Proposed Generic Communication; Impact of Potentially Degraded Hemyc and Mt Fire Barriers on Compliance With Approved Fire Protection Programs, 42596-42602 [E5-3941]
Download as PDF
42596
Federal Register / Vol. 70, No. 141 / Monday, July 25, 2005 / Notices
schedule electronically, please send an
electronic message to dkw@nrc.gov.
Dated: July 20, 2005.
Sandy Joosten,
Office of the Secretary.
[FR Doc. 05–14674 Filed 7–21–05; 10:30 am]
BILLING CODE 7590–01–M
NUCLEAR REGULATORY
COMMISSION
Emergency Preparedness and
Response Actions for Security Based
Events
Nuclear Regulatory
Commission.
ACTION: Notice of issuance.
AGENCY:
SUMMARY: The U.S. Nuclear Regulatory
Commission (NRC) has issued Bulletin
(BL) 2005–02 to all holders of operating
licenses for nuclear power reactors,
except those who have permanently
ceased operation and have certified that
fuel has been removed from the reactor
vessel. The U.S. Nuclear Regulatory
Commission (NRC) is issuing this
bulletin to:
1. Notify addressees about NRC staff’s
need for information associated with
emergency preparedness (EP) for
security-based events at a nuclear power
plant;
2. Request addressees provide
information to the NRC within 30 days
of this bulletin regarding actions taken
or planned to be taken in the areas
discussed below:
a. Security-based emergency
classification levels and emergency
action levels (EALs), emergency
response organization augmentation for
security-based events, and a securitybased EP drill and exercise program,
b. Accelerated NRC notifications and
onsite protective measures;
3. If actions regarding the topics
covered in this bulletin have not been
taken, the addressees are requested to
provide a schedule detailing expected
completion dates for all pending
activities; and
4. Require addressees to provide a
written response to the NRC in
accordance with 10 CFR 50.54(f).
This Federal Register notice is
available through the NRC’s
Agencywide Documents Access and
Management System (ADAMS) under
accession number ML051990027.
DATES: The bulletin was issued on July
18, 2005.
ADDRESSES: Not applicable.
FOR FURTHER INFORMATION, CONTACT:
Michael Norris at 301–415–4098 or by email mbn@nrc.gov, Greg Casto at 301–
VerDate jul<14>2003
14:21 Jul 22, 2005
Jkt 205001
415–4072 or by e-mail gac@nrc.gov, or
Douglas Pickett at 301–415–1364 or email dvp1@nrc.gov.
SUPPLEMENTARY INFORMATION: NRC
Bulletin 2005–02 may be examined,
and/or copied for a fee, at the NRC’s
Public Document Room at One White
Flint North, 11555 Rockville Pike (first
floor), Rockville, Maryland. Publicly
available records will be accessible
electronically from the Agencywide
Documents Access and Management
System (ADAMS) Public Electronic
Reading Room on the Internet at the
NRC Web site, https://www.nrc.gov/NRC/
ADAMS/. The ADAMS
number for the bulletin is
ML051740058.
If you do not have access to ADAMS
or if you have problems in accessing the
documents in ADAMS, contact the NRC
Public Document Room (PDR) reference
staff at 1–800–397–4209 or 301–415–
4737 or by e-mail to pdr@nrc.gov.
Dated at Rockville, Maryland, this 18th day
of July 2005.
For the Nuclear Regulatory Commission.
Patrick L. Hiland,
Chief, Reactor Operations Branch, Division
of Inspection Program Management, Office
of Nuclear Reactor Regulation.
[FR Doc. E5–3943 Filed 7–22–05; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
Proposed Generic Communication;
Impact of Potentially Degraded Hemyc
and Mt Fire Barriers on Compliance
With Approved Fire Protection
Programs
Nuclear Regulatory
Commission.
ACTION: Notice of opportunity for public
comment.
AGENCY:
SUMMARY: The U.S. Nuclear Regulatory
Commission (NRC) is proposing to issue
a generic letter (GL) to:
(1) Request that addressees evaluate
their facilities to confirm compliance
with the existing applicable regulatory
requirements in light of the information
provided in this generic letter and, if
appropriate, take additional actions.
Specifically, although Hemyc and MT
fire barriers in nuclear power plants
(NPPs) may be relied on to protect
electrical and instrumentation cables
and equipment that provide safe
shutdown capability during a fire,
recent NRC testing has revealed that
both materials failed to provide the
protective function intended for
compliance with existing regulations,
for the configurations tested using the
PO 00000
Frm 00066
Fmt 4703
Sfmt 4703
acceptance criteria in Generic Letter
(GL) 86–10, Supplement 1, ‘‘Fire
Endurance Test Acceptance Criteria for
Fire Barrier Systems Used To Separate
Redundant Safe Shutdown Trains
Within the Same Fire Area.’’
(2) Require that addressees submit a
written response to the NRC in
accordance with NRC regulations in
Title 10 of the Code of Federal
Regulations, Section 50.54(f) (10 CFR
50.54(f)).
This Federal Register notice is
available through the NRC’s
Agencywide Documents Access and
Management System (ADAMS) under
accession number ML051540292.
DATES: Comment period expires
September 23, 2005. Comments
submitted after this date will be
considered if it is practical to do so, but
assurance of consideration cannot be
given except for comments received on
or before this date.
ADDRESSES: Submit written comments
to the Chief, Rules and Directives
Branch, Division of Administrative
Services, Office of Administration, U.S.
Nuclear Regulatory Commission, Mail
Stop T6–D59, Washington, DC 20555–
0001, and cite the publication date and
page number of this Federal Register
notice. Written comments may also be
delivered to NRC Headquarters, 11545
Rockville Pike (Room T–6D59),
Rockville, Maryland, between 7:30 a.m.
and 4:15 p.m. on Federal workdays.
FOR FURTHER INFORMATION, CONTACT:
Angie Lavretta at (301) 415–3285 or by
e-mail axl3@nrc.gov, Daniel Frumkin at
(301) 415–2280 or e-mail dxf1@nrc.gov,
or Chandu Patel at (301) 415–3025 or by
e-mail at cpp@nrc.gov.
SUPPLEMENTARY INFORMATION:
NRC Generic Letter 2005–XX
Impact of Potentially Degraded Hemyc
and Mt Fire Barriers on Compliance
With Approved Fire Protection
Programs
Addressees
All holders of operating licenses for
light-water nuclear power reactors,
except those who have ceased
operations and have certified that fuel
has been permanently removed from the
reactor vessel.
Purpose
The U.S. Nuclear Regulatory
Commission (NRC) is issuing this
generic letter to:
(3) Request that addressees evaluate
their facilities to confirm compliance
with the existing applicable regulatory
requirements in light of the information
provided in this generic letter and, if
E:\FR\FM\25JYN1.SGM
25JYN1
Federal Register / Vol. 70, No. 141 / Monday, July 25, 2005 / Notices
appropriate, take additional actions.
Specifically, although Hemyc and MT
fire barriers in nuclear power plants
(NPPs) may be relied on to protect
electrical and instrumentation cables
and equipment that provide safe
shutdown capability during a fire,
recent NRC testing has revealed that
both materials failed to provide the
protective function intended for
compliance with existing regulations,
for the configurations tested using the
acceptance criteria in Generic Letter
(GL) 86–10, Supplement 1, ‘‘Fire
Endurance Test Acceptance Criteria for
Fire Barrier Systems Used To Separate
Redundant Safe Shutdown Trains
Within the Same Fire Area.’’
(4) Require that addressees submit a
written response to the NRC in
accordance with NRC regulations in
Title 10 of the Code of Federal
Regulations, Section 50.54(f) (10 CFR
50.54(f)).
Background
NRC’s concern with the performance
of fire barriers at nuclear power plants
began with the failure of Thermo-Lag to
pass performance tests in October 1989
at Southwest Research Institute. The
tests were done for the Gulf States
Utilities Company after visually
observing degradation of Thermo-Lag at
River Bend Station. In June and August
1992, two sets of full-scale fire
endurance tests on Thermo-Lag were
conducted at Omega Point Laboratories
in San Antonio, Texas, by Texas
Utilities Electric Company for
Comanche Peak Steam Electric Station,
with similar results. In July 1992, the
NRC sponsored a series of small-scale
fire endurance tests at the National
Institute of Standards and Technology.
The results again indicated that 1-hourand 3-hour-rated Thermo-Lag barrier
material failed to consistently provide
its intended protective function.
On August 6, 1991, the NRC issued
Information Notice (IN) 91–47, ‘‘Failure
of Thermo-Lag Fire Barrier Material To
Pass Fire Endurance Test,’’ the first in
a series of INs issued between 1991 and
1995 on performance test failures and
installation deficiencies related to
Thermo-Lag 330 fire barrier systems.
Because of questions about the ability
of 1-hour- and 3-hour-rated Thermo-Lag
fire barrier material to perform its
specified function and because of the
widespread use of Thermo-Lag in the
nuclear industry, the NRC issued the
following generic communications to
inform licensees of the Thermo-Lag test
results and to request that licensees
implement appropriate compensatory
measures and develop plans to resolve
any noncompliances with 10 CFR 50.48:
VerDate jul<14>2003
14:21 Jul 22, 2005
Jkt 205001
• Bulletin 92–01, ‘‘Failure of ThermoLag 330 Fire Barrier System To Maintain
Cabling in Wide Cable Trays and Small
Conduits Free From Fire Damage,’’ June
24, 1992.
• Bulletin 92–01, Supplement 1,
‘‘Failure of Thermo-Lag 330 Fire Barrier
System To Perform its Specified Fire
Endurance Function,’’ August 28, 1992.
• GL 92–08, ‘‘Thermo-Lag 330–1 Fire
Barriers,’’ December 17, 1992.
• Supplement 1 to GL 86–10, ‘‘Fire
Endurance Test Acceptance Criteria for
Fire Barrier Systems Used To Separate
Redundant Safe Shutdown Trains
Within the Same Fire Area,’’ March 25,
1994. GL 92–08 specifically asked
licensees to review any existing fire
barrier configurations credited for 10
CFR 50.48 compliance in light of the
concerns with Thermo-Lag 330–1 fire
barriers.
In response, the licensees reviewed
their fire protection safe shutdown
plans to determine if corrective actions
were needed. Some licensees had made
conservative commitments and installed
Thermo-Lag in locations where it was
not needed to satisfy NRC requirements,
therefore no corrective actions were
required. Where fire barrier materials
were required, licensees took one or a
combination of the following corrective
actions:
• Rerouted cables through other fire
areas so that redundant safe shutdown
trains were not located in the same fire
area.
• Replaced Thermo-Lag, or the
affected material, with an alternative
rated fire barrier material.
• Upgraded the installed fire barriers
to a rated configuration.
