
APD package, BLM and the FS will do so up
to the point that missing information or
uncorrected deficiencies renders further
processing impractical or impossible. The
operator has 45 days after receiving notice
from BLM to provide any additional
information requested or the APD may be
returned to the operator.
E:\FR\FM\27JYP1.SGM
27JYP1
43358
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
(b) Within 10 days of receiving the APD
package, BLM, in coordination with the
operator and Surface Managing Entity
(including, in the case of split estate, the
private surface owners), if appropriate, will
schedule a future date for the onsite
inspection unless the onsite inspection was
held as part of the Notice of Staking (see
Section III.F. of this Order). The onsite
inspection will be held as soon as practicable
based on schedules and weather conditions.
Within 7 days of the onsite inspection, BLM,
and the FS if appropriate, will notify the
operator that the APD is complete or that
additional information is required to make
the APD complete.
The operator has 45 days after receiving
notice from BLM or the FS to submit
additional information or correct deficiencies
noted during or after the onsite inspection.
BLM may return the APD without taking
action if any additional information is not
received or deficiencies are not corrected
within that period. Within 7 days of
receiving requested information, BLM will
notify the operator if the APD is complete.
(c) Once the APD or the Master
Development Plan is complete, BLM and the
FS will expeditiously review and process the
APD or Master Development Plan. Neither
BLM nor the FS can make a final decision on
any APD, Master Development Plan, or
Surface Use Plan of Operations until the
regulatory requirements of the Endangered
Species Act, the National Historic
Preservation Act, and the National
Environmental Policy Act have been
satisfied.
(d) For APDs on NFS lands, the decision
to approve a Surface Use Plan of Operations
or Master Development Plan may be subject
to the current applicable FS appeal
procedures and may take up to 105 days from
the date of the decision before that decision
can be implemented.
BLM does not approve Surface Use Plans
of Operations for National Forest Service
lands. The FS notifies BLM of its Surface Use
Plan of Operations approval and BLM
proceeds with its APD review.
D. Valid Period of Approved APD
1. An APD approval is valid for 1 year from
the date that it is approved, or until lease
expiration, whichever occurs sooner. Lease
suspension will not extend the 1 year APD
approval period. If the operator submits a
written request before the expiration of the
original approval, BLM in coordination with
the FS, as appropriate, may extend the APD’s
validity for up to 1 additional year.
2. If no drilling occurs during the original
or extended periods, the APD expires. If the
operator later decides to drill a well, it must
submit a new APD package for approval. The
operator cannot start drilling operations if the
APD has expired. The operator is responsible
for reclaiming any surface disturbance that
resulted from its actions, even if a well was
not drilled.
E. Components of a Complete APD Package
Best management practices help to
minimize the footprint of energy
development. The BLM has developed a best
management practices policy that includes
VerDate jul<14>2003
17:42 Jul 26, 2005
Jkt 205001
smart, up-front planning and good
implementation to reduce short- and longterm environmental impacts to public and
private resources. Best management practices
are voluntary unless they have been analyzed
as mitigation measures in the NEPA process
for a plan of development, APD, right-of-way,
or other related facility and included as a
Condition of Approval for an APD. Operators
are encouraged to incorporate best
management practices into their APDs
because they can result in reduced
processing times and appeals, protests, and
litigation.
An APD package must include a completed
Form 3160–3 and the following information
that technical specialists of the appropriate
agency will review to determine its technical
adequacy:
1. Surveying, Staking, and Inventories
(a) Surveying, staking, and inventories are
necessary casual uses, typically involving
negligible surface disturbance, and may be
done without advance approval from the
Surface Managing Entity, except for:
• Lands administered by the Department
of Defense,
• Other lands used for military purposes,
• Indian lands, or
• Where more than negligible surface
disturbance is likely to occur.
No entry on private lands for surveying,
staking, and inventories should occur
without the operator first making an effort to
obtain approval from the surface owner.
Also, operators are encouraged to notify BLM
or FS, as appropriate, before entering the
lands.
Typical off-road vehicular use, when
conducted in conjunction with these
activities, will not cause the activity to be
considered more than casual use because it
is a necessary action for obtaining a permit
for a regulated activity.
Operators must include in the APD
package a well location plat prepared by a
registered surveyor depicting the proposed
location of the well and identifying the
points of control and datum used to establish
the section lines or metes and bounds. The
purpose of this plat is to ensure that
operations are within the boundaries of the
lease/agreement and that the depiction of
these operations is accurately recorded both
as to location (latitude and longitude) and in
relation to the surrounding lease/agreement
boundaries (public land survey corner and
boundary ties). The registered surveyor
should coordinate with the cadastral survey
section of the appropriate BLM State Office,
particularly where the lands have not been
surveyed under the Rectangular Survey
System.
The plat and geospatial database must
describe the location of operations in:
• Geographical coordinates referenced to
the National Spatial Reference System, North
American Datum 1983, and
• In feet and direction from the nearest
two adjacent section lines, or, if not within
the Rectangular Survey System, the nearest
two adjacent property lines, generated from
BLM’s current Geographic Coordinate Data
Base.
PO 00000
Frm 00027
Fmt 4702
Sfmt 4700
The surveyor who prepared the plat must
sign it, certifying that the location has been
staked on the ground as shown on the plat.
(b) The operator is responsible for making
access arrangements with the appropriate
Surface Managing Entity (other than BLM
and FS) before surveying, staking, conducting
inventories, or for other purposes. On
allotted Indian lands, the operator must
contact the appropriate Area Office of the
Bureau of Indian Affairs (BIA) to make access
arrangements.
(c) Staking of the proposed drill pad must
include:
• The well location,
• Two 200-foot (61-meter) directional
reference stakes,
• The exterior pad dimensions,
• The reserve pit,
• Cuts and fills,
• Outer limits of the area to be disturbed
(catch points), and
• Any off-location facilities.
All surface disturbances that will result
from construction of ancillary facilities must
also be staked. Proposed new roads require
centerline flagging with stakes clearly visible
from one to the next. In rugged terrain, cut
and fill staking and/or slopestaking of
proposed new access roads and locations for
ancillary facilities may be necessary, as
determined by BLM or the FS.
(d) The onsite inspection will not occur
until the required surveying and staking is
complete, and any new access road(s) have
been flagged, unless a variance is first
granted under Section X. of this Order.
2. Drilling Plan
With each copy of Form 3160–3 the
operator must submit to BLM either a
Drilling Plan or reference a previously
approved field-wide drilling plan. These
plans must be in sufficient detail to permit
a complete appraisal of the technical
adequacy of, and environmental effects
associated with, the proposed project. The
Drilling Plan must adhere to the provisions
and standards of Onshore Oil and Gas Order
Number 2 (see 53 FR 46790) (Order 2) and,
if applicable, Onshore Oil and Gas Order
Number 6 (see 55 FR 48958) (Order 6), and
must include the following information:
a. Names and estimated tops of all geologic
groups, formations, members, or zones.
b. Estimated depth and thickness of
formations, members, or zones potentially
containing usable water, oil, gas, or
prospectively valuable deposits of other
minerals that the operator expects to
encounter, and the operator’s plans for
protecting such resources.
c. The operator’s minimum specifications
for blowout prevention equipment and
diverter systems to be used, including size,
pressure rating, configuration, and the testing
procedure and frequency. Blowout
prevention equipment must meet the
minimum standards outlined in Order 2.
d. The operator’s proposed casing program,
including size, grade, weight, type of thread
and coupling, the setting depth of each
string, and its condition. The operator must
include the minimum design criteria,
including casing loading assumptions and
corresponding safety factors for burst,
collapse, and tensions (body yield, and joint
E:\FR\FM\27JYP1.SGM
27JYP1
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
strength). The operator must also include the
lengths and setting depth of each casing
when a tapered casing string is proposed.
The hole size for each section of hole drilled
must be included. Special casing designs
such as the use of coiled tubing or
expandable casing may necessitate additional
information.
e. The estimated amount and type(s) of
cement expected to be used in the setting of
each casing string. If stage cementing will be
used, provide the setting depth of the stage
tool(s) and amount and type of cement,
including additives, to be used for each stage.
Provide the yield of each cement slurry and
the expected top of cement, with excess, for
each cemented string or stage.
f. Type and characteristics of the proposed
circulating medium or mediums proposed for
the drilling of each well bore section, the
quantities and types of mud and weighting
material to be maintained, and the
monitoring equipment to be used on the
circulating system. The operator must submit
the following information when air or gas
drilling is proposed:
• Length, size, and location of the blooie
line, including the gas ignition and dust
suppression systems,
• Location and capacity of the compressor
equipment, including safety devices, the
distance from the well bore, and location on
the drill site, and
• Anticipated amounts, types, and other
characteristics as defined in this Section, of
the stand-by mud or kill fluid and associated
circulating equipment.
g. The testing, logging, and coring
procedures proposed, including drill stem
testing procedures, equipment, and safety
measures.
h. The expected bottom-hole pressure and
any anticipated abnormal pressures,
temperatures, or potential hazards that the
operator expects to encounter, such as lost
circulation and hydrogen sulfide (see
Onshore Oil and Gas Order Number 6 (55 FR
48958) for information on hydrogen sulfide
operations). A description of the operator’s
plans for mitigating such hazards must be
included.
i. Any other facets of the proposed
operation that the operator would like BLM
to consider in reviewing the application.
Examples include, but are not limited to:
• For directional wells include proposed
directional design, plan view and vertical
section in true vertical and measured depths,
• Horizontal drilling, and
• Coil tubing operations.
3. Surface Use Plan of Operations
With each copy of Form 3160–3, the
operator must submit to BLM a Surface Use
Plan of Operations. The Surface Use Plan of
Operations must:
• Describe the access road(s) and drill pad,
the construction methods that the operator
plans to use, and the proposed means for
containment and disposal of all waste
materials,
• Provide for safe operations, adequate
protection of surface resources, groundwater,
and other environmental components,
• Include adequate measures for
stabilization and reclamation of disturbed
lands, and
VerDate jul<14>2003
17:42 Jul 26, 2005
Jkt 205001
• Where the surface is privately owned,
include a certification of surface owner
agreement or an adequate bond, as described
in Section VI. of this Order.
The Surface Use Plan of Operations must
describe any best management practices the
operator plans to use or is required to use.
All maps that are included in the Surface
Use Plan of Operations must be of a scale no
smaller than 1:24,000, unless otherwise
stated below. Geospatial vector and raster
data must include appropriate attributes and
metadata. Georeferenced raster images must
be from the same source as hardcopy plats
and maps submitted in the APD package.
Maps, plats, and narrative descriptions
must include the following:
a. Existing Roads: The operator must
submit a legible map such as a highway or
county road, United States Geological Survey
(USGS) topographic, Alaska Borough, or
other such map that shows the proposed well
site and access route to the proposed well in
relation to a town, village, or other locatable
public access point.
(1) The operator must improve or maintain
existing roads in a condition the same as or
better than before operations began. The
operator must provide any plans for
improvement and/or maintenance of existing
roads. The information provided by the
operator for construction and use of roads
will be used by BLM for any Right-of-Way
application, as described in Section V. of this
Order. The operator may use existing terrain
and two-track trails, where appropriate, to
assure environmental protection. The
operator should consider using best
management practices in improving or
maintaining existing roads.
(2) The operator may use existing roads
under the jurisdiction of the FS for access if
they meet the transportation objectives of the
FS. When access involves the use of existing
roads, the FS may require that the operator
contribute to road maintenance. This is
usually authorized by a Special Use
Authorization or a joint road use agreement.
The FS will charge the operator a pro rata
share of the costs of road maintenance and
improvement, based upon the anticipated use
of the road.
Information required by the paragraphs
that follow that relate to the Surface Use Plan
of Operations also may be shown on this
map, if appropriately labeled, or on a
separate plat or map.
b. New or Reconstructed Access Roads.
The operator must identify on a map or plat
all permanent and temporary access roads
that it plans to construct or reconstruct in
connection with the drilling of the proposed
well. Locations of all existing and proposed
road structures (culverts, bridges, low water
crossings, etc.) must be shown. The proposed
route to the proposed drill site must be
shown, including distances from the point
where the access route exits established
roads. All permanent and temporary access
roads must be located and designed to meet
the applicable standards of the appropriate
Surface Managing Entity, and be consistent
with the needs of the operator. Final route
location may be made by the Surface
Managing Entity at the time of the onsite
inspection or during approval of the APD.
