Regulations Governing the Conduct of Open Seasons for Alaska Natural Gas Transportation Projects, 35011-35027 [05-11658]
Download as PDF
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
ii. Power Factor Design Criteria (Reactive
Power)
needed to allow the Transmission Provider to
complete the System Impact Study.
A wind generating plant shall maintain a
power factor within the range of 0.95 leading
to 0.95 lagging, measured at the Point of
Interconnection as defined in this LGIA, if
the Transmission Provider’s System Impact
Study shows that such a requirement is
necessary to ensure safety or reliability. The
power factor range standard can be met by
using, for example, power electronics
designed to supply this level of reactive
capability (taking into account any
limitations due to voltage level, real power
output, etc.) or fixed and switched capacitors
if agreed to by the Transmission Provider, or
a combination of the two. The
Interconnection Customer shall not disable
power factor equipment while the wind plant
is in operation. Wind plants shall also be able
to provide sufficient dynamic voltage support
in lieu of the power system stabilizer and
automatic voltage regulation at the generator
excitation system if the System Impact Study
shows this to be required for system safety
or reliability.
[FR Doc. 05–11678 Filed 6–15–05; 8:45 am]
iii. Supervisory Control and Data Acquisition
(SCADA) Capability
The wind plant shall provide SCADA
capability to transmit data and receive
instructions from the Transmission Provider
to protect system reliability. The
Transmission Provider and the wind plant
Interconnection Customer shall determine
what SCADA information is essential for the
proposed wind plant, taking into account the
size of the plant and its characteristics,
location, and importance in maintaining
generation resource adequacy and
transmission system reliability in its area.
Appendix C
Note: These provisions to be adopted as
Appendix G to the LGIP.
Appendix G—Interconnection
Procedures for a Wind Generating Plant
Appendix G sets forth procedures specific
to a wind generating plant. All other
requirements of this LGIP continue to apply
to wind generating plant interconnections.
A. Special Procedures Applicable to Wind
Generators
The wind plant Interconnection Customer,
in completing the Interconnection Request
required by section 3.3 of this LGIP, may
provide to the Transmission Provider a set of
preliminary electrical design specifications
depicting the wind plant as a single
equivalent generator. Upon satisfying these
and other applicable Interconnection Request
conditions, the wind plant may enter the
queue and receive the base case data as
provided for in this LGIP.
No later than six months after submitting
an Interconnection Request completed in this
manner, the wind plant Interconnection
Customer must submit completed detailed
electrical design specifications and other data
(including collector system layout data)
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
18 CFR Part 157
[Docket No. RM05–1–001; Order No. 2005–
A]
Regulations Governing the Conduct of
Open Seasons for Alaska Natural Gas
Transportation Projects
Issued June 1, 2005.
Federal Energy Regulatory
Commission.
ACTION: Final rule; order on rehearing.
AGENCY:
SUMMARY: The Federal Energy
Regulatory Commission (Commission)
generally reaffirms its determinations in
Order No. 2005. Order No. 2005
establishes requirements governing the
conduct of open seasons for proposals to
construct Alaska natural gas
transportation projects, including
procedures for allocation of capacity.
Pursuant to the directive of section
103(e)(2) of the Alaska Natural Gas
Pipeline Act, enacted on October 13,
2004, the regulations promulgated in
Order No. 2005 include the criteria for
and timing of any open season, promote
competition in the exploration,
development, and production of Alaska
natural gas, and for any open seasons for
capacity exceeding the initial capacity,
provide for the opportunity for the
transportation of natural gas other than
from the Prudhoe Bay and Point
Thomson units.
In this order, the Commission
addresses the requests for rehearing
and/or clarification of Order No. 2005.
Here, we grant rehearing in part, deny
rehearing in part, and provide
clarification of Order No. 2005. In
specific, we: Clarify that the
Commission may require design
changes necessary to ensure that some
portion of a proposed voluntary
expansion will be allocated to new
shippers or shippers seeking to
transport gas from areas other than
Prudhoe Bay or Point Thomson,
provided such shippers are willing to
sign qualifying long-term firm
transportation agreements; codify the
expanded criteria for evaluating late
bids for capacity and the requirement
that any late bid contain a good faith
showing; in the case of the mandatory
pre-review, codify that the plan to be
PO 00000
Frm 00027
Fmt 4700
Sfmt 4700
35011
filed by the Commission must contain
the open season notice, and eliminates
the 30-day prior notice requirement;
discuss how the open season rules may
apply to jurisdictional gas treatment
plants; clarify that capacity bid for the
open season is exempt from allocation
only in a case where there is also
presubscribed capacity, and that in the
event there are more than one presubscription agreement, bidders in the
open season may not cherry-pick among
the provisions of the several agreements;
clarify the project applicant’s obligation
to establish a separate entity to conduct
the open season; and further codify the
requirements of the catchall provision
regarding information to be included in
an open season notice.
DATES: Effective Date: Revisions in this
order on rehearing will become effective
on June 16, 2005.
FOR FURTHER INFORMATION CONTACT:
Whit Holden, Office of the General
Counsel, (202) 502–8089,
edwin.holden@ferc.gov; Richard Foley,
Office of Energy Projects, (202) 502–
8955, richard.foley@ferc.gov; Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
SUPLEMENTARY INFORMATION:
Before Commissioners: Pat Wood, III,
Chairman; Nora Mead Brownell, Joseph
T. Kelliher, and Suedeen G. Kelly.
Order on Rehearing and Clarification
1. On February 9, 2005, the Federal
Energy Regulatory Commission
(Commission) issued a Final Rule, Order
No. 2005,1 amending its regulations by
adding Subpart B to Part 157 to
establish requirements governing the
conduct of open seasons for capacity on
proposals to construct Alaska natural
gas transportation projects. Order No.
2005 fulfilled the Commission’s
responsibilities to issue open season
regulations under section 103 of the
Alaska Natural Gas Pipeline Act
(ANGPA or the Act), enacted on October
13, 2004. Section 103(e)(1) of the Act
directs the Commission, within 120
days from enactment of the Act, to
promulgate regulations governing the
conduct of open seasons for Alaska
natural gas transportation projects,
including procedures for allocation of
capacity. As required by section
103(e)(2) of the Act, the regulations
promulgated in Order No. 2005 (1)
include the criteria for and timing of
any open season, (2) promote
competition in the exploration,
development, and production of Alaska
1 Regulations Governing the Conduct of Open
Seasons for Alaska Natural Gas Transportation
Projects, RM05–1–000, Order No. 2005, FERC Stats.
and Regs. ¶ 31,174 (2005).
E:\FR\FM\16JNR1.SGM
16JNR1
35012
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
natural gas, and (3) for any open seasons
for capacity exceeding the initial
capacity, provide for the opportunity for
the transportation of natural gas other
than from the Prudhoe Bay and Point
Thomson units.
2. The Commission affirms here the
legal and policy conclusions on which
Order No. 2005 was based. As stated in
Order No. 2005, the goal of the open
season regulations is to design an open
season process that provides nondiscriminatory access to capacity on any
Alaska natural gas transportation project
and, at the same time, allows sufficient
economic certainty to support the
construction of the pipeline and thereby
provide a stimulus for exploration,
development, and production of Alaska
natural gas. We find that Order No.
2005’s open season rules as revised and
clarified herein, satisfy that goal and,
therefore, are in the public interest.
Background
3. ANGPA mandates the expedited
processing by the Commission of any
application for an Alaska natural gas
transportation project. To this end, as
stated above, section 103(e)(1) of the Act
specifically directs the Commission to
prescribe the rules which shall apply to
any open season held for the purpose of
soliciting interest in, or making binding
commitments to the acquisition of
capacity on, any Alaska natural gas
transportation project, including the
criteria for allocating capacity among
competing bidders. In this regard,
Congress instructed the Commission to
include in its regulations the criteria for,
and timing of, any open season, and to
design its open season regulations to
promote competition in the exploration,
development, and production of Alaska
natural gas and, as to any open season
for the voluntary expansion 2 of the
initial capacity of any Alaska natural gas
transportation project, to specifically
provide the opportunity for gas other
than Prudhoe Bay and Point Thomson
production to have access to the
pipeline.
4. In response to the Act’s directive,
on November 15, 2004, the Commission
issued in Docket No. RM05–1–000 a
Notice of Proposed Rulemaking (NOPR)
in this proceeding containing the
Commission’s proposed Alaska natural
gas transportation project open season
regulations. Also, the Commission held
a public technical conference in
2 Excluded from the scope of the open season
rules are expansions compelled by the Commission
pursuant to section 105 of the Act. Section 105
authorizes the Commission to order these
‘‘involuntary’’ expansions upon the request of one
or more persons, and upon the satisfaction of
certain statutory criteria.
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
Anchorage, Alaska on December 3, 2004
to develop a record in this proceeding.
The Commission received 25 comments
in response to the NOPR.
5. On February 9, 2005, the
Commission issued Order No. 2005. The
open season regulations contained in
Order No. 2005 apply to any application
for a certificate or other Commission
authorization for an Alaska natural gas
transportation project, whether filed
pursuant to the NGA, the Alaska Natural
Gas Transportation Act of 1976, or
ANGPA, as well as to any voluntary
applications for expansions of such a
project.
6. The Final Rule adopted the NOPR’s
proposed requirements that the
applicant provide a 30-day prior public
notice containing extensive information
intended to allow all interested persons
to decide whether to participate in the
open season, followed by an actual open
season period of at least 90 days. The
regulations in the Final Rule also
adopted the NOPR’s approach of
allowing prospective applicants to
develop and state in detail the
methodologies for determining the value
of bids and for allocating capacity,
subject to the requirement that all
capacity be awarded without undue
discrimination or preference of any
kind. In addition, the Final Rule
required that at least 90 days prior to
providing the open season notice, the
prospective applicant must file its open
season plan with the Commission for
approval, and that the Commission will
act on the plan within 60 days of its
filing.
7. The Final Rule provided that
prospective applicants must conduct or
adopt a study of Alaska’s in-state needs,
and use the study results to design
capacity needs for use within the state,
and design in-state delivery points and
in-state transportation rates as part of an
open season. Moreover, bidding on instate capacity must be conducted
independent of out-of-state deliveries
during a prospective applicant’s open
season.
8. In order to further the
Commission’s goal of a nondiscriminatory open season, the Final
Rule applied certain of the Standards of
Conduct requirements of Order No.
2004, including the establishment of an
independent, functionally-separate unit
to conduct the open season. In addition,
the open season notice must identify the
prospective applicant’s affiliates
involved in the production of natural
gas in the state of Alaska, and all
information about the open season
disclosed to any potential shippers must
be made available to all potential
shippers.
PO 00000
Frm 00028
Fmt 4700
Sfmt 4700
9. The Final Rule permitted presubscription by anchor shippers, limited
to initial capacity only, in order to
facilitate the development of an Alaska
pipeline project. However, to ensure
that all other potential shippers have an
equal opportunity to obtain access to
capacity on the project in the open
season, all pre-subscription agreements
must be made public within ten days of
their execution, and capacity on the
proposed project must be offered to all
prospective qualifying shippers under
the same terms and conditions and at
the same rates as the pre-subscription
agreements. In addition, if capacity is
oversubscribed in the open season and
it is not feasible to redesign the
proposed project to meet both the presubscription shippers’ and the open
season shippers’ capacity needs, then
capacity bid for in the open season will
not be reduced, but all capacity subject
to the terms and conditions of presubscription agreements will be
allocated pro rata.
10. In an effort to allow as many
potential shippers as possible the
opportunity to acquire capacity in the
initial open season, the Final Rule
required that the project sponsor must
consider any qualifying bids tendered
after the expiration of the open season,
and reject them only if they cannot be
accommodated due to economic,
engineering, or operational constraints.
11. The Final Rule stated that, within
ten days after precedent agreements
have been executed for capacity
acquired in the open season, the
prospective applicant shall make public
the results of the open season, including
the names of the prospective shippers,
amount of capacity awarded, and the
terms of the agreements. Within 20 days
after precedent agreements have been
executed, copies of all precedent
agreements, as well as copies of any
correspondence with bidders whose
bids were not accepted, must be filed
with the Commission.
12. In another provision, the Final
Rule stated that, as a part of the
Commission’s review of any application
for an Alaska natural gas transportation
project, it will consider the extent to
which the proposed project has been
designed to accommodate the needs of
shippers who have made conforming
bids during an open season, as well as
the extent to which the project can
accommodate low-cost expansion, and
the Commission may require changes in
the project’s design necessary to
promote competition and offer a
reasonable opportunity for access to the
project.
13. Finally, to provide guidance to
interested parties on the important
E:\FR\FM\16JNR1.SGM
16JNR1
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
subject of expansion rate treatment, the
Final Rule establishes a presumption in
favor of rolled-in pricing for expansions
up to the point that it would cause there
to be a subsidy of expansion shippers by
initial shippers.
14. Requests for rehearing and/or
clarification were filed jointly by BP
Exploration (Alaska), Inc.,
ConocoPhillips Company and Exxon
Mobile Corporation (the North Slope
Producers), by Enbridge, Inc. (Enbridge),
by ChevronTexaco Natural Gas, a
division of Chevron U.S.A. Inc.
(ChevronTexaco), and by the State of
Alaska. In addition, Anadarko
Petroleum Corporation (Anadarko) and
the Legislative Budget and Audit
Committee of the Alaska State
Legislature (Alaska Legislators) filed
responses to the rehearing requests.3
Discussion
I. Mandating Pipeline Design
A. The Final Rule—§§ 157.36 and
157.37
15. Section 157.36 requires that any
open season for expansion capacity of
an Alaska natural gas transportation
project must provide the opportunity for
the transportation of gas other than
Prudhoe Bay or Point Thomson
production, and that the Commission, in
considering any proposed voluntary
expansion of an Alaska natural gas
pipeline project, ‘‘may require design
changes to ensure that all who are
willing to sign long-term firm
transportation contracts that some
portion of the expansion capacity be
allocated to new shippers or shippers
seeking to transport natural gas from
areas other than Prudhoe Bay and Point
Thomson.’’ Section 157.37 states that, in
reviewing any application for an Alaska
natural gas pipeline project, the
Commission ‘‘may require changes in
the project design necess[ary] to
promote competition and offer a
3 Under Rule 213 of the Commission’s Rules of
Practice and Procedure, answers to rehearing
requests are not permitted. However, the
Commission has discretion to waive this rule when
it finds that the answers will help provide a
complete record in the proceeding or allow a better
understanding of the issues. This proceeding
involves the establishment of open season rules for
capacity on an Alaska natural gas transportation
project, and is critical to the development of
Alaska’s vast natural gas resources to meet
anticipated national demand for natural gas,
thereby enhancing national security. The
Commission finds that the answers will provide
necessary information to provide a full and
complete record, which will assist the Commission
in addressing the issues on rehearing pertaining to
the complex and unique circumstances surrounding
the development of an Alaska natural gas
transportation project. Therefore, Anadarko’s and
the State of Alaska’s answers to the rehearing
requests are accepted. See 18 CFR 385.213 (2004).
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
reasonable opportunity for access to the
project, taking into account the extent to
which the proposed project design
accommodates the open season’s
conforming bids as well as low-cost
expansion.’’ 4 These provisions were
included in the Final Rule in response
to concerns of non-North Slope
producers that they have access to
capacity on an Alaska natural gas
transportation project when their
potential gas reserves are commercially
developed.
B. Rehearing/Clarification Requests
16. The North Slope Producers and
ChevronTexaco object to the provisions
contained in sections 157.36 and 157.37
to the extent that they authorize the
Commission to require changes in the
design of an Alaska natural gas
transportation project. The North Slope
Producers object to these provisions on
a number of grounds. First, they
contend that it is beyond the
Commission’s NGA authority to
mandate changes in the design of a
pipeline, either to provide additional
capacity or to enhance future
expandability. The North Slope
Producers contend that, in either case,
the result is a mandatory expansion of
the project, which according to section
7(a) of the NGA, is outside the
Commission’s authority to require.5 The
North Slope Producers maintain that
this limitation on the Commission’s
authority is reflected in the
Commission’s regulations providing that
open access pipelines are ‘‘not required
to provide any requested transportation
service for which capacity is not
available or that would require the
construction or acquisition of any new
facilities,’’ 6 and in judicial precedent.7
According to the North Slope Producers,
the Commission has acted unreasonably
in ‘‘morphing’’ ANGPA’s vague and
undefined open season requirements
pertaining to competition in the
exploration, development, and
production of Alaska gas and sufficient
opportunity for future access for the
transportation of non-Prudhoe Bay/
Point Thomson gas into factors to be
4 ‘‘Necessity’’ in section 157.37 is revised to read
‘‘necessary.’’
5 Section 7(a) of the NGA provides ‘‘[t]hat the
Commission shall have no authority to compel the
enlargement of transportation facilities * * *’’ 15
U.S.C. 717f(a).
6 18 CFR 284.7(f).
7 The North Slope Producers cite Panhandle
Eastern Pipe Line Co., 204 F.2d 675 (3rd Cir. 1953)
in which the court stated that ‘‘[i]n light of section
7(a) we are compelled to conclude that Congress
meant to leave the question whether to employ
additional capital in the enlargement of its pipeline
facilities to the unfettered judgment of the
stockholders and directors of each natural gas
company involved.’’ 204 F.2d at 680.
PO 00000
Frm 00029
Fmt 4700
Sfmt 4700
35013
considered by the Commission in its
NGA section 7 review of certificate
applications for Alaska natural gas
transportation projects.
17. Second, the North Slope
Producers assert that ANGPA section
105 further limits the Commission’s
authority to require an expansion of an
Alaska natural gas transportation project
sections. The North Slope Producers
state that before an involuntary
expansion can be ordered by the
Commission, section 105 lists a number
of statutory requirements that must be
met which are designed to balance
potential future shippers’ interests with
the need to protect the pipeline and
existing shippers and to protect against
uneconomic overbuilding. The North
Slope Producers state that none of these
statutory requirements are referenced in
or satisfied by section 157.36 or 157.37.
18. Third, the North Slope Producers
argue that the Commission appears to
mistakenly ‘‘assume that a pipeline can,
in all circumstances, be efficiently
designed to accommodate all qualifying
bids.’’ The North Slope Producers assert
that the most efficient and economic
pipeline design might not be one which
can accommodate 100 percent of the
capacity bid for in the open season. In
fact, according to the North Slope
Producers, it is possible that a pipeline
designed to accommodate all the
capacity bid in the open season ‘‘could
result in a design that is inefficient and/
or negatively impacts future expansion
design alternatives.’’
19. Fourth, the North Slope Producers
maintain that to the extent that it
authorizes a set-aside of capacity,
section 157.36 violates the Order No.
636’s goal of eliminating impediments
to the transmission of proper pricing
signals between producers and
consumers, as well as the Commission’s
non-discrimination policies. The North
Slope Producers point to the second
sentence of section 157.36, which states:
‘‘In considering a proposed voluntary
expansion of an Alaska natural gas
pipeline project, the Commission will
consider the extent to which the expansion
will be utilized by shippers other than
those who are the initial shippers on the
project, and in order to promote
competition and open access on the
project, may require design changes to
ensure that all who are willing to sign longterm firm transportation contracts to some
portion of the expansion capacity be
allocated to new shippers or shippers
seeking to transport natural gas from areas
other than Prudhoe Bay and Point
Thomson.’’ (Emphasis added).