• Concluded that certain Thermo-Lag
barriers were no longer required.
Subsequently, deficiencies were also
identified in other fire barrier materials.
In 1993, for example, Kaowool installed
as a 1-hour-rated fire barrier was found
to be unable to pass circuit integrity
tests. In response, the NRC reassessed
previous staff reviews of Kaowool fire
barriers and informed the industry and
the Commission of the potential failure
of Kaowool to perform as intended and
suggested additional testing of Kaowool
(SECY–99–204; ADAMS Accession No.
ML992810028). To resolve the issue, the
industry took voluntary corrective
actions. In August 1993, the Nuclear
Energy Institute (NEI) formed a Fire
Barrier Review Ad Hoc Advisory
Committee to address the adequacy of
fire barrier materials other than ThermoLag. The Committee performed reviews
of the original testing of the fire barrier,
Hemyc (performed in the early 1980s in
Spain), and concluded that Hemyc was
differently constructed than Thermo-Lag
PO 00000
Frm 00067
Fmt 4703
Sfmt 4703
42597
330–1, and therefore was not subject to
the same failure modes as Thermo-Lag
330–1. In May 1994, this review was
documented in the NEI report,
‘‘Documentation of the Adequacy of Fire
Barrier Materials in Raceway
`
Applications Vis-a-vis Failure
Characteristics Inherent to the ThermoLag 330–1.’’
However, beginning in late 1999,
three plant-specific findings by the staff
raised concerns about the performance
of Hemyc and MT fire barriers.
• In November 1999, during an
inspection at Shearon Harris Nuclear
Power Plant (IR 50–400/99–13; ADAMS
Accession No. ML003685341), the
inspection team noted that the
acceptance of the Hemyc and MT fire
barrier materials used was based on
American Nuclear Insurers (ANI)
Bulletin No. 5 test acceptance criteria,
even though the ANI test methodology
clearly stated that the tests were done
for insurance purposes only and were
not intended to be considered the
equivalent of fire barrier endurance tests
for fire barrier ratings.
• In October and November 2000,
during an inspection at McGuire 1 and
2 (IR 50–369/00–09, 50–370/00–09;
ADAMS Accession No. ML003778709),
the inspection team noted that the
licensee was unable to provide
documentation demonstrating
protection by Hemyc fire barrier
material used to separate safe shutdown
functions for two trains within a single
fire area.
• In September 2000, during an
inspection at Waterford 3 (IR 50–382/
00–07; ADAMS Accession No.
ML003773900), the inspectors noted
that the Hemyc materials were installed
in configurations which typically would
not be bounded by the existing tests.
In June 2001, the NRC initiated
confirmatory fire tests in response to
Task Interface Agreement 99–028
(ADAMS Accession No. ML003736721),
after concluding that existing testing
was likely insufficient to qualify Hemyc
or MT as rated fire barriers. The NRC
tests were based on ASTM E119
Standard time-temperature conditions
and the current NRC guidance in GL 86–
10, Supplement 1, for typical Hemyc
and MT installations used in U.S. NPPs.
The test results indicated that Hemyc
and MT fire barriers did not pass the GL
86–10, Supplement 1, criteria to achieve
a 1-hour fire rating for Hemyc or a 3hour fire rating for MT, for the
configuration tested. On April 1, 2005,
the NRC issued IN 2005–07, ‘‘Results of
Hemyc Electrical Raceway Fire Barrier
System Full Scale Fire Testing.’’ This IN
describes the results of the NRCsponsored confirmatory testing of
E:\FR\FM\25JYN1.SGM
25JYN1
42598
Federal Register / Vol. 70, No. 141 / Monday, July 25, 2005 / Notices
Hemyc. However, the staff recognized
that additional evaluations would be
needed to determine whether regulatory
compliance exists in light of the
concerns identified in IN 05–07.
On April 29, 2005, the staff held a
public meeting with licensees and
interested members of the public to
discuss the Hemyc and MT test results
and the staff’s intentions to take prompt
additional regulatory action to ensure
that appropriate measures are under
way for compliance with 10 CFR 50.48
requirements at affected plants. This
generic letter is the follow-on to IN 05–
07.
The NRC has established a Web page
to keep the public informed of the status
of the Hemyc/MT fire barrier issue at
https://www.nrc.gov/reactors/operating/
ops-experience/fire-protection/
technical-issues.html#fire.
This page provides links to
information on related fire protection
issues, along with documentation of
NRC interactions with industry
(including generic communications,
industry submittals, meeting notices,
presentation materials, and meeting
summaries). The NRC will continue to
update this Web page as new
information becomes available.
Hemyc Construction—Hemyc fire
barrier material consists of mats of 2inch Kaowool ceramic fiber insulation
inside an outer covering of Refrasil 1
high-temperature fabric. The mats are
custom-sized for the electrical raceway
and machine-stitched to produce the
factory mats. Hemyc mats, which are
installed over a metal frame to provide
the 2-inch air gap design, are identical
except that 11⁄2-inch Kaowool is used
instead of the 2-inch material.
MT Construction—MT used with
conduits has four layers. The first layer,
closest to the conduit, is 1 inch of
Kaowool ceramic fiber blanket wrapped
in a fiberglass fabric. The second layer
is a 2-mil sheet of stainless steel. The
third layer is a hydrate packet. This
packet is made by stitching together
packets of aluminum trihydrate in a
fiberglass-coated fabric. The fourth and
outermost layer is a 11⁄2-inch Kaowool
blanket wrapped in Refrasil. The
configuration is slightly different for air
drops and structural supports. Air drops
use a 3-inch blanket of Kaowool as the
inner layer. Structural supports do not
have the hydrating packet layer or the
stainless steel sheet.
1 Refrasil was used during NRC tests. Siltemp and
Refrasil were tested by the NRC and determined to
be essentially equivalent (ADAMS Accession No.
ML051190055).
VerDate jul<14>2003
14:21 Jul 22, 2005
Jkt 205001
Discussion
Hemyc and MT, manufactured by
Promatec, Inc, were installed at NPPs to
protect circuits and instrumentation
cables in order to meet regulatory
requirements and in accordance with
plant-specific commitments. The NRC
conducted confirmatory testing of both
materials at the Omega Point
Laboratories in San Antonio, Texas. The
test results indicated that when tested to
GL 86–10, Supplement 1, criteria,
neither the Hemyc nor the MT fire
barrier system would provide its rated
fire barrier protection.
The staff noted at least three failure
modes in the limited test program. Two
failure modes resulted from shrinkage of
outer material (Refrasil), causing the
barrier to open and exposing the interior
surfaces or layers to the fire. The third
failure mode resulted from failure to
adequately protect steel members
intruding into the barrier. The standard
used by some utilities required
protection of 3 inches of intruding steel
for the Hemyc 1-hour fire barrier and 18
inches of intruding steel for the MT 3hour fire barrier. The test results
indicated that additional protection of
intruding steel was required to achieve
a 1-hour or 3-hour fire rating. Based on
these test results, the NRC is concerned
that the Hemyc and MT fire barriers
may not provide the level of fire
endurance intended by licensees and
that licensees that use Hemyc or MT
may not be complying with NRC
regulations. Section 50.48 of 10 CFR
part 50 requires that each operating NPP
have a fire protection plan that satisfies
General Design Criterion (GDC) 3, ‘‘Fire
Protection,’’ of 10 CFR part 50,
Appendix A, ‘‘General Design Criteria
for Nuclear Power Plants.’’ The NRC
Regulation in 10 CFR 50.48 states that
each operating nuclear power plant
(licensed before or after issuance of GDC
3) must have a fire protection plan that
satisfies Criterion 3 of Appendix A. GDC
3 requires that structures, systems, and
components important to safety be
designed and located to minimize, in a
manner consistent with other
requirements, the probability and effect
of fires and explosions. Fire protection
features required to satisfy 10 CFR 50.48
include features to limit fire damage to
structures, systems or components
important to safety so that the capability
to shut down the plant safely is ensured.
One means of complying with this
requirement is to separate one safe
shutdown train from its redundant train
with rated fire barriers. The duration of
fire resistance required of the barriers,
usually 1 hour or 3 hours, depends on
the other fire protection features
PO 00000
Frm 00068
Fmt 4703
Sfmt 4703
provided in the fire area. The NRC
issued guidance on acceptable methods
of satisfying the regulatory requirements
of GDC 3 in the branch technical
positions (BTPs) and generic letters
identified below in the Applicable
Regulatory Guidance section of this
generic letter. GL 92–08 specifically
included the staff’s expectation that
licensees would review existing fire
barrier configurations credited for 10
CFR part 50, appendix R, compliance,
based on earlier concerns with ThermoLag. Licensees of plants licensed to
operate before January 1, 1979, must
comply with their fire protection
requirements as specified in 10 CFR 50,
appendix R, and licensees of plants
licensed to operate after January 1, 1979,
must comply with the approved fire
protection program incorporated into
their operating license. The staff expects
licensees to reevaluate their fire
protection programs in light of
information provided in IN 05–07 and
this generic letter and to implement
appropriate compensatory measures and
develop plans to resolve any
noncompliances within a reasonable
timeframe.
For guidance in addressing any
degraded or nonconforming Hemyc and
MT fire barrier configurations, licensees
should consult the guidance in Revision
1 to GL 91–18, ‘‘Information to
Licensees Regarding NRC Inspection
Manual Section on Resolution of
Degraded and Nonconforming
Conditions,’’ dated October 8, 1997.
Licensees are encouraged to review
Regulatory Issue Summary 2005–07,
‘‘Compensatory Measures To Satisfy the
Fire Protection Program Requirements,’’
in determining the appropriate
compensatory measures to meet fire
protection program requirements for the
degraded or nonconforming fire barrier
installations. All licensees should
consider the impact of fire barrier
degradation on the operability of
affected equipment and assess the
impact on plant safety.
NRC regulations do not require fire
detectors and automatic fire suppression
systems when 3-hour fire barriers are
used. NRC regulations do require fire
detectors and automatic fire suppression
systems when 1-hour-rated fire barriers
are used; however, the staff has
approved plant-specific requests for
exceptions (i.e., exemptions or
amendments) for specific areas of the
plant based on detailed evaluations of
the area configuration and combustible
loading. Hemyc and MT fire ratings are
expected to provide time to extinguish
fires before safe shutdown systems are
damaged.
