Standardization of Small Generator Interconnection Agreements and Procedures, 34190-34301 [05-11307]
Download as PDF
34190
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Before Commissioners: Pat Wood, III,
Chairman; Nora Mead Brownell, Joseph
T. Kelliher, and Suedeen G. Kelly.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
18 CFR Part 35
[Docket No. RM02–12–000; Order No. 2006;
111 FERC 61,220]
Standardization of Small Generator
Interconnection Agreements and
Procedures
Issued: May 12, 2005
Federal Energy Regulatory
Commission.
ACTION: Final rule.
AGENCY:
SUMMARY: The Federal Energy
Regulatory Commission (Commission) is
amending its regulations under the
Federal Power Act to require public
utilities that own, control, or operate
facilities for transmitting electric energy
in interstate commerce to amend their
open access transmission tariffs to
include standard generator
interconnection procedures and an
agreement that the Commission is
adopting in this order and to provide
interconnection service to devices used
for the production of electricity having
a capacity of no more than 20
megawatts. A non-public utility that
seeks voluntary compliance with the
reciprocity condition of an open access
transmission tariff may satisfy this
condition by adopting these procedures
and agreement.
DATES: Effective Date: This Final Rule
will become effective August 12, 2005.
FOR FURTHER INFORMATION CONTACT:
Kumar Agarwal (Technical
Information), Office of Market, Tariffs
and Rates, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426. (202) 502–8923.
Bruce Poole (Technical Information),
Office of Market, Tariffs and Rates,
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426. (202) 502–8468.
Kirk Randall (Technical Information),
Office of Market, Tariffs and Rates,
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426. (202) 502–8092.
Patrick Rooney (Technical
Information), Office of Market, Tariffs
and Rates, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426. (202) 502–6205.
Abraham Silverman (Legal
Information), Office of the General
Counsel, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426. (202) 502–6444.
SUPPLEMENTARY INFORMATION:
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
I. Introduction
1. This Final Rule requires all public
utilities 1 to adopt standard rules for
interconnecting new sources of
electricity no larger than 20 megawatts
(MW). It continues the process begun in
Order No. 2003 of standardizing the
terms and conditions of interconnection
service for Interconnection Customers of
all sizes.2 It will reduce interconnection
time and costs for Interconnection
Customers and Transmission
Providers,3 preserve reliability, increase
energy supply, lower wholesale prices
1 For purposes of this Final Rule, a public utility
is a utility that owns, controls, or operates facilities
used for transmitting electric energy in interstate
commerce, as defined by the Federal Power Act
(FPA). 16 U.S.C. 824(e) (2000). A non-public utility
that seeks voluntary compliance with the
reciprocity condition of an open access
transmission tariff may satisfy that condition by
adopting these procedures and agreement.
2 Standardization of Generator Interconnection
Agreements and Procedures, Order No. 2003, 68 FR
49845 (Aug. 19, 2003), FERC Stats. & Regs. ¶ 31,146
(2003) (Order No. 2003), order on reh’g, Order No.
2003–A, 69 FR 15932 (Mar. 26, 2004), FERC Stats.
& Regs. ¶ 31,160 (2004) (Order No. 2003–A), order
on reh’g, Order No. 2003–B, 70 FR 265 (Jan. 4,
2005), FERC Stats. & Regs. ¶ 31,171 (2005), reh’g
pending (Order No. 2003–B). See also Notice
Clarifying Compliance Procedures, 106 FERC ¶
61,009 (2004). We refer to the large generator
interconnection rulemaking as Order No. 2003
throughout this document. The Order No. 2003
Large Generator Interconnection Agreement and
Large Generator Interconnection Procedures, as
amended by Order Nos. 2003–A and 2003–B, are
referred to in this Final Rule as the LGIA and the
LGIP, respectively.
3 Capitalized terms used in this Final Rule have
the meanings specified in the Glossaries of Terms
or the text of the Small Generator Interconnection
Procedures (SGIP) or the Small Generator
Interconnection Agreement (SGIA). Small
Generating Facility means the device for which the
Interconnection Customer has requested
interconnection. The owner of the Small Generating
Facility is the Interconnection Customer. The utility
entity with which the Small Generating Facility is
interconnecting is the Transmission Provider. A
Small Generating Facility is a device used for the
production of electricity having a capacity of no
more than 20 MW. The interconnection process
formally begins with the Interconnection Customer
submitting an application for interconnection,
called an Interconnection Request, to the
Transmission Provider.
We are omitting from the SGIP and SGIA
glossaries terms that are defined through their use
in the documents themselves or are in such
common use in the industry that a definition is
unnecessary. Many terms that were capitalized in
the Small Generator Interconnection Notice of
Proposed Rulemaking are therefore not capitalized
in this Preamble, SGIP, and SGIA.
The documents put forward in the Small
Generator Interconnection NOPR are called the
‘‘Proposed SGIP’’ and the ‘‘Proposed SGIA’’ in this
Preamble. The documents that are being adopted in
this Final Rule for inclusion in a Transmission
Provider’s OATT are called simply the SGIP and
SGIA. Provisions of the SGIP are referred to as
‘‘sections’’ and provisions of the SGIA are referred
to as ‘‘articles.’’
PO 00000
Frm 00002
Fmt 4701
Sfmt 4700
for customers by increasing the number
and types of new generation that will
compete in the wholesale electricity
market, facilitate development of nonpolluting alternative energy sources,
and help remedy undue discrimination,
as sections 205 and 206 of the FPA
require.4 Public utilities must amend 5
their open access transmission tariffs
(OATTs) to include a Small Generator
Interconnection Procedures document
(SGIP—Appendix E to this Preamble)
and a Small Generator Interconnection
Agreement (SGIA—Appendix F to this
Preamble).
2. The SGIP contains the technical
procedures the Interconnection
Customer and Transmission Provider
(the Parties) must follow once the
Interconnection Customer requests
interconnection of its Small Generating
Facility. It provides three ways to
evaluate the Interconnection Request.
They are the default Study Process that
could be used by any Small Generating
Facility, and two procedures that use
technical screens to evaluate proposed
interconnections: (1) The Fast Track
Process for a certified Small Generating
Facility no larger than 2 MW 6 and (2)
the 10 kW Inverter Process for a
certified inverter-based Small
Generating Facility no larger than 10
kW.7 All three are designed to ensure
that the proposed interconnection will
not endanger the safety and reliability of
the Transmission Provider’s
Transmission System.
3. The SGIA contains contractual
provisions appropriate for the
interconnection of a Small Generating
Facility, including provisions for the
payment for modifications made to the
Transmission Provider’s Transmission
System to accommodate the
interconnection. The SGIA is signed by
the Parties after they have successfully
completed the evaluation of a proposed
interconnection under the SGIP Study
Process or Fast Track Process. The SGIA
4 16
U.S.C. 824d and 824e (2000).
procedures are discussed in Part
II.I, below.
6 A Small Generating Facility equipment package
is considered certified if it has been submitted,
tested, and listed by a nationally recognized testing
and certification laboratory. The Small Generator
Interconnection NOPR used the term ‘‘precertified’’
to describe such a facility. We adopt in this Final
Rule the term ‘‘certified’’ to be consistent with
industry usage. To avoid further confusion, we also
use ‘‘certified’’ when describing the Small
Generator Interconnection NOPR. See the SGIP,
especially Attachments 3 and 4.
7 An inverter is a device that converts the direct
current voltage and current of a DC generator to
alternating voltage and current. For example, the
output of a solar panel is direct current. The solar
panel’s output must be converted by an inverter to
alternating current before it can be interconnected
with a utility’s alternating current electric system.
5 Compliance
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
does not apply to requests to
interconnect submitted under the 10 kW
Inverter Process, however, which uses a
simplified all-in-one application form/
procedures/terms and conditions
document that is included in SGIP
Attachment 5.
4. We conclude that general
consistency between the Commission’s
interconnection procedures document
and interconnection agreement adopted
in this Final Rule and those of the states
will be helpful to removing roadblocks
to the interconnection of Small
Generating Facilities. To a large extent,
this Final Rule harmonizes state and
federal practices by adopting many of
the best practices interconnection rules
recommended by the National
Association of Regulatory Utility
Commissioners (NARUC). By doing so,
we hope to minimize the federal-state
division and promote consistent,
nationwide interconnection rules. We
hope that states that do not currently
have interconnection rules for small
generators will look to the documents
presented in this Final Rule and
NARUC as guides for their own. In
particular, the ‘‘Fast Track Process’’ and
the ‘‘10 kW Inverter Process’’ should go
a long way towards harmonizing statefederal interconnection practices.
5. Finally, the application of this
Final Rule is the same as with Order No.
2003 for Large Generating Facilities.
Specifically, this Final Rule applies
only to interconnections with facilities
that are already subject to the
Transmission Provider’s OATT at the
time the Interconnection Request is
made.
6. The SGIP and SGIA include
separate definitions for ‘‘Transmission
System’’ and ‘‘Distribution System’’ to
account for the distinct engineering and
cost allocation implications of an
interconnection with a Distribution
System. The SGIP and SGIA, like Order
No. 2003, define ‘‘Transmission
System’’ as ‘‘[t]he facilities owned,
controlled or operated by the
Transmission Provider or the
Transmission Owner that are used to
provide transmission service under the
Tariff.’’ Any interconnection with a
Transmission System (under an OATT)
by a Small Generating Facility is subject
to this Final Rule.
7. The SGIP and the SGIA, like Order
No. 2003, also use the term
‘‘Distribution System.’’ ‘‘Distribution
System’’ is defined as ‘‘[t]he
Transmission Provider’s facilities and
equipment used to transmit electricity
to ultimate usage points such as homes
and industries directly from nearby
generators or from interchanges with
higher voltage transmission networks
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
which transport bulk power over longer
distances. The voltage levels at which
Distribution Systems operate differ
among areas.’’ If a Small Generating
Facility proposes to interconnect with a
portion of the Distribution System
subject to an OATT for the purpose of
making wholesale sales, then this Final
Rule would apply.8 However, an
interconnection to a portion of a
Distribution System that is not already
subject to an OATT would not be
subject to this Final Rule.
8. ‘‘Distribution’’ is a vague term,
usually used to refer to non-networked,
often lower-voltage facilities, that carry
power in one direction. Commissionjurisdictional facilities with these
characteristics are referred to as
‘‘Distribution Systems subject to an
OATT’’ throughout this Final Rule. This
Final Rule’s use of the term
‘‘Distribution System’’ has nothing to do
with whether the facility is under this
Commission’s jurisdiction; some
‘‘distribution’’ facilities are under our
jurisdiction and others are ‘‘local
distribution facilities’’ subject to state
jurisdiction.9 This Final Rule does not
violate the FPA section 201(b)(1)
provision that the Commission does not
have jurisdiction over local distribution
facilities ‘‘except as specifically
provided * * *.’’ 10 This is because the
Final Rule applies only to
interconnections to facilities that are
already subject to a jurisdictional OATT
at the time the interconnection request
is made and that will be used for
purposes of jurisdictional wholesale
sales. Because of the limited
applicability of this Final Rule, and
because the majority of small generators
interconnect with facilities that are not
subject to an OATT, this Final Rule will
not apply to most small generator
8 See Detroit Edison v. FERC, 334 F.3d 48 (DC Cir.
2003) (Detroit Edison). There, the court explained
that:
When a local distribution facility is used to
delivery [sic] energy to an unbundled retail
customer, FERC lacks any statutory authority, and
the state has jurisdiction over that transaction. By
contrast, when a local distribution facility is used
in a wholesale transaction, FERC has jurisdiction
over that transaction pursuant to its wholesale
jurisdiction under FPA Section 201(b)(1). In sum,
FERC has jurisdiction over all interstate
transmission service and over all wholesale service,
but FERC has no jurisdiction over unbundled retail
distribution service—i.e., unbundled retail service
over local distribution facilities.
Id. at 51 (citations omitted).
9 See Detroit Edison, 334 F.3d at 51. (‘‘For our
purposes, the most important result of these
jurisdictional determinations is that customers can
take any FERC-jurisdictional service under a
utility’s open access tariff, which the utility is
required to file with FERC. Customers must take
non FERC-jurisdictional service, such as unbundled
retail distribution, under a state tariff.’’)
10 16 U.S.C. 824 (2000).
PO 00000
Frm 00003
Fmt 4701
Sfmt 4700
34191
interconnections. Nonetheless, our hope
is that states may find this rule helpful
in formulating their own
interconnection rules.
A. Background
9. This Final Rule responds to
business and technology changes in the
electric industry. Where the electric
industry was once primarily the domain
of vertically integrated utilities
generating power at large centralized
plants, advances in technology have
created a burgeoning market for small
power plants that may offer economic,
reliability, or environmental benefits.
10. With these developments in mind,
the Commission continues in this
rulemaking to work to encourage fully
competitive bulk power markets. The
effort took its first significant step with
Order No. 888,11 which required public
utilities to provide other entities
comparable access to their Transmission
Systems. The effort continued with
Order No. 2000,12 which began the
process of developing Regional
Transmission Organizations (RTOs).
Most recently, the Commission
established a standard Large Generator
Interconnection Procedures document
(LGIP) and a standard Large Generator
Interconnection Agreement (LGIA) for
generating facilities larger than 20
MW.13
11. The Commission, pursuant to its
responsibility under sections 205 and
206 of the FPA to remedy undue
discrimination, is requiring all public
utilities that own, control, or operate
facilities for transmitting electric energy
in interstate commerce to append to
their OATTs the SGIP and SGIA we are
adopting in this Final Rule. These
documents provide just and reasonable
terms and conditions of interconnection
service. They also strike a reasonable
balance between the competing goals of
uniformity and flexibility while
ensuring safety and reliability are
protected.
11 Promoting Wholesale Competition Through
Open Access Non-Discriminatory Transmission
Services by Public Utilities: Recovery of Stranded
Costs by Public Utilities and Transmitting Utilities,
Order No. 888, 61 FR 21540 (May 10, 1996), FERC
Stats. & Regs. ¶ 31,036 (1996), order on reh’g, Order
No. 888–A, 62 FR 12274 (Mar. 14, 1997), FERC
Stats. & Regs. ¶ 31,048 (1997), order on reh’g, Order
No. 888–B, 81 FERC ¶ 61,248 (1997), order on reh’g,
Order No. 888–C, 82 FERC ¶ 61,046 (1998), aff’d
in part sub nom. Transmission Access Policy Study
Group v. FERC, 225 F.3d 667 (DC Cir. 2000), aff’d
sub nom. New York v. FERC, 535 U.S. 1 (2002)
(TAPS v. FERC).
12 Regional Transmission Organizations, Order
No. 2000, 65 FR 810 (Jan. 6, 2000), FERC Stats. &
Regs. ¶ 31,089 (1999), order on reh’g, Order No.
2000–A, 65 FR 12088 (Mar. 8, 2000), FERC Stats.
& Regs. ¶ 31,092 (2000), aff’d sub nom. Public Util.
Dist. No. 1 v. FERC, 272 F.3d 607 (DC Cir. 2001).
13 See Order No. 2003 passim.
E:\FR\FM\13JNR2.SGM
13JNR2
34192
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
B. Need for a Standard Generator
Interconnection Procedures and
Agreement
12. In fulfilling its responsibilities
under sections 205 and 206 of the FPA,
the Commission is required to remedy
undue discrimination. The Commission
must also ensure that the rates,
contracts, and practices affecting
jurisdictional transmission service do
not reflect an undue preference or
advantage for Transmission Providers
and their affiliates and are just and
reasonable. The Commission’s
regulatory authority under the FPA
‘‘clearly carries with it the responsibility
to consider, in appropriate
circumstances, the anticompetitive
effects of regulated aspects of interstate
utility operations* * *.’’ 14
13. The record underlying Order No.
888 showed that public utilities owning
or controlling jurisdictional
transmission facilities had the incentive
to engage in, and had engaged in,
unduly discriminatory transmission
practices.15 The Commission in Order
No. 888 thoroughly discussed the
legislative history and case law
involving sections 205 and 206,
concluded that it has the authority and
responsibility to remedy the undue
discrimination it found by requiring
open access, and decided to do so
through a rulemaking on a generic,
industry-wide basis.16 The Supreme
Court affirmed the Commission’s
decision to exercise this authority by
requiring non-discriminatory
(comparable) open access as a remedy
for undue discrimination.17 However,
Order No. 888 did not specifically
address interconnection service.18
14. In Tennessee Power,19 the
Commission clarified that
interconnection is a critical component
of open access transmission service and
thus is subject to the requirement that
utilities offer comparable service under
the OATT. The Commission
encouraged, but did not require, each
Transmission Provider to revise its
OATT to include interconnection
procedures, including a standard
14 Gulf States Utils. Co. v. FPC, 411 U.S. 747, 758–
59 (1973); see City of Huntingburg v. FPC, 498 F.2d
778, 783–84 (DC Cir. 1974) (noting the
Commission’s duty to consider the potential
anticompetitive effects of a proposed
interconnection agreement).
15 Order No. 888 at 31,679–84; Order No. 888–A
at 30,209–10.
16 Order No. 888 at 31,668–73, 31,676–79; Order
No. 888–A at 30,201–12; TAPS v. FERC at 687–88.
17 New York v. FERC, 535 U.S. 1 (2002).
18 Order No. 888–A, FERC Stats. & Regs ¶ 31,048
at 30,230–31.
19 Tennessee Power Co. (Tennessee Power), 90
FERC ¶ 61,238 at 61,761 (2000), reh’g denied, 91
FERC ¶ 61,271 (2000).
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
interconnection agreement and specific
criteria, procedures, milestones, and
timelines for evaluating applications for
interconnection.20
15. As discussed in Order No. 2003,
interconnection is a critical component
of transmission service, and having a
standard interconnection procedures
and a standard agreement applicable to
Small Generating Facilities will (1) limit
opportunities for transmitting utilities to
favor their own generation, (2) remove
unfair impediments to market entry for
small generators by reducing
interconnection costs and time, and (3)
encourage investment in generation and
transmission infrastructure, where
needed.21 We expect the SGIP and SGIA
adopted here will resolve most disputes,
minimize opportunities for undue
discrimination, foster increased
development of economic Small
Generating Facilities, and protect
system reliability.
C. The Large and Small Generator
Interconnection Rulemaking
Proceedings
16. In the Advance Notice of Proposed
Rulemaking (ANOPR) issued in Docket
No. RM02–1–000, the Commission
initiated a collaborative process where
members of the public, electric industry
participants, and federal and state
agencies (collectively, stakeholders)
were invited to draft proposed generator
interconnection procedures and a
generator interconnection agreement.22
The stakeholders filed their consensus
documents in January 2002. The
Commission then issued a Notice of
Proposed Rulemaking (Large Generator
Interconnection NOPR) 23 proposing
standard interconnection procedures
and a standard interconnection
agreement that generally followed the
consensus documents. The Large
Generator Interconnection NOPR also
proposed solutions to issues left
unresolved in the consensus documents.
17. Although the Large Generator
Interconnection NOPR provided special
treatment for Small Generating
Facilities, some commenters urged the
Commission to initiate a separate
proceeding to develop standard
interconnection procedures and
agreements that addressed the unique
concerns of Small Generating
20 See, e.g., Commonwealth Edison Co., 91 FERC
¶ 61,083 (2000).
21 Order No. 2003 at P 10.
22 Standardizing Generator Interconnection
Agreements and Procedures, Advance Notice of
Proposed Rulemaking, 66 FR 55140 (Nov. 1, 2001),
FERC Stats. & Regs. ¶ 35,540 (2002).
23 Standardization of Generator Interconnection
Agreements and Procedures, Notice of Proposed
Rulemaking, 67 FR 22250 (May 2, 2002), FERC
Stats. & Regs. ¶ 32,560 (2002).
PO 00000
Frm 00004
Fmt 4701
Sfmt 4700
Facilities.24 They proposed one set of
simplified interconnection rules for
Small Generating Facilities no larger
than 2 MW, and another for facilities
larger than 2 MW but no larger than 20
MW. Persuaded that different
procedures and agreements were indeed
needed, the Commission severed Small
Generating Facilities from the Large
Generator Interconnection proceeding
and issued a Small Generator
Interconnection Advance Notice of
Proposed Rulemaking (ANOPR) in
August 2002.25 The Small Generator
Interconnection ANOPR proposed two
SGIPs and two SGIAs (ANOPR SGIPs
and SGIAs) using 2 MW as a breakpoint.
It encouraged stakeholders to pursue
consensus on the ANOPR SGIPs and
SGIAs. To that end, the Commission
convened a series of public meetings
designed to enable them to discuss and
reach as much consensus as possible.
18. The negotiating parties, who we
refer to collectively as Joint
Commenters, then filed SGIPs and
SGIAs (Joint Commenters’ SGIPs and
SGIAs) with the Commission.26 While
Joint Commenters reached consensus on
some issues, many remained
unresolved. Joint Commenters’ SGIPs
included two procedures for evaluating
whether a proposed Small Generating
Facility could be interconnected safely
and without degrading reliability. The
first was a standard Study Process that
24 Those commenters included the Solar Energy
Industries Association, the U.S. Fuel Cell Council,
the American Solar Energy Society, the U.S.
Combined Heat and Power Association, the
International District Energy Association, and the
American Wind Energy Association.
25 Standardization of Small Generator
Interconnection Agreements and Procedures,
Advance Notice of Proposed Rulemaking, 67 FR
54749 (Aug. 26, 2002), FERC Stats. & Regs. ¶ 35,544
(2002).
26 This group refers to itself as the Coalition.
However, in this Final Rule we shall refer to the
group as ‘‘Joint Commenters’’ to distinguish it from
the similarly named Small Generator Coalition.
With the exception of these early references to Joint
Commenters’ comments submitted in response to
the ANOPR, all references in the remainder of this
Preamble to Joint Commenters are to its
supplemental comments. Joint Commenters did not
file initial comments in response to the Small
Generator Interconnection NOPR, only
supplemental comments. Joint Commenters is a
diverse group of stakeholders that includes:
• Over 25 small generator trade groups,
promoters, and equipment manufacturers, who refer
to themselves collectively as the ‘‘Small Generator
Coalition,’’
• State regulatory agencies represented by the
National Association of Regulatory Utility
Commissioners,
• American Public Power Association (which did
not participate in the filing of Joint Commenters’
supplemental comments), and
• Transmission Providers represented by Edison
Electric Institute (EEI) and National Rural Electric
Cooperative Association (NRECA)
A list of commenter acronyms may be found in
Appendix A.
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
used a scoping meeting and three
technical studies to evaluate a proposed
interconnection. The second was a
streamlined procedure that used
technical screens to identify those
proposed interconnections that clearly
would not jeopardize the safety and
reliability of the Transmission
Provider’s electric system. Public
comments on the Small Generator
Interconnection ANOPR were filed
shortly thereafter.
19. In July 2003, the Commission
issued Order No. 2003, which
established standard procedures and an
interconnection agreement for the
interconnection of large generators and
explained the Commission’s jurisdiction
over interconnections. The Commission
simultaneously issued the Small
Generator Interconnection NOPR.27
Certain provisions in the Large
Generator Interconnection Final Rule as
well as Joint Commenters’ SGIPs/SGIAs
influenced the Small Generator
Interconnection NOPR.28 The
Commission asked commenters to
address whether Small Generating
Facilities should be treated differently
from Large Generating Facilities under
the LGIP and LGIA adopted in Order
No. 2003.
20. Sixty-five entities submitted
initial comments in response to the
Small Generator Interconnection NOPR.
The comments generally support the
Commission’s effort to remove barriers
to the development of Small Generating
Facilities. Following the issuance of the
Small Generator Interconnection NOPR
and the initial comment due date,
NARUC in October 2003 updated its
own interconnection procedures and
agreement, referred to here as the
NARUC Model. NARUC stated that the
NARUC Model is based on the best
practices of the state regulatory agencies
that have interconnection procedures
for small generators. NARUC
encouraged state regulators to use the
NARUC Model as a basis for developing
their interconnection procedures and
suggested that the Commission’s
documents reflect these ‘‘best
practices.’’ On July 7, 2004, the
Commission staff added to the record in
this proceeding the latest version of the
NARUC Model.29 A few commenters
27 Standardization of Small Generator
Interconnection Agreements and Procedures, Notice
of Proposed Rulemaking, 60 FR 49974 (Aug. 19,
2003), FERC Stats. & Regs. ¶ 32,572 (2003) (Small
Generator Interconnection NOPR).
28 See, e.g., Proposed SGIA articles 4.1, 5.1.2,
5.1.2.1, 5.2, 6.1–6.9, 6.12–6.20, 7, and 8.
29 NARUC members had participated in the
ANOPR discussions fostered by the Commission;
there was much similarity between the provisions
of the NARUC Model and the Small Generator
Interconnection NOPR.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
favor terminating this proceeding or, in
the alternative, adopting the NARUC
Model.
21. The Commission then issued a
Notice of Request for Supplemental
Comments, observing that the small
generator industry had continued to
evolve since the Commission first
received comments in this proceeding.30
In the notice, the Commission observed
that several states had recently adopted
new guidelines for small generator
interconnections, and that the
stakeholders who participated in the
Commission’s ANOPR process were
continuing to work toward resolving
various SGIP and SGIA issues. The
Commission invited joint supplemental
comments describing new consensus
positions but discouraged resubmissions
of prior positions.
22. Joint Commenters, which as noted
above represents a diverse group of
small generator interests, Transmission
Providers, and state regulators who
participated in the ANOPR process, was
the only group to file a consensus
position. Some Joint Commenters—
Small Generator Coalition, NRECA, and
NARUC—filed their own supplemental
comments as well. Ten other entities
(mostly state regulatory commissions 31)
submitted supplemental comments.32
23. In its supplemental comments,
Joint Commenters endorsed a single
SGIP and single SGIA for Small
Generating Facilities no larger than 20
MW. Joint Commenters recommended
several revised provisions in areas
where they had not been able to reach
consensus during the ANOPR process.
These included dispute resolution,
confidentiality, insurance, equipment
certification, and technical screens,
among others. Joint Commenters, which
includes NARUC, also endorsed a
greatly simplified all-in-one application
form/procedures/terms and conditions
document for the interconnection of
certified inverter-based Small
Generating Facilities no larger than 10
kW.
24. In Order No. 2003–A, the
Commission determined that the LGIP
and LGIA were designed around the
needs of traditional synchronous
technology generators and that
generators relying on non-synchronous
technologies, such as wind plants, may
30 See Notice of Request for Supplemental
Comments, 69 FR 51024 (Aug. 17, 2004). The
Commission then granted two extensions of time at
the request of Joint Commenters. See Notices issued
on September 30, 2004 and November 30, 2004 in
Docket No. RM02–12–000.
31 CT DPUC, Minnesota PUC, and Massachusetts
DTE submitted copies of their recently enacted
small generator interconnection rules.
32 The supplemental commenters are listed in
Appendix A.
PO 00000
Frm 00005
Fmt 4701
Sfmt 4700
34193
find that a specific requirement is
inapplicable or that a different approach
is needed.33 Accordingly, the
Commission added a blank Appendix G
(Requirements of Generators Relying on
Non-Synchronous Technologies) to the
LGIA as a placeholder for requirements
specific to non-synchronous
technologies.34 At a September 24, 2004
technical conference on the
interconnection requirements of nonsynchronous technologies, panelists
were asked whether Appendix G type
requirements should apply to Small
Generating Facilities. They responded
that special capabilities, such as low
voltage ride-through, simply were not
needed for any Small Generating
Facility, whether wind powered or not.
As a result, the Wind NOPR issued
shortly thereafter applies only to the
interconnection of wind powered
generators 20 MW or larger.35 In its
supplemental comments, National Grid
asks the Commission to implement
standards for Small Generating
Facilities that are similar to those
proposed for Large Generating Facilities
in the Wind NOPR. This Final Rule does
not include such standards. The wind
generating facilities that will
interconnect under this Final Rule will
be small and will have minimal impact
on the Transmission Provider’s electric
system. The reliability requirements
proposed for wind powered Large
Generating Facilities are not needed for
small wind generating facilities.
25. In crafting this Final Rule, we
considered all of the comments received
throughout the course of this
proceeding, including the initial
documents submitted by Joint
Commenters in response to the ANOPR,
the Small Generator Interconnection
NOPR and the comments filed in
response, the NARUC Model, and the
supplemental comments. We considered
all comments filed in response to the
Small Generator Interconnection NOPR
before April 29, 2005, and they are part
of the record in this proceeding.36
II. Discussion
26. Part A of this discussion
(Descriptions of the SGIP and SGIA)
describes in general terms the
interconnection procedures document
(SGIP) and interconnection agreement
33 Order
No. 2003–A at P 407, n. 86.
34 Id.
35 Interconnection for Wind Energy and Other
Alternative Technologies, Notice of Proposed
Rulemaking, 70 FR 4791 (Jan. 31, 2005) (Wind
NOPR).
36 Comments addressing issues filed in other
dockets (for instance, the Wind NOPR) are not part
of this proceeding even if they were cross-filed in
Docket No. RM02–12–000.
E:\FR\FM\13JNR2.SGM
13JNR2
34194
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
(SGIA) we are adopting in this Final
Rule.
27. Part B (Overview of the
Interconnection Process for Small
Generating Facilities) describes the
processes that the Interconnection
Customer and the Transmission
Provider must follow to interconnect the
Small Generating Facility with the
Transmission Provider’s Transmission
System.
28. Part C (Issues Related to Both the
SGIP and the SGIA) addresses issues
that are common to the interconnection
procedures and agreement documents.
29. Part D (Issues Related to the
Interconnection Request) addresses
issues related to the Interconnection
Request (application form) that the
Interconnection Customer submits to
the Transmission Provider to request
interconnection of its Small Generating
Facility.
30. Part E (Issues Related to the SGIP)
addresses issues related only to the
interconnection procedures document.
31. Part F (Issues Related to the SGIA)
addresses issues related only to the
interconnection agreement.
32. Part G (The 10kW Inverter
Process) describes the simplified all-inone application form/procedures/terms
and conditions document for the
interconnection of certified inverterbased Small Generating Facilities no
larger than 10 kW.
33. Part H (Other Significant Issues)
addresses the pricing of Interconnection
Facilities and Upgrades, jurisdictional
issues, variations from the Final Rule,
the availability of waivers for small
entities, the effect of this Final Rule on
the OATT reciprocity provisions, and
others.
34. Finally, Part I (Compliance Issues)
addresses issues pertaining to the
requirement that a Transmission
Provider file conforming amendments to
its existing OATT, the treatment to be
accorded to existing interconnection
agreements (grandfathering), and how a
Transmission Provider is to file
executed and unexecuted
interconnection agreements.
A. Descriptions of the SGIP and SGIA
35. In Order No. 2003, the
Commission adopted two documents
that are to be used for the
interconnection of Large Generating
Facilities—the Large Generator
Interconnection Procedures document
and the Large Generator Interconnection
Agreement. The LGIP describes how the
Interconnection Customer’s
Interconnection Request (i.e.,
application) is to be evaluated from an
engineering perspective using a fourstep process. These are the scoping
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
meeting, the feasibility study, the
system impact study, and the facilities
study. The purpose of the evaluation is
to determine the impact the proposed
interconnection will have on the
Transmission Provider’s electric system
and identify new equipment and
modifications needed to accommodate
the interconnection. The LGIA, which is
signed after the proposed
interconnection has been successfully
evaluated using the provisions
contained in the LGIP, describes the
legal relationships of the Parties,
including who pays for equipment
modifications to the Transmission
Provider’s electric system.
36. The SGIP and SGIA we adopt in
this Final Rule serve the same purposes
as the LGIP and LGIA. The SGIP
includes the same four-step process for
evaluating an Interconnection Request
as does the LGIP, except that it is
simplified in several aspects and
includes timelines to accelerate the
interconnection of Small Generating
Facilities. In the SGIP, this procedure is
termed the ‘‘Study Process.’’ The SGIP
also includes special procedures for
evaluating two subgroups of Small
Generating Facilities, (1) a ‘‘Fast Track
Process’’ that uses technical screens to
evaluate a certified Small Generating
Facility no larger than 2 MW, and (2) a
‘‘10 kW Inverter Process’’ that uses the
same technical screens to evaluate a
certified inverter-based Small
Generating Facility no larger than 10
kW. The SGIA serves the same purpose
for the interconnection of a Small
Generating Facility as the LGIA does for
a Large Generating Facility. It describes
the legal relationships of the Parties,
including who will pay for equipment
modifications to the Transmission
Provider’s electric system.
37. The Commission received many
comments proposing modifications to
the Proposed SGIP and Proposed SGIA,
which helped greatly to shape this Final
Rule. NARUC argued that the
Commission should adopt portions of
its Model to harmonize federal
interconnection rules with those found
in states with interconnection rules.
Small Generator Coalition
recommended that the Commission in
this proceeding adopt the NARUC
Model instead of the Proposed SGIP and
Proposed SGIA. Some of the provisions
proposed by Joint Commenters (which
includes NARUC representation) in its
supplemental comments also followed
the NARUC Model. We are adopting in
this Final Rule many of these consensus
provisions as well as those proposed by
NARUC because they are just and
reasonable and serve the twin goals of
removing barriers to the development of
PO 00000
Frm 00006
Fmt 4701
Sfmt 4700
small generation while preserving the
safety and reliability of the nation’s
electric system.
38. The SGIP, while relying heavily
on NARUC’s and Joint Commenters’
proposals, is not a significant departure
from the Proposed SGIP. Both use
nearly identical interconnection study
processes (‘‘Study Process’’) to evaluate
Interconnection Requests that do not
qualify for special handling. Regarding
special handling, both use technical
screens to identify Small Generating
Facilities no larger than 2 MW that can
be interconnected with no adverse
impact on safety or reliability. The SGIP
we adopt in this Final Rule, however,
includes two such special procedures,
the Fast Track Process and the 10 kW
Process. The choice of which one the
Interconnection Customer may use
depends on the size and technology of
the Small Generating Facility. The SGIP
also includes the Interconnection
Request (application form) that is to be
used by all Interconnection Customers
except those eligible to use the 10 kW
Process, and feasibility study, system
impact study, and facilities study
agreements that are to be used in the
Study Process.37
39. The SGIA is to be used for the
interconnection of all Small Generating
Facilities subject to this Final Rule, with
the exception of certain very small
inverter-based generators that use an allin-one application form/procedures/
terms and conditions document (the 10
kW Inverter Process document). The
Proposed SGIA included several
provisions that were similar to those
contained in the LGIA that was issued
concurrent with the Small Generator
Interconnection NOPR. Some
commenters complained that the
Proposed SGIA was too long and
complex for owners of Small Generating
Facilities, who may be small businesses
or operators of small farms, for example.
We are streamlining and simplifying the
SGIA in many ways to address these
concerns. We are adopting Joint
Commenters’ proposals submitted in its
supplemental comments where
appropriate and have given
consideration to the recommendations
contained in the NARUC Model and
those suggested by other commenters. In
particular, the SGIA does away with the
requirement that Interconnection
Customers maintain multiple kinds of
insurance, instead requiring only that
they maintain a reasonable amount
based on the specific characteristics of
37 Note that the scope and payment provisions of
the feasibility, system impact, and facilities studies
are contained in the actual study agreements which
are included as Attachments 6, 7, and 8 to the SGIP,
not section 3 of the SGIP.
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
the interconnection. We also adopt a
streamlined dispute resolution
provision designed to resolve disputes
as quickly and inexpensively as
possible. We have also shortened the
contract termination provisions and the
various liability related provisions.
40. We adopt in the SGIA the same
pricing policy for Network Upgrades to
the Transmission Provider’s
Transmission System as in Order No.
2003. For a Small Generating Facility
interconnecting with a non-independent
entity such as a vertically integrated
utility, the Interconnection Customer
initially funds the cost of any required
Network Upgrades (i.e., Upgrades to the
Transmission System at or beyond the
Point of Interconnection) and it is then
subsequently reimbursed for this
upfront payment by the Transmission
Provider. However, we expect that, for
most interconnections of Small
Generating Facilities, there will be no
Network Upgrades. We also allow more
pricing flexibility for a Transmission
System that is operated by an
independent entity such as an RTO or
Independent System Operator (ISO).
The costs of Distribution Upgrades are
directly assigned to the Interconnection
Customer.
41. In conclusion, we encourage the
standardization of interconnection
practices across the nation, using as a
starting point the SGIP and SGIA found
in this Final Rule. We hope to foster
seamless interconnection procedures for
Interconnection Customers and
Transmission Providers. Equipment
manufacturers will have compatible
technical specifications to meet. New
generation will be located on the basis
of what works best for the
Interconnection Customer and the
Transmission Provider, not
jurisdictional differences in
interconnection rules.
B. Overview of the Interconnection
Process for Small Generating Facilities
42. Before submitting its
Interconnection Request, the
Interconnection Customer may
informally discuss the proposed
interconnection with the Transmission
Provider.38 The Interconnection
Customer then submits an
Interconnection Request to the
Transmission Provider and the
Transmission Provider assigns the
Interconnection Customer’s project a
Queue Position based on the date and
time the Interconnection Request is
38 Flowcharts
depicting interconnection
procedures are presented in Appendices B (Study
Process), C (Fast Track Process), and D (10 kW
Inverter Process).
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
34195
received by the Transmission Provider.
The Interconnection Request must be
accompanied by a deposit that goes
toward the cost of the feasibility study,
unless it is submitted under the Fast
Track Process or the 10 kW Inverter
Process, which have small processing
fees.
43. As noted above, an
Interconnection Request can be
evaluated in one of three ways. The
Study Process is the default method; it
relies on the scoping meeting and
standard feasibility, system impact, and
facilities studies to evaluate the safety
and reliability of the proposed
interconnection. It is identical in
concept to the evaluation procedure that
is used for the interconnection of Large
Generating Facilities. Two optional
methods are available to
Interconnection Customers whose Small
Generating Facilities are certified and
no larger than 2 MW. The 10 kW
Inverter Process is available for owners
of inverter-based Small Generating
Facilities no larger than 10 kW and the
Fast Track Process is available for
owners of any kind of Small Generating
Facility no larger than 2 MW.
44. The Study Process normally
consists of a scoping meeting, a
feasibility study, a system impact study,
and a facilities study. At the scoping
meeting, the Parties discuss the
proposed interconnection and review
any existing studies that could aid in
the evaluation of the proposed
interconnection. The feasibility study is
a preliminary technical assessment of
the proposed interconnection. The
system impact study is a more detailed
assessment of the effect the
interconnection would have on the
Transmission Provider’s electric system
and Affected Systems. The facilities
study determines what modifications to
the Transmission Provider’s electric
system are needed, including the
detailed costs and scheduled
completion dates for these
modifications. These studies identify
adverse system impacts 39 that need to
be addressed before the Small
Generating Facility may be
interconnected and any equipment
modifications required to accommodate
the interconnection. The
Interconnection Customer pays the
Transmission Provider’s actual cost of
performing the studies. Once the
Interconnection Customer agrees to fund
any needed Upgrades, the Parties
execute an SGIA that, among other
things, formalizes responsibility for
construction and payment for
Interconnection Facilities and
Upgrades.40
45. A Fast Track Process is available
for certified Small Generating Facilities
no larger than 2 MW. Under this
process, in place of the scoping meeting
and three interconnection studies,
technical screens are used to quickly
identify reliability or safety issues. If the
proposed interconnection passes the
screens, the Transmission Provider
offers the Interconnection Customer an
SGIA. If the proposed interconnection
fails the screens, but the Transmission
Provider determines that the Small
Generating Facility may nevertheless be
interconnected without affecting safety
and reliability, the Transmission
Provider also offers the Interconnection
Customer an SGIA. However, if the
Transmission Provider is concerned that
the interconnection could degrade the
safety and reliability of its electric
system, the Parties may conduct a
customer options meeting to discuss
how to proceed. In that meeting, the
Transmission Provider must offer to
perform a supplemental review of the
proposed interconnection, paid for by
the Interconnection Customer, to
identify Upgrades needed to
accommodate the interconnection. Once
the Interconnection Customer agrees to
pay for any Upgrades called for in the
supplemental review, the Parties
execute an SGIA. If, after the
supplemental review, the Transmission
Provider still is unsure whether the
proposed interconnection will degrade
the safety and reliability of its electric
system, the Interconnection Request is
evaluated using the Study Process
described above; i.e., scoping meeting,
feasibility, system impact, and facilities
studies, followed by the execution of an
SGIA.
46. Finally, the 10 kW Inverter
Process is available for the
interconnection of certified inverterbased generators no larger than 10 kW.
The all-in-one 10 kW Inverter Process
document includes a simplified
application form, interconnection
procedures, and a brief set of terms and
conditions (akin to an interconnection
agreement). The 10 kW Inverter Process
uses the same technical screens to
evaluate the safety and reliability of the
proposed interconnection as the Fast
Track Process. Unless the Transmission
Provider demonstrates that the Small
Generating Facility cannot be
39 An adverse system impact means that technical
or operational limits on conductors or equipment
are exceeded under the interconnection, which may
compromise the safety or reliability of the electric
system.
40 The Study Process is similar to the LGIP.
However, we expect that the interconnection of a
Small Generating Facility will take substantially
less time and cost substantially less than a Large
Generating Facility.
PO 00000
Frm 00007
Fmt 4701
Sfmt 4700
E:\FR\FM\13JNR2.SGM
13JNR2
34196
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
interconnected safely and reliably based
on the results of an analysis using the
screens, the Transmission Provider
approves the application. Once the
Interconnection Customer certifies that
equipment installation is complete and
upon a satisfactory inspection by the
Transmission Provider, the
Transmission Provider authorizes the
interconnection. To further simplify the
interconnection process, what would
normally be considered a separate
interconnection agreement has been
distilled into a terms and conditions
document that the Interconnection
Customer agrees to at the time the
Interconnection Request is submitted to
the Transmission Provider. The all-inone 10 kW Process document is
included in Attachment 5 to the SGIP.
C. Issues Related to Both the SGIP and
the SGIA
47. This discussion, and those that
follow, addresses the evolution of the
SGIP and SGIA from the Proposed SGIP
and Proposed SGIA. As is the custom in
most Commission rulemakings, we use
the Small Generator Interconnection
NOPR as our point of reference,
discussing each issue in turn, describing
the comments addressed to the topic,
and closing with the Commission
conclusion. There are differences
between the Proposed SGIP and SGIA
and the documents we adopt in this
Final Rule that reflect the helpful
comments filed in this rulemaking. For
example, we have in some instances
adopted terminology more compatible
with that used in state interconnection
documents. This should make for
simpler, more easily understood
documents for small generators that are
compatible across jurisdictions for both
Interconnection Customers and
Transmission Providers. However, the
SGIP and SGIA also need to be
interpreted in the broader context of the
entire collection of generator
interconnection documents that will
appear in a Transmission Provider’s
OATT, including the LGIP and LGIA.
Thus, there are some instances where
consistency among generator
interconnection documents within a
single tariff makes it necessary to adopt
Large Generator Interconnection
terminology or policy. The Commission
asked for comments in the Small
Generator Interconnection NOPR
addressing this topic, and it is the first
to be addressed in the discussion that
follows.
48. Many of the issues in this
rulemaking also arose in the Large
Generator Interconnecting rulemaking
and we will not address them again here
at any great length. Where there is no
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
compelling reason to depart from prior
precedent, we affirm the Commission’s
prior decisions without detailed
discussion. Therefore, this order focuses
on those issues needing a smallgenerator-specific resolution.
49. Finally, we note that the 10 kW
Inverter Process for certified inverterbased Small Generating Facilities is an
all-in-one application form/procedures/
terms and conditions document that
does not lend itself easily to the separate
discussions of the Proposed SGIP/SGIA
and the SGIP and SGIA discussions that
follow. We will address it in the
separate Part G discussion, below. We
emphasize, however, that the intent of
this Final Rule is that the 10 kW
Inverter Process fits within the
framework of the SGIP and SGIA, and
it is for that reason that we encourage
Interconnection Customers and
Transmission Providers to use this
Preamble, the SGIP, and the SGIA for
assistance in interpreting the 10 kW
Inverter Process should a dispute arise.
Consistency Between the Large
Generator and Small Generator
Documents
50. In the Small Generator
Interconnection NOPR, the Commission
asked commenters to address the need
for consistency between the provisions
of the LGIP/LGIA and the SGIP/SGIA.
Comments
51. NARUC argued that the Small
Generator Interconnection NOPR was
too complicated for most small
generator interconnections. Instead, the
Commission should adopt portions of
the NARUC Model or otherwise
simplify the interconnection process.
NARUC pointed out that many Small
Generating Facilities (including most
inverter-based generators) will
interconnect with low voltage facilities,
whether Commission-jurisdictional or
state-jurisdictional. Thus, this Final
Rule should be as consistent with state
interconnection rules as possible to
encourage national consistency and
discourage forum-shopping. Joint
Commenters also supports this outcome.
52. AEP supports consistency
between the large and small generator
documents. However, it notes that Joint
Commenters developed consensus
positions on many issues during the
ANOPR process. Where such agreement
was reached, AEP proposes that the
Commission adopt that position.
53. Midwest ISO argues that the
Commission should ensure consistency
between the large and small generator
documents, wherever possible, because
all stakeholders will benefit from a
PO 00000
Frm 00008
Fmt 4701
Sfmt 4700
consistent approach to the
interconnection of generation facilities.
54. PJM, on the other hand, proposes
that the Commission simply use the
LGIA for all interconnections, arguing
that having different rules for large and
small generator interconnections would
be overly burdensome. PJM also states
that its own interconnection rules take
this approach and are hailed as being
very successful.
55. Baltimore G&E argues that the
Commission should require the same
terms for all generators, regardless of
size, unless there is a specific reason not
to do so. Therefore, it requests that the
Commission provide a clear explanation
wherever these Final Rule provisions
differ from those in Order No. 2003.
Southern Company agrees, arguing that
Large and Small Generating Facilities
should be treated similarly ‘‘because
both can have * * * significant impacts
upon the Transmission Provider’s
electric system.’’ 41
56. BPA argues that the procedures
and technical requirements applicable
to large generators ‘‘should not apply to
the interconnection of small generators
that have minimal impacts on a
transmission grid.’’ 42 However, where
the Commission does use ‘‘substantially
similar or consistent procedures,
contract terms, and other requirements’’
for both Large and Small Generating
Facilities, ‘‘the Commission should
strive to provide consistency between
its large and small generator rules.’’ 43
57. Nevada Power also supports the
concept of having the provisions
applicable to Small Generating Facilities
similar to those in Order No. 2003.
According to Nevada Power, ‘‘[t]hese
commonalities will avoid the confusion
of differing terminologies, facilitate
consistent and fair implementation, and
minimize the need for separate, parallel
administrative processes to administer
the agreements.’’ 44 However, Nevada
Power also argues that consistency
should not compromise the goals of
simplifying and expediting the
interconnection of Small Generating
Facilities. Instead, this Final Rule
should be designed to ‘‘enable a
common language and common
administrative procedures to be
implemented and still maintain
appropriate distinctions between the
small generators and the large
generators.’’ 45 Nevada Power argues
that the benefits of consistency are
illustrated by Proposed SGIA article
41 Southern
42 BPA
Company at 19.
at 3.
43 Id.
44 Nevada
45 Nevada
E:\FR\FM\13JNR2.SGM
Power at 4.
Power at 4–5.
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
5.1.2.1, which specifies the refund
process for advances made by the
Interconnection Customer for Network
Upgrades. By having the same refund
process for the amounts advanced for
Network Upgrades in the SGIA and the
LGIA, the Transmission Provider can set
up one system, instead of two separate
systems, to track and make any such
refunds.
58. In their supplemental comments,
NARUC and the other Joint Commenters
proposed SGIP and SGIA provisions
that balance the need for simplicity with
the need of Transmission Providers to
ensure the safety and reliability of the
Transmission Provider’s electric system.
In addition, Joint Commenters also
proposed a process for certified inverterbased Small Generating Facilities no
larger than 10 kW that can also be used
as a model for the states.
Commission Conclusion
59. Unless expressly changed in this
Final Rule, the Commission’s existing
interconnection precedent and Order
No. 2003 are relevant to this Final Rule
and should be used as guidance for
interpretation and implementation. We
have tried to be consistent between the
rules for Large and Small Generating
Facilities, unless there is a specific
reason to do otherwise, while
considering NARUC’s call for federalstate consistency and the
recommendations of other commenters.
60. We note Joint Commenters’
proposal of much simpler
interconnection procedures and
agreement for inverter-based generators
no larger than 10 kW.46 Taking these
extremely small units out of the mix has
allowed us to adopt standard rules for
larger Small Generating Facilities.
According to NARUC, the process of
interconnecting with a statejurisdictional facility should not be
substantially different from the process
for interconnecting with a Commissionjurisdictional facility. Standard
interconnection procedures are
especially important for Interconnection
Customers and manufacturers of off-theshelf generating equipment.
61. In general, we are including
standard contractual provisions in the
SGIA that are consistent with their
counterparts in the LGIA. However, in
many cases commenters stressed the
need to simplify those provisions to
avoid burdening Small Generating
Facilities. Many commenters offered
ways to shorten and simplify those
provisions. Where possible, we accept
46 The 10 kW Inverter Process is largely based on
the work of the Massachusetts DTE and its
stakeholders group.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
those proposals. These streamlined
provisions adequately protect the
Parties while lowering the transaction
costs of entering into an interconnection
agreement. The SGIP closely tracks the
revised NARUC Model but adopts the
single screen that NARUC and the other
Joint Commenters later proposed in
supplemental comments. Last, we have
ensured that provisions common to the
SGIP and SGIA (such as dispute
resolution and confidentiality) are
consistent.
62. Definitions of Terms Used in the
SGIP and SGIA—NARUC and others
propose that the Commission use the
defined terms in the NARUC Model
instead of those found in the Small
Generator Interconnection NOPR. We
conclude that several of the terms
defined in the Proposed SGIP and SGIA
are either unnecessary or add
complexity to the interconnection
process. We are simplifying the SGIP
and SGIA by deleting those definitions.
Comments on specific terms are
discussed below.
63. Emergency Condition—The
Proposed SGIA defined Emergency
Condition as a situation that, in the
judgment of the Party making the claim,
is imminently likely to (1) endanger life
or property, (2) have an adverse impact
on the safety or reliability of the
Transmission Provider’s or an affected
third party’s electric system (Affected
System), or (3) have a material adverse
effect on the safety or operation of the
Interconnection Customer’s facilities. If
there is an Emergency Condition, the
Transmission Provider may take
necessary and appropriate actions to
protect the safety and reliability of its
electric system, including interrupting,
suspending, or curtailing
interconnection service. While system
restoration and black start are
considered Emergency Conditions, the
Small Generating Facility is not
obligated to have black start capability.
Comment
64. Bureau of Reclamation objects to
the provision that the Small Generating
Facility is not obligated by the SGIA to
have black start capability. Black start
capability is an issue best handled by
the control area rather than the
Transmission Provider and that
mentioning black start here raises the
question of by whom and when black
start capability could be required of the
Small Generating Facility. In addition,
Bureau of Reclamation proposes that the
definition of Emergency Condition also
include a ‘‘threat or danger to the
environment.’’
PO 00000
Frm 00009
Fmt 4701
Sfmt 4700
34197
Commission Conclusion
65. We see no need to modify the
definition of Emergency Condition. The
SGIA does not interfere with the control
area’s ability to establish a voluntary
restoration plan, including black start.
The SGIA requires the Parties to adhere
to all Applicable Laws and Regulations
relating to pollution and protection of
the environment or natural resources.
Therefore, Bureau of Reclamations’
proposed revision is not necessary.
66. Network Upgrades—Comments
concerning the definition of Network
Upgrades are addressed in Part II.H
(Pricing/Cost Recovery for
Interconnection Facilities and
Upgrades).
67. Use of Calendar Days v. Business
Days—The Proposed SGIP and Proposed
SGIA used both calendar days and
Business Days to establish deadlines for
particular activities.
Comments
68. Ameren, EEI, and NYTO request
that all references to calendar day be
changed to ‘‘Business Day.’’ Ameren
and EEI state that doing so would make
the SGIP and SGIA consistent. They also
state that this is particularly important
for the three and five day time limits,
especially where the Transmission
Provider may not have sufficient staff to
respond within the required time.
Ameren and NYTO argue that using
both calendar days and Business Days is
confusing. NYTO further notes that
using Business Days rather than
calendar days gives the Parties more
time to meet deadlines. In addition,
NYTO states that using calendar days
does not account for normal business
delays, including those caused by storm
emergencies.
Commission Conclusion
69. We agree that references to the
passage of time should be consistent.
Accordingly, we are changing calendar
days to Business Days throughout the
SGIP and SGIA, with two exceptions.
First, using calendar days is proper in
the SGIA’s billing and payment
provisions because these activities are
traditionally tied to calendar days.
Second, SGIA article 7.6.1 Default
provisions are stated in terms of
calendar days to be consistent with the
Commission’s regulations that require at
least 60 calendar days notice of a
proposed cancellation or termination of
a contract. Where we have replaced
calendar days with Business Days, we
have adjusted the number of days to
reflect about the same passage of time.
Arguments relating to the amount of
time a Party has to complete an action
are discussed below.
E:\FR\FM\13JNR2.SGM
13JNR2
34198
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
70. Maximum Size of a Small
Generating Facility—In the Small
Generator Interconnection NOPR, the
maximum size of a Small Generating
Facility is 20 MW. Where there is more
than one unit generating power at a
particular site, the Commission
proposed to aggregate the total capacity
of all generation units using the same
Point of Interconnection. The
Commission sought comments on a
circumstance when the Interconnection
Customer desires to increase the
capacity of an existing generating
facility. The Commission proposed that
the total size of the facility would be
determined by the sum of the existing
and the incremental capacity. Thus, a 10
MW addition to an existing 15 MW
facility would be treated as a 25 MW
facility. The Commission also sought
comments on how to evaluate an
Interconnection Request that specifies a
level of capacity below the maximum
rating of the Small Generating Facility.
Finally, the Commission invited
comments on whether Small Generating
Facilities with multiple Points of
Interconnection should be treated
separately for queuing and
interconnection study purposes.
Comments
Revising the Maximum Size of a Small
Generating Facility
71. Ameren, EEI, and NRECA ask the
Commission to reduce the maximum
size of a Small Generating Facility from
20 MW to 10 MW. They argue that the
lower size limit would help ensure
safety and reliability of the
Transmission Provider’s electric system.
They also note that it would also be
consistent with IEEE Standard 1547,47
and argue that the 20 MW size limit is
particularly challenging for
Transmission Providers because of the
types of analyses required to evaluate
their interconnection and the restrictive
time limits placed on performing them.
72. EEI similarly argues that many
states have adopted 10 MW as the
maximum size of a Small Generating
Facility and that the Commission
should follow suit. It argues that a 10
MW size limit is better suited to the
Small Generating Facility configurations
most likely to be proposed under the
Final Rule. While reducing the size
limit to 10 MW creates a gap between
the Large and Small Generating Facility
interconnection provisions, that gap can
47 IEEE
Standard 1547, approved in June 2003, is
the Institute of Electrical and Electronics Engineers’
standard for interconnecting distributed resources
with electric power systems. The standard applies
only to generating equipment no larger than 10
MW.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
be easily remedied by making the LGIP
and LGIA applicable to generating
facilities larger than 10 MW.
73. NRECA notes in its initial
comments that 10 MW is the upper limit
for small generators in Texas, California,
New York, and Ohio, and that no state
currently has rules that apply to the
interconnection of generators larger than
10 MW. According to NRECA, the
Commission’s statement in the Small
Generator Interconnection NOPR that
the 20 MW maximum size would
‘‘encourage the development of a greater
number of small generators and promote
the development of innovative small
generation technologies’’ is not
supported by engineering reality and
industry practice. NRECA participated
with Joint Commenters in developing
consensus provisions for the SGIP and
SGIA that were submitted in Joint
Commenters’ supplemental comments.
Based on those provisions, and in
particular the technical screens
contained in the SGIP, NRECA states
that, ‘‘while it still believes that 20 MW
is too large a generator to be considered
‘small,’ * * * [Joint Commenters’] SGIA
and SGIP will work for all generators up
to that size.’’ 48
74. Cummins argues that the 20 MW
size limit would result in more
widespread use of on-site Small
Generating Facilities.
Commission Conclusion
75. We agree with commenters that
generator size does matter when
evaluating the effect of the Small
Generating Facility on the Transmission
Provider’s electric system. However, we
are keeping the 20 MW size limit for
Small Generating Facilities because the
interconnection studies and screens will
identify any safety and reliability
problems. In particular, the screens we
adopt in the SGIP are supported by
small generators, state regulators, and
Transmission Provider representatives
such as EEI and NRECA, as being
appropriate to evaluate the safety and
reliability of interconnections of Small
Generating Facilities that are eligible for
screening. We believe the higher
threshold will remove barriers to the
development of a greater number of
Small Generating Facilities and promote
the development of innovative small
generation technologies.
48 NRECA Supplemental Comments at 5. NRECA
also ‘‘believes that the screens adopted for review
of generators up to 2 MW in capacity reasonably
consider the impact that generators of those sizes
will have on distribution systems.’’ Id. The
technical screens of which NRECA speaks are the
same screens adopted in this Final Rule.
PO 00000
Frm 00010
Fmt 4701
Sfmt 4700
Increasing the Capacity of an Existing
Small Generating Facility
76. The Small Generator
Interconnection NOPR proposed to
evaluate increases in capacity to
existing Small Generating Facilities
using the total capacity of the modified
facility, and the Commission invited
comments on whether the proposal was
reasonable.
Comments
77. Several Transmission Providers 49
support the NOPR’s proposal. They add
that if, for example, the capacity of an
existing 18 MW Small Generating
Facility were to be increased by 5 MW,
the resulting 23 MW facility should be
evaluated under the LGIP. This would
keep the Interconnection Customer from
gaming the system by incrementally
increasing the size of an existing Small
Generating Facility so that the capacity
addition does not exceed the 20 MW
maximum, even though the ultimate
capacity of the facility does. BPA and
ISO New England state that processing
the Interconnection Request for such an
expansion on the basis of the total
capacity would better protect the safety
and reliability of the Transmission
Provider’s electric system. Tangibl, on
the other hand, argues that evaluating
the Interconnection Request based on
the total increased capacity of the Small
Generating Facility would discourage
such increases and hinder the increased
entry of generators into the energy
markets.
Commission Conclusion
78. We are persuaded by BPA and ISO
New England that when an existing
Small Generating Facility is expanded,
the Interconnection Request should be
evaluated based on the total capacity of
the facility as opposed to the
incremental amount of the expansion.
Similarly, an existing Large Generator
seeking to increase its capacity by less
than 20 MW would also have to follow
the Large Generator rule, because the
total capacity of the expanded facility
would be more than 20 MW. Section
4.10.1 of the SGIP reflects this
conclusion.
Evaluating the Generating Facility Based
on Less Than Its Maximum Rated
Capacity
79. In the Small Generator
Interconnection NOPR, the Commission
sought comments on whether the
maximum capacity of the Small
Generating Facility should be used to
evaluate the Interconnection Request
49 E.g., BPA, ISO–New England, NRECA, NYTO,
PG&E, and Western.
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
when the Interconnection Customer
specified an output level below the
facility’s maximum capability. For
example, the Commission asked
whether an Interconnection Request for
a generating facility with a maximum
capacity of 22 MW but seeking an
interconnection for only 20 MW (and
agreeing to restrict delivery to the
Transmission Provider’s Transmission
System to that level) should be
evaluated under the SGIP or the LGIP.
Comments
80. Several Transmission Providers 50
argue that the Interconnection Request
should be evaluated on the basis of the
maximum capacity of the Small
Generating Facility to ensure that safety
and reliability are not jeopardized. They
argue that the Commission should not
allow a 22 MW generator to be treated
as a 20 MW generator based on a
promise by the Interconnection
Customer that it will never generate
more than 20 MW. This would result in
an additional administrative burden on
the Commission or market monitors.
They also argue that evaluating the
Small Generating Facility at less than its
maximum rated capacity would not
ensure that Interconnection Facilities
and Upgrades are properly designed and
installed.
81. BPA argues that evaluating a
Small Generating Facility on the basis of
maximum rated capacity would prevent
gaming by an Interconnection Customer
and would prevent it from submitting a
request to interconnect its Small
Generating Facility at a lower capacity
when it really intend to operate the
facility at a higher capacity. Further,
evaluating a Small Generating Facility
based on its maximum operational
capacity would avoid the need to
perform a reevaluation each time the
Interconnection Customer seeks to
operate at a higher output level.
82. Likewise, NYTO claims that even
if a Small Generating Facility supplies
local load and delivers only half of its
output, it still contributes its full fault
current to the electric system if there is
an electrical fault. Also, stability
analysis is based on the full physical
characteristics of the facility, such as
maximum power capability and rotation
inertia. It further argues that if the
Commission adopts a value other than
the maximum capability of the Small
Generating Facility, the Interconnection
Customer could ‘‘forum shop’’ between
the Large and Small Generating Facility
50 E.g., AEP, Ameren, Avista, BPA, CA ISO,
Central Maine, MidAmerican, MISO, NYTO, PG&E,
SoCal Edison, and Western.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
interconnection provisions to get the
‘‘best deal.’’
83. On the other hand, Allegheny
states that if the Interconnection
Customer is willing to accept the
economic risks of its decision to limit
the output of its generating facility, the
Interconnection Request should be
evaluated at the lower capacity.