PO 00000
Frm 00028
Fmt 4702
Sfmt 4700
43359
The operator should consider using best
management practices in designing road
construction.
The operator must design roads based
upon the class or type of road, the safety
requirements, traffic characteristics,
environmental conditions, and the vehicles
the road is expected to carry. The operator
must describe for all road construction or
reconstruction:
• Road width,
• Maximum grade,
• Crown design,
• Turnouts,
• Drainage and ditch design,
• On and off site erosion control,
• Re-vegetation of disturbed areas,
• Location and size of culverts and/or
bridges,
• Fence cuts and/or cattleguards,
• Major cuts and fills,
• Source and storage sites of topsoil, and
• Type of surfacing materials, if any will
be used.
c. Location of Existing Wells: The operator
must include a map or plat and geospatial
database that includes all known wells,
regardless of status, within a 1-mile radius of
the proposed location.
d. Location of Existing and/or Proposed
Production Facilities: The operator must
include a plat diagram and geospatial
database of facilities planned either on or off
the well pad that shows, to the extent known
or anticipated, the location of all production
facilities and lines likely to be installed if the
well is successfully completed for
production.
The map and geospatial database must
show and differentiate between proposed and
existing flow lines, overhead and buried
power lines, and water lines. If facilities will
be located on the well pad, the information
should be consistent with the layout
provided in item i. of this Section.
The operator must show the dimensions of
the facility layouts for all new construction.
This information may be used by BLM or the
FS for Right-of-Way or Special Use
Authorization application information, as
specified in Section V. of this Order.
If the operator has not developed
information regarding production facilities, it
may defer submission of that information
until a production well is completed, in
which case the operator will follow the
procedures in Section VIII. of this Order.
However, for purposes of NEPA analysis,
BLM will need a reasonable estimate of the
facilities to be employed.
e. Location and Types of Water Supply:
Information concerning water supply, such
as rivers, creeks, springs, lakes, ponds, and
wells, may be shown by quarter-quarter
section on a map or plat, or may be described
in writing. The operator must identify the
source, access route, and transportation
method for all water anticipated for use in
drilling the proposed well. The operator must
describe any newly constructed or
reconstructed access roads crossing Federal
or Indian lands that are needed to haul the
water as provided in item b. of this Section.
The operator must indicate if it plans to drill
a water supply well on the lease and, if so,
the operator must describe the location,
E:\FR\FM\27JYP1.SGM
27JYP1
43360
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
construction details, and expected
production requirements, including a
description of how water will be transported
and procedures for well abandonment.
f. Construction Materials: The operator
must state the character and intended use of
all construction materials, such as sand,
gravel, stone, and soil material. If these
materials are Federally-owned, the proposed
source must be shown on a quarter-quarter
section either of a map or plat, or in a written
description. See 43 CFR 3602.33 for
additional guidance.
The affected Surface Managing Entity or
private or Indian mineral materials owner
must be contacted and agreement reached on
the use of mineral materials before those
mineral materials are used.
g. Methods for Handling Waste: The
Surface Use Plan of Operations must contain
a written description of the methods and
locations proposed for safe containment and
disposal of each type of waste material (e.g.,
cuttings, garbage, salts, chemicals, sewage,
etc.) that results from drilling the proposed
well. Likewise, the narrative must include
plans for the eventual disposal of drilling
fluids and any produced oil or water
recovered during testing operations. The
operator must describe plans for the
construction and lining, if necessary, of the
reserve pit.
h. Ancillary Facilities: The operator must
identify the location and construction
methods and materials for all anticipated
ancillary facilities such as camps, airstrips,
and staging areas on a map or plat. The
operator must stake on the ground the
approximate center of proposed camps and
the centerline of airstrips. If the ancillary
facilities are located off-lease, depending on
Surface Managing Entity policy, BLM or the
FS may require the operator to obtain an
additional authorization, such as a Right-ofWay or Special Use Authorization.
i. Well Site Layout: The plat and geospatial
database must have an arrow indicating the
north direction. Plats and geospatial database
with cuts and fills must be surveyed,
designed, drawn, digitized, and certified by
licensed professional surveyors or engineers.
The operator must submit a plat of a scale of
not less than 1 inch = 50 feet showing:
• The proposed drill pad,
• Reserve pit/blooie line/flare pit location,
• Access road entry points and their
approximate location with respect to
topographic features, along with cross section
diagrams of the drill pad, and
• The reserve pit showing all cuts and fills
and the relation to topography.
The plat and geospatial database must also
include the approximate proposed location
and orientation of the:
• Drilling rig,
• Dikes and ditches to be constructed, and
• Topsoil and/or spoil material stockpiles.
j. Plans for Surface Reclamation: The
operator must submit a plan for the surface
reclamation or stabilization of all disturbed
areas. This plan must address interim (during
production) reclamation for the area of the
well pad not needed for production, as well
as final abandonment of the well location.
Such plans must include, as appropriate:
• Configuration of the reshaped
topography,
VerDate jul<14>2003
17:42 Jul 26, 2005
Jkt 205001
• Drainage systems,
• Segregation of spoil materials,
• Surface manipulations,
• Back fill requirements,
• Proposals for pit/sump closures,
• Redistribution of topsoil,
• Soil treatments,
• Seeding or other steps to reestablish
vegetation,
• Weed control, and
• Practices necessary to reclaim all
disturbed areas, including any access roads
and pipelines.
The operator may amend this reclamation
plan at the time of abandonment. Further
details for reclamation are contained in
Section XI. of this Order.
k. Surface Ownership: The operator must
indicate the surface ownership at the well
location, and of all lands crossed by roads
that the operator plans to construct or
upgrade, including, if known, the name of
the agency or owner, phone number, and
address.
Other Information: The operator must
include other information required by
applicable orders and notices (43 CFR
3162.3–1(d)–(4)). When an integrated pest
management program is needed for weed or
insect control, the operator must coordinate
plans with state or local management
agencies and include the pest management
program in the Surface Use Plan of
Operations. BLM also encourages the
operator to submit any additional
information that may be helpful in
processing the application.
4. Master Development Plans
An operator may elect to submit a Master
Development Plan addressing two or more
APDs that share a common drilling plan,
Surface Use Plan of Operations, and plans for
future development and production.
Submitting a Master Development Plan
facilitates early planning, orderly
development, and the cumulative effects
analysis for all the APDs expected in a
developing field. Approval of a Master
Development Plan constitutes approval of all
of the APDs submitted with the Plan.
Processing of a Master Development Plan
follows the processes in Section III.C.2. of
this Order. After the Master Development
Plan is approved, subsequent APDs can
reference the Master Development Plan in
future applications. Therefore, an approved
Master Development Plan results in timelier
processing of subsequent APDs. Each
subsequent proposed well must have a
survey plat and an APD (Form 3160–3) that
references the Master Development Plan and
any specific variations for that well.
5. Bonding
(a) Most bonding needs for oil and gas
operations on Federal leases are discussed in
43 CFR subpart 3104. The operator must
obtain a bond in its own name as principal,
or a bond in the name of the lessee or
sublessee. If the operator uses the lessee’s or
sublessee’s bond, the operator must furnish
a rider (consent of surety and principal) that
includes the operator under the coverage of
the bond. The operator must specify on the
APD, Form 3160–3, the type of bond and
bond number under which the operations
will be conducted.
PO 00000
Frm 00029
Fmt 4702
Sfmt 4700
For Indian oil and gas, the appropriate
provisions at 25 CFR part 200, Subchapter I,
govern bonding.
Under the regulations at 43 CFR 3104.5
and 36 CFR 228.109, BLM or the FS may
require additional bond coverage for specific
APDs. Other factors that BLM or the FS may
consider include:
• History of previous violations,
• Location and depth of wells,
• The total number of wells involved,
• The age and production capability of the
field, and
• Unique environmental issues.
These bonds may be in addition to any
statewide, nationwide, or separate lease bond
already applicable to the lease. In
determining the bond amount, BLM may
consider impacts of activities on both Federal
and nonfederal lands required to develop the
lease that impact lands, waters, and other
resources off the lease.
Separate bonds may be required for
associated Rights-of-Way and/or Special Use
Authorizations that authorize activities not
covered by the approved APD.
(b) On Federal leases, operators may
request a phased release of an individual
lease bond. BLM will grant this reduction
only if the operator:
• Has satisfied the terms and conditions in
the plan for surface reclamation for that
particular operation, and
• No longer has any down-hole liability.
If appropriate, BLM may reduce the bond
in the amount requested by the appropriate
Surface Managing Entity. The FS also may
reduce bonds it requires (but not BLMrequired bonds). BLM and the FS will base
the amount of the bond reduction on a
calculation of the sum that is sufficient to
cover the remaining operations and
abandonment, including reclamation, as
authorized by the Surface Use Plan of
Operations.
6. Operator Certification
The operator must include its name,
address, and telephone number, and the
same information for its field representative,
in the APD package. The following
certification must carry the operator’s
original signature or meet BLM standards for
electronic commerce:
I hereby certify that I, or someone under
my direct supervision, have inspected the
drill site and access route proposed herein;
that I am familiar with the conditions which
currently exist; that I have full knowledge of
state and Federal laws applicable to this
operation; that the statements made in this
APD package are, to the best of my
knowledge, true and correct; and that the
work associated with the operations
proposed herein will be performed in
conformity with this APD package and the
terms and conditions under which it is
approved. I also certify that I, or the company
I represent, am responsible for the operations
conducted under this application. Bond
coverage is provided under BLM/BIA bond
#lll. These statements are subject to the
provisions of 18 U.S.C. 1001 for the filing of
false statements.
Executed this ll day of llll, 20ll.
Name llllllllllllllllll
E:\FR\FM\27JYP1.SGM
27JYP1
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
Position Title llllllllllllll
Address llllllllllllllll
Telephone lllllllllllllll
Field representative (if not above signatory).
Address (if different from above). lllll
Telephone (if different from above). llll
Agents not directly employed by the
operator must submit a letter from the
operator authorizing that agent to act or file
this application on their behalf.
F. Notice of Staking Option
Before filing an APD or Master
Development Plan, the operator may file a
Notice of Staking with BLM. The purpose of
the Notice of Staking is to provide the
operator with an opportunity to gather
information to better address site-specific
resource concerns before preparing the APD
package. This may expedite approval of the
APD. Attachment I, Sample Format for
Notice of Staking, provides the information
for the Notice of Staking option.
For Federal lands managed by other
Surface Managing Entities, BLM will provide
a copy of the Notice of Staking to the
appropriate Surface Managing Entity office.
In Alaska, when a subsistence stipulation is
part of the lease, the operator must also send
a copy of the Notice of Staking to the
appropriate Borough and/or Native Regional
or Village Corporation.
Within 10 days of receiving the Notice of
Staking, BLM or the FS will review it for
completeness and schedule a date for the
onsite inspection. The onsite inspection will
be conducted as soon as weather and other
conditions permit. The operator must
complete staking of the proposed drill pad
and ancillary facilities, and flagging of new
or reconstructed access routes, before the
onsite inspection. The staking must include
a center stake for the proposed well, two
reference stakes, and a flagged access road
centerline. Staking activities are considered
casual use unless the particular activity is
likely to cause more than negligible
disturbance or damage. Off-road vehicular
use is casual use unless, in a particular case,
it is likely to cause more than negligible
disturbance or damage. Before APD approval,
the operator must submit a complete survey
as described in Section III. E. of this Order.
If the surface is privately owned, the
operator must furnish the name, address, and
telephone number of the surface owner if
known. The BLM will invite the surface
owner to participate in the onsite inspection.
Within 7 days of the onsite inspection, all
parties, including the Surface Management
Entity, will jointly develop a list of resource
concerns that the operator must address in
the APD. Surface owner concerns will be
considered to the extent practical within the
law. Failure to submit an APD within 60 days
of the onsite inspection will result in the
Notice of Staking being returned to the
operator.
G. Approval of APDs
(a)(1) Except for NFS lands, BLM has the
lead responsibility for completing the
environmental review process.
(2) BLM cannot approve an APD or Master
Development Plan until it complies with
VerDate jul<14>2003
17:42 Jul 26, 2005
Jkt 205001
certain other laws and regulations including
NEPA, the National Historic Preservation
Act, and the Endangered Species Act. BLM
must document that the needed reviews have
been adequately conducted. In some cases,
operators conduct these reviews, but BLM
remains responsible for their scope and
content and makes its own evaluation of the
environmental issues, as required by 40 CFR
1506.5(b).