E:\FR\FM\25JYN1.SGM
25JYN1
Federal Register / Vol. 70, No. 141 / Monday, July 25, 2005 / Notices
If a nonconforming condition is
identified, then licensees can use at
least two methods, individually or in
combination, to restore compliance. One
way is to make plant modifications such
as replacing the Hemyc or MT fire
barriers with an appropriately rated fire
barrier material, upgrading the Hemyc
or MT to a rated barrier, or rerouting
cables or instrumentation lines through
another fire area. Another way to
address the issue is to perform a
technical evaluation that considers
defense-in-depth and safety margins as
follows:
• Plants licensed to operate before
January 1, 1979, that do not plan to
perform a plant modification must
request an exemption from 10 CFR part
50, appendix R, that demonstrates that
the configuration as installed meets the
requirements of 10 CFR 50.12, ‘‘Specific
Exemptions.’’ If the plant proposes to
use a risk-informed approach to justify
an exception in accordance with 10 CFR
50.12, then this approach should follow
the guidance of Regulatory Guide (RG)
1.174, ‘‘An Approach for Using
Probabilistic Risk Assessment in RiskInformed Decisions on Plant-Specific
Changes to the Licensing Basis.’’
• Plants licensed to operate after
January 1, 1979, that do not plan to
perform a plant modification must meet
the fire protection requirements in the
operating license condition. The
standard license condition allows a
licensee to make changes to the
approved fire protection program
without prior staff approval ‘‘if those
changes would not adversely affect the
ability to achieve and maintain safe
shutdown in the event of a fire.’’ GL 86–
10, ‘‘Implementation of Fire Protection
Requirements,’’ provides guidance on
performing and documenting these
changes.
Plants licensed after January 1, 1979,
that adopt a risk-informed approach,
must submit a license amendment in
accordance with 10 CFR 50.90. The
exception to 10 CFR 50.90, provided in
the standard license condition and in 10
CFR 50.48(f)(3), does not apply because
the risk assessment approaches used by
plants deviate from the approved
deterministic approaches used in their
licensing bases. Furthermore, the
licensees’ risk assessment tools have not
been reviewed or inspected against
quality standards found acceptable to
the NRC staff. Consequently, the staff is
not confident that a risk-informed
approach ‘‘would not adversely affect
the ability to achieve and maintain safe
shutdown in the event of a fire,’’ at this
time. Because this approach fails to
meet the exception criteria for an
exception to 10 CFR 50.90, a license
VerDate jul<14>2003
14:21 Jul 22, 2005
Jkt 205001
amendment is required for the change to
the license condition, in accordance
with 10 CFR 50.90.
Applicable Regulatory Requirements
NRC regulations in 10 CFR 50.48 and
10 CFR part 50, appendix A, GDC 3,
require each operating nuclear power
plant (licensed before or after issuance
of GDC 3) to have a fire protection plan
providing post-fire safe shutdown. That
is, a means must be provided to limit
fire damage to structures, systems or
components important to safety so that
the capability to shut down the plant
safely is ensured. The regulation in 10
CFR 50.90 requires a licensee who
desires to amend their license, to submit
an amendment request to the NRC. All
NPPs licensed to operate before January
1, 1979, are required to comply with 10
CFR part 50, appendix R, paragraph
III.G, ‘‘Fire Protection of Safe Shutdown
Capability.’’ All NPPs licensed to
operate after January 1, 1979, are
required to comply with 10 CFR
50.48(a), which requires that each
operating nuclear power plant have a
fire protection plan that satisfies GDC 3.
The fire protection plan is incorporated
into the operating license for each post1979 plant as a license condition. This
license condition specifically cites the
staff SER on the licensee’s fire
protection plan, to demonstrate that the
license condition has been met
(although licensees may modify their
fire protection plan as long as there is
no adverse effect on safe shutdown).
Applicable Regulatory Guidance
The NRC issued guidance on
acceptable methods of satisfying the
regulatory requirements of GDC 3 in
Auxiliary and Power Conversion
Systems Branch (APCSB) BTP 9.5–1,
‘‘Guidelines for Fire Protection for
Nuclear Power Plants,’’ May 1, 1976;
Appendix A to APCSB BTP 9.5–1,
February 24, 1977; and Chemical
Engineering Branch (CMEB) BTP 9.5–1,
‘‘Fire Protection for Nuclear Power
Plants,’’ July 1981. In response to
licensees’ questions, the staff provided
additional guidance on fire barriers in
GL 86–10. The staff issued additional
guidance as Supplement 1 to GL 86–10.
In the BTPs and in GL 86–10, the staff
states that the fire resistance ratings of
fire barriers should be established in
accordance with National Fire
Protection Association (NFPA) Standard
251, ‘‘Standard Methods of Fire Tests of
Building Construction and Materials,’’ 2
by subjecting a test specimen that
2 American Society for Testing and Materials
(ASTM) E–119, ‘‘Fire Test of Building Construction
Materials,’’ and NFPA 251 are essentially
equivalent.
PO 00000
Frm 00069
Fmt 4703
Sfmt 4703
42599
represents the materials, workmanship,
method of assembly, dimensions, and
configuration for which a fire rating is
desired to a ‘‘standard fire exposure.’’
Supplement 1 to GL 86–10 provides
guidance for fire barrier endurance
testing and for evaluating deviations
from tested configurations. This
guidance is repeated in RG 1.189, ‘‘Fire
Protection for Operating Nuclear Power
Plants.’’
Requested Actions
Within 60 days of the date of this
letter, all addressees are requested to
determine whether or not Hemyc or MT
fire barrier material is installed and
relied on for separation and/or safe
shutdown purposes to satisfy applicable
regulatory requirements.
Addressees who credit Hemyc or MT
for compliance should provide
information regarding the extent of the
installation; whether the material is
degraded or nonconforming; and any
compensatory actions in place to
provide equivalent protection and
maintain the safe shutdown function of
affected areas of the plant in light of the
recent findings of potential degradation
of Hemyc and MT. Licensees should
provide evaluations to support
conclusions that they are in compliance
with regulatory requirements for the
Hemyc and MT applications. Licensees
that can not justify their continued
reliance on Hemyc or MT shall provide
a description of corrective actions taken
or planned and a schedule for
milestones including when full
compliance will be achieved. In
addition, licensees should identify and
discuss all applications that are
considered degraded but operable,
including a basis for this conclusion.
Compensatory and corrective actions
shall be implemented in accordance
with existing regulations commensurate
with the safety significance of the
degraded or nonconforming condition.
The NRC expects that all licensees shall
fully restore compliance with 10 CFR
50.48, and submit the required
documentation to the NRC, by
December 1, 2007.
Requested Information
All addressees are requested to
provide the following information:
1. Within 60 days of the date of this
generic letter, provide a statement on
whether Hemyc or MT fire barrier
material is used at their NPPs and
whether it is relied on for separation
and/or safe shutdown purposes in
accordance with the licensing basis,
including whether Hemyc or MT is
credited in other analyses (e.g.,
E:\FR\FM\25JYN1.SGM
25JYN1
42600
Federal Register / Vol. 70, No. 141 / Monday, July 25, 2005 / Notices
exemptions, license amendments, GL
86–10 analyses).
2. Within 60 days of the date of this
generic letter, addressees who have
installed Hemyc or MT fire barrier
materials should discuss the following
in detail:
a. The extent of the installation (e.g.,
linear feet of wrap, areas installed,
systems protected),
b. Whether the Hemyc and/or MT
installed in their plants continues to
comply with 10 CFR 50.48, in light of
recent findings,
c. The compensatory measures that
have been implemented to provide
equivalent protection and maintain the
safe shutdown function of affected areas
of the plant in light of the recent
findings of potential degradation Hemyc
and MT, including evaluations to
support the addresses’ conclusions and
a discussion of the impact on plant risk,
d. A general description of, and
implementation schedule for, all
corrective actions to restore the fire
protection program to compliance with
the licensing basis, including a
description of any licensing actions or
exemption requests needed to support
changes to the plant licensing basis.
3. No later than December 1, 2007,
addressees that have degraded or
nonconforming Hemyc and/or MT and
rely on it for separation and/or safe
shutdown purposes should provide the
following information upon
implementing corrective actions:
a. Confirmation that the fire
protection program is in compliance
with the regulatory requirements listed
in the Applicable Regulatory
Requirements section of this generic
letter once all corrective actions for
regulatory compliance have been
completed and the licensing basis has
been updated to reflect the actions
taken.
b. A summary of the evaluation used
to determine the susceptibility of the
fire protection program to the adverse
effects of potentially degraded Hemyc or
MT fire barriers. (The submittal may
reference a guidance document, e.g., GL
86–10, or another approach previously
submitted to the NRC. The documents
submitted or referenced should include
the results of any supporting Hemyc or
MT tests or evaluations performed to
obtain pertinent information used in the
determination.)
c. A description of the existing
programmatic controls that will ensure
that other fire barrier types will be
assessed for potential degradation and
resultant adverse effects. Addressees
may reference their responses to GL 92–
08 to the extent that the responses
address this specific issue.
VerDate jul<14>2003
14:21 Jul 22, 2005
Jkt 205001
Required Response
In accordance with 10 CFR 50.54(f), in
order to determine whether a facility
license should be modified, suspended,
or revoked, or whether other action
should be taken, an addressee is
required to respond as described below.
Within 30 days of the date of this
generic letter, an addressee is required
to submit a written response if it is
unable to provide the information or it
cannot meet the requested completion
date. The addressee must address in its
response any alternative course of
action that it proposes to take, including
the basis for the acceptability of the
proposed alternative course of action.
The required written response should
be addressed to the U.S. Nuclear
Regulatory Commission, Attn:
Document Control Desk, 11555
Rockville Pike, Rockville, Maryland
20852, under oath or affirmation under
the provisions of Section 182a of the
Atomic Energy Act of 1954, as amended,
and 10 CFR 50.54(f). In addition, a copy
of the response should be submitted to
the appropriate regional administrator.
Reason for Information Request
The recent confirmatory testing of the
Hemyc and MT fire barriers revealed
that similar barriers installed at NPPs
may not perform their intended
protective function during a fire.
The NRC staff will review the
responses to this generic letter and will
notify affected addressees if concerns
are identified regarding compliance
with NRC regulations. The staff may
also conduct inspections to determine
addressees’ effectiveness in addressing
the generic letter.
Related Generic Communications
1. Regulatory Issue Summary 05–07,
‘‘Compensatory Measures To Satisfy the
Fire Protection Program Requirements,’’
April 19, 2005.
2. Information Notice 05–07, ‘‘Results
of Hemyc Electrical Raceway Fire
Barrier System Full Scale Fire Testing,’’
April 1, 2005.
3. Information Notice 99–17,
‘‘Problems Associated with Post-Fire
Safe-Shutdown Circuit Analysis,’’ June
3, 1999.
4. Information Notice 95–52,
Supplement 1, ‘‘Fire Endurance Test
Results for Electrical Raceway Fire
Barrier Systems Constructed from 3M
Company Interam Fire Barrier
Materials,’’ March 17, 1998.
5. Information Notice 95–49,
Supplement 1, ‘‘Seismic Adequacy of
Thermo-Lag Panels,’’ December 10,
1997.