84. American Forest, Cummins,
Nevada Power, NRECA, and Tangibl
also state that the Interconnection
Request should be evaluated on the
basis of requested capacity, not the
maximum capability of the generator, if
the Interconnection Customer commits
to restrict the output. American Forest
says that this is important for generators
that consume most of their electrical
output on-site in various manufacturing
processes and export only a small
fraction of their output. In its
supplemental comments, Small
Generator Coalition proposes a special
set of tests that could be used to
determine whether these kinds of
configurations jeopardize safety and
reliability.
Commission Conclusion
85. We are persuaded that the
Interconnection Request should be
evaluated based on the Small
Generating Facility’s maximum rated
capacity. We agree with commenters
that evaluating the proposed
interconnection at less than the
maximum rated capacity of the
generating facility does not ensure that
proper protective equipment is designed
and installed and the safety and
reliability of the Transmission
Provider’s electric system can be
maintained.
86. Nevada Power and other
commenters propose that the
Interconnection Request be evaluated on
the basis of requested capacity if the
Interconnection Customer agrees to
restrict the output of its facility. We
agree with NYTO, however, that even if
the Small Generating Facility delivers
only a portion of its capability, it still
contributes its full fault current to the
Transmission Provider’s electric system
if there is an electrical fault. Therefore,
the maximum capacity of the Small
Generating Facility should be used to
evaluate the Interconnection Request
(See section 4.10.3 of the SGIP).
Evaluating Small Generating Facilities
With Multiple Points of Interconnection
87. The Small Generator
Interconnection NOPR invited
comments on whether Small Generating
Facilities with multiple Points of
Interconnection (such as for a wind farm
or an industrial cogeneration project
PO 00000
Frm 00011
Fmt 4701
Sfmt 4700
34199
serving multiple facilities) should be
treated as separate projects or as a single
project for queuing and interconnection
study purposes.
Comments
88. BPA, CA ISO, ISO New England,
and Tangibl argue that Small Generating
Facilities with multiple Points of
Interconnection should be treated as a
single project for queuing and
interconnection study purposes. BPA
states that this promotes greater
efficiency and accuracy because the
effects of all the generators can be
evaluated in one study. According to
commenters, evaluating each Point of
Interconnection as a discrete facility
may not account for the aggregate effects
when multiple generation resources are
interconnected.
89. Tangibl recommends adopting
PJM’s approach of one Interconnection
Request for each Point of
Interconnection. Tangibl states that the
Interconnection Customer should
aggregate the capacity of the multiple
wind or solar projects that lie in close
proximity to one another. However, for
geographically dispersed wind or solar
projects, it recommends that the project
developer be able to ask the
Transmission Provider to treat each
project individually for interconnection
study purposes.
90. Central Maine, Idaho Power, and
others argue that evaluating
Interconnection Requests based upon a
single Point of Interconnection may
produce flawed results because it may
identify Upgrades incorrectly.
91. NYTO recommends that the
Transmission Provider have the option,
subject to Good Utility Practice, to
either treat such projects separately for
queuing and interconnection study
purposes, or as a single Point of
Interconnection. This is because each
proposed Point of Interconnection
presents numerous technical,
operational, and reliability issues.
Commission Conclusion
92. We adopt NYTO’s proposal for the
reasons cited by NYTO. The
Transmission Provider’s evaluation of a
project with multiple Points of
Interconnection should be performed,
using Good Utility Practice, based on
the project’s unique engineering and
geographic needs.
93. Dispute Resolution (Proposed
SGIA Article 8 and Proposed SGIP
Section 2.11) 51—The Commission
51 In the remainder of this Preamble, ‘‘Proposed
SGIA Article xxx’’ refers to a numbered article in
the Small Generator Interconnection NOPR, not the
SGIA adopted in this Final Rule. The same follows
E:\FR\FM\13JNR2.SGM
Continued
13JNR2
34200
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
proposed adopting the same dispute
resolution procedures contained in the
LGIA and LGIP. This was a departure
from Joint Commenters’ proposal
submitted in response to the ANOPR
which obliged the Commission to
supply technical experts to resolve
disputes between the Parties.
Comments
94. Commenters were split as to
which type of dispute resolution
procedures should be adopted by the
Commission. Small generator
proponents generally support allowing
either Party to require binding
arbitration, while Transmission
Providers generally oppose such
provisions. However, all commenters
stress the need for quick and costeffective dispute resolution.
95. CT DPUC argues that the
procedures in the Small Generator
Interconnection NOPR are too
cumbersome and that state commissions
are best positioned to resolve disputes
in a fair manner, especially disputes
over dual use facilities.
96. NRECA and BPA support adopting
the dispute resolution procedures in the
LGIA. However, BPA opposes binding
arbitration and asserts that the Parties
should keep whatever appeal rights they
have.
97. Small Generator Coalition argues
that most Interconnection Customers
that own Small Generating Facilities do
not have the resources to enter into
protracted dispute resolution
procedures with the larger Transmission
Provider. It argues that complex dispute
resolution procedures may discourage
Small Generating Facilities from seeking
to interconnect with Commissionjurisdictional facilities. Small Generator
Coalition questions why the
Commission would propose retreating
from the ANOPR consensus result. It
fears that Transmission Providers will
simply refuse to submit to arbitration,
forcing an Interconnection Customer to
engage in expensive and undefined
litigation. This is particularly true for
owners of Small Generating Facilities no
larger than 2 MW.
98. AEP proposes that either Party be
able to require binding arbitration. It
states that this approach is consistent
with the consensus reached during the
ANOPR process. Cummins agrees,
asserting that otherwise one Party can
obstruct the process. It points out that
Interconnection Customers often lack
the financial resources to pursue their
rights before the Commission or in
court, and need access to low-cost,
binding dispute resolution procedures.
99. American Forest proposes
allowing the Parties to agree on other
arbitration procedures if they want to
further tailor the procedures to the
needs of the specific Parties. It claims
that this is the approach common in the
industry.
100. Midwest ISO recommends that
where an RTO has Commissionapproved dispute resolution procedures,
it be allowed to apply those procedures
to interconnection disputes.
101. NARUC requests that the
Commission adopt the dispute
resolution provisions found in its
Model. It argues that ‘‘[e]ach State
already has in place a variety of avenues
for dispute resolution oriented to
protect the interests of the retail
customer, ranging from a simple phone
call to a State commission or consumer
advocate ‘consumer hotline’ to a fullblown complaint proceeding conducted
by the State Commission.’’52
Specifically, the NARUC Model states
that ‘‘[i]f a dispute arises at any time
during these procedures [the Parties]
may seek immediate resolution through
complaint procedures available’’
through the state regulatory
commission.53 The Model (1) states that
the Interconnection Customer’s Queue
Position is not to be affected by its
decision to pursue dispute resolution,
(2) allows either Party to require binding
arbitration, (3) allows the Parties to
request that the state regulatory agency
appoint a ‘‘technical master’’ to conduct
the dispute resolution process, and (4)
states that ‘‘where possible, dispute
resolution will be conducted in an
informal, expeditious manner in order
to reach resolution with minimal costs
and delay. When appropriate and
available, the dispute resolution may be
conducted by phone or through Internet
communications.’’ 54
102. Joint Commenters, in its
supplemental comments, proposes that
the Commission’s Dispute Resolution
Service (FERC DRS) assist Parties in
resolving their disputes. Under Joint
Commenters’ proposal, one Party would
give the other Party written notice that
they have reached an impasse. As soon
as two days afterwards, either Party may
consult with FERC DRS for guidance on
how best to resolve the dispute. FERC
DRS may provide the Parties with a
neutral venue to work out their dispute
or may recommend alternative avenues
of dispute resolution including, but not
limited to, mediation, settlement judge
for references to the Proposed SGIP. This is because
the numbering of the SGIP and SGIA does not
follow the Proposed SGIP and SGIA.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
52 NARUC
53 NARUC
at 12–13.
Model at F.
54 Id.
Frm 00012
Fmt 4701
Sfmt 4700
talks, early neutral evaluation, or
arbitration. The Parties could agree to
make such outcomes binding, but would
not be required to so agree, or even to
participate in alternative dispute
resolution procedures before FERC DRS.
Commission Conclusion
103. We are adopting a dispute
resolution provision for both the SGIP
and SGIA that closely resembles the
consensus recommendation of Joint
Commenters. As the widely disparate
recommendations show, different types
of interconnection disputes require
different types of dispute resolution
procedures. Small Generator Coalition
and others emphasize the need to avoid
expensive and time consuming
arbitration provisions. According to
these commenters, if a project is forced
to go to arbitration, it will likely never
be built. Instead, Joint Commenters
reached consensus on a set of principles
designed to encourage the Transmission
Provider and the Interconnection
Customer to use fast and low cost
alternative dispute resolution
procedures to work through their
differences.
104. Because the nature of the
disputes that may arise are so varied,
this approach will allow FERC DRS to
make specific recommendations to the
Parties designed to resolve the dispute
quickly and inexpensively. In some
cases, FERC DRS may simply provide
the Parties a neutral venue to discuss
their differences. In other cases, FERC
DRS may recommend that the Parties
put their case before a settlement judge
or technical master for either mediation
or arbitration. The Parties are free to
specify whether the outcome of this
alternative dispute resolution is
binding.
105. As recommended by Joint
Commenters, we will not mandate that
the Parties use the FERC DRS’ resources.
Alternative dispute resolution is, by its
nature, a collaborative and voluntary
process. However, both Parties must
work in good faith to resolve their
disputes. Additionally, the provision
specifies that each Party is responsible
for paying one-half of the cost of a
neutral third-party employed to assist in
settling the dispute.
106. We agree with CT DPUC,
NARUC, and Joint Commenters (in its
supplemental comments) that a state
regulatory agency may often be the best
place to quickly resolve a dispute. As
mentioned above, the FERC DRS is wellequipped to recommend to Parties the
best avenue for resolving a dispute. In
many cases, that may be a state
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
regulatory agency, if that body is willing
to mediate or arbitrate the dispute.55
107. While we are allowing Parties to
select a dispute resolution process, we
count on FERC DRS to ensure that both
Parties are treated fairly. Thus, we
disagree with American Forest that the
Parties should be able to deviate from
the established dispute resolution
procedures without Commission
guidance or oversight. While flexibility
is important, as many commenters have
pointed out, the Parties are rarely on an
equal footing. Thus, we will scrutinize
the process to ensure that
Interconnection Customers are treated
fairly, especially by non-independent
Transmission Providers.
108. In response to Midwest ISO’s
request to include ISO-specific dispute
resolution rules, under the independent
entity variation, it and other
independent Transmission Providers
may propose such a plan in their
compliance filings.
109. Confidentiality (Proposed SGIA
Article 7 and Proposed SGIP Section
2.11)—These provisions detailed the
rights and responsibilities of each Party
to keep any Confidential Information
shared during the interconnection
process.
Comments
110. Avista and Idaho Power assert
that the confidentiality provisions
should give state regulators conducting
an investigation the same access to
confidential information as is provided
to the Commission when it conducts an
investigation. Avista also requests that
the Commission address recent rulings
by the Internal Revenue Service
applicable to confidential transactions.
Similarly, NARUC is concerned that the
proposed confidentiality provisions
might prevent state regulators from
getting the information they need in the
course of conducting an investigation.
The NARUC Model SGIP includes a
confidentiality provision that is similar
to that proposed in the Small Generator
Interconnection NOPR. The NARUC
Model SGIA simply leaves a place
holder to be filled in by the Parties.
111. Southern Company argues that
Proposed SGIA article 7.1 should
specify that information supplied ‘‘as
part of this [interconnection]
agreement’’ be confidential rather than
information supplied ‘‘prior to
execution of this agreement.’’ It also
55 The Commission does not require states to
serve a dispute resolution function; it lacks the
statutory authority to do so. However, because
commenters argue that state participation could be
beneficial, we encourage states that have the
expertise, resources, and interest to help resolve
these disputes as they arise.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
says that Proposed SGIA article 7.12
allows a broader class of information to
qualify for confidential treatment than
does article 7.1, and proposes deleting
article 7.12. Finally, article 7.4 should
be revised to prohibit the
Interconnection Customer from sharing
Confidential Information with
‘‘potential purchasers or assignees of the
Interconnection Customer.’’
112. In its supplemental comments,
Joint Commenters propose the following
provision in lieu of the proposal:
Confidential Information is as defined in
this Agreement but does not include
information previously in the public domain,
required to be publicly submitted or divulged
by Governmental Authorities (after notice to
the other party and after exhausting any
opportunity to oppose such publication or
release), or necessary to be divulged in an
action to enforce this agreement. Each party
receiving Confidential Information shall hold
such information in confidence and shall not
disclose it to any third party nor to the public
without the prior written authorization from
the party providing that information, except
to fulfill obligations under this agreement, or
to fulfill legal or regulatory requirements.
Each party shall employ at least the same
standard of care to protect Confidential
Information obtained from the other party as
it employs to protect its own Confidential
Information. Each party is entitled to
equitable relief, by injunction or otherwise,
to enforce its rights under this provision to
prevent the release of Confidential
Information without bond or proof of
damages, and may seek other remedies
available at law or in equity for breach of this
provision.
Commission Conclusion
113. We are adopting confidentiality
provisions in both the SGIP and SGIA
that closely resemble those proposed by
Joint Commenters. While the provisions
we adopt here are shorter than those in
the LGIP and LGIA, they are similar in
content.
114. To clarify the Commission’s right
to otherwise Confidential Information
during an investigation, we include an
SGIA provision similar to LGIA article
22.1.10.56 This addition also clarifies
that a Party is not prohibited from
disclosing Confidential Information to a
state regulatory body where the state
regulatory body has the authority to
request the information.
115. We deny Southern Company’s
request to remove proposed language
allowing the Interconnection Customer
to share Confidential Information with
potential assignees and financers. The
Interconnection Customer must be able
to share such information to secure
financing and remain competitive.
However, we are modifying the
PO 00000
56 See
Order No. 2003–A at P 486.
Frm 00013
Fmt 4701
Sfmt 4700
34201
provision to specify that any such
person receiving Confidential
Information agree to abide by the same
confidentiality rules as the Parties.57 We
agree with Southern Company that
confidentiality should apply to all
information shared between the Parties;
however, its proposal is obviated by the
new language.
116. Keeping the Small Generator
Interconnection Rules Current—The
Small Generator Interconnection NOPR
did not envision that the SGIP and SGIA
would be periodically revised.
Comment
117. In its supplemental comments,
Small Generator Coalition asks the
Commission to adopt a mechanism to
allow periodic revisiting of its
interconnection rules as the industry
evolves. It proposes that the
Commission encourage or charter a
stakeholder committee to meet
periodically to consider and recommend
consensus proposals for changes.
Commission Conclusion
118. We commend the persistence of
the Joint Commenters who met on
numerous occasions over the duration
of this proceeding to aid the
Commission in its decision-making. As
one can see in the contents of this Final
Rule, those negotiations have been very
successful. We believe Small Generator
Coalition’s proposal has merit. We ask
the Joint Commenters to take the lead in
this process, and encourage interested
entities to continue to work together on
small generator interconnection issues.
We are asking this informal group to
meet biennially, beginning two years
from the issuance of this order, to
consider and recommend consensus
proposals for changes in the
Commission’s rules for small generator
interconnection. The Commission will
provide appropriate resources to
facilitate the process. To the extent that
this group identifies needed changes,
they may file a petition to amend the
Commission’s regulations. The
Commission will review the petition
and, if appropriate, notice that petition
for public comment.
D. Issues Related to the Interconnection
Request
119. The Interconnection Request is
the application form that the
Interconnection Customer uses to start
the process of interconnecting its Small
Generating Facility with the
Transmission Provider’s Transmission
System. The issues discussed below
either did not arise in the Large
57 Id.
E:\FR\FM\13JNR2.SGM
at P 490.
13JNR2
34202
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Generator Interconnection proceeding or
we conclude that a different conclusion
should apply to Small Generating
Facilities.
120. Processing Fees and Study
Deposits—The Proposed SGIP set out a
fixed processing fee schedule for
processing all Interconnection Requests.
The amount of the fee was to be tied to
the size of the Small Generating Facility.
Small Generating Facilities no larger
than 2 MW in size would be charged the
greater of (1) $0.50/kVA rating, or $100
for single phase generators no larger
than 25 kVA or (2) $500 for generators
larger than 25 kVA. The fee for a Small
Generating Facility larger than 2 MW
but no larger than 10 MW would be
$1,000, and the fee for one larger than
10 MW would be $2,000. In addition, if
the Small Generating Facility was to be
evaluated using the interconnection
studies, the Interconnection Customer
would pay a deposit prior to each study
that would be applied to the
Transmission Provider’s actual costs of
performing the study.
Comments
121. NARUC urges that the processing
fee be cost-based so that there is no
subsidization by either the
Transmission Provider or the
Interconnection Customer.
122. NRECA generally supports a
fixed processing fee approach, but says
that the proposed fees are unrelated to
the actual cost of conducting the
analysis under the screens. It asks the
Commission to let each Transmission
Provider file fees that are designed to
recover the actual cost of conducting the
analysis under the screens.
123. NYTO asks the Commission to
clarify that the proposed fee covers
administrative and engineering costs not
covered by other fees. PacifiCorp states
that it does not appear that the owner
of a Small Generating Facility no larger
than 2 MW would pay any fee other
than the fee to conduct the analysis
under the screens. It asks the
Commission to require the owner of
such a generator to pay the actual cost
of interconnection, if any, beyond the
processing fee.
124. Southern Company states that
the proposed processing fee schedule
conflicts with the deposit provisions of
the proposed interconnection study
agreements. It argues that a Small
Generating Facility interconnecting at
the transmission level should submit an
interconnection feasibility study deposit
rather than the application fee because
it appears that the processing fee is a
charge for conducting the analysis
under the screens. Southern Company
also states that evaluating an
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
Interconnection Request for a noncertified Small Generating Facility
requires time and effort, and the
Interconnection Customer should pay
twice the processing fee assessed to the
owner of a certified Small Generating
Facility.
Commission Conclusion
125. Under this Final Rule, the
Interconnection Customer shall submit
with its Interconnection Request a
processing fee or feasibility study
deposit, but not both, depending on
how the Interconnection Request is to
be evaluated. If it is to be evaluated
using the Study Process, which usually
includes a scoping meeting and
feasibility, system impact, and facilities
studies, the Interconnection Customer
shall make a deposit towards the cost of
the feasibility study at the time the
Interconnection Request is submitted to
the Transmission Provider. The amount
of the deposit is the lesser of 50 percent
of the good faith estimated feasibility
study costs or $1,000. If the
Interconnection Request is to be
evaluated using the Fast Track Process,
it is to be accompanied by a $500
processing fee. If the Interconnection
Request is to be evaluated using the 10
kW Inverter Process, it is to be
accompanied by a $100 processing fee.
126. The purpose of the $100 and
$500 processing fees is to recover the
Transmission Provider’s costs of
evaluating Interconnection Requests
under the 10 kW Inverter Process and
Fast Track Process, respectively. This
approach to fees is simple, easy to
administer, and gives many
Interconnection Customers the cost
certainty they need to move forward
with their projects. However, because
administratively fixed fees will
sometimes either under- or over-recover
a particular Transmission Provider’s
costs, we will allow the Transmission
Provider to charge a cost-based fee for
processing Interconnection Requests if it
has first made an appropriate rate filing
with appropriate detailed cost
justification under FPA section 205.58 If
the Transmission Provider decides to
revise its processing fee schedule
through a rate filing, the revised fees
would, of course, apply prospectively to
all new Interconnection Requests under
the Fast Track Process or the 10 kW
Inverter Process. Otherwise, the
processing fees in the SGIP will serve as
a default.
127. Given our concerns about the
need for many Interconnection
Customers to know beforehand the costs
58 16 U.S.C. 824d (2000); see also 18 CFR § 35.12
(2004).
PO 00000
Frm 00014
Fmt 4701
Sfmt 4700
they will incur for the evaluation of
their Interconnection Request under the
screens, we will disallow formula rates
or true up provisions in any rate
submission. The cost support for the
filed fixed processing fee schedule
(designed in a manner similar to the
processing fees in the SGIP) shall reflect
the Transmission Provider’s costs for
processing Interconnection Requests
under the Fast Track and the 10 kW
Inverter Processes, as it would for the
embedded cost based pricing of any
other jurisdictional service.
128. Southern Company’s first
comment highlights an unintended
inconsistency in the NOPR. To clarify,
the fixed processing fee schedule
delineated above is only for submissions
under the10 kW Inverter Process and
the Fast Track Process which use the
technical screens. A submission under
the Study Process instead will include
a deposit towards the Transmission
Provider’s cost of performing the
feasibility study, not both a deposit and
a processing fee. However, an
Interconnection Customer whose
proposed interconnection fails the Fast
Track Process or the 10 kW Inverter
Process and is then evaluated under the
Study Process would pay both the fixed
processing fee with the initial
submission and then a feasibility study
deposit before the Study Process begins.
129. Receipt Confirmation and
Requests for Additional Data—Proposed
SGIP sections 3.2 and 4.2 govern the
submission and receipt of the
Interconnection Customer’s
Interconnection Request.
Comments
130. Central Maine argues that the
Transmission Provider should be able to
use alternative methods to mail, such as
fax and overnight delivery services, to
tell the Interconnection Customer that it
has received the Interconnection
Request. It also asks that the
Commission increase the Transmission
Provider’s notification time period from
ten to fifteen Business Days. Central
Maine and EEI note that the
Interconnection Customer does not have
a deadline to supply missing
information. They recommend that the
Commission establish ten Business Days
as the deadline and to state that failure
to provide such information within that
time will result in the Interconnection
Request being deemed withdrawn.
Commission Conclusion
131. We agree that the Transmission
Provider may use alternate methods of
confirming receipt of the
Interconnection Request. The
notification requirement is needed
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
because it provides a date certain for
affirming that the Transmission
Provider has received the
Interconnection Request. We also
decline to increase the time by which
the Interconnection Customer must be
told whether the Interconnection
Request is complete. Ten Business Days
is sufficient time for the Transmission
Provider to make an initial assessment
as to whether the requisite information
has been provided; an in-depth
evaluation of the project is not required
during this period. However, we agree
with Central Maine and EEI that the
Proposed SGIP does not address when
the Interconnection Customer must
furnish the missing information.
Accordingly, the SGIP provides that the
Interconnection Customer has ten
Business Days after receipt of the notice
to submit the missing information or to
provide an explanation as to why
extension of time is needed to provide
such information. If the Interconnection
Customer does not provide the missing
information or a request for an
extension of time within the deadline,
the Interconnection Request shall be
deemed withdrawn.
132. Interconnection Products and
Service Options—The Proposed
Interconnection Request would have
directed the Interconnection Customer
to state whether it intends to participate
as a ‘‘Network Resource,’’ ‘‘Energy-Only
Resource,’’ ‘‘Non-Exporting Resource
Participating in a Wholesale Market,’’ or
‘‘Other.’’
Comments
133. Alabama PSC, EEI, Mississippi
PSC, Southern Company, and others are
concerned that the Interconnection
Request could be construed to mean that
a Small Generating Facility is eligible
for the same Network Resource
Interconnection Service that Order No.
2003 makes available to Large
Generating Facilities. They argue that
this service should not be provided to
a Small Generating Facility. For
example, Alabama PSC and Mississippi
PSC argue that a Small Generating
Facility does not meet the basic
prerequisites to receive a ‘‘network’’
type of service. They state that Small
Generating Facilities almost universally
interconnect with either ‘‘distribution’’
or sub-transmission facilities that are
not ‘‘networked’’ but are radial in
nature. The costs to make such facilities
networked to provide such a service
would be prohibitive. Southern
Company asks that the references to
resource options be deleted. TAPS states
that the Small Generator
Interconnection NOPR correctly
dispenses with Order No. 2003’s
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
Network Resource Interconnection
Service, which TAPS claims is
incompatible with Network Integration
Transmission Service under the OATT.
134. Taking the opposite view,
National Grid states that the
Commission should establish two
interconnection products for Small
Generating Facilities, arguing that
Energy Resource Interconnection
Service and Network Resource
Interconnection Service are just as
important for a Small Generating
Facility as they are for a Large
Generating Facility. National Grid states
that Network Resource Interconnection
Service has important market
implications for new resources, because
only generating facilities that meet this
interconnection standard should qualify
for installed capacity credits. It argues
that Small Generating Facilities should
have the option of being studied as
deliverable network resources so that
they may be eligible for such credits. If
the Commission does not mandate two
separate interconnection products for
Small Generating Facilities, National
Grid requests that, at a minimum, the
single interconnection product ensure
deliverability of generating facility
output, consistent with the
Commission’s ruling in New England
with respect to large generator
interconnections.59
135. NARUC asks the Commission to
remove the category ‘‘non-exporting
resource participating in a wholesale
market’’ from the Interconnection
Request. It notes that the
Interconnection Request instructs the
Interconnection Customer to declare its
intention to sell electricity at wholesale
in interstate commerce. However, the
phrase ‘‘non-exporting resource
participating in a wholesale market,’’
which is used nowhere else in the Small
Generator Interconnection NOPR, raises
unnecessary questions and extends its
reach far beyond its stated intention.
136. PacifiCorp states that none of
these service categories is defined in the
Proposed SGIP and that the significance
of each designation is unknown. It
argues that the different service options
must be defined in the SGIP and that the
additional information needed to permit
a Transmission Provider to conduct
studies must be provided. PacifiCorp
asks the Commission to explain the
significance of ‘‘Non-Exporting
Resource Participating in a Wholesale
Market’’ and ‘‘Other.’’ It adds that there
should be an opportunity for comment
on the workability of these proposals
and on what information a
59 New England Power Pool (New England), 109
FERC ¶ 61,155 at P 43–44 (2004).
PO 00000
Frm 00015
Fmt 4701
Sfmt 4700
34203
Transmission Provider may need to
provide this kind of interconnection
service.
137. SoCal Edison seeks clarification
that, to interconnect a Small Generating
Facility with a Distribution System, the
Transmission Provider must study
deliverability 60 on the system, even if
no delivery service is sought on either
the Transmission or Distribution
System. In studying distribution-level
interconnections, the Small Generating
Facility is assumed to be running at
maximum output and the power is
flowing onto the directly attached
distribution facility. SoCal Edison
argues that there is no way to study an
interconnection with the Distribution
System without assuming power flows
on that Distribution System.
138. SoCal Edison further argues that,
unlike an energy resource on a
Transmission System, the generator
cannot for safety and reliability reasons
opt to generate only when distribution
‘‘capacity’’ is available because the
characteristics of a Distribution System
(i.e., radial) differ from those of a
Transmission System (i.e., network).
Given how a Distribution System
operates, the provision of distribution
interconnection service in the absence
of a wholesale distribution service
request is a meaningless exercise, and
there are considerable efficiencies in
requesting and studying the two
services at the same time. Also, SoCal
Edison is concerned that some
Interconnection Customers may not
realize that a separate rate may be
charged to use the Distribution System
in addition to the Transmission System.
It states that the Commission should
clarify that both interconnection and
wholesale delivery service may be
required. Although SoCal Edison does
not believe that the Commission needs
to require that wholesale distribution
service and distribution-level
interconnection service be provided
only on a bundled basis, it asks the
Commission to permit ‘‘bundled’’
applications like those under SoCal
Edison’s Wholesale Distribution Access
Tariff.
Commission Conclusion
139. We clarify that the resource
options listed in the Small Generator
Interconnection NOPR’s Interconnection
Request are not interconnection service
options. Rather, they are merely the
possible ways the Interconnection
Customer may use its Small Generating
60 Deliverability refers to the ability of the electric
system to accept the Small Generating Facility’s
output without regard to the ultimate point of
delivery.
E:\FR\FM\13JNR2.SGM
13JNR2
34204
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Facility once delivery service begins.
The purpose of this information is to
give the Transmission Provider an early
indication of how the Small Generating
Facility is likely to operate. The one
interconnection service that the
Commission proposed to make available
to the Small Generating Facility is
similar to the Energy Resource
Interconnection Service that is offered
under the LGIA. Nevertheless, based on
the comments, we are concerned that
requesting service-related information
in the Interconnection Request could
lead to misunderstanding. Because the
information is related to the delivery
component of transmission service, not
interconnection service, it is not needed
in the SGIP’s Interconnection Request
form. Therefore, we are removing this
information from the Interconnection
Request. This should address the
concerns of most commenters.
140. In response to National Grid, we
note that the LGIA’s more expansive
Network Resource Interconnection
Service is intended to give the
Interconnection Customer broad access
to the backbone of the Transmission
Provider’s Transmission System. In
essence, it allows the generating facility
to pre-qualify as a Network Resource for
any Network Customer on the
Transmission System and, as National
Grid notes, may make it eligible for
installed capacity credits. Because
Network Resource Interconnection
Service entails high technical standards,
we expect that an Interconnection
Customer, particularly one
interconnecting at a lower voltage,
would rarely find this service to be
efficient or practical. Nevertheless, we
do not want to preclude it from
choosing this option. If it wishes to
interconnect its Small Generating
Facility using Network Resource
Interconnection Service, it may do so.
However, it must request
interconnection under the LGIP and
execute the LGIA.
141. In response to SoCal Edison’s
request for clarification, we note that the
SGIP lets the Transmission Provider
study the potential impacts of the
proposed interconnection on the
Distribution System. Also, we clarify
that nothing in this Final Rule (which
concerns interconnection service only)
prevents the Transmission Provider
from evaluating the Interconnection
Request and requests for wholesale
distribution service and transmission
delivery service simultaneously.
However, the Transmission Provider
may not require the Interconnection
Customer to request wholesale
distribution service or transmission
delivery service as a condition for
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
granting a request for interconnection
service. We expect the Transmission
Provider to explain to the
Interconnection Customer what delivery
services may be needed to meet its
needs.
142. Ministerial Changes to the
Interconnection Request—The Proposed
Interconnection Request was crafted
largely by Joint Commenters in response
to the ANOPR. It is similar in many
respects to the NARUC Model. Joint
Commenters in its supplemental
comments submitted ministerial
changes to the Proposed Interconnection
Request. Other commenters 61 also seek
changes to the Interconnection Request,
most reflecting misplaced or missing
technical information. The
Interconnection Request we adopt in
this Final Rule largely tracks the
NARUC Model version and also reflects
many of the changes proposed by the
commenters.
E. Issues Related to the SGIP
143. Using Voltage Level to Determine
Which Procedures Apply—The
Proposed SGIP divided Interconnection
Requests into two groups for initial
processing based on the voltage level of
the interconnection. Interconnections to
High-Voltage (at or above 69 kV) would
be evaluated using the interconnection
studies. Interconnection to Low-Voltage
(below 69 kV) would be processed
differently depending upon the size and
the certification status of the Small
Generating Facility as explained below.
An Interconnection Request for a
certified Small Generating Facility no
larger than 2 MW interconnecting at
Low-Voltage would be evaluated using
super-expedited screening criteria; an
Interconnection Request for a Small
Generating Facility no larger than 10
MW interconnecting at Low-Voltage
would be evaluated using expedited
screening criteria; and an
Interconnection Request for a Small
Generating Facility larger than 10 MW
but no larger than 20 MW
interconnecting at Low-Voltage would
be evaluated using the interconnection
studies. If an Interconnection Request
did not pass the super-expedited
screening criteria or expedited screening
criteria, it would be evaluated using
interconnection studies.
Comments
144. Several commenters 62 object to
using voltage level to distinguish which
61 E.g., Bureau of Reclamation, Central Maine,
Cummins, EEI, Joint Commenters, Northwestern
Energy, NYTO, PacifiCorp, PG&E, and Small
Generator Coalition.
62 E.g., CA ISO, EEI, Idaho Power, PG&E, PSE&G,
SoCal Edison, and Southern Company.
PO 00000
Frm 00016
Fmt 4701
Sfmt 4700
review process initially applies to an
Interconnection Request. They argue
that the distinction should be based on
whether the Small Generating Facility is
being interconnected with distribution
or transmission facilities. The decision
should be consistent with the physical
facilities and operational realities of the
electric system. They also contend that
electric system configurations vary
widely in terms of voltage levels and
that the effect of an interconnection is
not necessarily determined by voltage,
but also by location and size of the
Small Generating Facility. In addition,
they state that this distinction was not
a part of the ANOPR proposal and that
using voltage to distinguish which set of
procedures applies is confusing.
145. In its supplemental comments,
Joint Commenters propose using
whether the proposed interconnection is
with a transmission line (i.e.,
interconnections with transmission
lines may not be evaluated using the
technical screens) to determine whether
screens may be used to evaluate the
proposed interconnection.
Commission Conclusion
146. For the reasons given above, we
agree with commenters that
interconnection voltage should not be
used as a determinative factor for
whether the Interconnection Request
may be evaluated using the technical
screens. Instead, we are adopting the
technical screens proposed by Joint
Commenters in its supplemental
comments. The SGIP specifies that an
Interconnection Request for a certified
Small Generating Facility no larger than
2 MW shall be evaluated using the
technical screens, either under the Fast
Track Process or the 10 kW Inverter
Process, whichever applies. Under the
first provision of the screens, SGIP
section 2.2.1.1, the proposed Small
Generating Facility’s Point of
Interconnection must be on a portion of
the Transmission Provider’s
Distribution System that is subject to the
Tariff.63
147. Certification of the Small
Generating Facility (Proposed SGIP
Section 3.1)—In the Small Generator
Interconnection NOPR, the Commission
proposed that Interconnection Requests
for certified generators no larger than 2
63 As noted above, ‘‘transmission’’ is both an
engineering term of art and a term used in the FPA.
As used in the technical screens, ‘‘transmission’’ is
used in the engineering sense, not in a
jurisdictional sense. Likewise, references in other
technical screens to ‘‘radial distribution circuits,’’
‘‘3-phase primary distribution lines,’’ and other
uses of the word distribution are used in an
engineering sense, not in a jurisdictional sense. In
no case do we intend that this Final Rule applies
to non-Commission-jurisdictional facilities.
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
MW would be reviewed using the superexpedited screening criteria that
employed technical screens. The
Commission also noted that Joint
Commenters (in its response to the
ANOPR) preferred that the Commission
itself implement a single, uniform,
nationwide process for the certification
of Small Generating Facility equipment
packages no larger than 2 MW.64 The
Commission proposed, however, that
this function instead be performed by an
industry-recognized testing
organization. In addition, the
Commission requested comments as to
whether IEEE 1547 (Standard for
Interconnecting Distributed Resources
with Electric Power Systems), together
with other technical industry
documents, could be the basis for a
national certification standard.
Comments
148. Commenters generally agree with
the value of having a certification
process for Small Generating Facilities.
They believe that such a process can
speed interconnection and eliminate the
need to ‘‘reinvent the wheel’’ each time
an interconnection is made. In general,
commenters agree that IEEE 1547, in
conjunction with other standards, could
be the basis for a certification standard.
149. NYTO requests that the
Commission adopt the process and
registry proposal described in the
November 12, 2002 Joint Commenters
filing. That would have the Commission
maintain a list of certified equipment
and to centralize the registry function. It
claims that this would provide certainty
to the industry as to which equipment
has been certified and would avoid the
development of competing and
potentially inconsistent lists of certified
equipment, which could lead to
disputes and slow down the
interconnection process.
150. The NARUC Model certification
provision relies on Nationally
Recognized Testing Laboratories (NRTL)
to test and certify the safety of electrical
equipment used for the production of
electricity. That provision, which was
developed for use by state regulators,
requires that the NRTL be used by the
state regulatory authority or approved
by the U.S. Department of Energy.
151. American Forest and others state
that if the Commission chooses not to
certify and maintain a registry of
equipment, it should establish and
oversee a stakeholder process for the
64 A ‘‘certified’’ Small Generating Facility is one
that has been certified by a nationally recognized
laboratory before the Interconnection Request is
submitted to the Transmission Provider. Such a
facility is said to be ‘‘certified’’ for purposes of the
interconnection process.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
development of certification criteria.
Without the Commission’s involvement,
the process of establishing certification
standards will languish.
152. Cummins and others, however,
argue that a nationally recognized
testing laboratory and agencies like the
Department of Energy should oversee
the certification process. They also note
that a national testing laboratory, such
as Underwriter Laboratories, typically
not only tests and verifies the
performance of prototype equipment,
but also provides follow-up services to
verify that production equipment is
designed and manufactured to the same
standards as the tested equipment.
153. Ameren and others complain that
the NOPR does not explain what
industry operational and safety
standards are applicable. Likewise, the
NOPR does not specify what is needed
to qualify as a national testing
laboratory. They claim that leaving
these issues open could lead to
unnecessary or improper testing. They
recommend that the Commission (1)
adopt a specific set of standards for
operation and safety requirements that
are continually updated to meet current
safety and reliability requirements set
forth by NERC or the regional reliability
councils, and (2) maintain a list of
qualified national testing laboratories.
154. Allegheny Energy argues that
certification guarantees the safety and
reliability of the equipment in a standalone mode only, but not safety and
reliability when the equipment becomes
part of an integrated system.
155. Joint Commenters, in its
supplemental comments, proposes a
consensus equipment certification
provision that it states was developed
under a stakeholder process convened
by the U.S. Department of Energy’s
Office of Electric Transmission and
Distribution. The participants in the
process included Joint Commenter
members representing small generator
interests, state regulators, and
Transmission Providers, as well as
experts from the electrical equipment
manufacturing industry and testing
laboratories. Joint Commenters’
proposed certification provision
provides that Small Generating Facility
equipment shall be considered certified
if (1) it has been tested in accordance
with industry standards for continuous
utility interactive operation in
compliance with the appropriate codes
and standards by any NRTL recognized
by the United States Occupational
Safety and Health Administration to test
and certify interconnection equipment
pursuant to the relevant codes and
standards, (2) it has been labeled and is
publicly listed by such NRTL at the time
PO 00000
Frm 00017
Fmt 4701
Sfmt 4700
34205
the Interconnection Request is made,
and (3) such NRTL makes readily
available for verification all test
standards and procedures it utilized in
performing such equipment certification
and, with consumer approval, the test
data itself.
Commission Conclusion
156. We agree with Cummins that
nationally recognized laboratories
should oversee the certification process
and maintain registries of certified
equipment. A NRTL not only tests and
verifies the performance of prototypes,
but it provides follow-up services to
verify that production equipment is
designed and manufactured to the same
standards as the tested equipment. In
this Final Rule, we are adopting Joint
Commenters’ proposal. This
certification provision was vetted by a
diverse group of stakeholders and is
fundamentally consistent with the
Proposed SGIP as well as the provision
contained in the NARUC Model. We are
especially encouraged by the report
from Joint Commenters that one wellknown NRTL intends to begin the
certification of equipment as soon as the
summer of 2005. This should hasten the
development of certified Small
Generating Facilities no larger than 2
MW under the Fast Track and 10 kW
Inverter Processes. The certification
provision we adopt in this Final Rule is
contained in Attachments 3 and 4 of the
SGIP.
157. Finally, we acknowledge
Allegheny Energy’s concerns. Electric
system safety and reliability issues are
to be addressed when the proposed
interconnection of the certified
equipment is evaluated under the Fast
Track Process or the 10 kW Inverter
Process.
158. Super-Expedited Procedures
(Proposed SGIP Section 3) and
Expedited Procedures (Proposed SGIP
Section 4.3)65—In the NOPR, proposed
SGIP section 3 stated that if the
proposed Small Generating Facility is
certified, no larger than 2 MW, and the
interconnection is with Low-Voltage
facilities, the interconnection would be
evaluated using super-expedited
screens. Proposed SGIP section 4.3
stated that if the proposed Small
Generating Facility is no larger than 10
MW and the interconnection is with
Low-Voltage facilities, the
65 In the Small Generator Interconnection NOPR,
the term Super-Expedited Procedure referred to the
process that used the super-expedited screens and
Expedited Procedure referred to the process that
used the expedited screens. In this Final Rule, we
are adopting only one set of screens, which are used
in both the Fast Track Process and the 10 kW
Inverter Process.
E:\FR\FM\13JNR2.SGM
13JNR2
34206
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
interconnection would be evaluated
using expedited screens. Proposed SGIP
section 4.3 also provided that the
expedited screens would be used to
evaluate proposed interconnections that
failed the super-expedited screens.
159. The NOPR proposed that if the
Transmission Provider determines that
the proposed interconnection fails the
super-expedited screens and is not
satisfied that the Small Generating
Facility can be interconnected safely
and reliably, the Interconnection
Customer can pay for an additional
review. The review would not exceed
six hours and would determine whether
minor modifications to the
Transmission Provider’s electric system
(e.g., changing meters, fuses, relay
settings) could enable the
interconnection to be made safely and
reliably. If the results of the review were
positive and the Interconnection
Customer agreed to pay for these minor
modifications, the Transmission
Provider would tender an executable
SGIA to the Interconnection Customer.
Comments
160. Joint Commenters, Small
Generator Coalition, and NARUC
recommend that the Commission
require the use of screens to evaluate
Interconnection Requests. NARUC and
Small Generator Coalition initially
proposed using two sets of screens.
However, Joint Commenters (which
includes both NARUC and Small
Generator Coalition) now recommends
adopting a single set of screens that
serves the same purpose as the two
initially proposed.
161. Several commenters 66 asked that
the screens be clarified, modified, or
eliminated. EEI recommended that the
screens be available only for
interconnection with radial facilities.
162. Cinergy, EEI, Idaho Power,
NYTO, and others maintain that even if
the Small Generating Facility is certified
and passes the screens, there is no
assurance that safety and reliability or
the quality of service is not degraded as
a result of the interconnection. Cinergy
and EEI argue the rule should require a
showing that the interconnection does
not degrade safety and reliability.
163. BPA and Central Maine oppose
limiting the additional review to six
hours, arguing that each interconnection
is unique.
164. PJM argues that the Final Rule
should not allow screens to be used in
lieu of the feasibility study. It claims
66 E.g.,
ameren, BPA, Bureau of Reclamation,
Central Maine, Cinergy, EEI, Exelon, MISO, NRECA,
NYPSC, NYTO, PR&E, PJM, and Southern
Company.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
that while screens allow a project to be
expedited, they do not necessarily
provide the type of information needed
by the Interconnection Customer to
determine whether the project is viable
(e.g., information concerning the
estimated cost of interconnection or the
effects on other projects).
165. BPA claims that it is
unreasonable to hold the Transmission
Provider to stringent deadlines without
establishing corresponding deadlines for
the Interconnection Customer. MISO
and BPA contend that the timelines do
not give the Transmission Provider
sufficient time to review the
Interconnection Request. MISO
proposes that the Transmission Provider
be permitted to notify the
Interconnection Customer if it is unable
to meet the target date, along with the
reasons for delay.
166. NRECA and others ask the
Commission to reduce the maximum
size of a facility that may be evaluated
under the screens to as small as 3 kW.
In its supplemental comments, Small
Generator Coalition argues against
imposing any size limits.
167. Southern Company argues that
certain base case assumptions are
necessary for an accurate representation
of the electric system when an
Interconnection Request is evaluated
under screens. It would like the
evaluation to include all pending
higher-queued Interconnection Requests
because only then could the effect of an
Interconnection Request be truly
determined.
Commission Conclusion
168. In SGIP section 2.2.1, we are
adopting a single set of screens
submitted by Joint Commenters in its
supplemental comments, with minor
editorial changes. These are the screens
that would be applied in the Fast Track
and the 10 kW Inverter Processes. We
are adopting only one set of screens
rather than the two in the NARUC
Model and the Small Generator
Interconnection NOPR. The individual
screening criteria in this set are very
similar to those in the NARUC Model
and closely track both those contained
in the Small Generator Interconnection
NOPR and those proposed by Joint
Commenters in the ANOPR process.
169. The NOPR did not contain a
screen that would permit
interconnection with a secondary
network 67 and Joint Commenters were
67 A secondary network is a type of distribution
system that is generally used in large metropolitan
areas that are densely populated in order to provide
high reliability of service to multiple customers.
(Source: Standard Handbook for Electrical
PO 00000
Frm 00018
Fmt 4701
Sfmt 4700
unable to agree on one. We are also not
adopting any additional screen that
would permit interconnection with a
secondary network in this Final Rule.
170. We are deleting ‘‘and must
comply with all requirements of
approved industry standards for
interconnection technical specifications
and requirements’’ from one of Joint
Commenters’ proposed screens because
this language is redundant; a Small
Generating Facility that is being
evaluated under the Fast Track Process
or 10 kW Inverter Process must meet the
codes, standards, and certification
requirements of Attachments 3 and 4 of
the SGIP.
171. Concerns raised by commenters
that screens do not accurately reflect the
true effect of the interconnection on
safety and reliability are unfounded. We
believe the thresholds used in the
screens to be conservative and that there
is negligible chance that a proposed
interconnection could pass the screens
and actually impact the safety and
reliability of the Transmission
Provider’s electric system. These
thresholds have been vetted by
Transmission Providers, small generator
developers, and representatives of state
regulators alike.
172. We reject Small Generator
Coalition’s argument that there should
be no size restrictions for Small
Generating Facilities whose
interconnections may be evaluated
using the screens. We are retaining the
proposed 2 MW threshold for certified
generators as a critical eligibility
criterion for using the screens. It helps
ensure the safety and reliability of the
Transmission Provider’s electric system.
Small Generator Coalition, together with
a number of Transmission Providers and
representatives of state regulatory
agencies, vetted the threshold when
submitting the package of screens
through Joint Commenters’
supplemental comments.
173. In response to objections to the
NOPR’s expedited screening
procedures, the Final Rule SGIP does
not include any screens for Small
Generating Facilities larger than 2 MW.
Accordingly, only a request to
interconnect a certified Small
Generating Facility no larger than 2 MW
shall be evaluated using the screens. A
request to interconnect a Small
Generating Facility larger than 2 MW or
a Small Generating Facility of any size
that is not certified shall be evaluated
using the Study Process.
174. BPA and others oppose limiting
the additional review to six hours. We
Engineers, 11th edition, Donald Fink, McGraw Hill
Book Company).
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
are eliminating this restriction.68 The
SGIP includes a customer options
meeting where the Transmission
Provider may propose modifications to
the proposed interconnection or the
Small Generating Facility itself, or
perform a supplemental review if the
Interconnection Customer agrees to pay
for it. This allows the Transmission
Provider to determine the modifications
needed to accommodate the
interconnection without the need for
detailed and more costly
interconnection studies.
175. Southern Company and Joint
Commenters (in its supplemental
comments) argue that the Transmission
Provider should be allowed to consider
the effects of all pending higher-queued
Interconnection Requests when
evaluating the Interconnection Request
under the screens. We agree.
176. Queuing Priority (Proposed SGIP
Section 4.4)—In the NOPR, the
Commission proposed that each
Transmission Provider maintain a single
queue per geographic area. A queue lists
Interconnection Requests in the order in
which they are received. The Queue
Position determines the order of
performing interconnection studies, if
required, and the Interconnection
Customer’s cost responsibility for any
Upgrades to the Transmission Provider’s
electric system. In Order No. 2003, the
Commission decided that the
Transmission Provider should maintain
a single integrated queue per geographic
region. However, RTOs and ISOs have
flexibility to propose queues and
queuing rules designed to meet their
regional needs.69 We are adopting the
same provision here, for the same
reasons. Accordingly, there is no need
to separately address again the same
comments raised in this proceeding on
that issue.
Comments
177. Small Generator Coalition
requests that the Commission establish
separate queues for Large and Small
Generating Facilities. Failing that, the
Commission should clarify that the
interconnection study periods identified
in the SGIP are binding without regard
to the Queue Position of other
generating facilities. Alternatively,
Small Generating Facilities should be
clustered for study purposes within a
given time frame (e.g., 90 days). It states
that requiring a single queue for all
generating facilities undercuts whatever
progress has been made in
68 In the Proposed SGIP, the Commission termed
this ‘‘additional review.’’ In the SGIP, we adopt the
NARUC Model’s term ‘‘supplemental review.’’
69 Order No. 2003 at P 147.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
interconnecting Small Generator
Facilities. Small Generator Coalition,
Solar Turbines, and others state that, in
light of their relatively simple
interconnection requirements, use of
off-the-shelf equipment, and minimal
effects on the Transmission Provider’s
electric system, Small Generating
Facilities should be able to be
interconnected quickly. They complain
that the interconnection can be delayed
by higher-queued Large Generating
Facilities that require longer, more
frequent, and more expensive
interconnection studies and restudies.
Commission Conclusion
178. We disagree with Small
Generator Coalition that a single queue
is unfavorable to Small Generating
Facilities. Although Queue Position
determines the order of the
interconnection studies and the cost
responsibility for the Network Upgrades
necessary to accommodate the
interconnection, it does not determine
the order in which the interconnections
are completed.
179. For many Transmission
Providers, the requirement to maintain
two queues could actually delay, rather
than speed up, the interconnection
process. Thus, we are requiring a
Transmission Provider to use a single
queue for all Generating Facilities,
regardless of size. Also, the SGIP allows
Small Generating Facilities to be
interconnected without going through
the Study Process if they pass the
screens. However, under the
independent entity variation available
to RTOs and ISOs under this Final Rule,
such entities may propose multiple
queues in their compliance filings.70
180. Small Generator Coalition is
correct that a non-clustering
Transmission Provider must meet all
deadlines established in the SGIP
without regard to queue position or
queue-related delays.
181. We reiterate that clustering is the
Commission’s preferred method for
conducting interconnection studies, and
should be seriously considered by all
Transmission Providers.71 Clustering of
studies allows the Transmission
Provider to study multiple
Interconnection Requests
simultaneously, thereby maximizing the
effectiveness of its staff. Clustering may
also reduce interconnection study and
Upgrade costs; for example, multiple
Interconnection Customers can share
the cost of Upgrades.
182. Scoping Meeting (Proposed SGIP
Section 4.5)—Proposed SGIP section 4.5
PO 00000
Order No. 2003 at P 185.
at P 155.
would require the Parties to hold a
scoping meeting within ten Business
Days after the Interconnection Request
is deemed complete by the
Transmission Provider. The purpose of
the meeting is to review the
characteristics of the Transmission
Provider’s electric system, discuss the
technical aspects of the proposed
interconnection, and review existing
studies and the results of the
application of the technical screens, if
applicable. If the Parties agree that a
feasibility study is needed, the
Transmission Provider would provide
the Interconnection Customer with a
feasibility study agreement.
Comments
183. Central Maine asks that the
Transmission Owner also be included in
the scoping meeting. Small Generator
Coalition asks that the provision be
revised to allow the Parties to conduct
the scoping meeting by telephone.
Commission Conclusion
184. In the SGIP, Transmission
Provider is defined to include both the
Transmission Provider and
Transmission Owner, when they are
separate entities. Accordingly, the
Transmission Owner may attend the
scoping meeting. Also, there was
nothing in the Proposed SGIP that
mandates that the scoping meeting be
held face-to-face. We encourage the
Parties to conduct the interconnection
process in the most expeditious manner
possible and to take advantage of
telephone, fax, and e-mail. Finally, as in
Order No. 2003–A, we are requiring that
any scoping meeting between the
Transmission Provider and an affiliate
be announced publicly and transcribed,
with the transcripts made available
upon request for a period of three
years.72 While the Transmission
Provider may redact portions of the
transcripts deemed to be commercially
sensitive or containing Critical Energy
Infrastructure Information, the
Commission will decide which redacted
portions are to be made public.
185. Interconnection Studies
(Proposed SGIP Sections 4.6, 4.7, and
4.8)—Proposed SGIP sections 4.6, 4.7,
and 4.8 and the associated study
agreements described the feasibility,
system impact, and facilities studies
(collectively, interconnection studies)
and the Interconnection Customer’s cost
responsibility for each study. For a
Small Generating Facility larger than 2
MW but no larger than 10 MW
interconnecting at Low-Voltage, the
Proposed SGIP would first evaluate the
70 See
71 Id.
Frm 00019
Fmt 4701
Sfmt 4700
34207
72 Order
E:\FR\FM\13JNR2.SGM
No. 2003–A at P 101–107.
13JNR2
34208
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
proposed interconnection using
expedited screens. However, if the
Transmission Provider believed that the
interconnection would undermine
safety and reliability even though the
proposed interconnection passed the
screens, the Transmission Provider
would pay for the feasibility study if
that study subsequently identified no
adverse system impact. The cost of the
system impact and facilities studies,
however, would always be paid by the
Interconnection Customer.
Comments—Study Cost Obligations
186. Central Maine, Exelon, and
PacifiCorp argue that the
Interconnection Customer should
always pay for interconnection studies,
regardless of the conclusions reached.
Small Generator Coalition maintains
that the Transmission Provider should
pay for the feasibility study only if it
shows no adverse impact.
Commission Conclusion
187. The Interconnection Customer
should pay for all of the interconnection
studies, regardless of the conclusions
reached, because it is unreasonable to
shift this cost to other transmission
customers that do not benefit from the
studies, which is what would occur if
the Transmission Provider were to pay
for them. The Transmission Provider
should, of course, use existing studies
instead of performing additional
analyses to reduce costs for the
Interconnection Customer, whenever
possible. The Interconnection Customer
is not to be charged for such existing
studies; however, it is responsible for
costs associated with any new study and
any modification to an existing study
that is reasonably necessary to evaluate
the proposed interconnection.
Comments—Study Requirements
188. PJM and Southern Company
argue that a system impact study should
always be performed to detect adverse
impacts that may not have been
detected in the feasibility study. Small
Generator Coalition argues that in many
situations only a feasibility study or a
system impact study is needed, but not
both; Parties should be able to agree to
skip the feasibility study. PacifiCorp
states that, for a small project, the
feasibility study is not much different
from the system impact study and
recommends that the former be
eliminated. SoCal Edison argues that the
provisions of the SGIP dealing with
interconnection studies should refer to
the distribution provider, if applicable,
and the Transmission Provider. Bureau
of Reclamation asks the Commission to
clarify that the Transmission Provider
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
should perform flicker and voltage drop
studies.
Commission Conclusion
189. We agree that, on occasion, there
may be some overlap between the
feasibility study and the system impact
study. For a small project, the
distinction may not be enough to
require that both studies be performed.
In such cases, it may be reasonable to
skip the feasibility study entirely.
Therefore, as the Commission did for
Large Generating Facilities in Order No.
2003–A, we are allowing the Parties to
skip the feasibility study upon mutual
agreement. As to SoCal Edison’s
comment, we do not see any need to
include the term ‘‘distribution provider’’
when referring to SGIP provisions.
Transmission Provider is already
defined as ‘‘[t]he public utility (or its
designated agent) that owns, controls, or
operates transmission or distribution
facilities used for the transmission of
electricity in interstate commerce and
provides transmission service under the
Tariff.’’ As to Bureau of Reclamation’s
request for clarification, voltage drop,
voltage limit violation, and grounding
studies are indeed included in the study
process.
Comments—Study Deadlines and
Restudy
190. Southern Company, PG&E, and
others contend that the proposed
interconnection study deadlines are too
short. NARUC proposes giving the
Transmission Provider 30 Business Days
to complete the feasibility study, 30
Business Days to complete the
distribution system impact study, 45
Business Days to complete the
transmission system impact study, 30
Business Days to complete the facilities
study when no Upgrades are required,
and 45 Business Days to complete the
facilities study when Upgrades are
required.
191. PacifiCorp states that a restudy
provision should be included in the
SGIP so that the Interconnection
Request could be restudied if a higherqueued Interconnection Customer drops
out. It argues that the LGIP included a
restudy provision for each of the three
studies.
Commission Conclusion
192. We are adopting the deadlines
proposed by NARUC and incorporating
them in the interconnection study
agreements. They strike a good balance,
allowing sufficient time to complete the
studies while ensuring that Small
Generating Facilities can be
interconnected within a reasonable
time. Also, as noted above, with the
PO 00000
Frm 00020
Fmt 4701
Sfmt 4700
exception of payment provisions, we are
replacing ‘‘calendar days’’ with
‘‘Business Days’’ in the SGIP and SGIA.
However, where appropriate, we are
revising the number of days to
correspond to the actual passage of time.
193. We disagree that a restudy
provision is needed in the SGIP. The
very purpose of the Small Generator
Final Rule is to expedite
interconnections of Small Generating
Facilities by removing unnecessary
delays. While a restudy provision in the
LGIP context is meaningful because
system conditions may change between
completion of a particular study and the
Parties’ signing the LGIA, it is unlikely
that any significant change in system
conditions will occur that was not
foreseen by the Transmission Provider
at the time of study because the SGIP
has a much shorter timeline.
Comments—Post-Operational
Evaluation of the Interconnection
194. PacifiCorp argues that, after the
Small Generating Facility is operational,
an interconnection may cause problems
that were unforeseen when the project
was initially evaluated. For example,
wind generators may need to fine tune
their reactive power output. Also,
because the certification and screening
processes are new, the Transmission
Provider should be permitted to perform
post-interconnection reviews and
adjustments, including additional
Upgrades, if necessary, to be paid for by
the Interconnection Customer.
Commission Conclusion
195. The purpose of the evaluation
processes in the SGIP is to determine
the effect the interconnection will have
on the Transmission Provider’s electric
system. Such evaluations are also
performed to ascertain the
Interconnection Customer’s cost
responsibility for Interconnection
Facilities and Upgrades. We reject
PacifiCorp’s proposal because accepting
it would make determination of cost
responsibility open-ended and create
uncertainty for the Interconnection
Customer. Should unforeseen problems
arise, the Parties may make a filing with
the Commission and request expedited
consideration.
196. Execution of the SGIA—
Although the Proposed SGIP required
the Transmission Provider to deliver an
executable SGIA to the Interconnection
Customer within a time certain, the
Interconnection Customer had no
deadline to sign and return the
document to the Transmission Provider.
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Comment
197. In its supplemental comments,
Joint Commenters propose that the
Interconnection Customer have 30
Business Days to sign and return the
SGIA.
Commission Conclusion
198. We adopt Joint Commenters’
proposal. The Transmission Provider
needs to know whether the proposed
project will go forward. Giving the
Interconnection Customer a deadline
within which to act gives the
Transmission Provider the certainty it
needs for system planning purposes.
The SGIP states that, after receiving an
interconnection agreement from the
Transmission Provider, the
Interconnection Customer shall have 30
Business Days or another mutually
agreeable timeframe to sign and return
the SGIA, or request that the
Transmission Provider file an
unexecuted SGIA with the Commission.
If that is not done, the Interconnection
Request shall be deemed withdrawn.
F. Issues Related to the SGIA
199. Responsibilities of the Parties
(Proposed SGIA Article 2.2)—Article 2.2
of the Proposed SGIA set out each
Party’s responsibilities under the SGIA.
It included the obligation of the
Interconnection Customer to
interconnect, operate, and construct its
facilities in a safe manner and to follow
Good Utility Practice. It would similarly
require the Transmission Provider to
operate its electric system in a safe and
reliable manner.
Comments
200. BPA asserts that Proposed SGIA
article 2.2 should require the
Interconnection Customer to abide by
national and regional reliability rules,
such as those developed by NERC and
the Western Electricity Coordinating
Council, that are generally applicable to
all generators in a control area or
geographic region. Furthermore,
according to BPA, the interconnection
agreement should require the
Interconnection Customer to abide by
any technical requirements established
by the Transmission Provider to govern
the safe interconnection of generating
facilities.
201. NARUC offers alternative
language laying out the responsibilities
of the Parties, consistent with its Model.
Specifically, NARUC proposes replacing
article 2.2 with the following:
Each Party will, at its own cost and
expense, operate, maintain, repair, and
inspect, and shall be fully responsible for the
facility or facilities which it now or hereafter
may own or lease unless otherwise specified
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
in Exhibit A. Maintenance of Interconnection
Customer’s Small Resource and
interconnection facilities shall be performed
in accordance with the applicable
manufacturer’s recommended maintenance
schedule.
The Parties agree to cause their facilities or
systems to be constructed in accordance with
specifications provided by the National
Electrical Safety Code, the National Electric
Code, and as approved by the American
National Standards Institute, and
interconnected in accordance with the
Institute of Electrical and Electronics
Engineers standards where applicable.
Interconnection Provider and
Interconnection Customer shall each be
responsible for the safe installation,
maintenance, repair and condition of their
respective lines and appurtenances on their
respective sides of the Point Of Common
Coupling. The Interconnection Provider or
the Interconnection Customer, as
appropriate, shall provide interconnection
facilities that adequately protect the
Interconnection Provider’s distribution
system, personnel, and other persons from
damage and injury. The allocation of
responsibility for the design, installation,
operation, maintenance and ownership of the
Interconnection Facilities shall be made part
of this agreement as Exhibit C.
202. Avista states that ‘‘the
Interconnection Customer should be
required not only to construct its
generating facility in accordance with
operating requirements to be set forth in
Appendix 4 to the Proposed SGIA, but
also to maintain and operate its [Small
Generating Facility] in accordance with
such operating requirements.’’ 73
203. Nevada Power asserts that the
IEEE 1547 standards referred to in
Proposed SGIA article 2.2.4 were never
designed to be applied to generating
facilities larger than 10 MW and that in
fact ‘‘there is no extant national
standard that can be reasonably applied
to govern the Interconnection Facilities
for Generating Facilities greater than ten
megawatts.’’ 74 Instead, Nevada Power
proposes that until a national standard
is developed to address this 10–20
megawatt gap, the Commission modify
article 2.2.4 to read:
Interconnection Customer agrees to cause
its facilities or systems to be constructed in
accordance with applicable specifications
that meet or exceed those provided by the
National Electrical Safety Code, the
American National Standards Institute, IEEE,
Underwriter’s Laboratory, Operating
Requirements, and, where the Generating
Facility will have a capacity greater than ten
megawatts, the Transmission Provider’s
applicable Interconnection Facility standards
in effect at the time of construction * * *.[75]
73 Avista
at 14.