The North Slope Producers assert that if
this ‘‘indecipherable’’ language is
intended to set aside capacity for new
E:\FR\FM\16JNR1.SGM
16JNR1
35014
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
shippers or shippers of gas from areas
other than Prudhoe Bay and Point
Thomson, then the Commission is
favoring one shipper’s bid over another
bid that otherwise meets all of the bid
criteria. The North Slope Producers
assert that ANGPA’s section 103(e)(2)(C)
requirement that open season
regulations for voluntary expansions are
to ‘‘provide an opportunity for the
transportation of gas other than Prudhoe
Bay and Point Thomson gas’’ does not
support section 157.36’s apparent setaside or preference. The North Slope
Producers state that not only is such a
preference inconsistent with the
Commission’s open access policies, it is
patently discriminatory and anticompetitive and unlawful under the
NGA. The North Slope Producers
contend that allocating pipeline
capacity in an open season to customers
who value it most, i.e., through the use
of the Commission-favored net present
value capacity allocation methodology,
ensures pipelines and shippers that
capacity will be allocated in a nondiscriminatory and economically
efficient manner. The North Slope
Producers also assert that development
of multi-owner fields could be delayed
or hampered if one group of shipper/
owners had a competitive advantage
over another shipper/owner group due
to a capacity allocation advantage or
preference.
20. Finally, the North Slope Producers
maintain that sections 157.36 and
157.37 are contrary to the Commission’s
reliance on market forces, on which its
existing policies are based. Specifically,
the North Slope Producers claim that
Order No. 2005 fails to reconcile
Subparts 157.36 and 157.37 with
current Commission policies in favor of
‘‘facilitate[ing] the unimpeded operation
of market forces to stimulate the
production of natural gas,’’8 and against
the subsidization of new services by
existing shippers. The North Slope
Producers state that it would be
unreasonable to expect that the pipeline
sponsors would simply assume the
financial risk for significant amounts of
uncontracted capacity on such an
enormous project, yet Order No. 2005
fails to address cost recovery issues
associated with any mandated design
changes that might be ordered.
21. ChevronTexaco claims that the
regulations promulgated in Order No.
2005 apply to open seasons for initial or
voluntary expansion capacity; therefore,
the idea of post-open season
Commission-mandated design changes
8 Order No. 636, FERC Stats. and Regs. ¶ 30,939
at 30,393 (1992), quoting S.Rep. No. 30 9, 101st
Cong., 1st Sess. at p. 2 (1989).
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
is inconsistent with and outside the
scope of this rulemaking. Moreover,
ChevronTexaco asserts that the design
change provisions of sections 157.36
and 157.37 should be deleted from the
open season regulations because the
subject was not included in the Notice
of Proposed Rulemaking.
ChevronTexaco states that absent
removing sections 157.36 and 157.37
from the open season regulations, the
Commission should provide that it
would not require project design
changes if doing so would negatively
impact the rates, terms or conditions of
service for initial shippers or otherwise
adversely affect pipeline operations of
efficiency.
22. In its response to the rehearing
requests, Anadarko argues that ANGPA
and the NGA provide the Commission
with ample authority to require changes
in the design of an initial or expanded
Alaska natural gas transportation project
necessary to meet the statutory
objectives of promoting competition and
provide a reasonable opportunity for
access to all shippers who have made
conforming bids during the open
season. Anadarko states that clearly
there is interplay between the NGA and
ANGPA. Specifically, states Anadarko,
section 7(e) of the NGA provides that a
‘‘certificate shall be issued * * * if it is
found that proposed service, sale,
operation, construction * * * to the
extent authorized by the certificate, is or
will be required by the present or future
public convenience and necessity.’’
Anadarko states that the Commission
considers many factors in making this
public convenience and necessity
finding, and, in the case of an Alaska
natural gas transportation project,
should consider the requirements of
ANGPA.
23. Anadarko asserts that the
Commission often imposes conditions
to its certificates requiring routing or
design modifications in order to support
a finding that a particular project is in
the public convenience and necessity.
In any event, sections 157.36 and 157.37
do not mandate an expansion, according
to Anadarko, because the applicant may
choose not to accept a certificate that
requires that the project be redesigned.
Anadarko states that the regulations
merely put the applicant on notice that
its proposed project design might be
rejected as failing to meet the objectives
of ANGPA, and consequently, not being
required by the public convenience and
necessity.
24. In response to the North Slope
Producers’ charge that section 157.36
provides for discriminatory reallocation
of capacity contrary to existing
Commission policy, Anadarko contends
PO 00000
Frm 00030
Fmt 4700
Sfmt 4700
that the Commission is merely following
the mandate of ANGPA section
103(e)(2)(C). Anadarko states that under
section 103(e)(2)(C), the Commission’s
regulations must ensure that any open
season for expansion capacity provides
the opportunity for the transportation of
natural gas other than from Prudhoe
Bay/Point Thomson, and section 157.36
seeks to do just that.
25. Anadarko also disputes the North
Slope Producers’ claim that parties were
not adequately notified in the NOPR
that pipeline design would be a subject
of the rulemaking. Anadarko maintains
that the regulations contained in
sections 157.36 and 157.37 reasonably
respond to many concerns expressed
throughout the rulemaking process.9
Anadarko contends that under the
Administrative Procedure Act (APA),
the Commission was required in this
informal rulemaking proceeding to
provide either the terms or substance of
the proposed rule or a description of the
subjects and issues involved.10
Moreover, Anadarko points out that the
courts have held that ‘‘even if the final
rule deviates from the proposed
rule,’[s]o long as the final rule
promulgated by the agency is a ‘‘logical
outgrowth’’ of the proposed rule’’ the
purposes of the notice and comment
have been adequately served.’’ 11
Anadarko states that Order No. 2005’s
pipeline design provisions were a
‘‘logical outgrowth’’ of the NOPR and
the issues discussed therein, e.g., the
major goals of ANGPA, concerns over
potential discrimination, producer/
sponsor preferences, the role of presubscriptions, and tensions between
ANGPA’s goals and the application of
existing policies to an Alaska project.
26. Lastly, Anadarko contends that
the Commission provided ample
support for not following current
Commission policies that favor reliance
on market forces. Anadarko states that
the rulemaking record in Order No.
2005 thoroughly discusses the
conditions and circumstances in Alaska
that are much different than those found
in the lower 48 states, requiring the
appropriate regulatory action taken in
sections 157.36 and 157.37. In
conclusion, Anadarko disagrees that
157.36 is ‘‘indecipherable’’ as claimed
by the North Slope Producers.
27. The Alaska Legislators maintain
that sections 157.36 and 157.37 are well
within the Commission’s broad power
9 Anadarko identifies comments addressing
pipeline size both at the technical conference and
written. See Anadarko’s March 29, 2005 response
at 15–16.
10 See 5 U.S.C.A. 553(b)(3).
11 Appalachian Power Co. v. EPA, 135 F.3d 791,
804 n.22 (DC Cir. 1998).
E:\FR\FM\16JNR1.SGM
16JNR1
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
to attach to certificates any conditions
that may be found to be required by the
public convenience and necessity. They
claim that the ‘‘forced expansion’’
argument fails to acknowledge that
ANGPA has injected into the public
convenience and necessity standard of
the NGA a new statutory standard, i.e.,
the promotion of competition in the
exploration, development and
production of Alaska natural gas with
respect to Alaska natural gas
transportation projects. Moreover, the
Alaska legislators contend that the
Commission’s pipeline design concerns
are required not only by the mandate of
ANGPA, but also by the economic
realities in Alaska, where virtually all of
the proven reserves are held by the
North Slope Producers. The Alaska
legislators state that the Commission is
simply announcing in sections 157.36
and 157.37 that it may condition the
approval of the certificate upon the
applicant’s making necessary design
changes required to satisfy the public
convenience and necessity standard,
including the ‘‘promote competition’’
standard, which is uniquely applicable
to an Alaska natural gas transportation
project.
28. Addressing the North Slope
Producers’ claim that section 157.36
provides for an unduly discriminatory
set aside of capacity for non-North
Slope shippers, the Alaska legislators
agree with Anadarko that ANGPA
mandates that in the case of an
expansion of an Alaska natural gas
transportation project, the Commission
must provide an opportunity for the
transportation of natural gas other than
from Prudhoe Bay and Point Thomson
units in its open season rules. Alaska
legislators state that section 157.36 is
consistent with that mandate.
29. The Alaska legislators also defend
the Commission’s ‘‘proactive’’ approach
through which it fashioned the open
season rules in recognition of the
recognized differences between
competitive forces in the lower 48 states
and the lack of competition in Alaska.
Given these differences, the Alaska
legislators maintain that the
Commission was right to depart from
existing Commission policy. They assert
that the fact that Congress required the
Commission to promulgate the Alaska
open season rules in place of the
Commission’s long-standing policy of
evaluating open seasons on a case-bycase, after-the-fact basis, is an
illustration of the need for a different
approach based on the unique
circumstances surrounding an Alaska
pipeline. The Alaska Legislators
conclude that, unlike the situation in
the lower 48 states, there is no existing
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
or foreseeable competitive environment
in Alaska, where the North Slope
Produces not only control all the known
gas reserves, but also may become the
sponsors of the Alaska pipeline.
Therefore, the Commission was right to
not rely on market forces in Alaska to
ensure the development, routing, sizing
and timing of an Alaska pipeline.
30. Finally, the state of Alaska
suggests that section 157.36 be
expanded to better reflect its intent.
According to the State of Alaska, section
157.36 should read:
In considering a proposed voluntary
expansion of an Alaska natural gas
transportation project, the Commission will
consider the extent to which the expansion
will be utilized by shippers other than those
who are the initial shippers on the project
and, in order to promote competition and
open access to the project, may require
design changes to ensure that new shippers
willing to sign long-term firm transportation
contracts or shippers seeking to transport
natural gas from areas other than Prudhoe
Bay or Point Thomson who are willing to
sign long-term contracts can have access to
some portion of the expansion capacity.
C. Commission Response
31. The North Slope Producers’
assertion that the Commission has no
authority under the NGA to require
changes in the design of a proposed
Alaska natural gas transportation project
in connection with an application for
authorization either to construct the
project, or to expand the project is
inconsistent with law and precedent. At
the outset, we reject the notion that any
design change that might be required
under either section 157.36 or 157.37
would constitute a mandatory
expansion of the project. First, in every
case in which the section 7(a) limitation
has been addressed, the facilities
involved were existing facilities subject
to existing certificate authorization. The
reasoning behind this limitation is clear.
Once a natural gas company accepts a
certificate and in reliance thereof
expends resources to construct the
facilities authorized therein, the
pipeline and its customers should have
the right to rely on the authorizations
contained in that certificate. It is quite
another thing where the Commission
tells a certificate applicant that unless it
agrees to certain changes (including cost
allocations and the design of initial
service rates), its proposal will not be
found to be in the public convenience
and necessity. In such case, if the
applicant does not want to change its
proposed project design, it is not
required to accept the certificate.
Furthermore, because design changes
under either 157.36 or 157.37 would not
constitute a mandatory project
PO 00000
Frm 00031
Fmt 4700
Sfmt 4700
35015
expansion, the statutory requirements of
ANGPA section 105 have no
application.
32. In considering an application for
a certificate of public convenience and
necessity under section 7 of the NGA,
the Commission has the authority to
consider all factors bearing on the
public interest,12 and in particular, the
Commission ‘‘certainly has the right to
consider a congressional expression of
fundamental national policy as bearing
upon the question whether a particular
certificate is required by the public
convenience and necessity.’’ 13 In the
case of an Alaska natural gas
transportation project, these factors
would properly include the
requirements of ANGPA, including the
statutory objectives of promoting
competition and provide a reasonable
opportunity for access to all shippers
who have made conforming bids during
the open season.
33. The Commission has authority
under NGA section 7(e) to attach to a
certificate of public convenience and
necessity any conditions it deems
necessary to meet the public interest.14
The Commission has exercised this
conditioning authority to require
routing or design modifications in order
to support a finding that a particular
project is in the public convenience and
necessity.15 Sections 157.36 and 157.37
merely codify our existing authority and
practice.
34. The North Slope Producers’ claim
that sections 157.36 and 157.37 are
predicated on the Commission’s
erroneous assumption ‘‘that a pipeline
can, in all circumstances, be efficiently
designed to accommodate all qualifying
bids.’’ This is inaccurate. We noted in
Order No. 2005 that both the North
Slope Producers and Enbridge
maintained that an Alaska pipeline
could be designed and built with
sufficient capacity to accommodate the
needs of every qualified shipper.16 Our
expectation is that an Alaska natural gas
transportation project will be designed
and built, to the extent possible, to
12 See, e.g., FPC v. Transcontinental Gas Pipe
Line Corporation, 365 U.S. 1, 81 S.Ct. 435 (1961);
Office of Consumers’ Counsel v. FERC, 655 F.2d
1132, 210 U.S. App. D.C. 315 (1980).
13 City of Pittsburgh v. FPC, 237 F.2d 741 at 754
(D.C. Cir. 1965).
14 See, e.g., FPC v. Hunt, 376 U.S. 515, 525–527,
84 S.Ct. 861 (1964); Atlantic Refining Co. v. Public
Service Commission of New York, 360 U.S. 378
(1959).
15 See, e.g., Vector Pipeline, L.P., 87 FERC
¶ 61,225 at 61,892–893 (1999); Maritimes &
Northeast Pipelines, L.L.C., 80 FERC ¶ 61,345
(1997); NE Hub Partners, L.P., 83 FERC ¶ 61,043
(1998); see also, Transcontinental Gas Pipe Line
Corp v. FERC, 589 F.2d 186 (5th Cir.), cert. denied,
445 U.S. 915 (1979).
16 See, e.g., Order No. 2005 at P 29, 37, and 88.
E:\FR\FM\16JNR1.SGM
16JNR1
35016
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
accommodate all qualified shippers who
are ready to sign firm transportation
agreements. Nonetheless, in Order No.
2005 we certainly did not rule out the
possibility that a project, with or
without pre-subscription agreements,
might be oversubscribed.17 On this note,
we should emphasize that in our review
of any application for initial Alaska
project or any expansion thereof, our
consideration of the project design will
be driven by our need to find that the
proposal is in the public convenience
and necessity. Any conditions we
impose must be required by the public
interest, and be based on substantial
evidence.
35. The North Slope Producers’ claim
that section 157.36 provides for an
unduly discriminatory set-aside of
capacity for non-North Slope shippers
discounts, if not ignores, the
Congressional mandate of ANGPA
section 103(e)(2)(C) that requires our
open season regulations to ensure that
any open season for expansion capacity
provides the opportunity for the
transportation of natural gas other than
from Prudhoe Bay/Point Thomson.
Section 157.36 does so in a reasonable
manner. In any event, our regulations do
not require that an expansion proposal
must, regardless of economic and
technical considerations, provide
transportation of gas other than Prudhoe
Bay/Point Thomson volumes. The
regulations simply require that an
opportunity for such transportation be
provided.
36. As pointed out elsewhere in this
order, and throughout Order No. 2005,
a number of existing Commission
policies predicated on competitive
conditions in the lower 48 states are illsuited for application in the case of an
Alaska natural gas transportation
project, particularly in view of ANGPA’s
directives. As we stated in Order No.
2005, a successful Alaska natural gas
transportation project will have to
overcome a variety of significant
obstacles, including unique and
complex competitive conditions. Those
competitive conditions, we said, are
intensified by the generally agreed-upon
fact that there will be only one such
Alaska pipeline for the foreseeable
future.18 Against that backdrop, we
affirm the conclusions of Order No.
2005, which serve as the underpinnings
of the Final Rule’s regulations,
including the need in certain instances
to accommodate existing Commission
17 See
id. at P 37; see also § 157.34(c)(15).
18 The North Slope Producers, in their rehearing
request, claim that it is too early to conclude that
only one Alaska pipeline will ever be built. We find
nothing in the record to support a contrary
conclusion.
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
policy to the unique circumstances
surrounding the exploration,
production, development, and
transportation to market of Alaska
natural gas.
37. Finally, while due process and the
APA impose an obligation on agencies
to provide adequate notice of issues to
be considered,19 that obligation is
satisfied in this informal rulemaking by
providing either the terms or substance
of the proposed rule or a description of
the subjects and issues involved.20
Order No. 2005’s pipeline design
provisions were a logical outgrowth of
the NOPR and the issues discussed
therein, e.g., major goals of ANGPA,
concerns over potential discrimination,
producer/sponsor preferences, potential
role of pre-subscriptions, tensions
between ANGPA’s goals, and
application of existing policies to the
circumstances of an Alaska project.
Indeed, the critical importance of
properly sizing the pipeline was a
recurring theme throughout this
proceeding, and was raised by several
parties at the technical conference, and
in later comments and reply
comments.21 Thus, Order No. 2005 does
not unduly change the scope of this
proceeding. In any event, the parties’
ability to seek rehearing resolves any
due process issues.
38. Although the North Slope
Producers describe section 157.36 to be
‘‘indecipherable,’’ their comments
demonstrate that they understand its
intent. Section 157.36 is intended to
provide that the Commission may
require design changes necessary to
ensure that some portion of a proposed
voluntary expansion will be allocated to
new shippers or shippers seeking to
transport gas from areas other than
Prudhoe Bay or Point Thomson,
provided such shippers are willing to
sign qualifying long-term firm
transportation agreements. To ensure
clarity, we will revise section 157.36 to
read as follows:
‘‘In considering a proposed voluntary
expansion of an Alaska natural gas
transportation project, the Commission will
consider the extent to which the expansion
will be utilized by shippers other than those
who are the initial shippers on the project
and, in order to promote competition and
open access to the project, may require
design changes to ensure that some portion
of the expansion capacity will be allocated to
new shippers willing to sign qualifying long19 Public Service Commission of the
Commonwealth of Kentucky v. FERC, 397 F.3d 1004
(DC Cir. 2005), citing Williston Basin Interstate
Pipeline Co. v. FERC, 165 F.3d 54 (DC Cir. 1999);
see 5 U.S.C. 554(b)(3).
20 See 5 U.S.C. 553(b)(3).
21 See n. 8, supra.
PO 00000
Frm 00032
Fmt 4700
Sfmt 4700
term firm transportation contracts, including
shippers seeking to transport natural gas from
areas other than Prudhoe Bay or Point
Thomson.’’
II. Presumption of Rolled-in Rates for
Expansions
A. Final Rule—§ 157.39
39. Section 157.39 states that ‘‘[t]here
shall be a rebuttable presumption that
rates for any expansion of an Alaska
natural gas transportation project shall
be determined on a rolled-in basis.’’ The
Commission stated in Order No. 2005
that by providing for this presumption,
the Commission is advising potential
shippers, in advance of any initial
Alaska natural gas transportation project
open season, of its intention to
harmonize the objective of rate
predictability for initial shippers with
the objective of reducing barriers to
future exploration and production in
designing rates for future expansions of
any Alaska natural gas transportation
project. The Commission concluded in
Order No. 2005 that section 157.39 is
consistent with ‘‘our guiding principle
that competition favors all of the
Commission’s customers, as well as
with the objectives of the Act, to adopt
rolled-in rate treatment up to the point
that would cause there to be a subsidy
of expansion shippers by initial
shippers, if any subsidy were to be
found.’’
B. Rehearing/Clarification Requests
40. The North Slope Producers,
Enbridge, and ChevronTexaco assert
that the presumption in favor of rolledin rates for voluntary expansions
established in section 157.39 creates
uncertainty for shippers and project
sponsors, and, therefore, section 157.39
should be eliminated from the
regulations or substantially revised. The
North Slope Producers and Enbridge
claim that prospective initial shippers,
fearing that in the future their rates may
be increased to subsidize the cost of
expansion facilities, will be less willing
to make the long-term commitments
necessary to support an Alaska project.
This uncertainty, they predict, will
discourage rather than advance the
development of an Alaska pipeline or
any voluntary expansion thereof—a
result clearly inconsistent with
ANGPA’s primary goal. Moreover, the
North Slope Producers and Enbridge
suggest that mandatory expansions
pursuant to ANGPA section 105 will
become more attractive than voluntary
expansions because of the explicit rate
protection for existing shippers in
section 105.