(3) The approved APD will contain
Conditions of Approval that reflect necessary
mitigation measures, if necessary.
(4) BLM will establish the terms and
Conditions of Approval for both the APD and
any associated Right-of-Way when the
application is approved.
(b) For NFS lands, the FS will establish the
terms and Conditions of Approval for both
the Surface Use Plan of Operations and any
associated Surface Use Authorization.
After the FS notifies BLM it has approved
a Surface Use Plan of Operations on NFS
lands, BLM must approve the APD before the
operator may begin any surface-disturbing
activity. BLM will not approve an APD until
it is complete.
(c) On Indian lands, BIA has responsibility
for approving Rights-of-Way. In these cases,
the BLM will be a cooperating or co-lead
agency for NEPA compliance.
The responsible agency will incorporate
any mitigation requirements, identified
through the APD review and associated
NEPA and related analyses, as Conditions of
Approval to the APD. In accordance with 43
CFR 3101.1–2 and 36 CFR 228.107, the BLM
or the FS may require reasonable mitigation
measures to ensure that the proposed
operations minimize adverse impacts to other
resources, uses, and users, consistent with
granted lease rights.
IV. General Operating Requirements
Operator Responsibilities
In the APD package, the operator must
describe or show, as set forth in this Order,
the procedures, equipment, and materials to
be used in the proposed operations. The
operator must conduct operations to
minimize adverse effects to surface and
subsurface resources, prevent unnecessary
surface disturbance, and conform with
currently available technology and practice.
While compliance with certain statutes, such
as NEPA, the National Historic Preservation
Act, and the Endangered Species Act, are
Federal responsibilities, the operator may
choose to conduct inventories and provide
other supporting documentation to meet
these requirements. The inventories and
other work may require entering the lease
and adjacent lands before approval of the
APD. As in Staking and Surveying, the
operator is urged to contact the Surface
Managing Entity before entry upon the lands
for these purposes.
The operator can not commence either
drilling operations or preliminary
construction activities before BLM’s approval
of the APD. Operators are responsible for
their contractor’s and subcontractor’s
compliance with the requirements of the
approved APD and/or plan. Drilling without
approval or causing surface disturbance
without approval is a violation of 43 CFR
PO 00000
Frm 00030
Fmt 4702
Sfmt 4700
43361
3162.3–1(c) and is subject to an immediate
daily assessment under 43 CFR 3163.1(b)(2).
The operator must comply with the
provisions of the approved APD, and
applicable laws, regulations, Orders, and
notices to lessees, including, but not limited
to, those that address:
a. Cultural and Historic Resources. If
historic or archaeological materials are
uncovered during construction, the operator
must immediately stop work that might
further disturb such materials, and contact
BLM and, if appropriate, the FS or other
Surface Managing Entity. BLM or the FS will
inform the operator within 7 days as to
whether the materials appear eligible for
listing on the National Register of Historic
Places.
The operator is responsible for recording
the location of any historic or archaeological
resource that is discovered as a result of the
operator’s actions, even if the operator
decides to relocate operations to avoid
further costs to mitigate the site. The operator
also is responsible for stabilizing the exposed
cultural material if the operator created an
unstable condition that must be addressed
immediately. BLM, the FS, or other
appropriate Surface Managing Entity will
assume responsibility for further work
related to the historic or archaeological site.
If the operator does not relocate, the
operator is responsible for mitigation and
stabilization costs and BLM, the FS, or
appropriate Surface Managing Entity will
provide technical and procedural guidelines
for conducting mitigation. The operator may
resume construction when BLM or the FS
verifies that the operator has completed the
required mitigation. Relocation of activities
may subject the proposal to additional
environmental review. Therefore, if the
presence of such sites is suspected, the
operator may want to submit alternate
locations for advance approval before starting
construction.
b. Endangered Species Act. To comply
with the Endangered Species Act , as
amended (16 U.S.C. 1531, et seq.), and its
implementing regulations (50 CFR part 402),
the operator must conduct all operations to
avoid jeopardizing protected fisheries,
wildlife, plants, and their habitats.
c. Watershed Protection. Except as
otherwise provided in an approved Surface
Use Plan of Operations, the operator must not
conduct operations in areas subject to mass
soil movement, riparian areas, floodplains,
lakeshores, and/or wetlands. The operator
also must take measures to minimize or
prevent erosion and sediment production.
Such measures may include, but are not
limited to:
• Avoiding steep slopes and excessive
land clearing when siting structures,
facilities, and other improvements, and
• Temporarily suspending operations
when frozen ground, thawing, or other
weather-related conditions would cause
otherwise avoidable or excessive impacts.
d. Safety Measures. The operator must
maintain structures, facilities, improvements,
and equipment in a safe condition in
accordance with the approved APD. The
operator must also take appropriate measures
as specified in Orders and Notices to Lessees
E:\FR\FM\27JYP1.SGM
27JYP1
43362
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
and Operators to protect the public from any
hazardous conditions resulting from
operations.
In the event of an emergency, the operator
may take immediate action without prior
Surface Managing Entity approval to
safeguard life or to prevent significant
environmental degradation. BLM or the FS
must receive notification of the emergency
situation and the remedial action taken by
the operator as soon as possible, but not later
than 24 hours after the emergency occurred.
If the emergency involves surface resources
on Surface Managing Entity lands, the
operator must notify the Surface Managing
Entity within 24 hours. Upon conclusion of
the emergency, BLM or the FS, where
appropriate, will review the incident and
take appropriate action. If the emergency
only affected drilling operations and had no
surface impacts, only BLM must be notified.
(e) Completion Reports. Within 30 days
after the well completion, the lessee or
operator must submit to BLM two copies of
Form 3160–4, Well Completion or
Recompletion Report and Log. Well logs may
be submitted to BLM in an electronic format
such as ‘‘.LAS’’ format. Surface and bottom
hole locations must be in latitude and
longitude.
V. Rights-of-Way and Special Use
Authorizations
BLM or the FS will notify the operator of
any additional Rights-of-Way, Special Use
Authorizations, licenses, or other permits
that are needed for roads and support
facilities for drilling or off-lease access. This
will normally occur at the time the operator
submits the APD or Notice of Staking
package, or Sundry Notice, or during the
onsite inspection.
BLM or the FS, as appropriate, will
approve or accept on-lease activities that are
associated with actions proposed in the APD
or Sundry Notice and that will occur on the
lease as part of the APD or Sundry Notice.
These actions do not require a Right-of-Way
or Special Use Authorization. For pipeline
Rights-of-Way crossing lands under the
jurisdiction of two or more Federal Surface
Managing Entities, except lands in the NPS
or Indian lands, applications should be
submitted to BLM. Refer to 43 CFR parts
2800 and 2880 for guidance on BLM Rightof-Ways and 36 CFR part 251 for guidance on
FS Special Use Authorizations.
A. Rights-of-Way (BLM). For BLM lands,
the APD package may serve as the supporting
document for the Right-of-Way application in
lieu of a Right-of-Way plan of development.
Any additional information, specified in 43
CFR parts 2800 and 2880, will be required in
order to process the Right-of-Way.
BLM will notify the operator within 10
days of receipt of a Notice of Staking, APD,
or other notification if any parts of the project
require a Right-of-Way. This information may
be submitted by the operator with the APD
package if the Notice of Staking option has
been used.
B. Special Use Authorizations (FS) (36 CFR
251 Subpart B). On NFS lands, uses directly
related to the drilling and production of a
well (e.g., an access road off-lease or crew
camp, or connecting pipeline to a gathering
VerDate jul<14>2003
17:42 Jul 26, 2005
Jkt 205001
system), will be incorporated into the
approved Surface Use Plan of Operations,
rather than a separate Special Use
Authorization. When a Special Use
Authorization is required, the Surface Use
Plan of Operations may serve as the
application for the Special Use Authorization
if the facility for which a Special Use
Authorization is required is adequately
described. Conditions regulating the
authorized use may be imposed to protect the
public interest, to ensure compatibility with
other NFS lands programs and activities, and
to comply with directions provided in the
Forest Land and Resources Management
Plan. The Special Use Authorization requires
payment of an annual fee in advance,
commensurate with the fair market value of
the rights or privileges authorized, except
where otherwise authorized by statute or
regulation. A Special Use Authorization will
include terms and conditions (36 CFR
251.56) and may require a specific
reclamation plan or incorporate applicable
parts of the Surface Use Plan of Operations
reclamation plan by reference.
VI. Operating on Lands With Private/State
Surface and Federal or Indian Oil and Gas
When authorizing lease operations on split
estate lands where the surface is not
Federally-owned and the oil and gas is
Federal or Indian, BLM must comply with
NEPA, the National Historic Preservation
Act, the Endangered Species Act, and related
Federal statutes. For split estate lands within
FS administrative boundaries, BLM has the
lead responsibility, unless there is a local
BLM/FS agreement that gives the FS this
responsibility. For any split estate involving
Indian lands, refer to Section VII.B. of this
Order.
The operator must make a good faith effort
to notify the private surface owner before
entry and obtain an access agreement from
the surface owner. The access agreement may
include terms or conditions of use, be a
wavier, or an agreement for compensation.
The operator must certify to BLM that (1) it
made a good faith effort to notify the surface
owner before entry and (2) that an agreement
with the surface owner has been reached or
that a good faith effort to reach an agreement
failed. If no agreement was reached, the
operator must submit an adequate bond to
BLM for the benefit of the surface owner
sufficient to pay for loss or damages, such as
loss of or damage to agriculture, other
tangible improvements, or structures, as
required by the specific statutory authority
under which the surface was patented or the
terms of the lease. The minimum acceptable
bond amount is $1,000.
Surface owners have the right to appeal the
sufficiency of the bond. Before the approval
of the APD, BLM will make a good faith effort
to contact the surface owner to assure that
they understand their rights of appeal.
The operator must describe the terms of the
Surface Owner Agreement, if one was
obtained, in sufficient detail in the Surface
Use Plan of Operations to enable BLM to
evaluate impacts to adjacent off-site Federal
and Indian lands and resources and prepare
the necessary NEPA documentation. BLM
will make the final determination of
PO 00000
Frm 00031
Fmt 4702
Sfmt 4700
appropriate surface use requirements. In
doing so, BLM will carefully consider the
views of the surface owner and the effect on
the surface owner’s use of the surface before
implementing mitigation measures. The
operator must submit the name, address, and
phone number of the surface owner, if
known. BLM will invite the surface owner to
the onsite inspection to assure that their
concerns are considered. Surface owner
concerns will be considered to the extent that
they are consistent with Federal land
management policy.
VII. Leases for Indian Oil and Gas
A. Approval of Operations
BLM will process APDs, Master
Development Plans, and Sundry Notices on
Indian tribal and allotted oil and gas leases
and Indian Mineral Development Act mineral
agreements in a manner similar to Federal
leases. However, the approval procedures,
including environmental and archaeological
clearance procedures, may vary between
Reservations depending on tribal ordinances.
For processing such applications, BLM
considers the tribe to be the Surface
Managing Entity for tribal lands and the BIA
to be the Surface Managing Entity for allotted
lands. Operators are responsible for obtaining
any special use or access permits from
appropriate BIA and tribal offices. BLM is not
required to post for public inspection APDs
for minerals subject to Indian leases or
agreements.
B. Surface Use
Where the wellsite and/or access road is
proposed on Indian lands, the operator is
responsible for entering into a surface use
agreement with the Indian tribe or the BIA
on behalf of the individual Indian owners.
This agreement must specify the
requirements for protection of surface
resources, mitigation, and reclamation of
disturbed areas. The BIA (25 CFR 211.4,
212.4 and 225.4), the tribe, and BLM will
develop the Conditions of Approval .
VIII. Subsequent Operations and Sundry
Notices
Subsequent operations must follow 43 CFR
part 3160, applicable lease stipulations, and
APD Conditions of Approval.
A. Surface Disturbing Operations
Lessees and operators must submit for
BLM or FS approval, an amendment to the
approved APD on Form 3160–5 before:
• Undertaking any subsequent new
construction outside the approved area of
operations, or
• Reconstructing, or altering existing
facilities including, but not limited to, roads,
emergency pits, firewalls, flowlines, or other
production facilities on any lease that will
result in additional surface disturbance.
