Download as PDF 35030 Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations 5. Cardiovascular System (4.00 and 104.00): July 3, 2006. 6. Digestive System (5.00 and 105.00): July 3, 2006. 7. Genito-Urinary System (6.00 and 106.00): July 3, 2006. 8. Hematological Disorders (7.00 and 107.00): July 2, 2007. * * * * * 10. Endocrine System (9.00 and 109.00): July 2, 2007. 11. Multiple Body Systems (10.00): June 19, 2008 and (110.00): July 3, 2006. 12. Neurological (11.00 and 111.00): July 2, 2007. 13. Mental Disorders (12.00 and 112.00): July 2, 2007. * * * * * 15. Immune System (14.00 and 114.00): July 2, 2007. * * * * * [FR Doc. 05–11887 Filed 6–15–05; 8:45 am] BILLING CODE 4191–02–P DEPARTMENT OF HOMELAND SECURITY Coast Guard 33 CFR Part 117 [CGD08–05–039] Drawbridge Operation Regulations; Corpus Christi—Port Aransas Channel—Tule Lake, Corpus Christi, TX Coast Guard, DHS. Notice of temporary deviation from regulations. AGENCY: ACTION: SUMMARY: The Commander, Eighth Coast Guard District, has issued a temporary deviation from the regulation governing the operation of the Tule Lake Vertical Lift Span Highway and Railroad Bridge across the Corpus Christi—Port Aransas Channel, mile 14.0, at Corpus Christi, Nueces County, TX. This deviation allows the bridge to remain closed to navigation for six hours each day for three consecutive days. This temporary deviation is necessary for the repair of the haul rope anchors of the drawbridge. This deviation is effective from 8:30 a.m. on Tuesday, July 12, 2005, through 2:30 p.m. on Thursday, July 14, 2005. ADDRESSES: Materials referred to in this document are available for inspection or copying at the office of the Eighth Coast Guard District, Bridge Administration Branch, Hale Boggs Federal Building, room 1313, 500 Poydras Street, New Orleans, Louisiana 70130–3310 between 7 a.m. and 3 p.m., Monday through Friday, except Federal holidays. The DATES: VerDate jul<14>2003 16:54 Jun 15, 2005 Jkt 205001 telephone number is (504) 589–2965. The Bridge Administration Branch of the Eighth Coast Guard District maintains the public docket for this temporary deviation. Phil Johnson, Bridge Administration Branch, telephone (504) 589–2965. FOR FURTHER INFORMATION CONTACT: The Port of Corpus Christi Authority has requested a temporary deviation in order to repair the haul rope anchors of the Tule Lake vertical lift span bridge across Corpus Christi—Port Aransas Channel, mile 14.0 at Corpus Christi, Nueces County, Texas. This temporary deviation will allow the bridge to remain in the closed-to-navigation position from 8:30 a.m. to 2:30 p.m. on Tuesday, July 12, on Wednesday, July 13, and on Thursday, July 14, 2005. The bridge has a vertical clearance of 9.0 feet above mean high water, elevation 1.0 foot Mean Sea Level and 11.0 feet above mean low water, elevation ¥1.0 foot Mean Sea Level in the closed-to-navigation position. Navigation at the site of the bridge consists mainly of oil tankers and tows with barges. Recreational vessels do not generally transit this segment of the waterway. Due to prior experience, as well as coordination with waterway users, it has been determined that this three-day partial closure will not have a significant effect on these vessels. The bridge normally opens to pass navigation an average of 850 times per month. The bridge opens on signal as required by 33 CFR 117.5. The bridge may not be able to open for emergencies during the closure period. Alternate routes are not available. In accordance with 33 CFR 117.35(c), this work will be performed with all due speed in order to return the bridge to normal operation as soon as possible. This deviation from the operating regulations is authorized under 33 CFR 117.35. SUPPLEMENTARY INFORMATION: Dated: June 9, 2005. Marcus Redford, Bridge Administrator. [FR Doc. 05–11849 Filed 6–15–05; 8:45 am] BILLING CODE 4910–15–P PO 00000 Frm 00046 Fmt 4700 Sfmt 4700 DEPARTMENT OF HOMELAND SECURITY Coast Guard 33 CFR Part 117 [CGD13–05–020] RIN 1625–AA09 Drawbridge Operation Regulations; Duwamish Waterway, Seattle, WA Coast Guard, DHS. Temporary final rule. AGENCY: ACTION: SUMMARY: The Coast Guard has temporarily changed the operating regulations for the First Avenue South dual drawbridges across the Duwamish Waterway, mile 2.5, at Seattle, Washington. The change allows the bridge owner to keep the bridges closed during night hours from July 15 to November 15, 2005, between 9 p.m. and 5 a.m. Sunday through Friday. This will facilitate painting the structures while properly containing debris and paint. DATES: This rule is effective from 9 p.m. July 15, 2005, to 5 a.m. November 15, 2005. ADDRESSES: Comments and material received from the public as well as documents referred to in this preamble as being available in the docket, are part of docket (CGD13–04–047) and are available for inspection or copying at 13th Coast Guard District, Aids to Navigation and Waterways Management Branch, 915 Second Avenue, Seattle, WA 98174–1067 between 7:30 a.m. and 4 p.m., Monday through Friday, except Federal holidays. FOR FURTHER INFORMATION CONTACT: Austin Pratt, Chief Bridge Section, (206) 220–7282. SUPPLEMENTARY INFORMATION: Regulatory Information On January 21, 2005, we published a notice of proposed rulemaking (NPRM) entitled Drawbridge Operation Regulations; Duwamish Waterway, Seattle, Washington, in the Federal Register (70 FR 3168). We received no comments in response to the notice of proposed rulemaking. No public hearing was requested and none was held. Background and Purpose The dual First Avenue South bascule bridges provide 32 feet of vertical clearance above mean high water for the central 100 feet of horizontal distance in the channel spans. When the drawspans are open there is unlimited vertical clearance for the central 120 feet of the spans. Drawbridge openings are provided for recreational vessels, large E:\FR\FM\16JNR1.SGM 16JNR1

