Notice of Application for Amendment of License and Soliciting Comments, Motions To Intervene, and Protests, 39267-39268 [E5-3565]
Download as PDF
Federal Register / Vol. 70, No. 129 / Thursday, July 7, 2005 / Notices
making. This filing is considered a
‘‘Comment on Filing.’’
When Sonora submits its application
for authorization to construct and
operate the Burgos Hub Expansion
Project, the Commission will publish a
Notice of Application in the Federal
Register and will establish a deadline
for interested persons to intervene in the
proceeding. Because the Commission’s
Pre-filing Process occurs before an
application to begin a proceeding is
officially filed, petitions to intervene
during this process are premature and
will not be accepted by the Commission.
Site Visit
On July 14, 2005, the OEP staff will
conduct a pre-certification site visit of
the planned Burgos Hub Export/Import
Project.
We will view the proposed route and
variations that are being considered for
the planned pipeline. Examination will
be by automobile and on foot.
Representatives of Sonora will be
accompanying the OEP staff.
All interested parties may attend.
Those planning to attend must provide
their own transportation. Those
interested in attending the site visit
should meet at 9 a.m. in parking lot of
the Renaissance Casa De Palmas Hotel,
101 N. Main Street McAllen, Texas. You
may have also been notified by Sonora
that it plans on holding an Open House
that evening, at the Renaissance Casa De
Palmas Hotel in McAllen, Texas at 6:30
p.m.
For additional information, please
contact the Commission’s Office of
External Affairs at 1–866–208–FERC
(3372).
Availability of Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs
at 1–866–208 FERC (3372) or on the
FERC Internet Web site (https://
www.ferc.gov). Using the ‘‘eLibrary’’
link, select ‘‘General Search’’ from the
eLibrary menu, enter the selected date
range and ‘‘Docket Number’’ (i.e., PF05–
15–000), and follow the instructions.
Searches may also be done using the
phrase ‘‘Burgos Hub Export/Import’’ in
the ‘‘Text Search’’ field. For assistance
with access to eLibrary, the helpline can
be reached at 1–866–208–3676, TTY
(202) 502–8659, or at
FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC Internet Web
site also provides access to the texts of
formal documents issued by the
Commission, such as orders, notices,
and rule makings.
In addition, the FERC now offers a
free service called eSubscription that
VerDate jul<14>2003
19:31 Jul 06, 2005
Jkt 205001
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. To register for this service,
go to https://www.ferc.gov/
esubscribenow.htm.
Public meetings or site visits will be
posted on the Commission’s calendar
located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
You can also contact Mr. James
Blackwell, Sonora Representative by
phone at (512) 930–2044 or by e-mail at
jimblackwell@bnceng.com with your
specific concerns or comments
regarding this project.
Magalie R. Salas,
Secretary.
[FR Doc. E5–3568 Filed 7–6–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application for Amendment
of License and Soliciting Comments,
Motions To Intervene, and Protests
June 29, 2005.
Take notice that the following
application has been filed with the
Commission and is available for public
inspection:
a. Application Type: Change in
Project Boundary, Transfer of Project
Lands, and Acquisition of Lands.
b. Project No.: 2192–022.
c. Date Filed: May 24, 2005.
d. Applicant: Consolidated Water
Power Company.
e. Name of Project: Biron.
f. Location: The project is located on
the Wisconsin River in Wood County,
Wisconsin.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a), 825(r) and 799
and 801.
h. Applicant Contact: Mr. Mike
Scheirer, Consolidated Water Power
Company, PO Box 8050, Wisconsin
Rapids, Wisconsin 54495–8050. Phone:
715/422–3927.
i. FERC Contact: Any questions on
this notice should be addressed to Mrs.
Patricia Grant at 312–596–4435, or email address: patricia.grant@ferc.gov.
j. Deadline for filing comments and or
motions: July 29, 2005.
k. All documents (original and eight
copies) should be filed with: Ms.
Magalie R. Salas, Secretary, Federal
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
39267
Energy Regulatory Commission, 888
First Street, NE., Washington DC 20426.