If, at the time the original APD was filed,
the lessee or operator elected to defer
submitting information under Section
III.E.3.d. (Location of Existing and/or
Proposed Facilities) of this Order, the lessee
or operator must supply this information
before construction and installation of the
facilities. BLM, in consultation with any
other involved Surface Managing Entity, may
E:\FR\FM\27JYP1.SGM
27JYP1
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
require a field inspection before approving
the proposal. The lessee or operator may not
begin construction until BLM approves the
proposed plan in writing.
B. Emergency Repairs
Lessees or operators may undertake
emergency repairs without prior approval if
they promptly notify BLM. Lessees or
operators must submit sufficient information
to BLM or the FS to permit a proper
evaluation of any:
• Resulting surface disturbing activities, or
• Planned accommodations necessary to
mitigate potential adverse environmental
effects.
IX. Well Conversions
(a) Conversion to an Injection Well
When subsequent operations will result in
a well being converted to a Class II injection
well (i.e., for disposal of produced water, oil
and gas production enhancement, or
underground storage of hydrocarbons), the
operator must file with the appropriate BLM
office and the Surface Managing Entity a
Sundry Notice, Notice of Intent to Convert to
Injection on Form 3160–5. BLM, and the
Surface Managing Entity, if appropriate, will
review the information to ensure its technical
and administrative adequacy. Following the
review, BLM, and the Surface Managing
Entity, where applicable, will decide upon
the approval or disapproval of the
application based upon relevant laws and
regulations and the circumstances (e.g., well
used for lease or non-lease operations,
surface ownership, and protection of
subsurface mineral ownership). BLM will
determine if a Right-of-Way or Special Use
Authorization and additional bonding are
necessary and notify the operator.
(b) Conversion to a Water Supply Well
In cases where the Surface Managing Entity
desires to acquire an oil and gas well and
convert it to a water supply well or acquire
a water supply well that was drilled by the
operator to support lease operations, the
Surface Managing Entity must inform the
appropriate BLM office of its intent before
the approval of the APD in the case of a dry
hole and no later than the time a Notice of
Intent to Abandon is submitted for a depleted
production well. The operator must abandon
the well according to BLM instructions, and
must complete the surface cleanup and
reclamation, in conjunction with the
approved APD, Surface Use Plan of
Operations, or Notice of Intent to Abandon,
if BLM or the FS require it. The Surface
Managing Entity must reach agreement with
the operator as to the satisfactory completion
of reclamation operations before BLM will
approve any abandonment or reclamation.
BLM approval of the partial abandonment
under this section, completion of any
required reclamation operations, and the
signed release agreement will relieve the
operator of further obligation for the well.
X. Variances
The operator may make a written request
to the agency with jurisdiction to request a
variance from this Order. The operator may
include the request in the APD package. A
VerDate jul<14>2003
17:42 Jul 26, 2005
Jkt 205001
variance from the requirements of this Order
does not constitute a variance to provisions
of other regulations, laws, or orders. When
BLM is the decision maker on a request for
a variance, the decision whether to grant or
deny the variance request is entirely within
BLM’s discretion. The decision is not subject
to administrative appeals either to the State
Director or pursuant to 43 CFR part 4.
An operator may also request that BLM
waive, except or modify a lease stipulation
for a Federal lease. An exception is a onetime waiver. In the case of Federal leases, a
request to waive, except or modify a
stipulation should also include information
demonstrating that the factors leading to its
inclusion in the lease have changed
sufficiently to make the protection provided
by the stipulation no longer justified or that
the proposed operation would not cause
unacceptable impacts.
When the waiver, exception or
modification is substantial, the proposed
waiver, exception or modification is subject
to public review for thirty days. Prior to such
public review, the BLM, and when applicable
the FS, will post it in their local field office
and, when possible, electronically on the
internet. When the request is included in the
Notice of Staking or APD, the request will be
included as part of the well posting under
Section III. C. of this Order. Prior to granting
a waiver, exception or modification, the BLM
will obtain the concurrence or approval of
the FS or Federal surface management entity.
Decisions on such waivers, exceptions or
modifications are subject to administrative
review by the State Director and thereafter
appeal pursuant to 43 CFR Part 4.
After drilling has commenced, the BLM
and FS may consider verbal requests for
variances. However, the operator must
submit a written notice within 7 days after
the verbal request. BLM and the FS will
confirm in writing any verbal approval.
Decisions on waivers, exceptions or
modifications submitted after drilling has
commenced are final for the Department and
not subject to administrative review by the
State Director or pursuant to 43 CFR Part 4.
43363
submit a Notice of Intent to Abandon in
advance of plugging.
XI. Abandonment
In accordance with the requirements of 43
CFR 3162.3–4, before starting abandonment
operations the operator must submit a Notice
of Intent to Abandon on Sundry Notices and
Reports Form 3160–5. If the operator
proposes to modify the plans for surface
reclamation approved at the APD stage, the
operator must attach these modifications to
the Notice of Intent to Abandon.
B. Reclamation
Plans for surface reclamation are a part of
the Surface Use Plan of Operations, as
specified in Section III.E.3.j., and must be
designed to return the disturbed area to
productive use and to meet the objectives of
the land and resource management plan. If
the operator proposes to modify the plans for
surface reclamation approved at the APD
stage, the operator must attach these
modifications to the Subsequent Report of
Plug and Abandon using Sundry Notices and
Reports Form 3160–5.
For wells not having an approved plan for
surface reclamation, operators must submit a
proposal describing the procedures to be
followed for complete abandonment,
including a map showing the disturbed area
and roads to be reclaimed. The operator must
submit the request to BLM. BLM will forward
the request to the FS or other Surface
Managing Entity, if appropriate. Neither BLM
nor the FS will approve the complete
abandonment of an well if the Surface
Managing Entity commits to acquiring the
well for water use purposes. The party
acquiring the well assumes liability for the
well.
Earthwork for intermediate and final
reclamation must be completed within 6
months of well completion or well plugging
(weather permitting). All pads, pits, and
roads must be reclaimed to a satisfactorily
revegetated, safe, and stable condition, unless
an agreement is made with the landowner or
Surface Managing Entity to keep the road or
pad in place. Pits containing fluid must not
be breached (cut) and pit fluids must be
removed or solidified before backfilling. Pits
may be allowed to air dry subject to BLM or
FS approval, but the use of chemicals to aid
in fluid evaporation, stabilization, or
solidification must have prior BLM or FS
approval. Seeding or other activities to
reestablish vegetation must be completed
within the time period approved by BLM or
the FS.
Upon completion of reclamation
operations, the lessee or operator must notify
BLM or the FS using Form 3160–5, Final
Abandonment Notice, when the location is
ready for inspection. Final abandonment will
not be approved until the surface reclamation
work required in the Surface Use Plan of
Operations or Subsequent Report of Plug and
Abandon has been completed to the
satisfaction of BLM or the FS and Surface
Managing Entity, if appropriate.
A. Plugging
The operator must obtain BLM approval for
the plugging of the well by submitting a
Notice of Intent to Abandon. In the case of
dry holes, drilling failures, and in emergency
situations, verbal approval for plugging may
be obtained from BLM, with the Notice of
Intent to Abandon promptly submitted as
written confirmation. Within 30 days
following completion of well plugging, the
operator must file with BLM a Subsequent
Report of Plug and Abandon, using Sundry
Notices and Reports Form 3160–5. For
depleted production wells, the operator must
XII. Appeal Procedures
Complete information concerning the
review and appeal processes for BLM actions
is contained in 43 CFR part 4 and subpart
3165. Incorporation of an FS approved
Surface Use Plan of Operations into the
approval of an APD or a Master Development
Plan is not subject to protest to BLM or
appeal to the Interior Board of Land Appeals.
FS decisions approving use of National
Forest System Lands are subject to agency
appeal procedures, currently in accordance
with 36 CFR part 215 or 251. Decisions
governing Surface Use Plan of Operations
PO 00000
Frm 00032
Fmt 4702
Sfmt 4700
E:\FR\FM\27JYP1.SGM
27JYP1
43364
Federal Register / Vol. 70, No. 143 / Wednesday, July 27, 2005 / Proposed Rules
and Special Use Authorization approvals on
NFS lands that involve analysis,
documentation, and other requirements of
the NEPA are subject to agency appeal
procedures, currently under 36 CFR part 215.
If an appeal is filed, the FS must respond
within 45 days and operations must not
occur for 15 days following the date of appeal
disposition.
FS regulations at 36 CFR part 251 govern
appeals of written decisions of the FS related
to issuance, denial, or administration of
written instruments to occupy and use NFS
lands. A list of the types of written
instruments is provided at 36 CFR 251.82,
and includes an SUA and Surface Use Plan
of Operations related to the authorized use
and occupancy of a particular site or area.
The operator may appeal decisions of the
BIA under 25 CFR part 2.
Attachment I—Sample Format for Notice of
Staking
Attachment I—Sample Format for Notice of
Staking
(Not to be used in place of Application for
Permit to Drill Form 3160–3)
1. Oil Well, Gas Well, Other (Specify).
2. Name, Address, and Telephone of
Operator.
3. Name and Telephone of Specific Contact
Person.
4. Surface Location of Well.
Attach:
(a) Sketch showing road entry onto pad,
pad dimensions, and reserve pit.
(b) Topographical or other acceptable map
showing location, access road, and lease
boundaries.
4a. A map (e.g., a USGS 71⁄2″ Quadrangle)
of the area including the proposed well
location and access road.
5. Lease Number.
6. If Indian, Allottee or Tribe Name.
7. Unit Agreement Name.
8. Well Name and Number.
9. American Petroleum Institute Well
Number (if available).
10. Field Name or Wildcat.
11. Section, Township, Range, Meridian; or
Block and Survey; or Area.
12. County, Parish, or Borough.
13. State.
14. Name and Depth of Formation
Objective(s).
15. Estimated Well Depth.
16. For directional or horizontal wells,
anticipated bottom hole location, if known.
17. Additional Information (as appropriate;
include surface owner’s name, address and,
if known, telephone).
18. Signed llll Title llll Date
Note: When the Bureau of Land
Management or Forest Service, as
appropriate, receives this Notice, the agency
will schedule the date of the onsite
inspection. You must stake the location and
flag the access road before the onsite
inspection. Operators should consider the
following before the onsite inspection and
incorporate these considerations into the
Notice of Staking Option, as appropriate:
(a) H2S Potential.
(b) Cultural Resources (Archeology).
VerDate jul<14>2003
17:42 Jul 26, 2005
Jkt 205001
(c) Federal Right-of-Way or Special Use
Permit.
[FR Doc. 05–14103 Filed 7–26–05; 8:45 am]
BILLING CODE 3410–11–P; 4310–84–P
LIBRARY OF CONGRESS
Copyright Royalty Board
37 CFR Part 270
[Docket No. RM 2005–2]
Notice and Recordkeeping for Use of
Sound Recordings Under Statutory
License
Copyright Royalty Board,
Library of Congress.
ACTION: Supplemental request for
comments.
AGENCY:
SUMMARY: The Interim Chief Copyright
Royalty Judge, on behalf of the
Copyright Royalty Board of the Library
of Congress, is issuing a supplemental
request for comments regarding rules for
the delivery and format of records of use
of sound recordings for statutory
licenses under sections 112 and 114 of
the Copyright Act.
DATES: Written comments should be
received no later than August 26, 2005.
Reply comments should be received no
later than September 16, 2005.
ADDRESSES: If hand delivered by a
private party, an original and five copies
of comments and reply comments must
be brought to Room LM–401 of the
James Madison Memorial Building,
Monday through Friday, between 8:30
a.m. and 5 p.m., and the envelope must
be addressed as follows: Copyright
Royalty Board, Library of Congress,
James Madison Memorial Building, LM–
401, 101 Independence Avenue, SE.,
Washington, DC 20559–6000. If
delivered by a commercial courier
(excluding overnight delivery services
such as Federal Express, United Parcel
Service and other similar overnight
delivery services), an original and five
copies of comments and reply
comments must be delivered to the
Congressional Courier Acceptance Site
located at 2nd and D Street, NE.,
Monday through Friday, between 8:30
a.m. and 4 p.m., and the envelope must
be addressed as follows: Copyright
Royalty Board, Library of Congress,
James Madison Memorial Building, LM–
403, 101 Independence Avenue, SE.,
Washington, DC 20559–6000. If sent by
mail (including overnight delivery using
United States Postal Service Express
Mail), an original and five copies of
comments and reply comments must be
addressed to: Copyright Royalty Board,
PO 00000
Frm 00033
Fmt 4702
Sfmt 4702
P.O. Box 70977, Southwest Station,
Washington, DC 20024–0977.
