Transcontinental Gas Pipe Line Corporation; Notice of Application for Abandonment, 36136-36137 [E5-3248]
Download as PDF
36136
Federal Register / Vol. 70, No. 119 / Wednesday, June 22, 2005 / Notices
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Protest Date: 5 p.m. Eastern Time on
June 23, 2005.
Magalie R. Salas,
Secretary.
[FR Doc. E5–3244 Filed 6–21–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP05–362–000]
Transcontinental Gas Pipe Line
Corporation; Notice of Application for
Abandonment
June 16, 2005.
Take notice that on May 27, 2005,
Transcontinental Gas Pipe Line
Corporation (Transco) tendered for
filing an application under Section 7 of
the Natural Gas Act to abandon the firm
transportation service provided to
Eastern Shore Natural Gas Company
(Eastern Shore) under Transco’s Rate
Schedule FT.
Transco states that it currently
renders for Eastern Shore, under a
service agreement dated February 1,
1992, firm transportation service under
Transco’ s Rate Schedule FT. Transco
explains that service agreement sets
forth the terms and conditions under
which Transco provides firm
transportation of 2,815 Dt of gas per day
for Eastern Shore. Although the firm
transportation service is being rendered
by Transco pursuant to Transco’s
blanket certificate authorization under
Part 284(G) of the Commission’s
regulations, Transco states that it
requires specific Section 7(b)
abandonment authorization (instead of
simply abandoning the service
automatically under Section 284.221(d)
of the regulations) because: (1) The
subject FT service for Eastern Shore was
previously converted from firm sales
service to firm transportation service
under Transco’s Rate Schedule FT
pursuant to Transco’s revised
Stipulation and Agreement in Docket
Nos. RP88–68, et al.; and (2) the
settlement provides that pre-granted
abandonment shall not apply to such
conversions (as further described in
Article IV of the Service Agreement). As
is more fully explained in the
application, Transco proposes to
abandon the 2,815 Dt/day of firm
transportation service to Eastern Shore
to allow Eastern Shore to effectuate a
VerDate jul<14>2003
21:12 Jun 21, 2005
Jkt 205001
prearranged permanent release of that
capacity.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed in accordance
with the provisions of Section 154.210
of the Commission’s regulations (18 CFR
154.210). Anyone filing an intervention
or protest must serve a copy of that
document on the Applicant. Anyone
filing an intervention or protest on or
before the intervention or protest date
need not serve motions to intervene or
protests on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Magalie R. Salas,
Secretary.
[FR Doc. E5–3245 Filed 6–21–05; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP05–373–000]
Transcontinental Gas Pipe Line
Corporation; Notice of Application for
Abandonment
June 15, 2005.
Take notice that on June 8, 2005,
Transcontinental Gas Pipe Line
Corporation (Transco) tendered for
filing an application under section 7 of
the Natural Gas Act to abandon the firm
transportation service provided to the
customers listed on Exhibit Z1 of the
application (Cities) under Transco’s
Rate Schedule FT pursuant to Service
Agreements dated February 1, 1992.
Transco states that the service
agreements, included in Exhibit U of the
application, set forth the terms and
conditions under which Transco
provides firm transportation up to
maximum quantities for each customer.
Transco further states that although the
firm transportation service is being
tendered by Transco pursuant to
Transco’s blanket certificate
authorizations under Part 284(G) of the
Commission’s regulations, Transco
requires specific section 7(b)
abandonment authorization (instead of
simply abandoning the service
automatically under Section 284.221(d)
of the regulations) because the subject
FT service for the Cities was previously
converted from firm sales service to firm
transportation service under Transco’s
Rate Schedule FT pursuant to Transco’s
revised Stipulation and Agreement in
Docket Nos. RP88–68, et al. Transco
notes that the settlement provides that
pre-granted abandonment shall not
apply to such conversions.
Transco states that it proposes to
abandon the aforementioned firm
transportation service to the Cities in
order that the Cities may implement a
permanent release of that capacity in
accordance with the terms of Transco’s
tariff to the prearranged replacement
buyer, the Municipal Gas Authority of
Georgia.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
E:\FR\FM\22JNN1.SGM
22JNN1
Federal Register / Vol. 70, No. 119 / Wednesday, June 22, 2005 / Notices
protests must be filed on or before the
date as indicated below. Anyone filing
an intervention or protest must serve a
copy of that document on the Applicant.
Anyone filing an intervention or protest
on or before the intervention or protest
date need not serve motions to intervene
or protests on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment: 5 pm Eastern Time July 6,
2005.
Magalie R. Salas,
Secretary.
[FR Doc. E5–3248 Filed 6–21–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP05–378–000]
Transcontinental Gas Pipe Line
Corporation; Notice of Application for
Abandonment
June 15, 2005.
Take notice that on June 8, 2005,
Transcontinental Gas Pipe Line
Corporation (Transco) tendered for
filing an application under section 7 of
the Natural Gas Act to abandon the firm
transportation service provided to the
City of Monroe, Georgia (Monroe) under
Transco’s Rate Schedule FT pursuant to
the Service Agreement dated August 1,
1991.
