Federal Register / Vol. 70, No. 111 / Friday, June 10, 2005 / Notices
The notice has been mailed again to
all affected parties. The scoping period
closing date is hereby extended to June
29, 2005.
Magalie R. Salas,
Secretary.
[FR Doc. E5–3008 Filed 6–9–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Accepting for
Filing and Soliciting Motions To
Intervene, Protests and Comments
June 1, 2005.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
permit.
b. Project No.: 12579–000.
c. Date filed: March 14, 2005.
d. Applicant: Alaska Power &
Telephone Company.
e. Name of Project: Boundary Lake
Hydroelectric Project.
f. Location: On Boundary Creek and
Boundary Lake, near the City of Juneau,
Borough of Juneau, Alaska, within the
Tongass National Forest.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)—825(r).
h. Applicant Contact: Mr. Robert S.
Grimm, President, Alaska Power &
Telephone Company, P.O. Box 3222,
Port Townsend, WA 98368, (360) 385–
1733 x 120.
i. FERC Contact: Etta Foster, (202)
502–8769.
j. Deadline for filing comments,
protests, and motions to intervene: 60
days from the issuance date of this
notice.
All documents (original and eight
copies) should be filed with Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
Please include the project number (P–
12579–000) on any comments, protests,
or motions filed.
k. Description of Project: The
proposed project would consist of: (1) A
proposed concrete, steel, or wood crib
diversion and intake structure
approximately 45-feet-high and 100feet-long on Boundary Lake and
Boundary Creek; (2) a reservoir with a
surface area of 50 acres and a storage
capacity of 5,000 acre-feet at an
elevation of 900 feet; (3) a low-pressure
pipe penstock approximately 1,800 feet
in length and 60-inches in diameter; (4)
VerDate jul<14>2003
17:22 Jun 09, 2005
Jkt 205001
a powerhouse containing 1 or 2 turbines
to achieve the maximum capacity for
generation of 9 megawatts; (5) a tailrace
that will extend a short distance to the
Taku River; (6) a 35 kV transmission
line that is 0.4 miles long, and (7)
appurtenant facilities.
The project would have an annual
generation of 35(GWh) gigawatt-hours.
l. Location of Application: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street, NE.,
Room 2A, Washington, DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h.
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Competing Preliminary Permit—
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30(b) and 4.36.
o. Competing Development
Application—Any qualified
development applicant desiring to file a
competing development application
must submit to the Commission, on or
before a specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30(b) and 4.36.
p. Notice of Intent—a notice of intent
must specify the exact name, business
PO 00000
Frm 00016
Fmt 4703
Sfmt 4703
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
q. Proposed Scope of Studies Under
Permit—A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
r. Comments, Protests, or Motions To
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper; see 18 CFR
385.2001 (a)(1)(iii) and the instructions
on the Commission’s Web site under ‘‘efiling’’ link. The Commission strongly
encourages electronic filing.
s. Filing and Service of Responsive
Documents—Any filings must bear in
all capital letter the title
‘‘COMMENTS’’,
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’, as
applicable, and the Project Number of
the particular application to which the
filing refers. Any of the above-named
documents must be filed by providing
the original and the number of copies
provided by the Commission’s
regulations to: The Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
A copy of any motion to intervene must
also be served upon each representative
of the Applicant specified in the
particular application.
E:\FR\FM\10JNN1.SGM
10JNN1
Federal Register / Vol. 70, No. 111 / Friday, June 10, 2005 / Notices
t. Agency Comments—Federal, State,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E5–2995 Filed 6–9–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Accepted for
Filing and Soliciting Comments,
Protests, and Motions To Intervene
June 1, 2005.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
permit.
b. Project No.: 12586–000.
c. Date filed: April 27, 2005.
d. Applicant: Paradise Irrigation
District.
e. Name and Location of Project: The
proposed Paradise Hydroelectric Project
would be located in Butte County in
California and would occupy lands
administered by the Bureau of Land
Management and the U.S. Forest
Service.
f. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)—825(r).
g. Applicant contact: Mr. George
Barber, District Manager, Paradise
Irrigation District, 5325 Black Olive
Drive, P.O. Box 2409, Paradise, CA
95967–4971, (530) 877–4971.
h. FERC Contact: Tom Papsidero,
(202) 502–6002.
i. Deadline for filing comments,
protests, and motions to intervene: 60
days from the issuance date of this
notice.
All documents (original and eight
copies) should be filed with Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper; see 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. The Commission
strongly encourages electronic filings.
VerDate jul<14>2003
17:22 Jun 09, 2005
Jkt 205001
Please include the project number (P–
12586–000) on any comments or
motions filed.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
j. Description of Existing Facilities
and Proposed Project: The proposed
project would use the applicant’s
existing 175-foot-high, 975-foot-long
Paradise Dam and Reservoir, which
occupies approximately 90 acres of
Federal land, and which has a storage
capacity of 11,500 acre-feet, a surface
area of 244 acres, and normal maximum
surface elevation of 2,568 feet msl. The
applicant proposes to study several
alternatives at the site and the proposed
project would likely consist of: (1) A
new powerhouse to be located on
Federal land, containing one turbinegenerator unit with a total installed
capacity of 350 kW; (2) a new 30-inchwide steel penstock (3) a new 0.5-milelong transmission line; and (4)
appurtenant facilities. The proposed
project would have an annual
generation of 1,091 MWh.
k. Location of Applications: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room or may be viewed on the
Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, call toll-free 1–866–208–
3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item g
above.
l. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
m. Competing Preliminary Permit—
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
PO 00000
Frm 00017
Fmt 4703
Sfmt 4703
33895
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30(b) and 4.36.
m. Competing Development
Application—Any qualified
development applicant desiring to file a
competing development application
must submit to the Commission, on or
before a specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30(b) and 4.36.
n. Notice of Intent—A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
o. Proposed Scope of Studies Under
Permit—A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
p. Comments, Protests, or Motions To
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Comments, protests and interventions
may be filed electronically via the
E:\FR\FM\10JNN1.SGM
10JNN1
Agencies
[Federal Register Volume 70, Number 111 (Friday, June 10, 2005)]
[Notices]
[Pages 33894-33895]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-2995]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Application Accepting for Filing and Soliciting Motions
To Intervene, Protests and Comments
June 1, 2005.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary permit.
b. Project No.: 12579-000.
c. Date filed: March 14, 2005.
d. Applicant: Alaska Power & Telephone Company.
e. Name of Project: Boundary Lake Hydroelectric Project.
f. Location: On Boundary Creek and Boundary Lake, near the City of
Juneau, Borough of Juneau, Alaska, within the Tongass National Forest.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)--825(r).
h. Applicant Contact: Mr. Robert S. Grimm, President, Alaska Power
& Telephone Company, P.O. Box 3222, Port Townsend, WA 98368, (360) 385-
1733 x 120.
i. FERC Contact: Etta Foster, (202) 502-8769.
j. Deadline for filing comments, protests, and motions to
intervene: 60 days from the issuance date of this notice.
All documents (original and eight copies) should be filed with
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426. Please include the project
number (P-12579-000) on any comments, protests, or motions filed.
k. Description of Project: The proposed project would consist of:
(1) A proposed concrete, steel, or wood crib diversion and intake
structure approximately 45-feet-high and 100-feet-long on Boundary Lake
and Boundary Creek; (2) a reservoir with a surface area of 50 acres and
a storage capacity of 5,000 acre-feet at an elevation of 900 feet; (3)
a low-pressure pipe penstock approximately 1,800 feet in length and 60-
inches in diameter; (4) a powerhouse containing 1 or 2 turbines to
achieve the maximum capacity for generation of 9 megawatts; (5) a
tailrace that will extend a short distance to the Taku River; (6) a 35
kV transmission line that is 0.4 miles long, and (7) appurtenant
facilities.
The project would have an annual generation of 35(GWh) gigawatt-
hours.
l. Location of Application: A copy of the application is available
for inspection and reproduction at the Commission in the Public
Reference Room, located at 888 First Street, NE., Room 2A, Washington,
DC 20426, or by calling (202) 502-8371. This filing may also be viewed
on the Commission's Web site at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, call toll-free 1-866-208-3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item
h. above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Competing Preliminary Permit--Anyone desiring to file a
competing application for preliminary permit for a proposed project
must submit the competing application itself, or a notice of intent to
file such an application, to the Commission on or before the specified
comment date for the particular application (see 18 CFR 4.36).
Submission of a timely notice of intent allows an interested person to
file the competing preliminary permit application no later than 30 days
after the specified comment date for the particular application. A
competing preliminary permit application must conform with 18 CFR
4.30(b) and 4.36.
o. Competing Development Application--Any qualified development
applicant desiring to file a competing development application must
submit to the Commission, on or before a specified comment date for the
particular application, either a competing development application or a
notice of intent to file such an application. Submission of a timely
notice of intent to file a development application allows an interested
person to file the competing application no later than 120 days after
the specified comment date for the particular application. A competing
license application must conform with 18 CFR 4.30(b) and 4.36.
p. Notice of Intent--a notice of intent must specify the exact
name, business address, and telephone number of the prospective
applicant, and must include an unequivocal statement of intent to
submit, if such an application may be filed, either a preliminary
permit application or a development application (specify which type of
application). A notice of intent must be served on the applicant(s)
named in this public notice.
q. Proposed Scope of Studies Under Permit--A preliminary permit, if
issued, does not authorize construction. The term of the proposed
preliminary permit would be 36 months. The work proposed under the
preliminary permit would include economic analysis, preparation of
preliminary engineering plans, and a study of environmental impacts.
Based on the results of these studies, the Applicant would decide
whether to proceed with the preparation of a development application to
construct and operate the project.
r. Comments, Protests, or Motions To Intervene--Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
Comments, protests and interventions may be filed electronically
via the Internet in lieu of paper; see 18 CFR 385.2001 (a)(1)(iii) and
the instructions on the Commission's Web site under ``e-filing'' link.
The Commission strongly encourages electronic filing.
s. Filing and Service of Responsive Documents--Any filings must
bear in all capital letter the title ``COMMENTS'', ``RECOMMENDATIONS
FOR TERMS AND CONDITIONS'', ``PROTEST'', or ``MOTION TO INTERVENE'', as
applicable, and the Project Number of the particular application to
which the filing refers. Any of the above-named documents must be filed
by providing the original and the number of copies provided by the
Commission's regulations to: The Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE., Washington, DC 20426. A copy of any
motion to intervene must also be served upon each representative of the
Applicant specified in the particular application.
[[Page 33895]]
t. Agency Comments--Federal, State, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the applicant. If
an agency does not file comments within the time specified for filing
comments, it will be presumed to have no comments. One copy of an
agency's comments must also be sent to the Applicant's representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E5-2995 Filed 6-9-05; 8:45 am]
BILLING CODE 6717-01-P