Comments and reply comments may not
be delivered by means of overnight
delivery services such as Federal
Express, United Parcel Service, etc., due
to delays in processing receipt of such
deliveries.
FOR FURTHER INFORMATION CONTACT:
William J. Roberts, Jr., Senior Attorney,
or Abioye E. Oyewole, CRB Program
Specialist. Telephone (202) 707–8380.
Telefax: (202) 252–3423.
SUPPLEMENTARY INFORMATION:
I. Overview
The Copyright Act, as amended by the
Digital Millennium Copyright Act (Pub.
L. 105–304, 112 Stat. 2860 (1998)),
provides a statutory license for digital
audio transmissions by certain eligible
subscription, nonsubscription, satellite
digital audio radio, business
establishment and new subscription
services (17 U.S.C. 114(f)(4)(A)) and a
related ‘‘ephemeral’’ statutory license
for the temporary recordings used in
those transmissions (17 U.S.C.
112(e)(4)). The statute directs the
Librarian of Congress to ‘‘establish
requirements by which copyright
owners may receive reasonable notice of
the use of their sound recordings under
this section, and under which records of
use shall be kept and made available by
entities performing sound recordings[]’’
by digitial audio transmission. 17 U.S.C.
114(f)(4)(A); see, also 17 U.S.C.
112(e)(4). Avoidance of infringement
liability is contingent upon ‘‘complying
with such notice requirements * * *.’’
17 U.S.C. 114(f)(4)(B)(i).
Through extensive prior proceedings,
the Librarian has partially ‘‘establish[ed]
requirements by which copyright
owners may receive reasonable notice of
the use of their sound recordings,’’
adopting interim regulations on the
types of information that must be kept
by digital audio services under 17
U.S.C. 114(f)(4)(A) and 112(e)(4). See, 69
FR 11515 (March 11, 2004). A notice of
proposed rulemaking on the issues of
delivery and formatting was published
on April 27, 2005, by the Copyright
Office. 70 FR 21704. Responsibility for
the notice and recordkeeping
regulations was transferred by Congress
to the Copyright Royalty Judges (‘‘CRJs’’)
by amended sections 114(f)(4)(A) and
112(e)(4) in the Copyright Royalty and
Distribution Reform Act of 2004, Pub. L.
108–419, 118 Stat. 2341 (November 30,
2004), which became effective on May
31, 2005. As anticipated in the April 27,
2005, notice of proposed rulemaking,
the rulemaking record, including the
comments received on the proposed
E:\FR\FM\27JYP1.SGM
27JYP1
Agencies
[Federal Register Volume 70, Number 143 (Wednesday, July 27, 2005)]
[Proposed Rules]
[Pages 43349-43364]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 05-14103]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF AGRICULTURE
Forest Service
36 CFR Part 228
RIN 0596-AC20
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
43 CFR Part 3160
[W0-610-411H12-24 1A]
RIN 1004-AD59
Onshore Oil and Gas Operations; Federal and Indian Oil and Gas
Leases; Onshore Oil and Gas Order Number 1, Approval of Operations
AGENCIES: U.S. Forest Service, Agriculture; Bureau of Land Management,
Interior.
ACTION: Joint proposed rule.
-----------------------------------------------------------------------
SUMMARY: This proposed rule would revise existing Onshore Oil and Gas
Order Number 1, which was published in the October 21, 1983, edition of
the Federal Register. The Order provides the requirements necessary for
the approval of all proposed oil and gas exploratory, development, or
service wells on all Federal and Indian (except Osage tribe) onshore
oil and gas leases, including leases where the surface is managed by
the U.S. Forest Service (FS). It also covers most approvals necessary
for subsequent well operations, including abandonment. The revision is
necessary due to provisions of the 1987 Federal Onshore Oil and Gas
Leasing Reform Act (Reform Act), legal opinions, court cases since the
Order was issued, and other policy and procedural changes. The revised
Order would address the submittal of a complete Application for Permit
to Drill or Deepen package (APD), including a Drilling Plan, Surface
Use Plan of Operations, evidence of bond coverage and Operator
Certification.
DATES: Send your comments to reach the Bureau of Land Management (BLM)
on or before August 26, 2005. The BLM and the FS will not necessarily
consider any comments received after the above date during its decision
on the proposed rule.
[[Page 43350]]
ADDRESSES: Mail: Director (630), Bureau of Land Management, Eastern
States Office, 7450 Boston Boulevard, Springfield, VA 22153.
Hand Delivery: 1620 L Street, NW., Suite 401, Washington, DC 20036.
E-mail: comments_washington@blm.gov. Federal eRulemaking Portal:
https://www.regulations.gov.
FOR FURTHER INFORMATION CONTACT: James Burd at (202) 452-5017 or Ian
Senio at (202) 452-5049 at BLM or Barry Burkhardt at (801) 625-5157 at
the Forest Service. Persons who use a telecommunications device for the
deaf (TDD) may contact these persons through the Federal Information
Relay Service (FIRS) at 1-800-877-8339, 24 hours a day, 7 days a week.
SUPPLEMENTARY INFORMATION:
I. Public Comment Procedures
II. Background
III. Discussion of Proposed Rule
IV. Procedural Matters
I. Public Comment Procedures
A. How Do I File Comments?
You may submit your comments by any one of several methods:
You may mail your comments to: Director (630), Bureau of
Land Management, Eastern States Office, 7450 Boston Boulevard,
Springfield, Virginia 22153, Attention: RIN 1004-AD59.
You may deliver comments to 1620 L Street NW., Suite 401,
Washington, DC 20036.
You may e-mail your comment to: comments_
washington@blm.gov (Include ``Attn: AD59'' in the subject line).
Please make your comments on the proposed rule as specific as
possible, confine them to issues pertinent to the proposed rule, and
explain the reason for any changes you recommend. Where possible, your
comments should reference the specific section or paragraph of the
proposal that you are addressing.
The Department of the Interior and the FS may not necessarily
consider or include in the Administrative Record for the final rule
comments that we receive after the close of the comment period (see
DATES) or comments delivered to an address other than those listed
above (see ADDRESSES).
B. May I Review Comments Others Submit?
BLM intends to post all comments on the internet. If you are
requesting that your comment remain confidential, do not send us your
comment at the direct internet address or the e-mail address because we
immediately post all comments we receive on the internet. Also,
comments, including names and street addresses of respondents, will be
available for public review at the address listed under ``ADDRESSES:
Personal or messenger delivery'' during regular business hours (7:45
a.m. to 4:15 p.m.), Monday through Friday, except holidays.
Individual respondents may request confidentiality, which we will
honor to the extent allowable by law. If you wish to withhold your name
or address, except for the city or town, you must state this
prominently at the beginning of your comment. We will make all
submissions from organizations or businesses, and from individuals
identifying themselves as representatives or officials of organizations
or businesses, available for public inspection in their entirety.
II. Background
The regulations at 43 Code of Federal Regulations (CFR) part 3160,
Onshore Oil and Gas Operations, in section 3164.1 provide for the
issuance of Onshore Oil and Gas Orders to ``implement and supplement''
the regulations in part 3160. Also, 36 CFR 228.105 provides for the
issuance of FS Onshore Orders or for the co-signing of Orders with BLM.
Although they are not codified in the CFR, all onshore orders are
issued using notice and comment rulemaking and, when issued in final
form, apply nationwide to all Federal and Indian (except the Osage
Tribe) onshore oil and gas leases. The table in 43 CFR 3164.1(b) lists
existing Orders. This proposed rule would revise existing Onshore Oil
and Gas Order Number 1 (the Order) which supplements primarily 43 CFR
3162.3 and 3162.5. 43 CFR 3162.3 covers conduct of operations,
applications to drill on a lease, subsequent well operations, other
miscellaneous lease operations, and abandonment. Section 3162.5 covers
environmental and safety obligations. The FS would adopt the Order
which would supplement 36 CFR part 228 subpart E. The existing Order
has been in effect since November 21, 1983. For further information,
see the October 21, 1983 Federal Register at 48 FR 48916.
III. Discussion of the Proposed Rule
There are four primary reasons the Order is being revised:
1. The 1987 Reform Act, which amended the Mineral leasing Act, 30
U.S.C. 181 et seq., included two significant changes affecting APD
processing on Federal leases. The first important change is the
addition of a provision for public notification of a proposed action
before APD approval or substantial modification of the terms of a
Federal lease.
The second important change the Act made is the assignment of
authority to the FS to approve and regulate the surface disturbing
activity associated with oil and gas wells on National Forest System
(NFS) lands. Where NFS lands are involved, a Surface Use Plan of
Operations, included in an APD, is now approved by the FS. The FS also
approves surface disturbing aspects of related and subsequent
operations. The FS has actively participated in this revision, and is a
cosigner of this Order. The Order would apply to FS review of oil and
gas surface operations.
2. In response to protests to two Resource Management Plans in
April 1988, the Office of the Solicitor of the Department of the
Interior issued two memorandums related to oil and gas issues. The
first and most far-reaching (issued by the Associate Solicitor, Energy
and Resources on April 1, 1988, titled ``Legal Responsibilities of BLM
for Oil and Gas Leasing and Operations on Split Estate Lands''),
concerned BLM responsibilities on Federal leases overlain by private
surface (split-estate). In this memorandum the Solicitor's Office
opined that the National Environmental Policy Act (NEPA), the
Endangered Species Act (ESA), and the National Historic Preservation
Act (NHPA) require BLM to regulate exploration, development, and
abandonment on Federal leases on split-estate lands in essentially the
same manner as a lease overlain by Federal surface. The memorandum also
stated that while a private owner's wishes should be considered in
decisions, they do not overrule requirements of these statutes and
their implementing regulations.
The second memorandum (issued by the Assistant Solicitor, Onshore
Minerals, Division of Energy and Resources on April 4, 1988, titled
``Legal Responsibilities of BLM for Oil and Gas Leasing and Operations
under the National Historic Preservation Act'') lays out in more detail
BLM's responsibilities under NHPA, elucidating further the discussion
on cultural resources in the first opinion.
The pertinent requirements of existing Order Number 1 do not fully
conform to the memorandums issued by the Solicitor's Office in 1988.
3. The existing Order does not adequately address BLM Rights-of-Way
or FS Special Use Authorizations which are often required for off-lease
facilities or those activities outside of lands committed to a unitized
area. This has led to confusion and delays on the part
[[Page 43351]]
of both the agencies and industry. Under the existing Order, APD
approval is often delayed pending completion and approval of a Right-
of-Way or Special Use Authorization. We intend for the proposal to
eliminate or reduce this delay. The proposed rule provides for early
identification of any needed Right-of-Way or Special Use Authorization,
allows for conducting a single environmental analysis for the APD and
Right-of-Way or Special Use Authorization, and permits concurrent
approval of the Right-of-Way or Special Use Authorization with the APD.
On NFS lands, the FS will approve off-lease activities directly related
to the drilling and production of the well as part of the Surface Use
Plan of Operations instead of through issuing a separate Special Use
Authorization. Please specifically comment on the provisions in the
proposal (see proposed Section V. Rights-of-Way (R/W) `` Special Use
Authorization (SUA)) that would expedite Right-of-Way or Special Use
Authorization approvals. We are interested in suggestions of other
methods BLM and the FS could incorporate to expedite approval of energy
projects.
4. Existing Order Number 1 is over 20 years old. Conditions,
regulations, policies, procedures, and requirements have been altered,
added, and eliminated since the Order was issued. BLM is in the process
of reviewing field office practices and the preliminary findings from
that review were considered in the proposed revisions to the Order. BLM
has reorganized the Order to follow the review and approval process and
the processing timeframes for each step are now in one section. Also,
split estate operations are discussed in more detail.