Power at 15.
204. PacifiCorp notes that the
Proposed SGIA assumes that the
Interconnection Customer and the
Transmission Provider are each
responsible for the maintenance of
equipment on its side of the point of
change of ownership. But as a practical
matter, more flexibility is needed
because non-utility companies cannot
usually maintain certain equipment,
such as communications equipment,
that is critical to the protection of the
Transmission Provider’s electric system.
Moreover, the Transmission Provider
often owns and maintains revenue
meters on the customer’s side of the
point of change of ownership.
Therefore, argues PacifiCorp, the SGIA
should clarify that unless provided
otherwise in an attachment, each Party
is responsible for the equipment on its
side of the point of change of
ownership.
205. Small Generator Coalition
requests that the Commission restrict
the ability of the Transmission Provider
to impose additional technical
requirements on the Small Generating
Facility. Otherwise, it fears that
Interconnection Customers will be
subjected to additional requirements
under the guise of reliability rules that
make it difficult to interconnect in a
cost-effective manner. On the other
hand, Southern Company contends that
the standards for operating in parallel
should be codified in the SGIA. This
way, the Transmission Provider can
then confirm that all the requirements
are met before granting the
authorization to operate.
206. In its supplemental comments,
Joint Commenters recommends several
changes to Proposed SGIA article 2.2.
Specifically, Joint Commenters
recommend clarifying that the
Transmission Provider must coordinate
with an Affected System operator to
complete the interconnection, but need
not negotiate on behalf of the
Interconnection Customer. Joint
Commenters also propose changing the
last sentence of proposed article 2.2.4 to
read:
Interconnection Customer agrees to design,
install, maintain, and operate, or cause the
design, installation, maintenance, and
operation of the Generating Facility and
Interconnection Customer Interconnection
Facility so as to reasonably minimize the
likelihood of a disturbance, originating on
such equipment affecting or impairing the
system or equipment of Transmission
Provider, or Affected Systems.76
74 Nevada
75 Id. (Emphasis added to show the new language
proposed by Nevada Power.)
PO 00000
Frm 00021
Fmt 4701
Sfmt 4700
34209
76 Emphasis added to show the language
proposed by the Joint Commenters.
E:\FR\FM\13JNR2.SGM
13JNR2
34210
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Commission Conclusion
207. We are adopting a version of this
provision that is based on the NARUC
Model and Joint Commenters’
proposals. Redrafting article 2.2 as
requested by commenters clarifies the
rights and responsibilities of the Parties
and aids them in better understanding
their roles in the interconnection
process.
208. Several commenters also ask the
Commission to clarify the right of the
Transmission Provider to include
supplemental ‘‘Interconnection
Guidelines,’’ either in the SGIA or as an
attachment to it. As the Commission
stated in Order No. 2003-A, the
Transmission Provider may include
supplemental interconnection
requirements if (1) they are authorized
by the applicable reliability council and
(2) the Transmission Provider imposes
such requirements on itself and all other
Interconnection Customers, including
its affiliates.77 We see no reason to
depart from this standard. The
Commission has consistently held that
an Interconnection Customer must
adhere to established reliability
practices within the control area with
which it is interconnecting.78 The same
would be true for including
supplemental guidelines for generators
larger than 10 MW, as requested by
Nevada Power.
209. In response to Nevada Power’s
comments about the applicability of the
IEEE 1547 standard to generating
facilities no larger than 10 MW, we note
that the SGIA states that this standard
is required only ‘‘where applicable.’’
210. The SGIA also addresses
PacifiCorp’s concerns over using the
point of change of ownership as the
basis for establishing the Parties’
respective roles and allows the Parties
to specify their respective roles in SGIA
Attachment 2.
211. Metering (Proposed SGIA Article
2.4)—Proposed SGIA article 2.4 would
specify that the Interconnection
Customer is responsible for the
Transmission Provider’s reasonable cost
for the purchase, installation, operation,
maintenance, testing, repair, and
replacement of any metering and data
acquisition equipment. It also would
require that the Interconnection
Customer’s metering equipment
conform to applicable industry rules
and operating requirements.
Comment
212. CA ISO argues that Proposed
SGIA article 2.4 should require any
77 Order
No. 2003–A at P 399.
e.g., Order No. 2003-A at P 44, Order No.
2003 at P 823, and Order No. 888 at 31,770.
78 See,
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
Small Generating Facility larger than 1
MW to provide real-time telemetry to
the Transmission Provider to better
maintain reliability and meet regional
requirements.
Commission Conclusion
213. We are not requiring Small
Generating Facilities to provide realtime telemetry because doing so may
hamper their development and we are
not convinced that it is necessary in
every instance. However, if regional
reliability requirements dictate real-time
telemetry for Small Generating
Facilities, we expect the Interconnection
Customer to meet such requirements.
214. Equipment Testing and
Inspection (Proposed SGIA Article
3.1)—Proposed SGIA article 3.1
described the pre-operational testing
and inspection requirements for the
Small Generating Facility.
Comments
215. Central Maine argues that the
Interconnection Customer should
periodically test the Small Generating
Facility and Interconnection Facilities
after they achieve commercial operation
and that the Transmission Provider
should be allowed to witness such
testing. The purpose of such testing is
to ensure that the Interconnection
Customer’s equipment is operating
properly. Southern Company argues that
the Interconnection Customer should
pay the Transmission Provider’s
expenses for such pre-operational
testing.
Commission Conclusion
216. We decline to expand the
provisions of this article to require
generically that every Interconnection
Customer perform periodic testing of its
Small Generating Facility, regardless of
circumstances. To so do would be
burdensome on the Interconnection
Customer, costly, and potentially allow
a self-interested Transmission Provider
to impose multiple rounds of costly
testing on competing generators.
However, should the Transmission
Provider believe in good faith that the
Small Generating Facility or the
Interconnection Facilities is affecting
safety and reliability, the Transmission
Provider may, upon advance written
notice, require the Interconnection
Customer to perform reasonable
additional post-operational testing. The
Transmission Provider may witness
such testing. The Transmission Provider
and the Interconnection Customer shall
be responsible for their own staff,
equipment, and other costs associated
with the testing and inspection.
PO 00000
Frm 00022
Fmt 4701
Sfmt 4700
217. Right of Access (Proposed SGIA
Article 3.3)—The Proposed SGIA would
give the Transmission Provider access to
land owned or controlled by the
Interconnection Customer to construct
Interconnection Facilities or for other
specified purposes.
Comment
218. NARUC urges the Commission to
adopt the following right of access
provision from its Model:
Upon reasonable notice, the
Interconnection Provider may send a
qualified person to the premises of the
Interconnection Customer at or immediately
before the time the Small Resource first
produces energy to inspect the
interconnection, and observe the
commissioning of the Small Resource
(including any required testing), startup, and
operation for a period of up to no more than
three days after initial start-up of the unit. In
addition, the Interconnection Customer shall
notify the Interconnection Provider at least
seven days before conducting any on-site
Verification Testing of the Small Resource.
Following the initial inspection process
described above, at reasonable hours, and
upon reasonable notice, or at any time
without notice in the event of an emergency
or hazardous condition, Interconnection
Provider shall have access to Interconnection
Customer’s premises for any reasonable
purpose in connection with the performance
of the obligations imposed on it by this
Agreement or if necessary to meet its legal
obligation to provide service to its
[customers].
Commission Conclusion
219. We largely adopt NARUC’s
proposal. It uses the concepts found in
the Small Generator Interconnection
NOPR, but shortens and simplifies the
provisions. However, we are adding that
each Party is responsible for its own
staff, equipment, and other costs in
carrying out this provision.
220. Term of Agreement (Proposed
SGIA Article 4.2)—Proposed SGIA
article 4.2 would require that the
interconnection agreement remain in
effect for ten years, or longer by request,
and that it can be automatically
renewed for each successive one year
period thereafter.
Comments
221. BPA argues that the
interconnection agreement should
remain in effect as long as the Small
Generating Facility remains
interconnected, subject to the
termination provision of the SGIA or as
agreed to by the Parties. The article
unnecessarily requires the Parties to
negotiate a follow-on agreement after
ten years.
222. Central Maine requests that the
SGIA terminate after a set number of
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
years agreed to by the Parties. It states
that the provision is unacceptable
because it allows the Interconnection
Customer to unilaterally select the term
of the interconnection agreement.
Commission Conclusion
223. We deny BPA’s and Central
Maine’s requests to revise the term of
the interconnection agreement. These
issues were addressed in Order No.
2003, and neither commenter raises any
new arguments here.79
224. Termination (Proposed SGIA
Article 4.3) and Default (Proposed SGIA
Article 6.17)—Proposed article 4.3.1
would grant the Interconnection
Customer the right to terminate the
SGIA at any time by giving 30 days
written notice. Proposed article 4.3.2
would allow the Transmission Provider
to terminate the interconnection
agreement if a material change in law or
regulations would either prevent
performance of the interconnection
agreement or impose on the
Transmission Provider substantial
additional costs that are not reimbursed
by another entity. Proposed article 6.17
described when a Default takes place
and the Parties’ right to cure upon
notice of a Default. Because these
provisions are closely related, we
discuss them together.
Comments
225. Several commenters ask the
Commission to grant the Transmission
Provider termination rights comparable
to those given the Interconnection
Customer.80 PG&E and Southern
Company request that the Transmission
Provider have the right to terminate the
interconnection agreement if the Small
Generating Facility is either shut down
or abandoned. Southern Company asks
that the Transmission Provider be
allowed to terminate the agreement if
the Small Generating Facility either
does not begin commercial operation or
is inactive for three years. Absent
changes to this provision, the only
remedy available to the Transmission
Provider is to file an application to
terminate with the Commission.
226. Central Maine, Joint
Commenters, and PacifiCorp ask that if
the Interconnection Customer
terminates the SGIA, neither the
Transmission Provider nor its customers
should have to pay the costs of
termination, including the cost of site
restoration. Central Maine says these
costs should be paid by the
Interconnection Customer if it defaults
79 Order
No. 2003 at P 302–304.
e.g., BPA, Central Maine, PG&E, and
Southern Company.
on the interconnection agreement.
PacifiCorp requests that the SGIA
require the Interconnection Customer to
pay any outstanding costs under the
SGIP or SGIA during the 30 day notice
period, or else termination shall not
become effective. Joint Commenters also
propose including a provision
specifying that a Party remains liable for
expenses incurred under the SGIA even
after it has terminated. Central Maine
states that certain critical provisions,
such as access, confidentiality,
invoicing, limitation of liability, and
indemnification, should survive any
expiration or earlier termination of an
agreement.
227. NARUC urges the Commission to
adopt its Model interconnection
agreement, which allows the
Interconnection Customer to terminate
the agreement for any reason, including
default, provided 60 days’ written
notice is given. Alternatively, the
Transmission Provider may terminate
the agreement if the Small Generating
Facility does not generate energy in
parallel with the Transmission
Provider’s Transmission System by the
later of two years from the date of the
agreement or 12 months after
interconnection is completed.
228. NARUC also requests
clarification that the Transmission
Provider may terminate the
interconnection agreement for Default.
Both NARUC and Joint Commenters
propose adding a provision specifying
that a Transmission Provider may
terminate the SGIA if there is a material
change in a rule or statute concerning
interconnection and parallel operation
of the Small Generating Facility that
would impose additional costs on the
Transmission Provider. Finally, the
NARUC Model clarifies that termination
does not relieve either Party of its
obligations to the other Party.
229. Central Maine and NYTO ask the
Commission to clarify the difference
between ‘‘Default’’ and ‘‘Breach,’’ as it
did in the LGIA. Specifically, Central
Maine states that a Breach, if uncured,
becomes a Default and may result in
termination.
Commission Conclusion
230. As Order No. 2003 stated, there
is no reason to allow the Transmission
Provider to terminate the
interconnection agreement if the
Interconnection Customer has met all its
obligations.81 As we have noted
elsewhere in this Final Rule, the
interests of a Transmission Provider
may be adverse to those of the
Interconnection Customer, and it has an
80 See,
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
81 Order
PO 00000
No. 2003 at P 313.
Frm 00023
Fmt 4701
Sfmt 4700
34211
incentive to discriminate against the
Interconnection Customer. The
Interconnection Customer’s business
decision not to operate its Small
Generating Facility for an extended
period of time should not result in the
loss of its rights under the SGIA.
231. We adopt NARUC’s proposal that
a Party be given 60 calendar days in
which to cure a Default once notified
that it is in Default. If at the end of the
60 calendar days, the Default continues
to exist, the non-defaulting Party may
terminate the interconnection
agreement. This is consistent with the
Commission’s regulations that require
an entity to notify the Commission of
the proposed cancellation or
termination of a contract at least 60
calendar days before the cancellation or
termination is proposed to take effect.
However, to allow for situations where
60 calendar days are not sufficient time
to cure the default, the SGIA allows up
to six months in which to cure the
Default so long as the Party
‘‘continuously and diligently’’ works
towards curing the Default.
232. Joint Commenters and Central
Maine propose provisions that address
the cost responsibility of the Parties if
the SGIA is terminated. Both the
Termination and Default provisions
now clarify that the Parties’ financial
obligations and other responsibilities
survive the termination of the SGIA.
The SGIA also addresses PacifiCorp’s
concern that the Interconnection
Customer would be able to terminate the
interconnection agreement and escape
financial responsibility for costs it has
already incurred.
233. The Proposed SGIA included a
provision allowing the Transmission
Provider to terminate the SGIA should
there be a regulatory change that would
impose additional costs on the
Transmission Provider. Consistent with
the LGIA, we are not including such a
provision in the SGIA. Should a
significant regulatory change take place,
the Transmission Provider may request
termination of the interconnection
agreement under section 205 of the FPA.
234. Central Maine and NYTO are
correct that the term ‘‘breach’’ does not
appear in the SGIA. Upon discovering a
Default, the non-defaulting Party gives
notice of the Default to the defaulting
Party. The defaulting Party then has
time to cure the Default. If it does not
do so, the SGIA may then be terminated.
We are revising the SGIA accordingly.
235. Emergency Conditions (Proposed
SGIA Article 4.4.1)—Proposed SGIA
article 4.4.1 would give the
Transmission Provider the right to
immediately suspend interconnection
service and temporarily disconnect the
E:\FR\FM\13JNR2.SGM
13JNR2
34212
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Small Generating Facility under
Emergency Conditions.
Comment
236. SoCal Edison proposes adding
the term ‘‘Distribution Provider’s
Distribution System’’ to each place
where the definition of Emergency
Condition says ‘‘Transmission
Provider’s Transmission System.’’ 82
Commission Conclusion
237. The owner of the Commissionjurisdictional facility with which the
Interconnection Customer interconnects
is the ‘‘Transmission Provider’’
regardless of how the facility may be
classified by the Transmission Provider.
As defined by this Final Rule,
‘‘Transmission Provider’’ means ‘‘the
public utility * * * that owns, controls,
or operates transmission or distribution
facilities used for the transmission of
electricity in interstate commerce and
provides transmission service under the
Tariff’’ (emphasis added). The change
suggested by SoCal Edison would be
redundant.83
238. Temporary Disconnection—
Routine Maintenance, Construction, and
Repair (Proposed SGIA Article 4.4.2)
and Forced Outages (Proposed SGIA
Article 4.4.3)—Proposed SGIA article
4.4.2 would require that the
Transmission Provider give five
Business Days’ notice before
interrupting interconnection service,
curtailing the output of the Small
Generating Facility, or temporarily
disconnecting the Small Generating
Facility for routine maintenance,
construction, and repairs. Proposed
SGIA article 4.4.3 would give the
Transmission Provider the right to
suspend interconnection service to
make repairs during forced outages. It
would also require the Transmission
Provider to give the Interconnection
Customer written documentation to
explain the circumstances of the
disconnection if prior notice was not
given. Both provisions would require
the Transmission Provider to use its best
efforts to coordinate disconnections,
curtailments, and forced outages with
the Interconnection Customer.
Comments
239. PG&E states that it has thousands
of small solar projects interconnected
with its ‘‘Distribution System’’ and
82 SoCal Edison does not give any rationale for its
proposed change, only modified tariff sheets.
83 If the Small Generatiing Facility is
interconntected with nonjurisdictional lines, then
this Final Rule does not reach the issue of whether
a jurisdictional Transmission Provider may
disconnect the Small Generating Facility in an
emergency. The Transmission Provider would have
to deal with the non-jurisdictional utility.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
requests that the five Business Day
notice requirement be waived for
distribution level generators because it
would interfere with a Distribution
System owner’s ability to work on its
facilities.
240. Empire District argues that it
should not take five days to shut down
a Small Generating Facility. If some
minimum notice is required, it should
apply only to Small Generating
Facilities larger than 2 MW. Empire
District also questions the need for an
‘‘individual notice’’ to every generator
and whether it is really necessary to
notify the operators of small certified
units under 100 kW in size. If
individual notifications are required,
the Interconnection Customer should
have a method in place whereby ‘‘nearly
instantaneous, two-way
communication’’ (notification and
verification of receipt of notice) can be
made within 24 hours.
241. EEI, PacifiCorp, and Southern
Company ask that the term ‘‘reasonable
efforts’’ be used instead of ‘‘best efforts’’
in Proposed SGIA articles 4.4.2 and
4.4.3, noting that ‘‘reasonable efforts’’
was used in the ANOPR consensus
document.
242. EEI and PacifiCorp ask the
Commission to clarify that the
Transmission Provider must provide
written documentation to the
Interconnection Customer only when
the latter requests it.
Commission Conclusion
243. We are not convinced that a five
Business Day notice is unduly
burdensome to the Transmission
Provider or that it should apply only to
Small Generating Facilities larger than 2
MW. Even if PG&E has thousands of
small solar projects interconnected with
its Distribution System subject to an
OATT, as it states, it is highly unlikely
that it will ever have to provide notice
to all of them simultaneously.
244. We agree that the term
‘‘reasonable efforts’’ should be used
instead of ‘‘best efforts’’ in the SGIA. We
are making this change throughout the
SGIA.
245. Finally, we are persuaded that
written documentation need be
provided only upon request by the
Interconnection Customer, and the SGIA
reflects this change.
246. Temporary Disconnection—
Adverse Operating Effects (Proposed
SGIA Article 4.4.4)—Proposed SGIA
article 4.4.4 said that after being notified
that its Small Generating Facility may
degrade the reliability of the
Transmission Provider’s electric system,
the Interconnection Customer must be
given reasonable time to make necessary
PO 00000
Frm 00024
Fmt 4701
Sfmt 4700
corrections. If it does not make the
corrections within that time, the
Transmission Provider must provide a
second notice to the Interconnection
Customer stating that the Small
Generating Facility may be
disconnected in five Business Days.
Comments
247. Several commenters 84 contend
that the five day notice period is
unreasonable, restricts the Transmission
Provider’s ability to respond to
reliability concerns, and could be
misinterpreted to mean that an
Interconnection Customer whose Small
Generating Facility is causing adverse
operating conditions has priority over
other customers.
248. EEI recommends that the last
sentence of Proposed SGIA article 4.4.4
be revised to read: ‘‘Transmission
Provider shall provide Interconnection
Customer notice of such disconnection
within a reasonable time period, unless
the provisions of article 4.4.1
[Emergency Conditions] apply.’’
249. National Grid states that some
form of advance notice and the ability
to cure is generally reasonable before
disconnection; however, such steps
cannot be mandated all the time. It
proposes language giving the
Transmission Provider the right to take
unilateral action to avoid service
disruptions to other customers or
damage to facilities caused by the Small
Generating Facility.
250. According to Small Generator
Coalition, the Transmission Provider
should notify the Interconnection
Customer if, based on sound
engineering judgment, it concludes that
adverse operating conditions exist.
Commission Conclusion
251. This article applies only if the
Transmission Provider determines that
the Small Generating Facility may
adversely affect its electric system and
the Interconnection Customer has failed
to take the necessary remedial action
within the time specified by the
Transmission Provider. We are not
convinced that the notice period is too
long, could endanger reliability or
safety, or unnecessarily expose the
Transmission Provider to liability
claims when damage and disruption to
its electric system is imminent. There
could be legitimate reasons for the
Interconnection Customer not to make
the necessary corrections within the
allotted time (e.g., replacement parts are
on back order). SGIA article 3.4.1
provides that the Transmission Provider
84 E.g., Ameren, EEI, National Grid, PacifiCorp,
PG&E, and Southern Company.
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
may declare an emergency and
disconnect the Small Generating
Facility if there is an imminent threat to
its electric system, which provides the
Interconnection Customer with ample
incentive to promptly resolve any
adverse operating effects. Accordingly,
we reject the request to eliminate the
notification period from this article.
However, we are revising this provision
to specify that no notice is necessary in
order to resolve an Emergency
Condition.
252. We agree with Small Generator
Coalition that the Transmission
Provider should immediately notify the
Interconnection Customer when
operation of the Small Generating
Facility may cause disruption or
deterioration of service to other
customers and that this finding must be
based on and supported by sound
engineering principles. We also stress
that all documentation supporting the
problem must be provided to the
Interconnection Customer upon request.
253. Temporary Disconnection—
Modification of the Generating Facility
(Proposed SGIA Article 4.4.5)—
Proposed SGIA article 4.4.5 would
require the Interconnection Customer to
secure written authorization from the
Transmission Provider before making
any material modification to the Small
Generating Facility, or it can be
disconnected.
Comment
254. EEI recommends that the phrase
‘‘material modification’’ be replaced
with ‘‘modification.’’ This revised
language is used in LGIA article 5.19.2.
Commission Conclusion
255. We agree with EEI that the term
‘‘material modification’’ could be
ambiguous. Accordingly, we are
revising this article to provide that
Transmission Provider written approval
is required before the Interconnection
Customer may modify its Small
Generating Facility in such a way that
could materially impact the safety or
reliability of the Transmission
Provider’s electric system. We are also
requiring that any modifications be
done according to Good Utility Practice.
256. Temporary Disconnection—
Reconnection (Proposed SGIA Article
4.4.6)—Proposed SGIA article 4.4.6
would require the Parties to cooperate
with each other to restore the Small
Generating Facility, the Interconnection
Facilities, and the Transmission
Provider’s electric system to their
normal operating state as soon as
reasonably practicable following any
temporary disconnection.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
Comments
257. Southern Company contends that
this article should state that restoration
is required only when the events
causing the temporary disconnection are
over. Small Generator Coalition asks
that the provision use ‘‘interruption and
curtailment’’ instead of ‘‘reduction.’’
258. In its supplemental comments,
Joint Commenters propose the following
alternative language: ‘‘the Parties shall
cooperate with each other to restore the
Generating Facility, Interconnection
Facilities, and Transmission Provider’s
Transmission System to their normal
operating state as soon as reasonably
practicable following a temporary
disconnection.’’
Commission Conclusion
259. We are adopting the proposed
language submitted by Joint
Commenters because it removes
unnecessary jargon and simply requires
that the Parties work to restore normal
interconnection service as quickly as
possible. This language addresses
Southern Company’s and Small
Generator Coalition’s concerns as well.
260. Financial Security Arrangements
(Proposed SGIA Article 5.2)—Proposed
SGIA article 5.2 provided that the
Interconnection Customer provide
financial security to the Transmission
Provider for the construction of
Interconnection Facilities or Upgrades
through a guarantee, surety bond, letter
of credit, or other form of credit that
meets certain standards. The type of
financial security arrangement and
issuing entity would have to be
reasonably acceptable to the
Transmission Provider and have (1)
terms and conditions that guarantee
payment up to an agreed upon amount,
(2) a reasonable date of expiration, (3) be
issued at least 20 days before
construction, and (4) be consistent with
the Uniform Commercial Code of the
jurisdiction where the Point of
Interconnection is located.
Comments
261. PacifiCorp argues that this article
does not refer to design costs. It asserts
that this could lead to unnecessary
confusion over whether design costs
should be included with procurement,
resulting in the burden of design costs
falling on the Transmission Provider
and its customers.
262. Southern Company offers
proposed changes to provide protection
for the Transmission Owner and the
Transmission Provider. It asks the
Commission to delete any references to
surety bonds as an acceptable form of
payment on the grounds that they are
PO 00000
Frm 00025
Fmt 4701
Sfmt 4700
34213
not specifically mentioned in the OATT
and are not generally accepted as a form
of payment. It also requests that the
SGIA state clearly that the terms of any
letter of credit, guarantee or other
security must be reasonably acceptable
to the Transmission Provider.
263. In an effort to avoid fraudulent
conveyance issues or problems with the
enforcement of any guarantee through
bankruptcy procedures, Southern
Company proposes that the parent of the
Interconnection Customer (if any) serve
as the source of any guarantee,
specifically excluding affiliates from
proposing any guarantee. Additionally,
any proposed guarantor should have a
credit rating of BBB+ to protect against
rapid credit downgrades.
264. Southern Company also argues
that the dollar-for-dollar reduction of
security as payments are made to the
Transmission Provider is arbitrary and
capricious and imposes risks under
bankruptcy and fraudulent conveyance
law upon the Transmission Provider. At
a minimum, the Commission should not
require that security be reduced until
the expiration of any potential
bankruptcy preference period. Southern
Company also asks the Commission to
clarify that credit support is not to be
reduced by payments made to the
Transmission Provider that are
unrelated to the actions designated in
this article. It also proposes the
expansion of credit to cover all other
obligations of the Interconnection
Customer under the interconnection
agreement.
265. Finally, NYTO proposes that the
Interconnection Customer demonstrate
its creditworthiness in its
Interconnection Request.
Commission Conclusion
266. We agree with PacifiCorp that
design costs are a part of the
development process that should be
covered and are including such a
provision in the SGIA.
267. While Southern Company
opposes using surety bonds as an
acceptable form of payment, we are
following in this Final Rule the same
approach taken in the LGIA, which
states that the Interconnection Customer
has the right to select a form of security
that is acceptable to the Transmission
Provider and consistent with
commercial practices.85 Because SGIA
article 6.3 grants the Transmission
Provider the discretion to reject a form
of security (if it is reasonable to do so),
we reject Southern Company’s proposal
to eliminate the surety bond as an
acceptable form of credit. Giving the
85 Order
E:\FR\FM\13JNR2.SGM
No. 2003 at P 597.
13JNR2
34214
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Interconnection Customer a choice of
security is not unreasonable.86
Furthermore, granting the Transmission
Provider absolute discretion on what
forms of security to allow would
provide too great an opportunity to erect
hurdles to new small generation.87
268. For the same reasons, we reject
Southern Company’s proposals to (1)
limit the source of any guarantee to a
parent of the Interconnection Customer
and (2) require any proposed guarantor
to have a credit rating of BBB+. These
are hurdles that could be exploited to
discourage Small Generating Facilities.
The SGIA grants the Transmission
Provider the discretion to reject a form,
source, or issuing entity of security only
if doing so is reasonable. Giving the
Transmission Provider absolute
discretion on these choices would create
too great an opportunity for
exploitation.
269. We are requiring the reduction of
the security amount on a dollar-fordollar basis as payments are made
because this protects the
Interconnection Customer against
providing too much security while
ensuring that the Transmission Provider
is sufficiently protected against its real
cost exposure.88 We recognize that
reducing the security as the
Interconnection Customer pays its bills
may cause a small increase in risk to the
Transmission Provider, but the chilling
effect of requiring the Interconnection
Customer to maintain the full security
during the length of the interconnection
process would seriously discourage new
small generation.
270. We clarify that credit support is
not to be reduced by payments made to
the Transmission Provider that are
unrelated to the actions listed in this
article. In response to NYTO, we note
that the Interconnection Customer is
already required to give appropriate
financial guarantees before the
Transmission Provider begins
construction. Thus, the Interconnection
Customer need not demonstrate its
creditworthiness when it submits its
Interconnection Request.
271. Milestones (Proposed SGIA
Article 5.3)—Proposed SGIA article 5.3
stated that the Parties are to agree on
milestones that each Party is responsible
for meeting. These milestones are part of
86 See Florida Power & Light Company, 98 FERC
¶ 61,226 at 61,893–94, reh’g granted in part on
other grounds, 99 FERC ¶ 61,318 (2002); Florida
Power & Light Company, 98 FERC ¶ 61,324 at
62,358–59 (noting that the Transmission Provider’s
practice of limiting interconnection customers to a
letter of credit is unreasonable), reh’g rejected as
moot, 100 FERC ¶ 61,094 (2002).
87 Southwest Power Pool, Inc., 100 FERC ¶ 61,096
at P 12 (2002).
88 See Order No. 2003 at P 264.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
the interconnection agreement. Article
5.3 further specified that if either Party
does not meet a milestone, it must
compensate the other Party for its losses
(i.e., pay liquidated damages).
Comments
272. Several commenters ask the
Commission to remove references to
liquidated damages from the SGIA.
Others claim that the Commission lacks
the legal authority to impose liquidated
damages.
273. EEI seeks the elimination of this
article entirely. The provision is vague
and confusing because conflicting
milestone requirements appear in other
areas of the Proposed SGIA and
Proposed SGIP. NYTO contends that
Appendix 3 of the Proposed SGIA,
which requires the Parties to list agreed
upon milestones, is unnecessary.
274. Midwest ISO requests that the
Commission adopt the same liquidated
damages clause as in the LGIA. It states
that this will make the large and small
generator tariff provisions consistent.
275. PacifiCorp requests that
Proposed SGIA articles 5.3.1 and 5.3.2
be deleted. It contends that the
accomplishment of milestones should
be subject to a ‘‘reasonable efforts’’ or
‘‘good faith efforts’’ standard rather than
liquidated damages being applied. As a
matter of policy, good faith efforts
should not be penalized, since the
Transmission Provider does not profit
from interconnections.
276. In its supplemental comments,
Joint Commenters suggest replacing this
provision in its entirety. The proposed
replacement requires the Parties to agree
to extend milestone deadlines if the
milestone was missed in ‘‘reasonable
good faith.’’ However, the Party affected
by the failure to meet a milestone is not
required to agree to an extension if:
(1) It will suffer significant uncompensated
economic or operational harm from the delay
and believes that the delay is not or was not
unavoidable, (2) attainment of the same
milestone has previously been delayed, or (3)
it has reason to believe that the delay in
meeting the milestone is intentional or
unwarranted notwithstanding the
circumstances explained by the party
proposing the amendment.
277. Joint Commenters also suggest
making the provision bilateral and
removing the monetary penalty for
missing a milestone. Additionally, Joint
Commenters would require the Party
missing the milestone to fully explain to
the other Party why the milestone was
missed. Finally, Joint Commenters
propose adding a statement that any
dispute as to this provision should be
resolved according to the dispute
resolution portions of the SGIA.
PO 00000
Frm 00026
Fmt 4701
Sfmt 4700
Commission Conclusion
278. This Final Rule adopts many
concepts proposed by Joint
Commenters, including the notice
provisions and the preference that the
Parties agree to extend deadlines instead
of declaring that the other Party has
defaulted on the SGIA.
279. Regarding Joint Commenters’
proposal to add a statement regarding
dispute resolution, such a statement is
not needed because the SGIA’s dispute
resolution provision applies to the
entire document.
280. We reject PacifiCorp’s proposal
to delete SGIA milestone provisions.
These provisions provide a single
reference to the relevant milestones.
They will assist the Parties and will
minimize disagreements. Removing
them would create uncertainty for the
Parties.
281. Because we are not imposing in
this Final Rule a financial penalty on
the Transmission Provider for missing
milestones, there is no need to discuss
commenters’ arguments on that issue.
282. Billing and Payment (Proposed
SGIA Article 5.4)—Proposed SGIA
article 5.4 would provide that billing
and payment obligations are to be
performed under the terms of the SGIA.
Comments
283. PacifiCorp requests that this
article be revised to include billing and
payment requirements for Distribution
Upgrades or Network Upgrades. It also
states that billing and payment for
miscellaneous costs, such as restudy
costs, should be addressed.
Commission Conclusion
284. We agree with PacifiCorp in part
and are revising this article to clarify
that billing and payment requirements
are for Distribution Upgrades and
Network Upgrades. However, we see no
need to identify specific miscellaneous
costs because the obligations listed in
SGIA article 6.1 are for services
rendered, which already includes such
costs.
285. Billing Procedure for
Interconnection Facilities Construction
(Proposed SGIA Article 5.4.1) and Final
Accounting (Proposed SGIA Article
5.4.2)—Under Proposed SGIA article
5.4.1, the Transmission Provider would
bill monthly for expenditures for the
design, engineering and construction of,
or for other charges related to,
Interconnection Facilities. The
Interconnection Customer would remit
payment within 30 calendar days after
receipt of the bill.
286. Proposed SGIA article 5.4.2
would require that the Transmission
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Provider submit a final accounting
report to the Interconnection Customer
within 45 calendar days after installing
the Transmission Provider’s
Interconnection Facilities.
Comments
287. PacifiCorp suggests that
Proposed SGIA article 5.4.1 also include
procurement costs. Small Generator
Coalition argues that alternative
arrangements for payment of the bill
should be allowed if the Parties agree.
With respect to Proposed SGIA article
5.4.2, numerous commenters 89 argue
that 45 calendar days is not enough time
for the Transmission Provider to prepare
a final accounting report. They offer an
array of alternative deadlines ranging
from 60 Business Days to 90 days after
the Small Generating Facility begins
commercial operation. BPA complains
that there is not a similar deadline for
any additional payments owed by the
Interconnection Customer. It proposes
that any unpaid bill must be paid within
30 days after the bill is submitted by the
Transmission Provider.
Commission Conclusion
288. We agree with PacifiCorp that
procurement costs should be included.
We are also revising the provision to
allow the Parties to make other
reasonable payment arrangements
should they agree to do so, as requested
by Small Generator Coalition.
289. While we agree with commenters
that the proposed deadline for
submitting the final accounting report
may be too short, tying it to commercial
operation of the Small Generating
Facility is unrealistic because that event
may happen long after construction is
complete. A more realistic deadline, and
one that provides sufficient time for the
Transmission Provider to compile the
expenditures and process the final
accounting report, is three months from
the date construction of the facilities is
completed. We are so revising this
provision.
290. BPA is correct that proposed
SGIA article 5.4.2 did not include a
deadline for the Interconnection
Customer to pay its final accounting
bill. We are including in the SGIA 30
calendar days for the Interconnection
Customer to make payment to the
Transmission Provider.
291. Finally, we are consolidating
Proposed LGIA articles 5.2, 5.3, and 5.4
because they are so closely related. The
new article is entitled ‘‘Billing,
Payment, Milestones, and Financial
Security.’’
89 E.g., BPA, Central Maine, NYTO, PGE, and
Southern Company.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
292. Assignment (Proposed SGIA
Article 6.5)—Proposed SGIA article 6.5
would allow the Parties to assign their
rights under the interconnection
agreement to others under certain
circumstances.
Comments
293. Southern Company contends that
the proposed assignment provision
unreasonably allows one Party to freely
assign its rights to an affiliate without
consent from the other Party. It argues
that this subjects the Transmission
Provider to unnecessary risk from which
it cannot protect itself by requiring that
the assignee have a credit rating
equivalent to that of the assignor;
Transmission Providers typically rely
on guarantees or letters of credit, which
are personal to the obligor and would
likely not cover the assignee. Bureau of
Reclamation emphasizes that its policies
allow assignment of an interconnection
agreement only if both Parties agree to
the assignment and the assignor agrees
to remain bound by the original terms
of the SGIA.
294. Southern Company also argues
that it is unreasonable to make the
Transmission Provider get the
Interconnection Customer’s agreement
before it can assign the interconnection
agreement as collateral, while at the
same time allowing the Interconnection
Customer to assign the interconnection
agreement as collateral without the
Transmission Provider’s permission.
Southern Company contends that such
assignments could unfairly deprive the
Transmission Provider of the right to
require the assignee or purchaser in
foreclosure to assume the obligations of
the assignor and to fulfill performance.
In addition, the Transmission Provider
could lose the right to require collateral
assignees to cure Defaults of the
assignor, thereby allowing assignees or
purchasers in foreclosure to gain greater
rights under the interconnection
agreement than would have been
permitted to the original
Interconnection Customer. The
requirement that notice of collateral
assignment be provided by the secured
party, trustee, or mortgagee is
unworkable, as there would be no
enforceable penalties for breach of this
obligation. Not only do these parties
lack contractual privity with the
Transmission Provider, but they are also
not typically subject to Commission
jurisdiction.
295. Southern Company contends that
this article should provide Transmission
Providers and Transmission Owners
indemnification rights for any losses,
costs, and expenses they may incur in
connection with assignments or
PO 00000
Frm 00027
Fmt 4701
Sfmt 4700
34215
foreclosures. In addition, Southern
Company seeks clarification of the
conditions under which the
Transmission Provider must recognize
foreclosure rights and assignments. The
provision as written could expose the
Transmission Provider to
uncompensated risks, forcing its native
load to bear the costs.
296. Small Generator Coalition
requests that this article allow the
Interconnection Customer to assign its
rights and obligations under the
interconnection agreement without
consent of the Transmission Provider if
the Interconnection Customer sells or
transfers the Small Generating Facility
and the real property on which it is
located.
297. NARUC urges adoption of its
Model interconnection agreement
language, which allows assignment by
the Interconnection Customer in two
situations. First, assignment may be
made to a corporation or other limited
liability entity upon the consent of the
Transmission Provider. Such consent is
not to be withheld unless the
Transmission Provider ‘‘can
demonstrate that the corporate entity is
not reasonably capable of performing
the obligations of the assigning
Interconnection Customer.’’ Second, the
Interconnection Customer may assign
the interconnection agreement to a
person who is either the ‘‘owner, lessee,
or is otherwise responsible for the Small
[Generating Facility].’’
298. In its supplemental comments,
Joint Commenters recommend two
changes to the Proposed SGIA: (1)
Deleting the sentence requiring the
assignee to notify the other Party before
exercising its assignment rights and (2)
requiring the assigning Party to give the
other Party 15 days to object to an
assignment.
Commission Conclusion
299. The assignment provision
proposed by Joint Commenters is
similar to the provision in the Small
Generator NOPR. However, Joint
Commenters propose two minor
changes that we will adopt. First, Joint
Commenters propose to remove a very
technical sentence relating to financing
from the provision that is not well
suited to smaller projects. Second, Joint
Commenters require that a Party seeking
to assign the SGIA merely inform the
other Party of the pending assignment.
Should the Party not object, the
assignment may go forward. If the Party
does object, then the remainder of the
provision will apply. Making these
changes to the assignment provision
should reduce the administrative
E:\FR\FM\13JNR2.SGM
13JNR2
34216
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
burden on the Parties without
diminishing their substantive rights.
300. In Order No. 2003–A,90 the
Commission modified the assignment
provision of the LGIA in order to
address Southern Company’s concerns
relating to protecting native load
customers. We make corresponding
changes here, clarifying that (1) an
Interconnection Customer assigning its
rights under the SGIA is required to
notify the Transmission Provider of the
assignment and (2) an assignee is
responsible for meeting the same
insurance and financial security
obligations as a normal Interconnection
Customer upon exercising its right of
assignment.91 This is in addition to a
sentence specifying that ‘‘an assignment
under this provision shall not relieve a
Party of its obligations * * *.’’ We also
make various editorial changes that
make the provision easier to read.
Southern also requests that a
Transmission Provider be allowed to
assign the interconnection agreement as
collateral. We reject that request for the
same reasons discussed in Order No.
2003–A.92
301. Insurance (Proposed SGIA
Article 6.16)—In the Small Generator
Interconnection NOPR, the Commission
asked whether insurance should be
required for Small Generating Facility
interconnections and if so, how much.
While the Proposed SGIA itself
contained insurance provisions, the
Commission did not specify dollar
amounts and requested proposals from
commenters. The Commission also
requested comments on three specific
issues. First, should insurance coverage
vary with the size of the facility?
Should, for example, a 20 MW Small
Generating Facility be subject to higher
coverage amounts than a 10 MW
facility, which itself would be subject to
higher coverage amounts than a 5 MW
facility? Second, should coverage types
and amounts vary according to the type
of generator so that, for example, solar
or wind facilities would require
different insurance coverage than gasfired facilities? Third, should there be a
size cutoff that would exempt certain
facilities from some insurance
requirements?
Comments
302. The NARUC Model, while not
requiring insurance, proposes that state
regulators recommend that every
Interconnection Customer ‘‘protect itself
with insurance or other suitable
financial instrument sufficient to meet
Order No. 2003–A at P 470.
91 See Id. P 471.
92 See Id. P 475.
its construction, operating and liability
responsibilities * * *.’’ 93
303. NARUC argues that the
Commission’s proposal to require seven
different types of insurance is excessive
and makes federal interconnection rules
incompatible with state rules. The very
act of requiring insurance would drive
up prices because insurance companies
would then have a captive market that
must have insurance. Workers’
compensation and automobile insurance
are already required by state law;
accordingly, they should not be
mandated by the federal government.
NARUC also asserts that state regulators
will have more flexibility to assure low
insurance rates if this Final Rule does
not require insurance. Finally, NARUC
reports that while California requires
insurance for most projects, the majority
of other states (including New York,
Texas, and Ohio) do not. Therefore,
requiring insurance would be
inconsistent with the practice in most
states.
304. NYPSC reports that its own
efforts to establish minimum insurance
requirements were unsuccessful. While
it recognizes the risk Small Generating
Facilities pose to the Transmission
Provider, mandatory insurance ‘‘created
a substantial barrier to the proliferation
of distributed generation units.’’ 94 The
biggest barrier to entry is not the cost of
insurance (though that is a factor), but
the fact that insurance is unavailable at
any price in many situations. Insurance
companies are not yet familiar with the
risks posed by the interconnection of
Small Generating Facilities and often
will not insure them. NYPSC instead
proposes allowing the market to
determine insurance requirements. It
reports that the market has at least
partially responded to this need,
creating insurance pools to spread the
risk to multiple entities. It also notes
that manufacturers sometimes bundle
insurance coverage along with the
equipment.
305. ISO New England recognizes that
smaller generators generally pose less
risk than larger ones, but argues that the
level of risk should be evaluated on a
case-by-case basis. This Final Rule
should let an independent Transmission
Provider waive the insurance
requirement if it determines that the
project poses little risk to its electric
system. For many smaller facilities, the
liability, indemnity, and insurance
requirements typically required of larger
facilities may cost too much. Likewise,
MISO supports making the amount of
90 See
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
93 NARUC
Model—Interconnection Agreement at
article 7.
94 NYPSC at 9.
PO 00000
Frm 00028
Fmt 4701
Sfmt 4700
insurance required a function of the risk
of the particular interconnection.
However, MISO also supports
establishing minimum standard
insurance requirements (although it
does not offer specific amounts).
306. Some Transmission Providers 95
want the Commission to keep the
proposed insurance limits. Central
Maine and NYTO, among others, point
out that most small projects would not
have the financial resources to pay any
judgment against them and argue that
insurance is necessary to protect the
interests of the Transmission Provider,
and ultimately, its customers. EEI favors
using the same insurance limits as the
LGIA.
307. AEP also argues that there is no
reason why standard insurance
provisions should be different for a 1
MW facility than for a 20 MW facility.
Likewise, Allegheny Energy, Central
Maine, NYTO, and others argue that
even a very small generating facility can
damage the Transmission Provider’s
electric system.
308. Empire District, Nevada Power,
NRECA, and PG&E assert that the
amount of insurance required should
vary with generator size. As NRECA
puts it, ‘‘a residential consumer
installing a 3 kW Small Generating
Facility should not have to acquire $1
million in insurance * * *.’’ 96 Even so,
NRECA states that it would oppose any
attempt to create a minimum megawatt
threshold below which insurance would
not be required.
309. PG&E states that California has
long required insurance for all projects
larger than 10 kW and that this
requirement has not noticeably
dampened the market for on-site Small
Generating Facilities.
310. While Nevada Power agrees that
solar and wind projects present less risk
than does a traditional gas-fired
generator, it opposes insurance
requirements that differ by fuel type.
The market already recognizes these
reduced risks by charging
proportionately less for some types of
insurance than others. NRECA also
opposes distinguishing between
different fuel types, arguing that this is
only one of many factors that determine
a project’s risk.
311. In contrast, Tangibl supports
basing the required amount of insurance
on the type of generator being
interconnected. It argues that the risks
posed by Small Generating Facilities are
largely environmental, such as fuel
95 E.g., AEP, Allegheny Energy, Avista, BPA,
Central Maine, Cinergy, EEI, NRECA, NYTO, and
Southern Company.
96 NRECA at 34.
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
spills. Tangibl also argues that Small
Generating Facilities pose less risk than
do large generators because the former
need smaller amounts of fuel to be
stored on site. This risk is even less for
renewable sources such as wind or
solar.
312. Nevada Power says that knowing
how much insurance is going to be
required at the outset of the project is
important to its success.
313. While AEP supports including
standard insurance terms in this Final
Rule, the Parties should be able to
negotiate additional terms if warranted
by the physical characteristics of the
project. NRECA argues for permitting
the Transmission Provider to determine
the necessary level of insurance on a
case-by-case basis.
314. Cinergy also argues for increased
flexibility. It would let the Transmission
Provider reduce or eliminate the
required insurance provisions on a caseby-case basis if it believes in good faith
that the full amount of insurance is not
required to safeguard its interests.
Cinergy also argues that this Final Rule
should provide a mechanism for dealing
with insurance requirements that
simply do not apply to a given
generator, such as requiring workers’
compensation insurance for a generator
that does not have any on-site
employees.
315. National Grid proposes that the
Commission not set required levels of
insurance, and instead leave it to the
Transmission Provider and state law. It
points out that several states have, or are
in the process of developing, specific
insurance requirements for Small
Generating Facilities. The Commission
should not second-guess the attempt of
various states to encourage on-site Small
Generating Facilities. Specifically,
National Grid points to a proposal
developed by a working group of the
Massachusetts Public Utilities
Commission that proposes varying
levels of insurance depending on the
capacity of the project.97
316. NYTO makes a similar request,
arguing that the Transmission Provider
should be allowed to fill in specific
insurance amounts based on state law,
97 The proposal requires no insurance for projects
smaller than 10 kW; $500,000 for projects between
10 kW and 100 kW ($500,000 aggregate); $1 million
for projects between 100 kW and 1 MW ($1 million
aggregate); $2 million for projects larger than 1 MW
and no larger than 5 MW ($5 million aggregate); and
$5 million for projects larger than 5 MW ($5 million
aggregate). See National Grid Comments, Appendix
A (citing Tariff to Accompany Proposed Uniform
Standards for Interconnecting Distributed
Generation in Massachusetts, Submitted by the
Distributed Generation Interconnection
Collaborative to the Massachusetts Department of
Telecommunications and Energy in Compliance
with DTE Order No. 02–38-A (May 15, 2003)).
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
established local practice or, absent
those, its own business judgment.
317. Avista states that the Parties
should be allowed to negotiate
alternative mechanisms such as selfinsurance. It argues that even a
Transmission Provider facing financial
difficulty can always raise rates to cover
any potential liability. Southern
Company also proposes revisions to
clarify the meaning of this article.
318. NRECA, while it supports the
Commission’s insurance proposal,
opposes making the provision bilateral.
It argues that the Transmission
Provider’s operation of its electric
system does not create any greater risk
to the Interconnection Customer than to
any other customer. The
interconnection of the Small Generating
Facility, on the other hand, increases
the risks to the Transmission Provider.
Furthermore, according to NRECA, most
Transmission Providers are already
required to either self-insure or
otherwise carry insurance sufficient to
cover any liability that may arise from
operation of their electric systems, so
requiring further insurance is
duplicative.
319. Empire District supports
requiring the Transmission Provider to
be named as an additional insured for
generators larger than 5 or 10 kW, while
Avista opposes such a size-related
requirement.
320. Avista notes that workers’
compensation requirements vary
significantly by state. It argues that the
Commission should not attempt to
federally preempt these long-standing
practices. According to Avista and
Nevada Power, the interconnection
agreement should simply require
compliance by each Party with the
applicable state workers’ compensation
laws.
321. Cinergy states that while
insurance may be a significant barrier to
entry for some Interconnection
Customers, the Commission should
heed the insurance market’s
independent assessment of the risk of a
particular project. Fundamental
economic principles require
Interconnection Customers to bear the
costs of the risks they impose on third
parties, and there is no sound basis for
the Commission to shift that cost to the
Transmission Provider and its
customers. Nevada Power and NRECA
make similar arguments. NRECA also
argues that if Interconnection Customers
do not have insurance, insurance
companies will be forced to raise the
cost of insurance for Transmission
Providers, and that in turn will be paid
by all users of the Transmission System.
PO 00000
Frm 00029
Fmt 4701
Sfmt 4700
34217
322. Small Generator Coalition, like
most commenters representing Small
Generating Facilities, argues that
purchasing insurance is a business
decision and that the level and nature
of the insurance should be established
by each business according to its needs,
not mandated by the federal
government. It argues that requiring
insurance would create a major barrier
to small generator interconnections and
would prevent utility customers (as
opposed to commercial generation
projects) from pursuing interconnection
because the administrative and financial
barriers to entry would simply be too
great. It asserts that the insurance
requirements for a small wind turbine
should be less than for a nuclear power
plant or other large generator. Small
Generator Coalition is particularly
vehement in its opposition to insurance
requirements for projects under 2 MW
in size. Overall, Small Generator
Coalition supports NARUC’s comments
and asks the Commission to use the
NARUC Model in lieu of the Proposed
SGIA.
323. Small Generator Coalition states
that if the Commission does include
insurance requirements in its Final
Rule, it should exempt facilities no
larger than 2 MW and require only $1
million in general liability insurance for
projects 2 MW or larger.
324. In general, Transmission
Providers support requiring an
insurance regime with larger policy
limits and a broad array of coverage.
Interconnection Customers and NARUC
generally support requiring smaller
amounts of insurance or none at all.
Southern Company proposes revisions
to Proposed SGIA article 6.16.11 to
clarify the conditions under which one
Party must notify the other of accidents
and injuries arising out of the
interconnection agreement.
325. Central Maine proposes requiring
the following policies: $1 million in
employer’s liability and workers’
compensation insurance; $1 million in
Commercial General Liability Insurance
(with a $2 million aggregate combined
limit); comprehensive automobile
liability insurance of $1 million (with a
$2 million aggregate combined limit);
and an additional $1 million in excess
public liability insurance (with a $5
million aggregate cap).
326. Nevada Power proposes
requiring $1 million in general liability
coverage from projects greater than or
equal to 200 kW and $500,000 if the
project is no larger than 200 kW. It also
proposes requiring excess public
liability insurance of $10 million if the
facility is greater than or equal to 10
MW in size ($10 million aggregate); $5
E:\FR\FM\13JNR2.SGM
13JNR2
34218
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
million for projects between 5 and 10
MW ($5 million aggregate); $2 million
for projects between 200 kW and 5 MW
($2 million aggregate); and none for
projects less than 200 kW.
327. Southern Company is in favor of
requiring a flat level of coverage for all
Small Generating Facilities, regardless
of size, and proposes requiring $1
million workers’ compensation
insurance ($1 million aggregate); $2
million general liability insurance ($6
million aggregate); $2 million
comprehensive automobile liability
insurance; and $10 million excess
public liability insurance ($10 million
aggregate).
328. Tangibl proposes differing levels
of insurance requirements based on both
size and type of the generator. For solar
or wind generators, Tangibl proposes
requiring $2 million in insurance for
facilities larger than 10 MW; non-solar
or wind facilities larger than 10 MW
would maintain $4 million. However,
for facilities no larger than 10MW,
Tangibl proposes $500,000 in workers’
compensation insurance; $1 million
Commercial General Liability Insurance
($2 million aggregate); $1 million
comprehensive automobile insurance
($1 million aggregate); and $5 million
excess public liability insurance ($5
million aggregate).
329. SoCal Edison urges the
Commission to adopt the same
insurance requirements that the
California Public Utilities Commission
(CPUC) requires, asserting that
California’s extensive experience with
small generators should serve as a
model for the Commission. Specifically,
California’s Rule 21 requires general
liability coverage in the amount of $2
million for projects larger than 100 kW;
$1 million for projects larger than 20 kW
and no larger than 100 kW; and
$500,000 for projects no larger than 20
kW. Rule 21 also creates a special
reduced insurance requirement of
$200,000 for facilities no larger than 10
kW associated with a retail customer.
Rule 21 exempts some classes of solar
and wind generators from its insurance
requirements entirely, and provides for
waiver of the insurance requirements for
some small residential interconnections
if insurance is not easily obtainable.
330. In its supplemental comments,
Joint Commenters propose requiring the
Interconnection Customer to maintain
insurance in an amount ‘‘sufficient to
insure against all reasonably foreseeable
direct liabilities given the size and
nature of the generating equipment
being interconnected, the
interconnection itself, and the
characteristics of the system to which
the interconnection is made.’’ It also
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
specifies that the provision shall not
require the Interconnection Customer to
obtain additional insurance if the
insurance it already has is sufficient.
The Interconnection Customer is
required to document its insurance
coverage no later than ten days before
the anticipated commercial operation
date of the Small Generating Facility,
and afterwards as requested by the
Transmission Provider. The proposed
provision also allows the
Interconnection Customer to self insure
when appropriate and requires the
Transmission Provider to maintain
insurance ‘‘consistent with the
Transmission Provider’s commercial
practice.’’ While Joint Commenters were
able to reach consensus on the
insurance requirement for most Small
Generating Facilities, they were not able
to reach consensus on the issue of
insurance requirements for inverterbased generators no larger than 10 kW.
Commission Conclusion
331. The wide range of insurance
recommendations points out the
difficulties in establishing a set dollar
amount or type of insurance appropriate
to every Small Generating Facility.
Insurance can add significant costs to a
Small Generating Facility and may
affect the project’s economic feasibility.
Nevertheless, a mismanaged
interconnection can harm the
Transmission Provider’s electric system
and affect power customers, potentially
subjecting the Parties to liability.
332. We adopt in its entirety Joint
Commenters’ proposal, which reflects
appropriate compromises regarding this
diversity of insurance needs. We are
pleased that such a diverse group of
stakeholders could reach consensus on
this difficult issue.
333. The level of risk in
interconnecting a 50 kW photovoltaic
system with the Transmission
Provider’s Transmission System is very
different from the risk involved in
interconnecting a 10 MW generator.
Mandating that the Interconnection
Customer maintain a reasonable amount
of insurance based on the specific
characteristics of its interconnection
avoids the one-size-misfits-all problem
and addresses the differing needs of
different Interconnection Customers and
Transmission Providers.
334. Joint Commenters, however,
could not reach consensus on any
insurance provision for certified
inverter-based generators no larger than
10 kW. Commenters have convinced us
that the risk of interconnecting these
small inverter-based generators is low
and we therefore decline to impose a
generic insurance requirement in this
PO 00000
Frm 00030
Fmt 4701
Sfmt 4700
Final Rule.98 Instead, we adopt the
approach proposed by NARUC which is
that each Party be required to ‘‘follow
all applicable insurance requirements
imposed by the state in which the Point
of Interconnection is located. All
insurance policies must be maintained
with insurers authorized to do business
in that state.’’ Given that most
generators of this size and type will be
interconnecting with state-jurisdictional
facilities, it makes sense to coordinate
our approach with the approach
recommended by NARUC. This will
also avoid forum shopping. This is also
similar to the approach adopted in
Order No. 2003–A, which deferred to
state insurance laws rather than
imposing specific dollar amounts for
these types of insurance.99
335. However, because any uninsured
risk will fall squarely on the
Transmission Provider’s customers, who
would effectively subsidize the costs of
the interconnection, we reject proposals
that we completely waive insurance
requirement. Several commenters also
advise the Commission to leave the
issue of insurance to state regulators.
While this makes sense for small
inverter-based generators, for larger
Small Generating Facilities, having
insurance requirements vary by state
would hamper our effort to promulgate
national small generator interconnection
standards.
336. Cinergy asks that the
Transmission Provider be allowed to
waive or reduce insurance requirements
for a given project if it concludes that
it poses little risk to its electric system.
The provision proposed by Joint
Commenters would allow this type of
flexibility. If the Parties agree that the
interconnection is safe, then they can
agree that insurance is not necessary.
However, Transmission Providers must
waive or reduce the insurance
requirements on a non-discriminatory
basis that does not favor affiliated
facilities.
337. We also clarify that an RTO or
ISO may propose additional or different
insurance requirements under the
independent entity variation provision
contained in this Final Rule.
338. Reservation of Rights (Proposed
SGIA Article 6.20)—Some commenters
pointed out that Proposed SGIA article
6.20 contained a typographical error,
which we are correcting.
339. Signatures and Parties to the
SGIA (Proposed SGIA Article 9)—
98 See, e.g., Cinergy, Empire District, ISO New
England, NRECA, NYPSC, PG&E, and Small
Generator Coalition. But see, e.g., AEP, Central
Maine, EEI, NYTO, and Southern Company.
99 See Order No. 2003–A at P 462.
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Proposed SGIA article 9 required both
the Transmission Provider and the
Transmission Owner to sign the
interconnection agreement. This is the
same approach taken in Order No.
2003.100 In an RTO or ISO where the
Transmission Provider is not the
Transmission Owner, the RTO’s or ISO’s
compliance filing may propose a
modified interconnection agreement
that provides the Transmission Provider
and Transmission Owner different
rights and obligations.
Comments
340. ISO New England supports the
approach taken in Order No. 2003,
allowing Transmission Owners and
Transmission Providers to propose a
modified interconnection agreement
when the Transmission Provider is an
entity distinct from the Transmission
Owner. It contends that this approach is
necessary if the Commission wishes to
establish a single interconnection
agreement for a region encompassed by
an RTO or ISO.
341. NYISO argues that the SGIA
should assign certain basic
responsibilities to either the
Transmission Owner or Transmission
Provider.
342. Midwest ISO asserts that it is the
RTO’s role as an independent entity ‘‘to
ferret out unnecessary studies or
inappropriate contingencies.’’101
However, it argues that the ‘‘NOPR’s
failure to fully distinguish between a
transmission provider and transmission
owner belies the independence of the
RTO,’’ 102 and both it and other
commenters 103 request clarification of
the respective roles of the RTO and the
Transmission Owner.
343. National Grid argues that
defining ‘‘Transmission Provider’’ to
include both the Transmission Provider
and the Transmission Owner confuses
the issue and adds ambiguity into the
interconnection process. The
Commission should clearly define the
role of each Party. National Grid also
notes that the Small Generator
Interconnection NOPR did not account
for the role of stand-alone distribution
companies.
344. Central Maine asks the
Commission to clarify that the
Transmission Owner (or distribution
company, where applicable) must sign
the interconnection agreement and to
clarify whether the Transmission
Provider needs to be a Party to the
agreement. It asserts that the division of
100 Order
No. 2003 at P 909.
ISO at 6.
101 Midwest
102 Id.
103 E.g.,
NYTO and PG&E.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
functions between the Transmission
Owner and the Transmission Provider
varies by region and depends on the role
that the RTO or ISO plays in the region.
A request for interconnection with a
Distribution System may require that a
distribution company be a Party to the
interconnection agreement, in lieu of a
Transmission Owner or Transmission
Provider. Central Maine concludes that
the standard interconnection agreement
resulting from this proceeding must
ultimately be a contract between the
Interconnection Customer and the entity
that owns the Transmission System (i.e.,
the Transmission Owner or the
distribution company).
345. In RTO or ISO regions, if the
Commission determines that the
Transmission Provider must also sign
the interconnection agreement, Central
Maine asks the Commission to clarify
that, under section 205 of the FPA, the
Transmission Owner has the right to file
the agreement, consistent with Atlantic
City Electric Co., et al. v. FERC, 329 F.3d
856, 858–59 (D.C. Cir. 2003) (explaining
that while an ISO may have certain FPA
section 205 rights, the individual utility
also has FPA section 205 rights). Central
Maine also says that the Transmission
Owner, not the Transmission Provider,
has the right to file executed or
unexecuted interconnection agreements.
346. In lieu of requiring the signatures
of both the Transmission Owner and the
Transmission Provider, EEI contends
that the Commission should require the
signature only of the Transmission
Owner. Additionally, the Commission
should encourage ISOs and RTOs with
operational roles that cause this
distinction to clearly delineate the rights
and responsibilities in their operations
agreements and protocols. The
interconnection agreement can
specifically refer to the OATT already
approved by the Commission, thereby
eliminating the need to have both a
separate agreement between the
Transmission Provider and the
Interconnection Customer and a threeparty agreement.
347. PG&E argues that RTOs and ISOs
do not need to become Parties to
interconnection agreements for
distribution level projects because such
entities only operate transmission
systems. These entities have very little
interest in the smallest projects
interconnected with Distribution
Systems and therefore, should not be
the ones to receive Interconnection
Requests or maintain the queue for
distribution level interconnections. The
Commission should designate the
distribution provider to fulfill these
roles.
PO 00000
Frm 00031
Fmt 4701
Sfmt 4700
34219
348. NYTO asserts that since an
independent RTO or ISO has no right to
bind a Transmission Owner, the RTO or
ISO should not sign the interconnection
agreement.