E:\FR\FM\16JNR1.SGM
16JNR1
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
41. The North Slope Producers
contend that section 157.39 is
unjustifiably inconsistent with the
Commission’s current policy regarding
rate treatment of expansions, which is to
discourage uneconomic expansions and
assure that expansions will not be
subsidized by existing shippers. They
assert that even if, as claimed by the
Commission, only one pipeline will be
built in Alaska, that distinction does not
justify deviating from the Commission’s
current policy.
42. The North Slope Producers charge
that the Commission acted arbitrarily
and capriciously in relying on ANGPA
section 103(e) to justify its conclusion to
provide for a presumption of rolled-in
rates for expansions. Although the
North Slope Producers concede that the
Commission clearly has the authority
under ANGPA and the NGA to approve
rates for Alaska natural gas
transportation projects, they claim that
ANGPA section 103(e) has nothing to do
with rate regulation. Furthermore, state
the North Slope Producers, even if
section 103 could be read to give the
Commission authority to include rate
regulations in its open season rules, the
proper course would be to remove
section 157.39 from the open season
rules and instead address rate policy
issues only after the parties have the
opportunity of developing a complete
factual record. Failing this, the North
Slope Producers state that the
Commission should revise section
157.39 to provide that the Commission’s
current rate policies will apply to
Alaska projects.
43. Enbridge also argues that the
Commission acted arbitrarily and
capriciously by imposing a rebuttable
rolled-in presumption, even where
rolled-in pricing would increase
existing shippers’ rates. According to
Enbridge, Order No. 2005 identifies two
considerations, namely the
Commission’s disfavor of existing
shippers subsidizing the rates of new
shippers, and the Commission’s
reluctance to authorize an expansion
rate that would have an unduly negative
impact on the exploration and
development of Alaska reserves.
Enbridge contends that the presumption
should be ‘‘scaled back’’ to apply only
to cases where expansion rates are no
higher than pre-existing rates. Enbridge
points to the Commission’s
acknowledgement in Order No. 2005
that it ‘‘cannot at this point, without a
specific project proposal or the facts
surrounding a proposed expansion
before us, define exactly what will be
required to overcome the presumption.’’
Enbridge contends that the
Commission’s inability to explain how
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
the presumption can be rebutted renders
rolled-in pricing mandatory, leaving the
question of whether a rolled-in
expansion rate that is higher than
original rates is a subsidy to be resolved
in a future NGA section 7 filing.
44. ChevronTexaco stresses that
because the text of Order No. 2005
recognizes that ‘‘without a specific
project proposal or the facts
surrounding a proposed expansion’’ the
Commission cannot determine what is
needed to overcome the presumption
favoring rolled-in rates, the Commission
should defer any determination of rate
treatment for expansions until a record
can be developed after a specific
proposal is made. According to
ChevronTexaco, this inability to
articulate when the presumption will be
applied creates uncertainty that inhibits
the development of any Alaska project.
45. ChevronTexaco states that
inconsistency between the text of order
and the text of the regulations creates
further uncertainty. ChevronTexaco
states that while the regulations state
that the presumption applies to ‘‘any
expansion,’’ Order No. 2005’s text, at
paragraphs 124 and 125, suggests that
rolled-in rates are appropriate only if
there is no increase in rates for existing
shippers. ChevronTexaco urges the
Commission to clarify section 157.39 to
state that no cross-subsidy is intended.
Otherwise, the Commission should
consider issuing, in lieu of a regulation,
a policy statement which outlines the
general direction that the Commission
intends to take.
46. The Alaska Legislators and
Anadarko contend that rolled-in pricing
is essential and justified. Anadarko
asserts that the Commission clearly has
the statutory authority to establish a
presumption of rolled-in pricing for
future expansions in the open season
regulations. Both Anadarko and the
Alaska Legislators contend that the
significant differences identified in the
record between an Alaskan pipeline
project and a pipeline in the lower 48
states provide ample justification for
departing from the current pricing
policy. The Alaska Legislators contend
that even if there were some factual
reason for applying the current policy,
that policy cannot be reconciled with
the policy considerations stated in
ANGPA. Both Anadarko and the Alaska
Legislators state that incremental
pricing of expansions cannot be
reconciled with ANGPA’s goals of
promoting competition in the
exploration, development, and
production of Alaska natural gas, and
providing for the transportation of
natural gas other than from the Prudhoe
Bay and Point Thomson units in any
PO 00000
Frm 00033
Fmt 4700
Sfmt 4700
35017
expansions of the Alaska pipeline
facilities. The Alaska Legislators
estimate that expanding a pipeline,
through looping, to a capacity of 7
billion cubic feet (Bcf), would result in
an expansion rate 50 percent higher
than existing rates if incrementally
priced. Anadarko predicts that
incremental pricing of expansions of an
Alaskan pipeline beyond 6 Bcf would
cause the pipeline to be capped at 6 Bcf.
C. Commission Response
47. ANGPA section 103(i) gives the
Commission broad authority to establish
‘‘such regulations as are necessary’’ for
the conduct of open seasons. In this
regard, the Commission believes that it
is appropriate to establish rate criteria
that will assist potential shippers to
make informed open season bids, and
will promote competition, as required
by ANGPA. As discussed in detail in
Order No. 2005, these criteria include
projected rates for in-state deliveries of
gas, as well as a presumption for rolledin rate treatment for future pipeline
expansions.
48. In adopting the presumption for
rolled-in rate treatment, the Commission
balanced rate predictability for initial
shippers with the objective of reducing
barriers to future exploration,
development and production of Alaska
natural gas. The Commission was
concerned that the prospect of high
incremental transportation rates might
increase risks to Alaskan producers and
serve as a disincentive to future
exploration and development of
potentially valuable natural gas
resources. On the other hand, the
Commission does not wish to
discourage voluntary capacity
expansions.
49. The rolled-in rate presumption
was not an abandonment of our current
policy of not favoring rate subsidization
by existing customers of capacity
expansions as suggested in the requests
for rehearing. The Commission did,
however, suggest that because of the
likelihood of a single Alaskan pipeline
project, it would consider alternatives to
our current policy on how to define or
quantify subsidization by current
customers. Current policy primarily
considers whether the expansion project
will result in a rate higher than the
existing transportation rate for existing
customers. An alternative consideration
or definition of subsidization could be
whether the expansion rate is no higher
than the actual initial rate or of an
initial rate without built-in subsidies.
The Commission believed and
continues to believe that the appropriate
place to review this issue is in the
context of a future NGA section 7 filing.
E:\FR\FM\16JNR1.SGM
16JNR1
35018
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
In such a proceeding, if the pipeline
owners can show that the initial
pipeline was sized appropriately, i.e., it
was uneconomic or inefficient to build
a larger capacity pipeline, the
Commission would consider this in
overcoming the rolled-in rate
presumption.
50. The text of Order No. 2005
referred to by ChevronTexaco does not
simply state that rolled-in rates are
appropriate only if there is no increase
in rates for existing shippers; it suggests
that a rolled-in expansion rate that is
higher than the original rate is not
necessarily a subsidy. As noted above,
we will determine whether a particular
rate amounts to a subsidy when the
issue is presented to us.
51. Nothing in the requests for
rehearing causes us to question our
conclusion that a rebuttal presumption
of rolled-in treatment for the expansion
of an Alaska Project is a reasonable
approach to the difficult issues we, and
prospective pipeline proponents and
shippers, may face on the future. We
think that the signal we are sending is
a positive one that will help spur
natural gas exploration and
development in Alaska. At the same
time, we have not prejudged how we
will resolve future proceedings, and all
parties will have the opportunity to
convince us of appropriate rate
treatment if and when expansion
proposals for an Alaska project are
developed. We therefore will not change
the rule on this matter.
III. Late Bids
A. The Final Rule—§ 157.34(d)(2)
52. Order No. 2005 added a new
provision in the Final Rule, section
157.34(d)(2), that a project sponsor must
consider any bids tendered after the
expiration of the open season by
qualified bidders, and may reject them
only if they cannot be accommodated
due to economic, engineering, or
operational constraints, in which case
the project sponsor must provide a
detailed explanation for the rejection.
The Commission explained that this
requirement is designed to allow
reasonable access to those shippers who
may not be ready to participate during
the established open season period, and
at the same time provide the sponsor
with flexibility in the timing of its open
season.
B. Rehearing/Clarification Requests
53. The North Slope Producers and
Enbridge contend that it is important for
the timely development of any project
that the project sponsors be able to rely
on an open season that has a definite
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
term. They state that the open season
results are needed to permit the project
sponsor to gauge demand and in turn
finalize pipeline design. They assert that
the late bid provisions of section
157.34(d)(2) will result in unreasonable
risks and costs to the project sponsor by
creating a never-ending, open-ended
open season in which the project
sponsor will be required, for each and
every late bid received, to divert
resources and incur additional costs to
evaluate whether bid can be
accommodated. In addition, they state
that there is tremendous potential for
delay at each step of the development of
the project, if the project sponsor must
stop and make design changes at every
stage to accommodate a late bid. Thus,
they state, section 157.34(d)(2) would
frustrate the Commission’s stated goal of
adopting open season regulations that
ensure sufficient economic certainty to
support the construction of a pipeline.
54. The North Slope Producers add
that financing cannot be secured until
pipeline design and development costs
are known and precedent agreements
are in place. Consequently, they claim,
the prospect of having to make changes
to key project components to
accommodate late bids jeopardizes the
project sponsor’s ability to obtain
financing in a timely manner.
55. Both Enbridge and the North
Slope Producers also state that section
157.34(d)(2) fails to provide a clear
standard under which the project
sponsor must evaluate late bids. This
failure, they claim, presents another risk
of uncertainty and delay. Enbridge
argues that, even if it is necessary to
significantly re-design a project in order
to satisfy a late bid, the regulation
would require that such a bid be
accepted if the re-designed project
remains feasible from an ‘‘economic,
engineering or operational’’ perspective.
56. The North Slope Producers state
that another effect of the late bid
provision is that potential shippers will
be discouraged from participating in an
open season if they can submit a late
bid. They worry that this would
diminish the open season’s ability to
accurately demonstrate the demand for
pipeline capacity. Enbridge also claims
that, absent a good faith requirement in
connection with submitting late bids,
section 157.34(d)(2) permits such
gamesmanship. Enbridge states that at a
minimum, section 157.34(d)(2) should
put ‘‘the burden on the bidder to
demonstrate compelling circumstances
that prevented participation in open
season, and that the bid can be
accommodated without changing
system design, requiring capacity to be
allocated away from other shippers, or
PO 00000
Frm 00034
Fmt 4700
Sfmt 4700
otherwise adversely impacting the
project’s development and timing.’’ In
this regard, the State of Alaska
maintains the Commission should
include language in section 157.34(d)(2)
that requires late bidders to provide
adequate justification for their late bids.
57. Additionally, the North Slope
Producers assert that, to the extent a
project sponsor would be required to
expand the project to accommodate late
bids, the Commission is in effect
ordering an expansion of the pipeline.
In such a case, section 157.34(d)(2)
raises the same issues regarding forced
expansions as are raised by sections
157.36 and 157.37. The North Slope
Producers contend that whereas the
Commission may require an expansion
under section 105, that section places
the burden on the party seeking such
expansion to establish that specific
conditions are met, section 157.34(d)(2)
appears to place the burden on the
pipeline to justify why it cannot expand
the project to accommodate a late bid.
58. Enbridge states that in any event
there is little or no reason for section
157.34(d)(2) ‘‘given the other measures
instituted by Order No. 2005 to protect
the interests of late developing
shippers.’’ Specifically, Enbridge refers
to the unprecedented level of
information required in the open season
notice on which bidders will be able to
base their long-term capacity decisions,
Order No. 2005’s emphasis on requiring
that the project’s design demonstrate a
capability for low-cost expansion, and,
finally, the mandatory expansion
provisions of ANGPA 105. Enbridge
contends that to the extent late bids can
be accommodated without adversely
impacting the project’s development, it
is in the project sponsor’s economic
interests to do so.
59. ChevronTexaco requests that the
Commission clarify that project
sponsors will be required to consider
late bids only if there is excess capacity
after capacity is allocated to those open
who bid in the open season.
ChevronTexaco states that one of the
major purposes of the open season is
provide a level playing field for all
participants, thereby eliminating the
advantages of possessing superior or
advance information. ChevronTexaco
cannot understand the Commission’s
reasoning in giving special
consideration to one specific parameter
of a conforming bid, namely, the timing
of the bid. According to ChevronTexaco,
late bidders should not be allowed to
put new burdens on the project or to
adversely affect timely open season
bidders.
60. Anadarko states that section
157.34(d)(2) is a reasonable compromise
E:\FR\FM\16JNR1.SGM
16JNR1
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
balancing concerns that the open season
could be held prematurely with a
project sponsor’s desire to control open
season timing. Anadarko also states that
it is possible to accommodate all
qualified bidders up to the time the
pipeline design is finalized.
C. Commission Response
61. Under the Commission’s open
access policy and rules, all operating
interstate pipelines have an obligation
to receive and respond to new requests
for service, even if no capacity is
available. All operating pipelines have
provisions in their FERC tariffs
governing the procedures that the
pipeline will use in evaluating requests
for service. Absent an expansion,22
capacity could still be made available to
a prospective shipper via capacity
release or the capacity turnback
provisions of an interstate pipeline’s
FERC tariff. During the several years
between the time that the open season
ends and an Alaskan pipeline goes into
service, there will be no tariff with
provisions like those described above in
effect for that pipeline. Without the late
bidder provisions of section 157.34(d),
late-developing prospective shippers
would have no formal way of seeking
capacity on the pipeline after the open
season ends. As revised herein, the
Commission believes that the late
bidder provision is a fair and necessary
addition to the open season process for
an Alaska natural gas transportation
project.
62. The project sponsor’s obligation
under section 157.34(d)(2) is not
‘‘unbounded’’ or ‘‘open-ended,’’ as
North Slope Producers contend. We
added this requirement in recognition of
the possibility that an appreciable
amount of time might pass between the
close of the open season and the project
sponsor’s finalizing the details of the
proposed pipeline design and associated
development costs, given the size and
scope of an Alaska natural gas pipeline
project. During that time, it is possible
that producers of Alaska natural gas
who were not in a position to commit
to long-term capacity commitments
during the open season, might then be
in a position to request capacity
consistent with the open season notice
(except, of course, that the bid is
tendered out of time). We felt it proper
to require the project sponsor to
consider such a request. At the same
time, we appreciated that at some point
in time, either before or after the
22 Interstate pipelines, other than an Alaska
pipeline, cannot be required to expand their
systems, but pipelines are required to respond to
those who request service, even when none is
available.
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
proposed pipeline design is finalized,
the project sponsor might not be able to
accommodate reasonably a late request.
For that reason, we provided that late
requests could be rejected on the basis
of ‘‘economic, engineering or
operational constraints.’’ This is far
from an unbounded, open-ended
obligation. Indeed, as noted above,
Enbridge points out that to the extent
that late bids can be accommodated
without adversely impacting the
project’s development, it is in the
project sponsor’s economic interest to
do so. We see no harm in requiring that
result.
63. We will however, revise the
requirements of section 157.34(d)(2) in
response to the complaints that the
‘‘economic, engineering or operational
constraints’’ standard for rejecting late
bids is too vague. Specifically, we are
clarifying the criteria for rejecting late
bids in section 157.34(d)(2) to be
‘‘economic, engineering, design,
capacity or operational constraints, or
accommodating the request would
otherwise adversely impact the timely
development of the project.’’ 23
Additionally, we are adding a provision
to the section which will enable the
project sponsor, at the appropriate time
in the development of its project and
subject to Commission approval, to
determine, based on the above criteria,
that no further bids can be accepted. We
will also revise section 157.34(d)(2) to
provide that any bid tendered after the
expiration of an open season must
contain a good faith showing, including
a statement of the circumstances which
prevented the bidder from tendering a
timely bid, and how those
circumstances have changed. This
requirement is consistent with the
underlying premise of section
157.34(d)(2) in the Final Rule, and
should serve to protect against
‘‘gamesmanship.’’ With these revisions
and clarifications, we believe that the
late bid provision will permit latedeveloping shippers to obtain capacity
after the expiration of the open season,
while also providing the prospective
applicant the assurance that it will be
able to design and develop its project
according to its own schedule.
23 We are retaining the requirement that the
prospective applicant must provide a detailed
explanation for its rejection, at least until such time
as it has determined, subject to Commission
approval, that no further late bids can be accepted.
We find that, based on the prospective applicant’s
position, it is easier for it to evaluate why a late bid
cannot be accepted, than it is for a later bidder to
explain why its bid can be accommodated.
PO 00000
Frm 00035
Fmt 4700
Sfmt 4700
35019
IV. Mandatory Pre-Approval
A. The Final Rule—§ 157.38
64. Section 157.38 requires that, at
least 90 days prior to providing its
notice of open season, an applicant
must file, for Commission approval, a
detailed plan for conducting the open
season in conformance with the
regulations. The Commission will
establish a date by which comments on
the request for approval are due, and the
Commission, unless it directs otherwise,
will act on the request within 60 days
of its filing. The Commission concluded
in Order No. 2005 that this requirement
would allow for the resolution of
disputes or dissatisfaction with an open
season at the earliest possible time,
thereby reducing the risk of having to
require a second remedial open season
because the first one did not conform to
the regulations.
B. Rehearing/Clarification Requests
65. The North Slope Producers and
Enbridge urge the Commission to
eliminate the mandatory pre-review
process set out in section 157.38,
calculating that with the addition of this
mandatory review, the open season
process will take at least 210 days,
instead of the 120-day open season
period proposed in the NOPR and
established in section 157.34. They state
that this additional 90 days does not
include further delays that could result
from disputes arising during the prereview process, including the need to
consider requests for rehearing of any
orders pre-approving an open season or
the Commission’s inability to adhere to
its 90-day window. The result, they
claim, is that the open season process
will be delayed, not expedited. Enbridge
states that the 210-day period is longer
than the 180-day open season period
which the Commission rejected as
inconsistent with Congress’ sense of
urgency, as well as the Commission’s
conclusion in Order No. 2005 that
‘‘timing is of the essence.’’
66. The North Slope Producers
maintain that the Commission’s
justification for this requirement is that
a successful open season is more likely
to occur if issues are identified and
resolved at the earliest time. The North
Slope Producers disagree, claiming that,
instead of reducing the chance of postbid disputes, this layer of review will
provide those who would gain
commercial leverage by delaying the
open season process ‘‘with an additional
bite at the apple, first by objecting to the
bid package, then by objecting to the
results of the open season.’’
67. Both the North Slope Producers
and Enbridge contend that the
E:\FR\FM\16JNR1.SGM
16JNR1
35020
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
mandatory pre-review process is
unnecessary and duplicative of other
protections provided in Order No. 2005,
including the transparency and
specificity of the open season
information, the 30-day prior notice
requirement, the prohibition against
undue discrimination or preference in
rates, terms or conditions of service, and
the imposition of Order No. 2004
standards of conduct. They contend that
the effects of any delay of the open
season can be profound, due to narrow,
seasonal windows for environmental
studies and preliminary field work,
which cannot take place until the open
season has been held. These risks, they
claim, far outweigh any utility of a
mandatory pre-review. In conclusion,
the North Slope Producers contend that
any pre-review of the open season
notice should be voluntary, shortened,
and that the Commission decision on
the sufficiency should be deemed a predecisional, non-reviewable
determination, similar to the
Commission’s action in rejecting a
deficient certificate application under
section 157.8 of the Commission’s
regulations.
68. Anadarko defends the mandatory
pre-review requirement as striking an
‘‘appropriate balance between granting
project sponsors flexibility in designing
open seasons and providing regulatory
supervision to potential bidders by
requiring project sponsors to file and
obtain approval of the open season
plan.’’ Anadarko and the Alaska
Legislators state that pre-approval will
reduce any risk of having to hold a
second open season to correct one done
improperly. Anadarko states that this
will, as the Commission believes,
promote rather than hinder a timely and
successful open season. The Alaska
Legislators agree with this assessment,
contending that adding 90 days to the
front end of the open season process,
even with the prospect of a rehearing, is
better than having an open season called
back by an order on rehearing or on
appeal from the results of an open
season, and then having to hold another
open season. Moreover, they state that
once the open season is approved,
parties may rely on those terms being
controlling throughout the bidding and
contracting process.
