Hydraco Power, Inc; Notice of Application Tendered for Filing With the Commission, and Soliciting Additional Study Requests, 37815-37816 [E5-3402]
Download as PDF
Federal Register / Vol. 70, No. 125 / Thursday, June 30, 2005 / Notices
avoid or lessen environmental impact.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please mail your comments so
that they will be received in
Washington, DC on or before July 25,
2005 and carefully follow these
instructions:
• Send an original and two copies of
your letter to: Magalie R. Salas,
Secretary, Federal Energy Regulatory
Commission, 888 First St., NE., Room
1A, Washington, DC 20426;
• Label one copy of the comments for
the attention of the Gas Branch 1, DG2E;
and
• Reference Docket No. PF05–11–000
on the original and both copies.
We will include all comments that we
receive within a reasonable time frame
in our environmental analysis of the
project. To expedite our receipt and
consideration of your comments, the
Commission strongly encourages
electronic submission of any comments
on this project. See Title 18 Code of
Federal Regulations 385.2001(a)(1)(iii)
and the instructions on the
Commission’s website at https://
www.ferc.gov under the ‘‘e-Filing’’ link
and the link to the User’s Guide. Before
you can submit comments, you will
need to create a free account which can
be created online.
Once FGT formally files its
application with the Commission, you
may want to become an official party to
the proceeding known as an
‘‘intervenor.’’ Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in a
Commission proceeding by filing a
request to intervene. Instructions for
becoming an intervenor are included in
the User’s Guide under the ‘‘eFiling’’
link on the Commission’s website.
Please note that you may not request
intervenor status at this time. You must
wait until a formal application is filed
with the Commission.
Affected landowners and parties with
environmental concerns may be granted
intervenor status upon showing good
cause by stating that they have a clear
and direct interest in this proceeding
that would not be adequately
represented by any other parties. You do
not need intervenor status to have your
environmental comments considered.
Environmental Mailing List
If you wish to remain on our
environmental mailing list, please
return the Information Request Form
included in Appendix 2. If you do not
VerDate jul<14>2003
16:26 Jun 29, 2005
Jkt 205001
return this form, you will be removed
from our mailing list.
Availability of Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs
at 1–866–208 FERC or on the FERC
Internet website (https://www.ferc.gov)
using the ‘‘eLibrary’’ link. Click on the
eLibrary link, click on ‘‘General
Search,’’ and enter the docket number
excluding the last three digits in the
Docket Number field (i.e., PF05–11). Be
sure you have selected an appropriate
date range. For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
contact (202) 502–8659. The eLibrary
link on the FERC Internet Web site also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
In addition, the FERC now offers a
free service called eSubscription that
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. To register for this service,
go to https://www.ferc.gov/
esubscribenow.htm.
Magalie R. Salas,
Secretary.
[FR Doc. E5–3403 Filed 6–29–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12588–000]
Hydraco Power, Inc; Notice of
Application Tendered for Filing With
the Commission, and Soliciting
Additional Study Requests
June 22, 2005.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Exemption
from License, 5 MW or Less.
b. Project No.: 12588–000.
c. Date Filed: May 3, 2005.
d. Applicant: Hydraco Power, Inc.
e. Name of Project: A. H. Smith Dam
Project.
f. Location: On the San Marcos River
near the town of Martindale, Caldwell
County, Texas.
PO 00000
Frm 00071
Fmt 4703
Sfmt 4703
37815
g. Filed Pursuant to: Public Utility
Regulatory Policies Act of 1978, 16
U.S.C. 2705, 2708.
h. Applicant Contact: Linda A. Parker,
Small Hydro of Texas, Inc., 1298 FM
766, Cuero, Texas 77954. (361) 275–
9395.
i. FERC Contact: Monte TerHaar (202)
502–6035 or monte.terhaar@ferc.gov.
j. Cooperating agencies: We are asking
Federal, state, local, and tribal agencies
with jurisdiction and/or special
expertise with respect to environmental
issues to cooperate with us in the
preparation of the environmental
document. Agencies who would like to
request cooperating status should follow
the instructions for filing comments
described in item l below.
k. Pursuant to § 4.32(b)(7) of 18 CFR
of the Commission’s regulations, if any
resource agency, Indian Tribe, or person
believes that an additional scientific
study should be conducted in order to
form an adequate factual basis for a
complete analysis of the application on
its merit, the resource agency, Indian
Tribe, or person must file a request for
a study with the Commission not later
than 60 days from the date of filing of
the application, and serve a copy of the
request on the applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: 30 days from date of this
notice.