Commission Conclusion
349. As in Order No. 2003, we are
requiring three-party agreements in
areas where the Transmission Provider
and Transmission Operator are different
entities.104 In other regions of the
country where the Transmission
Provider and the Transmission Owner
are the same entity, there is no need for
a second signature block.105
350. Given that RTOs and ISOs have
distinct characteristics and challenges,
we have permitted each RTO or ISO to
propose, on compliance, an
interconnection procedures document
and agreement tailored to its individual
needs.106 Such proposals should
allocate to each entity the appropriate
rights and obligations. As the Order No.
2003 compliance process demonstrated,
the Transmission Provider and
Transmission Owner are capable of
dividing responsibility among
themselves.
351. Finally, Central Maine asks the
Commission to specify that, under
section 205 of the FPA, the
Transmission Owner, not the
Transmission Provider, must file the
interconnection agreement. This is an
issue better resolved on a case-by-case
basis through the compliance process. It
would be premature to conclude that in
all circumstances the Transmission
Owner, and not the Transmission
Provider, has the right to file the
interconnection agreement.
352. Liability—In the Proposed SGIA,
the Commission proposed including
provisions in the SGIA governing the
apportionment of liability between the
Parties. These provisions (indemnity,
consequential damages, and Force
Majeure) were similar to the provisions
in the LGIA. The Commission requested
comments on whether Small Generating
Facilities should be treated differently
from Large Generating Facilities with
respect to liability. We discuss our
general approach to the liability
provisions first, followed by a more
detailed discussion of each provision.
104 Order
No. 2003 at P 909.
note that whether a public utility
characterizes itself as a ‘‘transmission’’ provider or
a ‘‘distribution’’ provider does not matter, since the
Transmission Provider is defined to be the ‘‘public
utility * * * that owns, controls, or operates
transmission or distribution facilities used for the
transmission of electricity in interstate commerce
and provides transmission service under the
Tariff.’’
106 Order No. 2003 at P 909.
105 We
E:\FR\FM\13JNR2.SGM
13JNR2
34220
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
General Approach
Comments
353. In general, Transmission
Providers support liability provisions
similar to those in the LGIA, arguing
that interconnecting a Small Generating
Facility raises as many safety and
reliability issues as interconnecting a
Large Generating Facility.107
354. Small Generator Coalition and
NARUC generally argue that these
provisions should be tailored
specifically to Small Generating
Facilities, arguing that the Proposed
SGIA was simply too complicated for
many Small Generating Facilities. They
first argue that a Small Generating
Facility poses less danger to the
Transmission Provider’s electric system
than a Large Generating Facility.
Second, they argue that imposing
liability provisions similar to those in
the LGIA on Small Generating Facilities
would be a major financial barrier to
entry and deter the development of new
Small Generating Facilities. Third, they
point out that the Transmission
Provider has an incentive to include
onerous liability provisions in the SGIA
to deter competition.
355. ISO New England similarly
argues that Small Generating Facilities
do not present the same risks as do
Large Generating Facilities. It asks the
Commission to permit independent
entities to determine, on a case-by-case
basis, whether to waive or relax the
liability provisions for individual
generators.
356. Avista asks the Commission to
follow Midwest Independent System
Operator, Inc., et al., 100 FERC ¶ 61,144
(2002), which allows the Parties to
propose customized liability limitations.
It argues that the August 14, 2003
Northeast Blackout is evidence of the
need for a comprehensive look at
liability limitations. Avista argues that
the interconnection agreement should
have a savings clause to let an RTO
conform the liability and dispute
resolution provisions (and possibly
others) to the standards and procedures
being implemented by the RTO.
Otherwise, the Commission’s rule could
unnecessarily grandfather inconsistent
provisions.108 For example, the
Agreement Limiting Liability Among
Western Interconnected Systems (‘‘WIS
107 For instance, AEP, BPA, EEI, and Nevada
Power argue that the LGIA and the SGIA should be
consistent. Nevada Power argues that such
provisions would not discourage well-run
generators from interconnecting with the
Transmission Provider.
108 Avista at 18.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
Agreement’’) 109 should continue to be
an option for generators and utilities.
Avista argues that the SGIA should have
a savings clause for the WIS Agreement.
Commission Conclusion
357. Many commenters, including
NARUC and independent entities like
ISO New England, agree that the
Commission should modify the
proposed liability provisions for Small
Generating Facilities in this Final Rule.
We agree that the provisions can
generally be simplified without
increasing the liability of any Party. The
liability provisions adopted here use
many of the proposals made by NARUC
and other commenters. They address the
Transmission Provider’s need to protect
its electric system while removing
unreasonable barriers to entry for
Interconnection Customers.
358. We agree with ISO New England
that an independent Transmission
Provider (via the independent entity
variation standard) may propose on
compliance to evaluate each
Interconnection Request on a case-bycase basis and fashion liability
requirements that are suitable to that
particular entity.
359. We deny Avista’s request for
caps on the amount of liability the
Transmission Provider may be subject
to, or that we allow it to develop its own
liability rules.110 The liability rules
discussed in the interconnection context
are distinct from the liability rules in
the rest of the OATT.111 In the
interconnection context, the indemnity
provision is two-sided (or three-sided,
in the case of an independent
Transmission Provider). This means that
the indemnity provisions found in the
SGIA are very different than the
indemnity provisions found in the
OATT. Many of Avista’s comments have
more to do with the liability provisions
found in the transmission portions of
the OATT than they do with
interconnection. While we agree that
liability protection is important, this
109 ‘‘The WIS Agreement * * * is a multi-lateral
agreement among parties in the Pacific Northwest
that operates to limit liability among the
signatories.’’ Id.
110 In Puget Sound Energy, Inc., 107 FERC
¶ 61,287 (2004), the Commission denied a request
by Puget Sound to include the WIS Agreement in
its tariff because Puget Sound did not explain why
such inclusion was ‘‘consistent with or superior to’’
the pro forma OATT. However, the Commission did
not foreclose the possibility that a WIS Agreement
member may be able to make such a showing in a
future compliance filing.
111 Order No. 2003 at P 636 (‘‘Commenters have
convinced us that interconnection presents a greater
risk of liability than exists for the provision of
transmission service and that, therfore, the OATT
indemnity provision is not suitable in the
interconnection context.’’)
PO 00000
Frm 00032
Fmt 4701
Sfmt 4700
rulemaking is not the place to decide
such an issue. We also deny Avista’s
request to insert a savings clause into
the liability provision. Avista has not
explained how the Transmission
Provider’s participation in the WIS
Agreement would be affected by this
Final Rule. If Avista wishes, it may seek
to include such a provision on
compliance under the ‘‘consistent with
or superior to’’ standard.
Consequential Damages (Proposed SGIA
Article 6.19)
360. Proposed SGIA article 6.19 used
the LGIA consequential damages
provision, which states that neither
Party is liable to the other for special or
consequential damages except as
expressly provided for in the
interconnection agreement.
Comments
361. Central Iowa Coop is concerned
that the phrase ‘‘[o]ther than as
expressly provided for in this
agreement’’ could make the Parties
subject to consequential damages when
read in conjunction with the
indemnification provision in Proposed
SGIA article 6.13. It asks the
Commission to clarify that the bar
against consequential damages applies
in all circumstances, except when the
Parties have reached an express
agreement to the contrary.
362. Central Maine asks the
Commission to clarify that indemnity
payments to a third party are not
consequential damages.
363. NARUC proposes that the
Commission adopt its Model language,
which is less complicated than the
proposed provision. Specifically,
NARUC proposes replacing Proposed
SGIA article 6.19 with a generic
statement at the beginning of the
liability article:
Each Party’s liability to the other Party for
any loss, cost, claim, injury, liability, or
expense, including reasonable attorney’s fees,
relating to or arising from any act or omission
in its performance of this agreement, shall be
limited to the amount of direct damage
actually incurred. In no event shall either
Party be liable to the other Party for any
indirect, special, consequential, or punitive
damages of any kind whatsoever.
Commission Conclusion
364. We retain the provision as
proposed. This is a contractual term and
no commenter has convinced us that it
is necessary to deviate from the
approach taken in Order No. 2003.
365. Several commenters appear to
have misunderstood the relationship
between the indemnity and
consequential damages provisions in the
Proposed SGIA. The bar against
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
consequential damages does not apply
in the indemnity context. Instead, the
indemnification of one Party by another
is comprehensive, and the indemnifying
Party is responsible for all of the
indemnified Party’s costs, regardless of
whether those costs are compensatory or
punitive. While the consequential
damages provision adopted in this Final
Rule prevents one Party from seeking
consequential damages against another
Party, the purpose of the
indemnification provision is different; it
protects the indemnified Party from
liability to third parties (those who are
not Parties to the interconnection
agreement). Requiring the indemnifying
Party to reimburse the indemnified
Party for, say, only compensatory
damages and not punitive damages
would not make the indemnified Party
whole. We are adding language to the
beginning of the indemnity section to
make this clear.
Indemnity (Proposed SGIA Article 6.13)
366. Indemnification is compensating
another for a loss suffered due to a third
party’s act or default.112 The Proposed
SGIA contained indemnity provisions
similar to those contained in the LGIA.
The proposal would require the
Transmission Provider and the
Interconnection Customer to indemnify
each other for any damages, losses,
claims, and obligations by or to third
parties arising from performance of the
Transmission Provider’s or
Interconnection Customer’s obligations
under the interconnection agreement on
behalf of the other contracting party.
Indemnity protection would include the
amount of the indemnified Party’s loss,
net of any insurance recovery, but
would not apply where there is gross
negligence or intentional wrongdoing.
The proposed provision also set forth
detailed procedures for pursuing an
indemnity claim and allowed recovery
of legal costs in some cases.
Comments
367. AEP, BPA, Idaho Power, and
Nevada Power generally agree that
Small and Large Generating Facilities
should be treated consistently with
respect to indemnity protections.
368. Central Iowa Coop, Georgia
Transmission, and NYTO request that
the Commission replace the mutual
indemnity provision with a one-way
indemnity provision in favor of the
Transmission Provider. They argue that
the Transmission Provider receives no
benefit from an interconnection, but
does face additional safety, reliability,
and power quality concerns as a result
of it. To require the Transmission
Provider to indemnify the
Interconnection Customer unfairly shifts
the costs and risks to the Transmission
Provider’s other customers.
369. Central Maine contends that
Proposed SGIA article 6.13 should not
exclude ‘‘insurance or other recovery’’
from amounts owed to an indemnified
party. It argues that this is commercially
unreasonable and undermines the very
intent of the indemnity provision.
370. ISO New England argues that
applying the liability provisions
contained in the LGIA to Small
Generating Facilities is unreasonable
because the risks associated with
interconnecting the latter are not
comparable to those associated with
interconnecting Large Generating
Facilities. The Commission should
permit independent entities such as
RTOs and ISOs to determine, on a caseby-case basis, whether a waiver or
relaxation of the indemnity provisions
used for Large Generating Facilities
should be permitted based on the actual
risk the Small Generating Facility
presents. Permitting this type of
flexibility would minimize the cost of
interconnection and ensure adequate
protection for the Transmission
Provider.
371. Southern Company argues that
the proposed indemnity provision is not
workable. The provision requires each
Party to indemnify the other for
damages arising out of such other
Party’s ‘‘performance of obligations
under this Agreement on behalf of the
indemnifying Party.’’ 113 It argues that it
is unclear whether the indemnity
provision would ever apply because the
Parties do not perform obligations on
behalf of each other at all. It proposes
that each Party indemnify the other
from any liabilities or damages resulting
from activities on the indemnifying
Party’s own side of the point of change
of ownership. Additionally, each Party
should indemnify the other for the
indemnifying Party’s failure to adhere to
operating requirements and for breaches
of the interconnection agreement.
Southern Company also takes issue with
the provision’s limitation of expenses
paid for the legal defense of an
indemnified Party. If an indemnified
Party has additional legal defenses, the
proposed article requires the
indemnifying Party to pay for only one
attorney.114 Southern Company requests
that the Commission revise the
provision to require the payment of the
113 Southern
112 Black’s
VerDate jul<14>2003
Law Dictionary 772 (7th ed. 1999).
21:44 Jun 10, 2005
Jkt 205001
PO 00000
114 See
Company at 34.
Proposed SGIA article 6.13.
Frm 00033
Fmt 4701
Sfmt 4700
34221
indemnified party’s reasonable legal
expenses.
372. In its Model interconnection
agreement, NARUC proposes a different
approach to indemnity. There, the
Transmission Provider and the
Interconnection Customer would
assume liability and indemnify each
other for claims and expenses resulting
from their own negligence as it relates
to the design, construction, and
operation of their facilities. A Party
indemnifies the other only for claims
brought by claimants who could directly
recover from the Party itself. Indemnity
for both Parties includes monetary
losses, reasonable legal fees for
defending a third party action, damages
related to the death/injury of a third
party, damages to the Party’s property or
property of a third party, and damages
for disruption of a third party’s
business. Neither the Transmission
Provider nor the Interconnection
Customer assumes liability for
consequential, special, incidental, or
punitive damages, and neither is
responsible for disruption of the other’s
business or for the costs and expenses
of pursuing legal action against the
other.
Commission Conclusion
373. We are adopting a streamlined
indemnity provision in this Final Rule.
374. Several commenters appear to
have misunderstood the relation
between the proposed indemnity
provision and the bar against
consequential damages provision (now
called Limitation of Liability). We are
therefore including in the SGIA an
explanation that claims under the
indemnity provision are exempt from
the bar against consequential damages
contained in the Limitation of Liability
provision.
375. Many of the comments
addressing indemnity are identical to
those addressed in Order No. 2003 and
do not argue that Small Generating
Facilities should be treated differently
from Large Generating Facilities. We
will not repeat the discussion in those
orders. For instance, the Commission
addressed comments about the bilateral
nature of the provision in Order No.
2003 at P 637, and comments on which
side of the Point of Interconnection
work is conducted in Order No. 2003 at
P 638.
376. Because the purpose of
indemnification is to pay another for
actual losses, the exclusion of
‘‘insurance or other recovery’’ from
amounts owed to an indemnified Party
does not undermine the intent of this
provision, as Central Maine argues.
Forcing an indemnifying Party to pay
E:\FR\FM\13JNR2.SGM
13JNR2
34222
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
damages already covered under an
insurance policy would allow the
indemnified Party to profit at the
expense of the indemnifying Party.
Excluding insurance and other
recoverable amounts avoids
overcompensating an indemnified Party.
377. In response to Southern
Company’s request that the provision
cover an indemnifying Party’s failure to
meet operating requirements or its
breach of the SGIA, we note that it
covers damages from actions or
inactions under the interconnection
agreement. However, in response to
Southern Company’s comments, we are
modifying the provision to add: ‘‘arising
out of or resulting from the other Party’s
actions or failure to meet its obligations
under this SGIA.’’
Force Majeure (Proposed SGIA Article
6.14)
378. Proposed SGIA article 6.14
provided that no Party is considered to
be in default with respect to contractual
obligations, other than payment of
money due, if it is prevented from
fulfilling such obligations by a Force
Majeure event. The affected Party is to
exercise due diligence to remove the
disability and provide adequate notice
to the other Party. These provisions are
consistent with those in the LGIA. The
Commission requested comments
concerning whether a different
approach should be taken for Small
Generating Facilities.
Comments
379. AEP, BPA, Idaho Power, and
Nevada Power generally agree that all
generating facilities should be treated
the same with respect to Force Majeure.
AEP argues that because Force Majeure
can happen for either type of
interconnection, there is no reason that
the contractual protection should differ
according to generator size. Nevada
Power contends that consistent
treatment does not interfere with having
a simplified and expedited
interconnection process for Small
Generating Facilities.
380. While NARUC’s Model and the
Proposed SGIA included similar Force
Majeure clauses, NARUC recommends
that the Commission remove the
statement that economic hardship is not
considered a Force Majeure Event. It
also proposes that the Commission
require that an affected Party use
‘‘reasonable efforts’’ instead of ‘‘due
diligence’’ to resume its performance as
soon as possible. Additionally, NARUC
proposes changing the definition of
Force Majeure to include events that
‘‘the affected Party is unable to prevent
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
or provide against by exercising
reasonable diligence.’’ 115
each generator to ensure safe and
reliable operation.
Commission Conclusion
Commission Conclusion
387. We are requiring the
Interconnection Customer’s Small
Generating Facility to maintain a power
factor within the range of 0.95 leading
to 0.95 lagging, unless the Transmission
Provider establishes and the
Commission approves different
requirements that apply to all similarly
situated generators. There is no reactive
power requirement for wind powered
Small Generating Facilities.
388. Generator Balancing
Requirements—The Proposed SGIA did
not include a separate generator
balancing provision.
381. We agree with NARUC that some
modification to the Proposed SGIA is
needed and we are adopting a Force
Majeure clause that melds the best
aspects of NARUC’s and the
Commission’s proposals. For instance,
this Final Rule provision allows the
Party asserting the Force Majeure Event
to call or write to the other Party to
make the required notification. Easy
notification ensures that both Parties
know of a Force Majeure Event as soon
as possible.
382. We are not adopting all of
NARUC’s proposals, however. The
NARUC Model would not allow a Party
to invoke Force Majeure if it could have
prevented the event through the
exercise of ‘‘reasonable diligence.’’ Our
SGIA uses the terms ‘‘negligence’’ and
‘‘intentional wrongdoing,’’ which are
commonly accepted legal terms.
383. Finally, we are moving the
definition of Force Majeure Event to the
body of the SGIA from an appendix.
384. Reactive Power—The Proposed
SGIA did not include a separate
provision for reactive power; however,
the LGIA does.
Comments
385. CA ISO and Southern Company
ask the Commission to include a
provision for reactive power in the
interconnection agreement. CA ISO
argues that this provision is essential for
the reliability of the Western
Interconnection because the entire
region is afflicted by voltage instability.
A Small Generating Facility
interconnecting at the transmission
level should meet the reactive power
requirements of the CA ISO tariff and
abide by reactive power dispatch
instructions from the control area
operator. Moreover, a Small Generating
Facility interconnecting at the
‘‘distribution’’ level should meet
reactive power requirements specified
in the Wholesale Distribution Access
Tariff and abide by any reactive power
dispatch instructions from the
Distribution System operator.
386. Southern Company notes that the
LGIA has a reactive power provision
and argues that one should be included
in the SGIA as well. Otherwise, a Small
Generating Facility could become a
burden on the Transmission Provider’s
electric system. The Transmission
Provider should be provided real-time
information on the status and output of
PO 00000
115 NARUC
Frm 00034
Model—Definitions.
Fmt 4701
Sfmt 4700
Comment
389. Southern Company argues that
the SGIA should include provisions for
generator balancing service, and
presents several arguments in support of
its position.
Commission Conclusion
390. In Order No. 2003–A, the
Commission determined that generator
balancing service is more closely related
to delivery service than to
interconnection service, and because
delivery service requirements are
addressed elsewhere in the OATT, the
balancing service requirement need not
appear in the interconnection
agreement. On rehearing, the
Commission in Order No. 2003–B did
not add a generator balancing service
provision to the LGIA, but it did permit
the Transmission Provider to include a
provision for generator balancing
service in individual interconnection
agreements. We reach the same
conclusion here.116 Any such provision
should be tailored to the Parties’
specific circumstances and is subject to
Commission approval.
391. Appendices to the SGIA—The
Proposed SGIA included five
appendices (called attachments in the
Final Rule SGIA) that set forth technical
and operating information, including:
(1) A description and statement of the
costs of the Small Generating Facility,
Interconnection Facilities, and metering
equipment; (2) a one-line diagram
depicting the Small Generating Facility,
Interconnection Facilities, metering
equipment and Upgrades; (3) project
milestones; (4) additional operating
requirements for the Transmission
Provider’s electric system and Affected
Systems needed to support the
Interconnection Customer’s needs; and
(5) the Transmission Provider’s
116 Order
E:\FR\FM\13JNR2.SGM
No. 2003–B at P 72–75.
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
description of its Network Upgrades and
Distribution Upgrades and a best
estimate of their costs.
Comments
392. Central Maine and NYTO state
that these appendices would require
information that is not needed. They ask
that the appendices include only: (1)
Small Generating Facility description,
(2) one-line diagram, (3) description of
the Interconnection Facilities, (4)
operation and maintenance (O&M)
costs, and (5) operating procedures.
They state that additional operating
procedures may have to be developed
with input from the Transmission
Owner and the Interconnection
Customer to ensure system integrity and
reliability.
Commission Conclusion
393. We are not persuaded that any
change in the appendices is warranted.
With the exception of O&M costs, all the
items that Central Maine and NYTO
would have us include in the
appendices are already there. We agree
with Central Maine and NYTO that
additional operating procedures with
input from both the Transmission
Provider and the Interconnection
Customer may be needed, and we
encourage such efforts. The treatment of
O&M costs is discussed in more detail
in Part II.H below (Responsibility for
Operation and Maintenance Costs).
G. The 10 kW Inverter Process
394. In the Small Generator
Interconnection NOPR, the Proposed
SGIP included a default interconnection
Study Process for Small Generating
Facilities and a simplified procedure
that used technical screens for certified
Small Generating Facilities no larger
than 2 MW. The Proposed SGIA,
however, would be used for the
interconnection of all Small Generating
Facilities, up to and including 20 MW
in size. The NOPR did not include a
separate procedures document or
interconnection agreement for very
small generators, although some
commenters urged, in comments
submitted in response to the ANOPR,
that 0–50 kW facilities (especially
facilities that use inverters to convert
the direct current output of the
generator to alternating current) need a
separate and simpler process than other
generators.
Comments
395. Some commenters argue that the
Proposed SGIP and Proposed SGIA are
too complicated for very small
Interconnection Customers. Small
Generator Coalition states that unless
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
the Commission is willing to modify the
NOPR in fundamental ways, many of its
members believe that development of
Small Generating Facilities would be
better served if the NOPR were simply
withdrawn. It claims that, under the
Proposed SGIP and Proposed SGIA, the
only method by which even a small
photovoltaic system, say 10 kW, could
interconnect with the Transmission
Provider is to follow the same process
that would apply to generators 1,000
times larger. It asks the Commission to
‘‘recognize the simplicity of the very
smallest generators and [to] include an
exception for small inverter-based
systems.’’ Plug Power, also representing
small generator interests, states that a
special process should be adopted for
very small generators because their
interconnection requirements are
fundamentally different from those of
larger facilities. Moreover, adopting
simpler requirements would foster the
growth of ‘‘plug and play’’ equipment.
396. NRECA, which represents a wide
variety of cooperative utilities that
interconnect with small generators,
states that it has adopted special
procedures for evaluating very small
generators because they generally
interconnect at low voltage and have
different technical requirements from
larger ones.
397. Some state regulatory authorities
already have a simplified process for
very small generators. NJ BPU points
out that it has adopted simplified
procedures for qualified very small
inverter-based generators. NARUC, in its
updated Model, supports a simplified
Interconnection Request (application)
for very small generators.
398. Joint Commenters submits in its
supplemental comments a streamlined
process for certified inverter-based
generators no larger than 10 kW. This
consists of a simplified Interconnection
Request, simplified procedures, and a
brief set of terms and conditions (that is
essentially a highly simplified
interconnection agreement )—all
contained in a single document. This
Joint Commenter proposal consists of
the following steps: (1) The
Interconnection Customer completes an
abbreviated Interconnection Request
and signs the terms and conditions
when it submits its Interconnection
Request to the Transmission Provider;
(2) the Transmission Provider uses the
Fast Track Process technical screens to
evaluate the Interconnection Request;
(3) if the proposed interconnection
passes the technical screens, the
Transmission Provider approves the
application; (4) once the
Interconnection Customer’s equipment
has been installed, it sends a certificate
PO 00000
Frm 00035
Fmt 4701
Sfmt 4700
34223
of completion to the Transmission
Provider; and (5) the Transmission
Provider then inspects the equipment
installation and, if satisfied that it is safe
for operation, authorizes the
interconnection.
Commission Conclusion
399. The comments demonstrate a
near universal agreement of the need for
special provisions for very small
generators, a need that is being met at
least in part by some state regulatory
authorities. We agree with the
commenters who state that the Proposed
SGIP and Proposed SGIA are too
complicated for very small generators,
and we recognize the desire to
accommodate their interconnection
needs. However, a single document
tailored for the needs of the smallest
generators would be unsuitable for the
interconnection of larger small
generators; their technical evaluations
and their legal rights and
responsibilities must be set out in
greater detail.
400. We conclude that a balanced
response to the comments is to issue
two sets of documents—an SGIP and
SGIA that serve the needs of most small
generators, and a simplified document
that meets the needs of very small
generators.
401. Joint Commenters’ proposed
process for the interconnection of very
small generators, which enjoys broad
support from a variety of stakeholder
interests, is simple to implement while
ensuring the safety and reliability of the
Transmission Provider’s electric system.
Accordingly, we are adopting it in this
Final Rule with minor modification
under the name ‘‘10 kW Inverter
Process.’’ The simplified 10 kW Inverter
Process consists of an Interconnection
Request, simplified procedures, and a
brief set of terms and conditions
applicable to inverter-based 0–10 kW
generators. It is included as Attachment
5 to the SGIP. This ‘‘all-in-one’’
document combines the attributes of
both an interconnection procedures
document and an interconnection
agreement. We are including it in the
SGIP because it is the SGIP that the
Interconnection Customer will first
encounter in the process of
interconnecting its Small Generating
Facility with the Transmission Provider.
A flowchart showing the 10 kW Inverter
Process may be found in Appendix D of
this Final Rule.
402. The 10 kW Inverter Process is
user friendly and a straightforward
interconnection should be
accomplished in short order. To
accelerate the process, by signing the
application at the time of submission,
E:\FR\FM\13JNR2.SGM
13JNR2
34224
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
the Interconnection Customer executes
what essentially is an interconnection
agreement, in the form of standard terms
and conditions with which it agrees.
This eliminates the additional step of
signing an interconnection agreement if
the proposed interconnection passes the
screens.
403. The 10 kW Inverter Process, by
its very name, applies only to
equipment that is interconnected with
the Transmission Provider’s electric
system through an inverter. Inverterbased equipment has a very small
likelihood of causing safety and
reliability concerns on the Transmission
Provider’s electric system because it can
quickly disconnect from the electric
system when a disturbance occurs.
Nonetheless, while the 10 kW Inverter
Process should facilitate the
interconnection of this class of Small
Generating Facilities, the technical
requirements for interconnection are
just as rigid as those for all Small
Generating Facilities up to 2 MW in size
that elect to use the Fast Track Process.
Specifically, they must be certified by a
Nationally Recognized Testing
Laboratory and the proposed
interconnection must pass the technical
screens. Consequently, interconnections
will not be permitted if they jeopardize
the safety and reliability of the
Transmission Provider’s electric system.
404. Although the Interconnection
Customer signs an abbreviated set of
terms and conditions when it submits
its Interconnection Request under the 10
kW Inverter Process, it is a legal
instrument nonetheless. Its provisions
are consistent with the SGIA. Should a
dispute arise, we encourage the Parties
to use this rulemaking for assistance in
interpreting the terms and conditions of
the 10 kW Inverter Process. Moreover,
because the intent of the terms and
conditions in this document are the
same as those of the SGIA, no separate
discussion of them is necessary here
again in this Final Rule.
405. The 10 kW Inverter Process is
quick, inexpensive, and user friendly.
Including it in this Final Rule removes
barriers to the development and
interconnection of this class of Small
Generating Facilities, both at the federal
and state jurisdiction levels. Its
adoption should promote
standardization of interconnection rules
across the nation. We encourage states
that do not have interconnection
procedures for very small generators to
consider using this as a model for their
own rules.
H. Other Significant Issues
406. A number of issues, such as
interconnection pricing policy,
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
variations permitted for independent
transmission entities, and legal issues
such as liquidated damages, transcend
individual provisions of the SGIP and
SGIA. Accordingly, we address them
below.
Pricing/Cost Recovery for
Interconnection Facilities and Upgrades
(Proposed SGIA Article 5.1)
407. In the Small Generator
Interconnection NOPR, the Commission
proposed to retain its then existing
pricing policy for the interconnection of
a Generating Facility with a
Transmission System that is operated by
a non-independent entity. That policy,
as set forth in Order No. 2003, was to
allocate the costs of the new or
upgraded transmission facilities based
on a locational test: Whether they are at
or beyond the Point of Interconnection.
Facilities that are on the Small
Generating Facility’s side of the Point of
Interconnection would be considered
Interconnection Facilities, while those
that are at or beyond the Point of
Interconnection would be considered
Network Upgrades. The Interconnection
Customer would be directly assigned
the costs of all Interconnection Facilities
because they are sole use facilities. The
Interconnection Customer would
initially fund the Network Upgrades
required for the interconnection unless
the Transmission Provider chooses to
pay for them itself. However, the
Interconnection Customer would be
entitled to a refund equal to the total
amount paid to the Transmission
Provider and the Affected System
operator, if any, for Network Upgrades,
including any tax-related payments.
Order No. 2003 called for these refunds
to be paid to the Interconnection
Customer, with interest, as credits on a
dollar-for-dollar basis for the non-usage
sensitive portion 117 of transmission
charges, as payments are made under
the Transmission Provider’s tariff and
the Affected System’s tariff for any
transmission services taken by the
Interconnection Customer on the
respective systems, whether or not the
Generating Facility is the source of the
power being transmitted.118 Order No.
2003 permitted the Interconnection
Customer, Transmission Provider, and
Affected System operator to adopt any
alternative payment schedule that is
117 Non-usage sensitive transmission charges
include all transmission charges except those for
items that vary with the amount of power
transmitted, such as congestion charges, line losses,
and Ancillary Services.
118 In Order No. 2003–A, this policy was revised
to make credits available only for transmission
service that has the generating facility as the source
of the power transmitted.
PO 00000
Frm 00036
Fmt 4701
Sfmt 4700
mutually agreeable provided all
amounts paid by the Interconnection
Customer for Network Upgrades are
refunded, with interest, within five
years of the generating facility’s
commercial operation date.119 The
Interconnection Customer would be
allowed to assign its refund rights to any
person.
408. Because a Small Generating
Facility may interconnect with a
Transmission Provider’s Distribution
System subject to an OATT in order to
make a sale of electricity at wholesale in
interstate commerce, the Small
Generator Interconnection NOPR also
addressed cost recovery for Distribution
Upgrades at or beyond the Point of
Interconnection.120 Consistent with
Order No. 2003, the Commission
proposed that the costs of Distribution
Upgrades be directly assigned to the
Interconnection Customer because
Distribution Upgrades do not generally
benefit all users.
409. The Commission sought
comments on whether this approach
should also apply to Small Generating
Facilities. The Commission also invited
commenters to recount their recent
experiences with interconnecting small
generators with the ‘‘Distribution
System,’’ in particular the process for
determining whether Distribution
Upgrades are necessary, and the cost
assignment of those Upgrades.
410. For a Transmission Provider that
is an independent entity, such as an
RTO or ISO, the Commission’s policy,
as adopted in Order No. 2003, is to
allow more pricing flexibility, subject to
Commission approval. Also in Order
No. 2003, we permitted a Regional State
Committee to establish criteria that an
independent entity would use to
determine which Network Upgrades
should be subject to ‘‘participant
funding.’’ Order No. 2003 also
permitted, for a period of transition to
the start of RTO or ISO operations, not
to exceed a year, participant funding to
be used for Network Upgrades as soon
as an independent entity has been
approved by the Commission and the
affected states. In the Small Generator
Interconnection NOPR, the Commission
proposed to adopt the same policies for
Small Generating Facilities that
interconnect with a Transmission
System operated by an independent
entity. The Commission sought
comments on this approach.
119 The five year refund period was subsequently
changed to 20 years in Order No. 2003–B.
120 The costs of all Interconnection Facilities,
whether owned by the Interconnection Customer or
the Transmission Provider, are directly assigned to
the Interconnection Customer.
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
411. In the Small Generator
Interconnection NOPR, the Commission
also proposed certain pricing provisions
that are consistent with, but have no
direct parallel with, the Order No. 2003
pricing provisions. The Proposed SGIA
provided that costs associated with
Interconnection Facilities could be
shared with other entities that may
benefit from such facilities by agreement
of the Interconnection Customer, such
other entities, and the Transmission
Provider. It also proposed that, if the
Parties agree that the Small Generating
Facility benefits the Transmission
Provider’s electric system, the
Interconnection Customer’s cost
responsibility for the Transmission
Provider’s Interconnection Facilities or
Upgrades would be reduced. The
benefits would have to be measurable
and verifiable. Where there are multiple
Interconnection Requests and each
requires Network Upgrades,
Interconnection Customers would be
assigned costs or benefits separately if
effects can be attributed to different
projects. Where such attribution is not
possible, Interconnection Customers
would share costs or benefits in
proportion to their projected Small
Generating Facility capacities.
Pricing Comments That the Commission
Already Addressed in the Large
Generator Interconnection Proceeding
Comments
412. Several commenters object to
various features of the Commission’s
current interconnection pricing policy,
presenting arguments that the
Commission has addressed in Order No.
2003. For example, Alabama PSC and
others argue that prohibiting the direct
assignment of the cost of Network
Upgrades means that native load
customers subsidize the cost of Network
Upgrades that benefit only the
Interconnection Customer. They argue
that this may also cause the
Interconnection Customer to make
inefficient siting decisions. Mississippi
PSC objects to the requirement that the
Transmission Provider pay interest on
unused credits and that it make a lump
sum payment to the Interconnection
Customer for credits that remain unused
after five years. Alabama PSC argues
that transmission credits should be
provided only for Network Upgrades
that provide a system benefit and only
when the Small Generating Facility is
the source of power for the transaction.
413. NRECA argues that if a merchant
generator has not committed to serve
network and native load customers
within the Transmission Provider’s
footprint on a long-term basis, the
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
generator and the Transmission
Provider’s own generators are not
comparable. It asserts that credits are
appropriate only where the Small
Generating Facility is committed to
customers in the Transmission
Provider’s footprint.
414. Central Maine requests
clarification that transmission credits
should be required only when the
Interconnection Customer is taking and
paying for transmission service on the
Transmission System on which the
Network Upgrade was made for the
output of its facility. Central Maine also
requests clarification that cost
responsibility for Network Upgrades
required by an Affected System is
consistent with cost responsibility for
Network Upgrades required by the
Transmission Owner with whom an
Interconnection Customer is directly
interconnecting; that is, that
transmission credits are required only
when the Interconnection Customer
takes and pays for transmission service
from the Transmission Owner or
Affected System for the output of its
facility. It also asks that the contractual
provisions concerning cost
responsibility and payment obligations
among Affected Systems and
Interconnection Customers be in a
separate agreement, not in the
interconnection agreement.
415. Avista, Alabama PSC, and
Mississippi PSC argue that allowing
pricing flexibility to an independent
Transmission Provider such as an RTO
or ISO is unduly discriminatory. They
state that this policy penalizes the retail
customers of the non-independent
Transmission Provider because it forces
them to bear the cost of Network
Upgrades that benefit only the
Interconnection Customer. Idaho Power
argues that having different pricing for
an independent and a non-independent
Transmission Provider is bad public
policy, arbitrary and capricious, and
discriminatory. TAPS states that the
NOPR incorrectly proposes participant
funding for Upgrades to a Transmission
System operated by an independent
entity.
Commission Conclusion
416. All of the comments summarized
above relate to the Commission’s
general pricing policy, and each was
discussed in Order No. 2003.121 We
adopt here the general conclusions
adopted in those orders. However, those
orders did not address the specific
question of whether the Commission’s
121 See Order No. 2003 at P 675–750, Order No.
2003–A at P 562–697, and Order No. 2003–B at P
15–57.
PO 00000
Frm 00037
Fmt 4701
Sfmt 4700
34225
general interconnection pricing policy is
suitable for Small Generating Facilities.
Several commenters raise this question,
and we address their comments below.
Applicability of the Commission’s
Interconnection Pricing Policy to the
Interconnection of Small Generating
Facilities
Comments
417. Several commenters support the
use of the Commission’s current
interconnection pricing policy. Western
supports the Commission’s proposal to
have the Interconnection Customer
initially fund interconnections and
associated Transmission System
improvements and states that this
approach is consistent with the
budgetary realities that Western faces.
Georgia PSC agrees that Interconnection
Facilities are sole use facilities and,
accordingly, should be directly assigned
to (paid for by) the Interconnection
Customer.
418. Nevada Power states that
interconnection pricing policies must be
consistent for both Small and Large
Generating Facilities to avoid the
possibility of pricing manipulation. It
opposes credits for facilities that do not
increase transfer capability, but states
that the requirement that the
Interconnection Customer initially fund
the Network Upgrade costs is an
important safeguard to ensure that the
Transmission Provider and other
customers do not subsidize what would
otherwise be an uneconomic project.
SoCal Edison states that the Small
Generator Interconnection NOPR
correctly mirrors the Large Generator
Final Rule with respect to the pricing
policies for Network Upgrades and sole
use Interconnection Facilities. BPA
generally supports consistency between
pricing for Small and Large Generating
Facility interconnections, provided the
Commission clearly articulates the
physical boundary between
Interconnection Facilities and Network
Upgrades.
419. AEP and Midwest ISO agree that
an independent Transmission Provider
should be allowed interconnection
pricing policy flexibility, subject to
Commission approval. Midwest ISO
states that few circumstances would
warrant an approach for Small
Generating Facilities that differs from
the approach that an RTO would
establish for a Large Generating Facility.
A common approach makes good
business sense, assures comparability
and makes the interconnection process
more effective. Also, BPA generally
supports RTO pricing flexibility,
provided it does not conflict with an
E:\FR\FM\13JNR2.SGM
13JNR2
34226
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
RTO’s obligations under its governing
agreements.
420. Cummins, however, argues that
the Commission should adopt different
pricing rules for Small Generating
Facilities because the Commission’s
current policy gives the Transmission
Provider the discretion to place a huge
cost burden on the Small Generating
Facility. These costs may even exceed
the installation and operating costs of a
Small Generating Facility, completely
destroying project economics. Cummins
argues that this problem can be
addressed only by specific performance
standards (which Cummins does not
describe) that only the Commission can
establish. Also, if the Interconnection
Customer is deemed to be the only
beneficiary of the Upgrade or
interconnection, the five year refund
mechanism would be of no benefit, as
the project would not go forward.
421. The Small Generator
Interconnection NOPR asked for specific
examples of situations where a
Transmission Provider has seemingly
applied excessive fees for Upgrades.
Cummins describes two examples that
highlight its concerns:
A manufacturer installed a 300 kW
synchronous generator and cogeneration
system, and provided the interconnection
equipment specified by the [Transmission
Provider]. The system was approved by the
[Transmission Provider] and went into
successful operation. When the owner
decided to expand the facility to include a
second 300 kW generator, they were
informed that the distribution system would
need upgrades that would cost in excess of
$140,000. On further investigation, it was
learned that the upgrades included only
‘‘block closing’’ provisions on a recloser. This
device is effectively a simple voltage sensing
relay that would interconnect into the
existing infrastructure at a substation. After
intensive negotiations and investigations, the
customer was able to get the cost reduced to
under $50,000, and the project went forward.
The $50,000 cost was still far more than the
upgrade should have cost, but the customer
was forced to pay it because the generator
was key to the viability of the customer’s
business. This represented a 10% increase in
the overall project.
In another case, a customer installed a 2
MW synchronous generator with equipment
that allowed it to parallel with the utility for
1/10th of a second. The equipment included
timer functions that prevented the machine
from staying in parallel for more than 1
second, as required by local rules. The
[Transmission Provider], unsatisfied with the
‘‘quality’’ or ‘‘performance’’ of the relay in
the customer’s device, forced the customer to
install a new relay costing over $2,000 for the
1 second time function. This was an
excessively expensive piece [of] equipment
to perform a simple operation; however the
Interconnection Customer needed the
equipment to operate, and had to pay the
price.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
422. Small Generator Coalition argues
that the Small Generator
Interconnection NOPR’s cost allocation
provisions appear to guarantee
pancaked wheeling charges on energy
produced by Small Generating
Facilities, contrary to the Commission’s
goal of eliminating such pancaking.122
423. MidAmerican states that a
Commission rule requiring a
Transmission Provider to pay any
interconnection-related costs could
supersede state policy and also would
affect the ability of states to set retail
rates following well-established cost
causation principles. MidAmerican
argues that the rules should permit the
Transmission Provider to directly assign
all costs to the Interconnection
Customer unless that violates state
regulatory policy.
Commission Conclusion
424. We recognize that the
Interconnection Facilities, Distribution
Upgrades, and Network Upgrades
required to interconnect a generator can
be costly. Indeed, such costs can be a
significant portion of the total project
costs. Nevertheless, each Generating
Facility, whether large or small, must
bear its fair share of the cost of the
facilities and Upgrades from which it
benefits; otherwise, the facility simply
does not make economic sense.
425. To this end, the Small Generator
Interconnection NOPR proposed to
apply to Small Generating Facility
interconnections the same pricing
policy that the Commission adopted for
Large Generating Facilities in Order No.
2003. Among other things, this means
that the Interconnection Customer must
bear the cost of necessary
Interconnection Facilities and
Distribution Upgrades. Also, the
Interconnection Customer must initially
fund the cost of Network Upgrades, but
is entitled to credits against its charges
for transmission delivery service equal
to the amount funded, plus interest.
None of the arguments presented here
convinces us that the policies adopted
in Order No. 2003 should not also apply
to Small Generating Facility
interconnections. In particular, contrary
to the assertions of Cummins and Small
Generator Coalition, we do not view the
policy as creating rate pancaking or an
undue burden for the Small Generating
Facility. Thus, we adopt the Order No.
2003 pricing policies for small generator
interconnections in this Final Rule.
122 By ‘‘pancaking,’’ we presume that Small
Generator Coalition is referring to the possibility
that the Interconnection Customer may be required
to pay for Distribution Upgrades and to make an upfront payment for Network Upgrades.
PO 00000
Frm 00038
Fmt 4701
Sfmt 4700
426. With regard to Cummins’s
concern that the Transmission Provider
may be able to force the Small
Generating Facility to bear unreasonable
costs, we note that our principal
purpose in adopting a standardized
procedures document and agreement for
generator interconnections, and making
them part of the Transmission
Provider’s tariff, is to eliminate much of
the opportunity for the Transmission
Provider to act in this manner. Indeed,
adoption of this Final Rule should
greatly reduce the likelihood of the two
negative experiences that Cummins
describes, if indeed the cost were
unreasonable.
427. In response to MidAmerican, this
Final Rule applies only to generator
interconnections that are under the
jurisdiction of the Commission. It does
not apply where we do not have
jurisdiction. Although state regulators or
other rate-making authorities may
model their own policies after those
adopted herein, or the similar NARUC
Model, they are free to establish
whatever rules for determining cost
responsibility that they deem reasonable
for interconnections under their
jurisdiction.
428. The Commission modified and
clarified its pricing policy for Large
Generator Interconnections in Order
Nos. 2003–A and 2003–B, which were
issued after the Small Generator
Interconnection NOPR in this
proceeding. Upon review of the
revisions to the Commission’s pricing
policy included in those orders, we
conclude that they should apply to the
interconnection of Small Generating
Facilities as well. Therefore, we are
revising the Proposed SGIA to reflect
our current interconnection pricing
policy as modified by Order Nos. 2003–
A and 2003–B. (See articles 4 and 5 of
the SGIA).
Implementation of the Interconnection
Pricing Policy for Small Generating
Facilities
Comments
429. Midwest ISO notes that Chart 1
of the Proposed SGIP shows a difference
between the Point of Interconnection
and the ‘‘point of common coupling’’ 123
and says that equipment Upgrades may
sometimes be needed between these two
points. Midwest ISO asks who is to be
responsible for such Upgrades and
whether transmission service credits
will be provided to the Interconnection
Customer if it finances the Upgrades.
430. Empire District agrees that
Upgrades that are directly assigned,
123 The term ‘‘Point of Common Coupling’’ is not
used in the SGIP and SGIA.
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
such as radial extensions to the
generator, should not be paid for (or
reimbursable to the Interconnection
Customer) by the Transmission
Provider. In addition, it states that
interconnection costs should be treated
in a manner similar to the crediting
methods used by the Southwest Power
Pool (which Empire District does not
describe).
431. Many commenters support the
Commission’s proposal to directly
assign the cost of Distribution Upgrades
to the Interconnection Customer.124 For
example, AEP states that a Distribution
Upgrade that is required to
accommodate the proposed generator
does not benefit all users; rather, its sole
purpose is to accommodate one
customer. AEP contends, therefore, that
it is entirely reasonable for the
Interconnection Customer to be
responsible for the cost of the
Distribution Upgrade. Cinergy states
that such responsibility follows from the
radial nature of the Distribution System
and is consistent with the LGIA.
Baltimore G&E states that the
Commission must guarantee that
distribution utilities receive full cost
recovery from interconnecting Small
Generating Facilities to avoid
subsidization by retail customers.
432. Nevada Power agrees that the
cost of Distribution Upgrades should be
directly assigned to the Interconnection
Customer, but is concerned that
Proposed SGIA article 5.1.3 does not
adequately protect the Transmission
Provider from having to bear such costs.
This article could be construed to say
that wholesale transactions by the
Interconnection Customer change the
segment of the distribution facilities to
which the Interconnection Customer
connects into transmission facilities.
Nevada Power argues that the Proposed
SGIA definition of Transmission System
illustrates this concern: ‘‘Transmission
System shall mean the facilities owned,
controlled or operated by the
Transmission Provider or Transmission
Owner that are used to provide
transmission service under the Tariff.’’
An inference can be drawn that what
was previously a distribution facility is
now a transmission facility because it
provides transmission service, and is
therefore subject to the crediting
process. To address this concern,
Nevada Power proposes specific
changes to Proposed SGIA article 5.1.3.
433. SoCal Edison notes that in the
Small Generator Interconnection NOPR,
124 See, e.g., AEP, Alabama PSC, Baltimore G&E,
Central Maine, Cinergy, Consumers, MidAmerican,
Mississippi PSC, Nevada Power, NRECA, and SoCal
Edison.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
Distribution Upgrades and Network
Upgrades are both defined as being at or
beyond the Point of Interconnection.
Distribution Upgrades are defined as
upgrades to the Distribution System,
while Network Upgrades are defined as
upgrades to the Transmission System.
However, ‘‘Transmission System’’ is
defined to include any facility, be it
transmission or distribution, that is
subject to an OATT. Therefore, SoCal
Edison contends that because
‘‘Transmission System’’ is defined to
include portions of the Distribution
System, the definition of Network
Upgrades (in combination with other
provisions of the SGIP and SGIA) is
confusing. SoCal Edison argues that
keeping the terms Transmission System
and Distribution System distinct is
crucial. For this reason, the definition of
Transmission System needs to exclude
distribution facilities, which facilities
already are included in the term
Distribution System.
434. In a similar vein, PacifiCorp
argues that the definition of Network
Upgrades must be revised to prevent it
from being applied to Upgrades to a
Transmission Provider’s Distribution
System. The Proposed SGIA’s definition
of Network Upgrades could be read to
include Upgrades to radial feeders or
other facilities that are part of the
Transmission Provider’s Distribution
System. In PacifiCorp’s view, Network
Upgrades should include only Upgrades
to networked transmission or subtransmission facilities. Any Upgrades to
radial feeders or other facilities that
make up the Transmission Provider’s
Distribution System should be paid for
by the Interconnection Customer
without credits.
435. PSE&G states that the definition
of Network Upgrades should be
modified as follows: ‘‘[Network
Upgrades] shall mean the additions,
modifications and upgrades * * *
required (strike out ‘‘at or’’) beyond the
point at which the Interconnection
Customer interconnects to the
Transmission Provider’s or
Transmission Owner’s or distribution
owner’s (strike out ‘‘Transmission’’ and
add ‘‘Distribution’’) System to
accommodate the Generating Facility
* * *.’’
436. NRECA states that the
Commission has an important role in
determining whether facilities are
distribution or transmission. The
Commission should apply the sevenfactor test where there are disputes and
should not in doing so give undue
deference to state or public utility
classifications of facilities. As shown by
cases such as Arkansas Power &
PO 00000
Frm 00039
Fmt 4701
Sfmt 4700
34227
Light,125 the Commission may conclude
that a facility serves a transmission
function even if it is lower voltage and
serves a few end-use customers, if the
predominant use of the facility is to
provide wholesale transmission service.
437. In addition, NRECA seeks
clarification of the NOPR’s statement
that ‘‘if a proposed interconnection
passes either the super-expedited
screening procedures or the expedited
screening procedures, the
Interconnection Customer would have
no cost responsibility for Upgrades.’’
NRECA contends that this contradicts
article 5.1.3 of the Proposed SGIA
(Distribution Upgrades), and thus is
inconsistent with the Commission’s
proposal to require Distribution
Upgrades to be directly assigned to the
Interconnection Customer. Furthermore,
the statement would shift costs from the
Interconnection Customer to utilities
and their other customers. Also,
Cummins says that the proposal runs
counter to, or may confuse the
application of, screens that would
expedite the interconnection process.
438. Small Generator Coalition states
that although Proposed SGIA article
5.1.5 gives the Interconnection
Customer an opportunity to demonstrate
benefits to the Transmission Provider’s
electric system that would reduce the
Interconnection Customer’s costs, the
NOPR’s discussion of Distribution
Upgrades at P 72 appears to rule out any
cost reductions for Distribution
Upgrades. In addition, Small Generator
Coalition argues that ambiguous NOPR
provisions may permit Transmission
Owners to require the Interconnection
Customer to pay for Network Upgrades
with no compensation to the
Interconnection Customer or
consideration of network benefits.
Because downstream resources can
benefit system reliability, Small
Generator Coalition argues that the
Commission’s rule should allocate
Upgrade costs according to benefits to
all portions of an affected Transmission
System, including facilities operating at
distribution voltages.
439. Alabama PSC and Mississippi
PSC argue that distribution facilities
should be directly assigned. However,
because the Commission lacks
jurisdiction over distribution facilities,
cost responsibility for Distribution
Upgrades is an issue for state regulators
to address.
440. Midwest ISO notes that Proposed
SGIA article 5.1.5 provides that if the
Parties agree that the Small Generating
Facility benefits the Transmission
125 Arkansas Power & Light Co. v. FPC, 368 F. 2d
376 (8th Cir. 1966) (Arkansas Power & Light).
E:\FR\FM\13JNR2.SGM
13JNR2
34228
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Provider’s electric system, the
Interconnection Customer’s cost
responsibility may be reduced
accordingly. The Small Generator
Interconnection NOPR says that, if
multiple facilities are involved, pro rata
allocation of the costs or benefits must
be made. These provisions appear to
conflict with the NOPR’s proposal at P
71, which allows an RTO flexibility
with respect to interconnection pricing.
Commission Conclusion
441. With reference to Chart 1 of the
Proposed SGIP, Midwest ISO asks who
is responsible for the cost of Upgrades
between the point of common coupling
and the Point of Interconnection. Chart
1 was in error. The Point of
Interconnection is the point identified
as the point of common coupling, which
is the point in the diagram where the
Interconnection Facilities connect to the
Transmission Provider’s Distribution
System subject to an OATT. Thus, the
Upgrades to which Midwest ISO refers
are in fact Interconnection Facilities,
and their cost is directly assigned to the
Interconnection Customer.
442. In response to Empire District,
we confirm that radial extensions to the
Small Generating Facility are to be
directly assigned to the Interconnection
Customer if they are Interconnection
Facilities; that is, if the radial line is a
sole use facility located between the
Small Generating Facility and the Point
of Interconnection, its cost is directly
assigned to the Interconnection
Customer. Also, Empire District
recommends that the Commission adopt
a crediting policy that is similar to the
methods set forth by the Southwest
Power Pool. However, Empire District
does not explain how its recommended
methods differ from or are better than
those proposed in the NOPR.
443. In order to eliminate the
confusion expressed by Nevada Power,
SoCal Edison and others about the
distinction between Distribution
Upgrades and Network Upgrades, we
are adding the following sentence to the
definition of Network Upgrades:
‘‘Network Upgrades do not include
Distribution Upgrades.’’
444. NRECA seeks clarification of the
Small Generator Interconnection
NOPR’s statement that ‘‘if a proposed
interconnection passes either the superexpedited screening procedures or the
expedited screening procedures, the
Interconnection Customer would have
no cost responsibility for Upgrades.’’
The issue of who pays for an Upgrade
in the case of a proposed
interconnection passing all the screens
is moot because one of the provisions of
SGIP section 2.2.1 is a requirement to
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
pass a screen that the interconnection
must not require an Upgrade.
445. Small Generator Coalition is
concerned that the Proposed SGIA may
assign to the Interconnection Customer
cost responsibility for Interconnection
Facilities in a way that gives no
recognition to the benefits that the
Interconnection Facilities may bring to
the Transmission Provider’s electric
system. In response, we clarify that the
Interconnection Customer is responsible
for the cost of Interconnection Facilities
except when such cost is shared with
other entities that may benefit from the
Interconnection Facilities by agreement
of the Interconnection Customer, the
other entities, and the Transmission
Provider. This provision for cost sharing
is included in SGIA article 4.1.1.
446. Small Generator Coalition also
asks about sharing cost responsibility
for Distribution Upgrades and initial
funding responsibility for Network
Upgrades. The Interconnection
Customer is responsible for the upfront
funding of Network Upgrades unless the
Transmission Provider elects to provide
the upfront funding itself. This payment
option is included in SGIA article 5.2.
However, we are not adopting the
explicit cost sharing provisions of
Proposed SGIA article 5.1.5 relating to
Distribution Upgrades because they are
not consistent with Order No. 2003
which specified that all Distribution
Upgrades shall be directly assigned to
the Interconnection Customer.126
447. In response to Midwest ISO, we
clarify that we are allowing flexibility
for the pricing that an independent
Transmission Provider may propose to
adopt, subject to Commission approval,
under the ‘‘independent entity’’
variation. Accordingly, an independent
Transmission Provider may propose a
pricing method that differs from what
this Final Rule otherwise requires.
448. Alabama PSC and Mississippi
PSC assert that cost responsibility for
Distribution Upgrades is beyond the
scope of the Commission’s authority. As
explained above, the Commission’s
assertion of jurisdiction here is no
broader than in Order No. 888. This
Final Rule applies to interconnections
with a Transmission System or with a
Distribution System subject to an OATT
for the purpose of making wholesale
sales. The Commission’s authority over
such interconnections with Distribution
Systems, for the purposes of making a
wholesale sale of electricity in interstate
commerce, includes allocating the cost
of all of the Transmission Provider’s
LGIA article 11.3 (‘‘The Interconnection
Customer shall be responsible for all costs related
to Distribution Upgrades.’’)
PO 00000
126 See
Frm 00040
Fmt 4701
Sfmt 4700
Upgrades needed to effect the
interconnection. Otherwise, the
Commission could not ensure that the
costs incurred to provide a
jurisdictional service are allocated
appropriately. The pricing policy for
Distribution Upgrades directly assigns
costs to the Interconnection Customer so
there is no impact on retail customers of
the Distribution System.
Responsibility for Operation and
Maintenance Costs
449. Proposed SGIA article 5.1.4
stated that the Interconnection
Customer is responsible for the
operating and maintenance costs
associated with the Interconnection
Facilities that it owns as well as those
owned by the Transmission Provider.
The Proposed SGIA did not assign
responsibility for O&M costs associated
with Network Upgrades or Distribution
Upgrades.
Comments
450. Central Maine and NYTO ask the
Commission to clarify that the
Interconnection Customer is responsible
for ongoing O&M costs associated with
Network Upgrades when the
Interconnection Customer does not take
and pay for transmission service for the
output of its Small Generating Facility.
451. Southern Company contends that
Proposed SGIA article 5.1.4
contemplates that the Interconnection
Customer is responsible for all
reasonable expenses associated with
operating and maintaining its own
Interconnection Facilities and the
Transmission Provider’s
Interconnection Facilities, but it is
unclear whether all applicable O&M
costs are covered. It notes that LGIA
article 10.5 does not limit O&M cost
recovery to the Transmission Provider’s
Interconnection Facilities, but explicitly
provides that the Interconnection
Customer is responsible for all
reasonable O&M costs. Therefore,
Southern Company proposes to revise
article 5.1.4 to include Distribution
Upgrades so as to ensure that all
appropriate O&M costs are included.
452. Robert L. Carrey contends that
the Interconnection Customer should
pay only the O&M costs of the
Interconnection Facilities built on its
behalf. He argues that the
Interconnection Customer should not
have to pay for routine O&M costs
where no Interconnection Customer and
Transmission Provider share the same
poles and rights-of-way.
Commission Conclusion
453. The Commission has long held
that O&M costs associated with Network
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Upgrades cannot be directly assigned to
the Interconnection Customer, because
Network Upgrades are part of the
integrated transmission system from
which all transmission users benefit.127
Therefore, we deny the requests of
Central Maine and NYTO that the
Commission require the Interconnection
Customer to pay O&M costs associated
with Network Upgrades.128
454. While the SGIA authorizes the
Transmission Provider to collect O&M
costs associated with Interconnection
Facilities, this Final Rule does not
contain a rate recovery mechanism for
collecting those costs, because such
costs will vary from case to case.
Therefore, if a Transmission Provider
wishes, it may propose and justify its
rate to recover such costs under section
205 of the FPA.129 In response to
Southern Company, a Transmission
Provider may make a similar filing to
recover from the Interconnection
Customer an appropriate share of any
Commission-jurisdictional component
of the O&M costs of Distribution
Upgrades. Absent Commission approval
of such a rate schedule, the
Transmission Provider may not collect
Commission-jurisdictional O&M costs
associated with Interconnection
Facilities or Distribution Upgrades.
455. In response to Mr. Carrey, the
Transmission Provider is free to propose
to recover these expenses in any manner
it sees fit; however, the Commission
will approve the Transmission
Provider’s proposed rate if it is shown
to be just and reasonable and not
unduly discriminatory or preferential.
Responsibility for the Construction of
Upgrades
456. Proposed SGIA article 5.1.2
stated that the Transmission Provider or
Transmission Owner shall design,
procure, construct, install, and own the
Network Upgrades.
Comments
457. PacifiCorp states that the Parties
should be permitted to agree that the
Network Upgrades will be built by the
Interconnection Customer on its land.
127 See, e.g., PJM Interconnection, L.L.C., 109
FERC ¶ 61,326 (2004) (holding that O&M costs
associated with Network Upgrades may not be
directly assigned to the Interconnection Customer).
We note, however, that the Transmission Provider
may propose to recover the cost of Network
Upgrades from the Interconnection Customer
through an incremental transmission rate. In that
case, the Commission would entertain a proposal to
include in the incremental rate O&M costs
associated with the Network Upgrades. Order No.
2003–B at P 57.
128 This issue was discussed at P 421–424 of
Order No. 2003–A.
129 16 U.S.C. 824d (2000); see also 18 CFR 35.12
(2004).
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
This could facilitate a faster
interconnection. In addition, Proposed
SGIA article 3.3 should be revised to
give the Transmission Provider the right
to inspect, operate, or maintain Network
Upgrades on the Interconnection
Customer’s land.
458. AMP-Ohio states that, in the
region where its members’ Distribution
Systems are located, the Transmission
Provider would be an RTO. It notes that
Proposed SGIA article 5.1.3 stated that
the ‘‘Transmission Provider or
Transmission [Owner] shall design,
procure, construct, install, and own the
distribution Upgrades * * *’’ AMPOhio is concerned that this article could
be construed to allow the RTO to own
and operate piecemeal sections of a
member’s electric system. The
Commission should clarify that one
entity cannot assert the right to own a
portion of another’s electric system.
Commission Conclusion
459. In response to PacifiCorp, neither
Proposed SGIA article 5.1.2 nor article
5.1.3 precluded the Parties from
agreeing that the Interconnection
Customer may construct Network
Upgrades or Distribution Upgrades on
its own land. Nevertheless, we make
this option explicit in SGIA articles 4.2
and 5.2. PacifiCorp’s proposed revisions
to Proposed SGIA article 3.3 are
addressed above in our discussion of
that article.
460. In response to AMP-Ohio, we
clarify that this Final Rule does not
authorize any entity, including the
Transmission Provider, to own a portion
of another entity’s Transmission System
without the permission of the
Transmission Owner.
Miscellaneous Pricing Issues
Comments
461. PacifiCorp notes that Proposed
SGIA article 5.1.2.1 would permit a
refund to an Interconnection Customer
whose Small Generating Facility does
not achieve commercial operation, if
another customer uses the Network
Upgrades for which the first
Interconnection Customer paid.
PacifiCorp asks that this provision
specify that a refund is available only if
the second Interconnection Customer
actually requires the Network Upgrades
for its Small Generating Facility.
462. TAPS states that the NOPR does
not make the Transmission Provider
remove its own Interconnection
Facilities from rate base.
Commission Conclusion
463. We agree with PacifiCorp that the
first Interconnection Customer should
not receive a refund of amounts it has
PO 00000
Frm 00041
Fmt 4701
Sfmt 4700
34229
advanced for Network Upgrades unless
the later Interconnection Customer’s
Small Generating Facility actually
would have required the construction of
the Network Upgrades. However we
believe that the SGIA, as written, makes
this clear. To make a change to this
provision would imply that it means
something different from the similar
provision adopted in the LGIA, and that
is not our intent, therefore we decline to
accept PacifiCorp’s proposed
modification.