Please include the project number (P–
2192–022) on any comments or motions
filed. Comments, protests, and
interventions may be filed electronically
via the internet in lieu of paper. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site at https://www.ferc.gov under the ‘‘eFiling’’ link. The Commission strongly
encourages e-filings.
l. Description of Request: The licensee
filed a request, pursuant to articles 408,
409, 410, and 412 of its license, to
exchange approximately 3.14 acres of
licensee-owned lands with 3,000 linear
feet of shoreline along the Biron
flowage, for three different parcels of
land totaling approximately 205.213
total acres. The first parcel has 830
linear feet of river shoreline and
consists of 47.546 acres. The second
parcel has 126 linear feet of river
shoreline and consists of 2.960 acres,
abutting an existing licensee-owned
boat launch. The third parcel consists of
islands in the river, peninsulas, and a
roadside access totaling 154.84 acres
(48.82 acres above water). These island
perimeters, peninsulas, and the roadside
access total 33,749 linear feet of
waterfront. The licensee intends to
retain flowage rights over any
transferred lands and to retain said
lands within the project boundary.
m. Location of the Application: This
filing is available for review at the
Commission in the Public Reference
Room 888 First Street, NE, Room 2A,
Washington, DC 20426 or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the ‘‘ELibrary’’ link. Enter the docket number
excluding the last three digits in the
docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h
above.
n. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
o. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, 385.211,
385.214. In determining the appropriate
action to take, the Commission will
consider all protests or other comments
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
E:\FR\FM\07JYN1.SGM
07JYN1
39268
Federal Register / Vol. 70, No. 129 / Thursday, July 7, 2005 / Notices
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
p. Filing and Service of Responsive
Documents: Any filings must bear in all
capital letters the title ‘‘COMMENTS’’,
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’, ‘‘PROTEST’’, OR
‘‘MOTION TO INTERVENE’’, as
applicable, and the Project Number of
the particular application to which the
filing refers. A copy of any motion to
intervene must also be served upon each
representative of the Applicant
specified in the particular application.
q. Agency Comments: Federal, state,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E5–3565 Filed 7–6–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2354–087]
Georgia Power Company; Notice of
Application for Amendment of License
and Soliciting Comments, Motions To
Intervene, and Protests
June 29, 2005.
Take notice that the following
application has been filed with the
Commission and is available for public
inspection.
a. Type of Application: Amendment
of license that would allow the ClaytonRabun County Water and Sewer
Authority (Authority) to increase its
water withdrawal from Lake Rabun for
municipal water supply from 2.0
million gallons per (mgd) to 3.5 mgd.
b. Project Number: P–2354–087.
c. Date Filed: June 2, 2005.
d. Applicant: Georgia Power
Company.
e. Name of Project: North Georgia
Project (FERC No. 2354).
f. Location: Lake Rabun on the
Tallulah River, Rabun County, Georgia.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a), 825(r).
h. Applicant Contact: Mr. Scott
Hendricks, Georgia Power Company,
VerDate jul<14>2003
19:31 Jul 06, 2005
Jkt 205001
241 Ralpy McGill Boulevard NE, Bin
10151, Atlanta, GA 30308.
i. FERC Contact: Any questions on
this notice should be addressed to Mr.
John K. Novak at (202) 502–6076, or email address: john.novak@ferc.gov.
j. Deadline for filing comments and or
motions: 30 days from date of issuance
of this notice.
k. Description of Request: Georgia
Power Company is requesting
Commission authorization to permit the
Authority to increase its water
withdrawal from Lake Rabun from 2.0
mgd to 3.5 mgd to accommodate
expected growth in the Authority’s
service area. The proposal would
involve the replacement of the existing
10-inch piping from the intake pumps to
the distribution main with 16-inch
piping. No significant construction
activity would be required within the
project boundary.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street, NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
e-mail of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
e-mail FERCOnlineSupport@ferc.gov,
for TTY, call (202) 502–8659. A copy is
also available for inspection and
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, 385.211,
385.214. In determining the appropriate
action to take, the Commission will
consider all protests or other comments
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
o. Filing and Service of Responsive
Documents: Any filings must bear in all
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
capital letters the title ‘‘COMMENTS’’,
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’, ‘‘PROTEST’’, OR
‘‘MOTION TO INTERVENE’’, as
applicable, and the Project Number of
the particular application to which the
filing refers (P–2354–087). All
documents (original and eight copies)
should be filed with: Magalie R. Salas,
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington DC 20426. A copy of any
motion to intervene must also be served
upon each representative of the
Applicant specified in the particular
application.
p. Agency Comments: Federal, state,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
q. Comments, protests and
interventions may be filed electronically
via the Internet in lieu of paper. See, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site at https://www.ferc.gov under the ‘‘eFiling’’ link.
Magalie R. Salas,
Secretary.
[FR Doc. E5–3567 Filed 7–6–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. RM98–1–000]
Records Governing Off-the Record
Communications; Public Notice
June 29, 2005.