All documents (original and eight
copies) should be filed with: Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
Additional study requests and
requests for cooperating agency status
may be filed electronically via the
Internet in lieu of paper. The
Commission strongly encourages
electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov) under the ‘‘e-Filing’’ link.
m. This application is not ready for
environmental analysis at this time.
n. The proposed project consists of:
(1) An existing 10.5-foot-high by 86.5foot-long concrete dam with a 20-footwide concrete apron; (2) an existing 3foot-wide by 4-foot-high wooden
E:\FR\FM\30JNN1.SGM
30JNN1
37816
Federal Register / Vol. 70, No. 125 / Thursday, June 30, 2005 / Notices
stopgate positioned in the east bank of
the dam; (3) a 10.62-acre impoundment;
(4) an existing 20-foot-wide by 30-footlong powerhouse; (5) an existing
generator with installed capacity of 150
kilowatts (kW); (6) an existing 150 kW
turbine; and (7) an existing trashrack of
unknown dimensions.
The proposed project consists of an
existing dam, generating equipment,
and powerhouse which ceased
hydropower generation in early 1990.
Hydraco proposes to restore these
facilities.
o. A copy of the application is on file
with the Commission and is available
for public inspection. This filing is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
online support at
ferconlinesupport@ferc.gov or toll-free
at 1–866–208–3676, or for Text
Telephone (TTY) call (202) 502–8659. A
copy is also available for inspection and
reproduction at the address in item h
above.
p. With this notice, we are initiating
consultation with the Texas State
Historic Preservation Officer (SHPO), as
required by section 106, National
Historic Preservation Act, and the
regulations of the Advisory Council on
Historic Preservation, 36 CFR 800.4.
q. Procedural schedule and final
amendments: A separate notice will be
posted with the Commission’s proposed
Hydro Licensing Schedule and a
schedule for filing final amendments to
the application.
Magalie R. Salas,
Secretary.
[FR Doc. E5–3402 Filed 6–29–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 9184–013]
Flambeau Hydro, LLC; Notice of
Application Tendered for Filing with
the Commission, Soliciting Additional
Study Requests, and Establishing
Procedural Schedule for Relicensing
and a Deadline for Submission of Final
Amendments
June 21, 2005.
Take notice that the following
hydroelectric application has been filed
VerDate jul<14>2003
16:26 Jun 29, 2005
Jkt 205001
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
License.
b. Project No.: 9184–013.
c. Date Filed: June 10, 2005.
d. Applicant: Flambeau Hydro, LLC.
e. Name of Project: Danbury
Hydroelectric Project.
f. Location: On the Yellow River in
Burnett County, near Danbury,
Wisconsin. The project does not occupy
federal lands.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Scott Klabunde,
North American Hydro, Inc., PO Box
167, Neshkoro, WI 54960; 920–293–
4628 ext. 14.
i. FERC Contact: Timothy Konnert,
(202) 502–6359 or
timothy.konnert@ferc.gov.
j. Cooperating agencies: We are asking
Federal, state, local, and tribal agencies
with jurisdiction and/or special
expertise with respect to environmental
issues to cooperate with us in the
preparation of the environmental
document. Agencies who would like to
request cooperating status should follow
the instructions for filing comments
described in item l below.
k. Pursuant to § 4.32(b)(7) of 18 CFR
of the Commission’s regulations, if any
resource agency, Indian Tribe, or person
believes that an additional scientific
study should be conducted in order to
form an adequate factual basis for a
complete analysis of the application on
its merit, the resource agency, Indian
Tribe, or person must file a request for
a study with the Commission not later
than 60 days from the date of filing of
the application, and serve a copy of the
request on the applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: August 8, 2005.
All documents (original and eight
copies) should be filed with: Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
Additional study requests and
requests for cooperating agency status
may be filed electronically via the
Internet in lieu of paper. The
PO 00000
Frm 00072
Fmt 4703
Sfmt 4703
Commission strongly encourages
electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov) under the ‘‘eFiling’’ link.
m. This application is not ready for
environmental analysis at this time.