6. Generic Letter 91–18, ‘‘Information
to Licensees Regarding NRC Inspection
PO 00000
Frm 00070
Fmt 4703
Sfmt 4703
Manual Section on Resolution of
Degraded and Nonconforming
Conditions,’’ Revision 1, October 8,
1997.
7. Information Notice 97–70,
‘‘Potential Problems With Fire Barrier
Penetration Seals,’’ September 19, 1997.
8. Information Notice 97–59, ‘‘Fire
Endurance Test Results of Versawrap
Fire Barriers,’’ August 1, 1997.
9. Information Notice 94–86,
Supplement 1, ‘‘Legal Actions Against
Thermal Science, Inc., Manufacturer of
Thermo-Lag,’’ November 15, 1995.
10. Information Notice 95–52, ‘‘Fire
Endurance Test Results for Electrical
Raceway Fire Barrier Systems
Constructed from 3M Company Interam
Fire Barrier Materials,’’ November 14,
1995.
11. Information Notice 95–49,
‘‘Seismic Adequacy of Thermo-Lag
Panels,’’ October 27, 1995.
12. Information Notice 95–32,
‘‘Thermo-Lag 330–1 Flame Spread Test
Results,’’ August 10, 1995.
13. Information Notice 95–27, ‘‘NRC
Review of Nuclear Energy Institute,
Thermo-Lag 330–1 Combustibility
Evaluation Methodology Plant
Screening Guide,’’ May 31, 1995.
14. Information Notice 94–86, ‘‘Legal
Actions Against Thermal Science, Inc.,
Manufacturer of Thermo-Lag,’’
December 22, 1994.
15. Information Notice 94–34,
‘‘Thermo-Lag 330–660 Flexi-Blanket
Ampacity Derating Concerns,’’ May 13,
1994.
16. Information Notice 94–28,
‘‘Potential Problems With Fire Barrier
Penetration Seals,’’ April 5, 1994.
17. Generic Letter 86–10, Supplement
1, ‘‘Fire Endurance Test Acceptance
Criteria for Fire Barrier Systems Used
To Separate Redundant Safe Shutdown
Trains within the Same Fire Area,’’
March 25, 1994.
18. Information Notice 94–22, ‘‘Fire
Endurance and Ampacity Derating Test
Results for 3-Hour Fire-Rated ThermoLag 330–1 Fire Barriers,’’ March 16,
1994.
19. Information Notice 93–41, ‘‘One
Hour Fire Endurance Test Results for
Thermal Ceramics Kaowool, 3M
Company FS–195 and 3M Company
Interam E–50 Fire Barrier Systems,’’
May 28, 1993.
20. Information Notice 93–40, ‘‘Fire
Endurance Test Results for Thermal
Ceramics FP–60 Fire Barrier Material,’’
May 26, 1993.
21. Generic Letter 92–08, ‘‘ThermoLag 330–1 Fire Barriers,’’ December 17,
1992.
22. Information Notice 92–82,
‘‘Results of Thermo-Lag 330–1
Combustibility Testing,’’ December 15,
1992.
E:\FR\FM\25JYN1.SGM
25JYN1
Federal Register / Vol. 70, No. 141 / Monday, July 25, 2005 / Notices
23. Bulletin 92–01, Supplement 1,
‘‘Failure of Thermo-Lag 330 Fire Barrier
System To Perform its Specified Fired
Endurance Function,’’ August 28, 1992.
24. Information Notice 92–55,
‘‘Current Fire Endurance Test Results
for Thermo-Lag Fire Barrier Material,’’
July 27, 1992.
25. Bulletin 92–01, ‘‘Failure of
Thermo-Lag 330 Fire Barrier System To
Maintain Cabling in Wide Cable Trays
and Small Conduits Free from Fire
Damage,’’ June 24, 1992.
26. Information Notice 92–46,
‘‘Thermo-Lag Fire Barrier Material
Special Review Team Final Report
Findings, Current Fire Endurance Tests,
and Ampacity Calculation Error,’’ June
23, 1992.
27. Information Notice 91–79,
‘‘Deficiencies in the Procedures for
Installing Thermo-Lag Fire Barrier
Materials,’’ December 6, 1991.
28. Information Notice 91–47,
‘‘Failure of Thermo-Lag Fire Barrier
Material To Pass Fire Endurance Test,’’
August 6, 1991.
29. Information Notice 88–56,
‘‘Potential Problems With Silicone Foam
Fire Barrier Penetration Seals,’’ August
4, 1988.
30. Generic Letter 88–12, ‘‘Removal of
Fire Protection Requirements from
Technical Specifications,’’ August 2,
1988.
31. Generic Letter 86–10,
‘‘Implementation of Fire Protection
Requirements,’’ April 26, 1986.
32. Generic Letter 83–33, ‘‘NRC
Position on Certain Requirements of
Appendix R to 10 CFR Part 50,’’ October
19, 1983.
33. Generic Letter 81–12, ‘‘Fire
Protection Rule (45 FR 76602,
November 19, 1980),’’ February 20,
1981.
Backfit Discussion
Under the provisions of Section 182a
of the Atomic Energy Act of 1954, as
amended, 10 CFR 50.109(a)(4)(I) and 10
CFR 50.54(f), this generic letter asks
addressees to evaluate their facilities to
confirm compliance with the existing
applicable regulatory requirements as
discussed in this generic letter.
Specifically, although Hemyc and MT
fire barriers in NPPs may be relied on
to protect electrical and instrumentation
cables and equipment that provide safe
shutdown capability during a fire,
recent NRC testing has revealed that
both materials failed to provide the
protective function intended for
compliance with existing regulations.
For plants licensed to operate before
January 1, 1979, licensees are required
to comply with 10 CFR part 50,
appendix R, which requires protection
VerDate jul<14>2003
14:21 Jul 22, 2005
Jkt 205001
of safe shutdown capabilities. One
means of complying with this
requirement is to separate one safe
shutdown train from its redundant train
using rated fire barriers, as cited in
Appendix R, paragraph III.G.2(a). Recent
test results indicated that Hemyc and
MT fire barriers did not pass the GL 86–
10, Supplement 1, criteria to achieve a
1-hour fire rating for Hemyc or a 3-hour
fire rating for MT. Therefore, for any
such plant that relies on Hemyc and/or
MT for compliance, compliance with
Appendix R is in question and the
information requested by this generic
letter is a compliance exception to the
rule in accordance with 10 CFR
50.109(a)(4)(I).
For plants licensed to operate after
January 1, 1979, licensees are required
to comply with 10 CFR 50.48(a), which
requires that each operating nuclear
power plant have a fire protection plan
that satisfies GDC 3. The fire protection
plan is incorporated into the operating
license for each post-1979 plant as a
license condition and may rely on fire
barriers such as Hemyc and MT to
provide the required protection. The
license condition specifically cites the
staff SER on the licensee’s fire
protection plan, to demonstrate that the
license condition has been met
(although licensees may modify their
fire protection plan as long as there is
no adverse effect). However, recent test
results indicated that Hemyc and MT
fire barriers did not pass the GL 86–10,
Supplement 1, criteria to achieve a 1hour fire rating for Hemyc or a 3-hour
fire rating for MT. Therefore, for any
such plant where the staff-approved fire
protection plan relies on Hemyc and/or
MT for compliance with their license
condition, compliance with the license
condition is in question and the
information requested by this generic
letter is a compliance exception to the
rule in accordance with 10 CFR
50.109(a)(4)(I).
Federal Register Notification
A notice of opportunity for public
comment on this generic letter was
published in the Federal Register (XX
FR XXXXX) on July XX, 2005.
Small Business Regulatory Enforcement
Fairness Act
In accordance with the Small
Business Regulatory Enforcement
Fairness Act of 1996, the NRC has
determined that this generic letter is not
a major rule and has verified this
determination with the Office of
Information and Regulatory Affairs of
the Office of Management and Budget
(OMB).
PO 00000
Frm 00071
Fmt 4703
Sfmt 4703
42601
Paperwork Reduction Act Statement
This generic letter contains
information collection requirements that
are subject to the Paperwork Reduction
Act of 1995 (44 U.S.C. 3501 et seq.).
These information collections were
approved by the Office of Management
and Budget, clearance number 3150–
0011, which expires February 28, 2007.
The burden to the public for these
mandatory information collections is
estimated to average 300 hours per
response, including the time for
reviewing instructions, searching
existing data sources, gathering and
maintaining the data needed, and
completing and reviewing the
information collection. The U.S.
Nuclear Regulatory Commission is
seeking public comment on the
potential impact of the information
collections contained in the generic
letter and on the following issues:
1. Is the proposed information
collection necessary for the proper
performance of the functions of the
NRC, including whether the information
will have practical utility?
2. Is the estimate of burden accurate?
3. Is there a way to enhance the
quality, utility, and clarity of the
information collected?
4. How can the burden of the
information collection be minimized,
including the use of automated
collection techniques?
Send comments on any aspect of
these information collections, including
suggestions for reducing the burden, to
the Records and FOIA/Privacy Services
Branch (T–F52), U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001, or by Internet
electronic mail to
INFOCOLLECTS@NRC.GOV; and to the
Desk Officer, Office of Information and
Regulatory Affairs, NEOB–10202 (3150–
0011), Office of Management and
Budget, Washington, DC 20503.
Public Protection Notification
The NRC may not conduct or sponsor,
and a person is not required to respond
to, an information collection unless the
requesting document displays a
currently valid OMB control number.
Contact
Please direct any questions about this
matter to the Technical Contacts or the
Lead Project Manager listed below, or to
the appropriate Office of Nuclear
Reactor Regulation (NRR) project
manager.
Bruce A. Boger, Director, Division of
Inspection Program Management,
Office of Nuclear Reactor
Regulation.
E:\FR\FM\25JYN1.SGM
25JYN1
42602
Federal Register / Vol. 70, No. 141 / Monday, July 25, 2005 / Notices
Technical Contacts:
Daniel Frumkin, NRR, (301) 415–
2280, e-mail: dxf1@nrc.gov.
Angie Lavretta, NRR, (301) 415–3285,
e-mail: axl3@nrc.gov.
Lead Project Manager:
Chandu Patel, NRR, (301) 415–3025,
e-mail: cpp@nrc.gov.
Note: NRC generic communications may be
found on the NRC public Web site, https://
www.nrc.gov, under Electronic Reading
Room/Document Collections.