Transco states that although the firm
transportation service is being rendered
by it pursuant to Transco’s blanket
certificate authorization under Part 284
(G) of the Commission’s regulations,
Transco requires specific section 7(b)
VerDate jul<14>2003
21:12 Jun 21, 2005
Jkt 205001
abandonment authorization (instead of
simply abandoning the service
automatically under section 284.221(d)
of the regulations) because the subject
FT service for Monroe was previously
converted from firm sales service under
Transco’s then existing Rate Schedule
PS to firm transportation service under
Transo’s Rate Schedule FT pursuant to
Transco’s Stipulation and Agreement in
Docket Nos. RP87–7, et al. Transco
notes that the settlement provides that
pre-granted abandonment shall not
apply to such conversions.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
date as indicated below. Anyone filing
an intervention or protest must serve a
copy of that document on the Applicant.
Anyone filing an intervention or protest
on or before the intervention or protest
date need not serve motions to intervene
or protests on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 pm Eastern Time
July 6, 2005.
Magalie R. Salas,
Secretary.
[FR Doc. E5–3249 Filed 6–21–05; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00029
Fmt 4703
Sfmt 4703
36137
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice Of Filings #1
June 16, 2005.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER02–388–004.
Applicants: HC Power Marketing LLC.
Description: HC Power Marketing LLC
submits First Revised Sheet 3 to its Rate
Schedule FERC 1, which incorporates
the reporting requirement for changes in
status for public utilities with marketbased rates set forth in Commission
Order No. 652 .
Filed Date: June 14, 2005.
Accession Number: 20050616–0113.
Comment Date: 5 p.m. Eastern Time
on Tuesday, July 5, 2005.
Docket Numbers: ER04–691–030.
Applicants: Midwest Independent
Transmission System Operator, Inc.
Description: Potomac Economics,
Ltd., as the Independent Market Monitor
for the Midwest Independent
Transmission System Operator, Inc.,
provides a list of generators subject to
Narrow Constrained Area thresholds.
Filed Date: June 13, 2005.
Accession Number: 20050615–0001.
Comment Date: 5 p.m. Eastern Time
on Tuesday, July 5, 2005.
Docket Numbers: ER04–691–046;
EL04–104–044
Applicants: Midwest Independent
Transmission System Operator, Inc.
Description: Midwest Independent
Transmission System Operator, Inc
submits proposed revisions to its Open
Access Transmission and Energy
Markets Tariff in compliance with
FERC’s Order issued on 4/15/05, 111
FERC ¶ 61,043 (2005)
Filed Date: June 14, 2005.
Accession Number: 20050616–0005.
Comment Date: 5 p.m. Eastern Time
on Tuesday, July 5, 2005.
Docket Numbers: ER04–691–047;
EL04–104–045
Applicants: Midwest Independent
Transmission System Operator, Inc.
Description: Midwest Independent
Transmission System Operator Inc
submits proposed revisions to its Open
Access Transmission and Energy
Markets Tariff, FERC Electric Tariff,
Third Revised Volume 1, in compliance
with FERC’s Order issued 4/15/05, 111
¶ FERC 61,043 (2005).
Filed Date: June 14, 2005.
Accession Number: 20050616–0111.
Comment Date: 5 p.m. Eastern Time
on Tuesday, July 5, 2005.
E:\FR\FM\22JNN1.SGM
22JNN1
Agencies
[Federal Register Volume 70, Number 119 (Wednesday, June 22, 2005)]
[Notices]
[Pages 36136-36137]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-3248]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP05-373-000]
Transcontinental Gas Pipe Line Corporation; Notice of Application
for Abandonment
June 15, 2005.
Take notice that on June 8, 2005, Transcontinental Gas Pipe Line
Corporation (Transco) tendered for filing an application under section
7 of the Natural Gas Act to abandon the firm transportation service
provided to the customers listed on Exhibit Z1 of the application
(Cities) under Transco's Rate Schedule FT pursuant to Service
Agreements dated February 1, 1992. Transco states that the service
agreements, included in Exhibit U of the application, set forth the
terms and conditions under which Transco provides firm transportation
up to maximum quantities for each customer. Transco further states that
although the firm transportation service is being tendered by Transco
pursuant to Transco's blanket certificate authorizations under Part
284(G) of the Commission's regulations, Transco requires specific
section 7(b) abandonment authorization (instead of simply abandoning
the service automatically under Section 284.221(d) of the regulations)
because the subject FT service for the Cities was previously converted
from firm sales service to firm transportation service under Transco's
Rate Schedule FT pursuant to Transco's revised Stipulation and
Agreement in Docket Nos. RP88-68, et al. Transco notes that the
settlement provides that pre-granted abandonment shall not apply to
such conversions.
Transco states that it proposes to abandon the aforementioned firm
transportation service to the Cities in order that the Cities may
implement a permanent release of that capacity in accordance with the
terms of Transco's tariff to the prearranged replacement buyer, the
Municipal Gas Authority of Georgia.
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. Such notices,
motions, or
[[Page 36137]]
protests must be filed on or before the date as indicated below. Anyone
filing an intervention or protest must serve a copy of that document on
the Applicant. Anyone filing an intervention or protest on or before
the intervention or protest date need not serve motions to intervene or
protests on persons other than the Applicant.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at https://
www.ferc.gov. Persons unable to file electronically should submit an
original and 14 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at https://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC There is an ``eSubscription''
link on the Web site that enables subscribers to receive email
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please email
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Comment: 5 pm Eastern Time July 6, 2005.
Magalie R. Salas,
Secretary.
[FR Doc. E5-3248 Filed 6-21-05; 8:45 am]
BILLING CODE 6717-01-P