n. The existing Clam River Project
consists of: (1) A 30-foot-high dam with
a 48-foot-long, three-bay concrete
spillway section equipped with six steel
slide gates; (2) a 300-foot-long earthen
dike that connects to the north side of
the spillway; (3) a 255-acre reservoir
with a normal water surface elevation of
929.0 feet msl; (4) a forebay structure
with two steel slide gates leading to; (5)
two 26-foot-long, 5.75-foot-diameter
penstocks to convey flow to; (6)
powerhouse 1 integral with the dam
containing two generating units with a
combined capacity of 476 kW; (7) a
power canal headworks structure with
stoplogs; (8) a 53-foot-wide, 2,500-footlong power canal; (9) a 95-foot-long,
1.67-foot-diameter penstock to convey
flow from the power canal to; (10)
powerhouse 2 containing a generating
unit with a capacity of 600 kW; and (11)
appurtenant facilities. The applicant
estimates that the average annual
generation would be 3,844 megawatt
hours using the three generating units
with a combined capacity of 1,076 kW.
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. With this notice, we are initiating
consultation with the Wisconsin State
Historic Preservation Officer (SHPO), as
required by section 106, National
Historic Preservation Act, and the
regulations of the Advisory Council on
Historic Preservation, 36 CFR 800.4.
q. Procedural schedule and final
amendments: The application will be
processed according to the following
Hydro Licensing Schedule. Revisions to
the schedule will be made as
appropriate. The Commission staff
E:\FR\FM\30JNN1.SGM
30JNN1
Agencies
[Federal Register Volume 70, Number 125 (Thursday, June 30, 2005)]
[Notices]
[Pages 37815-37816]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-3402]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12588-000]
Hydraco Power, Inc; Notice of Application Tendered for Filing
With the Commission, and Soliciting Additional Study Requests
June 22, 2005.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Exemption from License, 5 MW or Less.
b. Project No.: 12588-000.
c. Date Filed: May 3, 2005.
d. Applicant: Hydraco Power, Inc.
e. Name of Project: A. H. Smith Dam Project.
f. Location: On the San Marcos River near the town of Martindale,
Caldwell County, Texas.
g. Filed Pursuant to: Public Utility Regulatory Policies Act of
1978, 16 U.S.C. 2705, 2708.
h. Applicant Contact: Linda A. Parker, Small Hydro of Texas, Inc.,
1298 FM 766, Cuero, Texas 77954. (361) 275-9395.
i. FERC Contact: Monte TerHaar (202) 502-6035 or
monte.terhaar@ferc.gov.
j. Cooperating agencies: We are asking Federal, state, local, and
tribal agencies with jurisdiction and/or special expertise with respect
to environmental issues to cooperate with us in the preparation of the
environmental document. Agencies who would like to request cooperating
status should follow the instructions for filing comments described in
item l below.
k. Pursuant to Sec. 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: 30 days from date of this notice.
All documents (original and eight copies) should be filed with:
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
Additional study requests and requests for cooperating agency
status may be filed electronically via the Internet in lieu of paper.
The Commission strongly encourages electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
(https://www.ferc.gov) under the ``e-Filing'' link.
m. This application is not ready for environmental analysis at this
time.
n. The proposed project consists of: (1) An existing 10.5-foot-high
by 86.5-foot-long concrete dam with a 20-foot-wide concrete apron; (2)
an existing 3-foot-wide by 4-foot-high wooden
[[Page 37816]]
stopgate positioned in the east bank of the dam; (3) a 10.62-acre
impoundment; (4) an existing 20-foot-wide by 30-foot-long powerhouse;
(5) an existing generator with installed capacity of 150 kilowatts
(kW); (6) an existing 150 kW turbine; and (7) an existing trashrack of
unknown dimensions.
The proposed project consists of an existing dam, generating
equipment, and powerhouse which ceased hydropower generation in early
1990. Hydraco proposes to restore these facilities.
o. A copy of the application is on file with the Commission and is
available for public inspection. This filing is available for review at
the Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC online support at ferconlinesupport@ferc.gov or toll-free at 1-
866-208-3676, or for Text Telephone (TTY) call (202) 502-8659. A copy
is also available for inspection and reproduction at the address in
item h above.
p. With this notice, we are initiating consultation with the Texas
State Historic Preservation Officer (SHPO), as required by section 106,
National Historic Preservation Act, and the regulations of the Advisory
Council on Historic Preservation, 36 CFR 800.4.
q. Procedural schedule and final amendments: A separate notice will
be posted with the Commission's proposed Hydro Licensing Schedule and a
schedule for filing final amendments to the application.
Magalie R. Salas,
Secretary.
[FR Doc. E5-3402 Filed 6-29-05; 8:45 am]
BILLING CODE 6717-01-P