DATES:
End of Draft Generic Letter
Documents may be examined, and/or
copied for a fee, at the NRC’s Public
Document Room at One White Flint
North, 11555 Rockville Pike (first floor),
Rockville, Maryland. Publicly available
records will be accessible electronically
from the Agencywide Documents
Access and Management System
(ADAMS) Public Electronic Reading
Room on the Internet at the NRC Web
site, https://www.nrc.gov/NRC/ADAMS/
index.html. If you do not have access to
ADAMS or if you have problems in
accessing the documents in ADAMS,
contact the NRC Public Document Room
(PDR) reference staff at 1–800–397–4209
or (301) 415–4737 or by e-mail to
pdr@nrc.gov.
Dated at Rockville, Maryland, this 18th day
of July, 2005.
For the Nuclear Regulatory Commission.
Patrick L. Hiland,
Chief, Reactor Operations Branch, Division
of Inspection Program Management, Office
of Nuclear Reactor Regulation.
[FR Doc. E5–3941 Filed 7–22–05; 8:45 am]
BILLING CODE 7590–01–P
OFFICE OF PERSONNEL
MANAGEMENT
Federal Employees Health Benefits
Program: Medically Underserved Areas
for 2006
Office of Personnel
Management.
ACTION: Notice of Medically
Underserved Areas for 2006.
AGENCY:
14:21 Jul 22, 2005
Jkt 205001
Effective Date: January 1, 2006.
FOR FUTHER INFORMATION CONTACT:
Ingrid Burford, (202) 606–0004.
FEHB law
(5 U.S.C. 8902(m)(2)) mandates special
consideration for enrollees of certain
FEHB plans who receive covered health
services in States with critical shortages
of primary care physicians. The FEHB
law also requires that a State be
designated as a Medically Underserved
Area if 25 percent or more of the
population lives in an area designated
by the Department of Health and Human
Services (HHS) as a primary medical
care manpower shortage area. Such
States are designated as Medically
Underserved Areas for purposes of the
FEHB Program, and the law requires
non-HMO FEHB plans to reimburse
beneficiaries, subject to their contract
terms, for covered services obtained
from any licensed provider in these
States.
FEHB regulations (5 CFR 890.701)
require OPM to make an annual
determination of the States that qualify
as Medically Underserved Areas for the
next calendar year by comparing the
latest HHS State-by-State population
counts on primary medical care
manpower shortage areas with U.S.
Census figures on State resident
populations.
SUPPLEMENTARY INFORMATION:
Office of Personnel Management.
Linda M. Springer,
Director.
[FR Doc. 05–14551 Filed 7–22–05; 8:45 am]
BILLING CODE 6325–39–P
The Office of Personnel
Management (OPM) has completed its
annual determination of the States that
qualify as Medically Underserved Areas
under the Federal Employees Health
Benefits (FEHB) Program for calendar
year 2006. This is necessary to comply
with a provision of the FEHB law that
mandates special consideration for
enrollees of certain FEHB plans who
receive covered health services in States
with critical shortages of primary care
physicians. Accordingly, for calendar
SUMMARY:
VerDate jul<14>2003
year 2006, OPM’s calculations show that
the following states are Medically
Underserved Areas under the FEHB
Program: Alabama, Alaska, Arizona,
Idaho, Kentucky, Louisiana,
Mississippi, Missouri, Montana, New
Mexico, North Dakota, South Carolina,
South Dakota, West Virginia, and
Wyoming. For the 2006 contract year
Arizona and West Virginia are being
added to the list and Texas is being
removed.
POSTAL RATE COMMISSION
[Docket No. MC2005–3; Order No. 1441]
Negotiated Service Agreement
Postal Rate Commission.
Notice and order on new
baseline negotiated service agreement
case.
AGENCY:
ACTION:
SUMMARY: This document establishes a
docket for consideration of the Postal
Service’s request for approval of a
baseline negotiated service agreement
PO 00000
Frm 00072
Fmt 4703
Sfmt 4703
with Bookspan. It identifies key
elements of the proposed agreement,
which involves Standard Mail letter
rates; its relationship to the Capital One
Services, Inc. negotiated service
agreement; and addresses preliminary
procedural matters.
DATES: Key dates are:
1. August 8, 2005: Deadline for filing
notices of intervention.
2. August 8–10, 2005: Authorized
alternative dates for settlement
conference.
3. August 11, 2005: Prehearing
conference (10 a.m.).
ADDRESSES: Submit comments
electronically via the Commission’s
Filing Online system at https://
www.prc.gov.
FOR FURTHER INFORMATION CONTACT:
Stephen L. Sharfman, general counsel,
at 202–789–6818.
SUPPLEMENTARY INFORMATION:
Procedural History
Capital One Services, Inc. Negotiated
Service Agreement, 67 FR 61355
(September 30, 2002).
Negotiated Service Agreement Final
Rule, 69 FR 7574 (February 18, 2004).
On July 14, 2005, the United States
Postal Service filed a request seeking a
recommended decision from the Postal
Rate Commission approving a
Negotiated Service Agreement (NSA)
with Bookspan.1 The NSA is proffered
as a new baseline agreement. This is the
first new baseline agreement filed since
the Capital One Negotiated Service
Agreement, MC2002–2, and the first
baseline agreement filed under the
Commission’s new rules for baseline
NSAs. Rule 195 [39 CFR 3001.195]. The
Request, which includes six
attachments, was filed pursuant to
Chapter 36 of the Postal Reorganization
Act, 39 U.S.C. 3601 et seq.2 The Postal
Service has identified Bookspan, along
with itself, as parties to the NSA. This
identification serves as notice of
intervention by Bookspan. It also
indicates that Bookspan shall be
considered a co-proponent,
1 Request of the United States Postal Service for
a Recommended Decision on Classifications and
Rates to Implement a Baseline Negotiated Service
Agreement with Bookspan, July 15, 2005 (Request).
2 Attachments A and B to the Request contain
proposed changes to the Domestic Mail
Classification Schedule and the associated rate
schedules; Attachment C is a certification required
by Commission rule 193(i) specifying that the cost
statements and supporting data submitted by the
Postal Service, which purport to reflect the books
of the Postal Service, accurately set forth the results
shown by such books; Attachment D is an index of
testimony and exhibits; Attachment E is a
compliance statement addressing satisfaction of
various filing requirements; and Attachment F is a
copy of the Negotiated Service Agreement.
E:\FR\FM\25JYN1.SGM
25JYN1
Agencies
[Federal Register Volume 70, Number 141 (Monday, July 25, 2005)]
[Notices]
[Pages 42596-42602]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-3941]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
Proposed Generic Communication; Impact of Potentially Degraded
Hemyc and Mt Fire Barriers on Compliance With Approved Fire Protection
Programs
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice of opportunity for public comment.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is proposing to
issue a generic letter (GL) to:
(1) Request that addressees evaluate their facilities to confirm
compliance with the existing applicable regulatory requirements in
light of the information provided in this generic letter and, if
appropriate, take additional actions. Specifically, although Hemyc and
MT fire barriers in nuclear power plants (NPPs) may be relied on to
protect electrical and instrumentation cables and equipment that
provide safe shutdown capability during a fire, recent NRC testing has
revealed that both materials failed to provide the protective function
intended for compliance with existing regulations, for the
configurations tested using the acceptance criteria in Generic Letter
(GL) 86-10, Supplement 1, ``Fire Endurance Test Acceptance Criteria for
Fire Barrier Systems Used To Separate Redundant Safe Shutdown Trains
Within the Same Fire Area.''
(2) Require that addressees submit a written response to the NRC in
accordance with NRC regulations in Title 10 of the Code of Federal
Regulations, Section 50.54(f) (10 CFR 50.54(f)).
This Federal Register notice is available through the NRC's
Agencywide Documents Access and Management System (ADAMS) under
accession number ML051540292.
DATES: Comment period expires September 23, 2005. Comments submitted
after this date will be considered if it is practical to do so, but
assurance of consideration cannot be given except for comments received
on or before this date.
ADDRESSES: Submit written comments to the Chief, Rules and Directives
Branch, Division of Administrative Services, Office of Administration,
U.S. Nuclear Regulatory Commission, Mail Stop T6-D59, Washington, DC
20555-0001, and cite the publication date and page number of this
Federal Register notice. Written comments may also be delivered to NRC
Headquarters, 11545 Rockville Pike (Room T-6D59), Rockville, Maryland,
between 7:30 a.m. and 4:15 p.m. on Federal workdays.
FOR FURTHER INFORMATION, CONTACT: Angie Lavretta at (301) 415-3285 or
by e-mail axl3@nrc.gov, Daniel Frumkin at (301) 415-2280 or e-mail
dxf1@nrc.gov, or Chandu Patel at (301) 415-3025 or by e-mail at
cpp@nrc.gov.
SUPPLEMENTARY INFORMATION:
NRC Generic Letter 2005-XX
Impact of Potentially Degraded Hemyc and Mt Fire Barriers on Compliance
With Approved Fire Protection Programs
Addressees
All holders of operating licenses for light-water nuclear power
reactors, except those who have ceased operations and have certified
that fuel has been permanently removed from the reactor vessel.
Purpose
The U.S. Nuclear Regulatory Commission (NRC) is issuing this
generic letter to:
(3) Request that addressees evaluate their facilities to confirm
compliance with the existing applicable regulatory requirements in
light of the information provided in this generic letter and, if
[[Page 42597]]
appropriate, take additional actions. Specifically, although Hemyc and
MT fire barriers in nuclear power plants (NPPs) may be relied on to
protect electrical and instrumentation cables and equipment that
provide safe shutdown capability during a fire, recent NRC testing has
revealed that both materials failed to provide the protective function
intended for compliance with existing regulations, for the
configurations tested using the acceptance criteria in Generic Letter
(GL) 86-10, Supplement 1, ``Fire Endurance Test Acceptance Criteria for
Fire Barrier Systems Used To Separate Redundant Safe Shutdown Trains
Within the Same Fire Area.''
(4) Require that addressees submit a written response to the NRC in
accordance with NRC regulations in Title 10 of the Code of Federal
Regulations, Section 50.54(f) (10 CFR 50.54(f)).
Background
NRC's concern with the performance of fire barriers at nuclear
power plants began with the failure of Thermo-Lag to pass performance
tests in October 1989 at Southwest Research Institute. The tests were
done for the Gulf States Utilities Company after visually observing
degradation of Thermo-Lag at River Bend Station. In June and August
1992, two sets of full-scale fire endurance tests on Thermo-Lag were
conducted at Omega Point Laboratories in San Antonio, Texas, by Texas
Utilities Electric Company for Comanche Peak Steam Electric Station,
with similar results. In July 1992, the NRC sponsored a series of
small-scale fire endurance tests at the National Institute of Standards
and Technology. The results again indicated that 1-hour-and 3-hour-
rated Thermo-Lag barrier material failed to consistently provide its
intended protective function.