464. With regard to the issue that
TAPS raises, the Commission addressed
this matter in Order No. 2003. There the
Commission required the Transmission
Provider to remove from transmission
rates the costs of Interconnection
Facilities constructed by the
Transmission Provider after March 15,
2000 to interconnect generating
facilities owned by the Transmission
Provider on the effective date of the
Final Rule in the Large Generator
Interconnection proceeding.130 The
Commission’s conclusion about the
need for the Transmission Provider to
remove its own Interconnection
Facilities from rate base was not
intended to be limited to Large
Generating Facilities. We clarify here
that it applies to all of the Transmission
Provider’s Interconnection Facilities,
regardless of the size of the associated
generating facility.
Commission Jurisdiction Under the
Federal Power Act
465. Sections 205 and 206 of the FPA
require the Commission to remedy
undue discrimination by public
utilities. In Order No. 888, the
Commission found that public utilities
owning or controlling jurisdictional
transmission facilities had the incentive
to engage in, and had engaged in,
unduly discriminatory practices.131
Because interconnection is an element
of transmission service that must be
provided under the OATT, the
Commission in Order No. 2003
established generic interconnection
terms and procedures under its
authority to remedy undue
discrimination under sections 205 and
206.132 The Small Generator
Interconnection NOPR proposed that its
jurisdictional reach would be identical
to Order No. 2003.
130 See Order No. 2003 at P 744 and Order No.
2003–A at P 663.
131 Order No. 888 at 31,679–84; Order No. 888–
A at 30,209–10.
132 Order No. 2003 at P 18–20.
E:\FR\FM\13JNR2.SGM
13JNR2
34230
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Comments
466. NARUC, NRECA, several state
regulatory commissions,133 and
others 134 argue that the Small Generator
Interconnection NOPR unlawfully
encroaches upon the jurisdiction of the
states by proposing to regulate
interconnections with ‘‘local
distribution’’ facilities.
467. Many of the commenters
opposing the Commission’s exercise of
jurisdiction over facilities used both for
Commission-jurisdictional and for statejurisdictional transactions (‘‘dual-use’’
facilities) cite Detroit Edison.135 They
appear to have read Detroit Edison as
forbidding the exercise of federal
jurisdiction over any facilities used to
any degree to distribute bundled power
to end-users at retail, regardless of
whether those facilities are also used for
transactions that are under the
Commission’s jurisdiction.136 Other
commenters, including Small Generator
Coalition and SoCal Edison,137 assert
that nothing in Detroit Edison prevents
the Commission from asserting
jurisdiction over all interconnections
made to facilitate Commissionjurisdictional activities.
468. Interconnections with
‘‘distribution’’ facilities, argues Alabama
PSC, should be exclusively statejurisdictional. It argues that ‘‘the Courts
have long recognized and enforced the
State’s primacy over the regulation of
distribution facilities.’’138 CPUC makes
a similar argument, stating that:
federal law was meant to supplement—and
not to supplant—state regulation of those
utilities. The FPA was enacted to fill in gaps
not covered by state regulation, not as a
mechanism for avoiding state regulation of
public utilities. In enacting the FPA,
Congress did not purport to exercise all of the
authority it might have exercised under the
Commerce Clause, because its intention was
to preserve, not override, state regulatory
jurisdiction.139
133 E.g., Alabama PSC, CPUC, CT PUC, Florida
PSC, Iowa Utilities Board, Mississippi PSC, North
Carolina Commission, and NYPSC.
134 E.g., Baltimore G&E, Central Maine,
Consumers, EEI, Idaho Power, PacifiCorp, Progress
Energy, and Southern Company.
135 Shortly before comments were due in this
docket, the DC Circuit issued Detroit Edison v.
FERC, 334 F.3d 48 (DC Cir. 2003) (Detroit Edison).
Since then, the Commission has issued both Order
Nos. 2003–A (at P 705 et seq.) and 2003–B (at P 14),
which discuss Detroit Edison at length.
136 Alabama PSC at 4–5 (citing 16 U.S.C. 824(b)
(2003), which states that ‘‘[t]he Commission * * *
shall not have jurisdiction * * * over facilities
used in local distribution * * *.’’)
137 Id. at 10 (emphasis in original).
138 Id. at 5 (citing Southern Co. Services, Inc. v.
FCC, 293 F.3d 1338, 1344 (11th Cir. 2002)).
139 CPUC at 8 (citing Conn. Light & Power Co. v.
FPC, 324 U.S. 515, 529–30 (1945)).
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
469. Alabama PSC, Mississippi PSC,
and Southern Company also cite the
preemption doctrine (that federal
preemption of state law is not to be
assumed unless Congress expresses a
clear intent to do so) as another reason
why the Commission is not permitted to
exercise jurisdiction over ‘‘distribution’’
facilities. ‘‘To the contrary,’’ Alabama
PSC argues, ‘‘the FPA expressly
provides that FERC does not have such
jurisdiction.’’ 140
470. CT PUC asks the Commission to
clarify that this Final Rule does not
preempt state regulatory authority with
respect to electric distribution company
regulation, environmental protection
(including Clean Air Act permitting),
fire and building safety regulation, etc.,
as these may apply to Small Generating
Facility interconnections with
‘‘distribution’’ facilities.
471. Idaho Power states that ‘‘[t]he
‘dual use’ theory leaves the
‘‘distribution’’ facility owner that is
trying to design an efficient and reliable
‘‘distribution’’ system in the untenable
position of having two masters
attempting to control the same physical
line for differing purposes.’’ 141
472. PacifiCorp cites forum shopping
concerns and suggests that a Small
Generating Facility interconnecting as a
Qualifying Facility (QF) to a dual use
facility could receive different treatment
depending on whether it sells its output
to the host utility under the Public
Utility Regulatory Policies Act of 1978
(PURPA)142 or to a customer other than
the host utility. In the first instance, the
interconnection would be statejurisdictional; in the second,
Commission-jurisdictional. PacifiCorp
asserts that this is a confusing outcome
and could be avoided if the Commission
disclaims jurisdiction over low voltage
and dual use facilities.
473. Small Generator Coalition argues
that not asserting jurisdiction over all
interconnections made to facilitate
Commission-jurisdictional activities
means adopting a circuit-by-circuit
approach to jurisdiction. This would be
contrary to the Commission’s approach
taken in a variety of contexts, including
assignment of system losses 143 and
recovery of fixed costs 144 on a systemwide basis. Further, if the Commission
allows a Transmission Provider to
refuse interconnections with the lowvoltage ‘‘distribution’’ portions of its
PSC at 6 (citing 16 U.S.C. 824(b)).
Power at 3.
142 16 U.S.C. 824a–3 (2004).
143 Small Generator Coalition at 37 (citing
Northern States Power Co. v. FERC, 30 F.3d 177 (D.
C. Cir. 1994)).
144 Id. (citing Fort Pierce Utilities Authority v.
FERC, 730 F.2d 778, 782 (DC Cir. 1984)).
PO 00000
140 Alabama
141 Idaho
Frm 00042
Fmt 4701
Sfmt 4700
system not already used for
jurisdictional transactions, ‘‘small
resource development would be
inhibited if not eliminated.’’ 145
Transmission Providers could ‘‘pick and
choose among interconnection
applicants based on any criteria they
elected to employ.’’ 146 Finally, Small
Generator Coalition argues that the
Commission adequately recognizes state
jurisdiction by claiming jurisdiction
over only interconnections with
‘‘distribution’’ facilities that are used for
wholesale transactions.
474. NRECA argues that, as more and
more distributed generators participate
in the wholesale market, ‘‘many if not
most distribution facilities will carry a
few wholesale electrons.’’ 147 Indeed,
‘‘many if not most distribution facilities
will become subject to Commission
jurisdiction. The jurisdictional divide
between the Federal Government and
the States that Congress clearly intended
in the FPA will have collapsed.’’ 148
Baltimore G&E asks the Commission to
explain how it will avoid a ‘‘chicken
and egg’’ situation where the
jurisdictional status of a particular
facility would change after the
interconnection takes place.
475. Solar Turbines expresses concern
that ‘‘[a] utility apparently need merely
deny that a particular line is currently
being used for any transmission of
power in interstate commerce or for any
sales for resale, and can then refuse to
accept an application for
interconnection to that specific
facility’’ 149 and requests that the
Commission clarify what the
Interconnection Customer should do if
it finds itself in such a situation.
476. MidAmerican asks whether this
Final Rule would apply to a net
metering arrangement that allows a
Small Generating Facility to net only a
portion of its output and resell the
remainder to the host utility. It also asks
what happens if it sells the non-net
metered portion of its output to a third
party.
477. Avista asks the Commission to
address the effect of Detroit Edison on
an interconnection for a purpose other
than to ‘‘engage in sale for resale in
interstate commerce or to transmit
electricity in interstate commerce.’’
Avista differentiates ‘‘load
interconnections’’ from ‘‘generator
interconnections,’’ which are
interconnections made to export power.
It requests clarification that a load
145 Id.
at 39.
at 39.
147 NRECA at 41.
148 Id.
149 Solar Turbines at 4.
146 Id.
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
interconnection to a dual use facility is
an exclusively state-jurisdictional
interconnection ‘‘except if and to the
extent there is an OATT on file by the
owner of the facilities that makes
available new Commissionjurisdictional service over those
facilities.’’ 150 Absent such a
clarification, Avista argues that
‘‘uncontrolled deregulation of service at
the distribution level may occur, since
any new load can seek to characterize
its service as ‘wholesale’ by inserting a
’sham utility’ between the customer and
the incumbent utility.’’ 151 Avista states
that FPA section 212(h) already
prohibits ‘‘sham wholesale
transactions’’ 152 and argues that ‘‘the
Commission has determined that
Section 212(h) only applies to
transmission orders, not interconnection
requests.’’ 153 Without such a
clarification, Avista fears that load
interconnections with dual use facilities
could be used to force otherwise nonCommission-jurisdictional
‘‘distribution’’ facilities into
Commission-jurisdictional status.
478. USCHPA and Solar Turbines ask
the Commission to exert jurisdiction
over all load interconnections.
Additionally, many cogeneration
projects, USCHPA asserts, make
sporadic sales of power when the
economics favor doing so. Such projects
should not be denied the benefits of
standardized interconnection rules
simply because their sales into the
wholesale energy marketplace are
sporadic. Solar Turbines argues that the
needs of Small Generating Facilities are
different and that there are good reasons
to depart from the large generator
precedent in this rulemaking.
Specifically, Small Generating Facilities
are more likely to be near to load, while
Large Generating Facilities are more
likely to be far from their load.
479. Midwest ISO argues that all
interconnections with ‘‘distribution’’
facilities within an RTO or ISO to sell
power at wholesale should be processed
under a single set of rules. This would
include both state- and Commissionjurisdictional facilities. Midwest ISO
remarks that regardless of ‘‘[w]hether
the physical requirements of the
interconnection come under the RTO’s
150 Avista
at 9.
at 9–10 (citing, e.g., Snake River Valley
Elec. Ass’n v. PacifiCorp, 238 F.3d 1189 (9th Cir.
2001)).
152 16 U.S.C. 824k(h) (2000).
153 Avista at 9–10 (citing Laguna Irrigation
District, 95 FERC ¶ 61,305 (2001), aff’d sub nom.
Pacific Gas & Electric Co. v. FERC, 44 Fed. Appx.
170 (9th Cir. 2002) (unpublished opinion); City of
Corona v. Southern California Edison Co., 101
FERC ¶ 61,240 at 62,025–026 (2002)).
151 Id.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
purview, the generating facility’s
operation will’’ come under the RTO’s
jurisdiction. Therefore, the RTO should
be able to ‘‘evaluate the proposed
interconnection with the generating
facility’s subsequent operation in
mind.’’ 154
480. Finally, several comments
address whether the use of a 69 kV
cutoff in the SGIP affects the
Commission’s jurisdiction.
Commission Conclusion
481. The Commission’s assertion of
jurisdiction in this Final Rule is
identical to the jurisdiction asserted in
Order Nos. 2003 and 888 and upheld by
the Supreme Court in New York v.
FERC. Just as the Commission stated in
Order No. 2003–A:
There is no intent to expand the
jurisdiction of the Commission in any way;
if a facility is not already subject to
Commission jurisdiction at the time
interconnection is requested, the Final Rule
will not apply. Thus, only facilities that
already are subject to the Transmission
Provider’s OATT are covered by this rule.
The Commission is not encroaching on the
States’ jurisdiction and is not improperly
asserting jurisdiction over ‘‘local
distribution’’ facilities.[155]
482. Many commenters seek
clarification of issues (particularly
related to the Detroit Edison case) that
were discussed at length in Order Nos.
2003–A and 2003–B, which were issued
after comments on the Small Generator
Interconnection NOPR were due.156
Since the jurisdiction asserted in this
Final Rule is identical to that asserted
in Order No. 2003, we adopt here our
discussion from those orders rather than
repeat the same information.
483. However, several commenters
focused on how the jurisdictional issues
raised by small generator
interconnections may differ from those
raised in the Large Generator
Interconnection rulemaking.
Additionally, some commenters raised
issues in this proceeding that were not
addressed in Order Nos. 2003–A or
2003–B. These issues we discuss in
more detail below.
484. We disagree with Alabama PSC,
Mississippi PSC, and Southern
Company that the Commission is
evading FPA section 201(b)(1) or
preempting state law. In New York v.
FERC, the U.S. Supreme Court approved
the Commission’s assertion of
jurisdiction in Order No. 888.157 The
applicability of this Final Rule is
ISO at 6.
No. 2003–A at P 700.
156 See Order No. 2003–A at P 698 et seq. and
Order No. 2003–B at P 12 et seq.
157 New York v. FERC, 535 U.S. 1 (2002).
PO 00000
154 Midwest
155 Order
Frm 00043
Fmt 4701
Sfmt 4700
34231
identical to the applicability of Order
No. 888.
485. CT PUC is correct that this Final
Rule in no way alters the permitting and
other environmental requirements
applicable to Interconnection
Customers. Nor does this Final Rule
affect any other state police powers.
486. NRECA asserts that while there
are now relatively few Small Generating
Facility interconnections that are
Commission-jurisdictional, that number
will increase as time passes. Small
Generator Coalition complains that the
number of lower voltage Commissionjurisdictional facilities is too small.
Ultimately, however, the Commission’s
jurisdiction does not rest on how
common dual use facilities may be or
how many interconnections are
Commission-jurisdictional.
487. Baltimore G&E asks if the
jurisdictional status of a facility would
change after an interconnection takes
place. Whether a facility is subject to
this rule depends on whether it is
subject to an OATT at the time the
Interconnection Request is filed. The
use of a facility and thus its inclusion
in an OATT can change over time.
Nothing in this Final Rule (or Order No.
2003) alters the status of any facility.
488. Avista is correct that some
interconnections are made simply to
receive power from the electric system.
These ‘‘load interconnections’’ are not
subject to this Final Rule.
489. In response to USCHPA’s
concern over Interconnection Customers
who may wish to make sporadic sales of
power into the marketplace, we clarify
that there is no requirement that an
Interconnection Customer’s
participation in the wholesale
marketplace be constant. An
Interconnection Customer is free to
request interconnection service and
then wait until the economics are
favorable before actually making a
wholesale sale.
490. In response to Midwest ISO’s
desire to process all interconnections
(whether to Commission-jurisdictional
or non-Commission-jurisdictional
facilities) under its tariff, we note that
the Commission does not have the
authority to order states to use Midwest
ISO’s tariff to process interconnections
with state or other non-jurisdictional
facilities. However, we encourage the
states and others to use the
Commission’s interconnection rule or
the NARUC Model as a starting point for
developing their own interconnection
rules.
491. Many commenters also address
the legality of the Small Generator
Interconnection NOPR’s proposed use of
69 kV to determine whether portions of
E:\FR\FM\13JNR2.SGM
13JNR2
34232
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
the SGIP would apply. Since the
Commission has abandoned this
distinction in this Final Rule, these
arguments are moot.
Arguments that the Commission Should
Delay or Abandon the Small Generator
Interconnection Rulemaking
492. Several commenters argue that
the Proposed SGIP and Proposed SGIA
are too complicated for small entities
and would create a barrier to entry.
Some commenters argue that the
Commission should delay issuing a
Final Rule and allow the various states
and other entities to develop their own
model rules. Others disagree.158
493. This Final Rule includes several
provisions to address these concerns.
First, we are adopting a separate
application/procedures/terms and
conditions document for very small
certified inverter-based Small
Generating Facilities. This is a big step
in facilitating quick interconnections at
very little cost, as long as they can be
made safely and without harming
reliability. We are also simplifying
many SGIA provisions at the request of
commenters. This Final Rule borrows
liberally from NARUC’s Model
interconnection rules, which are
simpler than the Small Generator
Interconnection NOPR.
494. We address below specific
comments relating to our decision to
proceed with this Final Rule. We have
divided commenters’ arguments into
three sections: (1) Arguments that the
Commission should defer to the states to
deal with small generator
interconnections; (2) arguments that the
Commission’s NOPR is too complex;
and (3) arguments that the Commission
should adopt a policy statement or
model rules instead of a Final Rule.
Arguments in Favor of Deferring to the
States on Small Generator
Interconnections
Comments
495. NARUC proposes that the
Commission adopt its Model, arguing
that it ‘‘would offer the greatest
possibility of consistency between
Federal and State interconnection
policies’’ 159 It explains that ‘‘the
NARUC Model was developed by
melding the best practices of existing
State distributed generation
interconnection programs.’’ 160 NARUC
158 CT DPUC at 1 (‘‘The CT DPUC generally
supports the effort by the Commission to initiate
standardization of interconnection agreements and
procedures * * * ’’); see also Cummins at 1 (‘‘We
strongly support the Commission’s continued work
in this area.’’)
159 NARUC at 18.
160 Id. at 8.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
argues in its supplemental comments
that state programs are successful and
that imposing an unnecessary layer of
federal regulation will be disruptive to
small generator developers and
customers. Commission action can only
create confusion and impede project
development. Because states have better
insight into local operating, planning,
safety, reliability, and adequacy needs
and conditions, they are in the best
position to address the interconnection
of small generators, regardless of what
those generators may do with the output
from their facilities or where they are
interconnected. At bottom, NARUC
urges the Commission to take no action
on the Small Generator Interconnection
NOPR. In the alternative, if the
Commission implements small
generator interconnection rules, it
should grandfather existing state
interconnection programs and the
interconnections accomplished under
such programs, and include a
mechanism for granting deference to
future state small generator
interconnection programs.
496. CPUC states that California, New
York, Ohio, and Texas all have
interconnection procedures applicable
to their state-regulated utility
‘‘distribution’’ systems.161 Because one
third of the country’s population
already lives in states with standard
interconnection rules, there is no need
for Commission action. It also contends
that (1) existing California
interconnection rules meet the needs of
small generators seeking to connect to
state-jurisdictional utility ‘‘distribution’’
systems, (2) California procedures
already provide small generators with
one-stop shopping, and (3) there is no
‘‘actual or legitimate need for FERC
assistance to cover interconnections to
state-jurisdictional facilities in states
where distributed generation
interconnection rules are already in
place.’’ 162
497. Furthermore, CPUC argues, only
state-specific interconnection rules can
account for ‘‘regional practices.’’ As an
example, CPUC’s rules allow it to
exempt small Transmission Providers,
but the Small Generator Interconnection
NOPR lacks such needed flexibility.163
In sum, CPUC questions the need for the
Commission’s proposal and asserts that
‘‘there is no legitimate public policy
basis for the assertion of FERC
jurisdiction over small generators that
161 Virginia, Massachusetts, and other states also
have small generator interconnection rules.
162 CPUC at 16.
163 Id. at 18.
PO 00000
Frm 00044
Fmt 4701
Sfmt 4700
would result if the FERC proposal were
adopted.’’ 164
498. In contrast, Cummins argues that
the Commission should assert
jurisdiction over all interconnections,
regardless of whether the
interconnection is with a Commissionjurisdictional facility. Cummins argues
that, although Small Generating
Facilities often connect at the
‘‘distribution’’ level, their effects can be
felt on the Transmission System. It
explains that, because Small Generating
Facilities can relieve congestion on
crowded transmission facilities, the
effect of even on-site Small Generating
Facilities is felt beyond the Point of
Interconnection. Thus, it is important
that the Commission use all its
jurisdictional authority to apply this
rule as broadly as possible. And, where
the Commission does not have
jurisdiction, Cummins encourages state
regulators to develop interconnection
rules that are consistent with this Final
Rule.
499. Plug Power claims that by not
proposing standards applicable to
interconnections with distribution
facilities, the Commission’s
interconnection rules will not help
small generators. Further, the rules
proposed in the NOPR are inferior to
those already in place in several states.
500. EEI urges the Commission to
work with states to better define the
state-federal role in small generator
interconnections. According to EEI, this
approach would provide both
Interconnection Customers and
Transmission Providers with clear
guidance as to which rules apply to
which interconnections. Finally, EEI
states that, with certain modifications,
the interconnection procedures
document and agreement could be a
model for use by both federal and state
authorities to process small generator
Interconnection Requests.
501. CT DPUC, while supporting the
Commission’s efforts, argues that this
Final Rule should not lead to a loss of
state jurisdiction.
Commission Conclusion
502. We agree with commenters that
general consistency between the
Commission’s interconnection
procedures document and agreement
and those of the states will be helpful
to removing roadblocks to the
interconnection of small generators. To
a large extent, this Final Rule
harmonizes state and federal practices
by adopting many of the provisions
proposed by NARUC and Joint
Commenters. This Final Rule adopts
164 Id.
E:\FR\FM\13JNR2.SGM
at 15.
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
interconnection rules that are largely
consistent with the ‘‘best practices’’
interconnection rules proposed by
NARUC. By doing so, we hope to
minimize the federal-state division and
promote consistent, nationwide
interconnection rules.165 We hope that
states that do not currently have
interconnection rules for small
generators will look to the documents
presented in this Final Rule and the
NARUC Model as guides for their own
rules. To grandfather existing state
interconnection programs and grant
deference to future state small generator
interconnection programs would not
fulfill the Commission’s statutory
mandate to regulate jurisdictional
activities, of which generator
interconnection is one. However, as
discussed elsewhere, the all-in-one
document for certified inverter-based
generators no larger than 10 kW should
go a long way towards harmonizing
state-federal interconnection practices
for this class of generators.
503. Our hope is that states may find
these interconnection rules helpful in
formulating their own interconnection
processes. In particular, we hope the
Fast Track and 10 kW Inverter Processes
will prove helpful as starting points
from which to develop their own
procedures and agreements.
504. The concerns of CPUC and
several other commenters that the
Commission is claiming jurisdiction
over interconnections with nonCommission jurisdictional facilities are
addressed elsewhere in more detail.
Arguments That the NOPR Is Too
Complex
Comments
505. CPUC argues that the Proposed
SGIA and Proposed SGIP are too
complicated for small Interconnection
Customers, especially the smallest, to
use. Small Generator Coalition argues
that unless the Commission is willing to
modify the NOPR in fundamental ways,
many of its members believe that
development of Small Generating
Facilities would be better served if the
NOPR were simply withdrawn.
According to Small Generator Coalition,
the NOPR’s framing of
interconnection issues as a competition
between maintaining system reliability and
encouraging small resources is wholly
inappropriate, and it gives disproportionate
weight to the reliability ‘concerns’ of
transmission/distribution owners with
generating units of their own. That system
reliability must not be compromised goes
without saying, but the need for system
reliability does not compete with the goal of
encouraging small resource development via
affordable and clear interconnection terms
and conditions. The compatibility of small
resources with the grid was proven long
ago—there are literally thousands of such
small resources in place and operating in the
United States, safely interconnected with the
grid (such as the solar array on the roof of
the Commission’s own office building).[166]
506. Small Generator Coalition says
that on-site Small Generating Facilities
actually enhance electric system
reliability, and that complex technical
provisions should therefore not be
required.
507. Plug Power asserts that unless
the Commission adopts a simpler SGIA,
the Commission’s rulemaking will not
help to reach national interconnection
standards.167 Of particular concern to
Plug Power are the Proposed SGIA’s
insurance requirements and what Plug
Power terms its open-ended cost
provisions.
508. CT DPUC urges the Commission
to adopt rules that are not unnecessarily
complicated to administer.
Commission Conclusion
509. We agree with commenters that
the Small Generator Interconnection
NOPR contained some provisions that
were overly complicated for many Small
Generating Facility interconnections.
Wherever possible, we have simplified
the SGIP and SGIA. And, for very small
certified Small Generating Facilities,
this Final Rule includes the highly
simplified 10 kW Inverter Process.
Arguments in Favor of a Non-Binding
Model Rule
Comments
510. CPUC states that it would
support Commission efforts to establish
non-binding guidelines, or a model rule,
for use by states that have not yet
adopted their own standards.
511. NARUC comments that any
standard interconnection procedures
document and agreement issued by the
Commission that disclaims jurisdiction
over ‘‘local distribution’’ facilities has
limited applicability. It also claims that
states are better situated to handle small
generator interconnections, and having
two competing interconnection regimes
for small generator interconnections
would be confusing. NARUC therefore
also urges the Commission to adopt a
policy statement instead of a binding
rule.
Commission Conclusion
512. We conclude that as much
standardization as possible of the rates,
165 A particular state’s interconnection rules may
also differ from the NARUC Model.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
166 Small
167 Plug
Generator Coalition at 7–8.
Power at 3.
Frm 00045
Fmt 4701
Sfmt 4700
34233
terms, and conditions of jurisdictional
interconnection service will help
eliminate undue discrimination. A nonbinding policy statement would not end
this undue discrimination. Further, not
regulating jurisdictional
interconnections would leave a
regulatory gap where neither the states
nor the Commission held sway. A gap
of this sort would make it more difficult
for Interconnection Customers wanting
to interconnect and would in fact, leave
them worse off than the owners of Large
Generating Facilities.
513. This Final Rule both fulfills the
Commission’s duty to remedy undue
discrimination when covered by this
rule and, when not covered by this rule,
provides a model that state regulators
may wish to use as a starting point for
developing their own procedures and
agreement. We hope that the SGIP and
SGIA we adopt in this Final Rule are a
step towards having a seamless
interconnection process where
interconnections with federaljurisdictional facilities and statejurisdictional facilities will be handled
in a similar fashion. By doing so, we
intend to avoid the very federal-state
clashes NARUC anticipates.
Issues Relating to Qualifying Facilities
514. The NOPR did not address the
issue of how QFs would be impacted by
the small generator rulemaking.
Comments
515. EEI and PacifiCorp ask the
Commission to clarify that a QF that is
not selling at wholesale, other than to a
host utility under PURPA, should seek
interconnection service through state
procedures, not through Commission
procedures. PacifiCorp states that the
PURPA regulatory scheme for QFs
involves considerable deference to state
regulation with regard to the
interconnection of QFs to stateregulated utilities. The Iowa Utilities
Board agrees and asserts that this Final
Rule should say that states have
authority to establish standards for the
interconnection of QFs. To avoid
confusion, PacifiCorp proposes that the
SGIP state clearly that a Small
Generating Facility with QF status or
one seeking such status is not eligible
for interconnection under the
Commission’s rule. PacifiCorp
recommends amending the
Interconnection Request so that the
Interconnection Customer must certify
that it does not intend to seek QF status.
If it then seeks QF status, PacifiCorp
proposes to require a review of the
interconnection to determine whether it
meets state interconnection standards
for QFs. The Interconnection Customer
E:\FR\FM\13JNR2.SGM
13JNR2
34234
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
would also pay any costs incurred by
the Transmission Provider that a QF
would have paid, if such costs would
not be recovered by the Transmission
Provider under the SGIP.
Commission Conclusion
516. The Commission has regulations
that govern a QF’s interconnection with
most electric utilities in the United
States,168 including normally nonjurisdictional utilities.169 When an
electric utility is required to
interconnect under section 292.303 of
the Commission’s regulations, that is,
when it purchases the QF’s total output,
the state has authority over the
interconnection and the allocation of
interconnection costs.170 But when an
electric utility interconnecting with a
QF does not purchase all of the QF’s
output and instead transmits the QF’s
power in interstate commerce, the
Commission exercises jurisdiction over
the rates, terms, and conditions affecting
or related to such service, such as
interconnections.171
517. The Commission thus exercises
jurisdiction over a QF’s interconnection
if the QF’s owner sells any of the QF’s
output to an entity other than the
electric utility directly interconnected
with the QF. This Final Rule applies
when the owner of the QF seeks
interconnection with a facility subject to
the OATT to sell any of the output of
the QF to a third party. This applies to
a new QF that plans to sell any of its
output to a third party and to an existing
QF interconnected with an electric
utility or on-site customer that decides
in the future to sell any of its output to
a third party. States continue to exercise
authority over QF interconnections
when the owner of the QF sells the
output of the QF only to the
interconnected utility or to on-site
customers.
518. PacifiCorp’s proposal that the
Commission require the Interconnection
Customer to certify that it does not
intend to seek QF status is unnecessary.
This Final Rule only applies when the
168 18
CFR 292.303, 292.306 (2004).
absence of interstate commerce in Alaska,
Hawaii, and portions of Texas and Maine, and
Puerto Rico is not germane to the Commission’s
jurisdiction over QF matters under PURPA. See 16
U.S.C. 2602 (2000).
170 See Western Massachusetts Electric Co., 61
FERC ¶ 61,182 at 61,661–62 (1992), aff’d sub nom.
Western Massachusetts Electric Co. v. FERC, 165
F.3d. 922, 926 (D.C. Cir. 1999).
171 Id. at 61,661–62. The Commission further
clarified that ‘‘[t]he fact that the facilities used to
support the jurisdictional service might also be
used to provide various nonjurisdictional services,
such as back-up and maintenance power for a QF,
does not vest state regulatory authorities with
authority to regulate matters subject to the
Commission’s exclusive jurisdiction.’’ Id. at 61,662.
169 The
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
interconnection is subject to the
Commission’s jurisdiction. Other rules
apply if the generator seeks to
interconnect as a QF. PacifiCorp has
provided no convincing rationale why
this proposed amendment is necessary
for this rulemaking.
Taxes
519. The NOPR did not explicitly
address the potential taxation of
payments made by the Interconnection
Customer to the Transmission Provider
for Interconnection Facilities and
Upgrades.
Comments
520. A few commenters urge the
Commission to address taxes. They
argue that the Commission should adopt
an approach similar to that taken in the
LGIA so that any taxes incurred by the
Transmission Provider are not shifted to
its customers.
521. Because payments received for
Upgrades by the Transmission Provider
may be taxed, EEI and Ameren ask the
Commission to clarify how the
Transmission Provider will recover
those tax payments. Further, EEI argues
that additional financial security may be
required because such facilities could be
jurisdictional to either the Commission
or state utility commissions. Additional
financial security would ensure that the
utility is not forced to recover such costs
from its entire customer base. EEI
proposes that the following sentence be
added to Proposed SGIA article 5.2:
‘‘[The] Transmission Provider may
request additional financial security to
cover tax liabilities that it may incur as
a result of a transaction being deemed
by the Internal Revenue Service to have
been a taxable event, for example, when
an Interconnection Customer terminates
a signed Interconnection Agreement.’’
522. Southern Company proposes a
tax provision modeled after the ANOPR
consensus documents. Under Proposed
SGIA article 5.1.2.1, the refunds paid to
the Interconnection Customer through
transmission credits include ‘‘any tax
gross-up or other tax-related payments’’
in connection with Network Upgrades
required for interconnection. It argues
that if the Interconnection Customer
receives transmission credits for such
payments, all other transmission
customers will have to bear the tax
liability created by the Interconnection
Customer. Transmission credits should
be provided to the Interconnection
Customer for the cost of installing
facilities only if those costs may
facilitate transmission delivery service.
Any tax gross-up paid by the
Interconnection Customer would not
facilitate transmission delivery service,
PO 00000
Frm 00046
Fmt 4701
Sfmt 4700
but instead would be a tax liability
created solely by the interconnection.
Moreover, requiring the refund through
credits of taxes paid, plus interest,
would force the Transmission Provider
to pay the full carrying cost of income
taxes on the Interconnection Customer’s
assets with no means of recouping the
expenditure.
Commission Conclusion
523. The commenters are correct that
payments received for Upgrades by the
Transmission Provider may be taxed
under certain circumstances. If
construction of Upgrades is necessary,
any associated taxes are to be handled
consistent with Commission precedent
and applicable tax rules and regulations.
In particular, the Parties should then
look to the LGIA’s tax framework.172 We
also reiterate that it is Commission
policy that each Party must cooperate
with the other Party to maintain the
Transmission Provider’s tax exempt
status, where applicable.
OATT Reciprocity Requirements
524. The Small Generator
Interconnection NOPR did not propose
any changes to the existing reciprocity
policy; accordingly, the Small Generator
Interconnection NOPR did not discuss
it.
Comments
525. NRECA states that it ‘‘applauds
the Commission’s decision to apply the
reciprocity provision in the OATT and
the reciprocity policy articulated in
Order No. 888 [and] appreciates the
sensitivity the Commission has
demonstrated to the needs of nonjurisdictional service providers.’’ 173
However, it remains concerned that
non-public utilities may be discouraged
from interconnecting new generation
out of fear that such an interconnection
will make them subject to the
jurisdiction of the Commission. To
avoid this, NRECA advocates the
creation of a safe harbor for nonjurisdictional entities that want to
interconnect new generation, yet
maintain their non-jurisdictional status.
NRECA points to several Commission
natural gas decisions that it asserts
provide precedent for creating a safe
harbor of the type it proposes. NRECA
also states that the Commission could
achieve the same result by ordering an
interconnection under section 211 of the
FPA.
526. AMP-Ohio and LADWP ask the
Commission to clarify that the
172 See, e.g., LGIA articles 5.17 and 5.18 and
Order No. 2003–A at P 324 et seq.
173 NRECA at 57.
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
reciprocity condition applies only to the
public utility over whose system the
non-public utility takes transmission
service. They also ask the Commission
to clarify that there is no reciprocity
obligation on the part of a non-public
utility that owns only distribution
facilities, not transmission facilities.
The effect of most small generators is
felt at the distribution level, LADWP
argues, and these interconnections are
more likely to affect retail customers.
SMUD makes a similar argument.
527. PacifiCorp requests that the
Commission clarify that if a public
utility is forced to offer interconnection
service on its distribution lines to a nonpublic utility under the reciprocity
condition, then the public utility must
be offered similar rights to interconnect
with the non-public utility. PacifiCorp
argues that
[b]ecause many non-jurisdictional utilities
own distribution systems that they do not
consider ‘transmission,’ even when the
corresponding system of a public utility is
considered transmission by the Commission,
the potential for discriminatory impact is
real. At a minimum, the definition of a nonjurisdictional utility’s ‘transmission facilities’
should be modified to include any
distribution facility that would be considered
‘transmission’ if it were owned by a
jurisdictional utility.174
528. SMUD asks if reciprocity applies
when the Interconnection Customer
seeks to connect at distribution voltage
to the non-jurisdictional utility and
proposes to engage in sales for resale. It
also asks if reciprocity applies
differently for non-jurisdictional
utilities seeking bilateral agreements
with public utilities than to nonjurisdictional utilities seeking approval
of safe harbor tariffs.
529. NRECA asks the Commission to
clarify that a non-jurisdictional utility is
not required to offer interconnection
service if doing so would jeopardize its
tax-exempt status.
530. Finally, Bureau of Reclamation,
BPA, and others assert that as federal
agencies, they are not able to comply
with all of the provisions of the
Proposed SGIP and SGIA. For instance,
BPA says its contracts must
accommodate the Freedom of
Information Act and that it could not
comply with all aspects of the
Commission’s proposed confidentiality
provisions. BPA and Bureau of
Reclamation request clarification that
they are not required to comply with
these provisions.
174 PacifiCorp
VerDate jul<14>2003
Commission Conclusion
531. Most of the comments focus on
whether interconnections with
‘‘distribution’’ systems are subject to the
reciprocity condition. The answer is, to
satisfy the reciprocity condition of
Order No. 888, a non-public utility must
offer to a public utility with an OATT
service comparable to that offered to its
own or affiliated Interconnection
Customers.175
532. PacifiCorp is correct that what
the facility is termed by its owner does
not affect its jurisdictional status. The
reciprocity condition would apply to
any facility used to offer services that
would be Commission-jurisdictional if
the non-public utility were a public
utility.
533. The reciprocity requirement in
Order No. 888 permits a public utility
to require, as a condition of providing
open access service to a non-public
utility that owns, controls, or operates
transmission facilities, that the nonpublic utility provide reciprocal
transmission service. In Order No.
2003–A, the Commission explained that
the reciprocity provision applies to
Interconnection Service in the same
way.176
534. There are three ways a nonpublic utility may satisfy the reciprocity
provision.177 First, it may provide
service under a Commission-approved
‘‘safe harbor’’ tariff—a tariff that the
Commission has determined offers truly
open access service. Second, it may
provide service to a public utility under
a bilateral agreement that satisfies its
reciprocity obligation. Third, the nonpublic utility may ask the public utility
to waive the reciprocity condition.
535. A non-public utility that has a
‘‘safe harbor’’ tariff that is modeled on
the OATT must add to that tariff an
interconnection procedures document
and interconnection agreement that
either are modeled on the OATT
interconnection procedures document
and agreement or are otherwise found to
offer truly open access service if it
wishes to continue to qualify for ‘‘safe
harbor’’ treatment.178 A non-public
utility that owns, controls, or operates
transmission, has not filed with the
Commission a ‘‘safe harbor’’ tariff, and
seeks transmission service from a public
utility that invokes the reciprocity
provision must either satisfy its
reciprocity obligation under a bilateral
agreement or ask the public utility to
waive the OATT reciprocity condition.
at 2–3.
21:44 Jun 10, 2005
Jkt 205001
PO 00000
175 Order
No. 2003–A at P 775.
Order No. 2003–A at P 760 et seq.
177 Id. at P 761.
178 Id.
536. This Final Rule does not modify
the Commission’s reciprocity policy as
laid out in Order Nos. 888 and 2003.
537. LADWP also states that there are
relatively few Commissionjurisdictional Small Generating Facility
interconnections and urges the
Commission not to apply its reciprocity
policy in the small generator context.
The fact that there may be relatively few
interconnections subject to this Final
Rule does not justify abandoning longstanding reciprocity policy.
538. As the Commission determined
in Order Nos. 888 179 and 2003–A,180
reciprocal service is not required if
providing such service would
jeopardize the tax-exempt status or bond
status of the non-public utility.
539. As to BPA and Bureau of
Reclamation’s comments, we reiterate
that reciprocity does not require federal
entities to provide services or sign
contracts that they cannot legally enter
into. If such entities choose to amend
their safe harbor tariffs on compliance,
they may propose modifications to the
SGIP and SGIA that address their
concerns.
540. Finally, we deny NRECA’s
proposed safe harbor provision. As it
notes, section 211 of the FPA already
allows a non-public utility to safeguard
its non-jurisdictional status. We see no
need to fix a system that does not
appear to be broken.
Coordination With Affected Systems
541. An Affected System is an electric
system other than the Transmission
Provider that may be affected by the
proposed interconnection. In the Small
Generator Interconnection NOPR, the
Commission proposed to treat
coordination between the Transmission
Provider, Interconnection Customer,
and any Affected Systems the same way
as in the LGIA. Order Nos. 2003 and
2003–A required the Transmission
Provider to coordinate with an Affected
System. The Commission requested
comments on whether there are any
issues specific to Small Generating
Facilities that necessitate a different
policy.
Comments
542. While no commenters present
any arguments on this issue specific to
the small generator context, some
discuss the Affected System provision
in terms of Distribution Systems.
Commission Conclusion
543. We are adopting an Affected
System provision comparable to the one
176 See
Frm 00047
Fmt 4701
Sfmt 4700
34235
179 Order
180 Order
E:\FR\FM\13JNR2.SGM
No. 888 at 31,762, n.499.
No. 2003–A at P 782.
13JNR2
34236
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
in the LGIP and LGIA. Regarding the
comments addressing the Affected
System provision in terms of
Distribution Systems subject to an
OATT, we note that the definition of
Affected System includes not only
transmission facilities. The definition is
more inclusive; it is ‘‘an electric system
* * * that may be affected by the
proposed interconnection.’’ Thus, an
Affected System may be any type of
electric system.181
I. Compliance Issues
Amendments to the Transmission
Provider’s OATT
544. In this Final Rule, we are
requiring all public utilities that own,
control, or operate interstate
transmission facilities to adopt the SGIP
and SGIA, but are using a process
different from the one used in Order No.
2003. On the effective date of Order No.
2003, the OATT of each Transmission
Provider was deemed to have included
the LGIP and LGIA.182 On the effective
date of this Final Rule, as in Order No.
2003,183 the OATTs of all nonindependent Transmission Providers are
deemed revised to include the Final
Rule SGIP and SGIA. But unlike the
Order No. 2003 process, where the
Commission directed Transmission
Providers to make ministerial filings to
include the LGIP and LGIA in their next
filings with the Commission, here the
Commission will require no formal
amendment until compliance is due in
the Commission’s rulemaking on
Electronic Tariff Filings.184 This means
that a non-independent Transmission
Provider that wishes to adopt the SGIP
and SGIA (without variations) into its
OATT need not formally add the
documents to its OATT until it submits
a compliance filing in response to the
Commission’s pending Electronic Tariff
Filings rulemaking. A non-independent
Transmission Provider that decides to
take this option nevertheless must apply
the SGIP and SGIA to any request for
small generator interconnection that it
receives after the effective date of this
Final Rule, but before it complies with
the rulemaking on Electronic Tariff
Filings. The compliance obligation is
181 We note that, similar to when the Affected
System is a non-jurisdictional entity, the
Commission does not have to have jurisdiction over
the Affected System in order for the interconnection
to proceed. See Order No. 2003–A at P 114–115.
182 Order No. 2003 at P 910.
183 See Standardization of Generator
Interconnection Agreements and Procedures, Notice
Clarifying Compliance Procedures, 106 FERC
¶ 61,009 at P 2 (2004).
184 Electronic Tariff Filings, Notice of Proposed
Rulemaking, 69 FR 43929 (July 23, 2004), FERC
Stats. & Regs., Proposed Regulations, ¶ 32,575 (July
8, 2004).
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
different for non-independent
Transmission Providers that seek
variations from the Final Rule
documents, as discussed further below.
545. If an RTO or ISO wishes to adopt
the SGIP and SGIA into its OATT, it
may also await compliance with the
Electronic Tariff Filings rulemaking
before formally adding the documents to
its OATT. But the RTO or ISO should
notify the Commission by the effective
date of this Final Rule that it will adopt
the Final Rule documents and that
requests for interconnection of Small
Generating Facilities will be subject to
the SGIP and SGIA in the interim
period. An RTO or ISO that does not
adopt the SGIP and SGIA will have
additional time to submit its compliance
filings to allow for the stakeholder
process and other measures that must be
taken before an RTO or ISO adopts tariff
changes. Therefore, an RTO or ISO that
seeks variations will have an additional
90 days to submit its compliance filing.
As in the Order No. 2003 proceeding,
until the Commission acts on the
compliance filing of an RTO or ISO that
seeks variations, the RTO’s or ISO’s
existing Commission-approved
interconnection procedures and
agreement remain in effect.
Variations From the Final Rule
546. As in Order No. 2003, the
Commission will consider two
categories of variations from the Final
Rule submitted by a non-independent
Transmission Provider.185 First, the
Commission will consider ‘‘regional
reliability variations’’ that track
established reliability requirements (i.e.,
requirements approved by the
applicable regional reliability council).
Any request for a ‘‘regional reliability
variation’’ must be supported by
references to established reliability
requirements,186 and the text of the
reliability requirements must be
provided in support of the variation. If
the variation is for any other reason, the
non-independent Transmission Provider
must demonstrate that the variation is
‘‘consistent with or superior to’’ the
Final Rule provision. Blanket statements
that a variation meets the standard or
clarifies the Final Rule provision are not
sufficient. Any request for application of
this standard will be considered under
FPA section 205 and must be supported
by arguments explaining how each
variation meets the standard.
547. Requests for regional reliability
variations are due on the effective date
No. 2003 at P 824–25.
also New York Independent System
Operator, Inc., 108 FERC ¶ 61,159 at P 95 (2004),
reh’g pending.
PO 00000
185 Order
186 See
Frm 00048
Fmt 4701
Sfmt 4700
of this Final Rule. Requests for
‘‘consistent with or superior to’’
variations may be submitted on or after
the effective date of the Final Rule. We
note that the ‘‘consistent with or
superior to’’ standard is difficult to meet
because the burden of showing that a
variation is ‘‘consistent with or superior
to’’ the relevant provision or provisions
in the Final Rule document is
significant.
548. Any request for a variation
should be accompanied by a request to
include the complete SGIP and SGIA
into the Transmission Provider’s OATT.
The Commission will consider
incomplete any request for a variation
that does not also propose to append to
the Transmission Provider’s OATT the
complete SGIP and SGIA. As explained
above, an RTO or ISO will have 90
additional days (for a total of 150 days)
to submit a compliance filing. That
compliance filing must contain all
proposed independent entity variations.
549. With respect to an RTO or ISO,
at the time its compliance filing is
made, as explained in Order No. 2003,
the Commission will allow it to seek
‘‘independent entity variations’’ from
the Final Rule pricing and non-pricing
provisions.187 The RTO or ISO should
explain the basis for each variation.
550. Finally, for a non-independent
Transmission Provider that belongs to
an RTO or ISO, the RTO’s or ISO’s
Commission-approved standards and
procedures are to govern
interconnection with its members’
facilities that are under the operational
control of the RTO or ISO. An
interconnection with a Commission
jurisdictional facility that is owned by a
non-independent Transmission Provider
but is not under the operational control
of the RTO or ISO is to be conducted
according to the non-independent
Transmission Provider’s procedures and
agreement. A non-independent
Transmission Provider, even if it
belongs to an RTO or ISO, is not eligible
for ‘‘independent entity variations’’ for
procedures and agreements applicable
to interconnection with facilities that
remain within its operational control
(and therefore, are subject to a tariff
different from the RTO or ISO’s OATT).
To clarify, if a non-independent
Transmission Provider belongs to an
RTO or ISO, but keeps operational
control of some jurisdictional facilities,
and those facilities are not subject to the
interconnection procedures under the
OATT of the RTO or ISO, then the nonindependent Transmission Provider
must have a separate set of
interconnection procedures and
187 Order
E:\FR\FM\13JNR2.SGM
No. 2003 at P 827.
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Interconnection Requests Submitted
Prior to the Effective Date of This Final
Rule and Grandfathering of Existing
Interconnection Agreements
551. The grandfathering of existing
agreements was not specifically
addressed in the Small Generator
Interconnection NOPR; however, the
Commission did request comments on
whether generic Commission policies
applicable to Large Generating Facilities
(such as grandfathering) should be
applied to Small Generating Facilities.
transmission requirements are
consistent with those provided for in
the prior agreement.
554. Finally, if the Commission
adopts the approach used in Order No.
2003, California Wind Energy requests
that the Commission clarify when a
change in a QF’s contract status triggers
an obligation to file a new
Interconnection Request. It notes that
Order No. 2003 states that the owner of
a QF formerly interconnected with a
Transmission System has no obligation
to file an Interconnection Request when
its contract status changes if the output
of its generator ‘‘will be substantially
the same as before.’’ 189 California Wind
Energy asserts that the term ‘‘output’’
leaves ambiguous the effect of the
Commission’s criteria on projects that
are to be repowered after contract
conversion. It explains that when a QF
repowers, it increases energy production
while maintaining its maximum
megawatt output. California Wind
Energy seeks clarification that when a
small generator increases energy
production as a result of a post-PURPA
contract repower, and there is no
meaningful change in the generator’s
maximum output, there is no obligation
to file a new Interconnection Request.
Comments
552. American Forest and National
Grid seek clarification that small
generators that are already
interconnected are not subject to this
rulemaking. To avoid unintended
barriers to Small Generating Facilities,
they urge the Commission to follow the
Order No. 2003 approach for
grandfathering. American Forest states
that generators should not have to
undergo this new interconnection
process, particularly where the
generating facilities that are already
interconnected have not changed their
physical operations.
553. California Wind Energy requests
that, as in Order No. 2003, contract
conversion of pre-existing
interconnection contracts with former
QFs should not trigger an obligation
under this Final Rule to file an
Interconnection Request because a
change in contract status alone does not
affect a generator’s demand on the
electric system. It also seeks
clarification that, when the QF’s
interconnection agreement provides for
greater capacity than what is to be sold
to the interconnecting utility under the
PURPA power purchase contract, upon
contract conversion, the former QF
should not have to submit an
Interconnection Request if the
Commission Conclusion
555. As in Order No. 2003, the
Commission is not requiring changes to
interconnection agreements filed with
the Commission before the effective date
of this Final Rule. Interconnection
agreements submitted for approval by
the Commission before the effective date
of this Final Rule are grandfathered and
will not be rejected outright for failing
to conform to the SGIA. Small
Generating Facilities already
interconnected that have not changed
their physical operations in such a way
as to require a new Interconnection
Request are not subject to this
rulemaking.
556. We also note that the Small
Generator NOPR did not address what
happens to Interconnection Customers
whose Interconnection Requests are
pending at the time this Final Rule goes
into effect. LGIP section 5 addresses
how such interconnections are to be
processed, and we adopt a shortened
version of that provision in the SGIP as
well. The new section 1.7 clarifies that
nothing in this Final Rule is intended to
affect an Interconnection Customer’s
Queue Position assigned prior to the
effective date of this rule. It also states
that the Parties shall continue to process
any executed interconnection study
agreements (or study agreements that
agreement applicable to these facilities.
To address the confusion that may arise
from having inconsistent
interconnection procedures and
agreements applicable within an RTO or
ISO region, we allow a non-independent
Transmission Provider that keeps
control over some jurisdictional
facilities to subject these facilities to an
RTO- or ISO-controlled interconnection
process. In such instance, the nonindependent Transmission Provider
must agree to transfer to the RTO or ISO
control over the significant aspects of
the interconnection process, including
the performance of all interconnection
studies and cost determinations
applicable to Network Upgrades.188
have been filed unexecuted with the
Commission) once this Final Rule
becomes effective. However, we will
require that any new interconnection
study agreement entered into after this
Final Rule becomes effective follow the
pro forma study agreements contained
in the SGIP. Any accommodation
needed to process such Interconnection
Requests (i.e., should the pre- and postFinal Rule study processes be
significantly different) should be filed
with the Commission and will be
evaluated on a case-by-case basis.
557. If an interconnection agreement
has been executed prior to the effective
date of this Final Rule, then no
additional steps need to be taken. We
agree with the commenters that an
existing Interconnection Customer
whose Small Generating Facility is
already interconnected should not have
to undergo a new interconnection
process.
558. We also reiterate that a change in
an Interconnection Customer’s contract
status does not, by itself, trigger an
obligation to file an Interconnection
Request. As the Commission noted in
Order Nos. 2003 and 2003–A, a former
QF interconnected with a Transmission
System that sells electric energy at
wholesale in interstate commerce need
not submit an Interconnection Request
if it represents that the output of the
generating facility is substantially the
same as before.190 Under the
Commission’s regulations,191 a QF must
provide electric energy to its
interconnecting utility much like the
interconnecting utility’s other network
resources because the utility must
purchase the QF’s power to displace its
own generation. When the owner of a
QF that was formerly interconnected
with a Transmission System seeks to
sell energy at wholesale and represents
that the output of its generator will be
substantially the same after conversion,
it would be unreasonable for a
Transmission Provider to require the
former QF to join the interconnection
queue.
559. California Wind Energy also asks
the Commission to clarify that a plant
repowering at the time of contract
conversion that does not increase plant
capacity will not trigger an obligation to
file an Interconnection Request. We
clarify that a contract conversion that
does not affect a generator’s demands on
the Transmission System does not
trigger an obligation to file. When a QF’s
existing interconnection agreement
provides for capacity greater than the
capacity sold by the QF to the
190 Order
188 See
Order No. 2003–B at P 80.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
189 Order
PO 00000
No. 2003 at P 815.
Frm 00049
Fmt 4701
Sfmt 4700
34237
191 18
E:\FR\FM\13JNR2.SGM
No. 2003 at P 815.
CFR 292.303 (2004).
13JNR2
34238
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
interconnecting utility under the
PURPA power purchase contract, the
QF’s contract conversion will not trigger
an obligation to file an Interconnection
Request if its transmission requirements
are consistent with the capacity
provided for in the existing
interconnection agreement.
Order No. 2001 and the Filing of
Interconnection Agreements
560. Order No. 2001 192 revised how
traditional public utilities and power
marketers must satisfy their obligation,
under section 205 of the FPA and Part
35 of the Commission’s regulations, to
file agreements with the Commission.193
Public utilities that have standard forms
of agreement in their OATTs, cost-based
power sales tariffs, or tariffs for other
generally applicable services no longer
need to file conforming service
agreements with the Commission. The
filing requirement for conforming
agreements (those that follow the
standard form) is now satisfied by filing
the standard form of agreement and an
Electronic Quarterly Report. Order No.
2001 also lifted the requirement that
Parties to an expiring conforming
agreement file a notice of cancellation or
a cancellation tariff sheet with the
Commission. The public utility may
simply remove the agreement from its
Electric Quarterly Report in the quarter
after it terminates.
561. Non-conforming agreements,
which are agreements for transmission,
cost-based power sales or other
generally applicable services that do not
conform to a standard form of agreement
in a public utility’s tariff, must continue
to be filed with the Commission for
approval before going into effect. This
category includes unexecuted
agreements and agreements that do not
precisely match the standard form of
agreement.
562. Order No. 2003 explained that,
under Order No. 2001, if an
interconnection agreement conforms to
a Commission-approved standard form
of interconnection agreement, the
Transmission Provider does not have to
file it with the Commission, but must
report it in its Electric Quarterly
Reports. The same filing rules will
apply to non-conforming SGIAs as for
non-conforming LGIAs. However, an
interconnection agreement that does not
precisely match the Transmission
Provider’s Commission-approved
standard interconnection agreements or
that is unexecuted must be filed in its
entirety. The Transmission Provider
shall clearly show where the filed
agreement does not conform to its
standard interconnection agreement
through red-lining and strike-out and
justify the basis for the
nonconformance.
III. Information Collection Statement
563. The Office of Management and
Budget (OMB) regulations require that
OMB approve certain reporting and
record keeping (collections of
information) imposed by an agency.194
The information collection requirements
in this Final Rule are identified under
the Commission data collection, FERC–
516A ‘‘Standardization of Small
Generator Interconnection Agreements
and Procedures.’’ Under section 3507(d)
of the Paperwork Reduction Act of
1995,195 the proposed reporting
requirements in the subject rulemaking
will be submitted to OMB for review.
Interested persons may obtain
information on the reporting
requirements by contacting the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426
(Attention: Michael Miller, Office of the
Executive Director, 202–502–8415) or
No. of
respondents
Data collection
from the Office of Management and
Budget (Attention: Desk Officer for the
Federal Energy Regulatory Commission,
fax: 202–395–7285, e-mail: n.;[9
oira_submission@omb.eop.gov).
564. The ‘‘public protection’’
provision of the Paperwork Reduction
Act 196 requires each agency to display
a currently valid OMB control number
and inform respondents that a response
is not required unless the information
collection displays a valid OMB control
number on each information collection.
This provision has two legal effects: (1)
It creates a legal responsibility for the
agency; and (2) it provides an
affirmative legal defense for respondents
if the information collection is imposed
on respondents by the Commission
through regulation or administrative
means in order to satisfy a legal
authority or responsibility of the
Commission. If the Commission should
fail to display an OMB control number,
then it is the Commission not the
respondent who is in violation of the
law. ‘‘Display’’ is defined as publishing
the OMB control number in regulations,
guidelines or other issuances in the
Federal Register (for example, in the
preamble or regulatory text for the final
rule containing the information
collection).197 Therefore, the
Commission may not conduct or
sponsor, and a person is not required to
respond to a collection of information
unless the information collection
displays a valid OMB control number.
565. Public Reporting Burden: The
Commission did not receive specific
comments concerning its burden
estimates and uses the same estimates
here in the Final Rule. Comments on the
substantive issues raised in the NOPR
are addressed elsewhere in the Final
Rule.
No. of
responses
Hours per
response
Total annual
hours
FERC–516A
SGIPs & SGIAs ........................................................................................
Recordkeeping ..........................................................................................
238
238
1
1
25
2
5,950
476
Totals .................................................................................................
........................
........................
........................
6,426
192 Revised Public Utility Filing Requirements,
Order No. 2001, 67 FR 31043 (May 8, 2002), FERC
Stats. & Regs. ¶ 31,127 (2002); reh’g denied, Order
2001–A, 100 FERC ¶ 61,074 (2002); reconsideration
and clarification denied, Order No. 2001–B, 100
FERC ¶ 61,342 (2002); further order, Order No.
2001–C, 101 FERC ¶ 61,314 (2002).
193 Order No. 2001 pointed out that Part 35 of the
Commission’s regulations does not make a
distinction between an interconnection agreement
and other agreements for service that must be filed
under the Commission’s regulations. Order No.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
2001, therefore, said that if an interconnection
agreement conforms to a Commission-approved
standard form of interconnection agreement, the
utility does not have to file it, but must report it
in the Electric Quarterly Reports. It also stated that
the requirement to file contract data and transaction
data begins with the first Electric Quarterly Report
filed after service begins under an agreement, and
continues until the Electric Quarterly Report filed
after it expires or by order of the Commission.
However, an interconnection agreement that does
not precisely match the Transmission Provider’s
PO 00000
Frm 00050
Fmt 4701
Sfmt 4700
approved interconnection agreement or that is
unexecuted must be filed with the Commission.
The Transmission Provider must clearly show
where the agreement does not conform to its
standard interconnection agreement, preferably
through red-lining and strike-out.
194 5 CFR 1320.11 (2004).
195 44 U.S.C. 3507(d) (2000).
196 44 U.S.C. 3512; 5 CFR 1320.5(b); 5 CFR
1320.6(a).
197 See 1 CFR 21.35 and 5 CFR 1320.3(f)(3).
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Total Annual Hours for Collection:
5,950 (reporting) [238 respondents × 1 ×
25 hours] + 476 hours (recordkeeping )
[238 hours × 1 filing × 2 hours to retain
interconnection documents] = 6,426.198
566. Information Collection Costs:
The Commission sought comments
about the time needed to comply with
these requirements. No comments were
received. Staffing requirements to
review and modify existing SGIPs and
SGIAs = $309,400 [238 respondents ×
$1,300 (25 hours @ $52 hourly rate)]. To
be added to this cost are the annualized
costs for operations and management
(238 respondents × $34 [2 hours @ $17
hourly rate for recordkeeping] or
$8,092)). Total costs of $317,492 for
preparing filings for modification of the
OATT and for recordkeeping of
interconnection documents. There will
be a one-time start up cost to comply
with these requirements for the
procedures and agreements and then an
additional cost to maintain them.199
Titles: FERC–516A ‘‘Standardization
of Small Generator Interconnection
Agreements and Procedures
Action: Revision of Currently
Approved Collection of Information
OMB Control Nos: 1902–0203.
Respondents: Business or other for
profit.
Frequency of Responses: One
occasion.
Necessity of Information: The Final
Rule revises the reporting requirements
contained in 18 CFR part 35. The
Commission promulgates a standardized
SGIP and SGIA that public utilities must
adopt. As noted in the Final Rule,
adopting these procedures and
agreement will (1) reduce
interconnection costs and time for the
owners of Small Generating Facilities
and Transmission Providers alike; (2)
limit opportunities for Transmission
Providers to favor their own generation;
(3) facilitate market entry for generation
competitors; and (4) encourage needed
investment in generator and
transmission infrastructure.
567. Interconnection plays a growing,
crucial role in bringing generation into
the market to meet the needs of
electricity customers. However, requests
for interconnection frequently result in
complex technical disputes about
interconnection feasibility, cost and cost
responsibility. The Commission expects
that a standardized SGIP and SGIA will
reduce interconnection costs and time
for Interconnection Customers and
198 Adjustments
made to reflect an increase in the
number of respondents from the estimate in the
Small Generator Interconnection NOPR.
199 Adjusted figures to reflect an increase in the
number of respondents.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
Transmission Providers, resolve most
interconnection disputes, minimize
opportunities for undue discrimination,
foster increased development of
economic generation, and improve
system reliability.
568. For information on the
requirements, submitting comments on
the collection of information and the
associated burden estimates including
suggestions for reducing this burden,
please send your comments to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426 (Attention: Michael Miller, Office
of the Executive Director, (202) 502–
8415) or send comments to the Office of
Management and Budget (Attention:
Desk Officer for the Federal Energy
Regulatory Commission, fax: (202) 395–
7285, e-mail
oira_submission@omb.eop.gov).
IV. Environmental Impact Statement
569. Commission regulations require
that an environmental assessment or an
environmental impact statement be
prepared for any Commission action
that may have a significant adverse
effect on the human environment.200 No
environmental consideration is
necessary for the promulgation of a rule
that is clarifying, corrective, or
procedural or does not substantially
change the effect of legislation or
regulations being amended,201 and also
for information gathering, analysis, and
dissemination.202 The Final Rule
updates part 35 of the Commission’s
regulations and does not substantially
change the effect of the underlying
legislation or the regulations being
revised or eliminated. In addition, the
Final Rule involves information
gathering, analysis, and dissemination.