BLM encourages operators to employ best management practices when
they develop their APDs. Best management practices are innovative,
dynamic, and economically feasible mitigation measures applied on a
site-specific basis to reduce, prevent, or avoid adverse environmental
or social impacts. BLM field offices incorporate appropriate best
management practices into proposed APDs and associated on and off-lease
Rights-of-Way approvals after required NEPA evaluation. They can then
be included in approved APDs as Conditions of Approval. Typical best
management practices can currently be found on BLM's Web site at http:/
/www.blm.gov/nhp/300/wo310/O&G/Ops/operations.html.
The following chart explains the major changes between the existing
Order and the proposed Order.
----------------------------------------------------------------------------------------------------------------
Existing order Proposed order Substantive changes
----------------------------------------------------------------------------------------------------------------
Introduction....................... I. Introduction............ The proposed rule would add a discussion of
A. Authority............... the authority for issuing Orders and the
requirements of the Federal Onshore Oil and
Gas Leasing Reform Act. The rule would
eliminate the discussion of summary
information related to other sections in this
Order because they are redundant of this
proposed section.
I. Accountability.................. IV. General Operating The rule would revise the accountability items
Requirements. and special situations in the existing Order
and move them to Section IV. General
Requirements.
None............................... I.B. Purpose............... The rule would add a new section describing
the purpose of the Order.
None............................... I.C. Scope................. The rule would add a short section describing
the extent to which the Order applies.
None............................... II. Definitions............ The rule would add a section that defines key
terms to ensure consistent understanding of
the terms. Terms that are defined in other
regulations or Orders are not repeated here.
The rule defines the meaning of ``Complete
APD'' for clarification and to ensure
consistent application of these terms. Please
see the more detailed discussion below. The
rule would also add a definition of the new
``Master Development Plan.'' Utilizing a
Master Development Plan would provide for
environmental analysis and approval of field
development or multiple proposed wells as a
single approval. ``Days'' are defined as
calendar days. The existing Order uses both
``business days'' and ``calendar days.''
II. Special Situations............. IV. General Operating The rule would amend the accountability items
Requirements. and special situations in the existing Order
and move them to Section IV. General
Requirements.
A. Surveying and Staking........... III.E. 1. Surveying, The rule would move the Surveying and Staking
III. Drilling Operations........... Staking, and Inventories. provisions to Section III.E. and include new
information related to more current surveying
technology. Maps would be required in both
paper and electronic geospatial database
format. The rule also contains a provision
that the operator make an effort to obtain
approval from the surface owner before
entering private lands. This provision does
not require approval before entry, only a
good faith effort to obtain approval.
B. Material to be Filed............ None....................... The information in existing Section III.A.
1. Notice of Staking............... III.F. Notice of Staking... would be incorporated into proposed Sections
2. Application for Permit to Drill. III.E. Required Components of a Complete APD
Package and III.F. Notice of Staking option
is retained.
C. Conferences and Inspections..... III.C.2. Processing........ The requirements for, and scheduling of,
D. Processing Time Frames.......... onsite inspections and the overall processing
timeframes would be incorporated into a new
section on processing. The new section would
consolidate all references to processing
issues into one section.
E. Cultural Resources Clearance.... IV. General Operating Information pertaining to cultural resources,
F. Threatened and Endangered Requirements. threatened and endangered species, watershed
Species Clearance and Other protection, and safety would be moved to
Critical Environmental Concerns. Section IV. General Operating Requirements.
[[Page 43352]]
G. Components of a Complete III.E. Components of a Some of the information contained in the first
Application for Permit to Drill. Complete ADP Package. subsections of existing Section III.G. would
be moved into the Drilling Plan (i.e., item
3.e.) in the proposed Order and duplication
eliminated. The requirements would be
unchanged.
IV. Subsequent Operations.......... VIII. Subsequent Operations/ The rule would delete language in the existing
Sundry Notice. Order that addresses well conversions because
it would be addressed in Section IX. of the
proposed Order.
A. Production Facilities........... None....................... The rule would incorporate information
relative to production facilities into other
sections.
B. Other Operations................ VIII.A. Surface Disturbing The rule would make minor editorial changes
Operations. especially to incorporate FS approval of
subsequent surface disturbing activities.
C. Emergency Repairs............... VIII.B. Emergency Repairs.. There would be no substantive change to these
provisions.
D. Environmental Review............ None....................... The rule would delete this section since the
information would be covered in proposed
Section III.C.2. Processing.
V. Well-Abandonment................ XI. Abandonment............ The rule would divide this section into two
subsections; A) Plugging and B) Reclamation.
The rule would also incorporate additional
information and make clearer the reclamation
subsection.
None............................... V. Rights-of-Way (R/W)-- The rule would add this section to explain
Special Use Authorization when the BLM or FS may require a Right-of-Way
(SUA). or Special Use Authorization and how these
authorizations would be incorporated into the
APD approval process.
VI. Water Well Conversion.......... IX. Well Conversions....... The rule would add a paragraph to address
conversion to a class II injection well and
would clarify the process to convert a well
to a water well.
VII. Privately Owned Surface....... VI. Operating on Lands with This section would change the provisions
A. Federal oil and gas leases...... Private/State Surface and regarding compensation to surface owners to
B. Indian oil and gas cases........ Federal or Indian Oil and that which is required by the authority that
Gas. granted the surface patent. It would
VII. Leases for Indian Oil incorporate the latest policy requiring a
and Gas. statement from the operator regarding whether
or not there is surface owner agreement. If
the operator cannot reach an agreement with
the surface owner, the operator must provide
a bond for the benefit of the surface owner.
The bond must must be sufficient to
compensate the surface owner in an amount
established by the original land patent or
statute authorizing the patent.
VIII. Reports and Activities None.......................
Required After Well Completion.
X. Variances............... The rule would move the the requirements to
submit completion or recompletion reports to
Section IV. General Requirements.
XII. Appeal Procedures.....
The rule would add a new
section to explain how an
operator may request a
variance from a
requirement of the Order
or a waiver, exemption, or
modification of a lease
stipulation and appeals
from denials of those
requests..
The rule would add a new
section to identify the
various appeal processes
and the timeframes
associated with certain FS
appeals. This section
would also clarify that
the incorporation of a FS
approved Surface Use Plan
of Operations into the
approval of an APD is not
subject to protest to BLM
or appeal to IBLA..
----------------------------------------------------------------------------------------------------------------
Discussion of Major Changes
Definition of Complete APD
The most significant change in the proposed rule is that it would
eliminate the term ``Technically and Administratively Complete'' and
replace it with a clear definition of ``Complete APD.'' This new
definition is consistent with the common practice in many field offices
and would require all field offices to adopt the same convention. The
new definition would bring needed consistency to the approval process.
BLM previously considered defining Administratively and Technically
complete separately, but decided to abandon this distinction because of
the difficulty in separating the two concepts and in potential delays
that might be caused in processing APDs in certain circumstances.
The Reform Act requires each APD (except on Indian lands) to be
posted for public review for 30 days. BLM, and the Surface Managing
Entity if appropriate, will post the required parts of the APD
immediately after receiving the application, therefore the 30 days will
commence immediately after the APD or Notice of Staking is filed. No
decision can be made before the end of the 30 day posting period. This
is not a change to existing practice. When possible, a copy will be
posted electronically on the internet.
Under the proposed process, BLM would review the APD package,
consult with FS if appropriate, and within 10
[[Page 43353]]
days of the filing determine if the package contains all the documents
and information sufficient and necessary for processing. If the APD
package did not contain the minimum documentation and information, BLM
or the FS would notify the operator about the deficiencies. If an
incomplete package were to contain sufficient information to continue
processing, BLM or the FS would process the package to the point where
continued processing would either be impractical or impossible without
additional information. Generally, a ``complete'' determination would
follow after the applicant submits any additional material.
Under the proposal, within 10 days of receiving an APD package or a
Notice of Staking, BLM will establish a future date for an onsite
inspection. Under the existing Order, the onsite is held within 15 days
of filing. Under this proposal, BLM and/or the FS would hold the onsite
inspection as soon as practical after filing. Providing more
flexibility in scheduling the onsite inspection will allow BLM to take
into account weather conditions and the availability of the operator
and agency staff, as well as the surface owner if split estate is
involved. It is both agencies' intent to hold the onsite as soon as
possible and normally within 15 days after filing. The agencies
recognize that conducting this event so soon after filing may be
difficult, but we consider it, nevertheless, desirable and necessary.
The proposal makes BLM, rather than the operator, responsible for
inviting surface owners to participate in onsite inspections.
BLM would initiate the review of the APD package as soon as
practical after filing by the operator. Some deficiencies are difficult
to detect and may not be evident until the onsite inspection.
Therefore, a determination of completeness may be delayed beyond 10
days after filing. Under this proposed Order, BLM may notify the
operator of any remaining deficiencies and any other changes necessary
within 7 days after the onsite inspection.
The operator is encouraged to respond to BLM requests for
additional information or to correct deficiencies within 45 days of the
request. Faster response times by the operator will help to expedite
the review process. BLM envisions that the operator may be asked for
additional information on more than one occasion. The technical review
of the APD package is made by many different specialists. In an effort
to expedite the approval process, BLM will not wait to compile a
complete list of all deficiencies in a particular application. Instead,
BLM will provide requests for additional information to the operator as
soon as BLM or FS staff identifies a specific deficiency. Waiting to
notify the operator of separate issues may unnecessarily slow the
approval process.
Under the proposed Order, after the operator provides all requested
information, BLM would determine if the package is complete, that is,
that the data submitted is accurate, complete, meets BLM standards
where applicable, and fully describes the proposed action. A complete
package must contain the information listed in 43 CFR 3162.3-1 and 43
CFR 3164.1, as appropriate, and the information this Order would
require. A complete application does not include a cultural or wildlife
inventory, NEPA documentation, or other materials that are not
requirements of the sections cited above or in this Order. It is the
policy of BLM and FS to begin the NEPA analysis and other inventories
as soon as sufficient information is present to support the work.
It is the intent of BLM and the FS to process APDs within 30 days
after the APD package is complete. However, other regulatory
requirements, such as those in the NEPA, NHPA, and ESA, may result in
further delay. Neither BLM nor the FS can make a final decision on any
APD or Surface Use Plan of Operations until these regulatory
requirements are completed. Compliance in some cases may depend on
actions taken by other agencies over which BLM and the FS have no
administrative control. Therefore, neither BLM nor the FS can commit to
processing all APDs within a given time, but intend to process all APDs
within the minimum time necessary to meet all regulatory requirements.
This is consistent with existing policy and practice. The existing
Order, effective in 1983, says that ``the 30-day time frame for
completion of the APD process may sometimes be exceeded where it is
necessary to prepare an EA. * * *'' BLM did not routinely prepare EAs
for each APD in 1983 because they were categorically excluded from NEPA
analysis until 1992. We now conduct some form of NEPA analysis for all
submitted APD packages. In addition, since the 1983 Order, NHPA and ESA
requirements have become more extensive. With these added regulatory
requirements, it is not realistic for BLM to commit to processing all
APDs in 30 days.
Drilling and Surface Use Plans
This proposal would make specific changes to the drilling and
surface use plans as follows:
The former 8-point Drilling Program (also referred to as the
Subsurface Use Plan) would be replaced with a 9-point Drilling Plan.
This proposal would expand the required description in the existing
Order addressing the anticipated casing program, and add a new
requirement to the Drilling Plan to address the type and amount of
cement operators propose to use in setting each casing string.
We would replace the former 13-point Surface Use Program (or Plan)
with a 12-point Surface Use Plan of Operations. We would remove the
former point 13 of the Surface Use Plan of Operations ``Operator
Certification'' and make it a separate component of the APD package.
This change makes it clear that the Operator Certification covers the
entire APD package and not just the Surface Use Plan of Operations.
The 13-point Surface Use Plan is currently codified in Forest
Service Regulations at 36 CFR 228 Subpart E, Appendix A. Under this
rule, Appendix A would be deleted. Although it would not be codified in
36 CFR, section III.E. of the proposed Order would apply to surface use
operations on NFS lands. That proposed section defines the components
of a complete Surface Use Plan of Operations or Master Development
Plan. The rule would also revise 36 CFR 228.105(a)(1) to direct
operators to submit surface use plans or Master Development Plans in
accordance with the proposed Order, or other applicable onshore orders.
Master Development Plans
This proposal would establish a new approval process for multiple
well proposals called a Master Development Plan. This process would be
used by an operator to submit plans for field development or a multiple
well program in lieu of several individual APDs.