On August 6, 1991, the NRC issued Information Notice (IN) 91-47,
``Failure of Thermo-Lag Fire Barrier Material To Pass Fire Endurance
Test,'' the first in a series of INs issued between 1991 and 1995 on
performance test failures and installation deficiencies related to
Thermo-Lag 330 fire barrier systems.
Because of questions about the ability of 1-hour- and 3-hour-rated
Thermo-Lag fire barrier material to perform its specified function and
because of the widespread use of Thermo-Lag in the nuclear industry,
the NRC issued the following generic communications to inform licensees
of the Thermo-Lag test results and to request that licensees implement
appropriate compensatory measures and develop plans to resolve any
noncompliances with 10 CFR 50.48:
Bulletin 92-01, ``Failure of Thermo-Lag 330 Fire Barrier
System To Maintain Cabling in Wide Cable Trays and Small Conduits Free
From Fire Damage,'' June 24, 1992.
Bulletin 92-01, Supplement 1, ``Failure of Thermo-Lag 330
Fire Barrier System To Perform its Specified Fire Endurance Function,''
August 28, 1992.
GL 92-08, ``Thermo-Lag 330-1 Fire Barriers,'' December 17,
1992.
Supplement 1 to GL 86-10, ``Fire Endurance Test Acceptance
Criteria for Fire Barrier Systems Used To Separate Redundant Safe
Shutdown Trains Within the Same Fire Area,'' March 25, 1994. GL 92-08
specifically asked licensees to review any existing fire barrier
configurations credited for 10 CFR 50.48 compliance in light of the
concerns with Thermo-Lag 330-1 fire barriers.
In response, the licensees reviewed their fire protection safe
shutdown plans to determine if corrective actions were needed. Some
licensees had made conservative commitments and installed Thermo-Lag in
locations where it was not needed to satisfy NRC requirements,
therefore no corrective actions were required. Where fire barrier
materials were required, licensees took one or a combination of the
following corrective actions:
Rerouted cables through other fire areas so that redundant
safe shutdown trains were not located in the same fire area.
Replaced Thermo-Lag, or the affected material, with an
alternative rated fire barrier material.
Upgraded the installed fire barriers to a rated
configuration.
Concluded that certain Thermo-Lag barriers were no longer
required.
Subsequently, deficiencies were also identified in other fire
barrier materials. In 1993, for example, Kaowool installed as a 1-hour-
rated fire barrier was found to be unable to pass circuit integrity
tests. In response, the NRC reassessed previous staff reviews of
Kaowool fire barriers and informed the industry and the Commission of
the potential failure of Kaowool to perform as intended and suggested
additional testing of Kaowool (SECY-99-204; ADAMS Accession No.
ML992810028). To resolve the issue, the industry took voluntary
corrective actions. In August 1993, the Nuclear Energy Institute (NEI)
formed a Fire Barrier Review Ad Hoc Advisory Committee to address the
adequacy of fire barrier materials other than Thermo-Lag. The Committee
performed reviews of the original testing of the fire barrier, Hemyc
(performed in the early 1980s in Spain), and concluded that Hemyc was
differently constructed than Thermo-Lag 330-1, and therefore was not
subject to the same failure modes as Thermo-Lag 330-1. In May 1994,
this review was documented in the NEI report, ``Documentation of the
Adequacy of Fire Barrier Materials in Raceway Applications Vis-
[agrave]-vis Failure Characteristics Inherent to the Thermo-Lag 330-
1.''
However, beginning in late 1999, three plant-specific findings by
the staff raised concerns about the performance of Hemyc and MT fire
barriers.
In November 1999, during an inspection at Shearon Harris
Nuclear Power Plant (IR 50-400/99-13; ADAMS Accession No. ML003685341),
the inspection team noted that the acceptance of the Hemyc and MT fire
barrier materials used was based on American Nuclear Insurers (ANI)
Bulletin No. 5 test acceptance criteria, even though the ANI test
methodology clearly stated that the tests were done for insurance
purposes only and were not intended to be considered the equivalent of
fire barrier endurance tests for fire barrier ratings.
In October and November 2000, during an inspection at
McGuire 1 and 2 (IR 50-369/00-09, 50-370/00-09; ADAMS Accession No.
ML003778709), the inspection team noted that the licensee was unable to
provide documentation demonstrating protection by Hemyc fire barrier
material used to separate safe shutdown functions for two trains within
a single fire area.
In September 2000, during an inspection at Waterford 3 (IR
50-382/00-07; ADAMS Accession No. ML003773900), the inspectors noted
that the Hemyc materials were installed in configurations which
typically would not be bounded by the existing tests.
In June 2001, the NRC initiated confirmatory fire tests in response
to Task Interface Agreement 99-028 (ADAMS Accession No. ML003736721),
after concluding that existing testing was likely insufficient to
qualify Hemyc or MT as rated fire barriers. The NRC tests were based on
ASTM E119 Standard time-temperature conditions and the current NRC
guidance in GL 86-10, Supplement 1, for typical Hemyc and MT
installations used in U.S. NPPs. The test results indicated that Hemyc
and MT fire barriers did not pass the GL 86-10, Supplement 1, criteria
to achieve a 1-hour fire rating for Hemyc or a 3-hour fire rating for
MT, for the configuration tested. On April 1, 2005, the NRC issued IN
2005-07, ``Results of Hemyc Electrical Raceway Fire Barrier System Full
Scale Fire Testing.'' This IN describes the results of the NRC-
sponsored confirmatory testing of
[[Page 42598]]
Hemyc. However, the staff recognized that additional evaluations would
be needed to determine whether regulatory compliance exists in light of
the concerns identified in IN 05-07.
On April 29, 2005, the staff held a public meeting with licensees
and interested members of the public to discuss the Hemyc and MT test
results and the staff's intentions to take prompt additional regulatory
action to ensure that appropriate measures are under way for compliance
with 10 CFR 50.48 requirements at affected plants. This generic letter
is the follow-on to IN 05-07.
The NRC has established a Web page to keep the public informed of
the status of the Hemyc/MT fire barrier issue at https://www.nrc.gov/
reactors/operating/ops-experience/fire-protection/technical-
issues.html#fire.
This page provides links to information on related fire protection
issues, along with documentation of NRC interactions with industry
(including generic communications, industry submittals, meeting
notices, presentation materials, and meeting summaries). The NRC will
continue to update this Web page as new information becomes available.
Hemyc Construction--Hemyc fire barrier material consists of mats of
2-inch Kaowool ceramic fiber insulation inside an outer covering of
Refrasil \1\ high-temperature fabric. The mats are custom-sized for the
electrical raceway and machine-stitched to produce the factory mats.
Hemyc mats, which are installed over a metal frame to provide the 2-
inch air gap design, are identical except that 1\1/2\-inch Kaowool is
used instead of the 2-inch material.
---------------------------------------------------------------------------
\1\ Refrasil was used during NRC tests. Siltemp and Refrasil
were tested by the NRC and determined to be essentially equivalent
(ADAMS Accession No. ML051190055).
---------------------------------------------------------------------------
MT Construction--MT used with conduits has four layers. The first
layer, closest to the conduit, is 1 inch of Kaowool ceramic fiber
blanket wrapped in a fiberglass fabric. The second layer is a 2-mil
sheet of stainless steel. The third layer is a hydrate packet. This
packet is made by stitching together packets of aluminum trihydrate in
a fiberglass-coated fabric. The fourth and outermost layer is a 1\1/2\-
inch Kaowool blanket wrapped in Refrasil. The configuration is slightly
different for air drops and structural supports. Air drops use a 3-inch
blanket of Kaowool as the inner layer. Structural supports do not have
the hydrating packet layer or the stainless steel sheet.
Discussion
Hemyc and MT, manufactured by Promatec, Inc, were installed at NPPs
to protect circuits and instrumentation cables in order to meet
regulatory requirements and in accordance with plant-specific
commitments. The NRC conducted confirmatory testing of both materials
at the Omega Point Laboratories in San Antonio, Texas. The test results
indicated that when tested to GL 86-10, Supplement 1, criteria, neither
the Hemyc nor the MT fire barrier system would provide its rated fire
barrier protection.
The staff noted at least three failure modes in the limited test
program. Two failure modes resulted from shrinkage of outer material
(Refrasil), causing the barrier to open and exposing the interior
surfaces or layers to the fire. The third failure mode resulted from
failure to adequately protect steel members intruding into the barrier.
The standard used by some utilities required protection of 3 inches of
intruding steel for the Hemyc 1-hour fire barrier and 18 inches of
intruding steel for the MT 3-hour fire barrier. The test results
indicated that additional protection of intruding steel was required to
achieve a 1-hour or 3-hour fire rating. Based on these test results,
the NRC is concerned that the Hemyc and MT fire barriers may not
provide the level of fire endurance intended by licensees and that
licensees that use Hemyc or MT may not be complying with NRC
regulations. Section 50.48 of 10 CFR part 50 requires that each
operating NPP have a fire protection plan that satisfies General Design
Criterion (GDC) 3, ``Fire Protection,'' of 10 CFR part 50, Appendix A,
``General Design Criteria for Nuclear Power Plants.'' The NRC
Regulation in 10 CFR 50.48 states that each operating nuclear power
plant (licensed before or after issuance of GDC 3) must have a fire
protection plan that satisfies Criterion 3 of Appendix A. GDC 3
requires that structures, systems, and components important to safety
be designed and located to minimize, in a manner consistent with other
requirements, the probability and effect of fires and explosions. Fire
protection features required to satisfy 10 CFR 50.48 include features
to limit fire damage to structures, systems or components important to
safety so that the capability to shut down the plant safely is ensured.
One means of complying with this requirement is to separate one safe
shutdown train from its redundant train with rated fire barriers. The
duration of fire resistance required of the barriers, usually 1 hour or
3 hours, depends on the other fire protection features provided in the
fire area. The NRC issued guidance on acceptable methods of satisfying
the regulatory requirements of GDC 3 in the branch technical positions
(BTPs) and generic letters identified below in the Applicable
Regulatory Guidance section of this generic letter. GL 92-08
specifically included the staff's expectation that licensees would
review existing fire barrier configurations credited for 10 CFR part
50, appendix R, compliance, based on earlier concerns with Thermo-Lag.
Licensees of plants licensed to operate before January 1, 1979, must
comply with their fire protection requirements as specified in 10 CFR
50, appendix R, and licensees of plants licensed to operate after
January 1, 1979, must comply with the approved fire protection program
incorporated into their operating license. The staff expects licensees
to reevaluate their fire protection programs in light of information
provided in IN 05-07 and this generic letter and to implement
appropriate compensatory measures and develop plans to resolve any
noncompliances within a reasonable timeframe.