Therefore, this Final Rule falls within
categorical exemptions provided in the
Commission’s regulations.
Consequently, neither an environmental
impact statement nor an environmental
assessment is required.
570. While some Small Generating
Facilities, such as reciprocating engines,
may produce more pollution, others,
such as photovoltaics and fuel cells,
produce significantly less air, water and
noise pollution than do new central
station technologies. Others, such as
micro-turbines, provide opportunities to
reduce emissions by improving the
efficiency with which energy is
consumed, through improved heat rates
and combined heat and power
200 Regulations Implementing National
Environmental Policy Act, Order No. 486, 52 FR
47897 (Dec. 17, 1987), FERC Stats. & Regs. ¶ 30,783
(1987).
201 18 CFR 380.4(a)(2)(ii) (2004).
202 18 CFR 380.4(a)(5) (2004).
PO 00000
Frm 00051
Fmt 4701
Sfmt 4700
34239
applications. Small Generating Facilities
may eliminate the need to run older,
more polluting generating units and
reduce power line losses. As one of the
goals of this rule is to allow
interconnection of Small Generating
Facilities that can provide
environmental and economic benefits,
this rule will benefit customers by
providing alternative generation
sources.
V. Regulatory Flexibility Act
571. The Regulatory Flexibility Act
(RFA) 203 requires that a rulemaking
contain either a description and analysis
of the effect that the proposed rule will
have on small entities or a certification
that the rule will not have a significant
economic impact on a substantial
number of small entities. However, the
RFA does not define ‘‘significant’’ or
‘‘substantial’’ instead leaving it up to
any agency to determine the impacts of
its regulations on small entities. In the
NOPR, the Commission stated that the
proposed regulations would impose
requirements only on interstate
Transmission Providers, which are not
small businesses. The Commission
certified that the proposed regulations
would not have a significant adverse
impact on a substantial number of small
entities. In making its certification, the
Commission determined that the rule
applies only to public utilities that own,
control, or operate facilities for
transmitting electric energy in interstate
commerce and not to electric utilities
per se. Small entities that believe this
rule will have a significant impact on
them may apply to the Commission for
waivers.
Comments
572. NRECA questions this
certification. NRECA argues that to
lessen the impact of this rule on small
entities, the Commission should: ‘‘(1)
Provide a durable blanket waiver of the
NOPR requirements to all currently
FPA-jurisdictional utilities, that qualify
as ’small’ public utilities under the
Small Business Administration (SBA)
utility size standards, and (2) provide a
safe harbor for all ‘small’ nonjurisdictional providers that want to
work with consumers to interconnect
generation, but want to maintain their
non-jurisdictional status.’’
Commission Conclusion
573. We are applying the same
standards to any entity seeking a waiver
of the requirements of this Final Rule.
Because the possible scenarios under
which small entities may seek waivers
203 5
E:\FR\FM\13JNR2.SGM
U.S.C. 601–612 (2000).
13JNR2
34240
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
are diverse, they are not susceptible to
resolution on a generic basis, and we are
requiring applications and fact-specific
determinations in each instance. The
Commission does not have jurisdiction
over non-public utilities’ rate, terms and
conditions of transmission service
under sections 205 and 206 of the FPA,
and Order No. 888 does not require that
non-public utilities file open access
transmission tariffs. In addition, under
the waiver provisions of Order No. 888,
small non-public utilities may seek
waiver from the reciprocity provision.
This waiver policy follows the SBA
definition of a small utility.204 The SBA
defines a small electric utility as one
that disposes of 4 MWh or less of
electric energy in a given year.205
574. We disagree with NRECA that
this Final Rule will have a significant
economic effect on a substantial number
of small entities. Of the 931 electric
cooperatives in the 47 states across the
country, 686 receive financial assistance
from the U.S. Department of Agriculture
and therefore are not subject to the
Commission’s jurisdiction.206 Of the 67
members of NRECA who have
generation and transmission facilities,
only 34 electric cooperatives are subject
to the Commission’s jurisdiction. They
are only a small subset of the entities
considered when determining a
significant impact on a substantial
number of small entities. Within the
subset of 34 entities, only a few own,
control, or operate interstate
transmission facilities.
575. As NRECA noted in its
comments, the Commission has an
important role in determining whether
facilities are distribution or
transmission, and as the Commission
noted elsewhere in this Final Rule, the
only facilities that are already subject to
a Transmission’s Provider’s OATT are
covered by this rule and apply only to
a small percentage of small generator
interconnections. The Commission
recognizes that most small generators
will interconnect with facilities that are
not subject to the OATT.
576. However, in drafting this rule the
Commission has followed the
provisions of both the RFA and the
Paperwork Reduction Act to consider
the potential impact of regulations on
small business and other small entities.
Specifically, the RFA directs agencies to
consider four regulatory alternatives to
be considered in a rulemaking to lessen
204 See
5 U.S.C. 601(3) and 601(6) and 15 U.S.C.
632(a).
205 See 13 CFR 121.601.
206 Source: Rural Utilities Service, U.S.
Department of Agriculture, https://
www.usdagov.rus/electric/borrowers/index.htm.
April, 2005.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
the impact on small entities: Tiering or
establishment of different compliance or
reporting requirements for small
entities, classification, consolidation,
clarification or simplification of
compliance and reporting requirements,
performance rather than design
standards, and exemptions. The
Commission has adopted both tiering,
and classification and simplification
when developing technical accelerated
procedures to apply to interconnections
that will have no adverse effect on the
Transmission Provider’s electric system.
By the use of tiering, the Commission is
creating three ways to evaluate
Interconnection Requests that can be
applied to size and operating conditions
of a small generating facility. As noted
earlier, all Small Generating Facilities
are subject to the Study Process, but in
order to expedite the process and reduce
the requirements on facilities smaller
than 2 MW, technical screens were
developed for certified Small Generating
Facilities no larger than 2 MW (Fast
Track) and certified inverter-based
Small Generating Facilities no larger
than 10 kW (10 kW Inverter Process).
The latter process was further simplified
as it does not use an SGIA, instead using
an all-in-one document that includes
the application form, interconnection
procedures, and terms and conditions.
In addition, many provisions of the
SGIA are based on the NARUC Model
which in turn is based on the
experience of several states for
implementing interconnections.
577. A core issue has been whether
standards could be developed that will
allow for a cost effective
interconnection solution without
jeopardizing the safety and reliability of
the Transmission System. One study
showed that the typical cost of
interconnection ranges from $50/kW–
$200/kW depending on the size of the
generating facility, application and
utility requirements.207 By simplifying
both the interconnection procedures
document and interconnection
agreement, the costs of small generating
facilities should be reduced, equipment
manufacturers will be able to operate
from a single set of technical
specifications, and seamless procedures
will be in place that do not jeopardize
the safety and reliability of the
Transmission System.
VI. Document Availability
578. In addition to publishing the full
text of this document in the Federal
Register, the Commission provides all
207 Souce: Arthur D. Little, Distribution
Generation: System Interfaces, Arthur D. Little, Inc.,
Cambridge, Massachusetts, 1999.
PO 00000
Frm 00052
Fmt 4701
Sfmt 4700
interested persons an opportunity to
obtain this document from the Public
Reference Room during normal business
hours (8:30 a.m. to 5 p.m. Eastern Time)
at 888 First Street, NE., Room 2A,
Washington, DC. The full text of this
document is also available
electronically from the Commission’s
eLibrary system (formerly called
FERRIS) in PDF and Microsoft Word
format for viewing, printing, and
downloading. eLibrary may be accessed
through the Commission’s Home Page
(https://www.ferc.gov). To access this
document in eLibrary, type ‘‘RM02–1-’’
in the docket number field and specify
a date range that includes this
document’s issuance date.
579. User assistance is available for
eLibrary and the Commission’s Web site
during normal business hours from our
Help Line at (202) 502–8222 or the
Public Reference Room at (202) 502–
8371 Press 0, TTY (202) 502–8659. EMail the Public Reference Room at
public.referenceroom@ferc.gov.
VII. Effective Date And Congressional
Notification
580. This Final Rule will take effect
on August 12, 2005. The Commission
has determined, with the concurrence of
the Administrator of the Office of
Information and Regulatory Affairs of
the Office of Management and Budget,
that this rule is not a ‘‘major rule’’
within the meaning of section 251 of the
Small Business Regulatory Enforcement
Fairness Act of 1996.208 The
Commission will submit the Final Rule
to both houses of Congress and the
General Accounting Office.209
List of Subjects in 18 CFR Part 35
Electric power rates, Electric utilities,
Reporting and recordkeeping
requirements.
By the Commission.
Linda Mitry,
Deputy Secretary.
In consideration of the foregoing, the
Commission amends part 35, Chapter I,
Title 18 of the Code of Federal
Regulations, as follows.
I
PART 35—FILING OF RATE
SCHEDULES AND TARIFFS
1. The authority citation for part 35
continues to read as follows:
I
Authority: 16 U.S.C. 791a–825r, 2601–
2645; 31 U.S.C. 9701; 42 U.S.C. 7101–7352.
2. In § 35.28, paragraph (f) is revised to
read as follows:
I
208 5
209 5
E:\FR\FM\13JNR2.SGM
U.S.C. 804(2) (2000).
U.S.C. 801(a)(1)(A) (2000).
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
§ 35.28 Non-discriminatory open access
transmission tariff.
*
*
*
*
*
(f) Standard generator
interconnection procedures and
agreements. (1) Every public utility that
is required to have on file a nondiscriminatory open access transmission
tariff under this section must amend
such tariff by adding the standard
interconnection procedures and
agreement contained in Order No. 2003,
FERC Stats. & Regs. ¶ 31,146 (Final Rule
on Generator Interconnection) and the
standard small generator
interconnection procedures and
agreement contained in Order No. 2006,
FERC Stats. & Regs. ¶lll (Final Rule
on Small Generator Interconnection), or
such other interconnection procedures
and agreements as may be approved by
the Commission consistent with Order
No. 2003, FERC Stats. & Regs. ¶ 31,146
(Final Rule on Generator
Interconnection) and Order No. 2006,
FERC Stats. & Regs. ¶lll (Final Rule
on Small Generator Interconnection).
(i) The amendment to implement the
Final Rule on Generator Interconnection
required by paragraph (f)(1) of this
section must be filed no later than
January 20, 2004.
Before Commissioners: Pat Wood, III,
Chairman;
(ii) The amendment to implement the
Final Rule on Small Generator
Interconnection required by paragraph
(f)(1) of this section must be filed no
later than August 12, 2005.
(iii) Any public utility that seeks a
deviation from the standard
interconnection procedures and
agreement contained in Order No. 2003,
FERC Stats. & Regs. ¶ 31,146 (Final Rule
on Generator Interconnection) or the
standard small generator
interconnection procedures and
agreement contained in Order No. 2006,
FERC Stats. & Regs. ¶ll (Final Rule on
Small Generator Interconnection), must
demonstrate that the deviation is
consistent with the principles of either
Order No. 2003, FERC Stats. & Regs. ¶
31,146 (Final Rule on Generator
Interconnection) or Order No. 2006,
FERC Stats. & Regs. ¶ll (Final Rule on
Small Generator Interconnection).
(2) The non-public utility procedures
for tariff reciprocity compliance
described in paragraph (e) of this
section are applicable to the standard
interconnection procedures and
agreements.
(3) A public utility subject to the
requirements of this paragraph
pertaining to the Final Rule on
Generator Interconnection may file a
request for waiver of all or part of the
requirements of this paragraph, for good
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
cause shown. An application for waiver
must be filed either:
(i) No later than January 20, 2004, or
(ii) No later than 60 days prior to the
time the public utility would otherwise
have to comply with the requirements of
this paragraph.
(4) A public utility subject to the
requirements of this paragraph
pertaining to the Final Rule on Small
Generator Interconnection may file a
request for waiver of all or part of the
requirements of this paragraph, for good
cause shown. An application for waiver
must be filed either:
(i) No later than August 12, 2005, or
(ii) No later than 60 days prior to the
time the public utility would otherwise
have to comply with the requirements of
this paragraph. [The following
Appendices will not be published in the
Code of Federal Regulations.]
Appendix A—Commenter Acronyms 1
AEP—American Electric Power System
Alabama PSC—Alabama Public Service
Commission
Allegheny Energy—Allegheny Energy
Supply Company, LLC and Allegheny Power
Ameren—Ameren Services Company
American Forest—American Forest &
Paper Association and the Process Gas
Consumers Group
AMP–Ohio—American Municipal Power—
Ohio, Inc.
Avista—Avista Corp. and Puget Sound
Energy, Inc.
Baltimore G&E—Baltimore Gas and Electric
Company
BPA—Bonneville Power Administration,
U.S. Department of Energy
Bureau of Reclamation—Bureau of
Reclamation, U.S. Department of Interior
CA ISO—California ISO
California Wind Energy—California Wind
Energy Association
Capstone—Capstone Turbine Corp.
Central Iowa Coop—Central Iowa Power
Cooperative and Corn Belt Power
Cooperative
Central Maine—Central Maine Power
Company, New York State Electric & Gas
Corporation, and Rochester Gas & Electric
Corporation
Cinergy—Cinergy Services, Inc.
Consumers—Consumers Energy Company
CPUC—California Public Utilities
Commission
CT DPUC—Connecticut Department of
Public Utility Control
Cummins—Cummins, Inc.
EEI—Edison Electric Institute
Empire District—Empire District Electric
Co.
Encorp—Encorp, Inc.
Exelon—Exelon Generation Company,
LLC, Commonwealth Edison Company,
1 This list includes commenters who filed in
response to the request for comments in the Notice
of Proposed Rulemaking, the August 12, 2004
Request for Supplemental Comments, or both.
Commenters who responded to the Request for
Supplemental Comments are also listed separately
at the end of this appendix.
PO 00000
Frm 00053
Fmt 4701
Sfmt 4700
34241
PECO Energy Company, and Sithe Energies,
Inc.
FERC DRS—Dispute Resolution Service,
Federal Energy Regulatory Commission
Florida PSC—Florida Public Service
Commission
Garwin McNeilus—Mr. Garwin McNeilus
Georgia PSC—Georgia Public Service
Commission
Georgia Transmission—Georgia
Transmission Corporation
Idaho Power—Idaho Power Company
Iowa Utilities Board—Iowa Utilities Board
ISO New England—ISO New England
Joint Commenters—National Association of
Regulatory Utility Commissioners, Small
Generator Coalition (members listed below),
American Public Power Association (who did
not participate in the filing of supplemental
comments), National Rural Electric
Cooperative Association, and Edison Electric
Institute
LADWP—Los Angeles Department of
Water and Power
Massachusetts DTE—Massachusetts
Department of Telecommunications and
Energy
MidAmerican—MidAmerican Energy
Company
Midwest ISO—Midwest Independent
Transmission System Operator, Inc.
Minnesota PUC—Minnesota Public
Utilities Commission and the Minnesota
Department of Commerce
Mississippi PSC—Mississippi Public
Service Commission
NARUC—National Association of
Regulatory Utility Commissioners
National Grid—National Grid USA
NEMA—National Electrical Manufacturers
Association
NEPOOL Participants—New England
Power Pool Participants Committee
Nevada Power—Nevada Power Company
and Sierra Pacific Power Company
NJ BPU—New Jersey Board of Public
Utilities
North Carolina Commission—North
Carolina Utilities Commission and the Public
Staff of the North Carolina Utilities
Commission
NorthWestern Energy—NorthWestern
Energy
NRECA—National Rural Electric
Cooperative Association
NYISO—New York Independent System
Operator, Inc.
NYPSC—New York State Public Service
Commission
NYTO—Central Hudson Gas and Electric
Corp., Consolidated Edison Company of New
York, Inc., Long Island Power Authority,
New York Power Authority, New York State
Electric and Gas Corp., Orange and Rockland
Utilities, Inc., and Rochester Gas and Electric
Corp.
Ohio PUC—Public Utilities Commission of
Ohio
PacifiCorp—PacifiCorp
PG&E—Pacific Gas and Electric Company
PJM—PJM Interconnection, L.L.C.
Plug Power—Plug Power, Inc.
Progress Energy—Progress Energy, Inc.,
Carolina Power and Light Co., and Florida
Power Corp.
PSE&G—Public Service Electric and Gas
Company
E:\FR\FM\13JNR2.SGM
13JNR2
34242
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Robert L. Carey—Mr. Robert L. Carey
RW Beck—R.W. Beck, Inc.
Small Generator Coalition—American
Council for an Energy Efficient Economy;
American Solar Energy Society; American
Wind Energy Association; BP Solar; Citizens
Action Coalition of Indiana; Coffman
Electrical Equipment; Cummins Power
Generation; Elliott Energy Systems; Encorp;
Environmental Law & Policy Center; Kyocera
Solar, Inc.; MAN Turbomachinery, Inc.;
Natural Resources Defense Council;
Northeast-Midwest Institute; Northwest
Energy Coalition; Pace Energy Program;
Pennsylvania Energy Project; Plug Power,
Inc.; Power Equipment Associates;
PowerLight Corporation; RWE SCHOTT
Solar, Inc.; Shepherd Advisors; Solar Energy
Industries Association; Spire Solar, Inc.; U.S.
Combined Heat and Power Association; and
University of Oregon Solar Radiation
Monitoring Laboratory.
SMUD—Sacramento Municipal Utility
District
SoCal Edison—Southern California Edison
Company
Solar Turbines—Solar Turbines, Inc.
Southern Company—Southern Company
Services, Inc.
SW TDU Group—Southwest Transmission
Dependent Utility Group (Aguila Irrigation
District, Ak-Chin Electric Utility Authority,
Buckeye Water Conservation and Drainage
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
District, Central Arizona Water Conservation
District, Electrical District No. 3, Electrical
District No. 4, Electrical District No. 5,
Electrical District No. 6, Electrical District
No. 7, Electrical District No. 8, Harquahala
Valley Power District, Maricopa County
Municipal Water District No. 1, McMullen
Valley Water Conservation and Drainage
District, City of Needles, Roosevelt Irrigation
District, City of Safford, Tonopah Irrigation
District, Wellton-Mohawk Irrigation and
Drainage District)
Tangibl—Tangibl, LLC
TAPS—Transmission Access Policy Study
Group
TDU Systems—Transmission Dependent
Utility Systems (Alabama Electric
Cooperative, Inc.; Arkansas Electric
Cooperative Corporation; Golden Spread
Electric Cooperative; Kansas Electric Power
Cooperative, Inc.; Old Dominion Electric
Cooperative; and Seminole Electric
Cooperative, Inc.)
USCHPA—U.S. Combined Heat and Power
Association
Western—Western Area Power
Administration
Commenters Who Filed in Response to the
Commission’s Request for Supplemental
Comments
CT DPUC—Connecticut Department of
Public Utility Control
PO 00000
Frm 00054
Fmt 4701
Sfmt 4700
FERC DRS—Dispute Resolution Service,
Federal Energy Regulatory Commission
Joint Commenters—National Association of
Regulatory Utility Commissioners, Small
Generator Coalition (members listed above),
National Rural Electric Cooperative
Association, and Edison Electric Institute
(American Public Power Association did not
participate in the filing of supplemental
comments)
Massachusetts DTE—Massachusetts
Department of Telecommunications and
Energy
Minnesota PUC—Minnesota Public
Utilities Commission and the Minnesota
Department of Commerce
National Grid—National Grid USA
NJ BPU—New Jersey Board of Public
Utilities
North Carolina Commission—North
Carolina Utilities Commission and the Public
Staff of the North Carolina Utilities
Commission
NRECA—National Rural Electric
Cooperative Association
Ohio PUC—Public Utilities Commission of
Ohio
PJM—PJM Interconnection, L.L.C.
Small Generator Coalition (members listed
above)
USCHPA—U.S. Combined Heat and Power
Association
BILLING CODE 6717–01–U
E:\FR\FM\13JNR2.SGM
13JNR2
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00055
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
34243
ER13JN05.000
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00056
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.001
34244
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
34245
Appendix D—Flow Chart for Interconnecting a Certified Inverter-Based Small Generating Facility No Larger Than 10 kW
Using the ‘‘10 kW Inverter Process’’
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00057
Fmt 4701
Sfmt 4700
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.002
BILLING CODE 6717—01—C
34246
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Appendix E to the Small Generator
Interconnection Final Rule
SMALL GENERATOR INTERCONNECTION
PROCEDURES (SGIP) (For Generating
Facilities No Larger Than 20 MW)
Table of Contents
Section 1. Application
1.1 Applicability
1.2 Pre-Application
1.3 Interconnection Request
1.4 Modification of the Interconnection
Request
1.5 Site Control
1.6 Queue Position
1.7 Interconnection Requests Submitted
Prior to the Effective Date of the SGIP
Section 2. Fast Track Process
2.1 Applicability
2.2 Initial Review
2.2.1 Screens
2.3 Customer Options Meeting
2.4 Supplemental Review
Section 3. Study Process
3.1 Applicability
3.2 Scoping Meeting
3.3 Feasibility Study
3.4 System Impact Study
3.5 Facilities Study
Section 4. Provisions That Apply to All
Interconnection Requests
4.1 Reasonable Efforts
4.2 Disputes
4.3 Interconnection Metering
4.4 Commissioning
4.5 Confidentiality
4.6 Comparability
4.7 Record Retention
4.8 Interconnection Agreement
4.9 Coordination With Affected Systems
4.10 Capacity of the Small Generating
Facility
Attachment 1—Glossary of Terms
Attachment 2—Small Generator
Interconnection Request
Attachment 3—Certification Codes and
Standards
Attachment 4—Certification of Small
Generator Equipment Packages
Attachment 5—Application, Procedures,
and Terms and Conditions for
Interconnecting a Certified Inverter-Based
Small Generating Facility No Larger Than 10
kW (‘‘10 kW Inverter Process’’)
Attachment 6—Feasibility Study
Agreement
Attachment 7—System Impact Study
Agreement
Attachment 8—Facilities Study Agreement
Section 1. Application
1.1 Applicability
1.1.1 A request to interconnect a certified
Small Generating Facility (See Attachments 3
and 4 for description of certification criteria)
no larger than 2 MW shall be evaluated under
the section 2 Fast Track Process. A request
to interconnect a certified inverter-based
Small Generating Facility no larger than 10
kW shall be evaluated under the Attachment
5 10 kW Inverter Process. A request to
interconnect a Small Generating Facility
larger than 2 MW but no larger than 20 MW
or a Small Generating Facility that does not
pass the Fast Track Process or the 10 kW
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
Inverter Process, shall be evaluated under the
section 3 Study Process.
1.1.2 Capitalized terms used herein shall
have the meanings specified in the Glossary
of Terms in Attachment 1 or the body of
these procedures.
1.1.3 Neither these procedures nor the
requirements included hereunder apply to
Small Generating Facilities interconnected or
approved for interconnection prior to 60
Business Days after the effective date of these
procedures.
1.1.4 Prior to submitting its
Interconnection Request (Attachment 2), the
Interconnection Customer may ask the
Transmission Provider’s interconnection
contact employee or office whether the
proposed interconnection is subject to these
procedures. The Transmission Provider shall
respond within 15 Business Days.
1.1.5 Infrastructure security of electric
system equipment and operations and
control hardware and software is essential to
ensure day-to-day reliability and operational
security. The Federal Energy Regulatory
Commission expects all Transmission
Providers, market participants, and
Interconnection Customers interconnected
with electric systems to comply with the
recommendations offered by the President’s
Critical Infrastructure Protection Board and
best practice recommendations from the
electric reliability authority. All public
utilities are expected to meet basic standards
for electric system infrastructure and
operational security, including physical,
operational, and cyber-security practices.
1.1.6 References in these procedures to
interconnection agreement are to the Small
Generator Interconnection Agreement (SGIA).
1.2 Pre-Application
The Transmission Provider shall designate
an employee or office from which
information on the application process and
on an Affected System can be obtained
through informal requests from the
Interconnection Customer presenting a
proposed project for a specific site. The
name, telephone number, and e-mail address
of such contact employee or office shall be
made available on the Transmission
Provider’s Internet web site. Electric system
information provided to the Interconnection
Customer should include relevant system
studies, interconnection studies, and other
materials useful to an understanding of an
interconnection at a particular point on the
Transmission Provider’s Transmission
System, to the extent such provision does not
violate confidentiality provisions of prior
agreements or critical infrastructure
requirements. The Transmission Provider
shall comply with reasonable requests for
such information.
1.3 Interconnection Request
The Interconnection Customer shall submit
its Interconnection Request to the
Transmission Provider, together with the
processing fee or deposit specified in the
Interconnection Request. The
Interconnection Request shall be date- and
time-stamped upon receipt. The original
date- and time-stamp applied to the
Interconnection Request at the time of its
PO 00000
Frm 00058
Fmt 4701
Sfmt 4700
original submission shall be accepted as the
qualifying date- and time-stamp for the
purposes of any timetable in these
procedures. The Interconnection Customer
shall be notified of receipt by the
Transmission Provider within three Business
Days of receiving the Interconnection
Request. The Transmission Provider shall
notify the Interconnection Customer within
ten Business Days of the receipt of the
Interconnection Request as to whether the
Interconnection Request is complete or
incomplete. If the Interconnection Request is
incomplete, the Transmission Provider shall
provide along with the notice that the
Interconnection Request is incomplete, a
written list detailing all information that
must be provided to complete the
Interconnection Request. The
Interconnection Customer will have ten
Business Days after receipt of the notice to
submit the listed information or to request an
extension of time to provide such
information. If the Interconnection Customer
does not provide the listed information or a
request for an extension of time within the
deadline, the Interconnection Request will be
deemed withdrawn. An Interconnection
Request will be deemed complete upon
submission of the listed information to the
Transmission Provider.
1.4 Modification of the Interconnection
Request
Any modification to machine data or
equipment configuration or to the
interconnection site of the Small Generating
Facility not agreed to in writing by the
Transmission Provider and the
Interconnection Customer may be deemed a
withdrawal of the Interconnection Request
and may require submission of a new
Interconnection Request, unless proper
notification of each Party by the other and a
reasonable time to cure the problems created
by the changes are undertaken.
1.5 Site Control
Documentation of site control must be
submitted with the Interconnection Request.
Site control may be demonstrated through:
1.8.1 Ownership of, a leasehold interest
in, or a right to develop a site for the purpose
of constructing the Small Generating Facility;
1.8.2 An option to purchase or acquire a
leasehold site for such purpose; or
1.8.3 An exclusivity or other business
relationship between the Interconnection
Customer and the entity having the right to
sell, lease, or grant the Interconnection
Customer the right to possess or occupy a site
for such purpose.
1.6 Queue Position
The Transmission Provider shall assign a
Queue Position based upon the date- and
time-stamp of the Interconnection Request.
The Queue Position of each Interconnection
Request will be used to determine the cost
responsibility for the Upgrades necessary to
accommodate the interconnection. The
Transmission Provider shall maintain a
single queue per geographic region. At the
Transmission Provider’s option,
Interconnection Requests may be studied
serially or in clusters for the purpose of the
system impact study.
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
1.7 Interconnection Requests Submitted
Prior to the Effective Date of the SGIP
Nothing in this SGIP affects an
Interconnection Customer’s Queue Position
assigned before the effective date of this
SGIP. The Parties agree to complete work on
any interconnection study agreement
executed prior the effective date of this SGIP
in accordance with the terms and conditions
of that interconnection study agreement. Any
new studies or other additional work will be
completed pursuant to this SGIP.
Section 2. Fast Track Process
2.1 Applicability
The Fast Track Process is available to an
Interconnection Customer proposing to
interconnect its Small Generating Facility
with the Transmission Provider’s
Transmission System if the Small Generating
Facility is no larger than 2 MW and if the
Interconnection Customer’s proposed Small
Generating Facility meets the codes,
standards, and certification requirements of
Attachments 3 and 4 of these procedures, or
the Transmission Provider has reviewed the
design or tested the proposed Small
Generating Facility and is satisfied that it is
safe to operate.
2.2 Initial Review
Within 15 Business Days after the
Transmission Provider notifies the
Interconnection Customer it has received a
complete Interconnection Request, the
Transmission Provider shall perform an
initial review using the screens set forth
below, shall notify the Interconnection
Customer of the results, and include with the
notification copies of the analysis and data
underlying the Transmission Provider’s
determinations under the screens.
2.2.1 Screens.
2.2.1.1 The proposed Small Generating
Facility’s Point of Interconnection must be on
a portion of the Transmission Provider’s
Distribution System that is subject to the
Tariff.
2.2.1.2 For interconnection of a proposed
Small Generating Facility to a radial
distribution circuit, the aggregated
generation, including the proposed Small
Generating Facility, on the circuit shall not
exceed 15% of the line section annual peak
load as most recently measured at the
substation. A line section is that portion of
a Transmission Provider’s electric system
connected to a customer bounded by
automatic sectionalizing devices or the end
of the distribution line.
2.2.1.3 For interconnection of a proposed
Small Generating Facility to the load side of
spot network protectors, the proposed Small
Generating Facility must utilize an inverterbased equipment package and, together with
the aggregated other inverter-based
generation, shall not exceed the smaller of
5% of a spot network’s maximum load or 50
kW.1
1 A spot Network is a type of distribution system
found within modern commercial buildings to
provide high reliability of service to a single
customer. (Standard Handbook for Electrical
Engineers, 11th edition, Donald Fink, McGraw Hill
Book Company).
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
2.2.1.4 The proposed Small Generating
Facility, in aggregation with other generation
on the distribution circuit, shall not
contribute more than 10% to the distribution
circuit’s maximum fault current at the point
on the high voltage (primary) level nearest
the proposed point of change of ownership.
2.2.1.5 The proposed Small Generating
Facility, in aggregate with other generation
on the distribution circuit, shall not cause
any distribution protective devices and
equipment (including, but not limited to,
substation breakers, fuse cutouts, and line
reclosers), or Interconnection Customer
equipment on the system to exceed 87.5% of
the short circuit interrupting capability; nor
shall the interconnection proposed for a
circuit that already exceeds 87.5% of the
short circuit interrupting capability.
2.2.1.6 Using the table below, determine
the type of interconnection to a primary
distribution line. This screen includes a
review of the type of electrical service
provided to the Interconnecting Customer,
including line configuration and the
transformer connection to limit the potential
for creating over-voltages on the
Transmission Provider’s electric power
system due to a loss of ground during the
operating time of any anti-islanding function.
Primary
distribution
line type
Type of
interconnection
to primary
distribution line
Result/
criteria
Three3-phase or single
phase,
phase, phase-tothree
phase.
wire.
ThreeEffectively-grounded
phase,
3 phase or Singlefour wire.
phase, line-toneutral.
Pass
screen.
Pass
screen.
2.2.1.7 If the proposed Small Generating
Facility is to be interconnected on singlephase shared secondary, the aggregate
generation capacity on the shared secondary,
including the proposed Small Generating
Facility, shall not exceed 20 kW.
2.2.1.8 If the proposed Small Generating
Facility is single-phase and is to be
interconnected on a center tap neutral of a
240 volt service, its addition shall not create
an imbalance between the two sides of the
240 volt service of more than 20% of the
nameplate rating of the service transformer.
2.2.1.9 The Small Generating Facility, in
aggregate with other generation
interconnected to the transmission side of a
substation transformer feeding the circuit
where the Small Generating Facility proposes
to interconnect shall not exceed 10 MW in
an area where there are known, or posted,
transient stability limitations to generating
units located in the general electrical vicinity
(e.g., three or four transmission busses from
the point of interconnection).
2.2.1.10 No construction of facilities by
the Transmission Provider on its own system
shall be required to accommodate the Small
Generating Facility.
2.2.2 If the proposed interconnection
passes the screens, the Interconnection
Request shall be approved and the
PO 00000
Frm 00059
Fmt 4701
Sfmt 4700
34247
Transmission Provider will provide the
Interconnection Customer an executable
interconnection agreement within five
Business Days after the determination.
2.2.3 If the proposed interconnection fails
the screens, but the Transmission Provider
determines that the Small Generating Facility
may nevertheless be interconnected
consistent with safety, reliability, and power
quality standards, the Transmission Provider
shall provide the Interconnection Customer
an executable interconnection agreement
within five Business Days after the
determination.
2.2.4 If the proposed interconnection fails
the screens, but the Transmission Provider
does not or cannot determine from the initial
review that the Small Generating Facility
may nevertheless be interconnected
consistent with safety, reliability, and power
quality standards unless the Interconnection
Customer is willing to consider minor
modifications or further study, the
Transmission Provider shall provide the
Interconnection Customer with the
opportunity to attend a customer options
meeting.
2.3
Customer Options Meeting
If the Transmission Provider determines
the Interconnection Request cannot be
approved without minor modifications at
minimal cost; or a supplemental study or
other additional studies or actions; or at
significant cost to address safety, reliability,
or power quality problems, within the five
Business Day period after the determination,
the Transmission Provider shall notify the
Interconnection Customer and provide copies
of all data and analyses underlying its
conclusion. Within ten Business Days of the
Transmission Provider’s determination, the
Transmission Provider shall offer to convene
a customer options meeting with the
Transmission Provider to review possible
Interconnection Customer facility
modifications or the screen analysis and
related results, to determine what further
steps are needed to permit the Small
Generating Facility to be connected safely
and reliably. At the time of notification of the
Transmission Provider’s determination, or at
the customer options meeting, the
Transmission Provider shall:
2.3.1 Offer to perform facility
modifications or minor modifications to the
Transmission Provider’s electric system (e.g.,
changing meters, fuses, relay settings) and
provide a non-binding good faith estimate of
the limited cost to make such modifications
to the Transmission Provider’s electric
system; or
2.3.2 Offer to perform a supplemental
review if the Transmission Provider
concludes that the supplemental review
might determine that the Small Generating
Facility could continue to qualify for
interconnection pursuant to the Fast Track
Process, and provide a non-binding good
faith estimate of the costs of such review; or
2.3.3 Obtain the Interconnection
Customer’s agreement to continue evaluating
the Interconnection Request under the
section 3 Study Process.
E:\FR\FM\13JNR2.SGM
13JNR2
34248
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
2.4 Supplemental Review
If the Interconnection Customer agrees to a
supplemental review, the Interconnection
Customer shall agree in writing within 15
Business Days of the offer, and submit a
deposit for the estimated costs. The
Interconnection Customer shall be
responsible for the Transmission Provider’s
actual costs for conducting the supplemental
review. The Interconnection Customer must
pay any review costs that exceed the deposit
within 20 Business Days of receipt of the
invoice or resolution of any dispute. If the
deposit exceeds the invoiced costs, the
Transmission Provider will return such
excess within 20 Business Days of the
invoice without interest.
2.4.1 Within ten Business Days following
receipt of the deposit for a supplemental
review, the Transmission Provider will
determine if the Small Generating Facility
can be interconnected safely and reliably.
2.4.1.1 If so, the Transmission Provider
shall forward an executable an
interconnection agreement to the
Interconnection Customer within five
Business Days.
2.4.1.2 If so, and Interconnection
Customer facility modifications are required
to allow the Small Generating Facility to be
interconnected consistent with safety,
reliability, and power quality standards
under these procedures, the Transmission
Provider shall forward an executable
interconnection agreement to the
Interconnection Customer within five
Business Days after confirmation that the
Interconnection Customer has agreed to make
the necessary changes at the Interconnection
Customer’s cost.
2.4.1.3 If so, and minor modifications to
the Transmission provider’s electric system
are required to allow the Small Generating
Facility to be interconnected consistent with
safety, reliability, and power quality
standards under the Fast Track Process, the
Transmission Provider shall forward an
executable interconnection agreement to the
Interconnection Customer within ten
Business Days that requires the
Interconnection Customer to pay the costs of
such system modifications prior to
interconnection.
2.4.1.4 If not, the Interconnection Request
will continue to be evaluated under the
section 3 Study Process.
Section 3. Study Process
3.1 Applicability
The Study Process shall be used by an
Interconnection Customer proposing to
interconnect its Small Generating Facility
with the Transmission Provider’s
Transmission System if the Small Generating
Facility (1) is larger than 2 MW but no larger
than 20 MW, (2) is not certified, or (3) is
certified but did not pass the Fast Track
Process or the 10 kW Inverter Process.
3.2 Scoping Meeting
3.2.1 A scoping meeting will be held
within ten Business Days after the
Interconnection Request is deemed complete,
or as otherwise mutually agreed to by the
Parties. The Transmission Provider and the
Interconnection Customer will bring to the
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
meeting personnel, including system
engineers and other resources as may be
reasonably required to accomplish the
purpose of the meeting.
3.2.2 The purpose of the scoping meeting
is to discuss the Interconnection Request and
review existing studies relevant to the
Interconnection Request. The Parties shall
further discuss whether the Transmission
Provider should perform a feasibility study or
proceed directly to a system impact study, or
a facilities study, or an interconnection
agreement. If the Parties agree that a
feasibility study should be performed, the
Transmission Provider shall provide the
Interconnection Customer, as soon as
possible, but not later than five Business
Days after the scoping meeting, a feasibility
study agreement (Attachment 6) including an
outline of the scope of the study and a nonbinding good faith estimate of the cost to
perform the study.
3.2.3 The scoping meeting may be
omitted by mutual agreement. In order to
remain in consideration for interconnection,
an Interconnection Customer who has
requested a feasibility study must return the
executed feasibility study agreement within
15 Business Days. If the Parties agree not to
perform a feasibility study, the Transmission
Provider shall provide the Interconnection
Customer, no later than five Business Days
after the scoping meeting, a system impact
study agreement (Attachment 7) including an
outline of the scope of the study and a nonbinding good faith estimate of the cost to
perform the study.
3.3 Feasibility Study
3.3.1 The feasibility study shall identify
any potential adverse system impacts that
would result from the interconnection of the
Small Generating Facility.
3.3.2 A deposit of the lesser of 50 percent
of the good faith estimated feasibility study
costs or earnest money of $1,000 may be
required from the Interconnection Customer.
3.3.3 The scope of and cost
responsibilities for the feasibility study are
described in the attached feasibility study
agreement.
3.3.4 If the feasibility study shows no
potential for adverse system impacts, the
Transmission Provider shall send the
Interconnection Customer a facilities study
agreement, including an outline of the scope
of the study and a non-binding good faith
estimate of the cost to perform the study. If
no additional facilities are required, the
Transmission Provider shall send the
Interconnection Customer an executable
interconnection agreement within five
Business Days.
3.3.5 If the feasibility study shows the
potential for adverse system impacts, the
review process shall proceed to the
appropriate system impact study(s).
3.4 System Impact Study
3.4.1 A system impact study shall
identify and detail the electric system
impacts that would result if the proposed
Small Generating Facility were
interconnected without project modifications
or electric system modifications, focusing on
the adverse system impacts identified in the
PO 00000
Frm 00060
Fmt 4701
Sfmt 4700
feasibility study, or to study potential
impacts, including but not limited to those
identified in the scoping meeting. A system
impact study shall evaluate the impact of the
proposed interconnection on the reliability of
the electric system.
3.4.2 If no transmission system impact
study is required, but potential electric
power Distribution System adverse system
impacts are identified in the scoping meeting
or shown in the feasibility study, a
distribution system impact study must be
performed. The Transmission Provider shall
send the Interconnection Customer a
distribution system impact study agreement
within 15 Business Days of transmittal of the
feasibility study report, including an outline
of the scope of the study and a non-binding
good faith estimate of the cost to perform the
study, or following the scoping meeting if no
feasibility study is to be performed.
3.4.3 In instances where the feasibility
study or the distribution system impact study
shows potential for transmission system
adverse system impacts, within five Business
Days following transmittal of the feasibility
study report, the Transmission Provider shall
send the Interconnection Customer a
transmission system impact study agreement,
including an outline of the scope of the study
and a non-binding good faith estimate of the
cost to perform the study, if such a study is
required.
3.4.4 If a transmission system impact
study is not required, but electric power
Distribution System adverse system impacts
are shown by the feasibility study to be
possible and no distribution system impact
study has been conducted, the Transmission
Provider shall send the Interconnection
Customer a distribution system impact study
agreement.
3.4.5 If the feasibility study shows no
potential for transmission system or
Distribution System adverse system impacts,
the Transmission Provider shall send the
Interconnection Customer either a facilities
study agreement (Attachment 8), including
an outline of the scope of the study and a
non-binding good faith estimate of the cost to
perform the study, or an executable
interconnection agreement, as applicable.
3.4.6 In order to remain under
consideration for interconnection, the
Interconnection Customer must return
executed system impact study agreements, if
applicable, within 30 Business Days.
3.4.7A deposit of the good faith estimated
costs for each system impact study may be
required from the Interconnection Customer.
3.4.8 The scope of and cost
responsibilities for a system impact study are
described in the attached system impact
study agreement.
3.4.9 Where transmission systems and
Distribution Systems have separate owners,
such as is the case with transmissiondependent utilities (‘‘TDUs’’)—whether
investor-owned or not—the Interconnection
Customer may apply to the nearest
Transmission Provider (Transmission Owner,
Regional Transmission Operator, or
Independent Transmission Provider)
providing transmission service to the TDU to
request project coordination. Affected
Systems shall participate in the study and
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
provide all information necessary to prepare
the study.
3.5 Facilities Study
3.5.1 Once the required system impact
study(s) is completed, a system impact study
report shall be prepared and transmitted to
the Interconnection Customer along with a
facilities study agreement within five
Business Days, including an outline of the
scope of the study and a non-binding good
faith estimate of the cost to perform the
facilities study. In the case where one or both
impact studies are determined to be
unnecessary, a notice of the fact shall be
transmitted to the Interconnection Customer
within the same timeframe.
3.5.2 In order to remain under
consideration for interconnection, or, as
appropriate, in the Transmission Provider’s
interconnection queue, the Interconnection
Customer must return the executed facilities
study agreement or a request for an extension
of time within 30 Business Days.
3.5.3 The facilities study shall specify
and estimate the cost of the equipment,
engineering, procurement and construction
work (including overheads) needed to
implement the conclusions of the system
impact study(s).
3.5.4 Design for any required
Interconnection Facilities and/or Upgrades
shall be performed under the facilities study
agreement. The Transmission Provider may
contract with consultants to perform
activities required under the facilities study
agreement. The Interconnection Customer
and the Transmission Provider may agree to
allow the Interconnection Customer to
separately arrange for the design of some of
the Interconnection Facilities. In such cases,
facilities design will be reviewed and/or
modified prior to acceptance by the
Transmission Provider, under the provisions
of the facilities study agreement. If the Parties
agree to separately arrange for design and
construction, and provided security and
confidentiality requirements can be met, the
Transmission Provider shall make sufficient
information available to the Interconnection
Customer in accordance with confidentiality
and critical infrastructure requirements to
permit the Interconnection Customer to
obtain an independent design and cost
estimate for any necessary facilities.
3.5.5 A deposit of the good faith
estimated costs for the facilities study may be
required from the Interconnection Customer.
3.5.6 The scope of and cost
responsibilities for the facilities study are
described in the attached facilities study
agreement.
3.5.7 Upon completion of the facilities
study, and with the agreement of the
Interconnection Customer to pay for
Interconnection Facilities and Upgrades
identified in the facilities study, the
Transmission Provider shall provide the
Interconnection Customer an executable
interconnection agreement within five
Business Days.
Section 4. Provisions That Apply to All
Interconnection Requests
4.1 Reasonable Efforts
The Transmission Provider shall make
reasonable efforts to meet all time frames
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
provided in these procedures unless the
Transmission Provider and the
Interconnection Customer agree to a different
schedule. If the Transmission Provider
cannot meet a deadline provided herein, it
shall notify the Interconnection Customer,
explain the reason for the failure to meet the
deadline, and provide an estimated time by
which it will complete the applicable
interconnection procedure in the process.
4.2 Disputes
4.2.1 The Parties agree to attempt to
resolve all disputes arising out of the
interconnection process according to the
provisions of this article.
4.2.2 In the event of a dispute, either
Party shall provide the other Party with a
written Notice of Dispute. Such Notice shall
describe in detail the nature of the dispute.
4.2.3 If the dispute has not been resolved
within two Business Days after receipt of the
Notice, either Party may contact FERC’s
Dispute Resolution Service (DRS) for
assistance in resolving the dispute.
4.2.4 The DRS will assist the Parties in
either resolving their dispute or in selecting
an appropriate dispute resolution venue (e.g.,
mediation, settlement judge, early neutral
evaluation, or technical expert) to assist the
Parties in resolving their dispute. DRS can be
reached at 1–877–337–2237 or via the
internet at https://www.ferc.gov/legal/adr.asp.
4.2.5 Each Party agrees to conduct all
negotiations in good faith and will be
responsible for one-half of any costs paid to
neutral third-parties.
4.2.6 If neither Party elects to seek
assistance from the DRS, or if the attempted
dispute resolution fails, then either Party
may exercise whatever rights and remedies it
may have in equity or law consistent with the
terms of this Agreement.
4.3 Interconnection Metering
Any metering necessitated by the use of the
Small Generating Facility shall be installed at
the Interconnection Customer’s expense in
accordance with Federal Energy Regulatory
Commission, state, or local regulatory
requirements or the Transmission Provider’s
specifications.
4.4 Commissioning
Commissioning tests of the Interconnection
Customer’s installed equipment shall be
performed pursuant to applicable codes and
standards. The Transmission Provider must
be given at least five Business Days written
notice, or as otherwise mutually agreed to by
the Parties, of the tests and may be present
to witness the commissioning tests.
4.5. Confidentiality
4.5 Confidentiality information shall mean
any confidential and/or proprietary
information provided by one Party to the
other Party that is clearly marked or
otherwise designated ‘‘Confidential.’’ For
purposes of this Agreement all design,
operating specifications, and metering data
provided by the Interconnection Customer
shall be deemed confidential information
regardless of whether it is clearly marked or
otherwise designated as such.
4.5.2 Confidential Information does not
include information previously in the public
PO 00000
Frm 00061
Fmt 4701
Sfmt 4700
34249
domain, required to be publicly submitted or
divulged by Governmental Authorities (after
notice to the other Party and after exhausting
any opportunity to oppose such publication
or release), or necessary to be divulged in an
action to enforce this Agreement. Each Party
receiving Confidential Information shall hold
such information in confidence and shall not
disclose it to any third party nor to the public
without the prior written authorization from
the Party providing that information, except
to fulfill obligations under this Agreement, or
to fulfill legal or regulatory requirements.
4.5.2.1 Each Party shall employ at least
the same standard of care to protect
Confidential Information obtained from the
other Party as it employs to protect its own
Confidential Information.
4.5.2.2 Each Party is entitled to equitable
relief, by injunction or otherwise, to enforce
its rights under this provision to prevent the
release of Confidential Information without
bond or proof of damages, and may seek
other remedies available at law or in equity
for breach of this provision.
4.5.3 Notwithstanding anything in this
article to the contrary, and pursuant to 18
CFR 1b.20, if FERC, during the course of an
investigation or otherwise, requests
information from one of the Parties that is
otherwise required to be maintained in
confidence pursuant to this Agreement, the
Party shall provide the requested information
to FERC, within the time provided for in the
request for information. In providing the
information to FERC, the Party may,
consistent with 18 CFR 388.112, request that
the information be treated as confidential and
non-public by FERC and that the information
be withheld from public disclosure. Parties
are prohibited from notifying the other Party
to this Agreement prior to the release of the
Confidential Information to FERC. The Party
shall notify the other Party to this Agreement
when it is notified by FERC that a request to
release Confidential Information has been
received by FERC, at which time either of the
Parties may respond before such information
would be made public, pursuant to 18 CFR
388.112. Requests from a state regulatory
body conducting a confidential investigation
shall be treated in a similar manner if
consistent with the applicable state rules and
regulations.
4.6 Comparability
The Transmission Provider shall receive,
process and analyze all Interconnection
Requests in a timely manner as set forth in
this document. The Transmission Provider
shall use the same reasonable efforts in
processing and analyzing Interconnection
Requests from all Interconnection Customers,
whether the Small Generating Facility is
owned or operated by the Transmission
Provider, its subsidiaries or affiliates, or
others.
4.7 Record Retention
The Transmission Provider shall maintain
for three years records, subject to audit, of all
Interconnection Requests received under
these procedures, the times required to
complete Interconnection Request approvals
and disapprovals, and justification for the
actions taken on the Interconnection
Requests.
E:\FR\FM\13JNR2.SGM
13JNR2
34250
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
4.8 Interconnection Agreement
After receiving an interconnection
agreement from the Transmission Provider,
the Interconnection Customer shall have 30
Business Days or another mutually agreeable
timeframe to sign and return the
interconnection agreement, or request that
the Transmission Provider file an unexecuted
interconnection agreement with the Federal
Energy Regulatory Commission. If the
Interconnection Customer does not sign the
interconnection agreement, or ask that it be
filed unexecuted by the Transmission
Provider within 30 Business Days, the
Interconnection Request shall be deemed
withdrawn. After the interconnection
agreement is signed by the Parties, the
interconnection of the Small Generating
Facility shall proceed under the provisions of
the interconnection agreement.
4.9 Coordination With Affected Systems
The Transmission Provider shall
coordinate the conduct of any studies
required to determine the impact of the
Interconnection Request on Affected Systems
with Affected System operators and, if
possible, include those results (if available)
in its applicable interconnection study
within the time frame specified in these
procedures. The Transmission Provider will
include such Affected System operators in all
meetings held with the Interconnection
Customer as required by these procedures.
The Interconnection Customer will cooperate
with the Transmission Provider in all matters
related to the conduct of studies and the
determination of modifications to Affected
Systems. A Transmission Provider which
may be an Affected System shall cooperate
with the Transmission Provider with whom
interconnection has been requested in all
matters related to the conduct of studies and
the determination of modifications to
Affected Systems.
4.10 Capacity of the Small Generating
Facility
4.10.1 If the Interconnection Request is
for an increase in capacity for an existing
Small Generating Facility, the
Interconnection Request shall be evaluated
on the basis of the new total capacity of the
Small Generating Facility.
4.10.2 If the Interconnection Request is
for a Small Generating Facility that includes
multiple energy production devices at a site
for which the Interconnection Customer
seeks a single Point of Interconnection, the
Interconnection Request shall be evaluated
on the basis of the aggregate capacity of the
multiple devices.
4.10.3 The Interconnection Request shall
be evaluated using the maximum rated
capacity of the Small Generating Facility.
Attachment 1—Glossary of Terms
10 kW Inverter Process—The procedure for
evaluating an Interconnection Request for a
certified inverter-based Small Generating
Facility no larger than 10 kW that uses the
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
section 2 screens. The application process
uses an all-in-one document that includes a
simplified Interconnection Request,
simplified procedures, and a brief set of
terms and conditions. See SGIP Attachment
5.
Affected System—An electric system other
than the Transmission Provider’s
Transmission System that may be affected by
the proposed interconnection.
Business Day—Monday through Friday,
excluding Federal Holidays.
Distribution System—The Transmission
Provider’s facilities and equipment used to
transmit electricity to ultimate usage points
such as homes and industries directly from
nearby generators or from interchanges with
higher voltage transmission networks which
transport bulk power over longer distances.
The voltage levels at which Distribution
Systems operate differ among areas.
Distribution Upgrades—The additions,
modifications, and upgrades to the
Transmission Provider’s Distribution System
at or beyond the Point of Interconnection to
facilitate interconnection of the Small
Generating Facility and render the
transmission service necessary to effect the
Interconnection Customer’s wholesale sale of
electricity in interstate commerce.
Distribution Upgrades do not include
Interconnection Facilities.
Fast Track Process—The procedure for
evaluating an Interconnection Request for a
certified Small Generating Facility no larger
than 2 MW that includes the section 2
screens, customer options meeting, and
optional supplemental review.
Interconnection Customer—Any entity,
including the Transmission Provider, the
Transmission Owner or any of the affiliates
or subsidiaries of either, that proposes to
interconnect its Small Generating Facility
with the Transmission Provider’s
Transmission System.
Interconnection Facilities—The
Transmission Provider’s Interconnection
Facilities and the Interconnection Customer’s
Interconnection Facilities. Collectively,
Interconnection Facilities include all
facilities and equipment between the Small
Generating Facility and the Point of
Interconnection, including any modification,
additions or upgrades that are necessary to
physically and electrically interconnect the
Small Generating Facility to the
Transmission Provider’s Transmission
System. Interconnection Facilities are sole
use facilities and shall not include
Distribution Upgrades or Network Upgrades.
Interconnection Request—The
Interconnection Customer’s request, in
accordance with the Tariff, to interconnect a
new Small Generating Facility, or to increase
the capacity of, or make a Material
Modification to the operating characteristics
of, an existing Small Generating Facility that
is interconnected with the Transmission
Provider’s Transmission System.
Material Modification—A modification
that has a material impact on the cost or
PO 00000
Frm 00062
Fmt 4701
Sfmt 4700
timing of any Interconnection Request with
a later queue priority date.
Network Upgrades—Additions,
modifications, and upgrades to the
Transmission Provider’s Transmission
System required at or beyond the point at
which the Small Generating Facility
interconnects with the Transmission
Provider’s Transmission System to
accommodate the interconnection with the
Small Generating Facility to the
Transmission Provider’s Transmission
System. Network Upgrades do not include
Distribution Upgrades.
Party or Parties—The Transmission
Provider, Transmission Owner,
Interconnection Customer or any
combination of the above.
Point of Interconnection—The point where
the Interconnection Facilities connect with
the Transmission Provider’s Transmission
System.
Queue Position—The order of a valid
Interconnection Request, relative to all other
pending valid Interconnection Requests, that
is established based upon the date and time
of receipt of the valid Interconnection
Request by the Transmission Provider.
Small Generating Facility—The
Interconnection Customer’s device for the
production of electricity identified in the
Interconnection Request, but shall not
include the Interconnection Customer’s
Interconnection Facilities.
Study Process—The procedure for
evaluating an Interconnection Request that
includes the section 3 scoping meeting,
feasibility study, system impact study, and
facilities study.
Transmission Owner—The entity that
owns, leases or otherwise possesses an
interest in the portion of the Transmission
System at the Point of Interconnection and
may be a Party to the Small Generator
Interconnection Agreement to the extent
necessary.
Transmission Provider—The public utility
(or its designated agent) that owns, controls,
or operates transmission or distribution
facilities used for the transmission of
electricity in interstate commerce and
provides transmission service under the
Tariff. The term Transmission Provider
should be read to include the Transmission
Owner when the Transmission Owner is
separate from the Transmission Provider.
Transmission System—The facilities
owned, controlled or operated by the
Transmission Provider or the Transmission
Owner that are used to provide transmission
service under the Tariff.
Upgrades—The required additions and
modifications to the Transmission Provider’s
Transmission System at or beyond the Point
of Interconnection. Upgrades may be
Network Upgrades or Distribution Upgrades.
Upgrades do not include Interconnection
Facilities.
BILLING CODE 6717–01–U
E:\FR\FM\13JNR2.SGM
13JNR2
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00063
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
34251
ER13JN05.003
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00064
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.004
34252
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00065
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
34253
ER13JN05.005
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00066
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.006
34254
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00067
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
34255
ER13JN05.007
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00068
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.008
34256
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00069
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
34257
ER13JN05.009
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00070
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.010
34258
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00071
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
34259
ER13JN05.011
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00072
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.012
34260
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00073
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
34261
ER13JN05.013
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00074
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.014
34262
34263
BILLING CODE 6717–01–C
VerDate jul<14>2003
22:03 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00075
Fmt 4701
Sfmt 4700
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.015
ER13JN05.016
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
34264
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Attachment 3—Certification Codes and
Standards
IEEE1547 Standard for Interconnecting
Distributed Resources with Electric Power
Systems (including use of IEEE 1547.1
testing protocols to establish conformity)
UL 1741 Inverters, Converters, and
Controllers for Use in Independent Power
Systems
IEEE Std 929–2000 IEEE Recommended
Practice for Utility Interface of Photovoltaic
(PV) Systems
NFPA 70 (2002), National Electrical Code
IEEE Std C37.90.1–1989 (R1994), IEEE
Standard Surge Withstand Capability
(SWC) Tests for Protective Relays and
Relay Systems
IEEE Std C37.90.2 (1995), IEEE Standard
Withstand Capability of Relay Systems to
Radiated Electromagnetic Interference from
Transceivers
IEEE Std C37.108–1989 (R2002), IEEE Guide
for the Protection of Network Transformers
IEEE Std C57.12.44–2000, IEEE Standard
Requirements for Secondary Network
Protectors
IEEE Std C62.41.2–2002, IEEE Recommended
Practice on Characterization of Surges in
Low Voltage (1000V and Less) AC Power
Circuits
IEEE Std C62.45–1992 (R2002), IEEE
Recommended Practice on Surge Testing
for Equipment Connected to Low-Voltage
(1000V and Less) AC Power Circuits
ANSI C84.1–1995 Electric Power Systems
and Equipment—Voltage Ratings (60 Hertz)
IEEE Std 100–2000, IEEE Standard Dictionary
of Electrical and Electronic Terms
NEMA MG 1–1998, Motors and Small
Resources, Revision 3
IEEE Std 519–1992, IEEE Recommended
Practices and Requirements for Harmonic
Control in Electrical Power Systems
NEMA MG 1–2003 (Rev 2004), Motors and
Generators, Revision 1
Attachment 4—Certification of Small
Generator Equipment Packages
1.0 Small Generating Facility equipment
proposed for use separately or packaged with
other equipment in an interconnection
system shall be considered certified for
interconnected operation if (1) it has been
tested in accordance with industry standards
for continuous utility interactive operation in
compliance with the appropriate codes and
standards referenced below by any
Nationally Recognized Testing Laboratory
(NRTL) recognized by the United States
Occupational Safety and Health
Administration to test and certify
interconnection equipment pursuant to the
relevant codes and standards listed in SGIP
Attachment 3, (2) it has been labeled and is
publicly listed by such NRTL at the time of
the interconnection application, and (3) such
NRTL makes readily available for verification
VerDate jul<14>2003
22:03 Jun 10, 2005
Jkt 205001
all test standards and procedures it utilized
in performing such equipment certification,
and, with consumer approval, the test data
itself. The NRTL may make such information
available on its website and by encouraging
such information to be included in the
manufacturer’s literature accompanying the
equipment.
2.0 The Interconnection Customer must
verify that the intended use of the equipment
falls within the use or uses for which the
equipment was tested, labeled, and listed by
the NRTL.
3.0 Certified equipment shall not require
further type-test review, testing, or additional
equipment to meet the requirements of this
interconnection procedure; however, nothing
herein shall preclude the need for an on-site
commissioning test by the parties to the
interconnection nor follow-up production
testing by the NRTL.
4.0 If the certified equipment package
includes only interface components
(switchgear, inverters, or other interface
devices), then an Interconnection Customer
must show that the generator or other electric
source being utilized with the equipment
package is compatible with the equipment
package and is consistent with the testing
and listing specified for this type of
interconnection equipment.
5.0 Provided the generator or electric
source, when combined with the equipment
package, is within the range of capabilities
for which it was tested by the NRTL, and
does not violate the interface components’
labeling and listing performed by the NRTL,
no further design review, testing or
additional equipment on the customer side of
the point of common coupling shall be
required to meet the requirements of this
interconnection procedure.
6.0 An equipment package does not
include equipment provided by the utility.
7.0 Any equipment package approved
and listed in a state by that state’s regulatory
body for interconnected operation in that
state prior to the effective date of these small
generator interconnection procedures shall
be considered certified under these
procedures for use in that state.
Attachment 5—Application, Procedures, and
Terms and Conditions for Interconnecting a
Certified Inverter-Based Small Generating
Facility No Larger Than 10 kW (‘‘10 kW
Inverter Process’’)
1.0 The Interconnection Customer
(‘‘Customer’’) completes the Interconnection
Request (‘‘Application’’) and submits it to the
Transmission Provider (‘‘Company’’).
2.0 The Company acknowledges to the
Customer receipt of the Application within
three Business Days of receipt.
3.0 The Company evaluates the
Application for completeness and notifies the
Customer within ten Business Days of receipt
PO 00000
Frm 00076
Fmt 4701
Sfmt 4700
that the Application is or is not complete
and, if not, advises what material is missing.
4.0 The Company verifies that the Small
Generating Facility can be interconnected
safely and reliably using the screens
contained in the Fast Track Process in the
Small Generator Interconnection Procedures
(SGIP). The Company has 15 Business Days
to complete this process. Unless the
Company determines and demonstrates that
the Small Generating Facility cannot be
interconnected safely and reliably, the
Company approves the Application and
returns it to the Customer. Note to Customer:
Please check with the Company before
submitting the Application if disconnection
equipment is required.
5.0 After installation, the Customer
returns the Certificate of Completion to the
Company. Prior to parallel operation, the
Company may inspect the Small Generating
Facility for compliance with standards which
may include a witness test, and may
schedule appropriate metering replacement,
if necessary.
6.0 The Company notifies the Customer
in writing that interconnection of the Small
Generating Facility is authorized. If the
witness test is not satisfactory, the Company
has the right to disconnect the Small
Generating Facility. The Customer has no
right to operate in parallel until a witness test
has been performed, or previously waived on
the Application. The Company is obligated to
complete this witness test within ten
Business Days of the receipt of the Certificate
of Completion. If the Company does not
inspect within ten Business Days or by
mutual agreement of the Parties, the witness
test is deemed waived.