These proposals could be addressed in a single NEPA analysis and
approval. This process would facilitate the consideration of cumulative
effects early in the process and enable broad application of identified
mitigation measures, while minimizing or significantly reducing the
cumulative timeframe for approval. We also anticipate that this
approval will lead to better planning of field development which will
minimize adverse environmental impacts.
The proposed rule envisions the APD as an application for a
proposed action that is impacted by other analytical requirements such
as the NHPA and the ESA. The documents other statutes require are not
part of a complete APD package. This proposal also explains the
approval process for certain subsequent
[[Page 43354]]
well operations. The revised Order would describe the relationship
between the APD package and any application for an associated BLM
Right-of-Way or FS Special Use Authorization that may be required. This
Order would replace the 1983 Order incorporated by the FS into its oil
and gas regulations.
Bonding
This proposal would also clarify that BLM authority to require
additional bond in 43 CFR 3104.5 applies to off-lease facilities
required to further development of the lease, such as the large
impoundments being created in Wyoming for produced water from Federal
and nonfederal coalbed natural gas wells. BLM is obligated by the
Reform Act to require sufficient bond to insure ``the restoration of
any lands or surface waters adversely affected by lease operations
after the abandonment or cessation of oil and gas operations on the
lease'' 30 U.S.C. 226(g). An Assistant Solicitor's memorandum of July
19, 2004, concluded that BLM has the authority to require additional
bond for such facilities and that the current regulation does not limit
BLM to increasing the required amount of an existing bond. Accordingly,
the proposal does not represent a change in the regulatory scheme.
Provisions in the final Order will supersede any inconsistent
provisions of existing regulations, inasmuch as they will constitute a
later exercise of Administrative Procedure Act rulemaking. To the
maximum extent practical, we will identify such inconsistencies and
include conforming amendments to titles 36 or 43, or both, of the CFR
in the final rule.
IV. Procedural Matters
Executive Order 12866, Regulatory Planning and Review
These proposed regulations are not a significant regulatory action
and are not subject to review by Office of Management and Budget (OMB)
under Executive Order 12866. OMB makes the final determination under
the Executive Order. These proposed regulations will not have an effect
of $100 million or more on the economy. They will not adversely affect
in a material way the economy, productivity, competition, jobs, the
environment, public health or safety, or state, local, or tribal
governments or communities. These proposed regulations will not create
a serious inconsistency or otherwise interfere with an action taken or
planned by another agency. These proposed regulations do not alter the
budgetary effects of entitlements, grants, user fees, or loan programs
or the right or obligations of their recipients; nor do they raise
novel legal or policy issues. The revisions this rule would make to the
Order primarily involve changes to BLM and FS administrative processes.
For example, changes to the term ``Administratively and Technically
Complete'' only pertain to the process BLM and the FS would use to
review APD packages and would not have any significant economic impact.
Other changes, such as the proposal to add a provision for the use of a
Master Development Plan, may improve processing and predictability of
operations due to better advance planning of field development.
Clarifying that our authority to require additional bond applies to
off-lease facilities would have no economic impact since BLM already
has the authority under the existing regulatory scheme to require this
bond. Also, as a result of more clear rules, operators will have a
better understanding of BLM and FS requirements, processes, and
timelines leading to reduction in delays in processing and possible
administrative cost savings for BLM, the FS, and operators.
Regulatory Flexibility Act
Congress enacted the Regulatory Flexibility Act of 1980 (RFA), as
amended, 5 U.S.C. 601-612, to ensure that Government regulations do not
unnecessarily or disproportionately burden small entities. The RFA
requires a regulatory flexibility analysis if a rule would have a
significant economic impact, either detrimental or beneficial, on a
substantial number of small entities. For the purposes of this
analysis, we will assume that all entities (all lessees and operators)
that may be impacted by these regulations are small entities.
The rule principally deals with the requirements necessary for the
approval of all proposed oil and gas exploratory, development, or
service wells on all Federal and Indian (except Osage tribe) onshore
oil and gas leases. These changes are not significantly different from
the existing Order and primarily consist of changes to BLM and FS
administrative processes that would not significantly impact operators
or lessees. As a result of more clear rules, operators will have a
better understanding of BLM and FS requirements, processes, and
timelines leading to a reduction in delays in processing and some
administrative cost savings for BLM, the FS, and operators. Therefore,
BLM and the FS have determined that under the RFA this proposed rule
would not have a significant economic impact on a substantial number of
small entities.
The use of best management practices in conditions of approval for
a permit to drill is not new. BLM currently uses them as conditions of
approval and therefore this provision will have no economic impact on
small entities.
The bonding provision in the rule would not impact small entities
since the provisions merely reflect existing authority. As stated
earlier, an Assistant Solicitor's opinion of July 19, 2004, concluded
that BLM has the authority to require additional bond for such
facilities and that the current regulation does not limit BLM to
increasing the required amount of an existing bond. Accordingly, the
proposal does not represent a change in the regulatory scheme.
Small Business Regulatory Enforcement Fairness Act
These proposed regulations are not a ``major rule'' as defined at 5
U.S.C. 804(2). For the reasons stated in the RFA discussion, this
proposed rule would not have an annual effect on the economy greater
than $100 million; it would not result in major cost or price increases
for consumers, industries, government agencies, or regions; and it
would not have significant adverse effects on competition, employment,
investment, productivity, innovation, or the ability of U.S.-based
enterprises to compete with foreign-based enterprises.
Unfunded Mandates Reform Act
These proposed regulations do not impose an unfunded mandate on
state, local, or tribal governments or the private sector of more than
$100 million per year; nor do these proposed regulations have a
significant or unique effect on state, local, or tribal governments or
the private sector. This proposed rule would primarily involve changes
to BLM's and the FS's administrative processes that would not have any
significant effect monetarily, or otherwise, on the entities listed.
Therefore, BLM and the FS are not required to prepare a statement
containing the information required by the Unfunded Mandates Reform Act
(2 U.S.C. 1531 et seq.).
Executive Order 12630, Governmental Actions and Interference With
Constitutionally Protected Property Rights (Takings)
The proposed rule does not represent a government action capable of
interfering with constitutionally protected property rights. This
proposed rule has no potential to effect property rights as the changes
it would make to
[[Page 43355]]
existing procedures primarily involve changes to BLM's and the FS's
administrative processes. Therefore, the Department of the Interior and
the Department of Agriculture have determined that the rule would not
cause a taking of private property or require further discussion of
takings implications under this Executive Order.
Executive Order 13132, Federalism
The proposed rule will not have a substantial direct effect on the
states, on the relationship between the national government and the
states, or on the distribution of power and responsibilities among the
various levels of government. The proposal will not have any effect on
any of the items listed. As stated above, the rule principally deals
with the requirements necessary for the approval of all proposed oil
and gas exploratory, development, or service wells on all Federal and
Indian (except Osage tribe) onshore oil and gas leases. In other words,
the rule affects the relationship between operators, lessees, and BLM
and the FS and would not impact states. Therefore, in accordance with
Executive Order 13132, BLM has determined that this proposed rule does
not have sufficient Federalism implications to warrant preparation of a
Federalism Assessment.
Executive Order 13175, Consultation and Coordination With Indian Tribal
Governments
BLM approves proposed operations on all Indian (except Osage)
onshore oil and gas leases and agreements. BLM has begun consultation
on the proposed revisions to the Order and will continue to consult
with Tribes during the formal comment period on the rule.
Executive Order 12988, Civil Justice Reform
Under Executive Order 12988, the Office of the Solicitor has
determined that this proposed rule would not unduly burden the judicial
system and that it meets the requirements of sections 3(a) and 3(b)(2)
of the Order. We have reviewed these regulations to eliminate drafting
errors and ambiguity. They have been written to minimize litigation,
provide clear legal standards for affected conduct rather than general
standards, and promote simplification. Drafting the regulations in
clear language and working closely with legal counsel assists in all of
these areas.
Paperwork Reduction Act
These regulations contain information collection requirements. As
required by the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et
seq.), we submitted a copy of the proposed information collection
requirements to the OMB for review. The OMB approved the information
collection requirements under Control Number 1004-0137, which expires
on March 31, 2007.
National Environmental Policy Act
BLM and the FS have prepared an environmental assessment (EA) and
have found that the proposed rule would not constitute a major Federal
action significantly affecting the quality of the human environment
under section 102(2)(C) of the NEPA, 42 U.S.C. 4332(2)(C). A detailed
statement under NEPA is not required. BLM has placed the EA and the
Finding of No Significant Impact on file in the BLM Administrative
Record at the address specified in the ADDRESSES section.
The proposed revisions to Order 1 would not impact the environment
significantly. For the most part, the revisions would involve changes
to BLM's and the FS's administrative processes. For example, replacing
the term ``Administratively and Technically Complete'' with the term
``Complete APD'' only changes the process BLM would use to review APD
packages and would not have any impact on the environment whatsoever.
Other changes, such as the proposal to add provisions for the use of a
Master Development Plan, may actually provide improved environmental
protection due to better advance planning of field development. The use
of best management practices can lead to reduced environmental damage.
Also, the procedural and clarifying changes would have no meaningful
impact of any kind on the physical or economic environment. Any
environmental effects of APDs on Federal lands are analyzed on a case-
by-case basis.
Executive Order 13211, Actions Concerning Regulations That
Significantly Affect Energy Supply, Distribution, or Use
In accordance with Executive Order 13211, BLM has determined that
the proposed rule will not have substantial direct effects on the
energy supply, distribution or use, including a shortfall in supply or
price increase. This rule would clarify the administrative processes
involved in approving an APD and more clearly lay out the timeline for
processing applications. It is not clear to what extent clarification
of the rules will save BLM, the FS, or operators administrative cost,
but we anticipate that the cost savings will be minimal, as will any
direct effects on the energy supply, distribution or use.
Clarity of the Regulations
Executive Order 12866 requires each agency to write regulations
that are simple and easy to understand. We invite your comments on how
to make these proposed regulations easier to understand, including
answers to questions such as the following:
1. Are the requirements in the proposed regulations clearly stated?
2. Do the proposed regulations contain technical language or jargon
that interferes with their clarity?
3. Does the format of the proposed regulations (grouping and order
of sections, use of headings, paragraphing, etc.) aid or reduce their
clarity?
4. Would the regulations be easier to understand if they were
divided into more (but shorter) sections?
5. Is the description of the proposed regulations in the
SUPPLEMENTARY INFORMATION section of this preamble helpful in
understanding the proposed regulations? How could this description be
more helpful in making the proposed regulations easier to understand?
Please send any comments you have on the clarity of the regulations
to the address specified in the ADDRESSES section.
Authors
The principal authors of this rule are: James Burd of the BLM
Washington Office; Bo Brown of the BLM Alaska State Office; Brian
Pruiett of the BLM Buffalo, Wyoming Field Office; Gary Stephens of the
BLM New Mexico State Office; Hank Szymanski of the BLM Colorado State
Office; Howard Clevinger of the BLM Vernal, Utah Field Office; Roy
Swalling of the Montana State Office; and Barry Burkhardt of the FS
Intermountain Regional Office, Ogden, Utah, and assisted by the staff
of BLM's Regulatory Affairs Group and the Department of the Interior's
Office of the Solicitor.
List of Subjects
36 CFR Part 228
Environmental protection; Mines; National forests; Oil and gas
exploration; Public lands-mineral resources; Public lands-rights-of-
way; Reporting and recordkeeping requirements; Surety bonds; Wilderness
areas.
43 CFR part 3160
Administrative practice and procedure; Government contracts;
Indians-lands; Mineral royalties; Oil and gas exploration; Penalties;
Public lands-
[[Page 43356]]
mineral resources; Reporting and recordkeeping requirements.
36 CFR Chapter II
For the reasons set out in the joint preamble, the FS proposes to
amend 36 CFR part 228 as follows:
PART 228--MINERALS
1. The authority citation for part 228 continues to read as
follows:
Authority: 30 Stat. 35 and 36, as amended (16 U.S.C. 478, 551);
41 Stat. 437, as amended, sec. 5102(d), 101 Stat. 1330-256 (30
U.S.C. 226); 61 Stat. 681, as amended (30 U.S.C. 601); 61 Stat. 914,
as amended (30 U.S.C. 352); 69 Stat. 368, as amended (30 U.S.C.
611); and 94 Stat. 2400.