For guidance in addressing any degraded or nonconforming Hemyc and
MT fire barrier configurations, licensees should consult the guidance
in Revision 1 to GL 91-18, ``Information to Licensees Regarding NRC
Inspection Manual Section on Resolution of Degraded and Nonconforming
Conditions,'' dated October 8, 1997. Licensees are encouraged to review
Regulatory Issue Summary 2005-07, ``Compensatory Measures To Satisfy
the Fire Protection Program Requirements,'' in determining the
appropriate compensatory measures to meet fire protection program
requirements for the degraded or nonconforming fire barrier
installations. All licensees should consider the impact of fire barrier
degradation on the operability of affected equipment and assess the
impact on plant safety.
NRC regulations do not require fire detectors and automatic fire
suppression systems when 3-hour fire barriers are used. NRC regulations
do require fire detectors and automatic fire suppression systems when
1-hour-rated fire barriers are used; however, the staff has approved
plant-specific requests for exceptions (i.e., exemptions or amendments)
for specific areas of the plant based on detailed evaluations of the
area configuration and combustible loading. Hemyc and MT fire ratings
are expected to provide time to extinguish fires before safe shutdown
systems are damaged.
[[Page 42599]]
If a nonconforming condition is identified, then licensees can use
at least two methods, individually or in combination, to restore
compliance. One way is to make plant modifications such as replacing
the Hemyc or MT fire barriers with an appropriately rated fire barrier
material, upgrading the Hemyc or MT to a rated barrier, or rerouting
cables or instrumentation lines through another fire area. Another way
to address the issue is to perform a technical evaluation that
considers defense-in-depth and safety margins as follows:
Plants licensed to operate before January 1, 1979, that do
not plan to perform a plant modification must request an exemption from
10 CFR part 50, appendix R, that demonstrates that the configuration as
installed meets the requirements of 10 CFR 50.12, ``Specific
Exemptions.'' If the plant proposes to use a risk-informed approach to
justify an exception in accordance with 10 CFR 50.12, then this
approach should follow the guidance of Regulatory Guide (RG) 1.174,
``An Approach for Using Probabilistic Risk Assessment in Risk-Informed
Decisions on Plant-Specific Changes to the Licensing Basis.''
Plants licensed to operate after January 1, 1979, that do
not plan to perform a plant modification must meet the fire protection
requirements in the operating license condition. The standard license
condition allows a licensee to make changes to the approved fire
protection program without prior staff approval ``if those changes
would not adversely affect the ability to achieve and maintain safe
shutdown in the event of a fire.'' GL 86-10, ``Implementation of Fire
Protection Requirements,'' provides guidance on performing and
documenting these changes.
Plants licensed after January 1, 1979, that adopt a risk-informed
approach, must submit a license amendment in accordance with 10 CFR
50.90. The exception to 10 CFR 50.90, provided in the standard license
condition and in 10 CFR 50.48(f)(3), does not apply because the risk
assessment approaches used by plants deviate from the approved
deterministic approaches used in their licensing bases. Furthermore,
the licensees' risk assessment tools have not been reviewed or
inspected against quality standards found acceptable to the NRC staff.
Consequently, the staff is not confident that a risk-informed approach
``would not adversely affect the ability to achieve and maintain safe
shutdown in the event of a fire,'' at this time. Because this approach
fails to meet the exception criteria for an exception to 10 CFR 50.90,
a license amendment is required for the change to the license
condition, in accordance with 10 CFR 50.90.
Applicable Regulatory Requirements
NRC regulations in 10 CFR 50.48 and 10 CFR part 50, appendix A, GDC
3, require each operating nuclear power plant (licensed before or after
issuance of GDC 3) to have a fire protection plan providing post-fire
safe shutdown. That is, a means must be provided to limit fire damage
to structures, systems or components important to safety so that the
capability to shut down the plant safely is ensured. The regulation in
10 CFR 50.90 requires a licensee who desires to amend their license, to
submit an amendment request to the NRC. All NPPs licensed to operate
before January 1, 1979, are required to comply with 10 CFR part 50,
appendix R, paragraph III.G, ``Fire Protection of Safe Shutdown
Capability.'' All NPPs licensed to operate after January 1, 1979, are
required to comply with 10 CFR 50.48(a), which requires that each
operating nuclear power plant have a fire protection plan that
satisfies GDC 3. The fire protection plan is incorporated into the
operating license for each post-1979 plant as a license condition. This
license condition specifically cites the staff SER on the licensee's
fire protection plan, to demonstrate that the license condition has
been met (although licensees may modify their fire protection plan as
long as there is no adverse effect on safe shutdown).
Applicable Regulatory Guidance
The NRC issued guidance on acceptable methods of satisfying the
regulatory requirements of GDC 3 in Auxiliary and Power Conversion
Systems Branch (APCSB) BTP 9.5-1, ``Guidelines for Fire Protection for
Nuclear Power Plants,'' May 1, 1976; Appendix A to APCSB BTP 9.5-1,
February 24, 1977; and Chemical Engineering Branch (CMEB) BTP 9.5-1,
``Fire Protection for Nuclear Power Plants,'' July 1981. In response to
licensees' questions, the staff provided additional guidance on fire
barriers in GL 86-10. The staff issued additional guidance as
Supplement 1 to GL 86-10.
In the BTPs and in GL 86-10, the staff states that the fire
resistance ratings of fire barriers should be established in accordance
with National Fire Protection Association (NFPA) Standard 251,
``Standard Methods of Fire Tests of Building Construction and
Materials,'' \2\ by subjecting a test specimen that represents the
materials, workmanship, method of assembly, dimensions, and
configuration for which a fire rating is desired to a ``standard fire
exposure.'' Supplement 1 to GL 86-10 provides guidance for fire barrier
endurance testing and for evaluating deviations from tested
configurations. This guidance is repeated in RG 1.189, ``Fire
Protection for Operating Nuclear Power Plants.''
---------------------------------------------------------------------------
\2\ American Society for Testing and Materials (ASTM) E-119,
``Fire Test of Building Construction Materials,'' and NFPA 251 are
essentially equivalent.
---------------------------------------------------------------------------
Requested Actions
Within 60 days of the date of this letter, all addressees are
requested to determine whether or not Hemyc or MT fire barrier material
is installed and relied on for separation and/or safe shutdown purposes
to satisfy applicable regulatory requirements.
Addressees who credit Hemyc or MT for compliance should provide
information regarding the extent of the installation; whether the
material is degraded or nonconforming; and any compensatory actions in
place to provide equivalent protection and maintain the safe shutdown
function of affected areas of the plant in light of the recent findings
of potential degradation of Hemyc and MT. Licensees should provide
evaluations to support conclusions that they are in compliance with
regulatory requirements for the Hemyc and MT applications. Licensees
that can not justify their continued reliance on Hemyc or MT shall
provide a description of corrective actions taken or planned and a
schedule for milestones including when full compliance will be
achieved. In addition, licensees should identify and discuss all
applications that are considered degraded but operable, including a
basis for this conclusion.
Compensatory and corrective actions shall be implemented in
accordance with existing regulations commensurate with the safety
significance of the degraded or nonconforming condition. The NRC
expects that all licensees shall fully restore compliance with 10 CFR
50.48, and submit the required documentation to the NRC, by December 1,
2007.
Requested Information
All addressees are requested to provide the following information:
1. Within 60 days of the date of this generic letter, provide a
statement on whether Hemyc or MT fire barrier material is used at their
NPPs and whether it is relied on for separation and/or safe shutdown
purposes in accordance with the licensing basis, including whether
Hemyc or MT is credited in other analyses (e.g.,
[[Page 42600]]
exemptions, license amendments, GL 86-10 analyses).
2. Within 60 days of the date of this generic letter, addressees
who have installed Hemyc or MT fire barrier materials should discuss
the following in detail:
a. The extent of the installation (e.g., linear feet of wrap, areas
installed, systems protected),
b. Whether the Hemyc and/or MT installed in their plants continues
to comply with 10 CFR 50.48, in light of recent findings,
c. The compensatory measures that have been implemented to provide
equivalent protection and maintain the safe shutdown function of
affected areas of the plant in light of the recent findings of
potential degradation Hemyc and MT, including evaluations to support
the addresses' conclusions and a discussion of the impact on plant
risk,
d. A general description of, and implementation schedule for, all
corrective actions to restore the fire protection program to compliance
with the licensing basis, including a description of any licensing
actions or exemption requests needed to support changes to the plant
licensing basis.
3. No later than December 1, 2007, addressees that have degraded or
nonconforming Hemyc and/or MT and rely on it for separation and/or safe
shutdown purposes should provide the following information upon
implementing corrective actions:
a. Confirmation that the fire protection program is in compliance
with the regulatory requirements listed in the Applicable Regulatory
Requirements section of this generic letter once all corrective actions
for regulatory compliance have been completed and the licensing basis
has been updated to reflect the actions taken.
b. A summary of the evaluation used to determine the susceptibility
of the fire protection program to the adverse effects of potentially
degraded Hemyc or MT fire barriers. (The submittal may reference a
guidance document, e.g., GL 86-10, or another approach previously
submitted to the NRC. The documents submitted or referenced should
include the results of any supporting Hemyc or MT tests or evaluations
performed to obtain pertinent information used in the determination.)
c. A description of the existing programmatic controls that will
ensure that other fire barrier types will be assessed for potential
degradation and resultant adverse effects. Addressees may reference
their responses to GL 92-08 to the extent that the responses address
this specific issue.
Required Response
In accordance with 10 CFR 50.54(f), in order to determine whether a
facility license should be modified, suspended, or revoked, or whether
other action should be taken, an addressee is required to respond as
described below.
Within 30 days of the date of this generic letter, an addressee is
required to submit a written response if it is unable to provide the
information or it cannot meet the requested completion date. The
addressee must address in its response any alternative course of action
that it proposes to take, including the basis for the acceptability of
the proposed alternative course of action.
The required written response should be addressed to the U.S.
Nuclear Regulatory Commission, Attn: Document Control Desk, 11555
Rockville Pike, Rockville, Maryland 20852, under oath or affirmation
under the provisions of Section 182a of the Atomic Energy Act of 1954,
as amended, and 10 CFR 50.54(f). In addition, a copy of the response
should be submitted to the appropriate regional administrator.
Reason for Information Request
The recent confirmatory testing of the Hemyc and MT fire barriers
revealed that similar barriers installed at NPPs may not perform their
intended protective function during a fire.
The NRC staff will review the responses to this generic letter and
will notify affected addressees if concerns are identified regarding
compliance with NRC regulations. The staff may also conduct inspections
to determine addressees' effectiveness in addressing the generic
letter.
Related Generic Communications
1. Regulatory Issue Summary 05-07, ``Compensatory Measures To
Satisfy the Fire Protection Program Requirements,'' April 19, 2005.
2. Information Notice 05-07, ``Results of Hemyc Electrical Raceway
Fire Barrier System Full Scale Fire Testing,'' April 1, 2005.