7.0 Contact Information—The Customer
must provide the contact information for the
legal applicant (i.e., the Interconnection
Customer). If another entity is responsible for
interfacing with the Company, that contact
information must be provided on the
Application.
8.0 Ownership Information—Enter the
legal names of the owner(s) of the Small
Generating Facility. Include the percentage
ownership (if any) by any utility or public
utility holding company, or by any entity
owned by either.
9.0 UL1741 Listed—This standard
(‘‘Inverters, Converters, and Controllers for
Use in Independent Power Systems’’)
addresses the electrical interconnection
design of various forms of generating
equipment. Many manufacturers submit their
equipment to a Nationally Recognized
Testing Laboratory (NRTL) that verifies
compliance with UL1741. This ‘‘listing’’ is
then marked on the equipment and
supporting documentation.
BILLING CODE 6717–01–U
E:\FR\FM\13JNR2.SGM
13JNR2
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00077
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
34265
ER13JN05.017
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00078
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.018
34266
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00079
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
34267
ER13JN05.019
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00080
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.020
34268
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00081
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
34269
ER13JN05.021
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00082
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.022
34270
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
34271
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00083
Fmt 4701
Sfmt 4700
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.023
BILLING CODE 6717–01–C
34272
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Terms and Conditions for Interconnecting an
Inverter-Based Small Generating Facility No
Larger Than 10kW
1.0
Construction of the Facility
The Interconnection Customer (the
‘‘Customer’’) may proceed to construct
(including operational testing not to exceed
two hours) the Small Generating Facility
when the Transmission Provider (the
‘‘Company’’) approves the Interconnection
Request (the ‘‘Application’’) and returns it to
the Customer.
2.0
Interconnection and Operation
The Customer may operate Small
Generating Facility and interconnect with the
Company’s electric system once all of the
following have occurred:
2.1 Upon completing construction, the
Customer will cause the Small Generating
Facility to be inspected or otherwise certified
by the appropriate local electrical wiring
inspector with jurisdiction, and
2.2 The Customer returns the Certificate
of Completion to the Company, and
2.3 The Company has either:
2.3.1 Completed its inspection of the
Small Generating Facility to ensure that all
equipment has been appropriately installed
and that all electrical connections have been
made in accordance with applicable codes.
All inspections must be conducted by the
Company, at its own expense, within ten
Business Days after receipt of the Certificate
of Completion and shall take place at a time
agreeable to the Parties. The Company shall
provide a written statement that the Small
Generating Facility has passed inspection or
shall notify the Customer of what steps it
must take to pass inspection as soon as
practicable after the inspection takes place;
or
2.3.2 If the Company does not schedule
an inspection of the Small Generating
Facility within ten business days after
receiving the Certificate of Completion, the
witness test is deemed waived (unless the
Parties agree otherwise); or
2.3.3 The Company waives the right to
inspect the Small Generating Facility.
2.4 The Company has the right to
disconnect the Small Generating Facility in
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
the event of improper installation or failure
to return the Certificate of Completion.
2.5 Revenue quality metering equipment
must be installed and tested in accordance
with applicable ANSI standards.
3.0 Safe Operations and Maintenance
The Customer shall be fully responsible to
operate, maintain, and repair the Small
Generating Facility as required to ensure that
it complies at all times with the
interconnection standards to which it has
been certified.
4.0 Access
The Company shall have access to the
disconnect switch (if the disconnect switch
is required) and metering equipment of the
Small Generating Facility at all times. The
Company shall provide reasonable notice to
the Customer when possible prior to using its
right of access.
5.0 Disconnection
The Company may temporarily disconnect
the Small Generating Facility upon the
following conditions:
5.1 For scheduled outages upon
reasonable notice.
5.2 For unscheduled outages or
emergency conditions.
5.3 If the Small Generating Facility does
not operate in the manner consistent with
these Terms and Conditions.
5.4 The Company shall inform the
Customer in advance of any scheduled
disconnection, or as is reasonable after an
unscheduled disconnection.
6.0 Indemnification
The Parties shall at all times indemnify,
defend, and save the other Party harmless
from, any and all damages, losses, claims,
including claims and actions relating to
injury to or death of any person or damage
to property, demand, suits, recoveries, costs
and expenses, court costs, attorney fees, and
all other obligations by or to third parties,
arising out of or resulting from the other
Party’s action or inactions of its obligations
under this agreement on behalf of the
indemnifying Party, except in cases of gross
negligence or intentional wrongdoing by the
indemnified Party.
PO 00000
Frm 00084
Fmt 4701
Sfmt 4700
7.0 Insurance
The Parties each agree to maintain
commercially reasonable amounts of
insurance.
8.0 Limitation of Liability
Each party’s liability to the other party for
any loss, cost, claim, injury, liability, or
expense, including reasonable attorney’s fees,
relating to or arising from any act or omission
in its performance of this Agreement, shall be
limited to the amount of direct damage
actually incurred. In no event shall either
party be liable to the other party for any
indirect, incidental, special, consequential,
or punitive damages of any kind whatsoever,
except as allowed under paragraph 6.0.
9.0 Termination
The agreement to operate in parallel may
be terminated under the following
conditions:
9.1
By the Customer
By providing written notice to the
Company.
9.2 By the Company
If the Small Generating Facility fails to
operate for any consecutive 12 month period
or the Customer fails to remedy a violation
of these Terms and Conditions.
9.3 Permanent Disconnection
In the event this Agreement is terminated,
the Company shall have the right to
disconnect its facilities or direct the
Customer to disconnect its Small Generating
Facility.
9.4 Survival Rights
This Agreement shall continue in effect
after termination to the extent necessary to
allow or require either Party to fulfill rights
or obligations that arose under the
Agreement.
10.0 Assignment/Transfer of Ownership of
the Facility
This Agreement shall survive the transfer
of ownership of the Small Generating Facility
to a new owner when the new owner agrees
in writing to comply with the terms of this
Agreement and so notifies the Company.
E:\FR\FM\13JNR2.SGM
13JNR2
WHEREAS, Interconnection Customer has
requested the Transmission Provider to
perform a feasibility study to assess the
feasibility of interconnecting the proposed
Small Generating Facility with the
Transmission Provider’s Transmission
System, and of any Affected Systems;
NOW, THEREFORE, in consideration of
and subject to the mutual covenants
contained herein the Parties agreed as
follows:
1.0 When used in this Agreement, with
initial capitalization, the terms specified
shall have the meanings indicated or the
meanings specified in the standard Small
Generator Interconnection Procedures.
2.0 The Interconnection Customer elects
and the Transmission Provider shall cause to
be performed an interconnection feasibility
study consistent with the standard Small
Generator Interconnection Procedures in
accordance with the Open Access
Transmission Tariff.
3.0 The scope of the feasibility study
shall be subject to the assumptions set forth
in Attachment A to this Agreement.
4.0 The feasibility study shall be based on
the technical information provided by the
Interconnection Customer in the
Interconnection Request, as may be modified
as the result of the scoping meeting. The
Transmission Provider reserves the right to
request additional technical information from
the Interconnection Customer as may
reasonably become necessary consistent with
Good Utility Practice during the course of the
feasibility study and as designated in
accordance with the standard Small
Generator Interconnection Procedures. If the
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
Interconnection Customer modifies its
Interconnection Request, the time to
complete the feasibility study may be
extended by agreement of the Parties.
5.0 In performing the study, the
Transmission Provider shall rely, to the
extent reasonably practicable, on existing
studies of recent vintage. The
Interconnection Customer shall not be
charged for such existing studies; however,
the Interconnection Customer shall be
responsible for charges associated with any
new study or modifications to existing
studies that are reasonably necessary to
perform the feasibility study.
6.0 The feasibility study report shall
provide the following analyses for the
purpose of identifying any potential adverse
system impacts that would result from the
interconnection of the Small Generating
Facility as proposed:
6.1 Initial identification of any circuit
breaker short circuit capability limits
exceeded as a result of the interconnection;
6.2 Initial identification of any thermal
overload or voltage limit violations resulting
from the interconnection;
6.3 Initial review of grounding
requirements and electric system protection;
and
6.4 Description and non-bonding
estimated cost of facilities required to
interconnect the proposed Small Generating
Facility and to address the identified short
circuit and power flow issues.
7.0 The feasibility study shall model the
impact of the Small Generating Facility
regardless of purpose in order to avoid the
further expense and interruption of operation
PO 00000
Frm 00085
Fmt 4701
Sfmt 4700
34273
for reexamination of feasibility and impacts
if the Interconnection Customer later changes
the purpose for which the Small Generating
Facility is being installed.
8.0 The study shall include the feasibility
of any interconnection at a proposed project
site where there could be multiple potential
Points of Interconnection, as requested by the
Interconnection Customer and at the
Interconnection Customer’s cost.
9.0 A deposit of the lesser of 50 percent
of good faith estimated feasibility study costs
or earnest money of $1,000 may be required
from the Interconnection Customer.
10.0 Once the feasibility study is
completed, a feasibility study report shall be
prepared and transmitted to the
Interconnection Customer. Barring unusual
circumstances, the feasibility study must be
completed and the feasibility study report
transmitted within 30 Business Days of the
Interconnection Customer’s agreement to
conduct a feasibility study.
11.0 Any study fees shall be based on the
Transmission Provider’s actual costs and will
be invoiced to the Interconnection Customer
after the study is completed and delivered
and will include a summary of professional
time.
12.0 The Interconnection Customer must
pay any study costs that exceed the deposit
without interest within 30 calendar days on
receipt of the invoice or resolution of any
dispute. If the deposit exceeds the invoiced
fees, the Transmission Provider shall refund
such excess within 30 calendar days of the
invoice without interest.
IN WITNESS WHEREOF, the Parties have
caused this Agreement to be duly executed
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.024
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
34274
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
by their duly authorized officers or agents on
the day and year first above written.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00086
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.025
BILLING CODE 6717–01–U
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00087
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
34275
ER13JN05.026
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Recitals
WHEREAS, the Interconnection Customer
is proposing to develop a Small Generating
Facility or generating capacity addition to an
existing Small Generating Facility consistent
with the Interconnection Request completed
by the Interconnection Customer
onlllll; and
WHEREAS, the Interconnection Customer
desires to interconnect the Small Generating
Facility with the Transmission Provider’s
Transmission System;
WHEREAS, the Transmission Provider has
completed a feasibility study and provided
the results of said study to the
Interconnection Customer (This recital to be
omitted if the Parties have agreed to forego
the feasibility study.); and
WHEREAS, the Interconnection Customer
has requested the Transmission Provider to
perform a system impact study(s) to assess
the impact of interconnecting the Small
Generating Facility with the Transmission
Provider’s Transmission System, and of any
Affected Systems;
NOW, THEREFORE, in consideration of
and subject to the mutual covenants
contained herein the Parties agreed as
follows:
1.0 When used in this Agreement, with
initial capitalization, the terms specified
shall have the meanings indicated or the
meanings specified in the standard Small
Generator Interconnection Procedures.
2.0 The Interconnection Customer elects
and the Transmission Provider shall cause to
be performed a system impact study(s)
consistent with the standard Small Generator
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
Interconnection Procedures in accordance
with the Open Access Transmission Tariff.
3.0 The scope of a system impact study
shall be subject to the assumptions set forth
in Attachment A to this Agreement.
4.0 A system impact study will be based
upon the results of the feasibility study and
the technical information provided by
Interconnection Customer in the
Interconnection Request. The Transmission
Provider reserves the right to request
additional technical information from the
Interconnection Customer as may reasonably
become necessary consistent with Good
Utility Practice during the course of the
system impact study. If the Interconnection
Customer modifies its designated Point of
Interconnection, Interconnection Request, or
the technical information provided therein is
modified, the time to complete the system
impact study may be extended.
5.0 A system impact study shall consist
of a short circuit analysis, a stability analysis,
a power flow analysis, voltage drop and
flicker studies, protection and set point
coordination studies, and grounding reviews,
as necessary. A system impact study shall
state the assumptions upon which it is based,
state the results of the analyses, and provide
the requirement or potential impediments to
providing the requested interconnection
service, including a preliminary indication of
the cost and length of time that would be
necessary to correct any problems identified
in those analyses and implement the
interconnection. A system impact study shall
provide a list of facilities that are required as
a result of the Interconnection Request and
PO 00000
Frm 00088
Fmt 4701
Sfmt 4700
non-binding good faith estimates of cost
responsibility and time to construct.
6.0 A distribution system impact study
shall incorporate a distribution load flow
study, an analysis of equipment interrupting
ratings, protection coordination study,
voltage drop and flicker studies, protection
and set point coordination studies, grounding
reviews, and the impact on electric system
operation, as necessary.
7.0 Affected Systems may participate in
the preparation of a system impact study,
with a division of costs among such entities
as they may agree. All Affected Systems shall
be afforded an opportunity to review and
comment upon a system impact study that
covers potential adverse system impacts on
their electric systems, and the Transmission
Provider has 20 additional Business Days to
complete a system impact study requiring
review by Affected Systems.
8.0 If the Transmission Provider uses a
queuing procedure for sorting or prioritizing
projects and their associated cost
responsibilities for any required Network
Upgrades, the system impact study shall
consider all generating facilities (and with
respect to paragraph 8.3 below, any
identified Upgrades associated with such
higher queued interconnection) that, on the
date the system impact study is
commenced—
8.1 Are directly interconnected with the
Transmission Provider’s electric system; or
8.2 Are interconnected with Affected
Systems and may have an impact on the
proposed interconnection; and
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.027
34276
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
10.0 A deposit of the equivalent of the
good faith estimated cost of a distribution
system impact study and the one half the
good faith estimated cost of a transmission
system impact study may be required from
the Interconnection Customer.
11.0 Any study fees shall be based on the
Transmission Provider’s actual costs and will
be invoiced to the Interconnection Customer
after the study is completed and delivered
and will include a summary of professional
time.
12.0 The Interconnection Customer must
pay any study costs that exceed the deposit
PO 00000
Frm 00089
Fmt 4701
Sfmt 4725
without interest within 30 calendar days on
receipt of the invoice or resolution of any
dispute. If the deposit exceeds the invoiced
fees, the Transmission Provider shall refund
such excess within 30 calendar days of the
invoice without interest.
IN WITNESS THEREOF, the Parties have
caused this Agreement to be duly executed
by their duly authorized officers or agents on
the day and year first above written.
BILLING CODE 6717–01–U
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.028
8.3 Have a pending higher queued
Interconnection Request to interconnect with
the Transmission Provider’s electric system.
9.0 A distribution system impact study, if
required, shall be completed and the results
transmitted to the Interconnection Customer
within 30 Business Days after this Agreement
is signed by the Parties. A transmission
system impact study, if required, shall be
completed and the results transmitted to the
Interconnection Customer within 45 Business
Days after this Agreement is signed by the
Parties, or in accordance with the
Transmission Provider’s queuing procedures.
34277
VerDate jul<14>2003
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00090
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.029
34278
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
34279
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00091
Fmt 4701
Sfmt 4700
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.030
BILLING CODE 6717–01–C
34280
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Recitals
2.0 The Interconnection Customer elects
and the Transmission Provider shall cause a
facilities study consistent with the standard
Small Generator Interconnection Procedures
to be performed in accordance with the Open
Access Transmission Tariff.
3.0 The scope of the facilities study shall
be subject to data provided in Attachment A
to this Agreement.
4.0 The facilities study shall specify and
estimate the cost of the equipment,
engineering, procurement and construction
work (including overheads) needed to
implement the conclusions of the system
impact study(s). The facilities study shall
also identify (1) the electrical switching
configuration of the equipment, including,
without limitation, transformer, switchgear,
meters, and other station equipment, (2) the
nature and estimated cost of the
Transmission Provider’s Interconnection
Facilities and Upgrades necessary to
accomplish the interconnection, and (3) an
estimate of the time required to complete the
construction and installation of such
facilities.
5.0 The Transmission Provider may
propose to group facilities required for more
than one Interconnection Customer in order
to minimize facilities costs through
economies of scale, but any Interconnection
Customer may require the installation of
facilities required for its own Small
Generating Facility if it is willing to pay the
costs of those facilities.
6.0 A deposit of the good faith estimated
facilities study costs may be required from
the Interconnection Customer.
WHEREAS, the Interconnection Customer
is proposing to develop a Small Generating
Facility or generating capacity addition to an
existing Small Generating Facility consistent
with the Interconnection Request completed
by the Interconnection Customer
onlllll; and
WHEREAS, the Interconnection Customer
desires to interconnect the Small Generating
Facility with the Transmission Provider’s
Transmission System;
WHEREAS, the Transmission Provider has
completed a system impact study and
provided the results of said study to the
Interconnection Customer; and
WHEREAS, the Interconnection Customer
has requested the Transmission Provider to
perform a facilities study to specify and
estimate the cost of the equipment,
engineering, procurement and construction
work needed to implement the conclusions
of the system impact study in accordance
with Good Utility Practice to physically and
electrically connect the Small Generating
Facility with the Transmission Provider’s
Transmission System.
NOW, THEREFORE, in consideration of
and subject to the mutual covenants
contained herein the Parties agreed as
follows:
1.0 When used in this Agreement, with
initial capitalization, the terms specified
shall have the meanings indicated or the
meanings specified in the standard Small
Generator Interconnection Procedures.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00092
Fmt 4701
Sfmt 4700
7.0 In cases where Upgrades are required,
the facilities study must be completed within
45 Business Days of the receipt of this
Agreement. In cases where no Upgrades are
necessary, and the required facilities are
limited to Interconnection Facilities, the
facilities study must be completed within 30
Business Days.
8.0 Once the facilities study is completed,
a facilities study report shall be prepared and
transmitted to the Interconnection Customer.
Barring unusual circumstances, the facilities
study must be completed and the facilities
study report transmitted within 30 Business
Days of the Interconnection Customer’s
agreement to conduct a facilities study.
9.0 Any study fees shall be based on the
Transmission Provider’s actual costs and will
be invoiced to the Interconnection Customer
after the study is completed and delivered
and will include a summary of professional
time.
10.0 The Interconnection Customer must
pay any study costs that exceed the deposit
without interest within 30 calendar days on
receipt of the invoice or resolution of any
dispute. If the deposit exceeds the invoiced
fees, the Transmission Provider shall refund
such excess within 30 calendar days of the
invoice without interest.
IN WITNESS WHEREOF, the Parties have
caused this Agreement to be duly executed
by their duly authorized officers or agents on
the day and year first above written.
BILLING CODE 6717–01–U
E:\FR\FM\13JNR2.SGM
13JNR2
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00093
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
34281
ER13JN05.031
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00094
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.032
34282
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00095
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
34283
ER13JN05.033
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00096
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.034
34284
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
34285
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00097
Fmt 4701
Sfmt 4700
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.035
BILLING CODE 6717–01–C
34286
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Appendix F to the Small Generator
Interconnection Final Rule
Small Generator Interconnection Agreement
(SGIA) (For Generating Facilities No Larger
Than 20 MW)
Table of Contents
Article 1. Scope and Limitations of
Agreement
1.5 Responsibilities of the Parties
1.6 Parallel Operation Obligations
1.7 Metering
1.8 Reactive Power
Article 2. Inspection, Testing, Authorization,
and Right of Access
2.1 Equipment Testing and Inspection
2.2 Authorization Required Prior to
Parallel Operation.
2.3 Right of Access
Article 3. Effective Date, Term, Termination,
and Disconnection
3.1 Effective Date
3.2 Term of Agreement
3.3 Termination
3.4 Temporary Disconnection
3.4.1 Emergency Conditions
3.4.2 Routine Maintenance, Construction,
and Repair
3.4.3 Forced Outages
3.4.4 Adverse Operating Effects
3.4.5 Modification of the Small
Generating Facility
3.4.6 Reconnection
Article 4. Cost Responsibility for
Interconnection Facilities and
Distribution Upgrades
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
4.1 Interconnection Facilities
4.2 Distribution Upgrades
Article 5. Cost Responsibility for Network
Upgrades
5.1 Applicability
5.2 Network Upgrades
5.2.1 Repayment of Amounts Advanced
for Network Upgrades
5.3 Special Provisions for Affected
Systems
5.4 Rights Under Other Agreements
Article 6. Billing, Payment, Milestones, and
Financial Security
6.1 Billing and Payment Procedures and
Final Accounting
6.2 Milestones.
6.3 Financial Security Arrangements
Article 7. Assignment, Liability, Indemnity,
Force Majeure, Consequential Damages,
and Default
7.1 Assignment
7.2 Limitation of Liability
7.3 Indemnity
7.4 Consequential Damages
7.5 Force Majeure.
7.6 Default
Article 8. Insurance
Article 9. Confidentiality
Article 10. Disputes
Article 11. Taxes
Article 12. Miscellaneous
12.1 Governing Law, Regulatory
Authority, and Rules
12.2 Amendment
12.3 No Third-Party Beneficiaries
12.4 Waiver
PO 00000
Frm 00098
Fmt 4701
Sfmt 4700
12.5 Entire Agreement
12.6 Multiple Counterparts.
12.7 No Partnership
12.8 Severability
12.9 Security Arrangements
12.10 Environmental Releases
12.11 Subcontractors
12.12 Reservation of Rights
Article 13. Notices
13.1 General
13.2 Billing and Payment
13.3 Alternative Forms of Notice
13.4 Designated Operating Representative
13.5 Changes to the Notice Information
Article 14. Signatures
Attachment 1—Glossary of Terms
Attachment 2—Description and Costs of the
Small Generating Facility,
Interconnection Facilities, and Metering
Equipment
Attachment 3—One-line Diagram Depicting
the Small Generating Facility,
Interconnection Facilities, Metering
Equipment, and Upgrades
Attachment 4—Milestones
Attachment 5—Additional Operating
Requirements for the Transmission
Provider’s Transmission System and
Affected Systems Needed to Support the
Interconnection Customer’s Needs
Attachment 6—Transmission Provider’s
Description of its Upgrades and Best
Estimate of Upgrade Costs
BILLING CODE 6717–01–U
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
34287
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00099
Fmt 4701
Sfmt 4700
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.036
BILLING CODE 6717–01–C
34288
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
In consideration of the mutual covenants
set forth herein, the Parties agree as follows:
Article 1. Scope and Limitations of
Agreement
1.1 This Agreement shall be used for all
Interconnection Requests submitted under
the Small Generator Interconnection
Procedures (SGIP) except for those submitted
under the 10 kW Inverter Process contained
in SGIP Attachment 5.
1.2 This Agreement governs the terms
and conditions under which the
Interconnection Customer’s Small Generating
Facility will interconnect with, and operate
in parallel with, the Transmission Provider’s
Transmission System.
1.3 This Agreement does not constitute
an agreement to purchase or deliver the
Interconnection Customer’s power. The
purchase or delivery of power and other
services that the Interconnection Customer
may require will be covered under separate
agreements. The Interconnection Customer
will be responsible for separately making all
necessary arrangements (including
scheduling) for delivery of electricity with
the applicable Transmission Provider.
1.4 Nothing in this Agreement is
intended to affect any other agreement
between the Transmission Provider and the
Interconnection Customer.
1.5 Responsibilities of the Parties
1.5.1 The Parties shall perform all
obligations of this Agreement in accordance
with all Applicable Laws and Regulations,
Operating Requirements, and Good Utility
Practice.
1.5.2 The Interconnection Customer shall
construct, interconnect, operate and maintain
its Small Generating Facility and construct,
operate, and maintain its Interconnection
Facilities in accordance with the applicable
manufacturer’s recommended maintenance
schedule, in accordance with this Agreement,
and with Good Utility Practice.
1.5.3 The Transmission Provider shall
construct, operate, and maintain its
Transmission System and Interconnection
Facilities in accordance with this Agreement,
and with Good Utility Practice.
1.5.4 The Interconnection Customer
agrees to construct its facilities or systems in
accordance with applicable specifications
that meet or exceed those provided by the
National Electrical Safety Code, the
American National Standards Institute, IEEE,
Underwriter’s Laboratory, and Operating
Requirements in effect at the time of
construction and other applicable national
and state codes and standards. The
Interconnection Customer agrees to design,
install, maintain, and operate its Small
Generating Facility so as to reasonably
minimize the likelihood of a disturbance
adversely affecting or impairing the system or
equipment of the Transmission Provider or
Affected Systems.
1.5.5 Each Party shall operate, maintain,
repair, and inspect, and shall be fully
responsible for the facilities that it now or
subsequently may own unless otherwise
specified in the Attachments to this
Agreement. Each Party shall be responsible
for the safe installation, maintenance, repair
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
and condition of their respective lines and
appurtenances on their respective sides of
the point of change of ownership. The
Transmission Provider and the
Interconnection Customer, as appropriate,
shall provide Interconnection Facilities that
adequately protect the Transmission
Provider’s Transmission System, personnel,
and other persons from damage and injury.
The allocation of responsibility for the
design, installation, operation, maintenance
and ownership of Interconnection Facilities
shall be delineated in the Attachments to this
Agreement.
1.5.6 The Transmission Provider shall
coordinate with all Affected Systems to
support the interconnection.
1.6 Parallel Operation Obligations
Once the Small Generating Facility has
been authorized to commence parallel
operation, the Interconnection Customer
shall abide by all rules and procedures
pertaining to the parallel operation of the
Small Generating Facility in the applicable
control area, including, but not limited to; 1)
the rules and procedures concerning the
operation of generation set forth in the Tariff
or by the system operator for the
Transmission Provider’s Transmission
System and; 2) the Operating Requirements
set forth in Attachment 5 of this Agreement.
1.7 Metering
The Interconnection Customer shall be
responsible for the Transmission Provider’s
reasonable and necessary cost for the
purchase, installation, operation,
maintenance, testing, repair, and replacement
of metering and data acquisition equipment
specified in Attachments 2 and 3 of this
Agreement. The Interconnection Customer’s
metering (and data acquisition, as required)
equipment shall conform to applicable
industry rules and Operating Requirements.
1.8 Reactive Power
1.8.1 The Interconnection Customer shall
design its Small Generating Facility to
maintain a composite power delivery at
continuous rated power output at the Point
of Interconnection at a power factor within
the range of 0.95 leading to 0.95 lagging,
unless the Transmission Provider has
established different requirements that apply
to all similarly situated generators in the
control area on a comparable basis. The
requirements of this paragraph shall not
apply to wind generators.
1.8.2 The Transmission Provider is
required to pay the Interconnection Customer
for reactive power that the Interconnection
Customer provides or absorbs from the Small
Generating Facility when the Transmission
Provider requests the Interconnection
Customer to operate its Small Generating
Facility outside the range specified in article
1.8.1. In addition, if the Transmission
Provider pays its own or affiliated generators
for reactive power service within the
specified range, it must also pay the
Interconnection Customer.
1.8.3 Payments shall be in accordance
with the Interconnection Customer’s
applicable rate schedule then in effect unless
the provision of such service(s) is subject to
a regional transmission organization or
PO 00000
Frm 00100
Fmt 4701
Sfmt 4700
independent system operator FERC-approved
rate schedule. To the extent that no rate
schedule is in effect at the time the
Interconnection Customer is required to
provide or absorb reactive power under this
Agreement, the Parties agree to expeditiously
file such rate schedule and agree to support
any request for waiver of the Commission’s
prior notice requirement in order to
compensate the Interconnection Customer
from the time service commenced.
1.9 Capitalized terms used herein shall
have the meanings specified in the Glossary
of Terms in Attachment 1 or the body of this
Agreement.
Article 2. Inspection, Testing, Authorization,
and Right of Access
2.1 Equipment Testing and Inspection
2.1.1 The Interconnection Customer shall
test and inspect its Small Generating Facility
and Interconnection Facilities prior to
interconnection. The Interconnection
Customer shall notify the Transmission
Provider of such activities no fewer than five
Business Days (or as may be agreed to by the
Parties) prior to such testing and inspection.
Testing and inspection shall occur on a
Business Day. The Transmission Provider
may, at its own expense, send qualified
personnel to the Small Generating Facility
site to inspect the interconnection and
observe the testing. The Interconnection
Customer shall provide the Transmission
Provider a written test report when such
testing and inspection is completed.
2.1.2 The Transmission Provider shall
provide the Interconnection Customer
written acknowledgment that it has received
the Interconnection Customer’s written test
report. Such written acknowledgment shall
not be deemed to be or construed as any
representation, assurance, guarantee, or
warranty by the Transmission Provider of the
safety, durability, suitability, or reliability of
the Small Generating Facility or any
associated control, protective, and safety
devices owned or controlled by the
Interconnection Customer or the quality of
power produced by the Small Generating
Facility.
2.2 Authorization Required Prior to Parallel
Operation
2.2.1 The Transmission Provider shall
use Reasonable Efforts to list applicable
parallel operation requirements in
Attachment 5 of this Agreement.
Additionally, the Transmission Provider
shall notify the Interconnection Customer of
any changes to these requirements as soon as
they are known. The Transmission Provider
shall make Reasonable Efforts to cooperate
with the Interconnection Customer in
meeting requirements necessary for the
Interconnection Customer to commence
parallel operations by the in-service date.
2.2.2 The Interconnection Customer shall
not operate its Small Generating Facility in
parallel with the Transmission Provider’s
Transmission System without prior written
authorization of the Transmission Provider.
The Transmission Provider will provide such
authorization once the Transmission
Provider receives notification that the
Interconnection Customer has complied with
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
all applicable parallel operation
requirements. Such authorization shall not be
unreasonably withheld, conditioned, or
delayed.
2.3 Right of Access
2.3.1 Upon reasonable notice, the
Transmission Provider may send a qualified
person to the premises of the Interconnection
Customer at or immediately before the time
the Small Generating Facility first produces
energy to inspect the interconnection, and
observe the commissioning of the Small
Generating Facility (including any required
testing), startup, and operation for a period
of up to three Business Days after initial startup of the unit. In addition, the
Interconnection Customer shall notify the
Transmission Provider at least five Business
Days prior to conducting any on-site
verification testing of the Small Generating
Facility.
2.3.2 Following the initial inspection
process described above, at reasonable hours,
and upon reasonable notice, or at any time
without notice in the event of an emergency
or hazardous condition, the Transmission
Provider shall have access to the
Interconnection Customer’s premises for any
reasonable purpose in connection with the
performance of the obligations imposed on it
by this Agreement or if necessary to meet its
legal obligation to provide service to its
customers.
2.3.3 Each Party shall be responsible for
its own costs associated with following this
article.
Article 3. Effective Date, Term, Termination,
and Disconnection
3.1 Effective Date
This Agreement shall become effective
upon execution by the Parties subject to
acceptance by FERC (if applicable), or if filed
unexecuted, upon the date specified by the
FERC. The Transmission Provider shall
promptly file this Agreement with the FERC
upon execution, if required.
3.2 Term of Agreement
This Agreement shall become effective on
the Effective Date and shall remain in effect
for a period of ten years from the Effective
Date or such other longer period as the
Interconnection Customer may request and
shall be automatically renewed for each
successive one-year period thereafter, unless
terminated earlier in accordance with article
3.3 of this Agreement.
3.3 Termination
No termination shall become effective until
the Parties have complied with all
Applicable Laws and Regulations applicable
to such termination, including the filing with
FERC of a notice of termination of this
Agreement (if required), which notice has
been accepted for filing by FERC.
3.3.1 The Interconnection Customer may
terminate this Agreement at any time by
giving the Transmission Provider 20 Business
Days written notice.
3.3.2 Either Party may terminate this
Agreement after Default pursuant to article
7.6.
3.3.3 Upon termination of this
Agreement, the Small Generating Facility
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
will be disconnected from the Transmission
Provider’s Transmission System. The
termination of this Agreement shall not
relieve either Party of its liabilities and
obligations, owed or continuing at the time
of the termination.
3.3.4 This provisions of this article shall
survive termination or expiration of this
Agreement.
3.4 Temporary Disconnection
Temporary disconnection shall continue
only for so long as reasonably necessary
under Good Utility Practice.
3.4.1 Emergency Conditions—
‘‘Emergency Condition’’ shall mean a
condition or situation: (1) That in the
judgment of the Party making the claim is
imminently likely to endanger life or
property; or (2) that, in the case of the
Transmission Provider, is imminently likely
(as determined in a non-discriminatory
manner) to cause a material adverse effect on
the security of, or damage to the
Transmission System, the Transmission
Provider’s Interconnection Facilities or the
Transmission Systems of others to which the
Transmission System is directly connected;
or (3) that, in the case of the Interconnection
Customer, is imminently likely (as
determined in a non-discriminatory manner)
to cause a material adverse effect on the
security of, or damage to, the Small
Generating Facility or the Interconnection
Customer’s Interconnection Facilities. Under
Emergency Conditions, the Transmission
Provider may immediately suspend
interconnection service and temporarily
disconnect the Small Generating Facility.
The Transmission Provider shall notify the
Interconnection Customer promptly when it
becomes aware of an Emergency Condition
that may reasonably be expected to affect the
Interconnection Customer’s operation of the
Small Generating Facility. The
Interconnection Customer shall notify the
Transmission Provider promptly when it
becomes aware of an Emergency Condition
that may reasonably be expected to affect the
Transmission Provider’s Transmission
System or other Affected Systems. To the
extent information is known, the notification
shall describe the Emergency Condition, the
extent of the damage or deficiency, the
expected effect on the operation of both
Parties’ facilities and operations, its
anticipated duration, and the necessary
corrective action.
3.4.2 Routine Maintenance, Construction,
and Repair—The Transmission Provider may
interrupt interconnection service or curtail
the output of the Small Generating Facility
and temporarily disconnect the Small
Generating Facility from the Transmission
Provider’s Transmission System when
necessary for routine maintenance,
construction, and repairs on the
Transmission Provider’s Transmission
System. The Transmission Provider shall
provide the Interconnection Customer with
five Business Days notice prior to such
interruption. The Transmission Provider
shall use Reasonable Efforts to coordinate
such reduction or temporary disconnection
with the Interconnection Customer.
3.4.3 Forced Outages—During any forced
outage, the Transmission Provider may
PO 00000
Frm 00101
Fmt 4701
Sfmt 4700
34289
suspend interconnection service to effect
immediate repairs on the Transmission
Provider’s Transmission System. The
Transmission Provider shall use Reasonable
Efforts to provide the Interconnection
Customer with prior notice. If prior notice is
not given, the Transmission Provider shall,
upon request, provide the Interconnection
Customer written documentation after the
fact explaining the circumstances of the
disconnection.
3.4.4 Adverse Operating Effects—The
Transmission Provider shall notify the
Interconnection Customer as soon as
practicable if, based on Good Utility Practice,
operation of the Small Generating Facility
may cause disruption or deterioration of
service to other customers served from the
same electric system, or if operating the
Small Generating Facility could cause
damage to the Transmission Provider’s
Transmission System or Affected Systems.
Supporting documentation used to reach the
decision to disconnect shall be provided to
the Interconnection Customer upon request.
If, after notice, the Interconnection Customer
fails to remedy the adverse operating effect
within a reasonable time, the Transmission
Provider may disconnect the Small
Generating Facility. The Transmission
Provider shall provide the Interconnection
Customer with five Business Day notice of
such disconnection, unless the provisions of
article 3.4.1 apply.
3.4.5 Modification of the Small
Generating Facility—The Interconnection
Customer must receive written authorization
from the Transmission Provider before
making any change to the Small Generating
Facility that may have a material impact on
the safety or reliability of the Transmission
System. Such authorization shall not be
unreasonably withheld. Modifications shall
be done in accordance with Good Utility
Practice. If the Interconnection Customer
makes such modification without the
Transmission Provider’s prior written
authorization, the latter shall have the right
to temporarily disconnect the Small
Generating Facility.
3.4.6 Reconnection—The Parties shall
cooperate with each other to restore the
Small Generating Facility, Interconnection
Facilities, and the Transmission Provider’s
Transmission System to their normal
operating state as soon as reasonably
practicable following a temporary
disconnection.
Article 4. Cost Responsibility for
Interconnection Facilities and Distribution
Upgrades
4.1 Interconnection Facilities
4.1.1 The Interconnection Customer shall
pay for the cost of the Interconnection
Facilities itemized in Attachment 2 of this
Agreement. The Transmission Provider shall
provide a best estimate cost, including
overheads, for the purchase and construction
of its Interconnection Facilities and provide
a detailed itemization of such costs. Costs
associated with Interconnection Facilities
may be shared with other entities that may
benefit from such facilities by agreement of
the Interconnection Customer, such other
entities, and the Transmission Provider.
E:\FR\FM\13JNR2.SGM
13JNR2
34290
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
4.1.2 The Interconnection Customer shall
be responsible for its share of all reasonable
expenses, including overheads, associated
with (1) owning, operating, maintaining,
repairing, and replacing its own
Interconnection Facilities, and (2) operating,
maintaining, repairing, and replacing the
Transmission Provider’s Interconnection
Facilities.
4.2 Distribution Upgrades
The Transmission Provider shall design,
procure, construct, install, and own the
Distribution Upgrades described in
Attachment 6 of this Agreement. If the
Transmission Provider and the
Interconnection Customer agree, the
Interconnection Customer may construct
Distribution Upgrades that are located on
land owned by the Interconnection
Customer. The actual cost of the Distribution
Upgrades, including overheads, shall be
directly assigned to the Interconnection
Customer.
Article 5. Cost Responsibility for Network
Upgrades
5.1 Applicability
No portion of this article 5 shall apply
unless the interconnection of the Small
Generating Facility requires Network
Upgrades.
5.2 Network Upgrades
The Transmission Provider or the
Transmission Owner shall design, procure,
construct, install, and own the Network
Upgrades described in Attachment 6 of this
Agreement. If the Transmission Provider and
the Interconnection Customer agree, the
Interconnection Customer may construct
Network Upgrades that are located on land
owned by the Interconnection Customer.
Unless the Transmission Provider elects to
pay for Network Upgrades, the actual cost of
the Network Upgrades, including overheads,
shall be borne initially by the
Interconnection Customer.
5.2.1 Repayment of Amounts Advanced
for Network Upgrades
The Interconnection Customer shall be
entitled to a cash repayment, equal to the
total amount paid to the Transmission
Provider and Affected System operator, if
any, for Network Upgrades, including any tax
gross-up or other tax-related payments
associated with the Network Upgrades, and
not otherwise refunded to the
Interconnection Customer, to be paid to the
Interconnection Customer on a dollar-fordollar basis for the non-usage sensitive
portion of transmission charges, as payments
are made under the Transmission Provider’s
Tariff and Affected System’s Tariff for
transmission services with respect to the
Small Generating Facility. Any repayment
shall include interest calculated in
accordance with the methodology set forth in
FERC’s regulations at 18 CFR 35.19a(a)(2)(iii)
from the date of any payment for Network
Upgrades through the date on which the
Interconnection Customer receives a
repayment of such payment pursuant to this
subparagraph. The Interconnection Customer
may assign such repayment rights to any
person.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
5.2.1.1 Notwithstanding the foregoing,
the Interconnection Customer, the
Transmission Provider, and Affected System
operator may adopt any alternative payment
schedule that is mutually agreeable so long
as the Transmission Provider and Affected
System operator take one of the following
actions no later than five years from the
Commercial Operation Date: (1) Return to the
Interconnection Customer any amounts
advanced for Network Upgrades not
previously repaid, or (2) declare in writing
that the Transmission Provider or Affected
System operator will continue to provide
payments to the Interconnection Customer on
a dollar-for-dollar basis for the non-usage
sensitive portion of transmission charges, or
develop an alternative schedule that is
mutually agreeable and provides for the
return of all amounts advanced for Network
Upgrades not previously repaid; however,
full reimbursement shall not extend beyond
twenty (20) years from the commercial
operation date.
5.2.1.2 If the Small Generating Facility
fails to achieve commercial operation, but it
or another generating facility is later
constructed and requires use of the Network
Upgrades, the Transmission Provider and
Affected System operator shall at that time
reimburse the Interconnection Customer for
the amounts advanced for the Network
Upgrades. Before any such reimbursement
can occur, the Interconnection Customer, or
the entity that ultimately constructs the
generating facility, if different, is responsible
for identifying the entity to which
reimbursement must be made.
5.3 Special Provisions for Affected Systems
Unless the Transmission Provider
provides, under this Agreement, for the
repayment of amounts advanced to Affected
System operator for Network Upgrades, the
Interconnection Customer and Affected
System operator shall enter into an
agreement that provides for such repayment.
The agreement shall specify the terms
governing payments to be made by the
Interconnection Customer to Affected System
operator as well as the repayment by Affected
System operator.
5.4 Rights Under Other Agreements
Notwithstanding any other provision of
this Agreement, nothing herein shall be
construed as relinquishing or foreclosing any
rights, including but not limited to firm
transmission rights, capacity rights,
transmission congestion rights, or
transmission credits, that the Interconnection
Customer shall be entitled to, now or in the
future, under any other agreement or tariff as
a result of, or otherwise associated with, the
transmission capacity, if any, created by the
Network Upgrades, including the right to
obtain cash reimbursements or transmission
credits for transmission service that is not
associated with the Small Generating
Facility.
Article 6. Billing, Payment, Milestones, and
Financial Security
6.1 Billing and Payment Procedures and
Final Accounting
6.1.1 The Transmission Provider shall
bill the Interconnection Customer for the
PO 00000
Frm 00102
Fmt 4701
Sfmt 4700
design, engineering, construction, and
procurement costs of Interconnection
Facilities and Upgrades contemplated by this
Agreement on a monthly basis, or as
otherwise agreed by the Parties. The
Interconnection Customer shall pay each bill
within 30 calendar days of receipt, or as
otherwise agreed to by the Parties.
6.1.2 Within three months of completing
the construction and installation of the
Transmission Provider’s Interconnection
Facilities and/or Upgrades described in the
Attachments to this Agreement, the
Transmission Provider shall provide the
Interconnection Customer with a final
accounting report of any difference between
(1) the Interconnection Customer’s cost
responsibility for the actual cost of such
facilities or Upgrades, and (2) the
Interconnection Customer’s previous
aggregate payments to the Transmission
Provider for such facilities or Upgrades. If the
Interconnection Customer’s cost
responsibility exceeds its previous aggregate
payments, the Transmission Provider shall
invoice the Interconnection Customer for the
amount due and the Interconnection
Customer shall make payment to the
Transmission Provider within 30 calendar
days. If the Interconnection Customer’s
previous aggregate payments exceed its cost
responsibility under this Agreement, the
Transmission Provider shall refund to the
Interconnection Customer an amount equal
to the difference within 30 calendar days of
the final accounting report.
6.2 Milestones
The Parties shall agree on milestones for
which each Party is responsible and list them
in Attachment 4 of this Agreement. A Party’s
obligations under this provision may be
extended by agreement. If a Party anticipates
that it will be unable to meet a milestone for
any reason other than a Force Majeure Event,
it shall immediately notify the other Party of
the reason(s) for not meeting the milestone
and (1) propose the earliest reasonable
alternate date by which it can attain this and
future milestones, and (2) requesting
appropriate amendments to Attachment 4.
The Party affected by the failure to meet a
milestone shall not unreasonably withhold
agreement to such an amendment unless it
will suffer significant uncompensated
economic or operational harm from the
delay, (2) attainment of the same milestone
has previously been delayed, or (3) it has
reason to believe that the delay in meeting
the milestone is intentional or unwarranted
notwithstanding the circumstances explained
by the Party proposing the amendment.
6.3 Financial Security Arrangements
At least 20 Business Days prior to the
commencement of the design, procurement,
installation, or construction of a discrete
portion of the Transmission Provider’s
Interconnection Facilities and Upgrades, the
Interconnection Customer shall provide the
Transmission Provider, at the
Interconnection Customer’s option, a
guarantee, a surety bond, letter of credit or
other form of security that is reasonably
acceptable to the Transmission Provider and
is consistent with the Uniform Commercial
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Code of the jurisdiction where the Point of
Interconnection is located. Such security for
payment shall be in an amount sufficient to
cover the costs for constructing, designing,
procuring, and installing the applicable
portion of the Transmission Provider’s
Interconnection Facilities and Upgrades and
shall be reduced on a dollar-for-dollar basis
for payments made to the Transmission
Provider under this Agreement during its
term. In addition:
6.3.1 The guarantee must be made by an
entity that meets the creditworthiness
requirements of the Transmission Provider,
and contain terms and conditions that
guarantee payment of any amount that may
be due from the Interconnection Customer,
up to an agreed-to maximum amount.
6.3.2 The letter of credit or surety bond
must be issued by a financial institution or
insured reasonably acceptable to the
Transmission Provider and must specify a
reasonable expiration date.
Article 7. Assignment, Liability, Indemnity,
Force Majeure, Consequential Damages, and
Default
7.1 Assignment
This Agreement may be assigned by either
Party upon 15 Business Days prior written
notice and opportunity to object by the other
Party; provided that:
7.1.1 Either Party may assign this
Agreement without the consent of the other
Party to any affiliate of the assigning Party
with an equal or greater credit rating and
with the legal authority and operational
ability to satisfy the obligations of the
assigning Party under this Agreement;
7.1.2 The Interconnection Customer shall
have the right to assign this Agreement,
without the consent of the Transmission
Provider, for collateral security purposes to
aid in providing financing for the Small
Generating Facility, provided that the
Interconnection Customer will promptly
notify the Transmission Provider of any such
assignment.
7.1.3 Any attempted assignment that
violates this article is void and ineffective.
Assignment shall not relieve a Party of its
obligations, nor shall a Party’s obligations be
enlarged, in whole or in part, by reason
thereof. An assignee is responsible for
meeting the same financial, credit, and
insurance obligations as the Interconnection
Customer. Where required, consent to
assignment will not be unreasonably
withheld, conditioned or delayed.
7.2 Limitation of Liability
Each Party’s liability to the other Party for
any loss, cost, claim, injury, liability, or
expense, including reasonable attorney’s fees,
relating to or arising from any act or omission
in its performance of this Agreement, shall be
limited to the amount of direct damage
actually incurred. In no event shall either
Party be liable to the other Party for any
indirect, special, consequential, or punitive
damages, except as authorized by this
Agreement.
7.3 Indemnity
7.3.1 This provision protects each Party
from liability incurred to third parties as a
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
result of carrying out the provisions of this
Agreement. Liability under this provision is
exempt from the general limitations on
liability found in article 7.2.
7.3.2 The Parties shall at all times
indemnify, defend, and hold the other Party
harmless from, any and all damages, losses,
claims, including claims and actions relating
to injury to or death of any person or damage
to property, demand, suits, recoveries, costs
and expenses, court costs, attorney fees, and
all other obligations by or to third parties,
arising out of or resulting from the other
Party’s action or failure to meet its
obligations under this Agreement on behalf
of the indemnifying Party, except in cases of
gross negligence or intentional wrongdoing
by the indemnified Party.
7.3.3 If an indemnified person is entitled
to indemnification under this article as a
result of a claim by a third party, and the
indemnifying Party fails, after notice and
reasonable opportunity to proceed under this
article, to assume the defense of such claim,
such indemnified person may at the expense
of the indemnifying Party contest, settle or
consent to the entry of any judgment with
respect to, or pay in full, such claim.
7.3.4 If an indemnifying party is obligated
to indemnify and hold any indemnified
person harmless under this article, the
amount owing to the indemnified person
shall be the amount of such indemnified
person’s actual loss, net of any insurance or
other recovery.
7.3.5 Promptly after receipt by an
indemnified person of any claim or notice of
the commencement of any action or
administrative or legal proceeding or
investigation as to which the indemnity
provided for in this article may apply, the
indemnified person shall notify the
indemnifying party of such fact. Any failure
of or delay in such notification shall not
affect a Party’s indemnification obligation
unless such failure or delay is materially
prejudicial to the indemnifying party.
7.4 Consequential Damages
Other than as expressly provided for in this
Agreement, neither Party shall be liable
under any provision of this Agreement for
any losses, damages, costs or expenses for
any special, indirect, incidental,
consequential, or punitive damages,
including but not limited to loss of profit or
revenue, loss of the use of equipment, cost
of capital, cost of temporary equipment or
services, whether based in whole or in part
in contract, in tort, including negligence,
strict liability, or any other theory of liability;
provided, however, that damages for which
a Party may be liable to the other Party under
another agreement will not be considered to
be special, indirect, incidental, or
consequential damages hereunder.
7.5 Force Majeure
7.5.1 As used in this article, a Force
Majeure Event shall mean ‘‘any act of God,
labor disturbance, act of the public enemy,
war, insurrection, riot, fire, storm or flood,
explosion, breakage or accident to machinery
or equipment, any order, regulation or
restriction imposed by governmental,
military or lawfully established civilian
PO 00000
Frm 00103
Fmt 4701
Sfmt 4700
34291
authorities, or any other cause beyond a
Party’s control. A Force Majeure Event does
not include an act of negligence or
intentional wrongdoing.’’
7.5.2 If a Force Majeure Event prevents a
Party from fulfilling any obligations under
this Agreement, the Party affected by the
Force Majeure Event (Affected Party) shall
promptly notify the other Party, either in
writing or via the telephone, of the existence
of the Force Majeure Event. The notification
must specify in reasonable detail the
circumstances of the Force Majeure Event, its
expected duration, and the steps that the
Affected Party is taking to mitigate the effects
of the event on its performance. The Affected
Party shall keep the other Party informed on
a continuing basis of developments relating
to the Force Majeure Event until the event
ends. The Affected Party will be entitled to
suspend or modify its performance of
obligations under this Agreement (other than
the obligation to make payments) only to the
extent that the effect of the Force Majeure
Event cannot be mitigated by the use of
Reasonable Efforts. The Affected Party will
use Reasonable Efforts to resume its
performance as soon as possible.
7.6 Default
7.6.1 No Default shall exist where such
failure to discharge an obligation (other than
the payment of money) is the result of a
Force Majeure Event as defined in this
Agreement or the result of an act or omission
of the other Party. Upon a Default, the nondefaulting Party shall give written notice of
such Default to the defaulting Party. Except
as provided in article 7.6.2, the defaulting
Party shall have 60 calendar days from
receipt of the Default notice within which to
cure such Default; provided however, if such
Default is not capable of cure within 60
calendar days, the defaulting Party shall
commence such cure within 20 calendar days
after notice and continuously and diligently
complete such cure within six months from
receipt of the Default notice; and, if cured
within such time, the Default specified in
such notice shall cease to exist.
7.6.2 If a Default is not cured as provided
in this article, or if a Default is not capable
of being cured within the period provided for
herein, the non-defaulting Party shall have
the right to terminate this Agreement by
written notice at any time until cure occurs,
and be relieved of any further obligation
hereunder and, whether or not that Party
terminates this Agreement, to recover from
the defaulting Party all amounts due
hereunder, plus all other damages and
remedies to which it is entitled at law or in
equity. The provisions of this article will
survive termination of this Agreement.
Article 8. Insurance
8.1 The Interconnection Customer shall,
at its own expense, maintain in force general
liability insurance without any exclusion for
liabilities related to the interconnection
undertaken pursuant to this Agreement. The
amount of such insurance shall be sufficient
to insure against all reasonably foreseeable
direct liabilities given the size and nature of
the generating equipment being
interconnected, the interconnection itself,
E:\FR\FM\13JNR2.SGM
13JNR2
34292
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
and the characteristics of the system to which
the interconnection is made. The
Interconnection Customer shall obtain
additional insurance only if necessary as a
function of owning and operating a
generating facility. Such insurance shall be
obtained from an insurance provider
authorized to do business in the State where
the interconnection is located. Certification
that such insurance is in effect shall be
provided upon request of the Transmission
Provider, except that the Interconnection
Customer shall show proof of insurance to
the Transmission Provider no later than ten
Business Days prior to the anticipated
commercial operation date. An
Interconnection Customer of sufficient creditworthiness may propose to self-insure for
such liabilities, and such a proposal shall not
be unreasonably rejected.
8.2 The Transmission Provider agrees to
maintain general liability insurance or selfinsurance consistent with the Transmission
Provider’s commercial practice. Such
insurance or self-insurance shall not exclude
coverage for the Transmission Provider’s
liabilities undertaken pursuant to this
Agreement.
8.3 The Parties further agree to notify
each other whenever an accident or incident
occurs resulting in any injuries or damages
that are included within the scope of
coverage of such insurance, whether or not
such coverage is sought.
Article 9. Confidentiality
9.1 Confidential Information shall mean
any confidential and/or proprietary
information provided by one Party to the
other Party that is clearly marked or
otherwise designated ‘‘Confidential.’’ For
purposes of this Agreement all design,
operating specifications, and metering data
provided by the Interconnection Customer
shall be deemed Confidential Information
regardless of whether it is clearly marked or
otherwise designated as such.
9.2 Confidential Information does not
include information previously in the public
domain, required to be publicly submitted or
divulged by Governmental Authorities (after
notice to the other Party and after exhausting
any opportunity to oppose such publication
or release), or necessary to be divulged in an
action to enforce this Agreement. Each Party
receiving Confidential Information shall hold
such information in confidence and shall not
disclose it to any third party nor to the public
without the prior written authorization from
the Party providing that information, except
to fulfill obligations under this Agreement, or
to fulfill legal or regulatory requirements.
9.2.1 Each Party shall employ at least the
same standard of care to protect Confidential
Information obtained from the other Party as
it employs to protect its own Confidential
Information.
9.2.2 Each Party is entitled to equitable
relief, by injunction or otherwise, to enforce
its rights under this provision to prevent the
release of Confidential Information without
bond or proof of damages, and may seek
other remedies available at law or in equity
for breach of this provision.
9.3 Notwithstanding anything in this
article to the contrary, and pursuant to 18
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
CFR 1b.20, if FERC, during the course of an
investigation or otherwise, requests
information from one of the Parties that is
otherwise required to be maintained in
confidence pursuant to this Agreement, the
Party shall provide the requested information
to FERC, within the time provided for in the
request for information. In providing the
information to FERC, the Party may,
consistent with 18 CFR 388.112, request that
the information be treated as confidential and
non-public by FERC and that the information
be withheld from public disclosure. Parties
are prohibited from notifying the other Party
to this Agreement prior to the release of the
Confidential Information to FERC. The Party
shall notify the other Party to this Agreement
when it is notified by FERC that a request to
release Confidential Information has been
received by FERC, at which time either of the
Parties may respond before such information
would be made public, pursuant to 18 CFR
388.112. Requests from a state regulatory
body conducting a confidential investigation
shall be treated in a similar manner if
consistent with the applicable state rules and
regulations.
Article 10. Disputes
10.1 The Parties agree to attempt to
resolve all disputes arising out of the
interconnection process according to the
provisions of this article.
10.2 In the event of a dispute, either Party
shall provide the other Party with a written
Notice of Dispute. Such Notice shall describe
in detail the nature of the dispute.
10.3 If the dispute has not been resolved
within two Business Days after receipt of the
Notice, either Party may contact FERC’s
Dispute Resolution Service (DRS) for
assistance in resolving the dispute.
10.4 The DRS will assist the Parties in
either resolving their dispute or in selecting
an appropriate dispute resolution venue (e.g.,
mediation, settlement judge, early neutral
evaluation, or technical expert) to assist the
Parties in resolving their dispute. DRS can be
reached at 1–877–337–2237 or via the
internet at https://www.ferc.gov/legal/adr.asp.
10.5 Each Party agrees to conduct all
negotiations in good faith and will be
responsible for one-half of any costs paid to
neutral third-parties.
10.6 If neither Party elects to seek
assistance from the DRS, or if the attempted
dispute resolution fails, then either Party
may exercise whatever rights and remedies it
may have in equity or law consistent with the
terms of this Agreement.
Article 11. Taxes
11.1 The Parties agree to follow all
applicable tax laws and regulations,
consistent with FERC policy and Internal
Revenue Service requirements.
11.2 Each Party shall cooperate with the
other to maintain the other Party’s tax status.
Nothing in this Agreement is intended to
adversely affect the Transmission Provider’s
tax exempt status with respect to the
issuance of bonds including, but not limited
to, local furnishing bonds.
PO 00000
Frm 00104
Fmt 4701
Sfmt 4700
Article 12. Miscellaneous
12.1 Governing Law, Regulatory Authority,
and Rules
The validity, interpretation and
enforcement of this Agreement and each of
its provisions shall be governed by the laws
of the state of llll(where the Point of
Interconnection is located), without regard to
its conflicts of law principles. This
Agreement is subject to all Applicable Laws
and Regulations. Each Party expressly
reserves the right to seek changes in, appeal,
or otherwise contest any laws, orders, or
regulations of a Governmental Authority.
12.2 Amendment
The Parties may amend this Agreement by
a written instrument duly executed by both
Parties.
12.3 No Third-Party Beneficiaries
This Agreement is not intended to and
does not create rights, remedies, or benefits
of any character whatsoever in favor of any
persons, corporations, associations, or
entities other than the Parties, and the
obligations herein assumed are solely for the
use and benefit of the Parties, their
successors in interest and where permitted,
their assigns.
12.4 Waiver
12.4.1 The failure of a Party to this
Agreement to insist, on any occasion, upon
strict performance of any provision of this
Agreement will not be considered a waiver
of any obligation, right, or duty of, or
imposed upon, such Party.
12.4.2 Any waiver at any time by either
Party of its rights with respect to this
Agreement shall not be deemed a continuing
waiver or a waiver with respect to any other
failure to comply with any other obligation,
right, or duty of this Agreement. Termination
or default of this Agreement for any reason
by Interconnection Customer shall not
constitute a waiver of the Interconnection
Customer’s legal rights to obtain an
interconnection from the Transmission
Provider. Any waiver of this Agreement
shall, if requested, be provided in writing.
12.5 Entire Agreement
This Agreement, including all
Attachments, constitutes the entire
agreement between the Parties with reference
to the subject matter hereof, and supersedes
all prior and contemporaneous
understandings or agreements, oral or
written, between the Parties with respect to
the subject matter of this Agreement. There
are no other agreements, representations,
warranties, or covenants which constitute
any part of the consideration for, or any
condition to, either Party’s compliance with
its obligations under this Agreement.
12.6 Multiple Counterparts
This Agreement may be executed in two or
more counterparts, each of which is deemed
an original but all constitute one and the
same instrument.
12.7 No Partnership
This Agreement shall not be interpreted or
construed to create an association, joint
E:\FR\FM\13JNR2.SGM
13JNR2
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
venture, agency relationship, or partnership
between the Parties or to impose any
partnership obligation or partnership liability
upon either Party. Neither Party shall have
any right, power or authority to enter into
any agreement or undertaking for, or act on
behalf of, or to act as or be an agent or
representative of, or to otherwise bind, the
other Party.
12.8 Severability
If any provision or portion of this
Agreement shall for any reason be held or
adjudged to be invalid or illegal or
unenforceable by any court of competent
jurisdiction or other Governmental
Authority, (1) such portion or provision shall
be deemed separate and independent, (2) the
Parties shall negotiate in good faith to restore
insofar as practicable the benefits to each
Party that were affected by such ruling, and
(3) the remainder of this Agreement shall
remain in full force and effect.
12.9 Security Arrangements
Infrastructure security of electric system
equipment and operations and control
hardware and software is essential to ensure
day-to-day reliability and operational
security. FERC expects all Transmission
Providers, market participants, and
Interconnection Customers interconnected to
electric systems to comply with the
recommendations offered by the President’s
Critical Infrastructure Protection Board and,
eventually, best practice recommendations
from the electric reliability authority. All
public utilities are expected to meet basic
standards for system infrastructure and
operational security, including physical,
operational, and cyber-security practices.
12.10 Environmental Releases
Each Party shall notify the other Party, first
orally and then in writing, of the release of
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
any hazardous substances, any asbestos or
lead abatement activities, or any type of
remediation activities related to the Small
Generating Facility or the Interconnection
Facilities, each of which may reasonably be
expected to affect the other Party. The
notifying Party shall (1) provide the notice as
soon as practicable, provided such Party
makes a good faith effort to provide the
notice no later than 24 hours after such Party
becomes aware of the occurrence, and (2)
promptly furnish to the other Party copies of
any publicly available reports filed with any
governmental authorities addressing such
events.
12.11 Subcontractors
Nothing in this Agreement shall prevent a
Party from utilizing the services of any
subcontractor as it deems appropriate to
perform its obligations under this Agreement;
provided, however, that each Party shall
require its subcontractors to comply with all
applicable terms and conditions of this
Agreement in providing such services and
each Party shall remain primarily liable to
the other Party for the performance of such
subcontractor.
12.11.1 The creation of any subcontract
relationship shall not relieve the hiring Party
of any of its obligations under this
Agreement. The hiring Party shall be fully
responsible to the other Party for the acts or
omissions of any subcontractor the hiring
Party hires as if no subcontract had been
made; provided, however, that in no event
shall the Transmission Provider be liable for
the actions or inactions of the
Interconnection Customer or its
subcontractors with respect to obligations of
the Interconnection Customer under this
Agreement. Any applicable obligation
imposed by this Agreement upon the hiring
Party shall be equally binding upon, and
PO 00000
Frm 00105
Fmt 4701
Sfmt 4700
34293
shall be construed as having application to,
any subcontractor of such Party.
12.11.2 The obligations under this article
will not be limited in any way by any
limitation of subcontractor’s insurance.