This constitutes notice, in accordance
with 18 CFR 385.2201(b), of the receipt
of prohibited and exempt off-the-record
communications.
Order No. 607 (64 FR 51222,
September 22, 1999) requires
Commission decisional employees, who
make or receive a prohibited or exempt
off-the-record communication relevant
to the merits of a contested proceeding,
to deliver to the Secretary, a copy of the
communication, if written, or a
summary of the substance of any oral
communication.
Prohibited communications are
included in a public, non-decisional file
associated with, but not a part of, the
decisional record of the proceeding.
E:\FR\FM\07JYN1.SGM
07JYN1
Agencies
[Federal Register Volume 70, Number 129 (Thursday, July 7, 2005)]
[Notices]
[Pages 39267-39268]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-3565]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Application for Amendment of License and Soliciting
Comments, Motions To Intervene, and Protests
June 29, 2005.
Take notice that the following application has been filed with the
Commission and is available for public inspection:
a. Application Type: Change in Project Boundary, Transfer of
Project Lands, and Acquisition of Lands.
b. Project No.: 2192-022.
c. Date Filed: May 24, 2005.
d. Applicant: Consolidated Water Power Company.
e. Name of Project: Biron.
f. Location: The project is located on the Wisconsin River in Wood
County, Wisconsin.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a), 825(r)
and 799 and 801.
h. Applicant Contact: Mr. Mike Scheirer, Consolidated Water Power
Company, PO Box 8050, Wisconsin Rapids, Wisconsin 54495-8050. Phone:
715/422-3927.
i. FERC Contact: Any questions on this notice should be addressed
to Mrs. Patricia Grant at 312-596-4435, or e-mail address:
patricia.grant@ferc.gov.
j. Deadline for filing comments and or motions: July 29, 2005.
k. All documents (original and eight copies) should be filed with:
Ms. Magalie R. Salas, Secretary, Federal Energy Regulatory Commission,
888 First Street, NE., Washington DC 20426. Please include the project
number (P-2192-022) on any comments or motions filed. Comments,
protests, and interventions may be filed electronically via the
internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and the
instructions on the Commission's Web site at https://www.ferc.gov under
the ``e-Filing'' link. The Commission strongly encourages e-filings.
l. Description of Request: The licensee filed a request, pursuant
to articles 408, 409, 410, and 412 of its license, to exchange
approximately 3.14 acres of licensee-owned lands with 3,000 linear feet
of shoreline along the Biron flowage, for three different parcels of
land totaling approximately 205.213 total acres. The first parcel has
830 linear feet of river shoreline and consists of 47.546 acres. The
second parcel has 126 linear feet of river shoreline and consists of
2.960 acres, abutting an existing licensee-owned boat launch. The third
parcel consists of islands in the river, peninsulas, and a roadside
access totaling 154.84 acres (48.82 acres above water). These island
perimeters, peninsulas, and the roadside access total 33,749 linear
feet of waterfront. The licensee intends to retain flowage rights over
any transferred lands and to retain said lands within the project
boundary.
m. Location of the Application: This filing is available for review
at the Commission in the Public Reference Room 888 First Street, NE,
Room 2A, Washington, DC 20426 or may be viewed on the Commission's Web
site at https://www.ferc.gov using the ``E-Library'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document. For assistance, call toll-free 1-866-208-
3676 or e-mail FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-
8659. A copy is also available for inspection and reproduction at the
address in item h above.
n. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
o. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210,
385.211, 385.214. In determining the appropriate action to take, the
Commission will consider all protests or other comments filed, but only
those who file a motion to intervene in accordance with the
Commission's Rules may become a
[[Page 39268]]
party to the proceeding. Any comments, protests, or motions to
intervene must be received on or before the specified comment date for
the particular application.
p. Filing and Service of Responsive Documents: Any filings must
bear in all capital letters the title ``COMMENTS'', ``RECOMMENDATIONS
FOR TERMS AND CONDITIONS'', ``PROTEST'', OR ``MOTION TO INTERVENE'', as
applicable, and the Project Number of the particular application to
which the filing refers. A copy of any motion to intervene must also be
served upon each representative of the Applicant specified in the
particular application.
q. Agency Comments: Federal, state, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the Applicant. If
an agency does not file comments within the time specified for filing
comments, it will be presumed to have no comments. One copy of an
agency's comments must also be sent to the Applicant's representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E5-3565 Filed 7-6-05; 8:45 am]
BILLING CODE 6717-01-P