2. Revise Sec. 228.105(a)(1) to read as follows:
Sec. 228.105 Issuance of onshore orders and notices to lessees.
(a) * * *
(1) Operators shall submit surface use plans of operations or
Master Development Plans in accordance with the applicable Onshore Oil
and Gas Order. Approval of a Master Development Plan constitutes
approval of any surface use plan of operations submitted as a part of,
or consistent with, the approved Master Development Plan.
* * * * *
3. Revise Sec. 228.107(c) to read as follows:
Sec. 228.107 Review of surface use plan of operations.
* * * * *
(c) The authorized Forest officer will give public notice of the
decision on a plan and include in that notice whether the decision may
be appealed under the applicable Forest Service appeal procedures.
* * * * *
Appendix A to Subpart E of Part 228 [Removed]
4. Remove Appendix A to Subpart E of Part 228.
Dated: August 26, 2004.
Sally D. Collins,
Acting Chief, USDA--Forest Service.
Editorial Note: This document was received at the Office of the
Federal Register on July 13, 2005.
43 CFR Chapter II
For the reasons set out in the joint preamble, the Bureau of Land
Management proposes to amend 43 CFR part 3160 as follows:
PART 3160--ONSHORE OIL AND GAS OPERATIONS
1. The authority citation for part 3160 continues to read as
follows:
Authority: 25 U.S.C. 396d and 2107; 30 U.S.C. 189, 306, 359, and
1751; and 43 U.S.C. 1732(b), 1733, and 1740.
2. Amend Sec. 3164.1(b) by revising the first entry in the chart
as follows:
Sec. 3164.1 Onshore Oil and Gas Orders.
* * * * *
(b) * * *
----------------------------------------------------------------------------------------------------------------
Federal
Order No. Subject Effective date Register Supersedes
reference
----------------------------------------------------------------------------------------------------------------
1............................ Approval of operations......... [insert 60 days 70 FR * * *... NTL-6
after date of
publication of
final rule].
----------------------------------------------------------------------------------------------------------------
* * * * *
Appendix--Text of Oil and Gas Onshore Order
Note --This appendix will not appear in the BLM regulations in
43 Code of Federal Regulations.
Dated: August 26, 2004.
Rebecca W. Watson,
Assistant Secretary, Land and Minerals Management.
Editorial Note: This document was received at the Office of the
Federal Register on July 13, 2005.
The following Order would be implemented by the BLM and FS, but
will not be codified in the Code of Federal Regulations.
Onshore Oil and Gas Order Number 1
Approval of Operations
I. Introduction
A. Authority
B. Purpose
C. Scope
II. Definitions
III. Application for Permit to Drill (APD)
A. Where to File
B. Early Notification
C. APD Posting and Processing
D. Valid Period of Approved APD
E. Components of a Complete APD Package
F. Notice of Staking Option
G. Approval of APDs
IV. General Operating Requirements
V. Rights-of-Way and Special Use Authorizations
VI. Operating on Lands with Private/State Surface and Federal or
Indian Oil and Gas
VII. Leases for Indian Oil and Gas
A. Approval of Operations
B. Surface Use
VIII. Subsequent Operations and Sundry Notices
A. Surface Disturbing Operations
B. Emergency Repairs
IX. Well Conversions
X. Variances
XI. Abandonment
A. Plugging
B. Reclamation
XII. Appeal Procedures
Attachment I--Sample Format for Notice of Staking
Onshore Oil and Gas Order Number 1
Approval of Operations
I. Introduction
A. Authority
The Secretaries of the Interior and Agriculture have authority
under various Federal and Indian mineral leasing laws, as defined in
30 U.S.C. 1702, to manage oil and gas operations. The Secretary of
the Interior has delegated this authority to the BLM, which has
issued onshore oil and gas operating regulations codified at part
3160 of Title 43 of the Code of Federal Regulations. The operating
regulations at 43 CFR 3164.1 authorize BLM's Director to issue
Onshore Oil and Gas Orders when necessary to implement and
supplement the operating regulations. The section also states that
all such Orders are binding on the operator(s) of Federal and Indian
onshore oil and gas leases (except the Osage Tribe). For leases on
Indian lands, the delegation to BLM appears at 25 CFR parts 211,
212, 213, 225, and 227.
The Secretary of Agriculture has authority under the Federal
Onshore Oil and Gas Leasing Reform Act of 1987 (Pub. L. 100-203)
(Leasing Reform Act) to regulate surface disturbing activities on
NFS lands. This authority has been delegated to the FS. Its
regulatory authority is at Title 36 CFR, Chapter II, including, but
not limited to, part 228 Subpart E, part 251 Subpart B, and part
261. Section 228.105 of 36 CFR authorizes the Chief of the FS to
issue, or cosign with the Director, BLM, Onshore Oil and Gas Orders
necessary to implement and supplement the operating regulations. The
FS is responsible only for approving and administering surface
disturbing activities on NFS lands and appeals related to FS
decisions or approvals.
B. Purpose
The purpose of this Order is to state the application
requirements for the approval of all proposed oil and gas and
service wells, certain subsequent well operations, and abandonment.
C. Scope
This Order applies to all onshore leases of Federal and Indian
oil and gas (except those of the Osage Tribe), and Federally-
approved
[[Page 43357]]
unit or communitization agreements. It also applies to Indian
Mineral Development Act agreements. References in this Order to
leases means unit or communitization agreements, as applicable.
II. Definitions
As used in this Order, the following definitions apply:
Blooie Line means a discharge line used in conjunction with a
rotating head in drilling operations when air or gas is used as the
circulating medium.
Complete APD means that BLM and the Surface Managing Entity, if
appropriate, have determined that the information in the APD package
is accurate and addresses all BLM requirements. The APD package must
contain:
A completed Form 3160-3 (Application for Permit to
Drill or Reenter) (see 43 CFR 3162.3-1(d)),
A well plat certified by a registered surveyor with a
surveyor's original stamp (see Section III.E.1. of this Order),
A Drilling Plan (see 43 CFR 3162.3-1(d) and Section
III.E.2. of this Order),
A Surface Use Plan of Operations (see 43 CFR 3162.3-
1(d) and Section III.E.3. of this Order),
Evidence of bond coverage (see 43 CFR 3162.3-1(d) and
Section III.E.5. of this Order),
Operator certification (see Section III.E.6. of this
Order),
An original signature, which may be an electronic
signature that meets BLM standards (see Section III.E.6. of this
Order), and
Other information that may be required by Order or
Notice (see 43 CFR 3162.3-1(d)(4)).
All maps and plats required as part of the APD must be submitted
in both hard copy and geospatial database formats. BLM or the
Surface Managing Entity, as appropriate, will review the APD package
and determine that all information in the drilling plan, the surface
use plan of operations, bonding requirements, and other information
that BLM may require (43 CFR 3162.3-1(d)(4)), including the well
location plat and geospatial databases, completely describe the
proposed action. A complete APD is not defined to include cultural,
wildlife, or other inventories that may be required or an
environmental assessment or environmental impact statement that may
be required by the NEPA.
Condition of Approval (COA) means a site-specific requirement
included in an approved APD or Sundry Notice that may limit or amend
the specific actions proposed by the operator. Conditions of
Approval minimize, mitigate, or prevent impacts to public lands or
other resources. Best management practices may be incorporated as a
Condition of Approval.
Days means all calendar days including holidays.
Drilling Plan means those documents an operator submits as part
of an APD package or as a supplement to an approved plan of
operations detailing the proposed drilling operations and containing
the information required by 43 CFR 3160 and applicable Orders.
Emergency Repairs means actions necessary to correct an
unforeseen problem that could cause or threaten immediate
substantial adverse impact on public health and safety or the
environment.
Geospatial Database means a set of georeferenced computer data
that contains both spatial and attribute data. The spatial data
defines the geometry of the object and the attribute data defines
all other characteristics.
Indian lands means any lands or interest in lands of an Indian
tribe or an Indian allottee held in trust by the United States or
which is subject to Federal restriction against alienation.
Indian Oil and Gas means any oil and gas interest of an Indian
tribe or on allotted lands where the interest is held in trust by
the United States or is subject to Federal restrictions against
alienation. It does not include minerals subject to the provisions
of section 3 of the Act of June 28, 1906 (34 Stat. 539), but does
include oil and gas on lands administered by the United States under
section 14(g) of Public Law 92-203, as amended.
Master Development Plan means information common to multiple
planned wells, including drilling plans, surface use plans of
operations, and plans for future production.
National Forest System Lands means those Federal lands
administered by the U.S. Forest Service, such as the National
Forests and the National Grasslands.
Onsite Inspection means an inspection of the proposed drill pad,
access road, flowline route, and any associated Right-of-Way or
Special Use Authorization needed for support facilities, conducted
before the approval of the APD or Surface Use Plan of Operations and
construction activities.
Reclamation means returning disturbed land as near to its
predisturbed condition as is reasonably practical.
Split Estate means lands where the surface is owned by an entity
or person other than the owner of the Federal or Indian oil and gas.
Surface Managing Entity means any Federal or state agency having
jurisdiction over the surface, or a private owner of the surface,
overlying Federal or Indian oil and gas.
Variance means an approved alternative to a provision or
standard of an Order, Notice to Lessee, or other requirement (see 43
CFR 3101.1-4).
III. Application for Permit To Drill (APD)
An Application for Permit to Drill or Reenter (APD), on Form
3160-3, is required for each proposed well, and for reentry and
deepening of existing wells (including disposal and service wells),
to develop an onshore lease for Federal or Indian oil and gas.
A. Where To File
The operator must file an APD, Sundry Notice, or other required
document in the BLM field office having jurisdiction over the lands
described in the application. As an alternative to filing in a local
BLM office, an operator may file an APD using BLM's electronic
commerce application for oil and gas permitting and reporting.
Contact the local BLM field office for details before using the
electronic commerce application.
B. Early Notification
The operator should contact BLM and any applicable Surface
Managing Entity, including all private surface owners, to request an
initial planning conference as soon as the operator has identified a
potential area of development. Early notification is voluntary, but
it allows the involved Surface Managing Entity to apprise the
prospective operator of any unusual conditions on the lease area.
Early notification also provides both the Surface Managing Entity
and the prospective operator with the earliest possible
identification of time-sensitive requirements and determination of
potential areas of conflict. The prospective operator should have a
map of the proposed project available for Surface Managing Entity
review to determine if a cultural or wildlife inventory or other
information may be required.
C. APD Posting and Processing
1. Posting
The Mineral Leasing Act, 30 U.S.C. 181 et seq., as amended,
requires BLM and the Federal Surface Managing Entity, if other than
BLM, to provide at least 30 days public notice before BLM or the FS
may approve an APD or Master Development Plan on a Federal oil and
gas lease. Posting is not required for Indian leases.
BLM will post the APD notice in an area of the BLM field office
having jurisdiction that is readily accessible to the public and,
when possible, electronically on the internet. If the surface is
managed by a Federal agency other than BLM, that agency also is
required to post the notice for 30 days. The posted notice is for
informational purposes only and is not an appealable decision. The
purpose of the posting is to give any interested party notification
that a Federal approval of mineral development has been requested.
BLM or the FS will not post confidential information.
If the operator subsequently moves the proposed location of the
well, reposting of the proposal for an additional 30-day period may
be necessary if BLM or the FS determines that the change is
significant.
2. Processing
The timeframes established in this subsection apply to both
individual APDs and to the multiple APDs included in Master
Development Plans.
(a) Within 10 days of receiving an APD package, BLM, in
consultation with the FS, if appropriate, will notify the operator
as to whether or not the APD is complete and will request additional
information and correction of any deficiencies if necessary. If
there is enough information to begin processing the APD package, BLM
and the FS will do so up to the point that missing information or
uncorrected deficiencies renders further processing impractical or
impossible. The operator has 45 days after receiving notice from BLM
to provide any additional information requested or the APD may be
returned to the operator.
[[Page 43358]]
(b) Within 10 days of receiving the APD package, BLM, in
coordination with the operator and Surface Managing Entity
(including, in the case of split estate, the private surface
owners), if appropriate, will schedule a future date for the onsite
inspection unless the onsite inspection was held as part of the
Notice of Staking (see Section III.F. of this Order). The onsite
inspection will be held as soon as practicable based on schedules
and weather conditions. Within 7 days of the onsite inspection, BLM,
and the FS if app