C. Commission Response
69. The North Slope Producers and
Enbridge correctly state that, by virtue
of the mandatory pre-approval
established in section 157.38, the
minimum duration of the whole open
season process would be 210 days.
However, the concept of a mandatory
pre-approval and the attendant
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
additional time that such review will
add is not inconsistent with our concern
that ‘‘time is of the essence’’ that caused
us to reject a 180-day open season
period, and instead provide for a 120day open season.24 Our focus in
establishing this 120-day period was to
arrive at a time period such that all
prospective bidders reasonably could
review the open season information and
evaluate whether to make multi-year
capacity commitments, thereby leveling
the playing field.
70. When discussing the duration of
the whole ‘‘open season process,’’ we
must consider the potential for delays
due to disputes arising during the open
season. In this regard, we found in
Order No. 2005 that pre-approval of
open season procedures would ‘‘allow
issues to be identified and resolved at
the earliest possible time and, ideally,
reduce the possibility of dissatisfaction
with open seasons, as well as the risk
that the Commission will have to
require that deficient open seasons be
conducted again.’’ 25 The North Slope
Producers’ and Enbridge’s disagreement
with this assessment is based on
arguments that the transparency and
specificity of the information required
in the open season and other protections
provided in the open season rules
render pre-approval unnecessary, and
that the pre-approval process itself
invites delay.
71. We are not as optimistic as the
North Slope Producers and Enbridge
that there is little likelihood that
disputes might arise over the conduct of
an open season and its conformance
with the open season rules. While the
transparency and specificity of the open
season rules might lead to a clearer
identification of any issues in dispute,
they do not change the fact that in any
open season there will be a universe of
potential bidders with starkly different,
competing needs and interests, and the
potential for dispute is real. We
continue to believe that getting it right
the first time is the best approach.
72. Nonetheless, in revisiting the
requirement for mandatory pre-approval
as a result of these rehearing requests,
we find that it is appropriate to make
some changes. First, we are revising
section 157.38 to make clear that the
plan to be filed by a prospective
applicant shall include the information
required in a notice of open season
under section 157.34. Second, we are
eliminating the 30-day prior notice
requirement in section 157.34(a). Since
24 The 120 days consists of the 30-day prior notice
period (section 157.34(a)), followed by a 90-day
open season (section 157.34(d)(1)).
25 Order No. 2005 at P 109.
PO 00000
Frm 00036
Fmt 4700
Sfmt 4700
the public will have actual notice of a
prospective applicant proposed open
season notice at least 90 days prior to
the open season, there is no reason to
provide for an additional prior notice
period. By this change, we are reducing
the 210-day period to 180 days. It also
is our conclusion that, given the fact
that participants in an open season will
have the opportunity to object to the
conduct of the open season after a
certificate application is filed, as is our
current practice, as well as the ability to
seek rehearing and obtain appellate
review of any Commission certificate
orders, orders approving open season
procedures will be interlocutory and not
subject to rehearing.
V. In-State Study
A. The Final Rule—§ 157.34(b)
73. In response to concerns expressed
by Alaska entities and in recognition of
Congress’s mandate that Alaska in-state
needs be given due consideration, the
Final Rule added in section 157.34(b) a
requirement not contained in the
proposed regulations that the open
season information include an
assessment of Alaska’s in-state needs
and prospective points of delivery
within the State of Alaska, based to the
extent possible on any available study
performed or otherwise approved by an
appropriate Alaska governmental entity.
B. Rehearing/Clarification Requests
74. While the North Slope Producers
find reasonable a requirement that a
study of in-state needs be completed
prior to any open season, they object to
section 157.34(b)’s requirement that the
contents of the open season notice rely
on an in-state study, if practicable. They
assert that ANGPA does not require a
pipeline sponsor’s study to ‘‘include or
consist’’ of a state-sanctioned study. The
North Slope Producers contend that this
requirement invites disputes as to
whether it is ‘‘practicable’’ to include a
state study, or whether ‘‘appropriate’’
state officials were involved.
Consequently, the North Slope
Producers request that the Commission
revise section 157.34(b) to require that
a project sponsor consult with the State
regarding the study for in-state needs.
75. The Alaska Legislators state that
the Commission has avoided the
problem of ‘‘dueling studies’’ by
deferring the study to the State of
Alaska. In this regard, the Alaska
legislators advise the Commission that
the State of Alaska has undertaken to
designate an appropriate agency to
conduct or sanction the required study,
and the Alaska House of Representatives
has passed a resolution urging the
E:\FR\FM\16JNR1.SGM
16JNR1
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
Administration to conduct, approve, or
sanction the required study prior to the
effective date of the opens season rules.
state rates are to be distance-sensitive in
order to ensure that the cost of in-state
service is calculated properly.
C. Commission Response
76. Section 157.34(b) does not
mandate the use of a particular study
but rather is premised on the commonsense notion that information provided
by the State of Alaska likely will be
valuable to potential shippers. We trust
that the State and prospective pipeline
applicants can agree on the manner in
which such information can be
provided. If questions arise as to the
extent to which it is possible to include
a state study, we will resolve them. Our
regulations offer several options that the
prospective applicant and the State of
Alaska could take to ensure the
adequate involvement of the State.
Accordingly, we will not revise section
157.34(b).
C. Commission Response
81. During the open season process,
qualified bidders must successfully bid
upon and arrange to consummate
service agreements for transportation
service. Projected rates for in-state
deliveries must be based on estimates of
costs for providing service to the in-state
delivery points. While prospective
applicants will estimate rates during an
open season, the Commission’s review
of proposed rates will be guided by
section 284.10(c)(3) of our regulations,
which states in part that ‘‘[a]ny rate filed
for service * * * must reasonably
reflect any material variation in the cost
of providing the service due to * * *
the distance over which the
transportation is provided.’’
82. All shippers on any new interstate
pipeline have a right to pay only the
initial rate on file as approved in the
NGA section 7 certificate of public
convenience and necessity. Those initial
rates, approved under section 7 as part
of the certificate, would be paid unless
changed under section 4 or 5 of the
NGA after appropriate regulatory
proceedings and upon the Commission’s
order. However, under the
Commission’s negotiated rate policy,26
pipelines and shippers are free to make
an agreement to ‘‘dispense with cost-ofservice regulation’’ and agree to any
mutually agreeable rate. A recourse rate
found in the pipeline’s tariff would be
available for those shippers preferring
traditional cost-of-service rates. Thus, if
an in-state service is successfully bid
upon, filed for and approved, an in-state
cost-of-service recourse rate would be
set in an Alaskan pipeline’s tariff, but
in-state shippers would also be free to
seek a negotiated in-state rate with an
Alaskan pipeline. Negotiated rates can
be used to lock in transportation costs
and pipeline revenues to the mutual
benefit of both the shippers and the
pipeline, without the risks of later
changes to rates and revenues under the
NGA.
83. If there are no successful bids for
in-state service, the prospective
applicant would nonetheless have to
include the in-state service as part of its
proposed initial tariff. An opportunity
to have in-state service might arise if the
pipeline voluntarily accepts a request
for it at a later time, or if the
VI. In-State Rates
A. The Final Rule—§ 157.34(c)(8)
77. In addition to the requirement that
in-state gas needs be addressed in the
open season, the Commission also
required, in section 157.34(c)(8), that,
based on in-state needs and the delivery
points identified in the study, open
season information includes a proposed
in-state transportation rate, based on the
costs of providing that service.
B. Rehearing/Clarification Requests
78. The North Slope Producers ask the
Commission to clarify that estimating
rates for in-state service does not create
a requirement to offer such a service at
that rate (or at all) if the open season
does not yield firm commitments for inState deliveries. They assert that the
ultimate indicator of any market for instate service is the willingness of
shippers to make firm commitments to
purchase capacity for in-state use during
the open season, not a study. They also
request that the Commission clarify that
the estimated in-state service rates are
merely illustrative and subject to
adjustment.
79. Enbridge requests that the
Commission make clear that the
‘‘estimated transportation rate’’ referred
to in section 157.34(c)(8) is one based
on project sponsor’s estimated costs to
make in-state deliveries, not upon any
rates assumed by the study.
Additionally, Enbridge states that the
Commission clarify that bids for in-state
service should be subjected to the same
requirements for creditworthiness,
collateral and execution of binding
contractual commitments as apply to
any other open season bidder.
80. The State of Alaska asks the
Commission to clearly state that the in-
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
26 Alternatives to Traditional Cost-of-Service
Ratemaking for Natural Gas Pipelines, Docket No.
RM95–6–000, Regulation of Negotiated
Transportation Services of Natural Gas Pipelines,
Docket No. RM96–7–000, 74 FERC ¶ 61,076, (Jan.
31, 1996).
PO 00000
Frm 00037
Fmt 4700
Sfmt 4700
35021
Commission acts under section 103(h)
of ANGPA and section 5 of the NGA to
require the pipeline to make such instate deliveries. The actual in-state rate
for in-state service would be an issue for
such future proceedings. Based on the
foregoing, we see no need to further
clarify the regulations.
VII. Tying Arrangements
A. The Final Rule—§§ 157.34(c)(6),
157.34(c)(10), and 157.35(a)
84. The Commission addressed the
matter of tying access to pipeline
capacity on an Alaska project to
ancillary services in two sections of the
Final Rule. First, section 157.34(c)(6)
requires that the open season notice
must contain an unbundled
transportation rate. Second, section
157.34 (c)(10) prohibits a prospective
applicant from requiring prospective
shippers to process or treat their gas at
any designated facility. We explained
elsewhere in Order No. 2005 ‘‘that [we]
can address any other discriminatory
conduct in connection with gas quality
requirements or other ancillary services
through the provisions of section 157.35
in conjunction with existing
Commission policies and procedures.’’
Relevant to this explanation, section
157.35(a) provides that ‘‘[a]ll binding
open seasons shall be conducted
without undue discrimination or
preference in the rates, terms, or
conditions of service and all capacity
awarded as a result of any open season
shall be awarded without undue
discrimination or preference of any
kind.’’
B. Rehearing/Clarification Requests
85. The State of Alaska states that the
Commission should more explicitly
explain the prohibition against tying
arrangements, and explain how the
open season rules will apply to gas
treatment plants. The State believes that
the open season rules should do more
than require an applicant to use an
unbundled transportation rate, prohibit
tying of capacity on the pipeline to the
use of a designated plant or facility, and
merely refer to the existing regulations
and policies prohibiting undue
discrimination or preference. Rather,
Alaska states that the open season rules
should make clear that any tying
arrangements will be subject to an
exacting inquiry by the Commission and
will require a compelling justification,
and even offers recommended language
to this end.
86. Alaska also states that since
ANGPA includes gas treatment plants in
its definition of an Alaska natural gas
E:\FR\FM\16JNR1.SGM
16JNR1
35022
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
transportation project,27 treatment
plants should be subject to the open
season regulations. Alaska points out
that the effect of the unbundling
requirement of section 157.34(c)(6) is to
exclude gas treatment plants from the
requirements of the open season. As a
possible solution, Alaska suggests that
the open season rules be clarified to
provide that the applicant must
separately offer gas treatment plant
capacity and pipeline capacity in the
open season notice, and give bidders an
opportunity to bid on either or both, as
they choose. ChevronTexaco contends
that because gas treatment plants are
jurisdictional facilities,28 Order No.
2005’s approach of deferring
consideration of any discriminatory
conduct as to necessary such ancillary
facilities and services to a later day does
not satisfy the requirements of the
ANGPA. Chevron Texaco maintains that
it is particularly important that access to
treatment facilities be subject to the
same open season, non-discriminatory
requirement as the pipeline because
pipeline capacity without access to gas
treatment facilities that maybe a part of
the pipeline system is meaningless.
C. Commission Response
87. The Commission did not intend to
preclude the inclusion of jurisdictional
natural gas conditioning facilities from
the open season. If, pursuant to ANGPA
section 103, a project sponsor intends to
file an application under section 7 of the
NGA for authorization of a project that
includes a jurisdictional natural gas
conditioning service, we will review the
open season plan and notice to ensure
that such service is offered in its open
season notice, subject to the same
requirements as apply to transportation
service. However, the prospective
applicant must offer a separate rate for
the gas treatment service and separate
rate for the transportation service.
Furthermore, the prospective applicant
can neither require bidders to bid on
both services, nor evaluate the bids
based on whether bidders requested one
or both services. Moreover, while the
prospective applicant can require
specific natural gas quality
specifications such as would be met by
using the conditioning services offered,
it cannot reject an otherwise qualified
27 ANGPA Section 102(2) defines the term ‘Alaska
natural gas transportation project’ as ‘‘any natural
gas pipeline system that carries Alaska natural gas
to the border between Alaska and Canada
(including related facilities subject to the
jurisdiction of the Commission) * * *’’
28 See Venice Gathering Co., 97 FERC ¶ 61,045 at
61,255 (2001) (Treatment of gas to enhance its safe
and efficient transportation is subject to
Commission jurisdiction).
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
bidder that states that it will deliver to
the pipeline facilities gas that meets the
stated quality specifications.
88. On the other hand, if a prospective
applicant is proposing to apply to revise
the Alaska Natural Gas Transportation
System (ANGTS) application now held
in abeyance, then a conditioning service
will have to be included as a part of the
open season but again, with all services
offered priced separately. Specifically,
in 1981, President Reagan submitted a
Waiver of Law to Congress for the
purpose of clearing away certain
government-imposed obstacles to the
private financing of the ANGTS. The
Commission implemented that portion
of the Presidential waiver that required
the Commission to include within the
ANGTS the gas conditioning plant at
Prudhoe Bay.29
VIII. Pre-Subscribed Capacity
A. The Final Rule—§§ 157.33(b) and
157.34(c)(15)
89. Under section 157.33(b), presubscription agreements for initial
capacity on a proposed Alaska natural
gas transportation project are permitted,
provided that capacity is offered to all
open season prospective bidders at the
same rates and on the same terms and
conditions as contained in the presubscription agreements. In addition, if
there is more than one pre-subscription
agreement, open season prospective
bidders are given the option of selecting
the rates, terms and conditions
contained in any one of the several
agreements. However, section
157.34(c)(15) states that ‘‘[i]f capacity is
oversubscribed and the prospective
applicant does not redesign the project
to accommodate all capacity requests,
only capacity that has been acquired
through pre-subscription shall be
subject to allocation on a pro rata basis;
no capacity acquired through the open
season shall be allocated.’’
B. Rehearing/Clarification Requests
90. The North Slope Producers assert
that the provision in section
157.34(c)(15) subjecting only
presubscribed capacity to pro rata
allocation, will dissuade any shippers
from signing up for the presubscribed
capacity, thereby ‘‘wholly negating’’ the
recognized benefits of allowing presubscription agreements to facilitate the
development of an Alaska natural gas
transportation project. They predict that
prospective shippers would rather wait
for the open season than risk proration.
The North Slope Producers maintain
that this selective proration unduly
29 See Alaskan Northwest Natural Gas
Transportation Co., 18 FERC ¶ 61,002 (1982).
PO 00000
Frm 00038
Fmt 4700
Sfmt 4700
discriminates against those shippers
who are willing to make early
commitments for firm capacity in order
to support the project, in violation of the
NGA and Commission policy. They add
that since section 157.33(b) allows all
open season participants to enjoy the
same benefits as contained in the presubscription agreements, such
discrimination is particularly
unjustified. The North Slope Producers
add that this is another example where
the Commission is attempting to compel
the project sponsor to make design
changes in order to accommodate all
bids.
91. The North Slope Producers also
state that the final clause of section
157.34(c)(15) is not consistent with the
Commission’s presumed intent not to
foreclose proration among open season
bidders where there is no presubscribed
capacity. They suggest that the final
clause of that provision, which states
‘‘no capacity acquired through the open
season shall be allocated,’’ should be
clarified.
92. In addition to agreeing that
proration renders pre-subscription an
unattractive option for prospective
shippers, Enbridge adds that the
additional requirement that the terms
and conditions of any pre-subscription
agreements be made public prior to the
open season notice renders presubscription even less desirable because
it put anchors shippers at a competitive
disadvantage to open season bidders
who would have prior knowledge of the
pre-subscription bids. At the same time,
Enbridge concedes that it would be
highly unlikely that project would not
be re-designed to accommodate capacity
of all qualified bids at the incipient,
open season stage.
93. Enbridge raises again the claim
that the ‘‘numerous and overlapping
protections’’ of Order No. 2005, in
particular the level of information
provided in open season notice and
measures provided to ensure against
discrimination, are sufficient to ensure
a fair, open and non-discriminatory
open season process. Enbridge also
states that the Commission should
clarify that open season shippers who in
the open season elect to select the terms
and conditions of a pre-subscription
agreement may not ‘‘cherry-pick’’ terms
and conditions from several agreements
but must accept any one agreement in
its entirety.
94. The State of Alaska seeks
clarification that, in the case of capacity
allocation on an oversubscribed
pipeline that cannot reasonably be
redesigned, both presubscribed capacity
and capacity later acquired on the same
rates, terms and conditions will be
E:\FR\FM\16JNR1.SGM
16JNR1
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
subject to allocation, for the reason that
the final words of section 157.34(c)(15)
stating that ‘‘no capacity acquired
through the open season shall be
allocated,’’ suggests otherwise.
95. ChevronTexaco maintains that the
Commission failed to consider and
provide for the various circumstances
that could trigger the pro-rationing of
pre-subscribed capacity. ChevronTexaco
states that bidders in the open season
could outbid pre-subscribing shippers
on the basis of any of the qualifying
conditions: For instance, an open season
bidder might outbid pre-subscribing
shippers whose agreements are at less
than maximum rates, or whose
agreements are of shorter terms.
ChevronTexaco is concerned that presubscribing shippers might lose their
capacity to open season bidders who
outbid them because they know the
salient terms of the pre-subscription
agreements. Therefore, ChevronTexaco
submits that the Commission should
expand the requirement of pro-rationing
by establishing that all bids eligible to
be allocated capacity in an open season
where pre-subscribing shippers will be
prorated should be treated as having
equal value to the pre-subscription
precedent agreement for purposes of
pro-rationing. In this way, later
qualifying bidders would be prevented
from outbidding pre-subscribing
shippers.
96. In response to the claims on
rehearing that the capacity allocation
provisions of section 157.34(c)(15) are
counterproductive because they will
deter potential anchor shippers from
entering into pre-subscription
agreements, Anadarko contends that the
Commission’s finding that the North
Slope Producers’ unique position of
control over pipeline design amply
justifies putting the consequences of any
decision not to redesign pipeline to
accommodate all bidders on them.
Anadarko also questions the importance
placed on pre-subscription agreements
in connection with an Alaska pipeline
project. According to Anadarko, the
only justification for a pre-subscription
agreement is to facilitate financing and
to provide the project sponsor with
assurances that it has the commitments
to justify development and construction
expenses. However, states Anadarko,
there is little doubt that any Alaska
natural gas transportation project will be
fully committed, even without presubscription agreements.
97. The Alaska Legislators support the
pre-subscription rules of Order No.
2005, claiming that the rules make sense
given the unique nature and
circumstances of an Alaska natural gas
transportation project and the need to
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
balance concerns ‘‘that pre-subscription
is essential to finance the pipeline with
concerns of those who feared that such
arrangements would favor affiliates of
the pipeline or otherwise undermine the
objectives of conducting public open
seasons for capacity.’’