12.12
Reservation of Rights
The Transmission Provider shall have the
right to make a unilateral filing with FERC
to modify this Agreement with respect to any
rates, terms and conditions, charges,
classifications of service, rule or regulation
under section 205 or any other applicable
provision of the Federal Power Act and
FERC’s rules and regulations thereunder, and
the Interconnection Customer shall have the
right to make a unilateral filing with FERC
to modify this Agreement under any
applicable provision of the Federal Power
Act and FERC’s rules and regulations;
provided that each Party shall have the right
to protest any such filing by the other Party
and to participate fully in any proceeding
before FERC in which such modifications
may be considered. Nothing in this
Agreement shall limit the rights of the Parties
or of FERC under sections 205 or 206 of the
Federal Power Act and FERC’s rules and
regulations, except to the extent that the
Parties otherwise agree as provided herein.
Article 13. Notices
13.1
General
Unless otherwise provided in this
Agreement, any written notice, demand, or
request required or authorized in connection
with this Agreement (‘‘Notice’’) shall be
deemed properly given if delivered in
person, delivered by recognized national
currier service, or sent by first class mail,
postage prepaid, to the person specified
below:
BILLING CODE 6717–01–U
E:\FR\FM\13JNR2.SGM
13JNR2
34294
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00106
Fmt 4701
Sfmt 4700
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.037
BILLING CODE 6717–01–C
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
34295
13.2 Billing and Payment
Billings and payments shall be sent to the
addresses set out below:
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
other and not required by this Agreement to
be given in writing may be so given by
telephone, facsimile or e-mail to the
PO 00000
Frm 00107
Fmt 4701
Sfmt 4700
telephone numbers and e-mail addresses set
out below:
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.038
13.3 Alternative Forms of Notice
Any notice or request required or
permitted to be given by either Party to the
13.4
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Designated Operating Representative
The Parties may also designate operating
representatives to conduct the
communications which may be necessary or
convenient for the administration of this
Agreement. This person will also serve as the
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
point of contact with respect to operations
and maintenance of the Party’s facilities.
Article 14. Signatures
BILLING CODE 6717–01–U
13.5 Changes to the Notice Information
Either Party may change this information
by giving five Business Days written notice
prior to the effective date of the change.
PO 00000
Frm 00108
Fmt 4701
Sfmt 4700
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.039
34296
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
their respective duly authorized
representatives.
PO 00000
Frm 00109
Fmt 4701
Sfmt 4700
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.040
IN WITNESS WHEREOF, the Parties have
caused this Agreement to be executed by
34297
34298
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00110
Fmt 4701
Sfmt 4700
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.041
BILLING CODE 6717–01–C
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
Attachment 1—Glossary of Terms
Affected System—An electric system other
than the Transmission Provider’s
Transmission System that may be affected by
the proposed interconnection.
Applicable Laws and Regulations—All
duly promulgated applicable federal, state
and local laws, regulations, rules, ordinances,
codes, decrees, judgments, directives, or
judicial or administrative orders, permits and
other duly authorized actions of any
Governmental Authority.
Business Day—Monday through Friday,
excluding Federal Holidays.
Default—The failure of a breaching Party to
cure its Breach under the Small Generator
Interconnection Agreement.
Distribution System—The Transmission
Provider’s facilities and equipment used to
transmit electricity to ultimate usage points
such as homes and industries directly from
nearby generators or from interchanges with
higher voltage transmission networks which
transport bulk power over longer distances.
The voltage levels at which Distribution
Systems operate differ among areas.
Distribution Upgrades—The additions,
modifications, and upgrades to the
Transmission Provider’s Distribution System
at or beyond the Point of Interconnection to
facilitate interconnection of the Small
Generating Facility and render the
transmission service necessary to effect the
Interconnection Customer’s wholesale sale of
electricity in interstate commerce.
Distribution Upgrades do not include
Interconnection Facilities.
Good Utility Practice—Any of the
practices, methods and acts engaged in or
approved by a significant portion of the
electric industry during the relevant time
period, or any of the practices, methods and
acts which, in the exercise of reasonable
judgment in light of the facts known at the
time the decision was made, could have been
expected to accomplish the desired result at
a reasonable cost consistent with good
business practices, reliability, safety and
expedition. Good Utility Practice is not
intended to be limited to the optimum
practice, method, or act to the exclusion of
all others, but rather to be acceptable
practices, methods, or acts generally accepted
in the region.
Governmental Authority—Any federal,
state, local or other governmental regulatory
or administrative agency, court, commission,
department, board, or other governmental
subdivision, legislature, rulemaking board,
tribunal, or other governmental authority
having jurisdiction over the Parties, their
respective facilities, or the respective services
they provide, and exercising or entitled to
exercise any administrative, executive,
police, or taxing authority or power;
provided, however, that such term does not
include the Interconnection Customer, the
Interconnection Provider, or any Affiliate
thereof.
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
Interconnection Customer—Any entity,
including the Transmission Provider, the
Transmission Owner or any of the affiliates
or subsidiaries of either, that proposes to
interconnect its Small Generating Facility
with the Transmission Provider’s
Transmission System.
Interconnection Facilities—The
Transmission Provider’s Interconnection
Facilities and the Interconnection Customer’s
Interconnection Facilities. Collectively,
Interconnection Facilities include all
facilities and equipment between the Small
Generating Facility and the Point of
Interconnection, including any modification,
additions or upgrades that are necessary to
physically and electrically interconnect the
Small Generating Facility to the
Transmission Provider’s Transmission
System. Interconnection Facilities are sole
use facilities and shall not include
Distribution Upgrades or Network Upgrades.
Interconnection Request—The
Interconnection Customer’s request, in
accordance with the Tariff, to interconnect a
new Small Generating Facility, or to increase
the capacity of, or make a Material
Modification to the operating characteristics
of, an existing Small Generating Facility that
is interconnected with the Transmission
Provider’s Transmission System.
Material Modification—A modification
that has a material impact on the cost or
timing of any Interconnection Request with
a later queue priority date.
Network Upgrades—Additions,
modifications, and upgrades to the
Transmission Provider’s Transmission
System required at or beyond the point at
which the Small Generating Facility
interconnects with the Transmission
Provider’s Transmission System to
accommodate the interconnection of the
Small Generating Facility with the
Transmission Provider’s Transmission
System. Network Upgrades do not include
Distribution Upgrades.
Operating Requirements—Any operating
and technical requirements that may be
applicable due to Regional Transmission
Organization, Independent System Operator,
control area, or the Transmission Provider’s
requirements, including those set forth in the
Small Generator Interconnection Agreement.
Party or Parties—The Transmission
Provider, Transmission Owner,
Interconnection Customer or any
combination of the above.
Point of Interconnection—The point where
the Interconnection Facilities connect with
the Transmission Provider’s Transmission
System.
Reasonable Efforts—With respect to an
action required to be attempted or taken by
a Party under the Small Generator
Interconnection Agreement, efforts that are
timely and consistent with Good Utility
Practice and are otherwise substantially
PO 00000
Frm 00111
Fmt 4701
Sfmt 4700
34299
equivalent to those a Party would use to
protect its own interests.
Small Generating Facility—The
Interconnection Customer’s device for the
production of electricity identified in the
Interconnection Request, but shall not
include the Interconnection Customer’s
Interconnection Facilities.
Tariff—The Transmission Provider or
Affected System’s Tariff through which open
access transmission service and
Interconnection Service are offered, as filed
with the FERC, and as amended or
supplemented from time to time, or any
successor tariff.
Transmission Owner—The entity that
owns, leases or otherwise possesses an
interest in the portion of the Transmission
System at the Point of Interconnection and
may be a Party to the Small Generator
Interconnection Agreement to the extent
necessary.
Transmission Provider—The public utility
(or its designated agent) that owns, controls,
or operates transmission or distribution
facilities used for the transmission of
electricity in interstate commerce and
provides transmission service under the
Tariff. The term Transmission Provider
should be read to include the Transmission
Owner when the Transmission Owner is
separate from the Transmission Provider.
Transmission System—The facilities
owned, controlled or operated by the
Transmission Provider or the Transmission
Owner that are used to provide transmission
service under the Tariff.
Upgrades—The required additions and
modifications to the Transmission Provider’s
Transmission System at or beyond the Point
of Interconnection. Upgrades may be
Network Upgrades or Distribution Upgrades.
Upgrades do not include Interconnection
Facilities.
Attachment 2—Description and Costs of the
Small Generating Facility, Interconnection
Facilities, and Metering Equipment
Equipment, including the Small Generating
Facility, Interconnection Facilities, and
metering equipment shall be itemized and
identified as being owned by the
Interconnection Customer, the Transmission
Provider, or the Transmission Owner. The
Transmission Provider will provide a best
estimate itemized cost, including overheads,
of its Interconnection Facilities and metering
equipment, and a best estimate itemized cost
of the annual operation and maintenance
expenses associated with its Interconnection
Facilities and metering equipment.
BILLING CODE 6717–01–U
Attachment 3—One-Line Diagram Depicting
the Small Generating Facility,
Interconnection Facilities, Metering
Equipment, and Upgrades
E:\FR\FM\13JNR2.SGM
13JNR2
VerDate jul<14>2003
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
21:44 Jun 10, 2005
Jkt 205001
PO 00000
Frm 00112
Fmt 4701
Sfmt 4725
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.042
34300
Federal Register / Vol. 70, No. 112 / Monday, June 13, 2005 / Rules and Regulations
The Transmission Provider shall also
provide requirements that must be met by the
Interconnection Customer prior to initiating
VerDate jul<14>2003
21:44 Jun 10, 2005
Jkt 205001
parallel operation with the Transmission
Provider’s Transmission System.
Attachment 6—Transmission Provider’s
Description of Its Upgrades and Best
Estimate of Upgrade Costs
The Transmission Provider shall describe
Upgrades and provide an itemized best
estimate of the cost, including overheads, of
PO 00000
Frm 00113
Fmt 4701
Sfmt 4700
the Upgrades and annual operation and
maintenance expenses associated with such
Upgrades. The Transmission Provider shall
functionalize Upgrade costs and annual
expenses as either transmission or
distribution related.
[FR Doc. 05–11307 Filed 6–10–05; 8:45 am]
BILLING CODE 6717–01–C
E:\FR\FM\13JNR2.SGM
13JNR2
ER13JN05.043
Attachment 5—Additional Operating
Requirements for the Transmission
Provider’s Transmission System and
Affected Systems Needed To Support the
Interconnection Customer’s Needs
34301
Agencies
[Federal Register Volume 70, Number 112 (Monday, June 13, 2005)]
[Rules and Regulations]
[Pages 34190-34301]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 05-11307]
[[Page 34189]]
-----------------------------------------------------------------------
Part II
Department of Energy
-----------------------------------------------------------------------
Federal Energy Regulatory Commission
-----------------------------------------------------------------------
18 CFR Part 35
Standardization of Small Generator Interconnection Agreements and
Procedures; Final Rule
Federal Register / Vol. 70 , No. 112 / Monday, June 13, 2005 / Rules
and Regulations
[[Page 34190]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
18 CFR Part 35
[Docket No. RM02-12-000; Order No. 2006; 111 FERC 61,220]
Standardization of Small Generator Interconnection Agreements and
Procedures
Issued: May 12, 2005
AGENCY: Federal Energy Regulatory Commission.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: The Federal Energy Regulatory Commission (Commission) is
amending its regulations under the Federal Power Act to require public
utilities that own, control, or operate facilities for transmitting
electric energy in interstate commerce to amend their open access
transmission tariffs to include standard generator interconnection
procedures and an agreement that the Commission is adopting in this
order and to provide interconnection service to devices used for the
production of electricity having a capacity of no more than 20
megawatts. A non-public utility that seeks voluntary compliance with
the reciprocity condition of an open access transmission tariff may
satisfy this condition by adopting these procedures and agreement.
DATES: Effective Date: This Final Rule will become effective August 12,
2005.
FOR FURTHER INFORMATION CONTACT:
Kumar Agarwal (Technical Information), Office of Market, Tariffs
and Rates, Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426. (202) 502-8923.
Bruce Poole (Technical Information), Office of Market, Tariffs and
Rates, Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426. (202) 502-8468.
Kirk Randall (Technical Information), Office of Market, Tariffs and
Rates, Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426. (202) 502-8092.
Patrick Rooney (Technical Information), Office of Market, Tariffs
and Rates, Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426. (202) 502-6205.
Abraham Silverman (Legal Information), Office of the General
Counsel, Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426. (202) 502-6444.
SUPPLEMENTARY INFORMATION:
Before Commissioners: Pat Wood, III, Chairman; Nora Mead Brownell,
Joseph T. Kelliher, and Suedeen G. Kelly.
I. Introduction
1. This Final Rule requires all public utilities \1\ to adopt
standard rules for interconnecting new sources of electricity no larger
than 20 megawatts (MW). It continues the process begun in Order No.
2003 of standardizing the terms and conditions of interconnection
service for Interconnection Customers of all sizes.\2\ It will reduce
interconnection time and costs for Interconnection Customers and
Transmission Providers,\3\ preserve reliability, increase energy
supply, lower wholesale prices for customers by increasing the number
and types of new generation that will compete in the wholesale
electricity market, facilitate development of non-polluting alternative
energy sources, and help remedy undue discrimination, as sections 205
and 206 of the FPA require.\4\ Public utilities must amend \5\ their
open access transmission tariffs (OATTs) to include a Small Generator
Interconnection Procedures document (SGIP--Appendix E to this Preamble)
and a Small Generator Interconnection Agreement (SGIA--Appendix F to
this Preamble).
---------------------------------------------------------------------------
\1\ For purposes of this Final Rule, a public utility is a
utility that owns, controls, or operates facilities used for
transmitting electric energy in interstate commerce, as defined by
the Federal Power Act (FPA). 16 U.S.C. 824(e) (2000). A non-public
utility that seeks voluntary compliance with the reciprocity
condition of an open access transmission tariff may satisfy that
condition by adopting these procedures and agreement.
\2\ Standardization of Generator Interconnection Agreements and
Procedures, Order No. 2003, 68 FR 49845 (Aug. 19, 2003), FERC Stats.
& Regs. ] 31,146 (2003) (Order No. 2003), order on reh'g, Order No.
2003-A, 69 FR 15932 (Mar. 26, 2004), FERC Stats. & Regs. ] 31,160
(2004) (Order No. 2003-A), order on reh'g, Order No. 2003-B, 70 FR
265 (Jan. 4, 2005), FERC Stats. & Regs. ] 31,171 (2005), reh'g
pending (Order No. 2003-B). See also Notice Clarifying Compliance
Procedures, 106 FERC ] 61,009 (2004). We refer to the large
generator interconnection rulemaking as Order No. 2003 throughout
this document. The Order No. 2003 Large Generator Interconnection
Agreement and Large Generator Interconnection Procedures, as amended
by Order Nos. 2003-A and 2003-B, are referred to in this Final Rule
as the LGIA and the LGIP, respectively.
\3\ Capitalized terms used in this Final Rule have the meanings
specified in the Glossaries of Terms or the text of the Small
Generator Interconnection Procedures (SGIP) or the Small Generator
Interconnection Agreement (SGIA). Small Generating Facility means
the device for which the Interconnection Customer has requested
interconnection. The owner of the Small Generating Facility is the
Interconnection Customer. The utility entity with which the Small
Generating Facility is interconnecting is the Transmission Provider.
A Small Generating Facility is a device used for the production of
electricity having a capacity of no more than 20 MW. The
interconnection process formally begins with the Interconnection
Customer submitting an application for interconnection, called an
Interconnection Request, to the Transmission Provider.
We are omitting from the SGIP and SGIA glossaries terms that are
defined through their use in the documents themselves or are in such
common use in the industry that a definition is unnecessary. Many
terms that were capitalized in the Small Generator Interconnection
Notice of Proposed Rulemaking are therefore not capitalized in this
Preamble, SGIP, and SGIA.
The documents put forward in the Small Generator Interconnection
NOPR are called the ``Proposed SGIP'' and the ``Proposed SGIA'' in
this Preamble. The documents that are being adopted in this Final
Rule for inclusion in a Transmission Provider's OATT are called
simply the SGIP and SGIA. Provisions of the SGIP are referred to as
``sections'' and provisions of the SGIA are referred to as
``articles.''
\4\ 16 U.S.C. 824d and 824e (2000).
\5\ Compliance procedures are discussed in Part II.I, below.
---------------------------------------------------------------------------
2. The SGIP contains the technical procedures the Interconnection
Customer and Transmission Provider (the Parties) must follow once the
Interconnection Customer requests interconnection of its Small
Generating Facility. It provides three ways to evaluate the
Interconnection Request. They are the default Study Process that could
be used by any Small Generating Facility, and two procedures that use
technical screens to evaluate proposed interconnections: (1) The Fast
Track Process for a certified Small Generating Facility no larger than
2 MW \6\ and (2) the 10 kW Inverter Process for a certified inverter-
based Small Generating Facility no larger than 10 kW.\7\ All three are
designed to ensure that the proposed interconnection will not endanger
the safety and reliability of the Transmission Provider's Transmission
System.
---------------------------------------------------------------------------
\6\ A Small Generating Facility equipment package is considered
certified if it has been submitted, tested, and listed by a
nationally recognized testing and certification laboratory. The
Small Generator Interconnection NOPR used the term ``precertified''
to describe such a facility. We adopt in this Final Rule the term
``certified'' to be consistent with industry usage. To avoid further
confusion, we also use ``certified'' when describing the Small
Generator Interconnection NOPR. See the SGIP, especially Attachments
3 and 4.
\7\ An inverter is a device that converts the direct current
voltage and current of a DC generator to alternating voltage and
current. For example, the output of a solar panel is direct current.
The solar panel's output must be converted by an inverter to
alternating current before it can be interconnected with a utility's
alternating current electric system.
---------------------------------------------------------------------------
3. The SGIA contains contractual provisions appropriate for the
interconnection of a Small Generating Facility, including provisions
for the payment for modifications made to the Transmission Provider's
Transmission System to accommodate the interconnection. The SGIA is
signed by the Parties after they have successfully completed the
evaluation of a proposed interconnection under the SGIP Study Process
or Fast Track Process. The SGIA
[[Page 34191]]
does not apply to requests to interconnect submitted under the 10 kW
Inverter Process, however, which uses a simplified all-in-one
application form/procedures/terms and conditions document that is
included in SGIP Attachment 5.
4. We conclude that general consistency between the Commission's
interconnection procedures document and interconnection agreement
adopted in this Final Rule and those of the states will be helpful to
removing roadblocks to the interconnection of Small Generating
Facilities. To a large extent, this Final Rule harmonizes state and
federal practices by adopting many of the best practices
interconnection rules recommended by the National Association of
Regulatory Utility Commissioners (NARUC). By doing so, we hope to
minimize the federal-state division and promote consistent, nationwide
interconnection rules. We hope that states that do not currently have
interconnection rules for small generators will look to the documents
presented in this Final Rule and NARUC as guides for their own. In
particular, the ``Fast Track Process'' and the ``10 kW Inverter
Process'' should go a long way towards harmonizing state-federal
interconnection practices.
5. Finally, the application of this Final Rule is the same as with
Order No. 2003 for Large Generating Facilities. Specifically, this
Final Rule applies only to interconnections with facilities that are
already subject to the Transmission Provider's OATT at the time the
Interconnection Request is made.
6. The SGIP and SGIA include separate definitions for
``Transmission System'' and ``Distribution System'' to account for the
distinct engineering and cost allocation implications of an
interconnection with a Distribution System. The SGIP and SGIA, like
Order No. 2003, define ``Transmission System'' as ``[t]he facilities
owned, controlled or operated by the Transmission Provider or the
Transmission Owner that are used to provide transmission service under
the Tariff.'' Any interconnection with a Transmission System (under an
OATT) by a Small Generating Facility is subject to this Final Rule.
7. The SGIP and the SGIA, like Order No. 2003, also use the term
``Distribution System.'' ``Distribution System'' is defined as ``[t]he
Transmission Provider's facilities and equipment used to transmit
electricity to ultimate usage points such as homes and industries
directly from nearby generators or from interchanges with higher
voltage transmission networks which transport bulk power over longer
distances. The voltage levels at which Distribution Systems operate
differ among areas.'' If a Small Generating Facility proposes to
interconnect with a portion of the Distribution System subject to an
OATT for the purpose of making wholesale sales, then this Final Rule
would apply.\8\ However, an interconnection to a portion of a
Distribution System that is not already subject to an OATT would not be
subject to this Final Rule.
---------------------------------------------------------------------------
\8\ See Detroit Edison v. FERC, 334 F.3d 48 (DC Cir. 2003)
(Detroit Edison). There, the court explained that:
When a local distribution facility is used to delivery [sic]
energy to an unbundled retail customer, FERC lacks any statutory
authority, and the state has jurisdiction over that transaction. By
contrast, when a local distribution facility is used in a wholesale
transaction, FERC has jurisdiction over that transaction pursuant to
its wholesale jurisdiction under FPA Section 201(b)(1). In sum, FERC
has jurisdiction over all interstate transmission service and over
all wholesale service, but FERC has no jurisdiction over unbundled
retail distribution service--i.e., unbundled retail service over
local distribution facilities.
Id. at 51 (citations omitted).
---------------------------------------------------------------------------
8. ``Distribution'' is a vague term, usually used to refer to non-
networked, often lower-voltage facilities, that carry power in one
direction. Commission-jurisdictional facilities with these
characteristics are referred to as ``Distribution Systems subject to an
OATT'' throughout this Final Rule. This Final Rule's use of the term
``Distribution System'' has nothing to do with whether the facility is
under this Commission's jurisdiction; some ``distribution'' facilities
are under our jurisdiction and others are ``local distribution
facilities'' subject to state jurisdiction.\9\ This Final Rule does not
violate the FPA section 201(b)(1) provision that the Commission does
not have jurisdiction over local distribution facilities ``except as
specifically provided * * *.'' \10\ This is because the Final Rule
applies only to interconnections to facilities that are already subject
to a jurisdictional OATT at the time the interconnection request is
made and that will be used for purposes of jurisdictional wholesale
sales. Because of the limited applicability of this Final Rule, and
because the majority of small generators interconnect with facilities
that are not subject to an OATT, this Final Rule will not apply to most
small generator interconnections. Nonetheless, our hope is that states
may find this rule helpful in formulating their own interconnection
rules.
---------------------------------------------------------------------------
\9\ See Detroit Edison, 334 F.3d at 51. (``For our purposes, the
most important result of these jurisdictional determinations is that
customers can take any FERC-jurisdictional service under a utility's
open access tariff, which the utility is required to file with FERC.
Customers must take non FERC-jurisdictional service, such as
unbundled retail distribution, under a state tariff.'')
\10\ 16 U.S.C. 824 (2000).
---------------------------------------------------------------------------
A. Background
9. This Final Rule responds to business and technology changes in
the electric industry. Where the electric industry was once primarily
the domain of vertically integrated utilities generating power at large
centralized plants, advances in technology have created a burgeoning
market for small power plants that may offer economic, reliability, or
environmental benefits.
10. With these developments in mind, the Commission continues in
this rulemaking to work to encourage fully competitive bulk power
markets. The effort took its first significant step with Order No.
888,\11\ which required public utilities to provide other entities
comparable access to their Transmission Systems. The effort continued
with Order No. 2000,\12\ which began the process of developing Regional
Transmission Organizations (RTOs). Most recently, the Commission
established a standard Large Generator Interconnection Procedures
document (LGIP) and a standard Large Generator Interconnection
Agreement (LGIA) for generating facilities larger than 20 MW.\13\
---------------------------------------------------------------------------
\11\ Promoting Wholesale Competition Through Open Access Non-
Discriminatory Transmission Services by Public Utilities: Recovery
of Stranded Costs by Public Utilities and Transmitting Utilities,
Order No. 888, 61 FR 21540 (May 10, 1996), FERC Stats. & Regs. ]
31,036 (1996), order on reh'g, Order No. 888-A, 62 FR 12274 (Mar.
14, 1997), FERC Stats. & Regs. ] 31,048 (1997), order on reh'g,
Order No. 888-B, 81 FERC ] 61,248 (1997), order on reh'g, Order No.
888-C, 82 FERC ] 61,046 (1998), aff'd in part sub nom. Transmission
Access Policy Study Group v. FERC, 225 F.3d 667 (DC Cir. 2000),
aff'd sub nom. New York v. FERC, 535 U.S. 1 (2002) (TAPS v. FERC).
\12\ Regional Transmission Organizations, Order No. 2000, 65 FR
810 (Jan. 6, 2000), FERC Stats. & Regs. ] 31,089 (1999), order on
reh'g, Order No. 2000-A, 65 FR 12088 (Mar. 8, 2000), FERC Stats. &
Regs. ] 31,092 (2000), aff'd sub nom. Public Util. Dist. No. 1 v.
FERC, 272 F.3d 607 (DC Cir. 2001).
\13\ See Order No. 2003 passim.
---------------------------------------------------------------------------
11. The Commission, pursuant to its responsibility under sections
205 and 206 of the FPA to remedy undue discrimination, is requiring all
public utilities that own, control, or operate facilities for
transmitting electric energy in interstate commerce to append to their
OATTs the SGIP and SGIA we are adopting in this Final Rule. These
documents provide just and reasonable terms and conditions of
interconnection service. They also strike a reasonable balance between
the competing goals of uniformity and flexibility while ensuring safety
and reliability are protected.
[[Page 34192]]
B. Need for a Standard Generator Interconnection Procedures and
Agreement
12. In fulfilling its responsibilities under sections 205 and 206
of the FPA, the Commission is required to remedy undue discrimination.
The Commission must also ensure that the rates, contracts, and
practices affecting jurisdictional transmission service do not reflect
an undue preference or advantage for Transmission Providers and their
affiliates and are just and reasonable. The Commission's regulatory
authority under the FPA ``clearly carries with it the responsibility to
consider, in appropriate circumstances, the anticompetitive effects of
regulated aspects of interstate utility operations* * *.'' \14\
---------------------------------------------------------------------------
\14\ Gulf States Utils. Co. v. FPC, 411 U.S. 747, 758-59 (1973);
see City of Huntingburg v. FPC, 498 F.2d 778, 783-84 (DC Cir. 1974)
(noting the Commission's duty to consider the potential
anticompetitive effects of a proposed interconnection agreement).
---------------------------------------------------------------------------
13. The record underlying Order No. 888 showed that public
utilities owning or controlling jurisdictional transmission facilities
had the incentive to engage in, and had engaged in, unduly
discriminatory transmission practices.\15\ The Commission in Order No.
888 thoroughly discussed the legislative history and case law involving
sections 205 and 206, concluded that it has the authority and
responsibility to remedy the undue discrimination it found by requiring
open access, and decided to do so through a rulemaking on a generic,
industry-wide basis.\16\ The Supreme Court affirmed the Commission's
decision to exercise this authority by requiring non-discriminatory
(comparable) open access as a remedy for undue discrimination.\17\
However, Order No. 888 did not specifically address interconnection
service.\18\
---------------------------------------------------------------------------
\15\ Order No. 888 at 31,679-84; Order No. 888-A at 30,209-10.
\16\ Order No. 888 at 31,668-73, 31,676-79; Order No. 888-A at
30,201-12; TAPS v. FERC at 687-88.
\17\ New York v. FERC, 535 U.S. 1 (2002).
\18\ Order No. 888-A, FERC Stats. & Regs ] 31,048 at 30,230-31.
---------------------------------------------------------------------------
14. In Tennessee Power,\19\ the Commission clarified that
interconnection is a critical component of open access transmission
service and thus is subject to the requirement that utilities offer
comparable service under the OATT. The Commission encouraged, but did
not require, each Transmission Provider to revise its OATT to include
interconnection procedures, including a standard interconnection
agreement and specific criteria, procedures, milestones, and timelines
for evaluating applications for interconnection.\20\
---------------------------------------------------------------------------
\19\ Tennessee Power Co. (Tennessee Power), 90 FERC ] 61,238 at
61,761 (2000), reh'g denied, 91 FERC ] 61,271 (2000).
\20\ See, e.g., Commonwealth Edison Co., 91 FERC ] 61,083
(2000).
---------------------------------------------------------------------------
15. As discussed in Order No. 2003, interconnection is a critical
component of transmission service, and having a standard
interconnection procedures and a standard agreement applicable to Small
Generating Facilities will (1) limit opportunities for transmitting
utilities to favor their own generation, (2) remove unfair impediments
to market entry for small generators by reducing interconnection costs
and time, and (3) encourage investment in generation and transmission
infrastructure, where needed.\21\ We expect the SGIP and SGIA adopted
here will resolve most disputes, minimize opportunities for undue
discrimination, foster increased development of economic Small
Generating Facilities, and protect system reliability.
---------------------------------------------------------------------------
\21\ Order No. 2003 at P 10.
---------------------------------------------------------------------------
C. The Large and Small Generator Interconnection Rulemaking Proceedings
16. In the Advance Notice of Proposed Rulemaking (ANOPR) issued in
Docket No. RM02-1-000, the Commission initiated a collaborative process
where members of the public, electric industry participants, and
federal and state agencies (collectively, stakeholders) were invited to
draft proposed generator interconnection procedures and a generator
interconnection agreement.\22\ The stakeholders filed their consensus
documents in January 2002. The Commission then issued a Notice of
Proposed Rulemaking (Large Generator Interconnection NOPR) \23\
proposing standard interconnection procedures and a standard
interconnection agreement that generally followed the consensus
documents. The Large Generator Interconnection NOPR also proposed
solutions to issues left unresolved in the consensus documents.
---------------------------------------------------------------------------
\22\ Standardizing Generator Interconnection Agreements and
Procedures, Advance Notice of Proposed Rulemaking, 66 FR 55140 (Nov.
1, 2001), FERC Stats. & Regs. ] 35,540 (2002).
\23\ Standardization of Generator Interconnection Agreements and
Procedures, Notice of Proposed Rulemaking, 67 FR 22250 (May 2,
2002), FERC Stats. & Regs. ] 32,560 (2002).
---------------------------------------------------------------------------
17. Although the Large Generator Interconnection NOPR provided
special treatment for Small Generating Facilities, some commenters
urged the Commission to initiate a separate proceeding to develop
standard interconnection procedures and agreements that addressed the
unique concerns of Small Generating Facilities.\24\ They proposed one
set of simplified interconnection rules for Small Generating Facilities
no larger than 2 MW, and another for facilities larger than 2 MW but no
larger than 20 MW. Persuaded that different procedures and agreements
were indeed needed, the Commission severed Small Generating Facilities
from the Large Generator Interconnection proceeding and issued a Small
Generator Interconnection Advance Notice of Proposed Rulemaking (ANOPR)
in August 2002.\25\ The Small Generator Interconnection ANOPR proposed
two SGIPs and two SGIAs (ANOPR SGIPs and SGIAs) using 2 MW as a
breakpoint. It encouraged stakeholders to pursue consensus on the ANOPR
SGIPs and SGIAs. To that end, the Commission convened a series of
public meetings designed to enable them to discuss and reach as much
consensus as possible.
---------------------------------------------------------------------------
\24\ Those commenters included the Solar Energy Industries
Association, the U.S. Fuel Cell Council, the American Solar Energy
Society, the U.S. Combined Heat and Power Association, the
International District Energy Association, and the American Wind
Energy Association.
\25\ Standardization of Small Generator Interconnection
Agreements and Procedures, Advance Notice of Proposed Rulemaking, 67
FR 54749 (Aug. 26, 2002), FERC Stats. & Regs. ] 35,544 (2002).
---------------------------------------------------------------------------
18. The negotiating parties, who we refer to collectively as Joint
Commenters, then filed SGIPs and SGIAs (Joint Commenters' SGIPs and
SGIAs) with the Commission.\26\ While Joint Commenters reached
consensus on some issues, many remained unresolved. Joint Commenters'
SGIPs included two procedures for evaluating whether a proposed Small
Generating Facility could be interconnected safely and without
degrading reliability. The first was a standard Study Process that
[[Page 34193]]
used a scoping meeting and three technical studies to evaluate a
proposed interconnection. The second was a streamlined procedure that
used technical screens to identify those proposed interconnections that
clearly would not jeopardize the safety and reliability of the
Transmission Provider's electric system. Public comments on the Small
Generator Interconnection ANOPR were filed shortly thereafter.
---------------------------------------------------------------------------
\26\ This group refers to itself as the Coalition. However, in
this Final Rule we shall refer to the group as ``Joint Commenters''
to distinguish it from the similarly named Small Generator
Coalition. With the exception of these early references to Joint
Commenters' comments submitted in response to the ANOPR, all
references in the remainder of this Preamble to Joint Commenters are
to its supplemental comments. Joint Commenters did not file initial
comments in response to the Small Generator Interconnection NOPR,
only supplemental comments. Joint Commenters is a diverse group of
stakeholders that includes:
Over 25 small generator trade groups, promoters, and
equipment manufacturers, who refer to themselves collectively as the
``Small Generator Coalition,''
State regulatory agencies represented by the National
Association of Regulatory Utility Commissioners,
American Public Power Association (which did not
participate in the filing of Joint Commenters' supplemental
comments), and
Transmission Providers represented by Edison Electric
Institute (EEI) and National Rural Electric Cooperative Association
(NRECA)
A list of commenter acronyms may be found in Appendix A.
---------------------------------------------------------------------------
19. In July 2003, the Commission issued Order No. 2003, which
established standard procedures and an interconnection agreement for
the interconnection of large generators and explained the Commission's
jurisdiction over interconnections. The Commission simultaneously
issued the Small Generator Interconnection NOPR.\27\ Certain provisions
in the Large Generator Interconnection Final Rule as well as Joint
Commenters' SGIPs/SGIAs influenced the Small Generator Interconnection
NOPR.\28\ The Commission asked commenters to address whether Small
Generating Facilities should be treated differently from Large
Generating Facilities under the LGIP and LGIA adopted in Order No.
2003.
---------------------------------------------------------------------------
\27\ Standardization of Small Generator Interconnection
Agreements and Procedures, Notice of Proposed Rulemaking, 60 FR
49974 (Aug. 19, 2003), FERC Stats. & Regs. ] 32,572 (2003) (Small
Generator Interconnection NOPR).
\28\ See, e.g., Proposed SGIA articles 4.1, 5.1.2, 5.1.2.1, 5.2,
6.1-6.9, 6.12-6.20, 7, and 8.
---------------------------------------------------------------------------
20. Sixty-five entities submitted initial comments in response to
the Small Generator Interconnection NOPR. The comments generally
support the Commission's effort to remove barriers to the development
of Small Generating Facilities. Following the issuance of the Small
Generator Interconnection NOPR and the initial comment due date, NARUC
in October 2003 updated its own interconnection procedures and
agreement, referred to here as the NARUC Model. NARUC stated that the
NARUC Model is based on the best practices of the state regulatory
agencies that have interconnection procedures for small generators.
NARUC encouraged state regulators to use the NARUC Model as a basis for
developing their interconnection procedures and suggested that the
Commission's documents reflect these ``best practices.'' On July 7,
2004, the Commission staff added to the record in this proceeding the
latest version of the NARUC Model.\29\ A few commenters favor
terminating this proceeding or, in the alternative, adopting the NARUC
Model.
---------------------------------------------------------------------------
\29\ NARUC members had participated in the ANOPR discussions
fostered by the Commission; there was much similarity between the
provisions of the NARUC Model and the Small Generator
Interconnection NOPR.
---------------------------------------------------------------------------
21. The Commission then issued a Notice of Request for Supplemental
Comments, observing that the small generator industry had continued to
evolve since the Commission first received comments in this
proceeding.\30\ In the notice, the Commission observed that several
states had recently adopted new guidelines for small generator
interconnections, and that the stakeholders who participated in the
Commission's ANOPR process were continuing to work toward resolving
various SGIP and SGIA issues. The Commission invited joint supplemental
comments describing new consensus positions but discouraged
resubmissions of prior positions.
---------------------------------------------------------------------------
\30\ See Notice of Request for Supplemental Comments, 69 FR
51024 (Aug. 17, 2004). The Commission then granted two extensions of
time at the request of Joint Commenters. See Notices issued on
September 30, 2004 and November 30, 2004 in Docket No. RM02-12-000.
---------------------------------------------------------------------------
22. Joint Commenters, which as noted above represents a diverse
group of small generator interests, Transmission Providers, and state
regulators who participated in the ANOPR process, was the only group to
file a consensus position. Some Joint Commenters--Small Generator
Coalition, NRECA, and NARUC--filed their own supplemental comments as
well. Ten other entities (mostly state regulatory commissions \31\)
submitted supplemental comments.\32\
---------------------------------------------------------------------------
\31\ CT DPUC, Minnesota PUC, and Massachusetts DTE submitted
copies of their recently enacted small generator interconnection
rules.
\32\ The supplemental commenters are listed in Appendix A.
---------------------------------------------------------------------------
23. In its supplemental comments, Joint Commenters endorsed a
single SGIP and single SGIA for Small Generating Facilities no larger
than 20 MW. Joint Commenters recommended several revised provisions in
areas where they had not been able to reach consensus during the ANOPR
process. These included dispute resolution, confidentiality, insurance,
equipment certification, and technical screens, among others. Joint
Commenters, which includes NARUC, also endorsed a greatly simplified
all-in-one application form/procedures/terms and conditions document
for the interconnection of certified inverter-based Small Generating
Facilities no larger than 10 kW.
24. In Order No. 2003-A, the Commission determined that the LGIP
and LGIA were designed around the needs of traditional synchronous
technology generators and that generators relying on non-synchronous
technologies, such as wind plants, may find that a specific requirement
is inapplicable or that a different approach is needed.\33\
Accordingly, the Commission added a blank Appendix G (Requirements of
Generators Relying on Non-Synchronous Technologies) to the LGIA as a
placeholder for requirements specific to non-synchronous
technologies.\34\ At a September 24, 2004 technical conference on the
interconnection requirements of non-synchronous technologies, panelists
were asked whether Appendix G type requirements should apply to Small
Generating Facilities. They responded that special capabilities, such
as low voltage ride-through, simply were not needed for any Small
Generating Facility, whether wind powered or not. As a result, the Wind
NOPR issued shortly thereafter applies only to the interconnection of
wind powered generators 20 MW or larger.\35\ In its supplemental
comments, National Grid asks the Commission to implement standards for
Small Generating Facilities that are similar to those proposed for
Large Generating Facilities in the Wind NOPR. This Final Rule does not
include such standards. The wind generating facilities that will
interconnect under this Final Rule will be small and will have minimal
impact on the Transmission Provider's electric system. The reliability
requirements proposed for wind powered Large Generating Facilities are
not needed for small wind generating facilities.
---------------------------------------------------------------------------
\33\ Order No. 2003-A at P 407, n. 86.
\34\ Id.
\35\ Interconnection for Wind Energy and Other Alternative
Technologies, Notice of Proposed Rulemaking, 70 FR 4791 (Jan. 31,
2005) (Wind NOPR).
---------------------------------------------------------------------------
25. In crafting this Final Rule, we considered all of the comments
received throughout the course of this proceeding, including the
initial documents submitted by Joint Commenters in response to the
ANOPR, the Small Generator Interconnection NOPR and the comments filed
in response, the NARUC Model, and the supplemental comments. We
considered all comments filed in response to the Small Generator
Interconnection NOPR before April 29, 2005, and they are part of the
record in this proceeding.\36\
---------------------------------------------------------------------------
\36\ Comments addressing issues filed in other dockets (for
instance, the Wind NOPR) are not part of this proceeding even if
they were cross-filed in Docket No. RM02-12-000.
---------------------------------------------------------------------------
II. Discussion
26. Part A of this discussion (Descriptions of the SGIP and SGIA)
describes in general terms the interconnection procedures document
(SGIP) and interconnection agreement
[[Page 34194]]
(SGIA) we are adopting in this Final Rule.
27. Part B (Overview of the Interconnection Process for Small
Generating Facilities) describes the processes that the Interconnection
Customer and the Transmission Provider must follow to interconnect the
Small Generating Facility with the Transmission Provider's Transmission
System.
28. Part C (Issues Related to Both the SGIP and the SGIA) addresses
issues that are common to the interconnection procedures and agreement
documents.
29. Part D (Issues Related to the Interconnection Request)
addresses issues related to the Interconnection Request (application
form) that the Interconnection Customer submits to the Transmission
Provider to request interconnection of its Small Generating Facility.
30. Part E (Issues Related to the SGIP) addresses issues related
only to the interconnection procedures document.
31. Part F (Issues Related to the SGIA) addresses issues related
only to the interconnection agreement.
32. Part G (The 10kW Inverter Process) describes the simplified
all-in-one application form/procedures/terms and conditions document
for the interconnection of certified inverter-based Small Generating
Facilities no larger than 10 kW.
33. Part H (Other Significant Issues) addresses the pricing of
Interconnection Facilities and Upgrades, jurisdictional issues,
variations from the Final Rule, the availability of waivers for small
entities, the effect of this Final Rule on the OATT reciprocity
provisions, and others.
34. Finally, Part I (Compliance Issues) addresses issues pertaining
to the requirement that a Transmission Provider file conforming
amendments to its existing OATT, the treatment to be accorded to
existing interconnection agreements (grandfathering), and how a
Transmission Provider is to file executed and unexecuted
interconnection agreements.
A. Descriptions of the SGIP and SGIA
35. In Order No. 2003, the Commission adopted two documents that
are to be used for the interconnection of Large Generating Facilities--
the Large Generator Interconnection Procedures document and the Large
Generator Interconnection Agreement. The LGIP describes how the
Interconnection Customer's Interconnection Request (i.e., application)
is to be evaluated from an engineering perspective using a four-step
process. These are the scoping meeting, the feasibility study, the
system impact study, and the facilities study. The purpose of the
evaluation is to determine the impact the proposed interconnection will
have on the Transmission Provider's electric system and identify new
equipment and modifications needed to accommodate the interconnection.
The LGIA, which is signed after the proposed interconnection has been
successfully evaluated using the provisions contained in the LGIP,
describes the legal relationships of the Parties, including who pays
for equipment modifications to the Transmission Provider's electric
system.
36. The SGIP and SGIA we adopt in this Final Rule serve the same
purposes as the LGIP and LGIA. The SGIP includes the same four-step
process for evaluating an Interconnection Request as does the LGIP,
except that it is simplified in several aspects and includes timelines
to accelerate the interconnection of Small Generating Facilities. In
the SGIP, this procedure is termed the ``Study Process.'' The SGIP also
includes special procedures for evaluating two subgroups of Small
Generating Facilities, (1) a ``Fast Track Process'' that uses technical
screens to evaluate a certified Small Generating Facility no larger
than 2 MW, and (2) a ``10 kW Inverter Process'' that uses the same
technical screens to evaluate a certified inverter-based Small
Generating Facility no larger than 10 kW. The SGIA serves the same
purpose for the interconnection of a Small Generating Facility as the
LGIA does for a Large Generating Facility. It describes the legal
relationships of the Parties, including who will pay for equipment
modifications to the Transmission Provider's electric system.
37. The Commission received many comments proposing modifications
to the Proposed SGIP and Proposed SGIA, which helped greatly to shape
this Final Rule. NARUC argued that the Commission should adopt portions
of its Model to harmonize federal interconnection rules with those
found in states with interconnection rules. Small Generator Coalition
recommended that the Commission in this proceeding adopt the NARUC
Model instead of the Proposed SGIP and Proposed SGIA. Some of the
provisions proposed by Joint Commenters (which includes NARUC
representation) in its supplemental comments also followed the NARUC
Model. We are adopting in this Final Rule many of these consensus
provisions as well as those proposed by NARUC because they are just and
reasonable and serve the twin goals of removing barriers to the
development of small generation while preserving the safety and
reliability of the nation's electric system.
38. The SGIP, while relying heavily on NARUC's and Joint
Commenters' proposals, is not a significant departure from the Proposed
SGIP. Both use nearly identical interconnection study processes
(``Study Process'') to evaluate Interconnection Requests that do not
qualify for special handling. Regarding special handling, both use
technical screens to identify Small Generating Facilities no larger
than 2 MW that can be interconnected with no adverse impact on safety
or reliability. The SGIP we adopt in this Final Rule, however, includes
two such special procedures, the Fast Track Process and the 10 kW
Process. The choice of which one the Interconnection Customer may use
depends on the size and technology of the Small Generating Facility.
The SGIP also includes the Interconnection Request (application form)
that is to be used by all Interconnection Customers except those
eligible to use the 10 kW Process, and feasibility study, system impact
study, and facilities study agreements that are to be used in the Study
Process.\37\
---------------------------------------------------------------------------
\37\ Note that the scope and payment provisions of the
feasibility, system impact, and facilities studies are contained in
the actual study agreements which are included as Attachments 6, 7,
and 8 to the SGIP, not section 3 of the SGIP.
---------------------------------------------------------------------------
39. The SGIA is to be used for the interconnection of all Small
Generating Facilities subject to this Final Rule, with the exception of
certain very small inverter-based generators that use an all-in-one
application form/procedures/terms and conditions document (the 10 kW
Inverter Process document). The Proposed SGIA included several
provisions that were similar to those contained in the LGIA that was
issued concurrent with the Small Generator Interconnection NOPR. Some
commenters complained that the Proposed SGIA was too long and complex
for owners of Small Generating Facilities, who may be small businesses
or operators of small farms, for example. We are streamlining and
simplifying the SGIA in many ways to address these concerns. We are
adopting Joint Commenters' proposals submitted in its supplemental
comments where appropriate and have given consideration to the
recommendations contained in the NARUC Model and those suggested by
other commenters. In particular, the SGIA does away with the
requirement that Interconnection Customers maintain multiple kinds of
insurance, instead requiring only that they maintain a reasonable
amount based on the specific characteristics of
[[Page 34195]]
the interconnection. We also adopt a streamlined dispute resolution
provision designed to resolve disputes as quickly and inexpensively as
possible. We have also shortened the contract termination provisions
and the various liability related provisions.
40. We adopt in the SGIA the same pricing policy for Network
Upgrades to the Transmission Provider's Transmission System as in Order
No. 2003. For a Small Generating Facility interconnecting with a non-
independent entity such as a vertically integrated utility, the
Interconnection Customer initially funds the cost of any required
Network Upgrades (i.e., Upgrades to the Transmission System at or
beyond the Point of Interconnection) and it is then subsequently
reimbursed for this upfront payment by the Transmission Provider.
However, we expect that, for most interconnections of Small Generating
Facilities, there will be no Network Upgrades. We also allow more
pricing flexibility for a Transmission System that is operated by an
independent entity such as an RTO or Independent System Operator (ISO).
The costs of Distribution Upgrades are directly assigned to the
Interconnection Customer.
41. In conclusion, we encourage the standardization of
interconnection practices across the nation, using as a starting point
the SGIP and SGIA found in this Final Rule. We hope to foster seamless
interconnection procedures for Interconnection Customers and
Transmission Providers. Equipment manufacturers will have compatible
technical specifications to meet. New generation will be located on the
basis of what works best for the Interconnection Customer and the
Transmission Provider, not jurisdictional differences in
interconnection rules.
B. Overview of the Interconnection Process for Small Generating
Facilities
42. Before submitting its Interconnection Request, the
Interconnection Customer may informally discuss the proposed
interconnection with the Transmission Provider.\38\ The Interconnection
Customer then submits an Interconnection Request to the Transmission
Provider and the Transmission Provider assigns the Interconnection
Customer's project a Queue Position based on the date and time the
Interconnection Request is received by the Transmission Provider. The
Interconnection Request must be accompanied by a deposit that goes
toward the cost of the feasibility study, unless it is submitted under
the Fast Track Process or the 10 kW Inverter Process, which have small
processing fees.
---------------------------------------------------------------------------
\38\ Flowcharts depicting interconnection procedures are
presented in Appendices B (Study Process), C (Fast Track Process),
and D (10 kW Inverter Process).
---------------------------------------------------------------------------
43. As noted above, an Interconnection Request can be evaluated in
one of three ways. The Study Process is the default method; it relies
on the scoping meeting and standard feasibility, system impact, and
facilities studies to evaluate the safety and reliability of the
proposed interconnection. It is identical in concept to the evaluation
procedure that is used for the interconnection of Large Generating
Facilities. Two optional methods are available to Interconnection
Customers whose Small Generating Facilities are certified and no larger
than 2 MW. The 10 kW Inverter Process is available for owners of
inverter-based Small Generating Facilities no larger than 10 kW and the
Fast Track Process is available for owners of any kind of Small
Generating Facility no larger than 2 MW.
44. The Study Process normally consists of a scoping meeting, a
feasibility study, a system impact study, and a facilities study. At
the scoping meeting, the Parties discuss the proposed interconnection
and review any existing studies that could aid in the evaluation of the
proposed interconnection. The feasibility study is a preliminary
technical assessment of the proposed interconnection. The system impact
study is a more detailed assessment of the effect the interconnection
would have on the Transmission Provider's electric system and Affected
Systems. The facilities study determines what modifications to the
Transmission Provider's electric system are needed, including the
detailed costs and scheduled completion dates for these modifications.
These studies identify adverse system impacts \39\ that need to be
addressed before the Small Generating Facility may be interconnected
and any equipment modifications required to accommodate the
interconnection. The Interconnection Customer pays the Transmission
Provider's actual cost of performing the studies. Once the
Interconnection Customer agrees to fund any needed Upgrades, the
Parties execute an SGIA that, among other things, formalizes
responsibility for construction and payment for Interconnection
Facilities and Upgrades.\40\
---------------------------------------------------------------------------
\39\ An adverse system impact means that technical or
operational limits on conductors or equipment are exceeded under the
interconnection, which may compromise the safety or reliability of
the electric system.
\40\ The Study Process is similar to the LGIP. However, we
expect that the interconnection of a Small Generating Facility will
take substantially less time and cost substantially less than a
Large Generating Facility.
---------------------------------------------------------------------------
45. A Fast Track Process is available for certified Small
Generating Facilities no larger than 2 MW. Under this process, in place
of the scoping meeting and three interconnection studies, technical
screens are used to quickly identify reliability or safety issues. If
the proposed interconnection passes the screens, the Transmission
Provider offers the Interconnection Customer an SGIA. If the proposed
interconnection fails the screens, but the Transmission Provider
determines that the Small Generating Facility may nevertheless be
interconnected without affecting safety and reliability, the
Transmission Provider also offers the Interconnection Customer an SGIA.
However, if the Transmission Provider is concerned that the
interconnection could degrade the safety and reliability of its
electric system, the Parties may conduct a customer options meeting to
discuss how to proceed. In that meeting, the Transmission Provider must
offer to perform a supplemental review of the proposed interconnection,
paid for by the Interconnection Customer, to identify Upgrades needed
to accommodate the interconnection. Once the Interconnection Customer
agrees to pay for any Upgrades called for in the supplemental review,
the Parties execute an SGIA. If, after the supplemental review, the
Transmission Provider still is unsure whether the proposed
interconnection will degrade the safety and reliability of its electric
system, the Interconnection Request is evaluated using the Study
Process described above; i.e., scoping meeting, feasibility, system
impact, and facilities studies, followed by the execution of an SGIA.
46. Finally, the 10 kW Inverter Process is available for the
interconnection of certified inverter-based generators no larger than
10 kW. The all-in-one 10 kW Inverter Process document includes a
simplified application form, interconnection procedures, and a brief
set of terms and conditions (akin to an interconnection agreement). The
10 kW Inverter Process uses the same technical screens to evaluate the
safety and reliability of the proposed interconnection as the Fast
Track Process. Unless the Transmission Provider demonstrates that the
Small Generating Facility cannot be
[[Page 34196]]
interconnected safely and reliably based on the results of an analysis
using the screens, the Transmission Provider approves the application.
Once the Interconnection Customer certifies that equipment installation
is complete and upon a satisfactory inspection by the Transmission
Provider, the Transmission Provider authorizes the interconnection. To
further simplify the interconnection process, what would normally be
considered a separate interconnection agreement has been distilled into
a terms and conditions document that the Interconnection Customer
agrees to at the time the Interconnection Request is submitted to the
Transmission Provider. The all-in-one 10 kW Process document is
included in Attachment 5 to the SGIP.
C. Issues Related to Both the SGIP and the SGIA
47. This discussion, and those that follow, addresses the evolution
of the SGIP and SGIA from the Proposed SGIP and Proposed SGIA. As is
the custom in most Commission rulemakings, we use the Small Generator
Interconnection NOPR as our point of reference, discussing each issue
in turn, describing the comments addressed to the topic, and closing
with the Commission conclusion. There are differences between the
Proposed SGIP and SGIA and the documents we adopt in this Final Rule
that reflect the helpful comments filed in this rulemaking. For
example, we have in some instances adopted terminology more compatible
with that used in state interconnection documents. This should make for
simpler, more easily understood documents for small generators that are
compatible across jurisdictions for both Interconnection Customers and
Transmission Providers. However, the SGIP and SGIA also need to be
interpreted in the broader context of the entire collection of
generator interconnection documents that will appear in a Transmission
Provider's OATT, including the LGIP and LGIA. Thus, there are some
instances where consistency among generator interconnection documents
within a single tariff makes it necessary to adopt Large Generator
Interconnection terminology or policy. The Commission asked for
comments in the Small Generator Interconnection NOPR addressing this
topic, and it is the first to be addressed in the discussion that
follows.
48. Many of the issues in this rulemaking also arose in the Large
Generator Interconnecting rulemaking and we will not address them again
here at any great length. Where there is no compelling reason to depart
from prior precedent, we affirm the Commission's prior decisions
without detailed discussion. Therefore, this order focuses on those
issues needing a small-generator-specific resolution.
49. Finally, we note that the 10 kW Inverter Process for certified
inverter-based Small Generating Facilities is an all-in-one application
form/procedures/terms and conditions document that does not lend itself
easily to the separate discussions of the Proposed SGIP/SGIA and the
SGIP and SGIA discussions that follow. We will address it in the
separate Part G discussion, below. We emphasize, however, that the
intent of this Final Rule is that the 10 kW Inverter Process fits
within the framework of the SGIP and SGIA, and it is for that reason
that we encourage Interconnection Customers and Transmission Providers
to use this Preamble, the SGIP, and the SGIA for assistance in
interpreting the 10 kW Inverter Process should a dispute arise.
Consistency Between the Large Generator and Small Generator Documents
50. In the Small Generator Interconnection NOPR, the Commission
asked commenters to address the need for consistency between the
provisions of the LGIP/LGIA and the SGIP/SGIA.
Comments
51. NARUC argued that the Small Generator Interconnection NOPR was
too complicated for most small generator interconnections. Instead, the
Commission should adopt portions of the NARUC Model or otherwise
simplify the interconnection process. NARUC pointed out that many Small
Generating Facilities (including most inverter-based generators) will
interconnect with low voltage facilities, whether Commission-
jurisdictional or state-jurisdictional. Thus, this Final Rule should be
as consistent with state interconnection rules as possible to encourage
national consistency and discourage forum-shopping. Joint Commenters
also supports this outcome.
52. AEP supports consistency between the large and small generator
documents. However, it notes that Joint Commenters developed consensus
positions on many issues during the ANOPR process. Where such agreement
was reached, AEP proposes that the Commission adopt that position.
53. Midwest ISO argues that the Commission should ensure
consistency between the large and small generator documents, wherever
possible, because all stakeholders will benefit from a consistent
approach to the interconnection of generation facilities.
54. PJM, on the other hand, proposes that the Commission simply use
the LGIA for all interconnections, arguing that having different rules
for large and small generator interconnections would be overly
burdensome. PJM also states that its own interconnection rules take
this approach and are hailed as being very successful.
55. Baltimore G&E argues that the Commission should require the
same terms for all generators, regardless of size, unless there is a
specific reason not to do so. Therefore, it requests that the
Commission provide a clear explanation wherever these Final Rule
provisions differ from those in Order No. 2003. Southern Company
agrees, arguing that Large and Small Generating Facilities should be
treated similarly ``because both can have * * * significant impacts
upon the Transmission Provider's electric system.'' \41\
---------------------------------------------------------------------------
\41\ Southern Company at 19.
---------------------------------------------------------------------------
56. BPA argues that the procedures and technical requirements
applicable to large generators ``should not apply to the
interconnection of small generators that have minimal impacts on a
transmission grid.'' \42\ However, where the Commission does use
``substantially similar or consistent procedures, contract terms, and
other requirements'' for both Large and Small Generating Facilities,
``the Commission should strive to provide consistency between its large
and small generator rules.'' \43\
---------------------------------------------------------------------------
\42\ BPA at 3.
\43\ Id.
---------------------------------------------------------------------------
57. Nevada Power also supports the concept of having the provisions
applicable to Small Generating Facilities similar to those in Order No.
2003. According to Nevada Power, ``[t]hese commonalities will avoid the
confusion of differing terminologies, facilitate consistent and fair
implementation, and minimize the need for separate, parallel
administrative processes to administer the agreements.'' \44\ However,
Nevada Power also argues that consistency should not compromise the
goals of simplifying and expediting the interconnection of Small
Generating Facilities. Instead, this Final Rule should be designed to
``enable a common language and common administrative procedures to be
implemented and still maintain appropriate distinctions between the
small generators and the large generators.'' \45\ Nevada Power argues
that the benefits of consistency are illustrated by Proposed SGIA
article
[[Page 34197]]
5.1.2.1, which specifies the refund process for advances made by the
Interconnection Customer for Network Upgrades. By having the same
refund process for the amounts advanced for Network Upgrades in the
SGIA and the LGIA, the Transmission Provider can set up one system,
instead of two separate systems, to track and make any such refunds.
---------------------------------------------------------------------------
\44\ Nevada Power at 4.
\45\ Nevada Power at 4-5.
---------------------------------------------------------------------------
58. In their supplemental comments, NARUC and the other Joint
Commenters proposed SGIP and SGIA provisions that balance the need for
simplicity with the need of Transmission Providers to ensure the safety
and reliability of the Transmission Provider's electric system. In
addition, Joint Commenters also proposed a process for certified
inverter-based Small Generating Facilities no larger than 10 kW that
can also be used as a model for the states.
Commission Conclusion
59. Unless expressly changed in this Final Rule, the Commission's
existing interconnection precedent and Order No. 2003 are relevant to
this Final Rule and should be used as guidance for interpretation and
implementation. We have tried to be consistent between the rules for
Large and Small Generating Facilities, unless there is a specific
reason to do otherwise, while considering NARUC's call for federal-
state consistency and the recommendations of other commenters.
60. We note Joint Commenters' proposal of much simpler
interconnection procedures and agreement for inverter-based generators
no larger than 10 kW.\46\ Taking these extremely small units out of the
mix has allowed us to adopt standard rules for larger Small Generating
Facilities. According to NARUC, the process of interconnecting with a
state-jurisdictional facility should not be substantially different
from the process for interconnecting with a Commission-jurisdictional
facility. Standard interconnection procedures are especially important
for Interconnection Customers and manufacturers of off-the-shelf
generating equipment.
---------------------------------------------------------------------------
\46\ The 10 kW Inverter Process is largely based on the work of
the Massachusetts DTE and its stakeholders group.
---------------------------------------------------------------------------
61. In general, we are including standard contractual provisions in
the SGIA that are consistent with their counterparts in the LGIA.
However, in many cases commenters stressed the need to simplify those
provisions to avoid burdening Small Generating Facilities. Many
commenters offered ways to shorten and simplify those provisions. Where
possible, we accept those proposals. These streamlined provisions
adequately protect the Parties while lowering the transaction costs of
entering into an interconnection agreement. The SGIP closely tracks the
revised NARUC Model but adopts the single screen that NARUC and the
other Joint Commenters later proposed in supplemental comments. Last,
we have ensured that provisions common to the SGIP and SGIA (such as
dispute resolution and confidentiality) are consistent.
62. Definitions of Terms Used in the SGIP and SGIA--NARUC and
others propose that the Commission use the defined terms in the NARUC
Model instead of those found in the Small Generator Interconnection
NOPR. We conclude that several of the terms defined in the Proposed
SGIP and SGIA are either unnecessary or add complexity to the
interconnection process. We are simplifying the SGIP and SGIA by
deleting those definitions. Comments on specific terms are discussed
below.
63. Emergency Condition--The Proposed SGIA defined Emergency
Condition as a situation that, in the judgment of the Party making the
claim, is imminently likely to (1) endanger life or property, (2) have
an adverse impact on the safety or reliability of the Transmission
Provider's or an affected third party's electric system (Affected
System), or (3) have a material adverse effect on the safety or
operation of the Interconnection Customer's facilities. If there is an
Emergency Condition, the Transmission Provider may take necessary and
appropriate actions to protect the safety and reliability of its
electric system, including interrupting, suspending, or curtailing
interconnection service. While system restoration and black start are
considered Emergency Conditions, the Small Generating Facility is not
obligated to have black start capability.
Comment
64. Bureau of Reclamation objects to the provision that the Small
Generating Facility is not obligated by the SGIA to have black start
capability. Black start capability is an issue best handled by the
control area rather than the Transmission Provider and that mentioning
black start here raises the question of by whom and when black start
capability could be required of the Small Generating Facility. In
addition, Bureau of Reclamation proposes that the definition of
Emergency Condition also include a ``threat or danger to the
environment.''
Commission Conclusion
65. We see no need to modify the definition of Emergency Condition.
The SGIA does not interfere with the control area's ability to
establish a voluntary restoration plan, including black start. The SGIA
requires the Parties to adhere to all Applicable Laws and Regulations
relating to pollution and protection of the environment or natural
resources. Therefore, Bureau of Reclamations' proposed revision is not
necessary.
66. Network Upgrades--Comments concerning the definition of Network
Upgrades are addressed in Part II.H (Pricing/Cost Recovery for
Interconnection Facilities and Upgrades).
67. Use of Calendar Days v. Business Days--The Proposed SGIP and
Proposed SGIA used both calendar days and Business Days