Agencies

[Federal Register Volume 70, Number 115 (Thursday, June 16, 2005)]
[Rules and Regulations]
[Page 35030]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 05-11849]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF HOMELAND SECURITY

Coast Guard

33 CFR Part 117

[CGD08-05-039]


Drawbridge Operation Regulations; Corpus Christi--Port Aransas 
Channel--Tule Lake, Corpus Christi, TX

AGENCY: Coast Guard, DHS.

ACTION: Notice of temporary deviation from regulations.

-----------------------------------------------------------------------

SUMMARY: The Commander, Eighth Coast Guard District, has issued a 
temporary deviation from the regulation governing the operation of the 
Tule Lake Vertical Lift Span Highway and Railroad Bridge across the 
Corpus Christi--Port Aransas Channel, mile 14.0, at Corpus Christi, 
Nueces County, TX. This deviation allows the bridge to remain closed to 
navigation for six hours each day for three consecutive days. This 
temporary deviation is necessary for the repair of the haul rope 
anchors of the drawbridge.

DATES: This deviation is effective from 8:30 a.m. on Tuesday, July 12, 
2005, through 2:30 p.m. on Thursday, July 14, 2005.

ADDRESSES: Materials referred to in this document are available for 
inspection or copying at the office of the Eighth Coast Guard District, 
Bridge Administration Branch, Hale Boggs Federal Building, room 1313, 
500 Poydras Street, New Orleans, Louisiana 70130-3310 between 7 a.m. 
and 3 p.m., Monday through Friday, except Federal holidays. The 
telephone number is (504) 589-2965. The Bridge Administration Branch of 
the Eighth Coast Guard District maintains the public docket for this 
temporary deviation.

FOR FURTHER INFORMATION CONTACT: Phil Johnson, Bridge Administration 
Branch, telephone (504) 589-2965.

SUPPLEMENTARY INFORMATION: The Port of Corpus Christi Authority has 
requested a temporary deviation in order to repair the haul rope 
anchors of the Tule Lake vertical lift span bridge across Corpus 
Christi--Port Aransas Channel, mile 14.0 at Corpus Christi, Nueces 
County, Texas. This temporary deviation will allow the bridge to remain 
in the closed-to-navigation position from 8:30 a.m. to 2:30 p.m. on 
Tuesday, July 12, on Wednesday, July 13, and on Thursday, July 14, 
2005.
    The bridge has a vertical clearance of 9.0 feet above mean high 
water, elevation 1.0 foot Mean Sea Level and 11.0 feet above mean low 
water, elevation -1.0 foot Mean Sea Level in the closed-to-navigation 
position. Navigation at the site of the bridge consists mainly of oil 
tankers and tows with barges. Recreational vessels do not generally 
transit this segment of the waterway. Due to prior experience, as well 
as coordination with waterway users, it has been determined that this 
three-day partial closure will not have a significant effect on these 
vessels. The bridge normally opens to pass navigation an average of 850 
times per month. The bridge opens on signal as required by 33 CFR 
117.5. The bridge may not be able to open for emergencies during the 
closure period. Alternate routes are not available.
    In accordance with 33 CFR 117.35(c), this work will be performed 
with all due speed in order to return the bridge to normal operation as 
soon as possible. This deviation from the operating regulations is 
authorized under 33 CFR 117.35.

    Dated: June 9, 2005.
Marcus Redford,
Bridge Administrator.
[FR Doc. 05-11849 Filed 6-15-05; 8:45 am]
BILLING CODE 4910-15-P