C. Commission Response
98. Although we allowed presubscription agreements in the belief
that they could have utility in
facilitating the development of an
Alaska natural gas transportation
project, we cannot quantify how
beneficial such arrangements are. Our
paramount consideration in allowing
pre-subscription was that it should not
impact in any way the capacity obtained
through the open season process. For
this reason, we provided that any
capacity acquired by reason of
agreements entered into prior to the
open season would have to yield to
capacity bid for in the open season in
the case of oversubscription We believe
our reasons for this selective proration,
as stated in Order No. 2005 and
reaffirmed here, are sound.
99. The argument that anchor
shippers will be dissuaded from
entering into pre-subscription
agreements if they risk losing capacity
as a result of open season bidding, and
that the ‘‘recognized benefits’’ of presubscription will be lost, is
unpersuasive. The North Slope
producers and other potential project
sponsors have developed a plethora of
information in recent years regarding
the viability of an Alaska project. They
are fully capable of deciding whether
they wish to execute pre-subscription
agreements. If they do not, capacity will
be allocated in an open season. There
has been no showing that an Alaska
project cannot be financed, as are many
major projects, based on commitments
made in an open season. While we have
concluded that the public interest
permits pre-subscription, under the
conditions established by the rule, we
do not find that the public interest
requires pre-subscription. It does
require competition and open-access.
We leave it to potential project sponsors
and shippers whether pre-subscription
makes sense to them.
100. We will, however, clarify section
157.34(c)(15) in two respects, first to
eliminate confusion over the last
sentence of that section which
concludes ‘‘no capacity acquired
through the open season shall be
allocated,’’ and second to make clear
that in the event there is more than one
pre-subscription agreement, bidders in
the open season may not cherry-pick
among the provisions of the several
PO 00000
Frm 00039
Fmt 4700
Sfmt 4700
35023
agreements. The North Slope Producers
contend that the last clause of section
157.34(c)(15) might be read to provide
that proration is foreclosed among open
season bidders even where there is no
presubscribed capacity. We will clarify
the language of the rule to avoid such
a misreading. Capacity bid for in the
open season is exempt from allocation
only in a case where there is also
presubscribed capacity, as explained in
the text of Order No. 2005. The State of
Alaska reads that clause to suggest that
capacity acquired by bidders in the
open season who elect to acquire their
capacity on the same rates, terms and
conditions as contained in a presubscription agreement will not be
subject to pro rata allocation along with
the pre-subscription shippers. Such an
interpretation also misreads the intent
of section 157.34(c)(15), and we will
clarify the language of the rule
accordingly. Finally, we will clarify
section 157.33 to make clear that open
season bidders may not cherry pick
among the provisions of several
precedent agreements, as was our intent
in the Final Rule.
IX. Other Issues
101. The North Slope Producers
request that the open season rules be
clarified in certain respects. First, they
request that the Commission clarify the
open season regulations by replacing
references to ‘‘prospective points of
delivery within the State of Alaska’’ or
‘‘delivery points’’ in several subsections
of the regulation with the term ‘‘tie-in
points.’’ 30 The North Slope Producers
assert that the term ‘‘delivery point’’
implies an obligation that the pipeline
will be finally designed to deliver gas all
the way to in-State markets and that
ANGPA does not contemplate or impose
such an obligation.
102. The Commission understands the
terms ‘‘prospective points of delivery
within the State of Alaska’’ or ‘‘delivery
points’’ to mean those points on the
interstate Alaskan pipeline where
custody of the gas would be transferred
to the facilities of an intrastate pipeline,
local distribution company, or end-user
whose facilities are not otherwise under
the Commission’s jurisdiction, assuming
that shippers on an Alaska pipeline
requested such deliveries. The term
‘‘tie-in points’’ as used only once in
ANGPA is used in reference to the study
of in-state needs in section 103(g) and
as a familiar natural gas industry phrase
is not as familiar to the Commission as
30 These sections include § 157.34(b) and
157.34(c)(1), (2), (3), (6), (8), and (16).
E:\FR\FM\16JNR1.SGM
16JNR1
35024
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
the terms ‘‘points of delivery’’ or
‘‘delivery points.’’ 31
103. As part of the open season, the
prospective applicant is in fact obligated
to offer to deliver gas at least at certain
prospective in-state delivery points
identified in the study of in-state needs.
However, the open season notice’s
initial design of the pipeline need only
match the prospective applicant’s open
season business proposal to deliver at
least the amount of gas identified in the
study of in-state needs at those
prospective in-state delivery points.
Bidders may seek alternative delivery
points (such as ones closer to their
market) as part of their bids, and as part
of the open season the prospective
applicant may consider building
additional facilities to such alternate
points, but has no obligation to do so as
long as it treats similar requests the
same. As discussed above, if the open
season ends without any successful bids
for in-state deliveries, then there is a
continuing obligation for the
prospective applicant to leave provision
for such in-state service available in its
tariff, but it would not have to
voluntarily propose such service as part
of its initial application. Also, as used
in section 157.34, the term ‘‘delivery
point(s)’’ also refers to the location at
the border between Alaska and Canada
where presumably prospective bidders
will seek to have their volumes
delivered. It would be much more
confusing if the regulations were revised
to refer to ‘‘tie-in points’’ for points
inside Alaska and ‘‘delivery points’’ for
locations at the border between Alaska
and Canada. Therefore, we will not
clarify the rules as requested by the
North Slope Producers in this regard.
104. Second, the North Slope
Producers state that the ‘‘catch-all’’
language in section 157.34(c)(18) was
not scaled back enough from the
language proposed in the NOPR.
Specifically, they state that as written,
the final regulation requires a pipeline
applicant to provide all bidders, not
only with information the applicant has
provided to any bidder, but also with
information ‘‘in the hands of’’ any
bidder. The North Slope Producers
claim that the applicant cannot know
what information identified in section
157.34(c)(18) is ‘‘in the hands of a
potential shipper.’’ Moreover, they
contend that while the text of Order No.
2005 does not discuss the intent of this
subsection, the Commission’s press
release and the Commission staff’s
31 Although tie-in point is used in some
Commission documents, the most common use is
to identify the point where a pipeline’s loop ties
back into the mainline.
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
PowerPoint presentation at the February
9, 2005 Commission Open Meeting
presentation refer to information that
the applicant has in some way made
available to a potential shipper, and the
regulations should be clarified to be
consistent with this intent. The North
Slope Producers add that, read literally,
this language would call for protected
information. Enbridge, on the other
hand, claims that section 15734(c)(18)
should be eliminated as unnecessary
due to the transparency assured by the
rest of the numbered subsections of
section 157.34(c).
105. Anadarko objects to this
requested clarification, pointing out that
the North Slope Producers are likely
already to possess relevant projectrelated information as a result of
discussions with other possible project
sponsors, and if the North Slope
Producers becomes the project sponsor,
this information is already in their
hands and was not made available to
them by an applicant.
106. The ‘‘catchall’’ provision
addresses the difficult issue of
separation of functions between a
prospective applicant and its affiliates
who produce, sell or market Alaska gas,
and as such are potential bidders for
capacity on an Alaska natural gas
transportation project. It has been
targeted as a problem since it appeared
in the NOPR and it was discussed
extensively in the Final Rule.32 The
North Slope Producers have undertaken
millions of dollars of due diligence
‘‘homework’’ on the design, cost,
operation and feasibility of an Alaska
pipeline. If they are not affiliated with
the prospective applicant for an Alaska
pipeline, then all that knowledge and
information is theirs and, presumably,
would give them an informational
advantage in the open season bidding.
However, if the North Slope Producers
are affiliated with the prospective
applicant, then the Commission and
other potential bidders must be assured
that any relevant information about the
design, cost, operation and feasibility of
an Alaska pipeline that the North Slope
Producers transfers to an affiliated
prospective applicant is available to
everyone. The Commission desires to
make this very important part of the
Final Rule as clear as possible. Thus, we
will revise section 157.34(c)(18) to read
as follows:
All information that the prospective
applicant has in its possession pertaining to
the proposed service to be offered, projected
pipeline capacity and design, proposed tariff
provisions, and cost projections, or that the
prospective applicant has made available to,
PO 00000
32 See
Order No. 2005 at P 72–83.
Frm 00040
Fmt 4700
Sfmt 4700
or obtained from, any potential shipper,
including any affiliates of the project sponsor
and any shippers with pre-subscribed
capacity, prior to the issuance of the public
notice of open season;
The Commission understands that the
scope of this information is extensive.
Therefore, we will not require that the
contents of the open season notice to be
published by the prospective applicant
must contain copies of all the
documents which would be covered
under section 157.34(c)(18), but that the
notice identify a ‘‘public reading room’’
where such information is available, for
copying at the reader’s expense. Further,
as the North Slope Producers point out,
dealing with potential ‘‘protected
information’’ will have to be addressed
as it is in any commercial situation. The
Commission expects that all parties will
cooperate in dealing with ‘‘protected
information,’’ but as in all matters
pertaining to the open season process,
the Commission and its staff stand ready
to assist in resolving any disputes.
107. Third, the North Slope Producers
request that the Commission clarify the
requirement in section 157.35(c) that the
project applicant ‘‘create or designate a
unit or division to conduct the open
season that must function independent
of the other divisions of the project
applicant as well as the applicant’s
Marketing and Energy affiliates.’’ They
claim that they intend to create a
separate entity to be the project sponsor
and to conduct the open season, and
that this section would require them to
establish yet another separate entity to
conduct the opens season, and that
section 157.35(c) should be revised to
reflect that this is sufficient.
Specifically, the North Slope Producers
propose to delete from the regulations
the language requiring that a project
applicant must designate a separate unit
or division to conduct the open season.
Anadarko claims that this requested
clarification would largely nullify the
purpose of section 157.35(c).
108. The Commission denies the
North Slope Producers’ proposed
change to section 157.35(c). However,
the Commission will amend the section
to take into account situations in which
a project applicant is an entity that has
been separately created for the purpose
of conducting an open season. In such
cases, the separate entity would comply
with the provisions of section 157.35(c)
if that project applicant functioned and
operated independently from the project
applicant’s Marketing and Energy
Affiliates, as well as the other divisions
of the project applicant. The purpose of
section 157.35(c) is to ensure that the
project applicant conducting the open
season is independent of, and does not
E:\FR\FM\16JNR1.SGM
16JNR1
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
favor, its affiliates. If the project
applicant was created to comply with
section 157.35(c) and does, in fact,
comply with the regulation, the project
applicant is not required to create a
further subdivision to achieve
compliance.
109. The North Slope Producers
identify several other non-substantive
clarifications to the regulatory language
that should be made to avoid
confusion.33 These corrections will be
made.
110. Enbridge argues that since the
open season regulations require that the
project design criteria include a
requirement that the project be capable
of ‘‘low-cost expansion,’’ 34 the
Commission should explain that the
threshold for satisfying the low-cost
expansion’’ standard is any expansion
that does not increase rates to initial
shippers. However, as Enbridge
recognizes, any certificate application
for an Alaska natural gas transportation
project might provide detail regarding
several expansion scenarios depending
on and in response to the results of the
open season. The project design review
that the Commission will undertake
focuses on the proposed project’s ability
to accommodate the capacity bid for in
the open season, as well as the extent to
which the project can accommodate
‘‘low-cost’’ expansion. All expansions
will involve cost. Obviously, as
recognized by virtually all stakeholders,
capacity that can be gained by
compression alone would typically be
the lowest-cost expansion. At the other
end of the spectrum would be a pipeline
that has no compression-only expansion
potential, necessitating the need for
looping in the first instance. The
operative word in connection with any
‘‘low-cost’’ standard in section 157.37,
is the extent of the design’s
expandability, and that standard is not
tied to the cost impact of a given
expansion. Consequently we will not
clarify section 157.37 as requested by
Enbridge.
111. ChevronTexaco claims that the
Final Rule contains a conflict about how
the contract term might be used by the
33 These include typographical errors in section
157.35(d) (references to sections 258.4(a)(1) and (3)
should be to sections 358.4(a)(1) and (3)), Order No.
2005, P 74 (should cite to §§ 358.5(d) and
358.4(e)(3) rather than §§ 358.4(d) and 358.(b)(e)(3));
section 157.34(c)(9) (‘‘proscribed’’ should be
changed to ‘‘prescribed’’); and section 157.33(b)
(‘‘terms, rates, terms and conditions’’ should be
changed to ‘‘duration, rates, terms and conditions’’).
The North Slope Producers also suggest that the
term ‘‘rate amounts’’ in section 157.34(c)(9) should
be changed to ‘‘rates’’ as the latter term is more
commonly used in the industry.
34 See, e.g., Order No. 2005 at P 82; section
157.37.
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
prospective applicant in establishing its
methodologies for the evaluation of bids
and the allocation of capacity due to
oversubscription, should that be
necessary. It states that this confusion is
caused because contract term is not
mentioned in section 157.34(c)(14)
regarding evaluation of bids, but is
mentioned in section 157.34(c)(15)
regarding allocation of capacity due to
oversubscription. ChevronTexaco also
complains that the Commission’s stated
intention to rely on after the fact
enforcement of issues that might be
caused by unusual contract terms, rather
than set a cap on contract term for the
purpose of bidding and allocation
review methodologies, does not satisfy
ANGPA’s mandate that the
Commission’s open season rules are
fully prescriptive. ChevronTexaco
requests that the Commission clarify the
open season regulations to require that
open season notices to include a cap on
the contract term for capacity bids.
112. First, our intention to rely on
after-the-fact enforcement of open
season issues that might be caused by
unusual contract terms, or by any other
aspect of the open season process that
is not specifically enumerated in the
open season regulations, completely
satisfies the intent of Congress as stated
in ANGPA. Moreover, as explained in
Order No. 2005, it is consistent with our
existing policy. However, we do agree
that the discrepancy in language
between section 157.34(c)(14) and
section 157.34(c)(15) should be clarified
to provide consistency between the
methodologies for the evaluation of bids
and the allocation of capacity due to
oversubscription. To be consistent and
avoid confusion, we will delete the
phrase ‘‘including price and contract
term’’ from section 157.34(c)(15).
Furthermore, we will look carefully at
this issue in our review of any open
season plan and notice under section
157.38.
113. ChevronTexaco claims that the
only way to assure that an open season
was conducted fairly and in accordance
with the open season rules is by making
the precedent agreements publicly
available. Therefore, ChevronTexaco
objects to the provision in section
157.34(d)(4) which provides that all
precedent agreements and
correspondence with bidders who were
not allocated capacity must be filed
with the Commission, but that they may
be filed under a request for confidential
treatment pursuant to section 388.112 of
the Commission’s regulations.
ChevronTexaco claims that since
precedent agreements will become
agreements that will appear in a pro
forma tariff or an effective tariff, there is
PO 00000
Frm 00041
Fmt 4700
Sfmt 4700
35025
little chance that the information in the
precedent agreements should be
confidential for any prolonged period of
time, or that any of the information
would fall under a Freedom of
Information Act exemption.
ChevronTexaco states that the precedent
agreements could be filed in a public
and non-public version in the event
parts of the agreements do contain
protected information.
114. We deny ChevronTexaco’s
request. Under section 388.112 of the
Commission’s regulations, any person
submitting a document to the
Commission may request privileged
treatment by claiming that some or all
other information is exempt from the
Freedom of Information Act’s disclosure
requirements. We are nor conferring any
special confidential status to the
agreements. The party requesting
privileged treatment must support that
claim. It may be, as ChevronTexaco
claims, that precedent agreements are
not likely to be exempt from disclosure.
Neither section 157.35(d)(4) nor section
388.112 predetermines whether
privileged treatment will be granted.
Document Availability
115. In addition to publishing the full
text of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the Internet through
FERC’s Home Page (https://www.ferc.gov)
and in FERC’s Public Reference Room
during normal business hours (8:30 a.m.
to 5 p.m. Eastern time) at 888 First
Street, NE., Room 2A, Washington DC
20426.
116. From FERC’s Home Page on the
Internet, this information is available in
the Federal Energy Regulatory Records
Information System (FERRIS). The full
text of this document is available on
FERRIS in PDF and Microsoft Word
format for viewing, printing, and/or
downloading. To access this document
in FERRIS, type the docket number
excluding the last three digits of this
document in the docket number field.
117. User assistance is available for
FERRIS and the FERC’s Web site during
normal business hours from our Help
line at (202) 502–8222 or the Public
Reference Room at (202) 502–8371 Press
0, TTY (202) 502–8659. E-Mail the
Public Reference Room at
public.referenceroom@ferc.gov.
Effective Date
118. These regulations are effective as
of the date of publication in the Federal
Register.
E:\FR\FM\16JNR1.SGM
16JNR1
35026
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
List of Subjects in 18 CFR Part 157
Administrative practice and
procedure; Natural gas; Reporting and
recordkeeping requirements.
By the Commission.
Linda Mitry,
Deputy Secretary.
In consideration of the foregoing, the
Commission amends Part 157, Chapter I,
Title 18, Code of Federal Regulations, as
follows.
I
PART 157—APPLICATIONS FOR
CERTIFICTES OF PUBLIC
CONVENIENCE AND NECESSITY AND
FOR ORDERS PERMITTING AND
APPROVING ABANDONMENT UNDER
SECTION 7 OF THE NATURAL GAS
ACT
1. The authority citation for Part 157 is
revised to read as follows:
I
Authority: 15 U.S.C. 717–717w.
Subpart B—Open Seasons for Alaska
Natural Gas Transportion Projects
2. In § 157.33, paragraph (b) is revised
to read as follows:
I
§ 157.33
Requirement for open seasons.
(a) * * *
(b) Initial capacity on a proposed
Alaska natural gas transportation project
may be acquired prior to an open season
through pre-subscription agreements,
provided that in any open season as
required in paragraph (a) of this section,
capacity is offered to all prospective
bidders at the same rates and on the
same terms and conditions as contained
in the pre-subscription agreements. All
pre-subscription agreements shall be
made public by posting on Internet
websites and press releases within ten
days of their execution. In the event
there is more than one such agreement,
all prospective bidders shall be allowed
the option of selecting among the
several agreements all of the rates, terms
and conditions contained in any one
such agreement.
3. In § 157.34, paragraphs (a), (c)(9),
(c)(15) and (c)(18), and (d)(2) are revised
to read as follows:
I
§ 157.34
Notice of open season.
(a) Notice. A prospective applicant
must provide reasonable public notice
of an open season through methods
including postings on Internet Web
sites, press releases, direct mail
solicitations, and other advertising. In
addition, a prospective applicant must
provide actual notice of an open season
to the State of Alaska and to the Federal
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
Coordinator for Alaska Natural Gas
Transportation Projects.
*
*
*
*
*
(c) * * *
(9) Negotiated rate and other rate
options under consideration, including
any rates and terms of any precedent
agreements with prospective anchor
shippers that have been negotiated or
agreed to outside of the open season
process prescribed in this section;
*
*
*
*
*
(15) The methodology by which
capacity will be awarded, in the case of
over-subscription, clearly stating all
terms that will be considered, except
that if any capacity is acquired through
pre-subscription agreements as provided
in § 157.33(b) and the prospective
applicant does not redesign the project
to accommodate all capacity requests,
only that capacity that was acquired
through pre-subscription or was bid in
the open season on the same rates,
terms, and conditions as any one of the
pre-subscription agreements shall be
allocated on a pro rata basis and no
other capacity acquired through the
open season shall be allocated.
*
*
*
*
*
(18) All information that the
prospective applicant has in its
possession pertaining to the proposed
service to be offered, projected pipeline
capacity and design, proposed tariff
provisions, and cost projections, or that
the prospective applicant has made
available to, or obtained from, any
potential shipper, including any
affiliates of the project sponsor and any
shippers with pre-subscribed capacity,
prior to the issuance of the public notice
of open season;
*
*
*
*
*
(d) * * *
(2) A prospective applicant must
consider any bids tendered after the
expiration of the open season by
qualifying bidders and may reject them
only if they cannot be accommodated
due to economic, engineering, design,
capacity or operational constraints, or
accommodating the request would
otherwise adversely impact the timely
development of the project, and a
detailed explanation must accompany
the rejection. Any bids tendered after
the expiration of the open season must
contain a good faith showing, including
a statement of the circumstances which
prevented the late bidder from tendering
a timely bid and how those
circumstances have changed. If a
prospective applicant determines at any
time that, based on the criteria stated in
this paragraph, no further late bids for
capacity can be accommodated, it may
PO 00000
Frm 00042
Fmt 4700
Sfmt 4700
request Commission approval to
summarily reject any further requests.