3. Information Notice 99-17, ``Problems Associated with Post-Fire
Safe-Shutdown Circuit Analysis,'' June 3, 1999.
4. Information Notice 95-52, Supplement 1, ``Fire Endurance Test
Results for Electrical Raceway Fire Barrier Systems Constructed from 3M
Company Interam Fire Barrier Materials,'' March 17, 1998.
5. Information Notice 95-49, Supplement 1, ``Seismic Adequacy of
Thermo-Lag Panels,'' December 10, 1997.
6. Generic Letter 91-18, ``Information to Licensees Regarding NRC
Inspection Manual Section on Resolution of Degraded and Nonconforming
Conditions,'' Revision 1, October 8, 1997.
7. Information Notice 97-70, ``Potential Problems With Fire Barrier
Penetration Seals,'' September 19, 1997.
8. Information Notice 97-59, ``Fire Endurance Test Results of
Versawrap Fire Barriers,'' August 1, 1997.
9. Information Notice 94-86, Supplement 1, ``Legal Actions Against
Thermal Science, Inc., Manufacturer of Thermo-Lag,'' November 15, 1995.
10. Information Notice 95-52, ``Fire Endurance Test Results for
Electrical Raceway Fire Barrier Systems Constructed from 3M Company
Interam Fire Barrier Materials,'' November 14, 1995.
11. Information Notice 95-49, ``Seismic Adequacy of Thermo-Lag
Panels,'' October 27, 1995.
12. Information Notice 95-32, ``Thermo-Lag 330-1 Flame Spread Test
Results,'' August 10, 1995.
13. Information Notice 95-27, ``NRC Review of Nuclear Energy
Institute, Thermo-Lag 330-1 Combustibility Evaluation Methodology Plant
Screening Guide,'' May 31, 1995.
14. Information Notice 94-86, ``Legal Actions Against Thermal
Science, Inc., Manufacturer of Thermo-Lag,'' December 22, 1994.
15. Information Notice 94-34, ``Thermo-Lag 330-660 Flexi-Blanket
Ampacity Derating Concerns,'' May 13, 1994.
16. Information Notice 94-28, ``Potential Problems With Fire
Barrier Penetration Seals,'' April 5, 1994.
17. Generic Letter 86-10, Supplement 1, ``Fire Endurance Test
Acceptance Criteria for Fire Barrier Systems Used To Separate Redundant
Safe Shutdown Trains within the Same Fire Area,'' March 25, 1994.
18. Information Notice 94-22, ``Fire Endurance and Ampacity
Derating Test Results for 3-Hour Fire-Rated Thermo-Lag 330-1 Fire
Barriers,'' March 16, 1994.
19. Information Notice 93-41, ``One Hour Fire Endurance Test
Results for Thermal Ceramics Kaowool, 3M Company FS-195 and 3M Company
Interam E-50 Fire Barrier Systems,'' May 28, 1993.
20. Information Notice 93-40, ``Fire Endurance Test Results for
Thermal Ceramics FP-60 Fire Barrier Material,'' May 26, 1993.
21. Generic Letter 92-08, ``Thermo-Lag 330-1 Fire Barriers,''
December 17, 1992.
22. Information Notice 92-82, ``Results of Thermo-Lag 330-1
Combustibility Testing,'' December 15, 1992.
[[Page 42601]]
23. Bulletin 92-01, Supplement 1, ``Failure of Thermo-Lag 330 Fire
Barrier System To Perform its Specified Fired Endurance Function,''
August 28, 1992.
24. Information Notice 92-55, ``Current Fire Endurance Test Results
for Thermo-Lag Fire Barrier Material,'' July 27, 1992.
25. Bulletin 92-01, ``Failure of Thermo-Lag 330 Fire Barrier System
To Maintain Cabling in Wide Cable Trays and Small Conduits Free from
Fire Damage,'' June 24, 1992.
26. Information Notice 92-46, ``Thermo-Lag Fire Barrier Material
Special Review Team Final Report Findings, Current Fire Endurance
Tests, and Ampacity Calculation Error,'' June 23, 1992.
27. Information Notice 91-79, ``Deficiencies in the Procedures for
Installing Thermo-Lag Fire Barrier Materials,'' December 6, 1991.
28. Information Notice 91-47, ``Failure of Thermo-Lag Fire Barrier
Material To Pass Fire Endurance Test,'' August 6, 1991.
29. Information Notice 88-56, ``Potential Problems With Silicone
Foam Fire Barrier Penetration Seals,'' August 4, 1988.
30. Generic Letter 88-12, ``Removal of Fire Protection Requirements
from Technical Specifications,'' August 2, 1988.
31. Generic Letter 86-10, ``Implementation of Fire Protection
Requirements,'' April 26, 1986.
32. Generic Letter 83-33, ``NRC Position on Certain Requirements of
Appendix R to 10 CFR Part 50,'' October 19, 1983.
33. Generic Letter 81-12, ``Fire Protection Rule (45 FR 76602,
November 19, 1980),'' February 20, 1981.
Backfit Discussion
Under the provisions of Section 182a of the Atomic Energy Act of
1954, as amended, 10 CFR 50.109(a)(4)(I) and 10 CFR 50.54(f), this
generic letter asks addressees to evaluate their facilities to confirm
compliance with the existing applicable regulatory requirements as
discussed in this generic letter. Specifically, although Hemyc and MT
fire barriers in NPPs may be relied on to protect electrical and
instrumentation cables and equipment that provide safe shutdown
capability during a fire, recent NRC testing has revealed that both
materials failed to provide the protective function intended for
compliance with existing regulations.
For plants licensed to operate before January 1, 1979, licensees
are required to comply with 10 CFR part 50, appendix R, which requires
protection of safe shutdown capabilities. One means of complying with
this requirement is to separate one safe shutdown train from its
redundant train using rated fire barriers, as cited in Appendix R,
paragraph III.G.2(a). Recent test results indicated that Hemyc and MT
fire barriers did not pass the GL 86-10, Supplement 1, criteria to
achieve a 1-hour fire rating for Hemyc or a 3-hour fire rating for MT.
Therefore, for any such plant that relies on Hemyc and/or MT for
compliance, compliance with Appendix R is in question and the
information requested by this generic letter is a compliance exception
to the rule in accordance with 10 CFR 50.109(a)(4)(I).
For plants licensed to operate after January 1, 1979, licensees are
required to comply with 10 CFR 50.48(a), which requires that each
operating nuclear power plant have a fire protection plan that
satisfies GDC 3. The fire protection plan is incorporated into the
operating license for each post-1979 plant as a license condition and
may rely on fire barriers such as Hemyc and MT to provide the required
protection. The license condition specifically cites the staff SER on
the licensee's fire protection plan, to demonstrate that the license
condition has been met (although licensees may modify their fire
protection plan as long as there is no adverse effect). However, recent
test results indicated that Hemyc and MT fire barriers did not pass the
GL 86-10, Supplement 1, criteria to achieve a 1-hour fire rating for
Hemyc or a 3-hour fire rating for MT. Therefore, for any such plant
where the staff-approved fire protection plan relies on Hemyc and/or MT
for compliance with their license condition, compliance with the
license condition is in question and the information requested by this
generic letter is a compliance exception to the rule in accordance with
10 CFR 50.109(a)(4)(I).
Federal Register Notification
A notice of opportunity for public comment on this generic letter
was published in the Federal Register (XX FR XXXXX) on July XX, 2005.
Small Business Regulatory Enforcement Fairness Act
In accordance with the Small Business Regulatory Enforcement
Fairness Act of 1996, the NRC has determined that this generic letter
is not a major rule and has verified this determination with the Office
of Information and Regulatory Affairs of the Office of Management and
Budget (OMB).
Paperwork Reduction Act Statement
This generic letter contains information collection requirements
that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501
et seq.). These information collections were approved by the Office of
Management and Budget, clearance number 3150-0011, which expires
February 28, 2007.
The burden to the public for these mandatory information
collections is estimated to average 300 hours per response, including
the time for reviewing instructions, searching existing data sources,
gathering and maintaining the data needed, and completing and reviewing
the information collection. The U.S. Nuclear Regulatory Commission is
seeking public comment on the potential impact of the information
collections contained in the generic letter and on the following
issues:
1. Is the proposed information collection necessary for the proper
performance of the functions of the NRC, including whether the
information will have practical utility?
2. Is the estimate of burden accurate?
3. Is there a way to enhance the quality, utility, and clarity of
the information collected?
4. How can the burden of the information collection be minimized,
including the use of automated collection techniques?
Send comments on any aspect of these information collections,
including suggestions for reducing the burden, to the Records and FOIA/
Privacy Services Branch (T-F52), U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001, or by Internet electronic mail to
INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information
and Regulatory Affairs, NEOB-10202 (3150-0011), Office of Management
and Budget, Washington, DC 20503.
Public Protection Notification
The NRC may not conduct or sponsor, and a person is not required to
respond to, an information collection unless the requesting document
displays a currently valid OMB control number.
Contact
Please direct any questions about this matter to the Technical
Contacts or the Lead Project Manager listed below, or to the
appropriate Office of Nuclear Reactor Regulation (NRR) project manager.
Bruce A. Boger, Director, Division of Inspection Program
Management, Office of Nuclear Reactor Regulation.
[[Page 42602]]
Technical Contacts:
Daniel Frumkin, NRR, (301) 415-2280, e-mail: dxf1@nrc.gov.
Angie Lavretta, NRR, (301) 415-3285, e-mail: axl3@nrc.gov.
Lead Project Manager:
Chandu Patel, NRR, (301) 415-3025, e-mail: cpp@nrc.gov.
Note: NRC generic communications may be found on the NRC public
Web site, https://www.nrc.gov, under Electronic Reading Room/Document
Collections.
End of Draft Generic Letter
Documents may be examined, and/or copied for a fee, at the NRC's
Public Document Room at One White Flint North, 11555 Rockville Pike
(first floor), Rockville, Maryland. Publicly available records will be
accessible electronically from the Agencywide Documents Access and
Management System (ADAMS) Public Electronic Reading Room on the
Internet at the NRC Web site, https://www.nrc.gov/NRC/ADAMS/.
If you do not have access to ADAMS or if you have problems in accessing
the documents in ADAMS, contact the NRC Public Document Room (PDR)
reference staff at 1-800-397-4209 or (301) 415-4737 or by e-mail to
pdr@nrc.gov.
Dated at Rockville, Maryland, this 18th day of July, 2005.
For the Nuclear Regulatory Commission.
Patrick L. Hiland,
Chief, Reactor Operations Branch, Division of Inspection Program
Management, Office of Nuclear Reactor Regulation.
[FR Doc. E5-3941 Filed 7-22-05; 8:45 am]