*
*
*
*
*
I 4. In § 157.35, paragraph (c) is revised
to read as follows and paragraph (d), the
word ‘‘258.4(a)(1)’’ is removed and the
word ‘‘358.4(a)(1)’’ is inserted in its
place.
§ 157.35 Undue discrimination or
preference.
(a) * * *
(b) * * *
(c) Each prospective applicant
conducting an open season under this
subpart must function independent of
the other divisions of the prospective
applicant as well as the prospective
applicant’s Marketing and Energy
affiliates as those terms are defined in
§ 358.3(d) and (k) of the Commission’s
regulations. In instances in which the
prospective applicant is not an entity
created specifically to conduct an open
season under this subpart, the
prospective applicant must create or
designate a unit or division to conduct
the open season that must function
independent of the other divisions of
the project applicant as well as the
project applicant’s Marketing and
Energy affiliates as those terms are
defined in § 358.3(d) and (k) of the
Commission’s regulations.
*
*
*
*
*
I 5. Section 157.36 is revised to read as
follows:
§ 157.36
Open seasons for expansions.
Any open season for capacity
exceeding the initial capacity of an
Alaska natural gas transportation project
must provide the opportunity for the
transportation of gas other than Prudhoe
Bay or Point Thomson production. In
considering a proposed voluntary
expansion of an Alaska natural gas
pipeline project, the Commission will
consider the extent to which the
expansion will be utilized by shippers
other than those who are the initial
shippers on the project and, in order to
promote competition and open access to
the project, may require design changes
to ensure that some portion of the
expansion capacity be allocated to new
shippers willing to sign long-term firm
transportation contracts, including
shippers seeking to transport natural gas
from areas other than Prudhoe Bay and
Point Thomson.
I 6. Section 157.38 is revised to read as
follows:
§ 157.38
Pre-approval procedures.
No later than 90 days prior to
providing the notice of open season
required by § 157.34(a), a prospective
E:\FR\FM\16JNR1.SGM
16JNR1
Federal Register / Vol. 70, No. 115 / Thursday, June 16, 2005 / Rules and Regulations
Before Commissioners: Pat Wood, III,
Chairman; Nora Mead Brownell, Joseph T.
Kelliher, and Suedeen G. Kelly.
and capacity is by submitting a single
electronic filing to the Commission via
the Division of Reliability’s pager
system at emergency@ferc.gov, in lieu of
the current requirement to file an
original and two copies with the
Secretary of the Commission.
2. Section 202(g) of the Federal Power
Act, 16 U.S.C 824a(g) (2000), which
implements section 206 of the Public
Utility Regulatory Policies Act of 1978
(Continuance of Service), directs the
Commission to promulgate a rule
requiring that each public utility report
‘‘promptly’’ to the Commission and
appropriate state regulatory authorities
any anticipated shortage of electric
energy or capacity which would affect
the public utility’s ability to serve its
wholesale customers.
3. In conformance with this statutory
provision, Part 294 of the Commission’s
regulations defines ‘‘anticipated
shortage of electric energy or capacity’’
and sets forth reporting requirements for
public utilities. Among other things, a
report filed pursuant to Part 294 must
include the nature and projected
duration of the anticipated shortage, a
list of firm wholesale customers likely
to be affected by the shortage,
procedures for accommodating the
shortage and a contact person at the
public utility.1 Section 294.101(e) of the
Commission’s regulations, 18 CFR
294.101(e) (2004), provides that a public
utility that submits a report pursuant to
Part 294 must file an original and at
least two copies to the Commission as
well as one copy to relevant state
regulators and firm power wholesale
customers, ‘‘unless otherwise required
by the Commission.’’
4. Generally, documents filed with the
Commission must be submitted to the
Secretary of the Commission, 18 CFR
375.105(c) (2004). However, time may
be of the essence when a public utility
is experiencing a shortage or anticipated
shortage of electric energy or capacity.
The Commission must receive
information in as close to real time as
possible for it to monitor meaningfully
and, if appropriate, react to the
situation. Accordingly, the Commission
is revising section 294.101(e) of its
regulations to provide that the means by
which public utilities must comply with
the requirement to report shortages and
anticipated shortages of electric energy
1. This Final Rule amends part 294 of
the Federal Energy Regulatory
Commission’s (Commission’s)
regulations, 18 CFR part 294 (2004), to
provide that the means by which public
utilities must comply with the
requirement to report shortages and
anticipated shortages of electric energy
1 18 CFR 294.101(c) (2004). Alternatively, 18 CFR
294.101(f) (2004) states that a public utility that
provides in its rate schedule that it will notify
appropriate states regulators and its firm power
wholesale customers of anticipated shortages need
only report to the Commission the nature and
projected duration of the anticipated shortage and
supply a list of firm power wholesale customers
affected or likely to be affected.
applicant must file, for Commission
approval, a detailed plan for conducting
an open season in conformance with
this subpart. The prospective
applicant’s plan shall include the
proposed notice of open season. Upon
receipt of a request for such a
determination, the Secretary of the
Commission shall issue a notice of the
request, which will then be published in
the Federal Register. The notice shall
establish a date on which comments
from interested persons are due and a
date, which shall be within 60 days of
receipt of the prospective applicant’s
request unless otherwise directed by the
Commission, by which the Commission
will act on the proposed plan.
[FR Doc. 05–11658 Filed 6–15–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
18 CFR Part 294
[Docket No. RM05–19–000; Order No. 659]
Electronic Reporting of Shortages and
Anticipated Shortages of Electric
Energy and Capacity
Issued May 27, 2005.
Federal Energy Regulatory
Commission, DOE.
ACTION: Final rule.
AGENCY:
SUMMARY: The Federal Energy
Regulatory Commission is revising its
regulations to provide that the means by
which public utilities must report
shortages and anticipated shortages of
electric energy and capacity is by
submitting an electronic filing via the
Division of Reliability’s pager system at
emergency@ferc.gov, instead of filing
with the Secretary of the Commission.
EFFECTIVE DATE: The rule will become
effective June 16, 2005.
FOR FURTHER INFORMATION CONTACT:
Jonathan E. First, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426,
(202) 502–8529.
SUPPLEMENTARY INFORMATION:
VerDate jul<14>2003
15:36 Jun 15, 2005
Jkt 205001
PO 00000
Frm 00043
Fmt 4700
Sfmt 4700
35027
and capacity is by promptly submitting
a single electronic report to the
Commission via the Division of
Reliability’s electronic pager system at
emergency@ferc.gov.
Information Collection Statement
5. The Office of Management and
Budget’s (OMB) regulations require that
OMB approve certain information
collection requirements imposed by the
agency. 5 CFR part 1320. This Final
Rule, which requires a single electronic
submission under part 294 of the
Commission’s regulations and
eliminates the filing of copies, is not
subject to OMB approval.
Environmental Analysis
6. The Commission is required to
prepare an Environmental Assessment
or an Environmental Impact Statement
for any action that may have a
significant adverse effect on the human
environment.2 The Commission has
categorically excluded certain actions
from this requirement as not having a
significant effect on the human
environment. Included are exemptions
for procedural or ministerial actions and
for information gathering.3 This
rulemaking is exempt under those
provisions.
Regulatory Flexibility Act Certification
7. The Regulatory Flexibility Act of
1980 4 generally requires a description
and analysis of final rules that will have
significant economic impact on a
substantial number of small entities.
This Final Rule does not create any new
substantive obligations and eliminates
the filing of copies under part 294 of the
Commission’s regulations. This change
will have no significant economic
impact on a substantial number of small
entities. Accordingly, no regulatory
flexibility analysis is required.
Document Availablity
8. In addition to publishing the full
text of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the Internet through
FERC’s Home Page (https://www.ferc.gov)
and in FERC’s Public Reference Room
during normal business hours (8:30 a.m.
to 5 p.m. eastern time) at 888 First
Street, NE., Room 2A, Washington DC
20426.
2 Order No. 486, Regulations Implementing the
National Environmental Policy Act, 52 FR 47897
(Dec. 17, 1987), FERC Stats. & Regs. Preambles
1986–1990 ¶ 30,783 (1987).
3 18 CFR 380.4(a)(1) and (5) (2004).
4 5 U.S.C. 601–612 (2000).
E:\FR\FM\16JNR1.SGM
16JNR1
Agencies
[Federal Register Volume 70, Number 115 (Thursday, June 16, 2005)]
[Rules and Regulations]
[Pages 35011-35027]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 05-11658]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
18 CFR Part 157
[Docket No. RM05-1-001; Order No. 2005-A]
Regulations Governing the Conduct of Open Seasons for Alaska
Natural Gas Transportation Projects
Issued June 1, 2005.
AGENCY: Federal Energy Regulatory Commission.
ACTION: Final rule; order on rehearing.
-----------------------------------------------------------------------
SUMMARY: The Federal Energy Regulatory Commission (Commission)
generally reaffirms its determinations in Order No. 2005. Order No.
2005 establishes requirements governing the conduct of open seasons for
proposals to construct Alaska natural gas transportation projects,
including procedures for allocation of capacity. Pursuant to the
directive of section 103(e)(2) of the Alaska Natural Gas Pipeline Act,
enacted on October 13, 2004, the regulations promulgated in Order No.
2005 include the criteria for and timing of any open season, promote
competition in the exploration, development, and production of Alaska
natural gas, and for any open seasons for capacity exceeding the
initial capacity, provide for the opportunity for the transportation of
natural gas other than from the Prudhoe Bay and Point Thomson units.
In this order, the Commission addresses the requests for rehearing
and/or clarification of Order No. 2005. Here, we grant rehearing in
part, deny rehearing in part, and provide clarification of Order No.
2005. In specific, we: Clarify that the Commission may require design
changes necessary to ensure that some portion of a proposed voluntary
expansion will be allocated to new shippers or shippers seeking to
transport gas from areas other than Prudhoe Bay or Point Thomson,
provided such shippers are willing to sign qualifying long-term firm
transportation agreements; codify the expanded criteria for evaluating
late bids for capacity and the requirement that any late bid contain a
good faith showing; in the case of the mandatory pre-review, codify
that the plan to be filed by the Commission must contain the open
season notice, and eliminates the 30-day prior notice requirement;
discuss how the open season rules may apply to jurisdictional gas
treatment plants; clarify that capacity bid for the open season is
exempt from allocation only in a case where there is also presubscribed
capacity, and that in the event there are more than one pre-
subscription agreement, bidders in the open season may not cherry-pick
among the provisions of the several agreements; clarify the project
applicant's obligation to establish a separate entity to conduct the
open season; and further codify the requirements of the catchall
provision regarding information to be included in an open season
notice.
DATES: Effective Date: Revisions in this order on rehearing will become
effective on June 16, 2005.
FOR FURTHER INFORMATION CONTACT: Whit Holden, Office of the General
Counsel, (202) 502-8089, edwin.holden@ferc.gov; Richard Foley, Office
of Energy Projects, (202) 502-8955, richard.foley@ferc.gov; Federal
Energy Regulatory Commission, 888 First Street, NE., Washington, DC
20426.
SUPLEMENTARY INFORMATION:
Before Commissioners: Pat Wood, III, Chairman; Nora Mead Brownell,
Joseph T. Kelliher, and Suedeen G. Kelly.
Order on Rehearing and Clarification
1. On February 9, 2005, the Federal Energy Regulatory Commission
(Commission) issued a Final Rule, Order No. 2005,\1\ amending its
regulations by adding Subpart B to Part 157 to establish requirements
governing the conduct of open seasons for capacity on proposals to
construct Alaska natural gas transportation projects. Order No. 2005
fulfilled the Commission's responsibilities to issue open season
regulations under section 103 of the Alaska Natural Gas Pipeline Act
(ANGPA or the Act), enacted on October 13, 2004. Section 103(e)(1) of
the Act directs the Commission, within 120 days from enactment of the
Act, to promulgate regulations governing the conduct of open seasons
for Alaska natural gas transportation projects, including procedures
for allocation of capacity. As required by section 103(e)(2) of the
Act, the regulations promulgated in Order No. 2005 (1) include the
criteria for and timing of any open season, (2) promote competition in
the exploration, development, and production of Alaska
[[Page 35012]]
natural gas, and (3) for any open seasons for capacity exceeding the
initial capacity, provide for the opportunity for the transportation of
natural gas other than from the Prudhoe Bay and Point Thomson units.
---------------------------------------------------------------------------
\1\ Regulations Governing the Conduct of Open Seasons for Alaska
Natural Gas Transportation Projects, RM05-1-000, Order No. 2005,
FERC Stats. and Regs. ] 31,174 (2005).
---------------------------------------------------------------------------
2. The Commission affirms here the legal and policy conclusions on
which Order No. 2005 was based. As stated in Order No. 2005, the goal
of the open season regulations is to design an open season process that
provides non-discriminatory access to capacity on any Alaska natural
gas transportation project and, at the same time, allows sufficient
economic certainty to support the construction of the pipeline and
thereby provide a stimulus for exploration, development, and production
of Alaska natural gas. We find that Order No. 2005's open season rules
as revised and clarified herein, satisfy that goal and, therefore, are
in the public interest.
Background
3. ANGPA mandates the expedited processing by the Commission of any
application for an Alaska natural gas transportation project. To this
end, as stated above, section 103(e)(1) of the Act specifically directs
the Commission to prescribe the rules which shall apply to any open
season held for the purpose of soliciting interest in, or making
binding commitments to the acquisition of capacity on, any Alaska
natural gas transportation project, including the criteria for
allocating capacity among competing bidders. In this regard, Congress
instructed the Commission to include in its regulations the criteria
for, and timing of, any open season, and to design its open season
regulations to promote competition in the exploration, development, and
production of Alaska natural gas and, as to any open season for the
voluntary expansion \2\ of the initial capacity of any Alaska natural
gas transportation project, to specifically provide the opportunity for
gas other than Prudhoe Bay and Point Thomson production to have access
to the pipeline.
---------------------------------------------------------------------------
\2\ Excluded from the scope of the open season rules are
expansions compelled by the Commission pursuant to section 105 of
the Act. Section 105 authorizes the Commission to order these
``involuntary'' expansions upon the request of one or more persons,
and upon the satisfaction of certain statutory criteria.
---------------------------------------------------------------------------
4. In response to the Act's directive, on November 15, 2004, the
Commission issued in Docket No. RM05-1-000 a Notice of Proposed
Rulemaking (NOPR) in this proceeding containing the Commission's
proposed Alaska natural gas transportation project open season
regulations. Also, the Commission held a public technical conference in
Anchorage, Alaska on December 3, 2004 to develop a record in this
proceeding. The Commission received 25 comments in response to the
NOPR.
5. On February 9, 2005, the Commission issued Order No. 2005. The
open season regulations contained in Order No. 2005 apply to any
application for a certificate or other Commission authorization for an
Alaska natural gas transportation project, whether filed pursuant to
the NGA, the Alaska Natural Gas Transportation Act of 1976, or ANGPA,
as well as to any voluntary applications for expansions of such a
project.
6. The Final Rule adopted the NOPR's proposed requirements that the
applicant provide a 30-day prior public notice containing extensive
information intended to allow all interested persons to decide whether
to participate in the open season, followed by an actual open season
period of at least 90 days. The regulations in the Final Rule also
adopted the NOPR's approach of allowing prospective applicants to
develop and state in detail the methodologies for determining the value
of bids and for allocating capacity, subject to the requirement that
all capacity be awarded without undue discrimination or preference of
any kind. In addition, the Final Rule required that at least 90 days
prior to providing the open season notice, the prospective applicant
must file its open season plan with the Commission for approval, and
that the Commission will act on the plan within 60 days of its filing.
7. The Final Rule provided that prospective applicants must conduct
or adopt a study of Alaska's in-state needs, and use the study results
to design capacity needs for use within the state, and design in-state
delivery points and in-state transportation rates as part of an open
season. Moreover, bidding on in-state capacity must be conducted
independent of out-of-state deliveries during a prospective applicant's
open season.
8. In order to further the Commission's goal of a non-
discriminatory open season, the Final Rule applied certain of the
Standards of Conduct requirements of Order No. 2004, including the
establishment of an independent, functionally-separate unit to conduct
the open season. In addition, the open season notice must identify the
prospective applicant's affiliates involved in the production of
natural gas in the state of Alaska, and all information about the open
season disclosed to any potential shippers must be made available to
all potential shippers.
9. The Final Rule permitted pre-subscription by anchor shippers,
limited to initial capacity only, in order to facilitate the
development of an Alaska pipeline project. However, to ensure that all
other potential shippers have an equal opportunity to obtain access to
capacity on the project in the open season, all pre-subscription
agreements must be made public within ten days of their execution, and
capacity on the proposed project must be offered to all prospective
qualifying shippers under the same terms and conditions and at the same
rates as the pre-subscription agreements. In addition, if capacity is
oversubscribed in the open season and it is not feasible to redesign
the proposed project to meet both the pre-subscription shippers' and
the open season shippers' capacity needs, then capacity bid for in the
open season will not be reduced, but all capacity subject to the terms
and conditions of pre-subscription agreements will be allocated pro
rata.
10. In an effort to allow as many potential shippers as possible
the opportunity to acquire capacity in the initial open season, the
Final Rule required that the project sponsor must consider any
qualifying bids tendered after the expiration of the open season, and
reject them only if they cannot be accommodated due to economic,
engineering, or operational constraints.
11. The Final Rule stated that, within ten days after precedent
agreements have been executed for capacity acquired in the open season,
the prospective applicant shall make public the results of the open
season, including the names of the prospective shippers, amount of
capacity awarded, and the terms of the agreements. Within 20 days after
precedent agreements have been executed, copies of all precedent
agreements, as well as copies of any correspondence with bidders whose
bids were not accepted, must be filed with the Commission.
12. In another provision, the Final Rule stated that, as a part of
the Commission's review of any application for an Alaska natural gas
transportation project, it will consider the extent to which the
proposed project has been designed to accommodate the needs of shippers
who have made conforming bids during an open season, as well as the
extent to which the project can accommodate low-cost expansion, and the
Commission may require changes in the project's design necessary to
promote competition and offer a reasonable opportunity for access to
the project.
13. Finally, to provide guidance to interested parties on the
important
[[Page 35013]]
subject of expansion rate treatment, the Final Rule establishes a
presumption in favor of rolled-in pricing for expansions up to the
point that it would cause there to be a subsidy of expansion shippers
by initial shippers.
14. Requests for rehearing and/or clarification were filed jointly
by BP Exploration (Alaska), Inc., ConocoPhillips Company and Exxon
Mobile Corporation (the North Slope Producers), by Enbridge, Inc.
(Enbridge), by ChevronTexaco Natural Gas, a division of Chevron U.S.A.
Inc. (ChevronTexaco), and by the State of Alaska. In addition, Anadarko
Petroleum Corporation (Anadarko) and the Legislative Budget and Audit
Committee of the Alaska State Legislature (Alaska Legislators) filed
responses to the rehearing requests.\3\
---------------------------------------------------------------------------
\3\ Under Rule 213 of the Commission's Rules of Practice and
Procedure, answers to rehearing requests are not permitted. However,
the Commission has discretion to waive this rule when it finds that
the answers will help provide a complete record in the proceeding or
allow a better understanding of the issues. This proceeding involves
the establishment of open season rules for capacity on an Alaska
natural gas transportation project, and is critical to the
development of Alaska's vast natural gas resources to meet
anticipated national demand for natural gas, thereby enhancing
national security. The Commission finds that the answers will
provide necessary information to provide a full and complete record,
which will assist the Commission in addressing the issues on
rehearing pertaining to the complex and unique circumstances
surrounding the development of an Alaska natural gas transportation
project. Therefore, Anadarko's and the State of Alaska's answers to
the rehearing requests are accepted. See 18 CFR 385.213 (2004).
---------------------------------------------------------------------------
Discussion
I. Mandating Pipeline Design
A. The Final Rule--Sec. Sec. 157.36 and 157.37
15. Section 157.36 requires that any open season for expansion
capacity of an Alaska natural gas transportation project must provide
the opportunity for the transportation of gas other than Prudhoe Bay or
Point Thomson production, and that the Commission, in considering any
proposed voluntary expansion of an Alaska natural gas pipeline project,
``may require design changes to ensure that all who are willing to sign
long-term firm transportation contracts that some portion of the
expansion capacity be allocated to new shippers or shippers seeking to
transport natural gas from areas other than Prudhoe Bay and Point
Thomson.'' Section 157.37 states that, in reviewing any application for
an Alaska natural gas pipeline project, the Commission ``may require
changes in the project design necess[ary] to promote competition and
offer a reasonable opportunity for access to the project, taking into
account the extent to which the proposed project design accommodates
the open season's conforming bids as well as low-cost expansion.'' \4\
These provisions were included in the Final Rule in response to
concerns of non-North Slope producers that they have access to capacity
on an Alaska natural gas transportation project when their potential
gas reserves are commercially developed.
---------------------------------------------------------------------------
\4\ ``Necessity'' in section 157.37 is revised to read
``necessary.''
---------------------------------------------------------------------------
B. Rehearing/Clarification Requests
16. The North Slope Producers and ChevronTexaco object to the
provisions contained in sections 157.36 and 157.37 to the extent that
they authorize the Commission to require changes in the design of an
Alaska natural gas transportation project. The North Slope Producers
object to these provisions on a number of grounds. First, they contend
that it is beyond the Commission's NGA authority to mandate changes in
the design of a pipeline, either to provide additional capacity or to
enhance future expandability. The North Slope Producers contend that,
in either case, the result is a mandatory expansion of the project,
which according to section 7(a) of the NGA, is outside the Commission's
authority to require.\5\ The North Slope Producers maintain that this
limitation on the Commission's authority is reflected in the
Commission's regulations providing that open access pipelines are ``not
required to provide any requested transportation service for which
capacity is not available or that would require the construction or
acquisition of any new facilities,'' \6\ and in judicial precedent.\7\
According to the North Slope Producers, the Commission has acted
unreasonably in ``morphing'' ANGPA's vague and undefined open season
requirements pertaining to competition in the exploration, development,
and production of Alaska gas and sufficient opportunity for future
access for the transportation of non-Prudhoe Bay/Point Thomson gas into
factors to be considered by the Commission in its NGA section 7 review
of certificate applications for Alaska natural gas transportation
projects.
---------------------------------------------------------------------------
\5\ Section 7(a) of the NGA provides ``[t]hat the Commission
shall have no authority to compel the enlargement of transportation
facilities * * *'' 15 U.S.C. 717f(a).
\6\ 18 CFR 284.7(f).
\7\ The North Slope Producers cite Panhandle Eastern Pipe Line
Co., 204 F.2d 675 (3rd Cir. 1953) in which the court stated that
``[i]n light of section 7(a) we are compelled to conclude that
Congress meant to leave the question whether to employ additional
capital in the enlargement of its pipeline facilities to the
unfettered judgment of the stockholders and directors of each
natural gas company involved.'' 204 F.2d at 680.
---------------------------------------------------------------------------
17. Second, the North Slope Producers assert that ANGPA section 105
further limits the Commission's authority to require an expansion of an
Alaska natural gas transportation project sections. The North Slope
Producers state that before an involuntary expansion can be ordered by
the Commission, section 105 lists a number of statutory requirements
that must be met which are designed to balance potential future
shippers' interests with the need to protect the pipeline and existing
shippers and to protect against uneconomic overbuilding. The North
Slope Producers state that none of these statutory requirements are
referenced in or satisfied by section 157.36 or 157.37.
18. Third, the North Slope Producers argue that the Commission
appears to mistakenly ``assume that a pipeline can, in all
circumstances, be efficiently designed to accommodate all qualifying
bids.'' The North Slope Producers assert that the most efficient and
economic pipeline design might not be one which can accommodate 100
percent of the capacity bid for in the open season. In fact, according
to the North Slope Producers, it is possible that a pipeline designed
to accommodate all the capacity bid in the open season ``could result
in a design that is inefficient and/or negatively impacts future
expansion design alternatives.''
19. Fourth, the North Slope Producers maintain that to the extent
that it authorizes a set-aside of capacity, section 157.36 violates the
Order No. 636's goal of eliminating impediments to the transmission of
proper pricing signals between producers and consumers, as well as the
Commission's non-discrimination policies. The North Slope Producers
point to the second sentence of section 157.36, which states:
``In considering a proposed voluntary expansion of an Alaska natural
gas pipeline project, the Commission will consider the extent to
which the expansion will be utilized by shippers other than those
who are the initial shippers on the project, and in order to promote
competition and open access on the project, may require design
changes to ensure that all who are willing to sign long-term firm
transportation contracts to some portion of the expansion capacity
be allocated to new shippers or shippers seeking to transport
natural gas from areas other than Prudhoe Bay and Point Thomson.''
(Emphasis added).
The North Slope Producers assert that if this ``indecipherable''
language is intended to set aside capacity for new
[[Page 35014]]
shippers or shippers of gas from areas other than Prudhoe Bay and Point
Thomson, then the Commission is favoring one shipper's bid over another
bid that otherwise meets all of the bid criteria. The North Slope
Producers assert that ANGPA's section 103(e)(2)(C) requirement that
open season regulations for voluntary expansions are to ``provide an
opportunity for the transportation of gas other than Prudhoe Bay and
Point Thomson gas'' does not support section 157.36's apparent set-
aside or preference. The North Slope Producers state that not only is
such a preference inconsistent with the Commission's open access
policies, it is patently discriminatory and anti-competitive and
unlawful under the NGA. The North Slope Producers contend that
allocating pipeline capacity in an open season to customers who value
it most, i.e., through the use of the Commission-favored net present
value capacity allocation methodology, ensures pipelines and shippers
that capacity will be allocated in a non-discriminatory and
economically efficient manner. The North Slope Producers also assert
that development of multi-owner fields could be delayed or hampered if
one group of shipper/owners had a competitive advantage over another
shipper/owner group due to a capacity allocation advantage or
preference.
20. Finally, the North Slope Producers maintain that sections
157.36 and 157.37 are contrary to the Commission's reliance on market
forces, on which its existing policies are based. Specifically, the
North Slope Producers claim that Order No. 2005 fails to reconcile
Subparts 157.36 and 157.37 with current Commission policies in favor of
``facilitate[ing] the unimpeded operation of market forces to stimulate
the production of natural gas,''\8\ and against the subsidization of
new services by existing shippers. The North Slope Producers state that
it would be unreasonable to expect that the pipeline sponsors would
simply assume the financial risk for significant amounts of
uncontracted capacity on such an enormous project, yet Order No. 2005
fails to address cost recovery issues associated with any mandated
design changes that might be ordered.
---------------------------------------------------------------------------
\8\ Order No. 636, FERC Stats. and Regs. ] 30,939 at 30,393
(1992), quoting S.Rep. No. 30 9, 101st Cong., 1st Sess. at p. 2
(1989).
---------------------------------------------------------------------------
21. ChevronTexaco claims that the regulations promulgated in Order
No. 2005 apply to open seasons for initial or voluntary expansion
capacity; therefore, the idea of post-open season Commission-mandated
design changes is inconsistent with and outside the scope of this
rulemaking. Moreover, ChevronTexaco asserts that the design change
provisions of sections 157.36 and 157.37 should be deleted from the
open season regulations because the subject was not included in the
Notice of Proposed Rulemaking. ChevronTexaco states that absent
removing sections 157.36 and 157.37 from the open season regulations,
the Commission should provide that it would not require project design
changes if doing so would negatively impact the rates, terms or
conditions of service for initial shippers or otherwise adversely
affect pipeline operations of efficiency.
22. In its response to the rehearing requests, Anadarko argues that
ANGPA and the NGA provide the Commission with ample authority to
require changes in the design of an initial or expanded Alaska natural
gas transportation project necessary to meet the statutory objectives
of promoting competition and provide a reasonable opportunity for
access to all shippers who have made conforming bids during the open
season. Anadarko states that clearly there is interplay between the NGA
and ANGPA. Specifically, states Anadarko, section 7(e) of the NGA
provides that a ``certificate shall be issued * * * if it is found that
proposed service, sale, operation, construction * * * to the extent
authorized by the certificate, is or will be required by the present or
future public convenience and necessity.'' Anadarko states that the
Commission considers many factors in making this public convenience and
necessity finding, and, in the case of an Alaska natural gas
transportation project, should consider the requirements of ANGPA.
23. Anadarko asserts that the Commission often imposes conditions
to its certificates requiring routing or design modifications in order
to support a finding that a particular project is in the public
convenience and necessity. In any event, sections 157.36 and 157.37 do
not mandate an expansion, according to Anadarko, because the applicant
may choose not to accept a certificate that requires that the project
be redesigned. Anadarko states that the regulations merely put the
applicant on notice that its proposed project design might be rejected
as failing to meet the objectives of ANGPA, and consequently, not being
required by the public convenience and necessity.
24. In response to the North Slope Producers' charge that section
157.36 provides for discriminatory reallocation of capacity contrary to
existing Commission policy, Anadarko contends that the Commission is
merely following the mandate of ANGPA section 103(e)(2)(C). Anadarko
states that under section 103(e)(2)(C), the Commission's regulations
must ensure that any open season for expansion capacity provides the
opportunity for the transportation of natural gas other than from
Prudhoe Bay/Point Thomson, and section 157.36 seeks to do just that.
25. Anadarko also disputes the North Slope Producers' claim that
parties were not adequately notified in the NOPR that pipeline design
would be a subject of the rulemaking. Anadarko maintains that the
regulations contained in sections 157.36 and 157.37 reasonably respond
to many concerns expressed throughout the rulemaking process.\9\
Anadarko contends that under the Administrative Procedure Act (APA),
the Commission was required in this informal rulemaking proceeding to
provide either the terms or substance of the proposed rule or a
description of the subjects and issues involved.\10\ Moreover, Anadarko
points out that the courts have held that ``even if the final rule
deviates from the proposed rule,'[s]o long as the final rule
promulgated by the agency is a ``logical outgrowth'' of the proposed
rule'' the purposes of the notice and comment have been adequately
served.'' \11\ Anadarko states that Order No. 2005's pipeline design
provisions were a ``logical outgrowth'' of the NOPR and the issues
discussed therein, e.g., the major goals of ANGPA, concerns over
potential discrimination, producer/sponsor preferences, the role of
pre-subscriptions, and tensions between ANGPA's goals and the
application of existing policies to an Alaska project.
---------------------------------------------------------------------------
\9\ Anadarko identifies comments addressing pipeline size both
at the technical conference and written. See Anadarko's March 29,
2005 response at 15-16.
\10\ See 5 U.S.C.A. 553(b)(3).
\11\ Appalachian Power Co. v. EPA, 135 F.3d 791, 804 n.22 (DC
Cir. 1998).
---------------------------------------------------------------------------
26. Lastly, Anadarko contends that the Commission provided ample
support for not following current Commission policies that favor
reliance on market forces. Anadarko states that the rulemaking record
in Order No. 2005 thoroughly discusses the conditions and circumstances
in Alaska that are much different than those found in the lower 48
states, requiring the appropriate regulatory action taken in sections
157.36 and 157.37. In conclusion, Anadarko disagrees that 157.36 is
``indecipherable'' as claimed by the North Slope Producers.
27. The Alaska Legislators maintain that sections 157.36 and 157.37
are well within the Commission's broad power
[[Page 35015]]
to attach to certificates any conditions that may be found to be
required by the public convenience and necessity. They claim that the
``forced expansion'' argument fails to acknowledge that ANGPA has
injected into the public convenience and necessity standard of the NGA
a new statutory standard, i.e., the promotion of competition in the
exploration, development and production of Alaska natural gas with
respect to Alaska natural gas transportation projects. Moreover, the
Alaska legislators contend that the Commission's pipeline design
concerns are required not only by the mandate of ANGPA, but also by the
economic realities in Alaska, where virtually all of the proven
reserves are held by the North Slope Producers. The Alaska legislators
state that the Commission is simply announcing in sections 157.36 and
157.37 that it may condition the approval of the certificate upon the
applicant's making necessary design changes required to satisfy the
public convenience and necessity standard, including the ``promote
competition'' standard, which is uniquely applicable to an Alaska
natural gas transportation project.
28. Addressing the North Slope Producers' claim that section 157.36
provides for an unduly discriminatory set aside of capacity for non-
North Slope shippers, the Alaska legislators agree with Anadarko that
ANGPA mandates that in the case of an expansion of an Alaska natural
gas transportation project, the Commission must provide an opportunity
for the transportation of natural gas other than from Prudhoe Bay and
Point Thomson units in its open season rules. Alaska legislators state
that section 157.36 is consistent with that mandate.
29. The Alaska legislators also defend the Commission's
``proactive'' approach through which it fashioned the open season rules
in recognition of the recognized differences between competitive forces
in the lower 48 states and the lack of competition in Alaska. Given
these differences, the Alaska legislators maintain that the Commission
was right to depart from existing Commission policy. They assert that
the fact that Congress required the Commission to promulgate the Alaska
open season rules in place of the Commission's long-standing policy of
evaluating open seasons on a case-by-case, after-the-fact basis, is an
illustration of the need for a different approach based on the unique
circumstances surrounding an Alaska pipeline. The Alaska Legislators
conclude that, unlike the situation in the lower 48 states, there is no
existing or foreseeable competitive environment in Alaska, where the
North Slope Produces not only control all the known gas reserves, but
also may become the sponsors of the Alaska pipeline. Therefore, the
Commission was right to not rely on market forces in Alaska to ensure
the development, routing, sizing and timing of an Alaska pipeline.
30. Finally, the state of Alaska suggests that section 157.36 be
expanded to better reflect its intent. According to the State of
Alaska, section 157.36 should read:
In considering a proposed voluntary expansion of an Alaska
natural gas transportation project, the Commission will consider the
extent to which the expansion will be utilized by shippers other
than those who are the initial shippers on the project and, in order
to promote competition and open access to the project, may require
design changes to ensure that new shippers willing to sign long-term
firm transportation contracts or shippers seeking to transport
natural gas from areas other than Prudhoe Bay or Point Thomson who
are willing to sign long-term contracts can have access to some
portion of the expansion capacity.
C. Commission Response
31. The North Slope Producers' assertion that the Commission has no
authority under the NGA to require changes in the design of a proposed
Alaska natural gas transportation project in connection with an
application for authorization either to construct the project, or to
expand the project is inconsistent with law and precedent. At the
outset, we reject the notion that any design change that might be
required under either section 157.36 or 157.37 would constitute a
mandatory expansion of the project. First, in every case in which the
section 7(a) limitation has been addressed, the facilities involved
were existing facilities subject to existing certificate authorization.
The reasoning behind this limitation is clear. Once a natural gas
company accepts a certificate and in reliance thereof expends resources
to construct the facilities authorized therein, the pipeline and its
customers should have the right to rely on the authorizations contained
in that certificate. It is quite another thing where the Commission
tells a certificate applicant that unless it agrees to certain changes
(including cost allocations and the design of initial service rates),
its proposal will not be found to be in the public convenience and
necessity. In such case, if the applicant does not want to change its
proposed project design, it is not required to accept the certificate.
Furthermore, because design changes under either 157.36 or 157.37 would
not constitute a mandatory project expansion, the statutory
requirements of ANGPA section 105 have no application.
32. In considering an application for a certificate of public
convenience and necessity under section 7 of the NGA, the Commission
has the authority to consider all factors bearing on the public
interest,\12\ and in particular, the Commission ``certainly has the
right to consider a congressional expression of fundamental national
policy as bearing upon the question whether a particular certificate is
required by the public convenience and necessity.'' \13\ In the case of
an Alaska natural gas transportation project, these factors would
properly include the requirements of ANGPA, including the statutory
objectives of promoting competition and provide a reasonable
opportunity for access to all shippers who have made conforming bids
during the open season.
---------------------------------------------------------------------------
\12\ See, e.g., FPC v. Transcontinental Gas Pipe Line
Corporation, 365 U.S. 1, 81 S.Ct. 435 (1961); Office of Consumers'
Counsel v. FERC, 655 F.2d 1132, 210 U.S. App. D.C. 315 (1980).
\13\ City of Pittsburgh v. FPC, 237 F.2d 741 at 754 (D.C. Cir.
1965).
---------------------------------------------------------------------------
33. The Commission has authority under NGA section 7(e) to attach
to a certificate of public convenience and necessity any conditions it
deems necessary to meet the public interest.\14\ The Commission has
exercised this conditioning authority to require routing or design
modifications in order to support a finding that a particular project
is in the public convenience and necessity.\15\ Sections 157.36 and
157.37 merely codify our existing authority and practice.
---------------------------------------------------------------------------
\14\ See, e.g., FPC v. Hunt, 376 U.S. 515, 525-527, 84 S.Ct. 861
(1964); Atlantic Refining Co. v. Public Service Commission of New
York, 360 U.S. 378 (1959).
\15\ See, e.g., Vector Pipeline, L.P., 87 FERC ] 61,225 at
61,892-893 (1999); Maritimes & Northeast Pipelines, L.L.C., 80 FERC
] 61,345 (1997); NE Hub Partners, L.P., 83 FERC ] 61,043 (1998); see
also, Transcontinental Gas Pipe Line Corp v. FERC, 589 F.2d 186 (5th
Cir.), cert. denied, 445 U.S. 915 (1979).
---------------------------------------------------------------------------
34. The North Slope Producers' claim that sections 157.36 and
157.37 are predicated on the Commission's erroneous assumption ``that a
pipeline can, in all circumstances, be efficiently designed to
accommodate all qualifying bids.'' This is inaccurate. We noted in
Order No. 2005 that both the North Slope Producers and Enbridge
maintained that an Alaska pipeline could be designed and built with
sufficient capacity to accommodate the needs of every qualified
shipper.\16\ Our expectation is that an Alaska natural gas
transportation project will be designed and built, to the extent
possible, to
[[Page 35016]]
accommodate all qualified shippers who are ready to sign firm
transportation agreements. Nonetheless, in Order No. 2005 we certainly
did not rule out the possibility that a project, with or without pre-
subscription agreements, might be oversubscribed.\17\ On this note, we
should emphasize that in our review of any application for initial
Alaska project or any expansion thereof, our consideration of the
project design will be driven by our need to find that the proposal is
in the public convenience and necessity. Any conditions we impose must
be required by the public interest, and be based on substantial
evidence.
---------------------------------------------------------------------------
\16\ See, e.g., Order No. 2005 at P 29, 37, and 88.
\17\ See id. at P 37; see also Sec. 157.34(c)(15).
---------------------------------------------------------------------------
35. The North Slope Producers' claim that section 157.36 provides
for an unduly discriminatory set-aside of capacity for non-North Slope
shippers discounts, if not ignores, the Congressional mandate of ANGPA
section 103(e)(2)(C) that requires our open season regulations to
ensure that any open season for expansion capacity provides the
opportunity for the transportation of natural gas other than from
Prudhoe Bay/Point Thomson. Section 157.36 does so in a reasonable
manner. In any event, our regulations do not require that an expansion
proposal must, regardless of economic and technical considerations,
provide transportation of gas other than Prudhoe Bay/Point Thomson
volumes. The regulations simply require that an opportunity for such
transportation be provided.
36. As pointed out elsewhere in this order, and throughout Order
No. 2005, a number of existing Commission policies predicated on
competitive conditions in the lower 48 states are ill-suited for
application in the case of an Alaska natural gas transportation
project, particularly in view of ANGPA's directives. As we stated in
Order No. 2005, a successful Alaska natural gas transportation project
will have to overcome a variety of significant obstacles, including
unique and complex competitive conditions. Those competitive
conditions, we said, are intensified by the generally agreed-upon fact
that there will be only one such Alaska pipeline for the foreseeable
future.\18\ Against that backdrop, we affirm the conclusions of Order
No. 2005, which serve as the underpinnings of the Final Rule's
regulations, including the need in certain instances to accommodate
existing Commission policy to the unique circumstances surrounding the
exploration, production, development, and transportation to market of
Alaska natural gas.
---------------------------------------------------------------------------
\18\ The North Slope Producers, in their rehearing request,
claim that it is too early to conclude that only one Alaska pipeline
will ever be built. We find nothing in the record to support a
contrary conclusion.
---------------------------------------------------------------------------
37. Finally, while due process and the APA impose an obligation on
agencies to provide adequate notice of issues to be considered,\19\
that obligation is satisfied in this informal rulemaking by providing
either the terms or substance of the proposed rule or a description of
the subjects and issues involved.\20\ Order No. 2005's pipeline design
provisions were a logical outgrowth of the NOPR and the issues
discussed therein, e.g., major goals of ANGPA, concerns over potential
discrimination, producer/sponsor preferences, potential role of pre-
subscriptions, tensions between ANGPA's goals, and application of
existing policies to the circumstances of an Alaska project. Indeed,
the critical importance of properly sizing the pipeline was a recurring
theme throughout this proceeding, and was raised by several parties at
the technical conference, and in later comments and reply comments.\21\
Thus, Order No. 2005 does not unduly change the scope of this
proceeding. In any event, the parties' ability to seek rehearing
resolves any due process issues.
---------------------------------------------------------------------------
\19\ Public Service Commission of the Commonwealth of Kentucky
v. FERC, 397 F.3d 1004 (DC Cir. 2005), citing Williston Basin
Interstate Pipeline Co. v. FERC, 165 F.3d 54 (DC Cir. 1999); see 5
U.S.C. 554(b)(3).
\20\ See 5 U.S.C. 553(b)(3).
\21\ See n. 8, supra.
---------------------------------------------------------------------------
38. Although the North Slope Producers describe section 157.36 to
be ``indecipherable,'' their comments demonstrate that they understand
its intent. Section 157.36 is intended to provide that the Commission
may require design changes necessary to ensure that some portion of a
proposed voluntary expansion will be allocated to new shippers or
shippers seeking to transport gas from areas other than Prudhoe Bay or
Point Thomson, provided such shippers are willing to sign qualifying
long-term firm transportation agreements. To ensure clarity, we will
revise section 157.36 to read as follows:
``In considering a proposed voluntary expansion of an Alaska
natural gas transportation project, the Commission will consider the
extent to which the expansion will be utilized by shippers other
than those who are the initial shippers on the project and, in order
to promote competition and open access to the project, may require
design changes to ensure that some portion of the expansion capacity
will be allocated to new shippers willing to sign qualifying long-
term firm transportation contracts, including shippers seeking to
transport natural gas from areas other than Prudhoe Bay or Point
Thomson.''
II. Presumption of Rolled-in Rates for Expansions
A. Final Rule--Sec. 157.39
39. Section 157.39 states that ``[t]here shall be a rebuttable
presumption that rates for any expansion of an Alaska natural gas
transportation project shall be determined on a rolled-in basis.'' The
Commission stated in Order No. 2005 that by providing for this
presumption, the Commission is advising potential shippers, in advance
of any initial Alaska natural gas transportation project open season,
of its intention to harmonize the objective of rate predictability for
initial shippers with the objective of reducing barriers to future
exploration and production in designing rates for future expansions of
any Alaska natural gas transportation project. The Commission concluded
in Order No. 2005 that section 157.39 is consistent with ``our guiding
principle that competition favors all of the Commission's customers, as
well as with the objectives of the Act, to adopt rolled-in rate
treatment up to the point that would cause there to be a subsidy of
expansion shippers by initial shippers, if any subsidy were to be
found.''
B. Rehearing/Clarification Requests
40. The North Slope Producers, Enbridge, and ChevronTexaco assert
that the presumption in favor of rolled-in rates for voluntary
expansions established in section 157.39 creates uncertainty for
shippers and project sponsors, and, therefore, section 157.39 should be
eliminated from the regulations or substantially revised. The North
Slope Producers and Enbridge claim that prospective initial shippers,
fearing that in the future their rates may be increased to subsidize
the cost of expansion facilities, will be less willing to make the
long-term commitments necessary to support an Alaska project. This
uncertainty, they predict, will discourage rather than advance the
development of an Alaska pipeline or any voluntary expansion thereof--a
result clearly inconsistent with ANGPA's primary goal. Moreover, the
North Slope Producers and Enbridge suggest that mandatory expansions
pursuant to ANGPA section 105 will become more attractive than
voluntary expansions because of the explicit rate protection for
existing shippers in section 105.
[[Page 35017]]
41. The North Slope Producers contend that section 157.39 is
unjustifiably inconsistent with the Commission's current policy
regarding rate treatment of expansions, which is to discourage
uneconomic expansions and assure that expansions will not be subsidized
by existing shippers. They assert that even if, as claimed by the
Commission, only one pipeline will be built in Alaska, that distinction
does not justify deviating from the Commission's current policy.
42. The North Slope Producers charge that the Commission acted
arbitrarily and capriciously in relying on ANGPA section 103(e) to
justify its conclusion to provide for a presumption of rolled-in rates
for expansions. Although the North Slope Producers concede that the
Commission clearly has the authority under ANGPA and the NGA to approve
rates for Alaska natural gas transportation projects, they claim that
ANGPA section 103(e) has nothing to do with rate regulation.
Furthermore, state the North Slope Producers, even if section 103 could
be read to give the Commission authority to include rate regulations in
its open season rules, the proper course would be to remove section
157.39 from the open season rules and instead address rate policy
issues only after the parties have the opportunity of developing a
complete factual record. Failing this, the North Slope Producers state
that the Commission should revise section 157.39 to provide that the
Commission's current rate policies will apply to Alaska projects.
43. Enbridge also argues that the Commission acted arbitrarily and
capriciously by imposing a rebuttable rolled-in presumption, even where
rolled-in pricing would increase existing shippers' rates. According to
Enbridge, Order No. 2005 identifies two considerations, namely the
Commission's disfavor of existing shippers subsidizing the rates of new
shippers, and the Commission's reluctance to authorize an expansion
rate that would have an unduly negative impact on the exploration and
development of Alaska reserves. Enbridge contends that the presumption
should be ``scaled back'' to apply only to cases where expansion rates
are no higher than pre-existing rates. Enbridge points to the
Commission's acknowledgement in Order No. 2005 that it ``cannot at this
point, without a specific project proposal or the facts surrounding a
proposed expansion before us, define exactly what will be required to
overcome the presumption.'' Enbridge contends that the Commission's
inability to explain how the presumption can be rebutted renders
rolled-in pricing mandatory, leaving the question of whether a rolled-
in expansion rate that is higher than original rates is a subsidy to be
resolved in a future NGA section 7 filing.
44. ChevronTexaco stresses that because the text of Order No. 2005
recognizes that ``without a specific project proposal or the facts
surrounding a proposed expansion'' the Commission cannot determine what
is needed to overcome the presumption favoring rolled-in rates, the
Commission should defer any determination of rate treatment for
expansions until a record can be developed after a specific proposal is
made. According to ChevronTexaco, this inability to articulate when the
presumption will be applied creates uncertainty that inhibits the
development of any Alaska project.
45. ChevronTexaco states that inconsistency between the text of
order and the text of the regulations creates further uncertainty.
ChevronTexaco states that while the regulations state that the
presumption applies to ``any expansion,'' Order No. 2005's text, at
paragraphs 124 and 125, suggests that rolled-in rates are appropriate
only if there is no increase in rates for existing shippers.
ChevronTexaco urges the Commission to clarify section 157.39 to state
that no cross-subsidy is intended. Otherwise, the Commission should
consider issuing, in lieu of a regulation, a policy statement which
outlines the general direction that the Commission intends to take.
46. The Alaska Legislators and Anadarko contend that rolled-in
pricing is essential and justified. Anadarko asserts that the
Commission clearly has the statutory authority to establish a
presumption of rolled-in pricing for future expansions in the open
season regulations. Both Anadarko and the Alaska Legislators contend
that the significant differences identified in the record between an
Alaskan pipeline project and a pipeline in the lower 48 states provide
ample justification for departing from the current pricing policy. The
Alaska Legislators contend that even if there were some factual reason
for applying the current policy, that policy cannot be reconciled with
the policy considerations stated in ANGPA. Both Anadarko and the Alaska
Legislators state that incremental pricing of expansions cannot be
reconciled with ANGPA's goals of promoting competition in the
exploration, development, and production of Alaska natural gas, and
providing for the transportation of natural gas other than from the
Prudhoe Bay and Point Thomson units in any expansions of the Alaska
pipeline facilities. The Alaska Legislators estimate that expanding a
pipeline, through looping, to a capacity of 7 billion cubic feet (Bcf),
would result in an expansion rate 50 percent higher than existing rates
if incrementally priced. Anadarko predicts that incremental pricing of
expansions of an Alaskan pipeline beyond 6 Bcf would cause the pipeline
to be capped at 6 Bcf.
C. Commission Response
47. ANGPA section 103(i) gives the Commission broad authority to
establish ``such regulations as are necessary'' for the conduct of open
seasons. In this regard, the Commission believes that it is appropriate
to establish rate criteria that will assist potential shippers to make
informed open season bids, and will promote competition, as required by
ANGPA. As discussed in detail in Order No. 2005, these criteria include
projected rates for in-state deliveries of gas, as well as a
presumption for rolled-in rate treatment for future pipeline
expansions.
48. In adopting the presumption for rolled-in rate treatment, the
Commission balanced rate predictability for initial shippers with the
objective of reducing barriers to future exploration, development and
production of Alaska natural gas. The Commission was concerned that the
prospect of high incremental transportation rates might increase risks
to Alaskan producers and serve as a disincentive to future exploration
and development of potentially valuable natural gas resources. On the
other hand, the Commission does not wish to discourage voluntary
capacity expansions.
49. The rolled-in rate presumption was not an abandonment of our
current policy of not favoring rate subsidization by existing customers
of capacity expansions as suggested in the requests for rehearing. The
Commission did, however, suggest that because of the likelihood of a
single Alaskan pipeline project, it would consider alternatives to our
current policy on how to define or quantify subsidization by current
customers. Current policy primarily considers whether the expansion
project will result in a rate higher than the existing transportation
rate for existing customers. An alternative consideration or definition
of subsidization could be whether the expansion rate is no higher than
the actual initial rate or of an initial rate without built-in
subsidies. The Commission believed and continues to believe that the
appropriate place to review this issue is in the context of a future
NGA section 7 filing.
[[Page 35018]]
In such a proceeding, if the pipeline owners can show that the initial
pipeline was sized appropriately, i.e., it was uneconomic or
inefficient to build a larger capacity pipeline, the Commission would
consider this in overcoming the rolled-in rate presumption.
50. The text of Order No. 2005 referred to by ChevronTexaco does
not simply state that rolled-in rates are appropriate only if there is
no increase in rates for existing shippers; it suggests that a rolled-
in expansion rate that is higher than the original rate is not
necessarily a subsidy. As noted above, we will determine whether a
particular rate amounts to a subsidy when the issue is presented to us.
51. Nothing in the requests for rehearing causes us to question our
conclusion that a rebuttal presumption of rolled-in treatment for the
expansion of an Alaska Project is a reasonable approach to the
difficult issues we, and prospective pipeline proponents and shippers,
may face on the future. We think that the signal we are sending is a
positive one that will help spur natural gas exploration and
development in Alaska. At the same time, we have not prejudged how we
will resolve future proceedings, and all parties will have the
opportunity to convince us of appropriate rate treatment if and when
expansion proposals for an Alaska project are developed. We therefore
will not change the rule on this matter.
III. Late Bids
A. The Final Rule--Sec. 157.34(d)(2)
52. Order No. 2005 added a new provision in the Final Rule, section
157.34(d)(2), that a project sponsor must consider any bids tendered
after the expiration of the open season by qualified bidders, and may
reject them only if they cannot be accommodated due to economic,
engineering, or operational constraints, in which case the project
sponsor must provide a detailed explanation for the rejection. The
Commission explained that this requirement is designed to allow
reasonable access to those shippers who may not be ready to participate
during the established open season period, and at the same time provide
the sponsor with flexibility in the timing of its open season.
B. Rehearing/Clarification Requests
53. The North Slope Producers and Enbridge contend that it is
important for the timely development of any project that the project
sponsors be able to rely on an open season that has a definite term.
They state that the open season results are needed to permit the
project sponsor to gauge demand and in turn finalize pipeline design.
They assert that the late bid provisions of section 157.34(d)(2) will
result in unreasonable risks and costs to the project sponsor by
creating a never-ending, open-ended open season in which the project
sponsor will be required, for each and every late bid received, to
divert resources and incur additional costs to evaluate whether bid can
be accommodated. In addition, they state that there is tremendous
potential for delay at each step of the development of the project, if
the project sponsor must stop and make design changes at every stage to
accommodate a late bid. Thus, they state, section 157.34(d)(2) would
frustrate the Commission's stated goal of adopting open season
regulations that ensure sufficient economic certainty to support the
construction of a pipeline.
54. The North Slope Producers add that financing cannot be secured
until pipeline design and development costs are known and precedent
agreements are in place. Consequently, they claim, the prospect of
having to make changes to key project components to accommodate late
bids jeopardizes the project sponsor's ability to obtain financing in a
timely manner.
55. Both Enbridge and the North Slope Producers also state that
section 157.34(d)(2) fails to provide a clear standard under which the
project sponsor must evaluate late bids. This failure, they claim,
presents another risk of uncertainty and delay. Enbridge argues that,
even if it is necessary to significantly re-design a project in order
to satisfy a late bid, the regulation would require that such a bid be
accepted if the re-designed project remains feasible from an
``economic, engineering or operational'' perspective.
56. The North Slope Producers state that another effect of the late
bid provision is that potential shippers will be discouraged from
participating in an open season if they can submit a late bid. They
worry that this would diminish the open season's ability to accurately
demonstrate the demand for pipeline capacity. Enbridge also claims
that, absent a good faith requirement in connection with submitting
late bids, section 157.34(d)(2) permits such gamesmanship. Enbridge
states that at a minimum, section 157.34(d)(2) should put ``the burden
on the bidder to demonstrate compelling circumstances that prevented
participation in open season, and that the bid can be accommodated
without changing system design, requiring capacity to be allocated away
from other shippers, or otherwise adversely impacting the project's
development and timing.'' In this regard, the State of Alaska maintains
the Commission should include language in section 157.34(d)(2) that
requires late bidders to provide adequate justification for their late
bids.
57. Additionally, the North Slope Producers assert that, to the
extent a project sponsor would be required to expand the project to
accommodate late bids, the Commission is in effect ordering an
expansion of the pipeline. In such a case, section 157.34(d)(2) raises
the same issues regarding forced expansions as are raised by sections
157.36 and 157.37. The North Slope Producers contend that whereas the
Commission may require an expansion under section 105, that section
places the burden on the party seeking such expansion to establish that
specific conditions are met, section 157.34(d)(2) appears to place the
burden on the pipeline to justify why it cannot expand the project to
accommodate a late bid.
58. Enbridge states that in any event there is little or no reason
for section 157.34(d)(2) ``given the other measures instituted by Order
No. 2005 to protect the interests of late developing shippers.''
Specifically, Enbridge refers to the unprecedented level of information
required in the open season notice on which bidders will be able to
base their long-term capacity decisions, Order No. 2005's emphasis on
requiring that the project's design demonstrate a capability for low-
cost expansion, and, finally, the mandatory expansion provisions of
ANGPA 105. Enbridge contends that to the extent late bids can be
accommodated without adversely impacting the project's development, it
is in the project sponsor's economic interests to do so.
59. ChevronTexaco requests that the Commission clarify that project
sponsors will be required to consider late bids only if there is excess
capacity after capacity is allocated to those open who bid in the open
season. ChevronTexaco states that one of the major purposes of the open
season is provide a level playing field for all participants, thereby
eliminating the advantages of possessing superior or advance
information. ChevronTexaco cannot understand the Commission's reasoning
in giving special consideration to one specific parameter of a
conforming bid, namely, the timing of the bid. According to
ChevronTexaco, late bidders should not be allowed to put new burdens on
the project or to adversely affect timely open season bidders.
60. Anadarko states that section 157.34(d)(2) is a reasonable
compromise
[[Page 35019]]
balancing concerns that the open season could be held prematurely with
a project sponsor's desire to control open season timing. Anadarko also
states that it is possible to accommodate all qualified bidders up to
the time the pipeline design is finalized.
C. Commission Response
61. Under the Commission's open access policy and rules, all
operating interstate pipelines have an obligation to receive and
respond to new requests for service, even if no capacity is available.
All operating pipelines have provisions in their FERC tariffs governing
the procedures that the pipeline will use in evaluating requests for
service. Absent an expansion,\22\ capacity could still be made
available to a prospective shipper via capacity release or the capacity
turnback provisions of an interstate pipeline's FERC tariff. During the
several years between the time that the open season ends and an Alaskan
pipeline goes into service, there will be no tariff with provisions
like those described above in effect for that pipeline. Without the
late bidder provisions of section 157.34(d), late-developing
prospective shippers would have no formal way of seeking capacity on
the pipeline after the open season ends. As revised herein, the
Commission believes that the late bidder provision is a fair and
necessary addition to the open season process for an Alaska natural gas
transportation project.
---------------------------------------------------------------------------
\22\ Interstate pipelines, other than an Alaska pipeline, cannot
be required to expand their systems, but pipelines are required to
respond to those who request service, even when none is available.
---------------------------------------------------------------------------
62. The project sponsor's obligation under section 157.34(d)(2) is
not ``unbounded'' or ``open-ended,'' as North Slope Producers contend.
We added this requirement in recognition of the possibility that an
appreciable amount of time might pass between the close of the open
season and the project sponsor's finalizing the details of the proposed
pipeline design and associated development costs, given the size and
scope of an Alaska natural gas pipeline project. During that time, it
is possible that producers of Alaska natural gas who were not in a
position to commit to long-term capacity commitments during the open
season, might then be in a position to request capacity consistent with
the open season notice (except, of course, that the bid is tendered out
of time). We felt it proper to require the project sponsor to consider
such a request. At the same time, we appreciated that at some point in
time, either before or after the proposed pipeline design is finalized,
the project sponsor might not be able to accommodate reasonably a late
request. For that reason, we provided that late requests could be
rejected on the basis of ``economic, engineering or operational
constraints.'' This is far from an unbounded, open-ended obligation.
Indeed, as noted above, Enbridge points out that to the extent that
late bids can be accommodated without adversely impacting the project's
development, it is in the project sponsor's economic interest to do so.
We see no harm in requiring that result.
63. We will however, revise the requirements of section
157.34(d)(2) in response to the complaints that the ``economic,
engineering or operational constraints'' standard for rejecting late
bids is too vague. Specifically, we are clarifying the criteria for
rejecting late bids in section 157.34(d)(2) to be ``economic,
engineering, design, capacity or operational constraints, or
accommodating the request would otherwise adversely impact the timely
development of the project.'' \23\ Additionally, we are adding a
provision to the section which will enable the project sponsor, at the
appropriate time in the development of its project and subject to
Commission approval, to determine, based on the above criteria, that no
further bids can be accepted. We will also revise section 157.34(d)(2)
to provide that any bid tendered after the expiration of an open season
must contain a good faith showing, including a statement of the
circumstan